Implementation Trip for
Date of TAC Presentation: April 14th, 2009
Project Location: El Chaguite, Yoro District, HondurasProject Risk Level: 2
Northeastern University’s Student Chapter
Implementation Trip Tentative Travel Dates: June 11th – June 26th, 2009
1Project: El Chaguite Water System
El Tecuan
Project: El Chaguite Water System 2
Los Planes
Project: El Chaguite Water System 3
El Chaguite
Project: El Chaguite Water System 4
El ChaguitePopulation: 333 people
Project: El Chaguite Water System 5
Project Schedule
Project: El Chaguite Water System 6
Dates of Travel Purpose Description
December 2007 Los Planes Implementation & El Chaguite Assessment
Complete Transmission Main in Los Planes, Visit El Chaguite
April – May 2008 El Chaguite Assess. Water Quality, Hydraulic Investigations, Existing System Inspections, Topographic Survey, Health Survey
December 14- December 29, 2008
El Chaguite Phase 1 Implementation
Construct Transmission Main/ Distribution System
June 11-June 26 (proposed)
El Chaguite Phase 2 Implementation
Storage Tank/ Inspect Distribution System
Objectives of El Chaguite Implementation Trip
Project: El Chaguite Water System 7
• Inspect the installed distribution system
• Construct a 6,500 gallon water storage tank.
• Provide El Chaguite a water system that is
more reliable and has the capacity to meet the growing demand for water.
• Teach the villagers about conservation and sanitation.
El Chaguite
Project: El Chaguite Water System 8
Design Process
Project: El Chaguite Water System 9
• Excel water flow model• WaterGEMS flow model• Multi-phase implementation
• Phase 1 (COMPLETE)– Construct Transmission Main– Instruct villagers on
construction of distribution system
– Build break pressure tank (float-valve tank)
• Phase 2– Water storage tank– Inspect village-constructed
distribution system
Tank Design
• Demand
• Sizing
• Sources
• Assumptions
• Tank Walls
• Foundation
• Roof
Project: El Chaguite Water System 10
Current and Future Conditions
Project: El Chaguite Water System 11
Chaguite now: Chaguite in 25 years:
60 homes 87 homes
333 people 483 people
68 students 99 students
Conditions now: Conditions in 25 years
Total Average Available Flow (GPD)
22,349Total Average Available Flow (GPD)
22,349
Total Average Demand for People (GPD)
8,797Total Average Demand for People (GPD)
12,755
Total Average Demand for Irrigation (GPD)
3,000Total Average Demand for Irrigation (GPD)
4,350
Total Demand (GPD) 11,797 Total Demand (GPD) 17,105
Overall Feasibility
Project: El Chaguite Water System 12
• Water Source : 15.52 gpm (22,348 gallons/day)
• 25 year projected demand: 12,755 gpd
+4,350 gpd (Irrigation use)
17,105 gpd• Diurnal Demand Cycle
• Conclusion: Feasible with water storage tank
Sizing
Project: El Chaguite Water System 13
Sizing
Project: El Chaguite Water System 14
Sources
Project: El Chaguite Water System 15
This design is based on:
Circular Storage Tanks and Silos by A. Ghali
Design of Concrete Structures by A. Nilson et. al.
Concrete Slabs Analysis and Design by R. J. Cope & L. A. Clark
Reinforced Concrete Slabs by R. Park & W. Gamble
See reference tables for formulas and assumed constants
Assumptions
Project: El Chaguite Water System 16
Tank Design
Tank Wall
No. 3 rebarevery 3rd brick layer
No. 4 rebar @ 18" O.C.
