LEED 2009 or CommErCiaL intEriors
i
The built environment has a profound impact on our natural environment, economy, health, and productivity.
Breakthroughs in building science, technology, and operations are now available to designers, builders, operators,
and owners who want to build green and maximize both economic and environmental performance.
Through the LEED green building certification program, the U.S. Green Building Council (USGBC) is transforming
the built environment. The green building movement offers an unprecedented opportunity to respond to the most
important challenges of our time, including global climate change, dependence on non sustainable and expensive
sources of energy, and threats to human health. The work of innovative building professionals is a fundamental
driving force in the green building moment. Such leadership is a critical component to achieving USGBCs mission of
a sustainable built environment for all within a generation.
USGBC MeMBerShip
USGBCs greatest strength is the diversity of our membership. USGBC is a balanced, consensus based nonprofit
with more than 18,000 member companies and organizations representing the entire building industry. Since itsinception in 1993, USGBC has played a vital role in providing a leadership forum and a unique, integrating force for
the building industry. USGBCs programs have three distinguishing characteristics:
Cmm-bsd
The heart of this effective coalition is our committee structure, in which volunteer members design strategies
that are implemented by staff and expert consultants. Our committees provide a forum for members to resolve
differences, build alliances, and forge cooperative solutions for influencing change in all sectors of the building
industry.
Mmb-dv
Membership is open and balanced and provides a comprehensive platform for carrying out important programs and
activities. We target the issues identified by our members as the highest priority. We conduct an annual review of
achievements that allows us to set policy, revise strategies, and devise work plans based on members needs.
Cssus-cusdWe work together to promote green buildings, and in doing so, we help foster greater economic vitality and
environmental health at lower costs. We work to bridge ideological gaps between industry segments and develop
balanced policies that benefit the entire industry.
Contact the U.S. Green Building Council
2101 L Street, NW
Suite 500
Washington, DC 20037
(800) 795-1747 Office
(202) 828-5110 Fax
www.usgbc.org
http://www.usgbc.org/http://www.usgbc.org/ -
7/29/2019 LEED 2009 CI guide
4/84
LEED 2009 or CommErCiaL intEriors
ii
CopyriGht
Copyright 2009 by the U.S. Green Building Council, Inc. All rights reserved.
The U.S. Green Building Council, Inc. (USGBC) devoted significant time and resources to create this LEED Rating
System. USGBC authorizes individual use of the LEED Rating System. In exchange for this authorization, the user
agrees:
1. to retain all copyright and other proprietary notices contained in the LEED Rating System,
2. not to sell or modify the LEED Rating System, and
3. not to reproduce, display, or distribute the LEED Rating System in any way for any public or commercial
purpose.
Unauthorized use of the LEED Rating System violates copyright, trademark, and other laws and is prohibited.
DiSClaiMer
None of the parties involved in the funding or creation of the LEED Rating System, including the USGBC, its
members, its members, volunteers, or contractors, assume any liability or responsibility to the user or any third
parties for the accuracy, completeness, or use of or reliance on any information contained in the LEED RatingSystem, or for any injuries, losses, or damages (including, without limitation, equitable relief) arising from such use
or reliance. Although the information contained in the LEED Rating System is believed to be reliable and accurate,
all materials set forth within are provided without warranties of any kind, either express or implied, including but
not limited to warranties of the accuracy or completeness of information or the suitability of the information for any
particular purpose.
As a condition of use, the user covenants not to sue and agrees to waive and release the U.S. Green Building Council,
its members, volunteers, and contractors from any and all claims, demands, and causes of action for any injuries,
losses, or damages (including, without limitation, equitable relief) that the user may now or hereafter have a right to
assert against such parties as a result of the use of, or reliance on, the LEED Rating System.
U.S. Green Building Council
2101 L Street, NWSuite 500
Washington, DC 20037
traDeMarkS
USGBC, U.S. Green Building Council and LEED are registered trademarks of the U.S. Green Building Council.
-
7/29/2019 LEED 2009 CI guide
5/84
LEED 2009 or CommErCiaL intEriors
iii
aCknowleDGMentS
The LEED 2009 Rating System has been made possible only through the efforts of many dedicated volunteers,
staff members, and others in the USGBC community. The Rating System improvement work was managed and
implemented by USGBC staff and included review and input by many Technical Advisory Group (TAG) members
with oversight by the LEED Steering Committee. We extend our deepest gratitude to all of our LEED committee
members who participated in the development of this guide, for their tireless volunteer efforts and constant supportof USGBCs mission:
leeD Sg CmmScot Horst, Chair, LSC Horst, Inc
Joel Ann Todd, Vice-Chair, LSC Joel Ann Todd
Muscoe Martin M2 Architecture
Stuart Carron JohnsonDiversey, Inc.
Holley Henderson H2 Ecodesign, LLC
Christine Magar Greenform
Kristin Shewfelt Architectural Energy Corporation
Jessica Millman Agora DC
Bryna Dunn Moseley Architects
Neal Billetdeaux JJR
Greg Kats Managing Good Energies
Mark Webster Simpson Gumpertz & Heger
Bob Thompson EPA Indoor Environment Management Branch
Malcolm Lewis Constructive Technologies Group, Inc.
John Boecker 7Group
Sara OMara Choate Construction Company
Alex Zimmerman Rep Canada Green Building Council
Ian Theaker Rep Canada Green Building Council
Susb Ss taGBryna Dunn, Chair Moseley Architects
Stewart Comstock, Vice-Chair Maryland Department of the Environment
Michele Adams Cahill Associates
Gina Baker Burt Hill
Ted Bardacke Global Green USA
Stephen Benz Sasaki
Mark Brumbaugh Brumbaugh & Associates
Laura Case Emory University Campus Services
Zach Christeson the HOK Planning Group
Jay Enck Commissioning & Green Building Services
Ron Hand E/FECT. Sustainable Design Solutions
Richard Heinisch Acuity Lighting GroupMichael Lane Lighting Design Lab
Marita Roos HNTB
Zolna Russell Hord Coplan Macht, Inc.
Alfred Vick Ecos Environmental Design, Inc.
-
7/29/2019 LEED 2009 CI guide
6/84
LEED 2009 or CommErCiaL intEriors
iv
w efcc taGNeal Billetdeaux, Chair JJR
John Koeller, Vice-Chair Alliance for Water Efficiency
David Carlson Columbia University
Bill Hoffman H.W. Hoffman and Associates, LLC
Geoff Nara Civil & Environmental Consultants
Stephanie Tanner U.S. Environmental Protection AgencyDaniel Yeh University of South Florida
David Bracciano Tampa Bay Water
Robert Rubin NCSU-BAE and McKim & Creed
Winston Huff SSR Engineers
Robert Benazzi Jaros Baum & Bolles
Gunnar Baldwin TOTO USA, INC
Heather Kinkade Forgotten Rain, LLC
Shabbir Rawalpindiwala Kohler Company
Bill Wall Clivus New England, Inc.
eg & ams taG
Greg Kats, Chair GoodEnergies
Marcus Sheffer, Vice-Chair 7group
Drury Crawley US Department of Energy
Jay Enck Commissioning & Green Building Solutions, Inc.
Ellen Franconi IPMVP and AEC
Mark Frankel New Buildings Institute
Nathan Gauthier Harvard Green Campus Initiative
Rusty Hodapp Dallas/Fort Worth, Energy & Transportation Management
John Hogan City of Seattle Department of Planning & Development
Bion Howard Building Environmental Science and Technology
Dan Katzenberger Engineering, Energy, and the Environment
Bob Maddox Sterling Planet
Brenda Morawa BVM Engineering, Inc.
Erik Ring LPA, Inc.
Michael Rosenberg Oregon Department of Energy
Mick Schwedler Trane
Gord Shymko IPMVP and G.F. Shymko & Associates
Gail Stranske CTG Energetics
Michael Zimmer Thompson Hine LLP
Ms & rsucs taGMark Webster, Chair Simpson Gumpertz & Heger
Steven Baer, Vice Chair Five Winds International
Paul Bertram NAIMAChris Dixon NBBJ
Ann Edminster Design AVEnues
Lee Gros Lee Gros Architect and Artisan, Inc
Theresa Hogerheide-Reusch Reusch Design Services
Nadav Malin BuildingGreen, LLC.
Nancy Malone Siegel & Strain Architects
-
7/29/2019 LEED 2009 CI guide
7/84
LEED 2009 or CommErCiaL intEriors
v
Kirsten Ritchie Gensler
Wayne Trusty Athena Sustainable Materials Institute
Denise Van Valkenburg MASCO Retail Cabinet Group
Gabe Wing Herman Miller, Inc.
id evm Qu taG
Bob Thompson, Chair EPA Indoor Environment Management BranchSteve Taylor, Vice-Chair Taylor Engineering
Nancy Clanton Clanton and Associates
Alexis Kurtz Ove Arup &Partners
George Loisos Loisos+ Ubelohde
Prasad Vaidya The Weidt Group
Daniel Bruck BRC Acoustics & Tech.
David Lubman David Lubman & Associates
Charles Salter Salter Associates
Ozgem Ornektekin DMJM Harris
Jude Anders Shoreline Concepts, LLC
Brian Cloward Mithun Architects+Designers+Planners
Larry Dykhuis Herman Miller, IncFrancis (Bud) Offerman Indoor Environmental Engineering
Christopher Schaffner The Green Engineer
Dennis Stanke Trane Company
The LEED 2009 for Commercial Interiors Rating System builds on the work of those who helped create previous
versions:
leeD Cmmc is Vs 2.0 C CmmHolley Henderson, Chair H2 Ecodesign, LLC
Denise Van Valkenburg, Vice Chair Steelcase Inc.
