Chris TowseyChris TowseyChief Operating Officer, Citigold Corporation LtdChief Operating Officer, Citigold Corporation Ltd
Narrow Vein Mining. CASE STUDY.Narrow Vein Mining. CASE STUDY.Citigold’s perspective on weighing up the Citigold’s perspective on weighing up the benefits against the challenges of narrow benefits against the challenges of narrow
vein miningvein mining
![Page 2: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/2.jpg)
1000 km625 miles
![Page 3: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/3.jpg)
4 kilometres
Railw
ay
Previous mining (yellow) developed200km of underground drives andproduced 6.6 million ounces of gold
![Page 4: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/4.jpg)
Processing Plant
Tailings dam
Stockholmmine
Washingtonmine
Declineportal
0 1km
XWarrior
mine
Warrior Mine
![Page 5: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/5.jpg)
![Page 6: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/6.jpg)
Diagram from Peters, 1987. EGRU Contrib 19
![Page 7: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/7.jpg)
No. 2 Cross Vein(Maude St. Leger reef)
![Page 8: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/8.jpg)
No. 2 Cross Vein (Maude St. Leger reef)
![Page 9: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/9.jpg)
Processing Plant
Tailings dam
Stockholmmine
Washingtonmine
Declineportal
0 1km
XWarrior
mine
Warrior Mine
![Page 10: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/10.jpg)
![Page 11: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/11.jpg)
Development PlanWarrior mine & gold resource – Long section
![Page 12: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/12.jpg)
Development PlanWarrior gold resource – drilling Cross Section
Cross sectionLooking West
![Page 13: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/13.jpg)
BENEFITS OF MECHANISEDBENEFITS OF MECHANISEDNARROW VEIN MININGNARROW VEIN MINING
Low mining cost per ounceLow mining cost per ounce–– low tonnage to break, haul and milllow tonnage to break, haul and mill–– high grade per tonne high grade per tonne –– 13 13 g/tg/t–– floor of drive preservedfloor of drive preserved
![Page 14: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/14.jpg)
Mining method:Longhole open stoping10m sub-levels
![Page 15: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/15.jpg)
![Page 16: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/16.jpg)
Atlas Copco Simba
![Page 17: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/17.jpg)
BENEFITS OF MECHANISEDBENEFITS OF MECHANISEDNARROW VEIN MININGNARROW VEIN MINING
Low mining cost per ounceLow mining cost per ounce–– low tonnage to break, haul and milllow tonnage to break, haul and mill–– high grade per tonne high grade per tonne –– 13 13 g/tg/t–– floor of drive preservedfloor of drive preservedSafer than handSafer than hand--heldheld
![Page 18: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/18.jpg)
MechanisedCut and fill
Shrink stoping
![Page 19: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/19.jpg)
Mining method:Longhole open stoping10m sub-levelsExpansion slot byvertical crater retreat
![Page 20: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/20.jpg)
![Page 21: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/21.jpg)
BENEFITS OF MECHANISEDBENEFITS OF MECHANISEDNARROW VEIN MININGNARROW VEIN MINING
Low mining cost per ounceLow mining cost per ounce–– low tonnage to break, haul and milllow tonnage to break, haul and mill–– high grade per tonne high grade per tonne –– 13 13 g/tg/t–– floor of drive preservedfloor of drive preservedSafer than handSafer than hand--heldheldAccurate grade controlAccurate grade control
![Page 22: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/22.jpg)
9.6 g/t Au1.1 g/t Au 7.0 g/t Au
Grade variationGrade variation
![Page 23: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/23.jpg)
No. 2 Cross Vein in stope pillarshowing rapid pinch-out
0.1m
0.2m
0.7m
![Page 24: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/24.jpg)
CHALLENGESCHALLENGES
Dilution Dilution –– planned and unplannedplanned and unplanned
![Page 25: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/25.jpg)
Planneddilution
Ore
![Page 26: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/26.jpg)
Overbreak
Unplanned dilution
Cross section
![Page 27: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/27.jpg)
Ore SortingDilution removed by ore sorting
Photometric ore sorter
The 30% waste and
dilution removed
by sorting
Feed screenedand washed
OREWASTE
![Page 28: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/28.jpg)
CHALLENGESCHALLENGES
Dilution Dilution –– planned and unplannedplanned and unplannedMultiple working faces requiredMultiple working faces required
![Page 29: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/29.jpg)
Conventional long-section view of a shoot within a planar structurePayability of structure 30%
Drill pierce pointsbelow cut-off
Drill pierce pointsAbove cut-off
Extraction levels
![Page 30: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/30.jpg)
Charters Towers structure with payable areas – no defined shootPayability of structure 30%70% chance of a barren hole
Drill pierce pointsbelow cut-off
Drill pierce pointsAbove cut-off
Extraction levels
Stope blocks
![Page 31: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/31.jpg)
CHALLENGESCHALLENGES
Dilution Dilution –– planned and unplannedplanned and unplannedMultiple working faces requiredMultiple working faces requiredFlatFlat--dipping stopes dipping stopes –– difficult muckingdifficult mucking
![Page 32: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/32.jpg)
Stope cleaning of 10m x 20m panelswill use water-jets rather than scrapers
![Page 33: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/33.jpg)
![Page 34: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/34.jpg)
Ore is jetted down the stope to a gully or sump
![Page 35: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/35.jpg)
Mining CostsMining Costs
222853352TOTAL COST 21844ADMINISTRATION 5202SURFACE HAULAGE
4517710PROCESSING 151582236Sub-total 7429623Development 77291613Production
MINING
Total$/oz
Total$/Tonne
Ore
Labour$/Tonne
Ore
Materials$/Tonne
Ore
![Page 36: Narrow Vein Mining Citicorp](https://reader035.vdocuments.mx/reader035/viewer/2022081417/5695d0391a28ab9b029185fb/html5/thumbnails/36.jpg)
Thank you