2" mortar thickness
Tank Foundation
No. 3 rebar @ 12" O.C.in both directions
3" up from compacted soil
No. 4 Rebar @ 12" O.C.in both directions7" up from compacted soil
Overflow drains to stream
Foundation – Wall Interface
Rounded Corner
24" Contact Lap Splice
24" Contact Lap Splice
No. 4 Rebar BetweenBrick Layers
No. 3 Rebar in Foundation
In BetweenBricks in Wall
Tank Roof
No. 3 rebar @ 6" O.C.in both directions
No. 3 rebar diagonalaround access hatch
3 - No. 3 rebararound access hatch
Tank Inlet and Outlet
TO HOUSE 17AND DOWNTOWN
TO HOUSE 11 ANDNORTH OF VILLAGE
45° ELBOW (2)
2" UNION (TYP. OF 4)
2" GATE VALVE (2)
OUTLET SCREENS (2)
BRICK AND MORTARVALVE BOX
2" UNION
2" GATE VALVE
45° ELBOW
RISER PIPE2 - 90° BENDS
BRICK AND MORTARVALVE BOX
TANK FOUNDATION
OUTSIDE OFTANK WALL
TOP OF INLET PIPEONE BRICK LAYERFROM ROOF
Trip Schedule
Project: El Chaguite Water System 23
Jun-11Fly to San Pedro SulaGet Supplies Order MaterialsVisit Rigo
Jun-12Buy GroceriesOrder Rest of SuppliesResearch Pumps for Carrizalito Project
Jun-13Drive To RosarioMeet with Village and Present DesignLay out Tank Site
Jun-14Dig Tank SiteTransport Bricks, Cement, Rebar, etc.
Jun-15 Train Villagers our process for concreteJun-16 Layout casting of FoundationJun-17 Cast Foundation
Jun-18Inspect Distribution System - Day 1Install Services - Day 1
Jun-19Start Walls of TankInspect Distribution System - Day 2Install Services - Day 2
Jun-20Visit Los PlanesVisit El Tecuan
Jun-21Survey CarrizalitoTake a trip to Yoro
Jun-22Cut GI pipe for tankVisit El Rosario School
Jun-23 Visit El Chaguite SchoolJun-24 Final Meeting With El ChaguiteJun-25 Drive to San Pedro SulaJun-26 Fly back to Boston
Budget
Project: El Chaguite Water System 24
El Chaguite Phase 2 Estimated Budget
Travel
Airfare $ 4,800
Exit Fees $ 210
Truck Rental $ 1,300
Gas $ 120
GroundHotel $ 300
Food $ 600
Labor
Guides $ 240
Laundress $ 100
Cooks $ 240
Materials
PVC Fittings/Valves $ 180
GI Pipes & Fittings $ 281
Tools $ 164
Tank Materials $ 1,365
Contingency $ 928
Total $ 10,827
Sustainability• Extra materials supplied for maintenance and replacement.
• Locals will be educated on water conservation and proper system maintenance.
• Water Board willcollect usage tax to fund future repairs.
• Simple design and construction
Project: El Chaguite Water System 25
Community Involvement
Project: El Chaguite Water System 26
• How has the community been involved in this project?– During the site assessment we inquired about the community’s wishes and took
their input into consideration during the design process. Letters have been sent to the villagers for approval of the design.
• Was a second, follow-up assessment conducted once the initial designs were completed?
– No, there was no follow-up assessment, but this trip will serve as a follow-up assessment before designing the second phase of the implementation of the system.
• How did everyone agree on this design?– We discussed the tentative initial plan with the villagers and formed our design
based upon these original discussions.
• How many people will this project impact?– This project will impact the quality of life for approximately 350 people.
• Has the NGO been helpful?– ACTS, the NGO in the area, has been extremely helpful in the progression of this
project. Since they already have a traveling infrastructure set up in the area, it has been much easier than expected to secure safe places to stay, guides to the area, and reliable sources of information. In addition, the wealth of knowledge that the group has about the history of El Rosario and the surrounding area has been beneficial in understanding the culture and social dynamics of El Chaguite.
Community Ownership & Education
Project: El Chaguite Water System 27
• What kind of help will the community be providing?– Labor (digging trench, laying pipe, mixing cement, transporting
materials).– We will coordinate a schedule of construction with El Chaguite’s
Water Board.
• Who will own the project once it’s completed? – El Chaguite will own the water system upon completion of the
project. The El Chaguite Water Board will manage the communally used infrastructure.
Community Ownership & Education
Project: El Chaguite Water System 28
• Who will be overseeing maintenance once the team leaves and how will repairs be paid for?– El Chaguite’s Water Board will be overseeing the maintenance
of the system. We will leave extra materials with the villagers to take care of any immediate necessary repairs. Hopefully, with improved health, the villagers will be able to establish community funds and pay for repairs further in the future.