Penny Bonda Environmental CommunicationsKeith Winn Catalyst Partners
Gina Baker Burt Hill Kosar Rittelmann Associates
Kirsten Childs Croxton Collaborative Architects, P.C.
Don Horn U.S. General Services Administration
Scot Horst Horst, Inc
Liana Kallivoka Austin Energy Green Building Program
Jill Kowalski EwingCole
Fran Mazarella U.S. General Services Administration
Roger McFarland HOK
Ken Wilson Envision Design
Elaine Aye Green Building Services
Carlie Bullock-Jones Thompson, Ventulett, Stainback & Associates
Rico Cedro Krueck & Sexton
Hellen Kessler HJKessler Associates, Inc
Mehran Khazra Guttmann & Blaevoet Consulting Engineer
Laurie McMahon Cassidy & Pinkard Colliers
Ralph Muehliesen Illinois Institute of Technology
Georgina Sikorski INVISTA
-
7/29/2019 LEED 2009 CI guide
8/84
LEED 2009 or CommErCiaL intEriors
vi
leeD 2009 or CoMMerCial interiorS projeCt CheCkliSt
Susb Ss 21 pssb ps
Ced 1 se selec 1-5
Ced 2 Develpe Dey d Cuy Cecvy 6
Ced 3.1 aleve tpPublc tp acce 6
Ced 3.2 aleve tpBcycle sge d Chgg r 2
Ced 3.3 aleve tpPkg avlbly 2
w efcc 11 pssb ps
Peeque 1 We Ue reduc requed
Ced 1 We Ue reduc 6-11
eg d ams 37 pssb ps
Peeque 1 udel Cg Buldg Eegy sye requed
Peeque 2 mu Eegy Pece requed
Peeque 3 udel rege mgee requed
Ced 1.1 opze Eegy PeceLghg Pwe 15
Ced 1.2 opze Eegy PeceLghg Cl 13
Ced 1.3 opze Eegy PeceHVaC 510
Ced 1.4 opze Eegy PeceEqupe d applce 14
Ced 2 Ehced Cg 5
Ced 3 meuee d Vec 2-5
Ced 4 Gee Pwe 5
Ms d rsucs 14 pssb ps
Peeque 1 sge d Cllec recyclble requed
Ced 1.1 te spceLg-te Ce 1
Ced 1.2 Buldg reuem ie nucul Cpe 1-2
Ced 2 Cuc We mgee 1-2
Ced 3.1 mel reue 1-2
Ced 3.2 mel reueuue d uhg 1
Ced 4 recycled Ce 1-2
Ced 5 regl mel 1-2
Ced 6 rpdly reewble mel 1
Ced 7 Ceed Wd 1
id evm Qu 17 pssb ps
Peeque 1 mu id a Quly Pece requed
Peeque 2 Evel tbcc ske (Ets) Cl requed
Ced 1 oud a Delvey mg 1
Ced 2 iceed Vel 1
Ced 3.1 Cuc id a Quly mgee PlDug Cuc 1
Ced 3.2 Cuc id a Quly mgee PlBee occupcy 1
-
7/29/2019 LEED 2009 CI guide
9/84
LEED 2009 or CommErCiaL intEriors
vi i
Ced 4.1 Lw-Eg meladheve d sel 1
Ced 4.2 Lw-Eg melP d Cg 1
Ced 4.3 Lw-Eg mellg sye 1
Ced 4.4 Lw-Eg melCpe Wd d agbe Pduc 1
Ced 4.5 Lw-Eg melsye uue d seg 1
Ced 5 id Checl d Pllu suce Cl 1
Ced 6.1 Cllbly syeLghg 1
Ced 6.2 Cllbly syethel C 1
Ced 7.1 thel CDeg 1
Ced 7.2 thel CVec 1
Ced 8.1 Dylgh d VewDylgh 1-2
Ced 8.2 Dylgh d VewVew seed spce 1
iv Dsg 6 pssb ps
Ced 1 iv Deg 1-5
Ced 2 LEED acceded Pel 1
rg p 4 pssb psCed 1 regl Py 1-4
________________________________________________________________________
leeD 2009 Cmmc is
100 be p; 6 pble iv Deg d 4 regl Py p
Ceed 4049 p
slve 5059 p
Gld 6079 p
Plu 80 p d bve
-
7/29/2019 LEED 2009 CI guide
10/84
LEED 2009 or CommErCiaL intEriors
viii
-
7/29/2019 LEED 2009 CI guide
11/84
LEED 2009 or CommErCiaL intEriors
ix
pc
iduc i. LEED Gee Buldg rg sye x
ii. ovevew d Pce x
iii. mu Pg requee xv
iV. Exeply Pece sege xv
Susb Ss (SS) 1
Ced 1 se selec 1
Ced 2 Develpe Dey d Cuy Cecvy 4
Ced 3.1 aleve tpPublc tp acce 6
Ced 3.2 aleve tpBcycle sge d Chgg r 7
Ced 3.3 aleve tpPkg avlbly 8
w efcc (we) 9
Peeque 1 We Ue reduc 9
Ced 1 We Ue reduc 11
eg d ams (ea) 13
Peeque 1 udel Cg Buldg Eegy sye 13
Peeque 2 mu Eegy Pece 15
Peeque 3 udel rege mgee 16
Ced 1.1 opze Eegy PeceLghg Pwe 17
Ced 1.2 opze Eegy PeceLghg Cl 18
Ced 1.3 opze Eegy PeceHVaC 19
Ced 1.4 opze Eegy PeceEqupe d applce 21
Ced 2 Ehced Cg 22
Ced 3 meuee d Vec 24
Ced 4 Gee Pwe 26
Ms d rsucs (Mr) 27
Peeque 1 sge d Cllec recyclble 27
Ced 1.1 te spceLg-te Ce 28
Ced 1.2 Buldg reuem ie nucul Cpe 29
Ced 2 Cuc We mgee 30
Ced 3.1 mel reue 31
Ced 3.2 mel reueuue d uhg 32
Ced 4 recycled Ce 33
Ced 5 regl mel 34
Ced 6 rpdly reewble mel 35
Ced 7 Ceed Wd 36
-
7/29/2019 LEED 2009 CI guide
12/84
LEED 2009 or CommErCiaL intEriors
x
id evm Qu (ieQ) 37
Peeque 1 mu id a Quly Pece 37
Peeque 2 Evel tbcc ske (Ets) Cl 38
Ced 1 oud a Delvey mg 40
Ced 2 iceed Vel 41
Ced 3.1 Cuc id a Quly mgee PlDug Cuc 43
Ced 3.2 Cuc id a Quly mgee PlBee occupcy 44
Ced 4.1 Lw-Eg meladheve d sel 46
Ced 4.2 Lw-Eg melP d Cg 48
Ced 4.3 Lw-Eg mellg sye 49
Ced 4.4 Lw-Eg melCpe Wd d agbe Pduc 51
Ced 4.5 Lw-Eg melsye uue d seg 52
Ced 5 id Checl d Pllu suce Cl 53
Ced 6.1 Cllbly syeLghg 54
Ced 6.2 Cllbly syethel C 55
Ced 7.1 thel CDeg 56
Ced 7.2 thel CVec 57Ced 8.1 Dylgh d VewDylgh 58
Ced 8.2 Dylgh d VewVew seed spce 62
iv Dsg (iD) 63
Ced 1 iv Deg 63
Ced 2 LEED acceded Pel 64
rg p (rp) 65
Ced 1 regl Py 65
-
7/29/2019 LEED 2009 CI guide
13/84
LEED 2009 or CommErCiaL intEriors
xi
i. leeD Green BUilDinG ratinG SySteM
Bcgud leeD
Following the formation of the U.S. Green Building Council (USGBC) in 1993, the organizations members quickly
realized that the sustainable building industry needed a system to define and measure green buildings. USGBC
began to research existing green building metrics and rating systems. Less than a year after formation, the members
acted on the initial findings by establishing a committee to focus solely on this topic. The composition of the
committee was diverse; it included architects, real estate agents, a building owner, a lawyer, an environmentalist, and
industry representatives. This cross section of people and professions added a richness and depth both to the process
and to the ultimate product.
The first LEED Pilot Project Program, also referred to as LEED Version 1.0, was launched at the USGBC MembershipSummit in August 1998. After extensive modifications, LEED Green Building Rating System Version 2.0 was released
in March 2000, with LEED Version 2.1 following in 2002 and LEED Version 2.2 following in 2005.
As LEED has evolved and matured, the program has undertaken new initiatives. In addition to a rating system
specifically devoted to building operational and maintenance issues (LEED for Existing Buildings: Operations
& Maintenance), LEED addresses the different project development and delivery processes that exist in the U.S.
building design and construction market, through rating systems for specific building typologies, sectors, and
project scopes: LEED for Core & Shell, LEED for New Construction, LEED for Schools, LEED for Neighborhood
Development, LEED for Retail, LEED for Healthcare, LEED for Homes, and LEED for Commercial Interiors.
Project teams interact with the Green Building Certification Institute (GBCI) for project registration and
certification. GBCI was established in 2008 as a separately incorporated entity with the support of the U.S. Green
Building Council. GBCI administers credentialing and certification programs related to green building practice.These programs support the application of proven strategies for increasing and measuring the performance of
buildings and communities as defined by industry systems such as LEED.
The green building field is growing and changing daily. New technologies and products are being introduced into
the marketplace, and innovative designs and practices are proving their effectiveness. The LEED rating systems and
reference guides will evolve as well. Project teams must comply with the version of the rating system that is current
at the time of their registration.
