What is Optimization?
Well Performance and System Analysis Production System Reservoir Fluid How do we get hydrocarbons to surface? Tubing Performance (Vertical Lift) Tubing Size Selection
System Analysis (Using Nodal Analysis)
Understand the components of Inflow Performance
Understand the components of vertical lift Performance
Understand combination of Inflow & vertical lift
performance
Objectives
Production Optimization
Production Optimization means… Balance between Production rate / Deliverability and demand Production Optimization includes a good understanding about Production
Systems and Reservoir Fluid
Well Performance & Production System
Production System
Production System
Reservoir Fluid
Phase Behavior Dry gas / Wet Gas, Condensate, Oil, Water
Fluid Properties Gas Properties Liquid Properties
Laboratory Measurements Composition Constant Volume Depletion
Reservoir Fluid Properties
Phase Behavior
The reservoir fluid can be classified into basically three types
i.e., single phase, two phases, or a combination.
Such information is used to determine the type of IPR equation
to be used.
From a technical point of view, the various types of reservoirs can be defined by the location of the initial reservoir temperature and pressure as commonly shown on pressure-temperature … (PT) phase diagrams.
Segments
Rock Properties & Reservoir character Reservoir Fluid qualities Reservoir flow paths The effect of pressure drop and back pressure on fluid flow in the Reservoir Fluid behavior in approach / entry to the wellbore Lift type and Optimization of flow from bottom hole through the tubing Operations effect on the flow rate… Choke setting Restrictions Separator operations Pipeline Start up/ shut down operations, stabilizing
System Analysis System Analysis
Well deliverability is determined by a well’s inflow performance.
The Inflow Performance Relationship (IPR) is defined as the functional relationship between the production rate and the bottom hole flowing pressure.
Productivity Index (PI or J) expresses the ability of a reservoir to deliver fluids to the wellbore.
Productivity Ratio (PR) is the ratio of actual productivity index to the ideal productivity index where skin, s=0.
Reservoir Deliverability System
Inflow Performance & Productivity Index
A commonly used measure of the ability of the well to produce …is Productivity Index
Defined by the symbol “J”, it is ratio of the total fluid flow rate to the pressure drawdown….
Drawdown (∆P) = (Pr- Pwf)
In generally,
PI = J = Q/ ∆P PI = Productivity Index Q = Flow rate, ∆P = Pressure drawdown, Pr = Average drainage pressure (static), Pwf = bottom hole flowing pressure,
System Analysis
In Flow Performance Relationship - IPR Curves The Inflow Performance Relationship (IPR) for a well is the relationship between the flow rate of the well q and the flowing pressure of the well Pwf. In single phase flow this is a straight line but when gas is moving in the reservoir, at a pressure below the bubble point, this in not a linear relationship.
Tubing Performance (Outflow Performance)
Tubing Performance (Outflow Performance)
Tubing Performance (Outflow Performance)
Picture yourself at the bottom of the flowing well …… Now this time …… Look up into the tubing …… What would prevent flow from the well? What would make this well produce more?
Tubing Performance (Outflow Performance)
The outflow system takes energy from the inflow system and use that energy to get the total fluid rate to surface
For the outflow system, the higher the pressure at the bottom of the well, the more fluid can be pushed from the well
( In order to overcome friction)
Tubing Performance (Outflow Performance)
Another convenient view of the Outflow is on a Depth Vs. Pressure graph (These are pressure in the tubing)
Factor Affecting Vertical Lift
Flowing Tubing Pressure Length of Tubing (Depth)
Friction factors
Tubing Diameter (ID)
Fluid Composition (Liquid / Gas)
Line Size Criteria
Erosional Velocity
Inflow Performance Relationship (IPR) & Tubing Performance Curves
System Analysis (Combination of Inflow Vs. Outflow)
IPR & TPR curves can be combined to find the Stabilized Flow Rate (Point of Natural Flow)
Tubing shoe reaches the perforation depth****
Wellbore flowing pressure and tubing intake pressure
are considered at the same depth
At a specific rate when these two pressures are equal, the flow system is in equilibrium and flow is Stable
System Analysis (Combination of Inflow Vs. Outflow)
System Analysis (Combination of Inflow Vs. Outflow)
Flowing bottom hole pressure (Pwf) = Tubing intake pressure(Pwf e) … the stable flow rate***
Production Rate & Tubing Sizing
Production Rate & Wellhead Pressures
Production Optimization using Nodal Analysis
Production Optimization Using Nodal Analysis
Well deliverability is determined by the combination of well inflow performance and wellbore flow performance. This work focuses on prediction of achievable fluid production rates from reservoirs with specified production string characteristics. The technique of analysis is called ‘‘Nodal analysis’’.
Its application to well producing systems was first proposed by Gilbert (1954).
Applications
Typical Applications include: Estimation of flow rates Selection of Tubing size Selection of Flowline size Selection of Wellhead pressure & surface choke Artificial Lift Design Estimation of the effects of reservoir pressure depletion Identification of flow restrictions
Optimization Procedure
Identify the components in the system
Select one component to be optimized
Select the node location that will best emphasize the effect of change
Develop expression for inflow and outflow
Calculate pressure drop versus rate for all components
Determine the effect of changing the characteristics of the selecting component Repeat the procedure for each component
Optimize the production system
Start Select Model Options
Set up and Match PVT Model
Input System Equipment & IPR
Yes
Match IPR & VLP
Calculate System Sensitivities
Performance Acceptable?
Review Design
Finish
Production
Optimization
Production
Optimization
Nodal Analysis
To simulate the fluid flow in the system, it is necessary to ‘‘break’’ the system into discrete nodes that separate system elements (equipment sections). Fluid properties at the elements are evaluated locally.
Nodal analysis is performed on the principle of pressure continuity, that is, there is only one unique pressure value at a given node regardless of whether the pressure is evaluated from the performance of upstream equipment or downstream equipment.
The performance curve (pressure–rate relation) of upstream equipment is called ‘‘inflow performance curve’’; the performance curve of downstream equipment is called ‘‘outflow performance curve.’’
The intersection of the two performance curves defines the operating point, that is, operating flow rate and pressure, at the specified node.
Production
Optimization
IPR & VLP Plot
Before Optimization
97 MMscf/day
Production Optimization
Effect of tubing size
79 MMscf/day
91 MMscf/day
104 MMscf/day
Production Optimization
Effect of Wellhead pressure
76
MMscf/day
94
MMscf/day
101
MMscf/day
Production Optimization
Effect of water cut
97 MMscf/day
80 MMscf/day
Production Optimization
Skin Effect
114 MMscf/day
84 MMscf/day
Production Optimization
After optimization
Specifications:
Tubing size: 6.18 inch
Wellhead pressure: 2000 psi
Assumptions:
Water Cut: 5%
Skin Factor: +1
Results
During the production, chosen well with tubing Size of 3.95" and 4.78" causes restriction because of tubing. But the production rate increases at the production with tubing Size of 6.18".
According to production potential of the well and reservoir and Capacity of surface equipment Wellhead Pressure 2000 psi for the well is appropriate.
If the creation restriction in bottom hole completion or Formation damage, inflow performance can be Improve using the Work Over Such as Hydraulic Fracturing or Acidizing.
According to formation stability (type and structure of reservoir rock), completion by the method of open hole is appropriate and there’s no need to mechanical integrity in the junction.
Commonly Accepted Correlations
Correlation Recommendations
Computer Programs for System Analysis