  • Activity ID Activity Name OriginalDuration

    Start Finish

    Tender Inv # AHG/2014.051/ITT:-Installation of Cathodic Protection System for Well CasingTender Inv # AHG/2014.051/ITT:-Installation of Cathodic Protection System for Well CasingTender Inv # AHG/2014.051/ITT:-Installation of Cathodic Protection System for Well CasingTender Inv # AHG/2014.051/ITT:-Installation of Cathodic Protection System for Well CasingTender Inv # AHG/2014.051/ITT:-Installation of Cathodic Protection System for Well CasingAWARD OF CONTRACTAWARD OF CONTRACTAWARD OF CONTRACTAWARD OF CONTRACTAWARD OF CONTRACT

    10 Award of Contract 1 01-Oct-14 01-Oct-14

    20 Kick off Meeting 1 02-Oct-14 02-Oct-14

    30 Mobilization of Engineering Team 5 20-Oct-14 25-Oct-14

    40 Site Survey & Collection of Datas 15 07-Dec-14 23-Dec-14

    DOCUEMENT SUBMISSION & APPROVALDOCUEMENT SUBMISSION & APPROVALDOCUEMENT SUBMISSION & APPROVALDOCUEMENT SUBMISSION & APPROVALDOCUEMENT SUBMISSION & APPROVAL50 Preparation & Submission of Project HSE,Quality

    Documents,Engineering Design & Drawings30 23-Oct-14 26-Nov-14

    60 Prepartion & Submission of Material Submittal 20 25-Oct-14 16-Nov-14

    70 Approval of Project HSE & Quality Documents 10 25-Nov-14 06-Dec-14

    80 Approval of Material Submittal,Engineering Design & Drawings 10 08-Nov-14 18-Nov-14

    PROCUREMENT OF PROJECT MATERIALPROCUREMENT OF PROJECT MATERIALPROCUREMENT OF PROJECT MATERIALPROCUREMENT OF PROJECT MATERIALPROCUREMENT OF PROJECT MATERIAL100 Procurement of Solar & Components 140 20-Nov-14 02-May-15

    90 Procurement of Material Except Solar 60 29-Dec-14 08-Mar-15

    PROJECT EXECUTIONPROJECT EXECUTIONPROJECT EXECUTIONPROJECT EXECUTIONPROJECT EXECUTION110 Mobilization of Execution Team 14 01-Mar-15 16-Mar-15

    120 Preacasting & Preparatory Works 30 07-Mar-15 09-Apr-15

    130 Drilling of Anode Ground Bed 20 01-Apr-15 23-Apr-15

    140 Civil Works,Installation of Solar Systems 40 11-Apr-15 26-May-15

    150 Termination of Electrical & CP Cables 15 16-May-15* 01-Jun-15

    COMMISSIONINGCOMMISSIONINGCOMMISSIONINGCOMMISSIONINGCOMMISSIONING160 Commissioning of CP Sysytems 15 02-Jun-15 18-Jun-15

    170 Submission of Final Documents 10 15-Jun-15 25-Jun-15

    180 Project Hand Over 1 27-Jun-15* 27-Jun-15

    -1 1 2 3 4 5 6 7 8 9 10 11Month

    Award of Contract

    Kick off Meeting

    Mobilization of Engineering Team

    Site Survey & Collection of Datas

    Preparation & Submission of Project HSE,Quality Documents,Engineering Design & Drawings

    Prepartion & Submission of Material Submittal

    Approval of Project HSE & Quality Documents

    Approval of Material Submittal,Engineering Design & Drawings

    Procurement of Solar & Components

    Procurement of Material Except Solar

    Mobilization of Execution Team

    Preacasting & Preparatory Works

    Drilling of Anode Ground Bed

    Civil Works,Installation of Solar Systems

    Termination of Electrical & CP Cables

    Commissioning of CP Sysytems

    Submission of Final Documents

    Project Hand Over

    TENTATIVE CONSTRUCTION SCHEDULE

    Tender Inv # AHG/2014.051/ITT:-Installation of Cathodic Protection System for WellCasing(BSST-CP14222)

    BSS TECHNOLOGIES

    Date Revision Checked Approved15-Jun-14 Rev 0 MN TM