USGBC will highlight new developments on its website on a continual basis atwww.usgbc.org.
us leeD
The LEED Green Building Rating Systems are voluntary, consensus-based, and market-driven. Based on existing and
proven technology, they evaluate environmental performance from a whole building perspective over a buildingslife cycle, providing a definitive standard for what constitutes a green building in design, construction, and operation.
The LEED rating systems are designed for rating new and existing commercial, institutional, and residential
buildings. They are based on accepted energy and environmental principles and strike a balance between known,
established practices and emerging concepts. Each rating system is organized into 5 environmental categories:
Sustainable Sites, Water Efficiency, Energy and Atmosphere, Materials and Resources, and Indoor Environmental
http://www.usgbc.org/http://www.usgbc.org/ -
7/29/2019 LEED 2009 CI guide
14/84
LEED 2009 or CommErCiaL intEriors
xi i
Quality. An additional category, Innovation in Design, addresses sustainable building expertise as well as design
measures not covered under the 5 environmental categories. Regional bonus points are another feature of LEED
and acknowledge the importance of local conditions in determining best environmental design and construction
practices.
t leeD Cd wggsIn LEED 2009, the allocation of points between credits is based on the potential environmental impacts and human
benefits of each credit with respect to a set of impact categories. The impacts are defined as the environmental
or human effect of the design, construction, operation, and maintenance of the building, such as greenhouse gas
emissions, fossil fuel use, toxins and carcinogens, air and water pollutants, indoor environmental conditions. A
combination of approaches, including energy modeling, life-cycle assessment, and transportation analysis, is used to
quantify each type of impact. The resulting allocation of points among credits is called credit weighting.
LEED 2009 uses the U.S. Environmental Protection Agencys TRACI1 environmental impact categories as the basis
for weighting each credit. TRACI was developed to assist with impact evaluation for life-cycle assessment, industrial
ecology, process design, and pollution prevention.
LEED 2009 also takes into consideration the weightings developed by the National Institute of Standards and
Technology (NIST); these compare impact categories with one another and assign a relative weight to each.
Together, the 2 approaches provide a solid foundation for determining the point value of each credit in LEED 2009.
The LEED 2009 credit weightings process is based on the following parameters, which maintain consistency and
usability across rating systems:
All LEED credits are worth a minimum of 1 point.
All LEED credits are positive, whole numbers; there are no fractions or negative values.
All LEED credits receive a single, static weight in each rating system; there are no individualized scorecards
based on project location.
All LEED rating systems have 100 base points; Innovation in Design (or Operations) and
Regional Priority credits provide opportunities for up to 10 bonus points.
Given the above criteria, the LEED 2009 credit weightings process involves 3 steps:
1. A reference building is used to estimate the environmental impacts in 13 categories associated with a typical
building pursuing LEED certification.
2. The relative importance of building impacts in each category are set to reflect values based on the NIST
weightings.2
3. Data that quantify building impacts on environmental and human health are used to assign points to individual
credits.
Each credit is allocated points based on the relative importance of the building-related impacts that it addresses.
The result is a weighted average that combines building impacts and the relative value of the impact categories.
Credits that most directly address the most important impacts are given the greatest weight, subject to the system
design parameters described above. Credit weights also reflect a decision by LEED to recognize the marketimplications of point allocation. The result is a significant change in allocation of points compared with previous
LEED rating systems. Overall, the changes increase the relative emphasis on the reduction of energy consumption
and greenhouse gas emissions associated with building systems, transportation, the embodied energy of water, the
embodied energy of materials, and where applicable, solid waste.
-
7/29/2019 LEED 2009 CI guide
15/84
LEED 2009 or CommErCiaL intEriors
xiii
The details of the weightings process vary slightly among individual rating systems. For example, LEED for Existing
Buildings: O&M includes credits related to solid waste management but LEED for New Construction does not. This
results in a difference in the portion of the environmental footprint addressed by each rating system and the relative
allocation of points. The weightings process for each rating system is fully documented in a weightings workbook.
The credit weightings process will be reevaluated over time to incorporate changes in values ascribed to different
building impacts and building types, based on both market reality and evolving scientific knowledge related to
buildings. A complete explanation of the LEED credit weightings system is available on the USGBC website, at
www.usgbc.org.
rg p CdsTo provide incentive to address geographically specific environmental issues, USGBC regional councils and chapters
have identified 6 credits per rating system that are of particular importance to specific areas. Each regional priority
credit is worth an additional 1 point, and a total of 4 regional priority points may be earned. Upon project registration,
LEED Online automatically determines a projects regional priority credits based on its zip code. If the project
achieves more than 4 regional priority credits, the team can choose the credits for which these points will apply. The
USGBC website also contains a searchable database of regional priority credits.
ii. oVerView anD proCeSSThe LEED 2009 Green Building Rating System for Commercial Interiors is a set of performance standards
for certifying the design and construction of tenant spaces for office, restaurant, healthcare, hotel/resort and
education buildings of all sizes, both public and private. The intent is to promote healthful, durable, affordable, and
environmentally sound practices in tenant space design and construction.
Prerequisites and credits in the LEED 2009 for Commercial Interiors Rating System addresses 7 topics:
Sustainable Sites (SS)
Water Efficiency (WE)
Energy and Atmosphere (EA)
Materials and Resources (MR)
Indoor Environmental Quality (IEQ)
Innovation in Design (ID)
Regional Priority (RP)
LEED 2009 for Commercial Interiors certifications are awarded according to the following scale:
Ceed 4049 p
slve 5059 p
Gld 6079 p
Plu 80 p d bve
GBCI will recognize buildings that achieve 1 of these rating levels with a formal letter of certification.
w Us leeD 2009 Cmmc is
LEED 2009 for Commercial Interiors addresses the specifics of tenant spaces primarily in office, retail, and
institutional buildings. Tenants who lease their space or do not occupy the entire building are eligible.
http://www.usgbc.org/http://www.usgbc.org/ -
7/29/2019 LEED 2009 CI guide
16/84
LEED 2009 or CommErCiaL intEriors
xiv
LEED for Commercial Interiors was designed to work hand-in-hand with the LEED for Core & Shell certification
system. LEED for Core & Shell is used by developers to certify the core and shell of a project; it prepares the building
for environmentally conscious tenants.
Many projects clearly fit the defined scope of only 1 LEED rating system; others may be eligible for 2 or more. The
project is a viable candidate for LEED certification if it can meet all prerequisites and achieve the minimum points
required in a given rating system. If more than 1 rating system applies, the project team can decide which to pursue.
For assistance in choosing the most appropriate LEED rating system, please e-mail [email protected].
rgsProject teams interested in earning LEED certification for their buildings must first register the project with GBCI.
Projects can be registered on the GBCI website (www.gbci.org). The website also has information on registration
costs for USGBC national members as well as nonmembers. Registration is an important step that establishes
contact with GBCI and provides access to software tools, errata, critical communications, and other essential
information.
CfcTo earn LEED certification, the applicant project must satisfy all the prerequisites and qualify for a minimum
number of points to attain the established project ratings as listed below. Having satisfied the basic prerequisites ofthe program, applicant projects are then rated according to their degree of compliance within the rating system.
LEED 2009 for Commercial Interiors provides the option of splitting a certification application into two phases,
design and construction, in lieu of a combined design and construction review. Documentation for design phase
credits, identified in LEED Online, can be submitted for review at the end of the design phase; the submittals for
these credits can be fully evaluated based on documentation available during this phase of the project. For example, if
a project site meets the requirements of LEED for Commercial Interiors SS Credit 3.1, Alternative Transportation
Public Transportation Access, the likelihood of credit achievement can be assessed prior to the completion of
construction. The LEED credit itself, however, is not awarded at the design review stage.
For more information on the LEED certification process including LEED Online, Credit Interpretation Requests and
Rulings, Appeals, and Fees please see the LEED Reference Guide for Green Building Design and Construction, 2009
Edition and visitwww.usgbc.org orwww.gbci.org.
iii. MiniMUM proGraM reQUireMentS
The LEED 2009 Minimum Program Requirements (MPRs) define the minimum characteristics that a project must
possess in order to be eligible for certification under LEED 2009. These requirements define the categories of
buildings that the LEED rating systems were designed to evaluate, and taken together serve three goals: to give clear
guidance to customers, to protect the integrity of the LEED program, and to reduce challenges that occur during the
LEED certification process. To view the MPRs and the MPR Supplemental Guidance, visit the LEED Resources and
Tools section ofwww.usgbc.org/projecttools.
iV. exeMplary perorManCe StrateGieS
Exemplary performance strategies result in performance that greatly exceeds the performance level or expands the
scope required by an existing LEED 2009 for Commercial Interiors credit. To earn exemplary performance credits,
teams must meet the performance level defined by the next step in the threshold progression. For credits with more
than 1 compliance path, an Innovation in Design point can be earned by satisfying more than 1 compliance path if
their benefits are additive.
http://localhost/var/www/apps/conversion/tmp/scratch_5/[email protected]://www.gbci.org/http://www.usgbc.org/http://www.gbci.org/http://www.usgbc.org/projecttoolshttp://www.usgbc.org/projecttoolshttp://www.gbci.org/http://www.usgbc.org/http://www.gbci.org/http://localhost/var/www/apps/conversion/tmp/scratch_5/[email protected] -
7/29/2019 LEED 2009 CI guide
17/84
LEED 2009 or CommErCiaL intEriors
xv
The credits for which exemplary performance points are available through expanded performance or scope are noted
in the LEED Reference Guide for Green Interior Design and Construction, 2009 Edition and in LEED Online.
Ede1 Tools for the Reduction and Assessment of Chemical and Other Environmental Impacts (TRACI). U.S.
