PLANIFICATION DES TRAVAUX 2014
RÉSEAU PJCCI
![Page 2: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/2.jpg)
2
PLAN DE PRÉSENTATION
1. Planification des travaux 2014
2. Calendrier préliminaire
3. Plan d’action Champlain
4. Réfection de la section fédérale du pont Honoré-Mercier
5. Pont de contournement de l’île des Sœurs
6. Communication
7. Questions
![Page 3: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/3.jpg)
3
PRÉSENTATION EN LIGNE POUR CONSULTATION
PRESENTATION ON LINEFOR CONSULTATION
![Page 4: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/4.jpg)
41 PLANIFICATION2014Sandra Martel, ing.Directrice principale, Planification
![Page 5: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/5.jpg)
ENVELOPPE BUDGÉTAIRE RÉALISATION DES TRAVAUX SUR NOTRE RÉSEAU
RÉALISÉRÉALISÉ PLANIFIÉ
2012 20132014
Pont Champlain 30 M $ 46 M $147 M $
A-15 (pont de l’île des Soeurs) 7 M $ 12 M $ 40 M $
A-Bonaventure 7 M $ 17 M $ 31 M $
Pont de contournement 2 M $ 33 M $ 57 M $
Estacade 2 M $ 4 M $ 4 M $
Pont Jacques-Cartier 18 M $ 25 M $ 35 M $
Tunnel de Melocheville 1 M $ 2 M $ 7 M $
Pont Honoré-Mercier 22 M $ 22 M $ 43 M $
(section fédéral)
TOTAL 89 M $ 161 M $ 364 M $
5
![Page 6: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/6.jpg)
6
1.PLANIFICATION 2014
• Travaux d’acier sous le pont Jacques-Cartier (renfort, appui, etc.)
• Pavage sur le pont Champlain (voie extérieure dans les deux directions)
• Pavage des viaducs l’A-15 Nord et Sud
• Remplacement de joints de dilatation sur le pont Champlain (8)
• Travaux de reconstruction du Viaduc N
• Travaux de reconstruction du Viaduc Principal
• Installation d’instrumentation sur le pont Champlain
• Travaux de remplacement du tablier d’une section de l’A-Bonaventure
• Travaux de réfection du Viaduc T
• Travaux de maintien du pont de l’Île-des-Sœurs
• Poursuite de la construction du pont de contournement de l’Île-des-Sœurs
• Divers travaux : secteur Ouest du Technoparc
• Remplacement du tablier du pont Honoré-Mercier
• Travaux dans les tubes du tunnel de Melocheville
AVEC IMPACT POTENTIEL SUR LA CIRCULATION
![Page 7: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/7.jpg)
7
1. PLANIFICATION 2014
PONT JACQUES-CARTIER
![Page 8: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/8.jpg)
8
1.1 PONT JACQUES-CARTIERTRAVAUX 2014
B - Travaux d’acier
A - Remplacement d’appareils d’appui de la rampe aval
![Page 9: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/9.jpg)
9
• RÉPARATION D’ACIER– Fermetures complètes de nuit (1h à 4h) (environ 15) – Fermetures ponctuelles de nuit (maintien d’une voie par direction)
• REMPLACEMENT DES APPAREILS D’APPUI DE LA RAMPE AVAL– Fermetures complètes de nuit de semaine (1h à 4h) (environ 6)
• INSTALLATION DE BARRIÈRES AUTOMATISÉES – APPROCHE MONTRÉAL– Fermetures ponctuelles de nuit de semaine ou de week-ends (à
