PROJECT BUDGETING
The overall goal in thebudgeting process of aproject is to determinehow much money is tobe spent each week or
each month.
PERT / Cost is a modification ofPERT that allows a manager to
plan, schedule, monitor, andcontrol cost as well as time.
Applied Management Science for Decision Making, 2e © 2014 Pearson Learning Solutions Philip A. Vaccaro , PhD
MGMT E-5050
![Page 2: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/2.jpg)
The Budgeting Process
STEPS
Identify all costs associated with each task.
Applied Management Science for Decision Making, 2e © 2014 Pearson Learning Solutions
![Page 3: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/3.jpg)
The Budgeting Process
STEPS
Identify all costs associated with each task.
Convert the budgeted cost per task into a cost per time period. We assume that the cost of completing a task is spent at a uni- form rate over time.
![Page 4: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/4.jpg)
The Budgeting Process
STEPS
Identify all costs associated with each task.
Convert the budgeted cost per task into a cost per time period. We assume that the cost of completing a task is spent at a uni- form rate over time.
Using the earliest and latest start times, we find out how much money should be spent during each week or month to finish the pro- ject by the desired date.
![Page 5: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/5.jpg)
Early Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “A”
Early Start Time - ES 0
Early Finish Time - EF 2
Expected Time - te 2 weeks
Budgeted Task Cost $22,000.00
Budgeted Weekly Cost $11,000.00 *
$22,000.00 / 2 WEEKS = $11,000.00*
![Page 6: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/6.jpg)
TASK Period 1 Period 2 Period 3 Period 4
A $11,000 $11,000
B
C
D
E
F
G
H
PERIOD TOTAL
CUMULATIVE FROM START
Early Start Budget Schedule
![Page 7: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/7.jpg)
Early Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “B”
Early Start Time - ES 0
Early Finish Time - EF 3
Expected Time - te 3 weeks
Budgeted Task Cost $30,000.00
Budgeted Weekly Cost $10,000.00 *
$30,000.00 / 3 WEEKS = $10,000.00*
![Page 8: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/8.jpg)
TASK Period 1 Period 2 Period 3 Period 4
A
B $10,000 $10,000 $10,000
C
D
E
F
G
HPERIOD TOTAL
CUMULATIVE FROM START
Early Start Budget Schedule
![Page 9: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/9.jpg)
Early Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “C”
Early Start Time - ES 2
Early Finish Time - EF 4
Expected Time - te 2 weeks
Budgeted Task Cost $26,000.00
Budgeted Weekly Cost $13,000.00 *
$26,000.00 / 2 WEEKS = $13,000.00*
![Page 10: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/10.jpg)
TASK Period 1 Period 2 Period 3 Period 4
A
B
C $13,000 $13,000
D
E
F
G
HPERIOD TOTAL
CUMULATIVE FROM START
Early Start Budget Schedule
![Page 11: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/11.jpg)
Early Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “D”
Early Start Time - ES 3
Early Finish Time - EF 7
Expected Time - te 4 weeks
Budgeted Task Cost $48,000.00
Budgeted Weekly Cost $12,000.00 *
$48,000.00 / 4 WEEKS = $12,000.00*
![Page 12: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/12.jpg)
TASK Period 4 Period 5 Period 6 Period 7
A
B
C
D $12,000 $12,000 $12,000 $12,000
E
F
G
HPERIOD TOTAL
CUMULATIVE FROM START
Early Start Budget Schedule
![Page 13: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/13.jpg)
Early Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “E”
Early Start Time - ES 4
Early Finish Time - EF 8
Expected Time - te 4 weeks
Budgeted Task Cost $56,000.00
Budgeted Weekly Cost $14,000.00 *
$56,000.00 / 4 WEEKS = $14,000.00*