Environmental Protection Agency, Office of Research and Development. http://www.epa.gov/nrmrl/std/sab/
traci/.2 Relative impact category weights based on an exercise undertaken by NIST (National Institute of Standards and
Technology) for the BEES program. http://www.bfrl.nist.gov/oae/software/bees/.
http://www.epa.gov/nrmrl/std/sab/traci/http://www.epa.gov/nrmrl/std/sab/traci/http://www.bfrl.nist.gov/oae/software/bees/http://www.bfrl.nist.gov/oae/software/bees/http://www.epa.gov/nrmrl/std/sab/traci/http://www.epa.gov/nrmrl/std/sab/traci/ -
7/29/2019 LEED 2009 CI guide
18/84
LEED 2009 or CommErCiaL intEriors
xvi
-
7/29/2019 LEED 2009 CI guide
19/84
LEED 2009 or CommErCiaL intEriors
1
SS Cd 1: S Sc
15 ps
i
To encourage tenants to select buildings that employ best practices systems and green strategies.
rqums
oPtion 1
Select a LEED certified building (5 points).
or
oPtion 2
Locate the tenant space in a building that has in place 1 or more of the following characteristics at time of
submittal (1 5 points). Each of the following options may also be met by satisfying the requirements of the
corresponding LEED 2009 for New Construction credit.
PatH 1. Bweld redevelpe (1 p)
A building developed on a site documented as contaminated (by an ASTM E1903-97 Phase II Environmental
Site Assessment or a local voluntary cleanup program) OR
A building on a site classified as a brownfield by a local, state or federal government agency.
Effective remediation of site contamination must have been completed.
PatH 2. swe DegQuy Cl (1 p)
A building that prior to its development had less than or equal to 50% imperviousness and has implemented
a stormwater management plan that is equal to or is less than the predevelopment 1 1/2 year 24-hour rate and
quantity discharge.
or
A building that prior to its development had more than 50% imperviousness and has implemented a
stormwater management plan that reduced predevelopment 1 1/2 year 24-hour rate and quantity discharge
by 25% of the annual on-site stormwater load. This mitigation can be achieved through a variety of measures
such as perviousness of site, stormwater retention ponds, and harvesting of rainwater for reuse.
Stormwater values are based on actual local rainfall unless the actual exceeds the 10-year annual average local
rainfall, in which case the 10-year annual average should be used.
PatH 3. swe DegQuly Cl (1 p)
A building that has in place site stormwater treatmen t systems d esigned to remove at least 80% of the
average annual site areas total suspended solids (TSS) and 40% of the average annual site areas total
phosphorus (TP).
-
7/29/2019 LEED 2009 CI guide
20/84
LEED 2009 or CommErCiaL intEriors
2
These values are based on the average annual loadings from all storms less than or equal to the 2-year 24-hour
storm. The building must implement and maintain best management practices (BMPs) outlined in Chapter
4, Part 2 Urban Runoff, of the EPA Guidance Specifying Management Measures for Sources of Nonpoint
Pollution in Coastal Waters, January 1993 (EPA 840B92002) or the local governments BMP document,
whichever is more stringent.
PatH 4. He ild Eecn (1 p)
A building that provides shade (or will provide shade within 5 years of landscape installation); and/ or uses
light-colored or high-albedo materials with a solar reflectance index (SRI)1 of at least 29; and/ or has open-
grid pavement areas that individually or in total equals at least 30% of the sites nonroof impervious surfaces,
such as parking areas, walkways, plazas, and fire lanes.
or
A building that has placed a minimum of 50% of parking spaces underground or covered by structured
parking.
or
A building that has an open-grid pavement system (less than 50% impervious) for 50% of the parking lot area.
PatH 5. He ild Eecr (1 p)
A building whose roofing has a solar reflectance index (SRI) of the following minimum values for at least 75%
of the roof surface;
Roof Type Slope SRI
Lw-lped 2:12 78
seep-lped > 2:12 29
orA building that has installed a vegetated roof for at least 50% of the roof area.
or
A building that has both high SRI roofs and vegetated roofs that satisfy the following area requirement:
tl r
ae [ ( ae sri r x 1.33 ) + ( ae Vegeed r x 2 )]
PatH 6. Lgh Pllu reduc (1 p)
A building whose nonemergency interior luminaires with a direct line of sight to any openings in the envelope
(translucent or transparent) must have their input power reduced (by automatic device) by at least 50%
between 11 p.m. and 5 a.m. After-hours override may be provided by a manual or occupant-sensing deviceprovided the override lasts no more than 30 minutes.
1 The solar reflectance index (SRI) is a measure of the constructed surfaces ability to reflect solar heat, as shown by a small temperature rise. It isdefined so that a standard black surface (reflectance 0.05, emittance 0.90) is 0 and a standard white surface (reflectance 0.80, emittance 0.90)is 100. To calculate the SRI for a given material, obtain the reflectance value and emittance value for the material. SRI is calculated according toASTM E 1980. Reflectance is measured according to ASTM E 903, ASTM E 1918 or ASTM C 1549. Emittance is measured according to ASTM E408 or ASTM C 1371.
-
7/29/2019 LEED 2009 CI guide
21/84
LEED 2009 or CommErCiaL intEriors
3
or
A building whose openings in the envelope (translucent or transparent) with a direct line of sight to any
nonemergency luminaires must have shielding (with transmittance of less than 10%) that is controlled or
closed by automatic device between 11 p.m. and 5 a.m.
PatH 7. We Ece Ldcpgreduce by 50% (2 p)
A building that employs high-efficiency irrigation technology OR uses harvested rainwater or recycled site
water to reduce potable water consumption for irrigation by at least 50% over conventional means.
PatH 8. We Ece Ldcpgn Pble We Ue ig (2 p dd
Ph 7)
A building that uses only harvested rainwater or recycled site water to eliminate all potable water use for site
irrigation (except for initial watering to establish plants), OR does not have permanent landscaping irrigation
systems.
PatH 9. ivve Wewe techlge (2 p)
A building that reduces the use of municipally provided potable water for building sewage conveyance by at
least50%, OR treats 100% of wastewater on-site to tertiary standards.
PatH 10. We Ue reduc30% reduc (1 p)
A building that meets the 30% reduction in water use requirement for the entire building and has an ongoing
plan to require future occupants to comply.
PatH 11. o-e reewble Eegy (1-2 p)
A building that supplies at least 2.5% (1 point) or 5% (2 points) of the buildings total energy use (expressed as
a fraction of annual energy cost) from on-site renewable energy systems.
PatH 12. ohe Quble Evel Pece (1 p)
A building that has in place at the time of selection other quantifiable environmental benefits.
p tcgs & Sgs
During the building selection process, give preference to those properties which exhibit green building strategies and
technologies.
-
7/29/2019 LEED 2009 CI guide
22/84
LEED 2009 or CommErCiaL intEriors
4
SS Cd 2: Dvm Ds d Cmmu Ccv
6 s
iTo channel development to urban areas with existing infrastructure, protect greenfields and preserve habitat and
natural resources.
rqums
oPtion 1. Develpe Dey
Select space in a building that is located in an established, walkable community with a minimum density of
60,000 square feet per acre net. The density calculation is based on a typical two-story downtown development
and must include the area of the project being built.
or
oPtion 2. Cuy Cecvy
Select space in a building on a site that meets the following criteria:
n Is located within 1/2-mile of a residential area or neighborhood with an average density of 10 units per acre
net
n Is within 1/2-mile of at least 10 basic services
n Has pedestrian access between the building and the services.
For mixed-use projects, no more than 1 service within the project boundary may be counted as 1 of the 10
basic services, provided it is open to the public. No more than 2 of the 10 services required may be anticipated
(i.e. at least 8 must be existing and operational). In addition, the anticipated services must be documented
appropriately to demonstrate that they will be operational in the locations indicated within 1 year of occupation
of the applicant project.
Examples of basic services include the following:
Bank
Place of Worship
Convenience Grocery
Day Care Center
Cleaners
Fire Station
Beauty Salon
Hardware
Laundry
Library
Medical or Dental Office
Senior Care Facility
Park
Pharmacy
Post Office
Restaurant
School
Supermarket
Theater
Community Center
Fitness Center
Museum
-
7/29/2019 LEED 2009 CI guide
23/84
LEED 2009 or CommErCiaL intEriors
5
Proximity is determined by drawing a 1/2-mile radius around a main building entrance on a site map and counting
the services within that radius.
Greenfield developments and projects that do not use existing infrastructure are not eligible.
p tcgs & SgsDuring the site selection process, give preference to urban sites with pedestrian access to a variety of services.
-
7/29/2019 LEED 2009 CI guide
24/84
LEED 2009 or CommErCiaL intEriors
6
SS Cd 3.1: av tspubc ts accss
6 s
iTo reduce pollution and land development impacts from automobile use.
rqums
oPtion 1. rl s Pxy
Locate the project in a building within 1/2-mile walking distance (measured from a main building entrance) of an
existing (or planned and funded) commuter rail, light rail or subway station.
or
oPtion 2. Bu sp Pxy
Locate the project within 1/4-mile walking distance (measured from a main building entrance) of 1 or more stops
for 2 or more public campus or private bus lines usable by tenant occupants.
p tcgs & Sgs
Perform a transportation survey of potential tenant occupants to identify transportation needs. Locate the building
near mass transit.
-
7/29/2019 LEED 2009 CI guide
25/84
LEED 2009 or CommErCiaL intEriors
7
SS Cd 3.2: av tsBcc Sg d Cgg rms
2 s
iTo reduce pollution and land development impacts from automobile use.
rqumsProvide secure bicycle racks and/or storage (within 200 yards of a main building entrance) for 5% or more of tenant
occupants (measured at peak periods).