déterminer)
1.1 PONT JACQUES-CARTIERTRAVAUX 2014
![Page 10: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/10.jpg)
10
1. PLANIFICATION 2014
CORRIDOR CHAMPLAIN
![Page 11: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/11.jpg)
11
-A-TRAVAUX DE PAVAGE, DE MEMBRANES DES VOIES EXTÉRIEURES ET DE TREILLIS MODULAIRE
BLITZ DU PRINTEMPS (MAI)
![Page 12: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/12.jpg)
12
Pavage des viaducs de l’A-15
Pavage et membrane des voies extérieures du pont Champlain
Maintien du pont de l’IDS
• Enlèvement de la poutre de support
• Installation du treillis modulaire
1.2 CORRIDOR DU PONT CHAMPLAINA- BLITZ DU PRINTEMPS 2014 (MAI)
![Page 13: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/13.jpg)
13
3 À 4 FINS DE SEMAINES DE TRAVAUX
XXX
MONTRÉAL
RIVE-SUD
X X
XXX
X X
FINS DE SEMAINE A FIN DE SEMAINE B
Po
nt
Ch
amp
lain
A-1
51.2 CORRIDOR DU PONT CHAMPLAINA- BLITZ DU PRINTEMPS 2014 (MAI)
FIN DE SEMAINE B
XXX XXX
Po
nt
IDS
![Page 14: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/14.jpg)
14
-B-TRAVAUX DE JOINTS DE DILATATION, DE GLISSIÈRES ET RACCORDEMENT DU PONT DE CONTOURNEMENT
BLITZ DE L’AUTOMNE
![Page 15: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/15.jpg)
15
Raccordement du pont de contournement
Glissières latérales
Joints de dilatation
1.2 CORRIDOR DU PONT CHAMPLAINB- BLITZ DE L’AUTOMNE 2014 (SEPTEMBRE ET OCTOBRE)
![Page 16: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/16.jpg)
16
Po
nt
Ch
amp
lain
A-1
5
FINS DE SEMAINE A FIN DE SEMAINE B
X XX
Remplacement de 8 demi joints de dilatation + glissières latérales
X XX
Remplacement de 8 demi joints de dilatation + glissières latérales
X X
4 à 5 FINS DE SEMAINES DE
TRAVAUX
POSSIBILITÉ DE COMBINER LES
INTERVENTIONS À VALIDER
MONTRÉAL
RIVE-SUD
1.2 CORRIDOR DU PONT CHAMPLAINB- BLITZ DE L’AUTOMNE 2014 (SEPTEMBRE ET OCTOBRE)
![Page 17: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/17.jpg)
17
1.2 CORRIDOR DU PONT CHAMPLAIN
PONT DE CONTOURNEMENT DE L’IDS
B- BLITZ DE L’AUTOMNE 2014 (SEPTEMBRE ET OCTOBRE)
![Page 18: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/18.jpg)
18
FINS DE SEMAINE CRACCORDEMENT
DE LA DIR. MONTRÉAL
Pont Champlain
Pont de l’île des Sœurs
X X X
Fermeture complète de
l’entrée de l’IDS pour l’A-15
Nord (1 mois) X
1.2 CORRIDOR DU PONT CHAMPLAINB- BLITZ DE L’AUTOMNE 2014 (SEPTEMBRE ET OCTOBRE)
Détour d’environ 4 km
![Page 19: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/19.jpg)
19
FINS DE SEMAINE DRACCORDEMENT
DE LA DIR. RIVE-SUD
Pont Champlain
X XX
Fermeture complète de la sortie 57 N de
l’A-15 Sud vers l’IDS (1 mois)
1.2 CORRIDOR DU PONT CHAMPLAINB- BLITZ DE L’AUTOMNE 2014 (SEPTEMBRE ET OCTOBRE)
Pont de l’île des Sœurs
Détour d’environ 4 km
