![Page 1: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/1.jpg)
Pacific Team
2001
![Page 2: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/2.jpg)
TEAM INTRODUCTION
Pacific2001
Crystal Lang ARCHITECT
Robert Wright ENGINEER
Edgar Leenen CONSTRUCTION MANAGER
Will Clift APPRENTICE
Robert Alvarado OWNER
![Page 3: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/3.jpg)
GENERAL INFORMATION
Pacific2001
Site: Univ. of the Pacific, Forest Grove, Oregon
Year: 2015
Surroundings:
•Atop a cliff looking out on Pacific Ocean
•Small pond on inland side
![Page 4: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/4.jpg)
GENERAL INFORMATION
Pacific2001
•Geologic Information: The site lies on top of bedrock.
•Precipitation: 65”-90” annually
•Flooding occurs occasionally
•Wind: Strong winds up to 85 mph can exist
![Page 5: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/5.jpg)
Budget in 2015 (Budget in 2001)*(1-Inflation Rate)^n
Budget in 2001 $5,500,000n = nr of years 14Budget Structural System in 2001 450000Inflation Rate 2.95%
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
BUDGET
Inflation Rate
0.00%
1.00%
2.00%
3.00%
4.00%
5.00%
6.00%
7.00%
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
Inflation Rate
Average: 2,95%
Budget in 2015 $3,620,000Budget Structural System in 2001 $296,000
![Page 6: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/6.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
ROCK•Light
•Functional space
![Page 7: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/7.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
![Page 8: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/8.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
LOADING
Live Loads•Atrium, Terrace, Storage 100 psf•Corridors 80 psf•Lobby, Auditorium 60 psf•Classrooms, Offices 50 psf•Roof 20 psf
Seismic Requirements•Zone III Seismic Activity•Occupancy Category, I = 1.0
Wind Requirements•Design Wind Speed 85 mph
![Page 9: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/9.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
M.E.P CONSIDERATIONS
•Cooling capacity 70 tons•Boiler room & chilled water 450 ft2
•Space for cooling towers 80 ft2
•Cooling air volume 27000 CFM•Main supply or return ducts area 16 ft2
•Branch supply or return ducts 27 ft2
•Area of fan rooms 750 ft2
•Area of fresh air louvers 65 ft2
•Area of exhaust air louvers 50 ft2
•Central mechanical room area 1200 ft2
![Page 10: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/10.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
ROCKStructural Solution I
Lateral SystemGravity System
Lateral System•Steel Moment Resistant Frames (N – S)•Reinforced Concrete Shearwalls (E – W)
Gravity System•Composite Steel/Concrete Deck
![Page 11: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/11.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
ROCKFirst Floor E E + A
TYPICAL SIZES
Gravity Beams W18X55 Columns W12X45
Second Floor Slab t = 4.5”
Lateral Beams W18X40 Columns W18X35 Shearwall h = 10”
Third Floor
![Page 12: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/12.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
STEEL CONNECTIONS
Steel Beam-Shearwall Connection Moment Connection
Beam-Girder Connection Girder-Column Connection
![Page 13: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/13.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
ROCKStructural Solution II
Lateral SystemGravity System
Lateral System•Post-Tensioned Moment Resistant Frames (N – S)•Reinforced Concrete Shearwalls (E – W)
Gravity System•Two-Way Post-Tensioned Slab •Reinforced Concrete Columns and Beams
![Page 14: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/14.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
ROCKFirst Floor E E + A
TYPICAL SIZES
Gravity Beams 7”X10” Columns 12”X12”
Second Floor Slab h = 9”
Lateral Shearwall h = 10”
Third Floor
![Page 15: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/15.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONCRETE POST-TENSIONED DETAILS
Tendon Support
Post-Tensioned Slab
Moment Connection
![Page 16: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/16.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
EQUIPMENT
![Page 17: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/17.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
SITE PLAN ROCK & EARTH
Pacific ocean
Sunny Pond
Mobile craneOfficeMaterial storageMaterial laydown areaLunch/dress roomGround surplus/garbage storage
Site Boundary
Construction
Main Road
Crane range
![Page 18: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/18.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SCHEDULE ROCK 1
![Page 19: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/19.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SCHEDULE ROCK
ROCK 1 (steel)
ROCK 2 (reinforced concrete/post-tensioned concrete)
![Page 20: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/20.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
CONSTRUCTION SEQUENCE ROCK
Pacific2001
![Page 21: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/21.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE ROCK
![Page 22: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/22.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE ROCK
![Page 23: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/23.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE ROCK
![Page 24: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/24.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE ROCK
![Page 25: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/25.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE ROCK
![Page 26: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/26.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE ROCK
![Page 27: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/27.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
WAVE•Dynamic
•Explore
![Page 28: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/28.jpg)
1
2
3
![Page 29: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/29.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
![Page 30: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/30.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
WAVEStructural Solution I
Lateral SystemGravity System
Lateral System•ShearWalls•Concrete Moment Frames•Two Separate Buildings
Gravity System•Two-Way Slabs•Reinforced Concrete Columns and Beams
![Page 31: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/31.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
WAVEFirst Floor E E + A
TYPICAL SIZES
Gravity Beams 10”X12” Columns 12”X12”
Second Floor Slab h = 10”
Lateral Beams 18”X18”
Columns 16”X14” Shearwall h = 10”
Third Floor
![Page 32: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/32.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
REINFORCED CONCRETE CONNECTIONS
Column Reinforcement Beam Reinforcement
Beam-Column Shear Reinforcement
![Page 33: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/33.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
WAVEStructural Solution II
Lateral SystemGravity System
Lateral System•ShearWalls•Steel Moment Resistant Frames