Provide shower and changing facilities in the building, or within 200 yards of a building entrance, for 0.5% of full-
time equivalent (FTE) occupants.
p tcgs & SgsSelect a building with transportation amenities such as bicycle racks and shower/changing facilities or add them as
part of the tenant fit-out.
-
7/29/2019 LEED 2009 CI guide
26/84
LEED 2009 or CommErCiaL intEriors
8
SS Cd 3.3: av tspg avb
2 s
iTo reduce pollution and land development impacts from automobile use.
rqums
CasE 1. Pjec wh ae Le th 75% he tl Buldg ae
oPtion 1
Parking spaces provided to tenant must meet but not exceed minimum number required by local zoning
regulations .
Preferred parking1 must be provided for carpools or vanpools capable of serving 5% or more of tenantoccupants.
or
oPtion 2
No parking is provided or subsidized for tenant occupants.
CasE 2. Pjec wh ae 75% me he tl Buldg ae
oPtion 1
Parking capacity must meet but not exceed minimum local zoning requirements.
Preferred parking must be provided for carpools or vanpools, capable of serving 5% of the building occupants.
or
oPtion 2
No new parking is added for rehabilitation projects.
Preferred parking must be provided for carpools or vanpools, capable of serving 5% of the building occupants.
p tcgs & SgsSelect a building with minimized car parking capacity and include limited parking inclusions in the lease.
1 Preferred parking refers to the parking spots that are closest to the main entrance of the project (exclusive of spaces designated forhandicapped persons) or parking passes provided at a discounted price.
-
7/29/2019 LEED 2009 CI guide
27/84
LEED 2009 or CommErCiaL intEriors
9
we pqus 1: w Us rduc
rqud
i
To increase water efficiency within the tenant space to reduce the burden on municipal water supply and wastewater
systems.
rqums
Employ strategies that in aggregate use 20% less water than the water use baseline calculated for the tenant space
(not including irrigation).
Calculate the baseline according to the commercial and/or residential baselines outlined below.1 Calculations are
based on estimated occupant usage and must include only the following fixtures and fixture fittings located within
the tenant space: water closets, urinals, lavatory faucets, showers, kitchen sink faucets and prerinse spray valves.2
Commercial Fixtures, Fittings, and Appliances Current Baseline
Cecl le1.6 gll pe luh (gp)*
Excep blw-u xue: 3.5 (gp)
Cecl ul 1.0 (gp)
Cecl lvy (e) uce
2.2 gll pe ue (gp) 60 pud pe que ch (p), pve pplc ly (hel
el gue , hpl pe )
0.5 (gp) 60 (p)** ll he excep pve pplc
0.25 gll pe cycle eeg uce
Cecl pee py vlve
( d evce pplc)
lw e 1.6 (gp)
( peue peced; pece equee)
Residential Fixtures, Fittings, and Appliances Current Baseline
redel le 1.6 (gp)***
redel lvy (bh) uce2.2 (gp) 60 p
redel kche uce
redel hwehed 2.5 (gp) 80 (p) pe hwe ll****
* EPac 1992 dd le pple bh cecl d edel del.
** i dd EPac equee, he aec scey mechcl Egee dd publc lvy uce 0.5 gp 60 p (asmE a112.18.1-2005).
th xu h bee cped he l U Plubg Cde d he iel Plubg Cde.
*** EPac 1992 dd le pple bh cecl d edel del.
**** redel hwe cpe (ll) dwellg u: the l llwble w e ll wg hwehed y gve e, cludg ye, well,
bdypy, bdyp d je, u be led he llwble hwehed w e pecfed bve (2.5 gp) pe hwe cpe, whee he e
he hwe cpe le h 2,500 que che. ech cee 2,500 que che e heee p hee, ddl hwehedwh l llwble w e ll wg devce equl le h he llwble w e pecfed bve u be llwed. Excep: shwe h e
ecculed pble we gg wh he hwe cpe whle peg e llwed exceed he xu lg he l pble we wde exceed he w e pecfed bve.
1 Tables adapted from information developed and summarized by the U.S. Environmental Protection Agency (EPA) Office of Water based onrequirements of the Energy Policy Act (EPAct) of 1992 and subsequent rulings b y the Department of Energy, requirements of the EPAct of 2005,and the plumbing code requirements as stated in the 2006 editions of the Uniform Plumbing Code or International Plumbing Code pertainingto fixture performance.
2 Projects where fixtures or fixture fittings are not within the tenant space are exempt from WE Prerequisite 1.
-
7/29/2019 LEED 2009 CI guide
28/84
LEED 2009 or CommErCiaL intEriors
10
The following fixtures, fittings and appliances are outside the scope of the water use reduction calculation:
Commercial Steam Cookers
Commercial Dishwashers
Automatic Commercial Ice Makers
Commercial (family-sized) Clothes Washers
Residential Clothes Washers
Standard and Compact Residential Dishwashers
p tcgs & SgsWaterSense-certified fixtures and fixture fittings should be used where available. Use high-efficiency fixtures
(e.g., water closets and urinals) and dry fixtures, such as toilets attached to composting systems, to reduce potable
water demand. Consider using alternative on-site sources of water (e.g., rainwater, stormwater, and air conditioner
condensate) and graywater for nonpotable applications such as custodial uses and toilet and urinal flushing. Thequality of any alternative source of water used must be taken into consideration based on its application or use.
-
7/29/2019 LEED 2009 CI guide
29/84
LEED 2009 or CommErCiaL intEriors
11
we Cd 1: w Us rduc
611 ps
iTo further increase water efficiency within the tenant space to reduce the burden on municipal water supply and
wastewater systems.
rqumsEmploy strategies that in aggregate use less water than the water use baseline calculated for the tenant space (not
including irrigation). The minimum water savings percentage for each point threshold is as follows:
Percentage Reduction Points
30% 6
35% 8
40% 11
Calculate the baseline according to the commercial and/or residential baselines outlined below.1 Calculations are
based on estimated occupant usage and must include only the following fixtures and fixture fittings necessary to
meet the needs of the occupants including fixtures and fixture fittings that may be outside the tenant space: water
closets, urinals, lavatory faucets, showers, kitchen sink faucets and pre-rinse spray valves.
Commercial Fixtures, Fittings, and Appliances Current Baseline
Cecl le1.6 gll pe luh (gp)*
Excep blw-u xue: 3.5 (gp)
Cecl ul 1.0 (gp)
Cecl lvy (e) uce
2.2 gll pe ue (gp) 60 pud pe que ch (p), pve pplc ly (hel
el gue , hpl pe )0.5 (gp) 60 (p)** ll he excep pve pplc
0.25 gll pe cycle eeg uce
Cecl pee py vlve
( d evce pplc)
lw e 1.6 (gp)
( peue peced; pece equee)
Residential Fixtures, Fittings, and Appliances Current Baseline
redel le 1.6 (gp)***
redel lvy (bh) uce2.2 (gp) 60 p
redel kche uce
redel hwehed 2.5 (gp) 80 (p) pe hwe ll****
* EPac 1992 dd le pple bh cecl d edel del.
** i dd EPac equee, he aec scey mechcl Egee dd publc lvy uce 0.5 gp 60 p (asmE a112.18.1-2005).
th xu h bee cped he l U Plubg Cde d he iel Plubg Cde.
*** EPac 1992 dd le pple bh cecl d edel del.
**** redel hwe cpe (ll) dwellg u: the l llwble w e ll wg hwehed y gve e, cludg ye, well,
bdypy, bdyp d je, u be led he llwble hwehed w e pecfed bve (2.5 gp) pe hwe cpe, whee he e
he hwe cpe le h 2,500 que che. ech cee 2,500 que che e heee p hee, ddl hwehedwh l llwble w e ll wg devce equl le h he llwble w e pecfed bve u be llwed. Excep: shwe h e
ecculed pble we gg wh he hwe cpe whle peg e llwed exceed he xu lg he l pble we wde exceed he w e pecfed bve.
1 Tables adapted from information developed and summarized by the U.S. Environmental Protection Agency (EPA) Office of Water based onrequirements of the Energy Policy Act (EPAct) of 1992 and subsequent rulings b y the Department of Energy, requirements of the EPAct of 2005,and the plumbing code requirements as stated in the 2006 editions of the Uniform Plumbing Code or International Plumbing Code pertainingto fixture performance.
-
7/29/2019 LEED 2009 CI guide
30/84
LEED 2009 or CommErCiaL intEriors
12
The following fixtures, fittings and appliances are outside the scope of the water use reduction calculation:
Commercial Steam Cookers
Commercial Dishwashers
Automatic Commercial Ice Makers
Commercial (family-sized) Clothes Washers
Residential Clothes Washers
Standard and Compact Residential Dishwashers
p tcgs & SgsUse WaterSense-certified fixtures and fixture fittings where available. Use high-efficiency fixtures (e.g., water closets
and urinals) and dry fixtures, such as toilets attached to composting systems, to reduce the potable water demand.
Consider using alternative on-site sources of water (e.g., rainwater, stormwater, and air conditioner condensate,
graywater) for nonpotable applications (e.g., toilet and urinal flushing, custodial uses). The quality of any alternativesource of water being used must be taken into consideration based on its application or use.
-
7/29/2019 LEED 2009 CI guide
31/84
LEED 2009 or CommErCiaL intEriors
13
ea pqus 1: udm Cmmssg Budg eg Ssms
rqud
i
To verify that the projects energy-related systems are installed and calibrated to performing according to the
owners project requirements, basis of design and construction documents.