![Page 14: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/14.jpg)
TASK Period 5 Period 6 Period 7 Period 8
A
B
C
D
E $14,000 $14,000 $14,000 $14,000
F
G
HPERIOD TOTAL
CUMULATIVE FROM START
Early Start Budget Schedule
![Page 15: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/15.jpg)
Early Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “F”
Early Start Time - ES 4
Early Finish Time - EF 7
Expected Time - te 3 weeks
Budgeted Task Cost $30,000.00
Budgeted Weekly Cost $10,000.00 *
$30,000.00 / 3 WEEKS = $10,000.00*
![Page 16: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/16.jpg)
TASK Period 5 Period 6 Period 7 Period 8
A
B
C
D
E
F $10,000 $10,000 $10,000
G
HPERIOD TOTAL
CUMULATIVE FROM START
Early Start Budget Schedule
![Page 17: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/17.jpg)
Early Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “G”
Early Start Time - ES 8
Early Finish Time - EF 13
Expected Time - te 5 weeks
Budgeted Task Cost $80,000.00
Budgeted Weekly Cost $16,000.00 *
$80,000.00 / 5 WEEKS = $16,000.00*
![Page 18: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/18.jpg)
TASK Period 9 Period 10 Period 11 Period 12
A
B
C
D
E
F
G $16,000 $16,000 $16,000 $16,000
HPERIOD TOTAL
CUMULATIVE FROM START
Early Start Budget Schedule
![Page 19: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/19.jpg)
TASK Period 13 Period 14 Period 15
A
B
C
D
E
F
G $16,000
HPERIOD TOTAL
CUMULATIVE FROM START
Early Start Budget Schedule
![Page 20: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/20.jpg)
Early Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “H”
Early Start Time - ES 13
Early Finish Time - EF 15
Expected Time - te 2 weeks
Budgeted Task Cost $16,000.00
Budgeted Weekly Cost $8,000.00 *
$16,000.00 / 2 WEEKS = $8,000.00*
![Page 21: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/21.jpg)
TASK Period 14 Period 15
A
B
C
D
E
F
G
H $8,000 $8,000PERIOD TOTAL
CUMULATIVE FROM START
Early Start Budget Schedule
![Page 22: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/22.jpg)
TASK Period 1 Period 2 Period 3 Period 4
A $11,000 $11,000
B $10,000 $10,000 $10,000
C $13,000 $13,000
D $12,000
E
F
G
HPERIOD TOTAL $21,000 $21,000 $23,000 $25,000CUMULATIVE FROM START $21,000 $42,000 $65,000 $90,000
Early Start Budget Schedule
![Page 23: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/23.jpg)
TASK Period 5 Period 6 Period 7 Period 8
A
B
C
D $12,000 $12,000 $12,000
E $14,000 $14,000 $14,000 $14,000
F $10,000 $10,000 $10,000
G
HPERIOD TOTAL $36,000 $36,000 $36,000 $14,000CUMULATIVE FROM START $126,000 $162,000 $198,000 $212,000
Early Start Budget Schedule
![Page 24: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/24.jpg)
TASK Period 9 Period 10 Period 11 Period 12
A
B
C
D
E
F
G $16,000 $16,000 $16,000 $16,000
HPERIOD TOTAL $16,000 $16,000 $16,000 $16,000CUMULATIVE FROM START $228,000 $244,000 $260,000 $276,000
Early Start Budget Schedule
![Page 25: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/25.jpg)
TASK Period 13 Period 14 Period 15
A
B
C
D
E
F
G $16,000
H $8,000 $8,000PERIOD TOTAL $16,000 $8,000 $8,000CUMULATIVE FROM START $292,000 $300,000 $308,000
Early Start Budget Schedule
![Page 26: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/26.jpg)
Cumulative Budget Schedule
EARLY START TIME
$300,000.
$250,000.
$200,000.
$150,000.
$100,000.
$50,000.
$0.
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 weeks
$308,000.00
![Page 27: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/27.jpg)
Late Start Time Budget
Tasks that are not on the critical path can be started at a later date.
This type of budget will delay the expenditure of funds until the last possible moment.
Unfortunately, the risk is that any subsequent delays in these tasks will delay the entire pro- ject!
