M. TYNDEL 1 LHCC Interactions May 2003

ATLAS ATLAS SCTSCT

SCT Production Status

‘Snap-shot’ of the status of the SCT production (May 2003)

1. Barrel Modules

2. Barrel Opto-harnesses

3. Barrel support structures & cooling

4. Endcap Modules

5. Endcap Opto-harnesses

6. Endcap support structures & cooling

7. Power & Cables

8. Off-detector readout

9. Assembly & Integration

Page 2: SCT Production Status

M. TYNDEL 2 LHCC Interactions May 2003

ATLAS ATLAS SCTSCT

Modules Barrel module PRR May 01 Detector production May 03 ( I.e. complete)

Hybrids target end date Aug 03 1214/2500 (49%) Baseboards target end date Oct 03 1481/2530 (59%)

Modules-Japan 356/ 786 (45%) Modules-UK 79/ 549 (14%) Modules-US 48/ 483 (10%) Modules-Scand (qualification soon) 16/ 404 ( Total (2112+5%) 499/ 2218 (22%)

Modules target end date Apr 04

Barrel Modules

Page 3: SCT Production Status

M. TYNDEL 3 LHCC Interactions May 2003

ATLAS ATLAS SCTSCT

Barrel Optoharnesses

Opto-harnesses Production now underway after slow start-up Main problem was ESD damage to DORIC ASIC First 2 harnesses fully evaluated Schedule can be recovered

B3 Jun 03 B6 Jul 03 B5 Sep 03 B4 Oct 03

Page 4: SCT Production Status

M. TYNDEL 4 LHCC Interactions May 2003

ATLAS ATLAS SCTSCT

Barrel Structure & Cooling

Support structures

All 4 CF cylinders delivered

…but there are ~40000 small parts!

Cooling

Design is finalised

Production of cooling circuits underway

On critical path

Page 5: SCT Production Status

M. TYNDEL 5 LHCC Interactions May 2003

ATLAS ATLAS SCTSCT

Endcap Modules

Modules Endcap module PRR Aug 02 & Nov 02

Hybrid design was validated as suitable for production Hybrid production & assembly transferred to industry Thermal performance validated

Production Hybrids

Pre-series of 200 in production – some delivered Full order for 2500 placed

Spines 200 in production by Protvino/MPI Contract in place for 2500

Module assembly All 3 clusters have started ‘qualification’ process 1rst modules within specification Aim is to have all sites qualified in 2 months Goal is to complete module production in Sep 04

Very ambitious – will require extra resources

Page 6: SCT Production Status

M. TYNDEL 6 LHCC Interactions May 2003

ATLAS ATLAS SCTSCT

Endcap Optoharnesses, Structure & Cooling

Opto-harnesses Simpler as the electronics is

incorporated in the hybrid Production can start as soon as fibre

lengths finalised Cooling

Design is finalised & prototyped Production of cooling circuits ready to

start Support structures

CF disks & support cylinders ordered First 4 delivered; complete by Dec 03

Again many small parts 4 first disks & Stub cylinder delivered Expect delivery of cylinders by Aug 03

Disk PAR MAY 19 Critical issue is to complete disc

machining by July

Page 7: SCT Production Status

M. TYNDEL 7 LHCC Interactions May 2003

ATLAS ATLAS SCTSCT

SCT Power, Cables, Readout, Assembly & Integration

Power & Cables System designed & all elements prototyped FDR/PRR scheduled for May 28 Early production necessary for macro-assembly Cable tender in June

Readout System designed & all elements prototyped FDR/PRR May 13 Early production necessary for macro-assembly

Assembly & Integration B3 is at RAL to be equipped with services B3 will go to Oxford to have modules added Jul 03 – Nov 03 SR building at CERN now available

Program of work underway to commission cooling, power & readout