Planning and Scheduling
Dr. Ir. HM. Agung Wibowo, MM, MSc
Jati Utomo Dwi Hatmoko, ST, MM, MSc, PhD
-
7/24/2019 Planning and Scheduling - CPM
2/30
Gantt Chart(Mawdesley, 1997)
-
7/24/2019 Planning and Scheduling - CPM
3/30
Linked Bar Chart(Mawdesley, 1997)
-
7/24/2019 Planning and Scheduling - CPM
4/30
Techniques of Scheduling
List of Activities
Bar chart / Gantt Chart
Critical Path Method (CPM)
Precedence Diagram Network (PDM)
PERT (Programme Evaluation & ReviewTechnique)
Line of Balance Method
Time Chainage Diagram (Mass HaulDiagram)
-
7/24/2019 Planning and Scheduling - CPM
5/30
Network
A network is a diagram showing allactivites which are needed to complete aproject and the order of which theymust be done.It therefore comprises two parts :
The activitiesSome method of displaying thetechnological logic of construction.
-
7/24/2019 Planning and Scheduling - CPM
6/30
Scheduling techniques
1. Bar chart (Gantt chart)2. Network Activity on Arrow (CPM - Critical Path Method)
Arrow Diagramming Method (ADM)
Activity on Node (PDMPrecedence DiagramMethod)
-
7/24/2019 Planning and Scheduling - CPM
7/30
Network (Mawdesley, 1997)Activity on Arrow
-
7/24/2019 Planning and Scheduling - CPM
8/30
Activity on Arrow (CPM - Critical Path Method)
North
base
South
base
South
stem
North
stem
North
wwalls
North
backfill
South
wwallsSouth
backfill
Deck
KerbsSurfacing
1 2
3
4
5
6 7 8 9 106 6
15
15
12
12
6
6
20
2 2
0 6
21
21
33
36 48 56 58 60
6058565036
36
21
21
60
-
7/24/2019 Planning and Scheduling - CPM
9/30
N & S
bases
N
stem
N
wwall
S
stem
S
wwall
S
b/fill
Deck
KerbsSur-
facing
12
15 12
15 12 6 2 21
2
3
4
5
6 20
7 9 10
0
6
activity
name
durationactivity
reference
earlieststart
earliest
finish
KEY
N
b/fill
68
12
6 21 21 33
21 36 36
33 39
48 48 54 56 58 58 60
5636
N
b/fill
68
33 39
0
6 21
21 36
26 38
38 50
36 56
50 56 56 58
50 56
58 6021
latest
start
latest
finish
50 56
12
Activity on Node
(PDMPrecedence Diagram Method)
-
7/24/2019 Planning and Scheduling - CPM
10/30
Project Scheduling
Steps
Define activities
Sequence activities
Estimate time /duration
Develop schedule
Excavate base
Blind base
Formwork
Reinforcement
Concrete
(4d)
(2d)
(5d)
(4d)
(1d)
Excavate base Blind base Formwork Reinforcement Concrete
4 d 2d 5d 4d 1d
-
7/24/2019 Planning and Scheduling - CPM
11/30
Linking Activities in the project
A B
A
B
Bar ChartActivity on the arrow
network
A B
Precedence diagram
Activity on B depends on activity A
predecessor successor
-
7/24/2019 Planning and Scheduling - CPM
12/30
Bar ChartActivity on the arrow
networkPrecedence diagram
AC
A
B
A
CCB B
Activity on C depends on activities A and B
Linking Activities in the project
-
7/24/2019 Planning and Scheduling - CPM
13/30
Bar ChartActivity on the arrow
networkPrecedence diagram
A CA
B
A C
C
B BDD D
Activity on C and D depends on activities A and B
Linking Activities in the project
-
7/24/2019 Planning and Scheduling - CPM
14/30
Bar ChartActivity on the arrow
networkPrecedence diagram
A C
A
B
A C
C
B BDD D
Activity on C depends on activity A and D depends on both activities A and B
Linking Activities in the project
Dummy
-
7/24/2019 Planning and Scheduling - CPM
15/30
Only one activity is allowed for two events
-
7/24/2019 Planning and Scheduling - CPM
16/30
Copyright 2006 John Wiley& Sons, Inc. 9-16
Concurrent Activities
2 3
Lay foundation
Order material
(a) Incorrect precedencerelationship
(b) Correct precedencerelationship
3
42
DummyLay
foundation
Order material
1
2 0
-
7/24/2019 Planning and Scheduling - CPM
17/30
Using dummies in the network
Excavate (A) Foundation (B) Wall (C)
The Project : 100 m Brickwall
Excavate (A)
Foundation (B)
Wall (C)
-
7/24/2019 Planning and Scheduling - CPM
18/30
A1 = Excavate base (40m)A2 = Excavate base (30m)A3 = Excavate base (30m)
B1 = Foundation (40m)
B2 = Foundation (30m)B3 = Foundation (30m)
C1 = Wall (40m)C2 = Wall (30m)C3 = Wall (30m)
Activity A(Excavate base 100m)
Activity B(Foundation 100m)
Activity C(Wall 100m)
Excavate (A)
Foundation (B)
Wall (C)
-
7/24/2019 Planning and Scheduling - CPM
19/30
Only one event at the start, and at the end of the network
-
7/24/2019 Planning and Scheduling - CPM
20/30
PM
Event i Eventj
i j
iES
jEFActivity A
Duration (d)LS LF
(ES) Early start : the earliest the event i (activity A) can start
(EF) Early finish : the earliest the event j can start or - the earliest the activity A can finish