![Page 28: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/28.jpg)
Late Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “A”
Late Start Time - LS 0
Late Finish Time - LF 2
Expected Time - te 2 weeks
Budgeted Task Cost $22,000.00
Budgeted Weekly Cost $11,000.00 *
$22,000.00 / 2 WEEKS = $11,000.00*
![Page 29: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/29.jpg)
TASK Period 1 Period 2 Period 3 Period 4
A $11,000 $11,000
B
C
D
E
F
G
HPERIOD TOTAL
CUMULATIVE FROM START
Late Start Budget Schedule
![Page 30: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/30.jpg)
Late Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “B”
Late Start Time - LS 1
Late Finish Time - LF 4
Expected Time - te 3 weeks
Budgeted Task Cost $30,000.00
Budgeted Weekly Cost $10,000.00 *
$30,000.00 / 3 WEEKS = $10,000.00*
![Page 31: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/31.jpg)
TASK Period 1 Period 2 Period 3 Period 4
A
B $10,000 $10,000 $10,000
C
D
E
F
G
HPERIOD TOTAL
CUMULATIVE FROM START
Late Start Budget Schedule
![Page 32: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/32.jpg)
Late Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “C”
Late Start Time - LS 2
Late Finish Time - LF 4
Expected Time - te 2 weeks
Budgeted Task Cost $26,000.00
Budgeted Weekly Cost $13,000.00 *
$26,000.00 / 2 WEEKS = $13,000.00*
![Page 33: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/33.jpg)
TASK Period 1 Period 2 Period 3 Period 4
A
B
C $13,000 $13,000
D
E
F
G
HPERIOD TOTAL
CUMULATIVE FROM START
Late Start Budget Schedule
![Page 34: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/34.jpg)
Late Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “D”
Late Start Time - LS 4
Late Finish Time - LF 8
Expected Time - te 4 weeks
Budgeted Task Cost $48,000.00
Budgeted Weekly Cost $12,000.00 *
$48,000.00 / 4 WEEKS = $12,000.00*
![Page 35: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/35.jpg)
TASK Period 5 Period 6 Period 7 Period 8
A
B
C
D $12,000 $12,000 $12,000 $12,000
E
F
G
HPERIOD TOTAL
CUMULATIVE FROM START
Late Start Budget Schedule
![Page 36: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/36.jpg)
Late Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “E”
Late Start Time - LS 4
Late Finish Time - LF 8
Expected Time - te 4 weeks
Budgeted Task Cost $56,000.00
Budgeted Weekly Cost $14,000.00 *
$56,000.00 / 4 WEEKS = $14,000.00*
![Page 37: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/37.jpg)
TASK Period 5 Period 6 Period 7 Period 8
A
B
C
D
E $14,000 $14,000 $14,000 $14,000
F
G
HPERIOD TOTAL
CUMULATIVE FROM START
Late Start Budget Schedule
![Page 38: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/38.jpg)
Late Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “F”
Late Start Time - LS 10
Late Finish Time - LF 13
Expected Time - te 3 weeks
Budgeted Task Cost $30,000.00
Budgeted Weekly Cost $10,000.00 *
$30,000.00 / 3 WEEKS = $10,000.00*
![Page 39: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/39.jpg)
TASK Period 9 Period 10 Period 11 Period 12
A
B
C
D
E
F $10,000 $10,000
G
HPERIOD TOTAL
CUMULATIVE FROM START
Late Start Budget Schedule
![Page 40: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/40.jpg)
TASK Period 13 Period 14 Period 15
A
B
C
D
E
F $10,000
G
HPERIOD TOTAL
CUMULATIVE FROM START
Late Start Budget Schedule
![Page 41: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/41.jpg)
Late Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “G”
Late Start Time - LS 8
Late Finish Time - LF 13
Expected Time - te 5 weeks
Budgeted Task Cost $80,000.00
Budgeted Weekly Cost $16,000.00 *
$80,000.00 / 5 WEEKS = $16,000.00*
![Page 42: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/42.jpg)
TASK Period 9 Period 10 Period 11 Period 12
A
B
C
D
E
F
G $16,000 $16,000 $16,000 $16,000
HPERIOD TOTAL
CUMULATIVE FROM START
Late Start Budget Schedule
![Page 43: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/43.jpg)
TASK Period 13 Period 14 Period 15
A
B
C
D
E
F
G $16,000