![Page 20: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/20.jpg)
20
-C-REMPLACEMENT DU TABLIER DE L’AUTOROUTE BONAVENTURE
9 MOIS
![Page 21: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/21.jpg)
21
Replacement of the concrete deck of the Bonaventure Expressway
1.2 CHAMPLAIN BRIDGE CORRIDORC- BONAVENTURE EXPRESSWAY DECK REPLACEMENT
![Page 22: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/22.jpg)
22
1.2 CHAMPLAIN BRIDGE CORRIDORC- BONAVENTURE EXPRESSWAY DECK REPLACEMENT
![Page 23: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/23.jpg)
XX
Section fédérale Autoroute Bonaventure
23
DIRECTION CENTRE-VILLE DE MONTRÉAL
DIRECTION PONT CHAMPLAIN
PHASE 1TRAVAUX EN CONTINUEAVRIL AU DÉBUT JUILLET
1.2 CORRIDOR DU PONT CHAMPLAINC- REMPLACEMENT DU TABLIER DE L’A-BONAVENTURE
![Page 24: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/24.jpg)
24
XX
DIRECTION CENTRE-VILLE DE MONTRÉAL
DIRECTION PONT CHAMPLAIN
Section fédérale Autoroute Bonaventure
PHASE 2TRAVAUX EN CONTINUE
DÉBUT JUILLET À MI-AOÛT
1.2 CORRIDOR DU PONT CHAMPLAINC- REMPLACEMENT DU TABLIER DE L’A-BONAVENTURE
![Page 25: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/25.jpg)
25
XX
25
DIRECTION CENTRE-VILLE DE MONTRÉAL
DIRECTION PONT CHAMPLAIN
Section fédérale Autoroute Bonaventure
PHASE 3TRAVAUX EN CONTINUE
MI-AOÛT À FIN SEPTEMBRE
1.2 CORRIDOR DU PONT CHAMPLAINC- REMPLACEMENT DU TABLIER DE L’A-BONAVENTURE
![Page 26: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/26.jpg)
26
XX
26
DIRECTION CENTRE-VILLE DE MONTRÉAL
DIRECTION PONT CHAMPLAIN
Section fédérale Autoroute Bonaventure
PHASE 4TRAVAUX EN CONTINUE
FIN SEPTEMBRE AU DÉBUT NOVEMBRE
1.2 CORRIDOR DU PONT CHAMPLAINC- REMPLACEMENT DU TABLIER DE L’A-BONAVENTURE
![Page 27: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/27.jpg)
27
XX
27
DIRECTION CENTRE-VILLE DE MONTRÉAL
DIRECTION PONT CHAMPLAIN
Section fédérale Autoroute Bonaventure
PHASE 5TRAVAUX EN CONTINUE
DÉBUT NOVEMBRE À FIN DÉCEMBRE
1.2 CORRIDOR DU PONT CHAMPLAINC- REMPLACEMENT DU TABLIER DE L’A-BONAVENTURE
![Page 28: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/28.jpg)
28
D- AUTRES TRAVAUX À EFFECTUER
• REMPLACEMENT DU VIADUC N (RACCORDEMENT)– Fermeture complète de l’accès de la sortie 60 de l’A-15 Nord vers le
centre-ville pour une fin de semaine
• RECONSTRUCTION DU VIADUC PRINCIPAL (MOBILISATION ET CHANGEMENT DE PHASE)– Fermetures ponctuelles de nuit (Entre le 1 avril et le 9 mai 2014)
• INSTALLATION D’INSTRUMENTATION SUR LE PONT CHAMPLAIN ET ENTRETIEN RÉGULIER– Plusieurs fermetures partielles de nuit (2 voies sur 3)
1.2 CORRIDOR DU PONT CHAMPLAIN
![Page 29: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/29.jpg)
29
VIADUC PRINCIPAL
CHAUSSÉESDRAINAGE
GLISSIÈRESET DIVERS
RÉTRÉCISSEMENTDES VOIES
D- AUTRES TRAVAUX À EFFECTUER
1.2 CORRIDOR DU PONT CHAMPLAIN
