IPD/BIM & Commissioning: The Future is Now
2013 IPD / BIM Symposium
Shane Nault, PE, CEM, CxA, LEED AP BD+C
President Building EnergetiCx, PLLC
Allen Angle VDC-FM Integration Manager Business Resource Group
The AIA Charlotte is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request. This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
AIA Quality Assurance
Course Description
Commissioning is a process that enhances the delivery of a project and benefits the entire project team.. Weaving the commissioning process into an Integrated Project Delivery (IPD) project should be a natural fit because it involves more participants at an early phase and encourages communication and collaboration throughout the project life. This course will provide a brief introduction to the commissioning process and how the emergence of cloud based commissioning integrates with the BIM and IPD. We will review the commissioning process for design-bid-build compared to design-build, review the commissioning deliverables, review the document turnover process, introduce cloud based commissioning, and how all this relates to facility management.
• Participants will understand the commissioning process and how it integrates with the overall project life cycle.
• Participants will be introduced to how IPD and Commissioning can work together.
• Participants will understand the different commissioning deliverables and documents provided on a project and how they can benefit the owner.
• Participants will be introduced to Cloud Based Commissioning.
Learning Objectives
Important Principles of IPD
0% 10% 20% 30% 40% 50% 60%
Early Involvement of Key Participants
Mutual Respect/Trust
Collaborative Innovation/Decision Making
Open Communication
Mutual Benefit/Reward
Early Goal Definition
Organization and Leadership
Intensified Planning
Appropriate Technology
53%
45%
43%
42%
24%
24%
24%
21%
13%
Research by Markku Allison, AIA
IPD Overview
CM
O
A
Owner
Construction Manager Architect
IPD (collaboration)
• “Pure” IPD
• “IPD-ish”
• Open “Collaboration”
“A quality-focused process for enhancing the delivery of a project. The process focuses on verifying and documenting that the facility and all of its systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the Owner’s Project Requirements.” ASHRAE Guideline 0-2005, The Commissioning Process
Commissioning
Commissioning Philosophy
Teamwork is the ability to work together toward a common vision. The ability to direct individual accomplishments toward organizational objectives. It is the fuel that allows common people to attain uncommon results. —Andrew Carnegie
Varying Perspectives
Reveals Information
Right or Wrong?
Equifinality • Variety of Solutions
Eliminates Blind Spots
More Perspectives the Better
Principle of Complimentary
Social Commissioning
Communication •Open / Frequent
Common Goals •Mutual Benefit
Relationships •Establish •Respect / Trust
Keys to Success
IPD & Commissioning encompasses “All”
IPD & Commissioning helps fill the gaps in coordination
Define and Measure Project
Outcomes
Goals
Standards
Energy Quality
Operation
IPD and Cx Working Together
IPD and Cx Working Together
Effo
rt
Typical ‘Value’ Engineering !
Strategy Design Construction Operation
25% 75%
Life
cycl
e co
st
Virtual Building Design Proposed Entry
Influence vs. Cost Curve
•Greater Opportunity for Impact (Cost / Design) •Communication, Coordination, and Cooperation
Implement the Cx Process Early
•Owners Project Requirements •Benchmarks
Begin with End in Mind
•Equipment Information •Setup Database (BIM) •System Manual Requirements
Establish Project Requirements
•Link Phases of Design and Construction •Ensure Quality of Building Systems •Building Turnover Suited to the Owners Operation Requirements
Results
Commissioning Process and IPD
Commissioning Deliverables
What Are the Commissioning Deliverables?
OPR / BOD Review
Design Review Report
Commissioning Plan
Provision of Commissioning Specifications
Cx Testing / Training Requirements
Pre-Functional Verification Test Checklists
Cx Issues Log /Action Items
Meeting Minutes / Site Visit Reports
Functional Performance Testing
Progress Reports
Submittal Review Comments
Systems Manual
Final Commissioning Report
Building Operations Review
Document Turnover
• Why / How / When • Handover Requirements
• BIM Close Out Deliverables • Commissioning Documents • LEED Documents • O&M Documents • Operations & Support
Information
• Digital Management Exchange Guidelines
Integrated projects often rely on cutting edge technologies. Technologies are specified at projects initiation to maximize functionality, generality and interoperability. Open and interoperable data exchanges based on disciplined and transparent data structures are essential to support IPD. Because open standards best enable communication among all participants, technology that is compliant with open standards is used whenever available.
Principle of IPD - Technology
Appropriate Technology
Improve User Experience
Improve Collaborative Experience
Provide Transparency
Sustainable – Paperless
Efficient – Real Time
Equipment Management
Cloud Based Commissioning
Web based software that is used to managed the commissioning process
Cloud Based Commissioning
Cloud Cx
Owner
Architect
MEP Engineer
General Contractor
Mechanical Contractor
Electrical Contractor
TAB Agency
Cx Agent
O&M Staff
Everyone is involved in the process
Sustainable
Efficient (Simple) • Intuitive / Easy to Use
Highly Organized
Accessibility
Instant Reports and Updates
Cloud Based Commissioning
Asset Management •Track Related Issues •Access Checklists •Access Functional Test
Results •Access O&M Information •Add Model and Serial
Numbers • Integrate with FM
Software
Scanning / Bar Coding
Preventative Maintenance •Access to Information
Cloud Based Commissioning
Facility Management
People Employees Occupants Vendors
Space Properties Buildings Floors Rooms
Things Infrastructure Furnishings Finishes
Facility Management means many things to many people. Primarily, it involves the management of the People, Spaces and Things that make-up our facilities.
What is Facility Management…really?
Facility Management
Minimize paper-based processes, and collaborate digitally.
Check for and manage interferences between trades, digitally.
Create a culture of trust and sharing.
Involve all team members in design meetings, including contractors.
Institute building information modeling.
Facilitate collaboration.
Set up contract mechanisms that enable open collaboration.
Communicate design ideas using 3D visualization to keep everyone aligned.
Facility Management Goals
BIM & IWMS Integration Options
ODBC
• Read Through Revit DB Link • Handover
• Read Compliant BIM Source • Handover • Spreadsheet
COBie
• Bidirectional Link • Real-Time Updating • Data Validation • Controlled Database
Direct BIM Integration
Revit CMMS/IWMS
Integrated Data & Management
BIM during Operations and Maintenance?
Workflow - Maintain Space Inventory
Building documentation
Maintenance manuals and schedules
Asset Management
Equipment Inventory
How To Reach Us
Shane H Nault PE, CEM, CxA, LEED AP BD+C