Benefits of commissioning include reduced energy use, lower operating costs, fewer contractor callbacks, better
building documentation, improved occupant productivity, and verification that the systems perform in accordance
with the owners project requirements.
rqumsThe following commissioning process activities must be completed by the project team:
n Designate an individual as the commissioning authority (CxA) to lead, review and oversee the completion of
the commissioning process activities.
The CxA must have documented commissioning authority experience in at least 2 building projects.
The individual serving as the CxA must be independent of the projects design and construction
management, though the CxA may be an employee of any firms providing those services. The CxA may be a
qualified employee or consultant of the owner.
The CxA must report results, findings and recommendations directly to the owner.
For projects smaller than 50,000 gross square feet, the CxA may be a qualified person on the design or
construction teams who has the required experience.
n The owner must document the owners project requirements. The design team must develop the basis of
design. The CxA must review these documents for clarity and completeness. The owner and design team must
be responsible for updates to their respective documents.
n Develop and incorporate commissioning requirements into the construction documents.
n Develop and implement a commissioning plan.
n Verify the installation and performance of the systems to be commissioned.
n Complete a summary commissioning report.
Ced sye
Commissioning process activities must be completed for the following energy-related systems at a minimum:
n
Heating, ventilating, air conditioning and refrigeration (HVAC&R) systems (mechanical and passive) andassociated controls.
n Lighting and daylighting controls.
n Domestic hot water systems.
n Renewable energy systems (e.g. PV, wind, solar).
-
7/29/2019 LEED 2009 CI guide
32/84
LEED 2009 or CommErCiaL intEriors
14
p tcgs & SgsEngage a CxA as early as possible in the design process. Determine the owners project requirements, develop
and maintain a commissioning plan for use during design and construction and incorporate commissioning
requirements in bid documents. Assemble the commissioning team, and prior to occupancy verify the performance
of energy consuming systems. Complete the commissioning reports with recommendations prior to accepting the
commissioned systems.
Owners are encouraged to seek out qualified individuals to lead the commissioning process. Qualified individuals are
identified as those who possess a high level of experience in the following areas:
n Energy systems design, installation and operation.
n Commissioning planning and process management.
n Hands-on field experience with energy systems performance, interaction, start-up, balancing, testing,
troubleshooting, operation and maintenance procedures.
n
Energy systems automation control knowledge.Owners are encouraged to consider including water-using systems, building envelope systems, and other systems in
the scope of the commissioning plan as appropriate. The building envelope is an important component of a facility
which impacts energy consumption, occupant comfort and indoor air quality. While this prerequisite does not
require building envelope commissioning, an owner can achieve significant financial savings and reduce risk of poor
indoor air quality by including it in the commissioning process.
-
7/29/2019 LEED 2009 CI guide
33/84
LEED 2009 or CommErCiaL intEriors
15
ea pqus 2: Mmum eg pmc
rqud
iTo establish the minimum level of energy efficiency for the tenant space systems to reduce environmental and
economic impacts associated with excessive energy use.
rqumsDesign portions of the building as covered by the tenants scope of work to comply with ANSI/ASHRAE/IESNA
Standard 90.1-2007 (with errata but without addenda1), and complete the following:
n Comply with the mandatory provisions (Sections 5.4, 6.4, 7.4, 8.4, 9.4 and 10.4) of ANSI/ASHRAE/IESNA
Standard 90.1-2007 (with errata but without addenda1).
n Achieve the prescriptive requirements (Sections 5.5, 5.6, 6.5, 7.5 and 9.5 or 9.6) or performance requirements
(Section 11) of ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1).
n Reduce connected lighting power density 10% below that allowed by ANSI/ASHRAE/IESNA Standard 90.1-
2007 (with errata but without addenda1) using either the Space-by-Space Method or by applying the whole
building lighting power allowance to the entire tenant space.
n Install ENERGY STAR qualified equipment for 50% (by rated-power) of ENERGY STAR eligible equipment2
installed as part of the tenants scope of work. This requirement includes appliances, office equipment,
electronics, and commercial food service equipment. Excluded are heating, ventilating and air conditioning
(HVAC), lighting, and building envelope products.
Projects in California may use Title 24-2005, Part 6 in place of ANSI/ASHRAE/IESNA Standard 90.1-2007.
p tcgs & Sgs
Design the systems impacted in the tenants scope of work to maximize energy performance. Use a computer
simulation model to assess the energy performance and identify the most cost-effective energy measures. Quantify
energy performance compared with a baseline building.
If local code has demonstrated quantitative and textual equivalence following, at a minimum, the U.S. Department
of Energy (DOE) standard process for commercial energy code determination, then the local code may be used
to satisfy this prerequisite in lieu of ANSI/ASHRAE/IESNA Standard 90.1-2007. Details on the DOE process for
commercial energy code determination can be found at http://www.energycodes.gov/implement/determinations_
com.stm.
1 Project teams wishing to use ASHRAE approved addenda for the purposes of this credit may do so at their discretion. Addenda must be appliedconsistently across all LEED credits.
http://www.energycodes.gov/implement/determinations_com.stmhttp://www.energycodes.gov/implement/determinations_com.stmhttp://www.energycodes.gov/implement/determinations_com.stmhttp://www.energycodes.gov/implement/determinations_com.stm -
7/29/2019 LEED 2009 CI guide
34/84
LEED 2009 or CommErCiaL intEriors
16
ea pqus 3: udm rg Mgm
rqud
iTo reduce stratospheric ozone depletion.
rqumsZero use of chlorofluorocarbon (CFC)-based refrigerants in tenant heating, ventilating, air conditioning and
refrigeration (HVAC&R) systems used within the LEED project scope of work.
p tcgs & Sgs
For new installations, specify new HVAC equipment that uses no CFC-based refrigerants. When reusing existing
HVAC systems, conduct an inventory to identify equipment that uses CFC-based refrigerants and replace or retrofit
these systems with non-CFC refrigerants.
Project teams are encouraged to either locate in buildings that have no CFC-based refrigerants or to influence the
building owner to use such systems to reduce ozone depletion.
-
7/29/2019 LEED 2009 CI guide
35/84
LEED 2009 or CommErCiaL intEriors
17
ea Cd 1.1: omz eg pmclgg p
15 s
iTo achieve increasing levels of energy conservation beyond the referenced standard to reduce environmental and
economic impacts associated with excessive energy use.
rqumsReduce connected lighting power density below that allowed by ANSI/ASHRAE/IESNA Standard 90.1-2007 (with
errata but without addenda1) using either the space-by-space method or by applying the whole building lighting
power allowance to the entire tenant space.
The points earned for reducing lighting power density below the standard are as follows:
Lighting Power Density Reduction
below the StandardPoints
15% 1
20% 2
25% 3
30% 4
35% 5
Project teams in California may use Title 24-2005, Part 6 in place of ANSI/ASHRAE/IESNA Standard 90.1-2007.
p tcgs & SgsDesign the connected lighting power to maximize energy performance. If the project warrants, consider a computer
simulation model to assess the performance and identify the most cost-effective energy efficiency measures.
1 Project teams wishing to use ASHRAE approved addenda for the purposes of this prerequisite may do so at their discretion. Addenda must beapplied consistently across all LEED credits..
-
7/29/2019 LEED 2009 CI guide
36/84
LEED 2009 or CommErCiaL intEriors
18
ea Cd 1.2: omz eg pmclgg Cs
13 s
iTo achieve increasing levels of energy conservation beyond the prerequisite standard to reduce environmental and
economic impacts associated with excessive energy use.
rqumsDesign the project to include 1 or more of the following independent strategies:
n Daylight controls for daylit areas: (1 point)
Install daylight responsive controls in all regularly occupied daylit spaces within 15 feet of windows and
under skylights. Daylight controls must switch or dim electric lights in response to the presence or absence of
daylight illumination in the space.1
n Daylight controls for 50% of the lighting load: (1 point)
Install daylight responsive controls for 50% or more of the connected lighting load and demonstrate that 50%
of the connected lighting load is daylight responsive. Daylight controls must switch or dim electric lights in
response to the presence or absence of daylight illumination in the space.2
n Occupancy sensors: (1 point)
Install occupancy sensors for 75% of the connected lighting load.
p tcgs & SgsDesign the lighting controls to maximize energy performance.
1 American Society of Heating, Refrigerating, and Air-Conditioning Engineers. ANSI/ASHRAE/IESNA Standard 90.1 2007 90.1 Users Manual.(Atlanta, 2008). P. 9-3
2 Ibid
-
7/29/2019 LEED 2009 CI guide
37/84
LEED 2009 or CommErCiaL intEriors
19
ea Cd 1.3: omz eg pmchVaC
510 s
iTo achieve increasing levels of energy conservation beyond the prerequisite standard to reduce environmental and
economic impacts associated with excessive energy use.
rqum
oPtion 1
Implement 1 or both of the following strategies:
n Equipment Efficiency(5 points)
Install heating, ventilation and air conditioning (HVAC) systems that comply with the efficiency requirementsoutlined in the New Building Institutes Advanced Buildings Core Performance Guide Sections 1.4:
Mechanical System Design, 2.9: Mechanical Equipment Efficiency and 3.10: Variable Speed Control.
n Appropriate Zoning and Controls: (5 points)
Zone tenant fit out of spaces to meet the following requirements:
Every solar exposure must have a separate control zone.
Interior spaces must be separately zoned.