• What education will be provided to the community?– The community will be educated on the maintenance of the
system, and we also plan to provide information about health and sanitation. In order for this to be a successful effort we will be working with the community Water Board and local organizations to ensure that the people understand the situation and are well informed about health and sanitation issues.
Questions?
Project: El Chaguite Water System 29
Thank you for your attention. This slide
concludes our formal presentation.
The following slides provide additional
information which may be useful.
Project Background
Project: El Chaguite Water System 30
• The need for EWB-NEU’s previous project, Los Planes water supply project was realized by EWB-NEU and ACTS, a non-profit organization that has been working in the area for over 15 years.
• ACTS has been working on improving the quality of life in the area by implementing medicinal and educational programs in the village of El Rosario as well as several of the surrounding villages.
• EWB-NEU has completed two projects in the area working with the villages of El Tecuan and Los Planes. During this time EWB-NEU realized the need for a similar project in El Chaguite.
• EWB-NEU was approved for an assessment trip that occurred in December 2007. During the assessment all the data that was necessary to design the system was collected
• Due to the shear size of the village, amount of work and materials needed, the design will need to be implemented over at least two phases.
• The following presentation outlines the final design for the El Chaguite water project, design alternatives, logistics of travel, and budget for Phase One.
El Chaguite Existing System
31Project: El Chaguite Water System
32Project: El Chaguite Water System
Existing Conditions
Project: El Chaguite Water System 33
• Sufficient, clean water source• Limited service• Unusable distribution system• Damaged main line• Diverse topography• Hurricane damage• Fire damage
Alternatives Considered
Project: El Chaguite Water System 34
North Water Storage Tank East Water Storage Tank
Trip Logistics
Project: El Chaguite Water System 35
Building Materials
Project: El Chaguite Water System 36
Equipment
Project: El Chaguite Water System 37
Survey Equipment:Topography MapsRented GPS UnitRod, Level, and Total Station200’ Tape Measures
Water Testing Equipment:Hach 5-in-1 Test StripsColiscan Easygels1mL Droppers Sterile Petri DishesWater Tap Pressure Gauge
Tools for GI pipes:GI Pipe CutterGI ReamerTree Vice
Other Equipment:2-Way Battery-Operated RadiosLocal Road MapsFirst Aid kitsDigital Camera
* All of the Equipment has been checked to clear Honduras’ Customs
Accommodations
Project: El Chaguite Water System 38
Dates, transportation, and lodging• Fly out of Boston on June 11, 2009. Pick up rental truck at the airport in San Pedro Sula and drive to the Hotel
Ejecutivo in the city.• Leave San Pedro Sula the next day, after securing materials, food and water. Travel 3.5 hours to the village of El
Rosario (location of the bunk house and ACTS clinic)• From June 11 to June 26 – travel between El Rosario, and surrounding villages, focusing our implementation
efforts on El Chaguite. Also travel to El Tecuan, La Reinada and Los Planes to check status of past projects.• Travel back to San Pedro Sula on December 28 and spend another night in the Hotel Ejecutivo in San Pedro
Sula. • Return Rental trucks and fly out of San Pedro Sula on December 29
Contact Information of accommodations• For the first and last nights the team we will be staying at the Hotel Ejecutivo in San Pedro Sula ( 011-504-552-
4289)• During the rest of the trip the team will be staying in a bunk house in El Rosario which is next to the health clinic.
There will be no way of directly contacting the team by phone during this phase of the project, however two households in this village have phones. (Santiago 011-504-608-6942, and Rosa Castro 011-504-608-7219)
Sources of food and water for the team• The first morning in San Pedro Sula, the team will shop for groceries. The team will also purchase all bottled
water needed for the trip. When in the villages the team will buy more, locally grown, food from the villagers, such as corn and beans. Food will be prepared by cooks in the bunk house.
State whether the team be visiting surrounding areas.• The majority of time will be spent in El Chaguite implementing the first phase of the project. For a few days
during the trip, the team will visit villages that EWB-NEU has worked with in the past, including El Tecuan, Los Planes and La Reinada.