(LS) Latest start : the latest the event i (activity A) can start without delaying the project
(LF) Latest finish : the latest the event j can start or the latest the activity A can finishwithout delaying the project
-
7/24/2019 Planning and Scheduling - CPM
21/30
iES
jEFActivity A
Duration (d)LS LF
(ES) Early start = EST (Early Start Time) = EETi (Early Event Time)
(EF) Early finish= EFT (Early FinishTime) = EETj (Early Event Time j)
(LS) Latest start = LST (Latest Start Time) = LETi (Latest Event Time i )
(LF) Latest finish = LFT (Latest FinishTime) = LETi (Latest Event Time j )
-
7/24/2019 Planning and Scheduling - CPM
22/30
Forward Pass
iES
jEFActivity A
Duration (d)
EF = ES + duration
-
7/24/2019 Planning and Scheduling - CPM
23/30
Backward Pass
i jActivity A
Duration (d)LS LF
LS = LF - duration
-
7/24/2019 Planning and Scheduling - CPM
24/30
embankmentalready
constructed
existing ground
profile
existing ground
profile
finished ground
profile
NORTH ABUTMENT SOUTH ABUTMENT
wingwalls stem
base
deck
backfill
embankmentalready
constructed
Activity Name Activity Reference Activity duration (days)
North base 1 6
South base 2 6North abutment stem 3 15
South abutment stem 4 15
North wingwalls 5 12
South wingwalls 8 12
North backfill 7 6
South backfill 6 6
Deck 9 20Kerbs 10 2
Surfacing 11 2
Resource constraint: only one set of formwork is available for
base, one set for abutment stems and one set for wingwalls
12
-
7/24/2019 Planning and Scheduling - CPM
25/30
Activity on Arrow (CPM - Critical Path Method)
North
base
South
base
South
stem
North
stem
North
wwalls
North
backfill
South
wwallsSouth
backfill
Deck
KerbsSurfacing
1 2
3
4
5
6 7 8 9 106 6
15
15
12
12
6
6
20
2 2
0 6
21
21
33
36 48 56 58 60
6058565036
36
21
21
60
FORWARD PASS
-
7/24/2019 Planning and Scheduling - CPM
26/30
Activity on Arrow (CPM - Critical Path Method)
North
base
South
base
South
stem
North
stem
North
wwalls
North
backfill
South
wwallsSouth
backfill
Deck
KerbsSurfacing
1 2
3
4
5
6 7 8 9 106 6
15
15
12
12
6
6
20
2 2
0 6
21
21
33
36 48 56 58 60
6058565036
36
21
21
60
BACKWARD PASS
-
7/24/2019 Planning and Scheduling - CPM
27/30
Activity on Arrow (CPM - Critical Path Method)
North
base
South
base
South
stem
North
stem
North
wwalls
North
backfill
South
wwallsSouth
backfill
Deck
KerbsSurfacing
1 2
3
4
5
6 7 8 9 106 6
15
15
12
12
6
6
20
2 2
0 6
21
21
33
36 48 56 58 60
6058565036
36
21
21
60
Free float (FF) : the maximum time an activity can be delayed without delaying any subsequent
activities that are starting at their earliest times
FF = EFjduration - ESi
iES
jEFActivity A
Duration
(d)LS LF
FF = 0TF= 0
FF =9TF=9
FF =0TF=0
FF =0TF=2
FF =2TF=2
FF =0TF =0
FF =0TF=0
FF =0TF =0
FF =17TF=17FF =0
TF=3FF = 0TF=0
-
7/24/2019 Planning and Scheduling - CPM
28/30
Activity on Arrow (CPM - Critical Path Method)
North
base
South
base
South
stem
North
stem
North
wwalls
North
backfill
South
wwallsSouth
backfill
Deck
KerbsSurfacing
1 2
3
4
5
6 7 8 9 106 6
15
15
12
12
6
6
20
2 2
0 6
21
21
33
36 48 56 58 60
6058565036
36
21
21
60
Total float (TF) : the maximum time an activity can be delayed without delaying the whole project
TF = LFjduration - ESi
iES
jEFActivity A
Duration
(d)LS LFThe Total float is shared by activities in the network.
FF = 0TF= 0
FF =9TF=9
FF =0TF=0
FF =0TF=2
FF =2TF=2
FF =0TF =0
FF =0TF=0
FF =0TF =0
FF =17TF=17FF =0
TF=3FF = 0TF=0
Interferent float (TF) = TF FF
-
7/24/2019 Planning and Scheduling - CPM
29/30
Activity
Name
Activity
Reference
Activity
duration
(days)
ES i LSi EFj LFj FF TF IF
North base 1 6
South base 2 6
North
abutment
stem
3 15
South
abutment
stem
4 15
North
wingwalls
5 12
South
wingwalls
8 12
North
backfill
7 6
South
backfill
6 6
Deck 9 20
Kerbs 10 2
Surfacing 11 2
We can use a table for this
-
7/24/2019 Planning and Scheduling - CPM
30/30
Critical Path
North
base
South
base
South
stem
North
stem
North
wwalls
North
backfill
South
wwallsSouth
backfill
Deck
KerbsSurfacing
1 2
3
4
5
6 7 8 9 106 6
15
15
12
12
6
6
20
2 2
0 6
21
21
33
36 48 56 58 60
6058565036
36
21
21
60
The longest path It determines the programme Any delay on the critical path means that the project will be delayed There could be > 1 critical path in the network
Path 1 = NB+SB+SS+SW+SB+K+S = 49Path2 = NB +NS+NW+NB+K+S= 43Path 3 = NB+SB+SS+D+K+S=51Path 4 = NB+NS+SS+SW+SB+K+S=58Path 5 = NB+NS+NW+SW+SB+K+S=55Path 6 = NB+NS+NW+D+K+S=57
Path 7 = NB+NS+SS+D+K+S=60 the critical path