![Page 30: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/30.jpg)
30
1. PLANIFICATION 2014
PONT HONORÉ-MERCIERSECTION FÉDÉRALE
![Page 31: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/31.jpg)
31
-A-REMPLACEMENT DU TABLIER DE BÉTON
7 SEMAINES CONSÉCUTIVES
![Page 32: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/32.jpg)
32
Po
nt
Mer
cier
XX
MONTRÉAL
RIVE-SUD
TRAVAUX INTENSIFS2014 (JUIN,
JUILLET ET AOÛT)
7 SEMAINES CONSÉCUTIVESD
E TRAVAUX
COORDINATION AVEC LE MTQ
SE
CT
ION
F
ÉD
ÉR
AL
ES
EC
TIO
N
PR
OV
INC
IAL
E
XX
A- REMPLACEMENT DU TABLIER DE BÉTON
1.3 SECTION FÉDÉRALE – PONT MERCIER
![Page 33: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/33.jpg)
33
FEDERALWORK ZONE
Pier 14
Pier 28
PHASE 2WORK TOWARDS MONTREALONE LANE / DIRECTION
SOUTH-SHORE
MONTREAL
![Page 34: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/34.jpg)
342 CALENDRIER PRÉLIMINAIRE
Sandra Martel, ing.Directrice principale, Planification
![Page 35: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/35.jpg)
35Travaux sur le Pont Jacques-Cartier
Travaux sur le Pont Champlain
Travaux sur le Pont Honoré-Mercier
Travaux sur le l’autoroute Bonaventure
2. CALENDRIER PRÉLIMINAIREJANVIER À JUIN
![Page 36: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/36.jpg)
36Travaux sur le Pont Jacques-Cartier
Travaux sur le Pont Champlain
Travaux sur le Pont Honoré-Mercier
Travaux sur le l’autoroute Bonaventure
2. CALENDRIER PRÉLIMINAIREJUILLET À DÉCEMBRE
![Page 37: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/37.jpg)
373 PLAN D’ACTIONPONT CHAMPLAIN
Steve Tselios, ing.Directeur principal, Ingénierie
![Page 38: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/38.jpg)
38
3. PLAN D’ACTION PONT CHAMPLAINRETOUR SUR L’OPÉRATION DE LA POUTRE DE SUPPORT
PHASE 1 : INSTALLATION POUTRE DE SUPPORT – 30 NOVEMBRE 2013
![Page 39: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/39.jpg)
39
3. PLAN D’ACTION PONT CHAMPLAINRETOUR SUR L’OPÉRATION DE LA POUTRE DE SUPPORT
INSTALLÉS PAR BARGE À PARTIR DE L’EAU POUR ÉVITER LES IMPACTS SUR LA CIRCULATION
PHASE 2 : INSTALLATION TREILLIS MODULAIRE
TREILLIS MODULAIRE
POUTRE DE SUPPORT
![Page 40: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/40.jpg)
40
3. PLAN D’ACTION PONT CHAMPLAINRETOUR SUR L’OPÉRATION DE LA POUTRE DE SUPPORT
PHASE 3A : TRANSFERT DES CHARGES
![Page 41: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/41.jpg)
41
3. PLAN D’ACTION PONT CHAMPLAINRETOUR SUR L’OPÉRATION DE LA POUTRE DE SUPPORT
PHASE 3B : DÉMANTÈLEMENT DE LA POUTRE DE SUPPORT
![Page 42: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/42.jpg)
3. ACTION PLAN CHAMPLAIN BRIDGERETURN TO THE OPERATION OF THE SUPPORT BEAM
42
RESULT: FULLY REOPEN LANE #1 AND RE-ESTABLISH THE RESERVED BUS LANE DURING MORNING RUSH-HOUR
X
.