Safety & Emergency Plan
Project: El Chaguite Water System 39
Safety PlanEl Rosario and the surrounding villages are rural and the crime rate is very low. When crimes do happen it is very rare that they involve foreigners. The team will always be traveling in groups and two individuals from the village will be accompanying and guiding the group. There is a medical clinic in El Rosario with a well stocked pharmacy that ACTS has worked with for years. The bunk house will serve as a meeting place and the trucks will be available for emergency transportation.
Emergency Plan & Exit StrategySOS evacuation insurance was strongly suggested by the ACTS group in case of emergency. Political unrest is rare in Honduras. The country is considered one of the most politically stable countries in Central America. In case of emergency the team will exercise good judgment and use advice from the local guides to leave the country in the best way possible.
Are there any State Department Warnings for this country?As of March 19, 2009 there are no State Department Warnings for this country (information retrieved from US Department of State website)
Are there any other safety concerns for traveling at this time? Heavy rain and hurricanes have hit this area in the past. In case of extreme weather the team will stay off the roads and use best judgment with counsel from the locals
Project Contact Information
Project: El Chaguite Water System 40
Daniel P. Saulnier, P.E. (email withheld)
(phone # withheld)Professional Mentor
Prof. Ferdi Hellweger, Sc.D.(email withheld)
(phone # withheld)Faculty Advisor
Rajesh Punjabi(email withheld)
(phone # withheld)Project Lead
Lucas Johnson(email withheld)
(phone # withheld)Chapter President
Dean J. Seibert, M.D., ACTS(email withheld)
(phone # withheld)Health Point Person
Patti Barahona(email withheld)
(phone # withheld)NGO/Community Contact
Project Team: • 16 Students working on project• 1 professional mentor and 1 professor working on project• Rajesh Punjabi, Mike Sanders, Ryan Mahoney, Lucas Johnson, Peter Privitera,
John Martin, Jennifer Chin, Ann Polaneczky, Ethan LaRochelle, Amanda Horton, Laurel Rowse, Andy Baummer, Megan Fritz, Christian Mantilla, John Monachelli, Noah Garguilo, Dan Saulnier, Ferdi Hellweger
Project Team and Travel Team
Project: El Chaguite Water System 41
• Chapter Traveling: Northeastern University
• On-the ground Contact Phone # for the travel team Patti Baharona – (phone # withheld)
• Nearest US Consulate Contact info:– Embajada de los Estados Unidos de América, Avenida La Paz, Tegucigalpa
M.D.C., Honduras Tel. (504) 236-9320 / 238-5114 Fax. (504) 236-9037
• Nearest Hospital Contact Info: San Pedro Sula– Phone: 011-504-558-1580
• Travel Team: – 5 Students Traveling– 1 Professionals Traveling
Hours
Project: El Chaguite Water System 42
Number of WeeksHours per Week (avg) Total Hours
Project Lead:40 6 240
Daniel P. Saulnier
Student Lead:40 6 240
Rajesh Punjabi
Student Members 40 30 1200
Faculty 40 1 40
Total 1720
Administrative Data
Project: El Chaguite Water System 43
Final Checklist before Travel
Project: El Chaguite Water System 44
The goal of the review process is to make sure that your team has a successful implementation trip
1) Submit this presentation to the project management staff and TAC liaison at [email protected]. Turn in WITH the following:
– Volunteer Waiver Form (#605) for each person traveling. Please submit all at one time.
2) Prior to the TAC meeting: The Project Management Staff and the liaison will review this presentation with the project lead, mentor and other relevant team members via a conference call prior to its presentation at the TAC meeting.
3) Before final travel, your team should have the following checklists signed off by the persons listed below, and get a final OK from the EWB-USA Project Staff:
– Travel Readiness Checklist (#601): to project staff– Personal Health Checklist (#603): to team’s health point person (to be taken on the trip)– Detailed Field Equipment Checklist: to mentor or project lead– Provided this presentation & emergency contact information to each and every member of the
team– Have each person review the Travel Tips Presentation (#602)
4) The Project team will be responsible for following up on TAC Comments and submitting changes/revisions to the project staff
5) The Project team MUST notify the project staff of any changes to travel dates or travel teams. Additional team members MUST send in Waivers (#605) prior to travel.
