Download - Power grid synopsis
A
PROJECT SYNOPSIS
ON
GRID SYNCHRONIZATION FAIL DETECTION WITH UNDER VOLTAGE AND OVER VOLTAGE
SUBMITTED IN PARTIAL FULFILLMENT FOR THE AWARD OF THE
DEGREE OF BACHELOR OF TECHNOLOGY
IN ELECTRICAL ENGINEERING
Submitted by
Karishma 1812018Princy 1812020Diksha 1812031
Under the guidance of
(2012 – 2016)
Haryana Engineering CollegeJagadhri
(Kurukshetra University, Kurukshetra
INTRODUCTION
There is an Under/over voltage or under/over frequency, then the comparator will detect the
difference the actual power and reactive. If there is no failure of power grid synchronization then
the detectors will give the zero values. Based on the Under/over voltage and under/over
frequency values the power suppliers will be disconnected if any out of limitation values are
observed.
Synchronization means the minimization of difference in voltage, frequency and phase angle
between the corresponding phases of the generator output and grid supply. An alternating current
generator must be synchronized with the grid prior to connection. It can’t deliver the power
unless it is running at same frequency as the network. Synchronization must occur before
connecting the generator to a grid. Synchronization can be achieved manually or automatically.
The purpose of synchronization is to monitor, access, enable, and automatically take the control
action to prevent the abnormalities of voltage and frequency.
Rules must be followed for Synchronization:
Voltage Fluctuation:
When a generator is synchronized with a power grid, normally there is a voltage fluctuation on
the distribution line. During synchronization the voltage fluctuation should not exceed 3% at the
at the point of common coupling.
Synchronization Limits:
The limits allowing for synchronization are
1. Phase angle- +/-20 degrees
2. Maximum voltage difference – 7%
3. Maximum slip frequency – 0.44%
Relays:
For checking the synchronization “synch check relay” must be used. The usage of relays can’t
apply for induction generators. The use of synch check relay is to accept as a backup during
synchronization and to ensure a generator will not connect to a dead distribution line.
Synchronization of Induction Generators:
For the synchronization of induction generators it just needs to be run up to synchronization
speed and connected. For this purpose standard motor controllers will be used. To mechanically
drive the generators up to synchronization speed turbine shaft power will be used. The speed of
the motors depends on supplied frequency and number of poles on the generators.
Synchronization of Synchronous Machines:
For synchronous generators output waveform should be in phase with the grid voltage waveform
or with in specified limits. The rate of change of phase angle between the grid and the machine
(generator) must be with in the specified limits.
Some other rules are variable speed drive arrangement to maintain a constant output frequency,
inter connection protection between the generator and distribution system.
Failure of Synchronization:
Synchronization circuit may fail for responding to a received input pulse when the received input
pulse is shorted than the sampling period of the synchronizer. Then no synchronized
representation will take place. When the pulse rate of the input signal is higher than the
synchronization rate of the synchronizer then also it may fail to respond. Some times the
synchronizer it self may fail by ignoring input events. These all are the circumstances which
could create problems if not detected. There are various reasons for failure of power grid
synchronization.
Synchronization Failures and their Detections:
There are some situations where the generators and some local loads have become disconnected
from main distribution lines. Due to this reduction in quality of supply, and it may prevent
automatic reconnection of devices. This is called as islanding. For this reason islanding must be
detected immediately and producing power must be stopped immediately.
Due to Islanding following hazards may take place
1. Generally distributed lines are earthed only at the sub station. When the distributing lines and
generators are disconnected the line is not earthed. Due to this reason line voltages may
excessive.
2. The fault level contribution from the grid to sub-station may be lost. This will effect the
operation of protection on distributed lines. Due to this sufficient current may not be generated.
3. Due to Islanding synchronization can’t be maintained. When the grip attempts to reconnect with
distribution line it may be out of synchronization at the reconnection point. Due to this, suddenly
large power may flows which cause damage for generators, distribution units and consumer
products.
Some other disadvantages due to islanding are the voltage levels may go outside of normal
operating limits, and the quality of supply may be reduced.
Detection methods of Islanding:
Detection of islanding can be done through active and passive methods. Passive methods look
for transient events on the grid and active methods will probe the grid by sending signals from
the distribution point of grid. Loss of Mains Protection (LoM) will be designed to sense the
disconnection of generators and loads when an island has been created. The most utilized LoM
detection methods may fail to detect islanding when the production matches closely with the
consumption in the island zone. This blind area is called Non Detection Zone (NDZ). The size of
NDZ can be reduced by tightening the LoM setting relays.
Active Methods:
Impedance measurement, Detection of impedance at specific frequency, slip mode frequency
shift, Frequency bias, and frequency jump detection methods are some passive methods for
islanding detection. The advantage of impedance measurement method is an extremely small
NDZ for a single inverter. Slip mode frequency shift method is relatively easy to implement. It is
highly effective in islanding prevention when compared to other detection methods.
Passive Methods:
All grid-connected PV inverters are required to have Over/Under frequency protections methods
and Under/Over voltage protection methods that cause the inverter to stop supplying power to
the utility grid if the frequency or voltage of grid at the point of coupling.
Block Diagram
These protection methods protect consumer’s equipment and also servicing as anti-islanding
methods. Voltage Phase Jump detection, and Detection of voltage harmonics are some more
passive methods for detection islanding. The Under/Over voltage protection methods and the
Under/over frequency methods are required other than preventing islanding. Several islanding
prevention methods produce abnormal voltage, and frequency. Under/Over voltage protection
methods and Under/Over frequency protection methods are low cost methods for the detection
islanding.
Applications of Power grid failure Detection:
Lighting is one of the main causes for power system faults. The entire power system is consisting
electrically of power plants, sub-stations and transmission lines, distribution feeders and power
consumers. Detecting the synchronization failure between generators and power grid is the major
advantage such as saving the energy. Then we can avoid the loss of power consumption by
disconnecting from the power consumption devices.
When there is an Under/over voltage or under/over frequency, then the comparator will detect
the difference the actual power and reactive. If there is no failure of power grid synchronization
then the detectors will give the zero values. Based on the Under/over voltage and under/over
frequency values the power suppliers will be disconnected if any out of limitation values are
observed.