Gravity System•Composite Steel/Concrete Deck•Steel Beams and Columns with Simple Shear Connections
![Page 34: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/34.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
WAVEFirst Floor E E + A
TYPICAL SIZES
Gravity Beams W16X36 Columns W12X40
Second Floor Slab h = 4.5”
Lateral Beams W16X40
Columns W16X31 Shearwall h = 8”
Third Floor
![Page 35: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/35.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
SHEARWALL DETAILS
Shearwall Reinforcement
Wall-Footing Elevation
Shearwall Corner Reinforcement
![Page 36: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/36.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
SITE PLAN WAVE
Pacific ocean
Sunny Pond
Main Road
Mobile craneOfficeMaterial storageMaterial laydown areaLunch/dress roomGround surplus/garbage storage
Site Boundary
Construction
Crane range
![Page 37: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/37.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SCHEDULE WAVE
WAVE 1 (reinforced concrete)
WAVE 2 (steel)
![Page 38: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/38.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE WAVE
![Page 39: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/39.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE WAVE
![Page 40: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/40.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE WAVE
![Page 41: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/41.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE WAVE
![Page 42: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/42.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE WAVE
![Page 43: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/43.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE WAVE
![Page 44: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/44.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE WAVE
![Page 45: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/45.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
EARTH
•Functional
•Flexible
![Page 46: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/46.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
![Page 47: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/47.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
EARTHStructural Solution I
Lateral SystemGravity System
Lateral System•ShearWalls (N – S)•ShearWalls (E – W)
Gravity System•Post-Tensioned Two-Way Slabs•Reinforced Concrete Beams and Columns
![Page 48: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/48.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
b
Pacific2001
EARTHFirst Floor E E + A
TYPICAL SIZES
Gravity Beams 7”X12” Columns 12”X12”
Second Floor Slab h = 9”
Lateral Shearwall N h = 10” Shearwall E h = 8”
Third Floor
![Page 49: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/49.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
EARTHStructural Solution II
Lateral SystemGravity System
Lateral System•ShearWalls (N – S)•ShearWalls (E – W)
Gravity System•Composite Steel/Concrete Deck•Steel Beams and Columns with Simple Shear Connections
![Page 50: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/50.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
b
Pacific2001
EARTHFirst Floor E E + A
TYPICAL SIZES
Gravity Beams W18X55 Columns W12X45
Second Floor Slab h = 9”
Lateral Shearwall N h = 10” Shearwall E h = 8”
Third Floor
![Page 51: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/51.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
FOUNDATION SYSTEM
•Spread for interior columns•Typical Size 4’ X 4’ X 2’
•Strip for perimeter columns and shearwalls•Typical Size 4’ X 2”
Typical Steel Column-Footing Typical Concrete Column-Footing
![Page 52: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/52.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SCHEDULE EARTH
EARTH 1 (reinforced concrete/post-tensioned concrete)
EARTH 2 (steel)
![Page 53: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/53.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE
![Page 54: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/54.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE
![Page 55: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/55.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE
![Page 56: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/56.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE
![Page 57: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/57.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE
![Page 58: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/58.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE
![Page 59: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/59.jpg)
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
CONSTRUCTION SEQUENCE
![Page 60: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/60.jpg)
3840000 3900000 3800000 3700000 3780000 3840000
300000 340000 220000 185000 180000 210000
0
500000
1000000
1500000
2000000
2500000
3000000
3500000
4000000
ROCK 1 ROCK 2 WAVE 1 WAVE 2 EARTH 1 EARTH 2
Structural System CostsTotal Costs
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
COST COMPARISON
BUDGET
![Page 61: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/61.jpg)
0
500000
1000000
1500000
2000000
2500000
3000000
3500000
ROCK 1 WAVE 2 EARTH 1
Clean up site
Plumbing systems
Electrical systems
Mechanical systems
Interior construction
Exterior closing
Conveying systems
Roof
Superstructure
Substructure
Foundation
Site Preparation
ARCHITECTENGINEERCONSTRUCTIONMANAGER
Pacific2001
COST COMPARISON
BUDGETStructural system $ 296.000
Total $ 3.620.000
COSTSStructural system $ 178.000
Total $ 3.700.000
WAVE 2Beams SteelColumns SteelMoment frames SteelSlab CompositeRoof Steel
![Page 62: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/62.jpg)
TEAM INTERACTIONS
1
AA+E+C
A+E E+C
SAMPLE DESIGN ITERATION
TimeC
![Page 63: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/63.jpg)
DECISION MATRIX
Rock Wave Earth A Functional space Responds to environment Spacious A Does not respond to
environment Walls under an angle Large monotonous facade
E Balanced structure Blends well with architecture Structure provides
flexibility E Highly skilled labor force
required No repetition in structural elements
Large spans require deep gravity members
C Short construction time Matches budget Prefab concrete possible C Expensive structural
system Non standard building Might exceed height limit
![Page 64: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/64.jpg)
PACIFIC 2001 CHOICE
WAVE!
![Page 65: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/65.jpg)
LESSONS LEARNED AND GOALS
Pacific2001
•Utilize available technology more effectively
•Improve communication
•Coordinate media we work in
•More interactions:
•Between team members
•With mentors
•With owner
![Page 66: Pacific Team 2001. TEAM INTRODUCTION Pacific 2001 Crystal LangARCHITECT Robert WrightENGINEER Edgar LeenenCONSTRUCTION MANAGER Will Clift APPRENTICE Robert](https://reader036.vdocuments.mx/reader036/viewer/2022081602/551829d0550346a7318b4d96/html5/thumbnails/66.jpg)
QUESTIONS
Pacific2001
?