Project Lead Sign-Off
Project: El Chaguite Water System 45
• I, Daniel P. Saulnier, P.E., as the Professional Mentor of this project, have reviewed the technical and logistical contents of this project, and approve of the proposed design. I will also comply with TAC recommended changes and make suggested changes before traveling on the implementation trip.
• Daniel P. Saulnier April 14, 2009 [signed]
Project: El Chaguite Water System 46
Project: El Chaguite Water System 47
Project: El Chaguite Water System 48
Data Collection
Project: El Chaguite Water System 49
• GPS Survey• Total Station Survey• Interviews
• Water quality testing– Total coliforms– VOCs– Metals
Trench Detail
Project: El Chaguite Water System 50
Trench Examples
Project: El Chaguite Water System 51
Tank Design
Project: El Chaguite Water System 52
Chaguite now: Growth projected by Thomas D. Jordan, Jr. Chaguite in 25 years: 60homes 45% 87homes
333people 482.85people 68students 98.6students
Projected Water Usage - Method 1Methodology based on "A Handbook of Gravity-Flow Water Systems" by Thomas D. Jordan, Jr. (p. 27-29)
45litre/day/person10litre/day/student at school
Current need: Need in 25 years:15665litres/day 22714litres/day
4138gallons/day 6000gallons/day
Projected Water Usage - Method 2Water usage according to "Health Aspects of Plumbing" (chapter 2)
published by the World Health Organization and the World Plumbing Council:
Minimum: 20litre/day/person (drinking, food preparation, basic hygiene)Moderate: 50litre/day/person (minimum plus laundry and bathing)Optimal: 100litre/day/person (moderate plus considerable comfort and well-being)
Current need: Need in 25 years: Minimum: 6660litre/day 1759gallon/day Minimum: 9657litre/day 2551gallon/dayModerate: 16650litre/day 4398gallon/day Moderate: 24143litre/day 6378gallon/dayOptimal: 33300litre/day 8797gallon/day Optimal: 48285litre/day 12755gallon/day
Additional Water for Irrigation of Personal Gardens189lpd/household for irrigation (source: Mike Sanders, Idaho Farmers Extension Report)
50gpd/household for irrigation (source: Mike Sanders, Idaho Farmers Extension Report)
Current need: Need in 25 years:11356liters/day 16467liters/day
3000gallons/day 4350gallons/day
ConclusionUse largest flow estimate (Method 2, Optimal water usage) for Tank Calculations, plus irrigation
Project: El Chaguite Water System 53
Walls: Horizontal Rebar
Test Wall for Cracking
Foundation Design
Roof Analysis
Roof Design
Project: El Chaguite Water System 58
Walls: Bending Moment
Project: El Chaguite Water System 59
Walls: Vertical Rebar
Demand
Project: El Chaguite Water System 60
Distribution System Model
Project: El Chaguite Water System 61
Transmission Main
Project: El Chaguite Water System 62
SourceProposed Tank Site
Existing Tank Site
Transmission Main
Project: El Chaguite Water System 63
Float Valve Tank
Project: El Chaguite Water System 64
Implementation Metrics
Project: El Chaguite Water System 65
Technical:
• Give a detailed description of the future monitoring of the impacts of your project
– Once the project is completed, the continuation of the monitoring of the system will be carried out by the community water board.
– We will initiate an education campaign to provide necessary water safety and sanitation information.
– Our chapter will remain in contact with the community to ensure that things are going smoothly, to provide any support that becomes necessary, and to ensure that the water availability issue has been fully addressed.
• What are the future plans for visiting and following up with any problems that might arise?
– We plan to implement this project in two phases, so the implementation trip for the second phase will also serve as a follow-up to the first phase.
– Since EWB-NEU plans on remaining active in the area around El Chaguite in the future, the group will check up on the village on any trips to the area. In addition, ACTS has a constant presence in El Rosario and the surrounding villages and can act as a liaison between El Chaguite and EWB-NEU.