![Page 43: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/43.jpg)
43
CHAMPLAIN BRIDGE
(UNIQUE)
CONVENTIONAL BRIDGE(TODAY)
DALLE INTERCALAIRE
DALLE INTERCALAIRE
DALLE INTERCALAIRE
DALLE INTERCALAIRE
DALLE INTERCALAIRE
DALLE INTERCALAIRE
54 transverse cables which compress the beams and deck slab together to form a ``sandwich``
3. ACTION PLAN CHAMPLAIN BRIDGECHAMPLAIN BRIDGE VS CONVENTIONAL BRIDGE
![Page 44: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/44.jpg)
44
CHAMPLAIN BRIDGE
(UNIQUE)
CONVENTIONAL BRIDGE(TODAY)
DALLE INTERCALAIRE
DALLE INTERCALAIRE
DALLE INTERCALAIRE
DALLE INTERCALAIRE
DALLE INTERCALAIRE
DALLE INTERCALAIRE
54 transverse cables which compress the beams and deck slab together to form a ``sandwich``
3. ACTION PLAN CHAMPLAIN BRIDGECHAMPLAIN BRIDGE VS CONVENTIONAL BRIDGE
![Page 45: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/45.jpg)
45
CHAMPLAIN BRIDGE
(UNIQUE)
CONVENTIONAL BRIDGE(TODAY)
P7 PROBLEMATIC
BEAMS
P1PROBLEMATIC
BEAMS
DALLE INTERCALAIRE
DALLE INTERCALAIRE
DALLE INTERCALAIRE
DALLE INTERCALAIRE
DALLE INTERCALAIRE
DALLE INTERCALAIRE
54 transverse cables which compress the beams and deck slab together to form a ``sandwich``
3. ACTION PLAN CHAMPLAIN BRIDGECHAMPLAIN BRIDGE VS CONVENTIONAL BRIDGE
![Page 46: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/46.jpg)
46
Corrosion of internal cables
3. ACTION PLAN CHAMPLAIN BRIDGEPROBLEMS ENCOUNTERED
![Page 47: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/47.jpg)
47
INSPECTIONS : (AECOM, B&T ET EXP) 2013
3. ACTION PLAN CHAMPLAIN BRIDGE
PUBLISHED ON OUR INTERNET SITE: JCCBI.CA – PJCCI.CA
![Page 48: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/48.jpg)
48
INSTRUMENTATION DU PONT (CAPTEURS DE FIBRE OPTIQUE)
100%
DES SECTIONS 5 ET 7 INSTRUMENTÉES
À LA FIN 2014
3. PLAN D’ACTION PONT CHAMPLAIN
Section 5 : 50 %
Section 7 : 100%
2014
![Page 49: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/49.jpg)
49
INDICE DE SANTÉ
(AUJOURD’HUI)
50 TRAVÉES
100 POUTRES
DE RIVE
3. PLAN D’ACTION PONT CHAMPLAIN
__________
Section 5
Section 7
![Page 50: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/50.jpg)
50
Modèle 1.0
Modèle 2.0
Modèle 1.0
3. PLAN D’ACTION PONT CHAMPLAINRENFORT AUX POUTRES
MESURE 1 - POST-TENSION 2.0: 48 % en 2014 + 17 % en 2015
![Page 51: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/51.jpg)
51
3. PLAN D’ACTION PONT CHAMPLAINRENFORT AUX POUTRES
QP1
QP2
MESURE 2 - ARBALÈTE: 40 % poutres complétées
![Page 52: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/52.jpg)
52
3. PLAN D’ACTION PONT CHAMPLAINRENFORT AUX POUTRES
MESURE 3 - FIBRE DE CARBONE: 42 % en 2014 + 17 % en 2015
![Page 53: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/53.jpg)
53
3. PLAN D’ACTION PONT CHAMPLAINRENFORT AUX POUTRES
MESURE 4 - TREILLIS MODULAIRE: 16 % en 2014 + 14 % en 2015
INSTALLÉS PAR BARGES À PARTIR DE L’EAU POUR ÉVITER LES IMPACTS SUR LA CIRCULATION
![Page 54: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/54.jpg)
54
3. PLAN D’ACTION PONT CHAMPLAINRENFORT DES CHEVÊTRES
MESURE - POST-TENSION: complété (100 %)
![Page 55: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/55.jpg)
55
3. PLAN D’ACTION PONT CHAMPLAINRÉPARATION DES PILIERS
MESURE - BÉTONNAGE: 22 % en 2014 + 16 % en 2015
![Page 56: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/56.jpg)
56
3. PLAN D’ACTION PONT CHAMPLAINJOINTS DE DILATATION
MESURE - REMPLACEMENT: 16 % en 2014 + 16 % en 2015
![Page 57: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/57.jpg)