HPERIOD TOTAL
CUMULATIVE FROM START
Late Start Budget Schedule
![Page 44: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/44.jpg)
Late Start Budget Schedule
GENERAL FOUNDRY EXAMPLE
Task “H”
Late Start Time - LS 13
Late Finish Time - LF 15
Expected Time - te 2 weeks
Budgeted Task Cost $16,000.00
Budgeted Weekly Cost $8,000.00 *
$16,000.00 / 2 WEEKS = $8,000.00*
![Page 45: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/45.jpg)
TASK Period 13 Period 14 Period 15
A
B
C
D
E
F
G
H $8,000 $8,000PERIOD TOTAL
CUMULATIVE FROM START
Late Start Budget Schedule
![Page 46: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/46.jpg)
TASK Period 1 Period 2 Period 3 Period 4
A $11,000 $11,000
B $10,000 $10,000 $10,000
C $13,000 $13,000
D
E
F
G
HPERIOD TOTAL $11,000 $21,000 $23,000 $23,000CUMULATIVE FROM START $11,000 $32,000 $55,000 $78,000
Late Start Budget Schedule
![Page 47: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/47.jpg)
TASK Period 5 Period 6 Period 7 Period 8
A
B
C
D $12,000 $12,000 $12,000 $12,000
E $14,000 $14,000 $14,000 $14,000
F
G
HPERIOD TOTAL $26,000 $26,000 $26,000 $26,000CUMULATIVE FROM START $104,000 $130,000 $156,000 $182,000
Late Start Budget Schedule
![Page 48: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/48.jpg)
TASK Period 9 Period 10 Period 11 Period 12
A
B
C
D
E
F $10,000 $10,000
G $16,000 $16,000 $16,000 $16,000
HPERIOD TOTAL $16,000 $16,000 $26,000 $26,000CUMULATIVE FROM START $198,000 $214,000 $240,000 $266,000
Late Start Budget Schedule
![Page 49: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/49.jpg)
TASK Period 13 Period 14 Period 15
A
B
C
D
E
F $10,000
G $16,000
H $8,000 $8,000PERIOD TOTAL $26,000 $8,000 $8,000CUMULATIVE FROM START $292,000 $300,000 $308,000
Late Start Budget Schedule
![Page 50: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/50.jpg)
Cumulative Budget Schedule
LATE START TIME
$300,000.
$250,000.
$200,000.
$150,000.
$100,000.
$50,000.
$0.
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 weeks
$308,000.00
![Page 51: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/51.jpg)
Cumulative Budget Schedule
EARLY START TIME
$300,000.
$250,000.
$200,000.
$150,000.
$100,000.
$50,000.
$0.
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 weeks
$308,000.00
![Page 52: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/52.jpg)
Cumulative Budget ScheduleFEASIBLE BUDGET RANGES
$300,000.
$250,000.
$200,000.
$150,000.
$100,000.
$50,000.
$0.
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 weeks
$308,000.00
EARLY START TIME
LATE START TIMEAREA
AREA
AR
EA
![Page 53: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/53.jpg)
PERT / CPM with QM for WINDOWS
![Page 54: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/54.jpg)
We Select TheCOST BUDGETING
Sub Program
![Page 55: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/55.jpg)
The Data Table IsCompleted As
Previously Shown
![Page 56: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/56.jpg)
The ExpectedProject Completion
Time( 15 weeks )
![Page 57: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/57.jpg)
The EARLY START BUDGET ( 1st 11 weeks )
![Page 58: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/58.jpg)
The EARLY START BUDGET( 5th through 15th week )
![Page 59: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/59.jpg)
The LATE START BUDGET( 1st 8 weeks )
![Page 60: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/60.jpg)
The LATE START BUDGET( 8th through 15th week )
![Page 61: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/61.jpg)
TheFeasible BudgetRegion
![Page 62: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/62.jpg)
Excelcannot do
projectbudgeting
![Page 63: PROJECT BUDGETING The overall goal in the budgeting process of a project is to determine how much money is to be spent each week or each month. PERT](https://reader035.vdocuments.mx/reader035/viewer/2022062802/56649e905503460f94b94491/html5/thumbnails/63.jpg)
PROJECT BUDGETING