Implementation Metrics(Health)
Project: El Chaguite Water System 66
Health:
• Give a detailed description of the baseline health assessment
– In January 2008 a standard EWB 509 Health Assessment Form was completed for the community of El Chaguite by one of the village elders on behalf of EWB-NEU. It is the intent of EWB-NEU to distribute additional forms for completion by other villagers during the implementation trip. The additional responses will allow for a cross-section of the community and provide greater insight into the village health situation.
– Our team conducted a health assessment of the village of El Chaguite. Interviews were made house by house to determine the public health status of the residents. All comments were recorded along with the number of people in each household, gender, and age
Implementation Metrics(Health)
Project: El Chaguite Water System 67
Health (continued)
• What health metrics were identified to measure the effect of this project on the community?
– We, or ACTS, will conduct another health survey after implementation to see if the number of cases of illnesses decreases after we improve the water availability in the village. We will be conducting water usage education and hope to improve basic sanitation practices in the village, such as encouraging hand washing. Through communication with ACTS in the future we can ask if spread of illnesses has decreased.
• What are the current health data findings? – The most common illnesses are malnutrition, headaches, common cold, diarrhea and fever.– Most of the illnesses listed are caused and/or spread more easily by the lack of clean and
reliable water in the village.
• What additional data is needed? – We may conduct more in depth water quality tests during the implementation trip to see if
water quality should be the focus of a future project in El Chaguite
Assessment for Future Project Phases
Project: El Chaguite Water System 68
• Will this trip be used as a site assessment for future projects? – This trip will be used as an assessment for the second phase of this project.
Because of the scale of the project, we have decided to implement it in two phases. The second phase will focus on the reservoir tank, completion of the distribution system and setting up taps at all of the houses.
• What are the community’s main concerns?– The main concern is to obtain a reliable source of water. We hope to increase
serviceability with a new transmission main. After the first trip, the main concern will be getting water to each house.
• Site Assessment Data Needs: – Verify location for reservoir tank.
• This information will be obtained by collecting GPS and survey data of potential locations and doing soil stability analysis.
– Determine locations for all of the taps to be installed. • This information will be obtained by collecting GPS data of the village and
working with the families to determine where the taps will go.
Assessment for Future Project Phases: Methodology
Project: El Chaguite Water System 69
• Describe the potential impacts to the physical environment that the project may cause.
– This project will affect the plant and animal life in the direct surroundings of the source box, float valve tank, reservoir tank, and water tap. We will attempt to make this effect as positive as possible.
• Describe what training your team has undergone/will undergo for this project.
– The team has knowledge in surveying and water systems, and will use the information gathered for the first phase of the design to help prepare for the project. In addition, the group has been educated by ACTS in regards to the cultural issues that exist in the area.
Project: El Chaguite Water System 70
Assessment for Future Project Phases: Metrics
Technical:• What metrics will be used to determine the technical success of this project?
– This project will be successful if the village has full access to clean drinking water. The success will be measured as follows. Water pressures were measured at many places in the existing system. The proposed design strives for a minimum pressure of 20 pounds per square inch (psi) and a maximum pressure of 80 psi. Tap pressures within this range will be considered successful.
– The quality of the water is also important to the success of the system. Water tests were conducted by the EWB-NEU travel team in December 2008. For a successful implementation, all the taps in the community should test negative for contaminants. Each of these tests will be conducted at representative locations throughout the distribution network.
Economic:• What additional metrics will be used to measure the effect of the next phase of this
project on the community?– This project will significantly increase the health and quality of life for the people of El
Chaguite, primarily the families who were not served by the original system.– The villagers will have the opportunity to invest their energy into different things which can
only bring about a bright future forr thecommunity. – Moreover, the health problems in El Chaguite will reduce. Having a plentiful supply of clean
water for drinking, cooking and bathing will undoubtedly improve the health of these people.
Project: El Chaguite Water System 71
Assessment for Future Project Phases: Metrics
Health:• What additional metrics will be used to measure the effect of the next phase of this
project on the community? – A health assessment has already been performed for the village of El Chaguite so we will
not need to collect another one at this time. After the project has been implemented, we may conduct a follow-up health survey to determine the effects of our system.
• What data is needed and from where will your team collect the data?– We have already gathered the necessary health information for this project.