100 %100 % 100 %
2009 à 2013
Treillis modulaire
73 %
2014 et 2015
30 %
65 %
54 %
3. PLAN D’ACTION PONT CHAMPLAIN
Arbalète
Ajout post-tension 2.0
65 %
Renforcementchevêtres
40%
Ajout post-tension
100 %Fibre de carbone
Ajout post-tension 1.0
100 %
5714%
35%33%
![Page 58: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/58.jpg)
584 Catherine Tremblay, ing.Directrice principale, Projets
PROJET DE RÉFECTIONPONT MERCIER
![Page 59: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/59.jpg)
Section MTQPJCCI
Rive-Sud Montréal
59
![Page 60: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/60.jpg)
Section MTQ
Pile 14
60
Rampe 3
Rampe 2
Rampe 4
SECTION FÉDÉRALE /TERRITOIRE DE KAHNAWAKE
Pile 32
60
![Page 61: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/61.jpg)
SECTION VOIE MARITIME
SECTION DE CONVERGENCE
Pile 14
Pile 27
Pile 28Pile 32
SECTION DE L’ÎLE MALINE
TRAVAUX EN COURS ET À VENIRTROIS SECTIONS
61
![Page 62: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/62.jpg)
62
REMPLACEMENT DU TABLIER DE BÉTON
PHASE FÉDÉRALE
![Page 63: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/63.jpg)
63
4. PROJET DE RÉFECTION DU PONT MERCIER
PHASE FÉDÉRALE
DÉBUT DU PROJET DE RÉFECTION EN 2009PHASE A COMPLÉTÉE – RAMPE D’ACCÈS DU CÔTÉ DE LA RIVE-SUD
![Page 64: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/64.jpg)
64
4. PROJET DE RÉFECTION DU PONT MERCIER
TABLIER DU PONT À LA FIN DE SA VIE UTILESURVEILLANCE ÉTROITE ET QUOTIDIENNE DU TABLIER
PHASE FÉDÉRALE
![Page 65: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/65.jpg)
65
4. PROJET DE RÉFECTION DU PONT MERCIER
REMPLACEMENT DU TABLIER EN DIRECTION DE MONTRÉAL EN 2013TRAVAUX INTENSIFS PENDANT CINQ SEMAINES CONSÉCUTIVES
PHASE FÉDÉRALE
![Page 66: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/66.jpg)
SLABS CUT AND REMOVED
![Page 67: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/67.jpg)
INSTALLATION OF THE NEW CONCRETE DECK SLABS
![Page 68: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/68.jpg)
NEW VS OLD DECK
NEW
OLD
![Page 69: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/69.jpg)
HIGH LEVEL OF PRECISION DURING THE INSTALLATION
![Page 70: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/70.jpg)
INSTALLATION OF NEW BEARING DEVICES
![Page 71: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/71.jpg)
71
INSTALLATION DE NOUVEAUX JOINTS DE DILATATION
![Page 72: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/72.jpg)
72
POST-TENSION DES DALLES (INSTALLATION CÂBLES D’ACIER)
![Page 73: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/73.jpg)
73
INSPECTION ET PAVAGE FINAL DU PONT
![Page 74: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/74.jpg)
74
4. PROJET DE RÉFECTION DU PONT MERCIER
SECTION FÉDÉRALE 2/3 DES TRAVAUX RÉALISÉS ACTUELLEMENT
636 DALLES REMPLACÉES
346 DALLES À ÊTRE INSTALLÉES
PHASE FÉDÉRALE
![Page 75: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/75.jpg)
75
4. PROJET DE RÉFECTION DU PONT MERCIER
MESURES DE MITIGATION
• AJOUT DE WAGONS SUR LA LIGNE CANDIAC.
• AJOUT D’AUTOBUS RÉGIONAUX.
• INTÉGRATION D’UNE VOIE RÉSERVÉE AUX ABORDS DU PONT POUR OFFRIR UN ACCÈS PRIVILÉGIER AUX USAGERS DU TRANSPORT EN COMMUN.
PHASE FÉDÉRALE
![Page 76: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/76.jpg)
76
4. PROJET DE RÉFECTION DU PONT MERCIER
MESURES DE MITIGATION
• INTERDICTION DES CAMIONS AUX HEURES DE POINTE DU MATIN (5H À 9H) ET DU SOIR (15H À 19H).
• MESURE ENTREPRISE LE MATIN EN 2013 AYANT UN IMPACT TRÈS FAVORABLE SUR LA CIRCULATION.