Private offices and special occupancies (conference rooms, kitchens, etc.) must have active controls
capable of sensing space use and modulating the HVAC system in response to space demand.
or
oPtion 2
Reduce design energy cost compared with the energy cost budget for regulated energy components described in
the requirements of ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1)
anD
PatH 1 (5 p)
Demonstrate that HVAC system component performance criteria used for tenant space are 15% better than
a system in minimum compliance with ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without
addenda1).
or
PatH 2 (10 p)
Demonstrate that HVAC system component performance criteria used for tenant space are 30% better than
a system that is in minimum compliance with ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but
without addenda1).
1 Project teams wishing to use ASHRAE approved addenda for the purposes of this credit may do so at their discretion. Addenda must be appliedconsistently across all LEED credits.
-
7/29/2019 LEED 2009 CI guide
38/84
LEED 2009 or CommErCiaL intEriors
20
p tcgs & SgsDesign the HVAC system components to maximize energy performance. Review compliance options for EA Credit
1.3 and determine the most appropriate approach. Option 1 provides a more prescriptive approach to recognizing
energy-efficient HVAC design, while Option 2 is performance based.
-
7/29/2019 LEED 2009 CI guide
39/84
LEED 2009 or CommErCiaL intEriors
21
ea Cd 1.4: omz eg pmcequm d acs
14 s
iTo achieve increasing levels of energy conservation beyond the prerequisite standard to reduce environmental and
economic impacts associated with excessive energy use.
rqumsFor all ENERGY STAR eligible equipment and appliances installed as part of the tenants scope of work, achieve one
of the following percentages (by rated power):
Percent Installed ENERGY STAR Qualified
Equipment of ENERGY STAR Eligible EquipmentPoints
70% 1
77% 2
84% 3
90% 4
This requirement applies to appliances, office equipment, electronics, and commercial food service equipment.
Excluded are HVAC, lighting, and building envelope products.
p tcgs & SgsSelect energy-efficient equipment and appliances, as qualified by the EPAs ENERGY STAR Program (http://www.
energystar.gov).
http://www.energystar.gov/http://www.energystar.gov/http://www.energystar.gov/http://www.energystar.gov/ -
7/29/2019 LEED 2009 CI guide
40/84
LEED 2009 or CommErCiaL intEriors
22
ea Cd 2: ecd Cmmssg
5 s
iTo verify and ensure that the tenant space is designed, constructed and calibrated to operate as intended.
rqumsImplement, or have a contract in place to implement, the following additional commissioning process activities in
addition to the requirements of EA Prerequisite 1: Fundamental Commissioning of the Building Energy Systems:
n Prior to the start of the construction documents phase, designate an independent commissioning authority
(CxA) to lead, review and oversee the completion of all commissioning process activities.
The CxA must have documented commissioning authority experience in at least 2 building projects.
The individual serving as the CxA:
Must be independent of the work of design and construction;
Must not be an employee of the design firm, though he or she may be contracted through them;
Must not be an employee of, or contracted through, a contractor or construction manager holding
construction contracts;
May be a qualified employee or consultant of the owner.
The CxA must report results, findings and recommendations directly to the owner.
n The CxA must conduct, at a minimum, 1 commissioning design review of the owners project requirements,
basis of design and design documents prior to the mid-construction documents phase and must back-check
the review comments in the subsequent design submission.
n The CxA must review contractor submittals applicable to systems being commissioned for compliance with
the owners project requirements and basis of design. This review must be concurrent with the reviews of the
architect or engineer of record and submitted to the design team and the owner.
n The CxA or other project team members must develop a systems manual that gives future operating staff the
information needed to understand and optimally operate the projects commissioned systems.
n The CxA or other project team members must verify that the requirements for training operating personnel
and building occupants have been completed.
n The CxA must be involved in reviewing the operation of the tenant space with operations and maintenance
(O&M) staff and occupants within 8 to 10 months after substantial completion. A plan for resolving
outstanding commissioning-related issues must be included.
p tcgs & Sgs
Engage a CxA as early as possible in the design process. Determine the owners project requirements, develop
and maintain a commissioning plan for use during design and construction and incorporate commissioning
requirements in bid documents. Assemble the commissioning team, and prior to occupancy verify the performance
-
7/29/2019 LEED 2009 CI guide
41/84
LEED 2009 or CommErCiaL intEriors
23
of energy-consuming systems. Complete the commissioning reports with recommendations prior to acceptance of
the commissioned systems.
Owners are encouraged to seek out qualified individuals to lead the commissioning process. Qualified individuals areidentified as those who possess a high level of experience in the following areas:
n Energy systems design, installation and operation
n Commissioning planning and process management
n Hands-on field experience with energy systems performance, interaction, start-up, balancing, testing,
troubleshooting, operation, and maintenance procedures
n Energy systems automation control knowledge
Owners are encouraged to consider including water-using systems, building envelope systems, and other systems in
the scope of the commissioning plan as appropriate. The building envelope is an important component of a facility
which impacts energy consumption, occupant comfort and indoor air quality. While this prerequisite does not
require building envelope commissioning, an owner can receive significant financial savings and reduce risk of poorindoor air quality by including it in the commissioning process.
The LEED Reference Guide for Green Interior Design and Construction, 2009 Edition provides detailed guidance on
the rigor expected for the following process activities:
n Owners project requirements.
n Basis of design.
n Commissioning plan.
n Commissioning specification.
n Performance verification documentation.
n Commissioning report.
-
7/29/2019 LEED 2009 CI guide
42/84
LEED 2009 or CommErCiaL intEriors
24
ea Cd 3: Msum d Vc
25 s
iTo provide for the ongoing accountability and optimization of tenant energy and water consumption performance
over time.
rqums
CasE 1. Pjec Le th 75% he tl Buldg ae
Complete 1 or more of the following:
n Install submetering equipment to measure and record energy use within the tenant space. (2 points)
n Negotiate a lease whereby energy costs are paid by the tenant and not included in the base rent. (3 points)
or
CasE 2. Pjec 75% me he tl Buldg ae
Install continuous metering equipment for the following end uses: (5 points)
n Lighting systems and controls.
n Constant and variable motor loads.
n Variable frequency drive operation.
n Chiller efficiency at variable loads (kW/ton).
n Cooling load.
n Air and water economizer and heat recovery cycles.
n Air distribution static pressures and ventilation air volumes.
n Boiler efficiencies.
n Building-related process energy systems and equipment.
n Indoor water riser and outdoor irrigation systems.
Develop and implement a measurement and verification (M&V) plan that incorporates the monitoring
information from the above end uses and is consistent with Option B, C or D of the 2001 International
Performance Measurement & Verification Protocol (IPMVP) Volume I: Concepts and Options for Determining
Energy and Water Savings.
Provide a process for corrective action if the results of the M&V plan indicate that energy savings are not being
achieved.
-
7/29/2019 LEED 2009 CI guide
43/84
LEED 2009 or CommErCiaL intEriors
25
p tcgs & SgsFor projects with an area that constitutes less than 75% of the total building area, tenant space is submetered and has
a direct pay clause in their lease for energy actually used instead of on a square foot basis. For projects with an area
that constitutes 75% or more of the total building area, model the energy and water systems to predict savings. Design
the project with equipment to measure energy and water performance. Draft a M&V plan to apply during building
operations that compares predicted savings to those actually achieved in the field.
-
7/29/2019 LEED 2009 CI guide
44/84
LEED 2009 or CommErCiaL intEriors
26
ea Cd 4: G p
5 s
iTo encourage the development and use of grid-source, renewable energy technologies on a net zero pollution basis.
rqums
oPtion 1
Engage in at least a 2-year renewable energy contract to provide at least 50% of the tenants electricity from
renewable sources, as defined by the Center for Resource Solutions Green-e energy product certification
requirements.
All purchases of green power must be based on the quantity of energy consumed, not the cost, as determined by
the annual electricity consumption results of EA Credit 1, Optimize Energy Performance.
or
oPtion 2
Engage in at least a 2-year renewable energy contract to purchase at least 8 kilowatt hours per square foot per
year from renewable electricity sources as defined by the Center for Resource Solutions (CRS) Green-e Energys
product certification requirements.
All purchases of green power must be based on the quantity of energy consumed, not the cost.
p tcgs & SgsDetermine the energy needs of the tenant space and investigate opportunities to engage in a green power contract.
Green power is derived from solar, wind, geothermal, biomass or low-impact hydro sources. Visit https://www.
green-e.org/energyfor details about the Green-e Energy program. The power product purchased to comply with
credit requirements need not be Green-e Energy certified. Other sources of green power are eligible if they satisfy
the Green-e Energy programs technical requirements. Renewable energy certificates (RECs), tradable renewable
certificates (TRCs), green tags and other forms of green power that comply with the technical requirements of the
Green-e Energy program may be used to document compliance with this credit.
https://www.green-e.org/energyhttps://www.green-e.org/energyhttps://www.green-e.org/energyhttps://www.green-e.org/energy -
7/29/2019 LEED 2009 CI guide
45/84
LEED 2009 or CommErCiaL intEriors
27
Mr pqus 1: Sg d Cc rccbs
rqud
i
To facilitate the reduction of waste generated by building occupants that is hauled to and disposed of in landfills.
rqums
Provide an easily accessible dedicated area or areas for the collection and storage of materials for recycling for the
tenant space. Materials must include at a minimum paper, corrugated cardboard, glass, plastics, and metals.
p tcgs & Sgs
Designate an area for recyclable collection and storage that is appropriately sized and located in a convenient area.
Identify local waste handlers and buyers for glass, plastic, metals, office paper, newspaper, cardboard and organic
wastes. Instruct occupants on recycling procedures. Instruct occupants on the recycling procedures. Consider
employing cardboard balers, aluminum can crushers, recycling chutes and other waste management strategies to
further enhance the recycling program.
