LESNER BRIDGE REPLACEMENT PROJECT
Department Leadership Meeting
February 27, 2013
David S. Jarman, P.E.
City of Virginia Beach
Department of Public Works
City Engineer’s Office
Transportation Division
![Page 2: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/2.jpg)
Lesner Bridge Replacement
• Project Location
2
![Page 3: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/3.jpg)
Lesner Bridge Replacement
3
• Existing Bridge
– 1530 ft long twin bridges
– EB built 1958, WB built 1967
– 28 spans: 25 concrete, 3 steel
– Corridor carries ~43,000 vpd
![Page 4: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/4.jpg)
Lesner Bridge Replacement
• Background
– Bridges were built in early days of prestressed concrete
– Salt environment has corroded steel strands
– Corrosion can not be stopped; only slowed with diligent maintenance
4
![Page 5: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/5.jpg)
Lesner Bridge Replacement
• Background
– Other repairs include pile jacketing, beam end repairs, and steel painting
– Current sufficiency ratings for the bridges are 34.9 (WB) and 39.0 (EB)
5
![Page 6: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/6.jpg)
6
• Design – Design team of Figg
Engineering/Clark-Nexsen was chosen in 2005
– Provide a signature bridge that reflects the surrounding community
– Extensive public involvement including Listening Tours, Design Charette & Citizen Information Meetings
– Community input on bridge theme, shapes, aesthetics, lighting, and other amenities
Lesner Bridge Replacement
![Page 7: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/7.jpg)
• Design Challenges – Maintain 4 lanes of traffic during construction
– Tie-in at existing intersections
– DVP Transmission Main
– Limiting r/w impacts based on chosen alignment
7
Lesner Bridge Replacement
![Page 8: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/8.jpg)
Lesner Bridge Replacement
• Detour Route—19.1 miles
8
![Page 9: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/9.jpg)
• Design Decisions – Use precast segmental
• Efficiency in construction, long term durability
• VDOT/ VA FHWA not enthusiastic due to previous experience – A lot of changes and lessons learned over the past 20 years
– Northern alignment • Best option for being “shovel ready”
• Less dependent on relocating utilities first
– Leave DVP transmission line in place • Cost prohibitive to move (~$14 million to underground)
• More risk in construction, but still feasible to build
9
Lesner Bridge Replacement
![Page 10: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/10.jpg)
Lesner Bridge Replacement
• Design
10
150’ (typ) 225’ main span
![Page 11: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/11.jpg)
Lesner Bridge Replacement
11
• Construction Staging
![Page 12: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/12.jpg)
12
Lesner Bridge Replacement
• Construction Staging
![Page 13: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/13.jpg)
13
Lesner Bridge Replacement
• Construction Staging
![Page 14: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/14.jpg)
14
Lesner Bridge Replacement
• Construction Staging
![Page 15: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/15.jpg)
15
Casting Yard (Jordan Bridge)
![Page 16: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/16.jpg)
16
Span-by-Span Construction
![Page 17: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/17.jpg)
17
Construction (Jordan Bridge)
![Page 18: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/18.jpg)
18
Construction (Jordan Bridge)
![Page 19: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/19.jpg)
19
![Page 20: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/20.jpg)
20
![Page 21: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/21.jpg)
21
![Page 22: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/22.jpg)
Lesner Bridge Replacement
• Project Status – Currently working on final design
– Project is fully funded (Governor’s Transportation Plan)
– Environmental process is complete
– Public participation is complete
– TS&L and VE are approved
– JPA submitted in mid-July 2012
– Coast Guard permit anticipated in May 2013
22
![Page 23: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/23.jpg)
Lesner Bridge Replacement
• Funding – Total project cost: $95 million
• Design: $10.2 million (City funded)
• RW/Utilities: $14.3 million
• Construction: $70.5 million
• Schedule – Advertise for construction by July 2013
– NTP January 2014
– Completion January 2017
23
![Page 24: LESNER BRIDGE REPLACEMENT PROJECT (CIP 2-168)...Lesner Bridge Replacement •Project Status –Currently working on final design –Project is fully funded (Governor’s Transportation](https://reader035.vdocuments.mx/reader035/viewer/2022081611/5f028c987e708231d404d0b8/html5/thumbnails/24.jpg)
Questions?
24