• DÉTOUR VIA LA NOUVELLE A30 ET LE PONT CHAMPLAIN (AUCUNS TRAVAUX MAJEURS DURANT CETTE PÉRIODE).
• DIFFUSION EN DIRECT DES IMPACTS RÉELS DES TRAVAUX AUX CHRONIQUEURS À LA CIRCULATION LE MATIN
PHASE FÉDÉRALE
![Page 77: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/77.jpg)
77
SECTION DE L’ÎLE MALINE
SECTION VOIE MARITIME
SECTION DE CONVERGENCE
2013
![Page 78: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/78.jpg)
78
SECTION DE L’ÎLE MALINE
SECTION VOIE MARITIME
SECTION DE CONVERGENCE
2014
Les travaux de sept (7) semaines inclus:• Installation des dalles• Travaux pour le « cross-over » (porte pour
faciliter le transfert du trafic d’une section à l'autre)
• Travaux de finalisation de la glissière centrale• Travaux à la piste cyclable
![Page 79: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/79.jpg)
79
SECTION DE L’ÎLE MALINE
SECTION VOIE MARITIME
SECTION DE CONVERGENCE
2015-2016
![Page 80: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/80.jpg)
805 Catherine Tremblay, ing.Directrice principale, Projets
PONT DECONTOURNEMENTDE L’IDS
![Page 81: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/81.jpg)
81
4. PONT DE CONTOURNEMENT DE L’IDSNOUVEAU PONT DANS LA CORRIDOR CHAMPLAIN
![Page 82: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/82.jpg)
82
4. PONT DE CONTOURNEMENT DE L’IDSNOUVEAU PONT DANS LA CORRIDOR CHAMPLAIN
PONT-JETÉE2 PILIERS
VIADUCPASSAGE
PISTE ACTUELLE
PISTE PROJETÉ
![Page 83: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/83.jpg)
Élimination du feu de circulation
TRACÉ PLANIFIÉ VOIE RÉSERVÉE EN SITE PROPRE
83
![Page 84: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/84.jpg)
AM - MATIN
Élimination du feu de circulation
TRACÉ PLANIFIÉ VOIE RÉSERVÉE EN SITE PROPRE
84
![Page 85: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/85.jpg)
PM – APRÈS-MIDIÉlimination du feu de circulation
TRACÉ PLANIFIÉ VOIE RÉSERVÉE EN SITE PROPRE
85
![Page 86: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/86.jpg)
Viaduc N - 2014
Viaduc principal - 2014 et 2015
Viaduc V - 2013
RECONSTRUCTION DE VIADUCSPRINCIPAL ET N
86
![Page 87: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/87.jpg)
RÉFECTION DE L’A-BONAVENTUREREMPLACEMENT COMPLET PAR SECTION
87
![Page 88: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/88.jpg)
RÉFECTION DE L’A-BONAVENTUREREMPLACEMENT COMPLET PAR SECTION
88
![Page 89: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/89.jpg)
895 COMMUNICATIONJean-Vincent LacroixDirecteur, Communications
![Page 90: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/90.jpg)
90
PJCCI.CAPONTCHAMPLAIN.CAPONTJACQUESCARTIER.CAPONTMERCIER.CA
![Page 91: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/91.jpg)
91
PJCCI.CAPONTCHAMPLAIN.CAPONTJACQUESCARTIER.CAPONTMERCIER.CA
5. COMMUNICATIONCONCOURS ET CAPSULES VIDÉOS EXPLICATIVES
![Page 92: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/92.jpg)
92
PJCCI.CAPONTCHAMPLAIN.CAPONTJACQUESCARTIER.CAPONTMERCIER.CA
5. COMMUNICATIONCONCOURS ET CAPSULES VIDÉOS EXPLICATIVES
![Page 93: Planification des travaux 2014 PJCCI](https://reader037.vdocuments.mx/reader037/viewer/2022102420/556c1221d8b42a852a8b4c90/html5/thumbnails/93.jpg)
936 QUESTIONSGlen P. Carlin, ing.Premier dirigeant