• Project Estimation Contd.– Critical Path Method, PERT
• Project Control Frameworks, practices, and Tool– WBS, Gantt Chart
– Project Plan
– EVA
– Scope Management
• Project success factors and risk
2
Study Objectives
![Page 3: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/3.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
• Critical Path
– sequence of activities whose sum is longer than any other path
– Slack
• Gantt Charts
– Scheduling activities
– Exhibit 3.6 (CISA Review Manual)
• PERT (Program Evaluation Review Technique)
– More sophisticated than CPM (Critical Path Method)
3
Scheduling
![Page 4: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/4.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
Critical Path – Exercise (5 mins)
4
Determine the Critical Path Time. What’s “slack”?
![Page 5: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/5.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
Critical Path – Exercise (5 mins)
5
A-D-E-C is part of the critical path from A to M. A-C has 2 days of “slack”
![Page 6: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/6.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
PERT– Exercise (10 mins)
6
Determine the PERT Time
![Page 7: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/7.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
PERT – Exercise (10 mins)
7
![Page 8: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/8.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
What is Work Break Down Structure?
- Exhibit 3.3 (CISA Review Manual an example)
- Identify the SDLC deliverables and “sequence” them in optimal way
- Microsoft Project is a common tool used for this
Example WBS Template:
http://www.projectmanagementdocs.com/templates/work-breakdown-structure-wbs.html
8
Scheduling - WBS
![Page 9: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/9.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
WBS Example – Sample Web Project
9
Web Ordering Project
1. Feasibility 2. Requirement 3. Design 4. Development5.
Implementation6. Post
Implementation
1.1 Feasibility
1.2 Business Case
1.3 RFP
2.1 Business Requirements
2.2 Systems Requirements
3.1 Architecture
3.2 HLD
3.3 DD
3.3.1 UI Design
3.3.2 Service Design3.3.3
Database Design
4.1 Coding/UT
4.2 Testing
4.3 Testing
4.3.1 QA
4.3.3 Systems Testing
4.3.2 Integration
Testing
5.1 Deployment Plan
5.2 Change Request
5.3 Operational Readiness
5.4 Data Conversion
5.5 Deployment
6.1 Lesson Learned
![Page 10: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/10.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
Gantt Chart – Sample Web Project
10
Where do we use Gantt Chart?
![Page 11: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/11.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
Project Controlling
Which of these a Project Manager do for tracking and oversight?
A. Actual time and resources spent against baseline (EVA –Earned Value Analysis)
B. Cost and OverrunC. Coding when neededD. Scope Management (Change
Control Board)E. Risk ManagementF. CommunicationG. AuditingH. Issues identification and
resolution
11
![Page 12: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/12.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
• Budget spending to date
• Hours to date
EVA helps understand the progress made in the project
It also helps fine-tune size/cost estimates vs. actuals for future projects
12
EVA – Earned Value Analysis
![Page 13: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/13.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
13
Understanding Project Plan
• What’s a Project Plan?– A valuable task detailed used by the PMs to schedule
the task, assign the resources, track the progress of the tasks
– Will discuss in detail in the next class (SDLC Phases)
Sample Project Plan (For Better Viewing)http://community.mis.temple.edu/mis5203spring2016/files/2016/01/Sample-Project-Plan-viewing.pdf
Sample Project Plan (For Printing)http://community.mis.temple.edu/mis5203spring2016/files/2016/01/Sample-Project-Plan-viewing.pdf
![Page 14: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/14.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
• Scope is typically locked after the Specification or Design phase (Baseline)
• Making changes to the original scope may have adverse impact as the time progresses during SDLC. It costs way more to make the changes during testing phase than during requirements or design phases
• Any changes to Baseline is typically managed through CCB (Change Control Board)
14
Scope Management
![Page 15: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/15.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
Risk Management Related to Software Development
Why Software Risks be analyzed and managed?
• To prevent loss of corruption of Information and IS Assets
• To prevent Disruption of customer service and other operations
• To prevent inefficient Management Decisions
• To help meet software development goals
• To meet Business Objectives
• All of the Above
15
![Page 16: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/16.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
• Benefit Risks– To avoid a new system may not meet business
goals and expectation
• Delivery Risk– Within the Project across SDLC phase
– With Partners and Suppliers
– Within Organization
– Technology Risk
– With External Environment
16
Software Development Risks
![Page 17: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/17.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
• Typical Process Steps
1. Inventory Risks – Possible ones
2. Assess Risks – Quantitative and Qualitative Analysis
3. Mitigate Risks – Mitigate, Avoid, Transfer, or Accept
4. Discover Risks – That materialize
5. Review and Evaluate – Effectiveness
17
Risk Management Process Steps
![Page 18: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/18.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
• Mitigate– Lessen the probability or impact
• Avoid– Where feasible, choose not to implement certain
activities
• Transfer– Deflect, Share with partners, Insurance
• Accept– Acknowledge and monitor
18
Risk Mitigation
![Page 19: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/19.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
• When can risk occur?– during entire SDLC
• When should the Risk Management Plan be developed?– during entire SDLC– Part of the Planning, Tracking and Oversight
• Section 2.8 of textbook (reference)
• A Risk Management Template Examplehttp://www.projectmanagementdocs.com/templates/risk-management-plan.html
19
Risk Management – More Details
![Page 20: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/20.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
• Adequacy of the level of oversight by the Steering Committee/ Project Committee
• Adequacy of typical Project Management Areas such the PMI Knowledge areas as below1. Project Integration Management2. Project Scope Management3. Project Time Management4. Project Cost Management5. Project Quality Management (including signoff process, issue
management)6. Project Human Resource Management7. Project Communications Management (including senior
management communication)8. Project Risk Management9. Project Procurement Management
20
Auditing Project Management
![Page 21: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/21.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
Which of the following risks could result from not baselining the software?
A. Scope creep
B. Sign-off delays
C. Software integrity violations
D. Inadequate controls
E. Financial Overhead
21
Questions
![Page 22: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/22.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
A project manager is in a process of identifying tasks responsible for project delays. What approach should he take?
A. Create Gantt analysis
B. Use Function point analysis
C. Come up with a Risk Analysis
D. Determine Critical Path
E. Complete PERT
22
Questions
![Page 23: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/23.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
1. Individual Case Study - 1 (Feasibility Study): Thu 1/28 before the class
2. Quiz 1 (Business Case Development, Project Management Practice, Develop Project Control, etc. Materials covered ion the first 4 Classes – 1/14, 1/21, 1/28, 2/4). Multiple Choice CISA Exam type questions: Thu 2/11
3. Group Project -1 (Business Case, RFP): Thu 2/18 before the class
Questions?
23
Upcoming Assignments/Tests
![Page 24: MIS 5203 Week 1 -1 Presentation...MIS 5203 Week 1 -1 Presentation Author: Kumar, Vasant Created Date: 1/29/2016 12:07:55 AM](https://reader030.vdocuments.mx/reader030/viewer/2022040122/5edd0e8cad6a402d666800c4/html5/thumbnails/24.jpg)
Systems & Infrastructure Lifecycle Management 1
Vasant Kumar
• Project Estimation
• Project Tracking and Oversight
– WBS
– Project Plan
– Risk Management Applied to Software Development
• Focus of the Next Class and Reading
• Questions