-
7/29/2019 LEED 2009 CI guide
46/84
LEED 2009 or CommErCiaL intEriors
28
Mr Cd 1.1: t Sclg-tm Cmmm
1
iTo encourage choices that will conserve resources, reduce waste and reduce the environmental impacts of tenancy as
they relate to materials, manufacturing and transport.
rqumsThe occupant or tenant must commit to remain in the same location for a minimum of10 years.
p tcgs & Sgs
Suggest negotiations resulting in longer leases or ownership.
-
7/29/2019 LEED 2009 CI guide
47/84
LEED 2009 or CommErCiaL intEriors
29
Mr Cd 1.2: Budg rusM i nsucu Cms
12 ps
iTo extend the life cycle of existing building stock, conserve resources, retain cultural resources, reduce waste and
reduce environmental impacts of new buildings as they relate to materials manufacturing and transport.
rqumsMaintain at least 40% or 60% by area of the existing non-shell, nonstructural components (e.g., walls, flooring and
ceiling systems). The minimum percentage interior component reuse for each point threshold is as follows:
Interior Reuse Points
40% 1
60% 2
p tcgs & SgsIdentify during the selection and design of the tenant space the potential to maintain as many of the existing interior
elements as possible. Remove elements that pose a contamination risk to occupants, and update components that
would improve energy and water efficiency, such as mechanical systems and plumbing fixtures. Quantify the extent
of building reuse.
-
7/29/2019 LEED 2009 CI guide
48/84
LEED 2009 or CommErCiaL intEriors
30
Mr Cd 2: Csuc ws Mgm
12 ps
iTo divert construction and demolition debris from disposal in landfills and incineration facilities. Redirect recyclable
recovered resources back to the manufacturing process and reusable materials to appropriate sites.
rqumsRecycle and/or salvage nonhazardous construction and demolition debris. Develop and implement a construction
waste management plan that, at a minimum, identifies the materials to be diverted from disposal and whether the
materials will be sorted on-site or comingled. Excavated soil and land-clearing debris do not contribute to this credit.
Calculations can be done by weight or volume, but must be consistent throughout. The minimum percentage debris
to be recycled or salvaged for each point threshold is as follows:
Recycled or Salvaged Points
50% 1
75% 2
p tcgs & SgsEstablish goals for diversion from disposal in landfills and incineration facilities and adopt a construction waste
management plan to achieve these goals. Consider recycling cardboard, metal, brick, concrete, plastic, clean wood,
glass, gypsum wallboard, carpet and insulation. Construction debris processed into a recycled content commodity
that has an open market value (e.g., wood derived fuel [WDF], alternative daily cover material, etc.) may be applied
to the construction waste calculation. Designate a specific area(s) on the construction site for segregated or
commingled collection of recyclable materials, and track recycling efforts throughout the construction process.
Identify construction haulers and recyclers to handle the designated materials, and seek verification that the
diverted materials are recycled or salvaged, as intended. Note that diversion may include donation of materials to
charitable organizations and salvage of materials on site. For commercial interior projects the recycling rate for the
landlords demolition activity (before delivery to the tenant) can contribute to the project calculations for this credit
if the team so chooses.
-
7/29/2019 LEED 2009 CI guide
49/84
LEED 2009 or CommErCiaL intEriors
31
Mr Cd 3.1: Ms rus
12 s
iTo reuse building materials and products to reduce demand for virgin materials and reduce waste, thereby lessening
impacts associated with the extraction and processing of virgin resources.
rqumsUse salvaged, refurbished or reused materials, the sum of which constitutes at least 5% or 10%, based on cost, of
building (construction) materials, excluding furniture and furnishings The minimum percentage materials reused
for each point threshold is as follows:
Reused Materials Points
5% 1
10% 2
p tcgs & Sgs
Identify opportunities to incorporate salvaged materials into project design and research potential material
suppliers. Consider salvaged materials such as beams and posts, flooring, paneling, doors and frames, cabinetry,
brick, and decorative items.
-
7/29/2019 LEED 2009 CI guide
50/84
LEED 2009 or CommErCiaL intEriors
32
Mr Cd 3.2: Ms rusuu d usgs
1
iTo reuse building materials and products to reduce demand for virgin materials and reduce waste, thereby reducing
impacts associated with the extraction and processing of virgin resources.
rqumsUse salvaged, refurbished or used furniture and furnishings for 30% of the total furniture and furnishings budget.
p tcgs & Sgs
Identify opportunities to incorporate salvaged and reuse furniture into project design and research potential
material suppliers. Consider salvaging and reusing systems furniture and furnishings such as case pieces, seating,
filing systems, decorative lighting and accessories.
-
7/29/2019 LEED 2009 CI guide
51/84
LEED 2009 or CommErCiaL intEriors
33
Mr Cd 4: rccd C
12 s
iTo increase demand for building products that incorporate recycled content materials, thereby reducing impacts
resulting from extraction and processing of virgin materials.
rqumsUse materials, including furniture and furnishings, with recycled content1 such that the sum of postconsumer2
recycled content plus 1/2 of the preconsumer3 content constitutes at least 10% or 20% based on cost of the total value
of the materials in the project. The minimum percentage materials recycled for each point threshold is as follows:
Recycled Content Points
10% 1
20% 2
The recycled content value of a material or furnishing is determined by weight. The recycled fraction of the assembly
is then multiplied by the cost of assembly to determine the recycled content value.
Mechanical, electrical and plumbing components cannot be included in this calculation.
p tcgs & SgsEstablish a project goal for recycled content materials, and identify material suppliers that can achieve this goal.
During construction, ensure that the specified recycled content materials are installed. Consider a range of
environmental, economic and performance attributes when selecting products and materials.
1 Recycled content is defined in accordance with the International Organization of Standards document, ISO 14021 Environmental labels anddeclarations Self-declared environmental claims (Type II environmental labeling).
2 Postconsumer material is defined as waste material generated by households or by commercial, industrial and institutional facilities in theirrole as end-users of the product, which can no longer be used for its intended purpose.
3 Preconsumer material is defined as material diverted from the waste stream during the manufacturing process. Reutilization of materials (i.e.,rework, regrind or scrap generated in a process and capable of being reclaimed within the same process that generated it) is excluded.
-
7/29/2019 LEED 2009 CI guide
52/84
LEED 2009 or CommErCiaL intEriors
34
Mr Cd 5: rg Ms
12 ps
iTo increase demand for building materials and products that are extracted and manufactured within the region,
thereby supporting the regional economy and reducing the environmental impacts resulting from transportation.
rqums
oPtion 1 (1 p)
Use a minimum of 20% of the combined value of construction and Division 12 (Furniture) materials and products
that are manufactured1 regionally within a radius of 500 miles.
or
oPtion 2 (2 p)
Meet the requirements for Option 1.
Use a minimum of 10% of the combined value of construction and Division 12 (furniture) materials and products
extracted, harvested or recovered, as well as manufactured, within 500 miles of the project.
p tcgs & Sgs
Establish a project goal for locally sourced materials and identify materials and material suppliers that can
achieve this goal. During construction, ensure that the specified local materials are installed and quantify the total
percentage of local materials installed. Consider a range of environmental, economic and performance attributes
when selecting products and materials.
1 Manufacturing refers to the final assembly of components into the building product that is furnished and installed by the tradesmen.For example, if the hardware comes from Dallas, Texas, the lumber from Vancouver, British Columbia, and the joist is assembled in Kent,Washington, then the location of the final assembly is Kent, Washington
-
7/29/2019 LEED 2009 CI guide
53/84
LEED 2009 or CommErCiaL intEriors
35
Mr Cd 6: rd rb Ms
1 p
iTo reduce the use and depletion of finite raw materials and long-cycle renewable materials by replacing them with
rapidly renewable materials.
rqumsUse rapidly renewable construction and Division 12 (Furniture and Furnishings) materials and products for 5% of the
total value of all materials and products used in the project, based on cost. Rapidly renewable building materials and
products are made from plants that are typically harvested within a 10-year or shorter cycle.
p tcgs & SgsEstablish a project goal for rapidly renewable materials and identify materials and suppliers that can achieve this
goal. Consider materials such as bamboo flooring, wool carpets, straw board, cotton batt insulation, linoleum
flooring, poplar OSB, sunflower seed board, wheatgrass cabinetry and others. During construction, ensure that the
specified rapidly renewable materials are installed.
-
7/29/2019 LEED 2009 CI guide
54/84
LEED 2009 or CommErCiaL intEriors
36
Mr Cd 7: Cd wd
1 p
iTo encourage environmentally responsible forest management.
rqumsWhen using new wood-based products and materials, use a minimum of 50% that are certified in accordance with
the Forest Stewardship Councils principles and criteria. Division 12 (Furniture) material value is included in the
determination of the certified wood content.
p tcgs & SgsEstablish a project goal for FSC-certified wood products and identify suppliers that can achieve this goal. During
construction, ensure that the FSC-certified wood products are installed and quantify the total percentage of FSC-
certified wood products installed.
-
7/29/2019 LEED 2009 CI guide
55/84
LEED 2009 or CommErCiaL intEriors
37
ieQ pqus 1: Mmum id a Qu pmc
rqud
i
To establish minimum indoor air quality (IAQ) performance to enhance indoor air quality in buildings, thus
contributing to the comfort and well-being of the occupants.
rqums
Meet the minimum requirements of Section 4 through 7 of ASHRAE Standard 62.1-2007, Ventilation for Acceptable
Indoor Air Quality (with errata but without addenda1).
anD
CasE 1. mechclly Veled spceMechanical ventilation systems must perform according to the ventilation rate procedure.
Modify or maintain existing building outside-air ventilation distribution system to supply at least the