Hardware Commissioning Tools
Robin
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 2
Summary Hardware Commissioning View
Slides from Antonio Vergara (PM Workshop) Inventory of Tools Spotlight on some favourites! Near future -> Vito
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 3
Commissioning of a SC Circuit1. Individual System Tests2. Short-Circuit Tests
Antonio V
ergara
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 4
Commissioning of a SC Circuit1. Individual System Tests2. Short-Circuit Tests3. Powering Procedure Tests
4. Interlock Tests PIC1
5. Powering Tests
COOL-DOWN
Connection Converter-Magnets
Antonio V
ergara
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 5
Single Circuit Powering Test
350A
PIC2 Injection 760A
EESPA FPA
Quench2 kA
Loss PP
EEQuench
6 kA
8.5 kA
12 kA
RB Circuit
PM data
PM data
PM data
PM data
PM data
PM Analysis Results
PM Analysis Results
PM Analysis Results
PM Analysis Results
Antonio V
ergara
The sequence is crucial - RJL
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 6
The Commissioning Scenario
RB, RQF,RQDIP Q&D
Correctors
80-120 AInner TripletCorrectors
FRONT 1
FRONT 2
Antonio V
ergara
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 7
Parallelisms and Constraints The 3 types of parallelisms:
Parallelisms between sectors Parallelisms between fronts Parallelisms between circuits – SOC
SOC: Set Of Circuits. Battery of circuits commissioned in parallel by the same front
Antonio V
ergaraSeveral: 1s of teams, 10s of tests, 100s of circuits, - RJL
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 8
The Commissioning Scenario: Schedule
SECTOR 7-8
2007
JAN
FEB
MAR
APR
MAY
JUNCo
ol-D
own
PIC1
Powe
ring
Test
s13 - 15 weeks
Connection to leads
200 SC Circuits
Antonio V
ergara
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 9
Developed Tools The Sequencer Reference and LSA Databases Individual Supervision Systems Alarms – Laser, Logging Test Management Software: SOC
Editor Post-Mortem Local Analysis Tools Post-Mortem Global Analysis Tool MTF
Antonio V
ergara
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 10
The LHC Ring Commissioning Tools
CERN Tools CCM Logbook LASER XCluc Equip State SDDS Brwsr
WIC Supervision LSA Function Generation and driving
Others
Measurement System Logging database Naming database Reference Database MTF LSA Database Timber and Meter Old Sequencer Equip Monitor for FGC Equip State Fixed Display Set of the Day Editor PIC Supervision JAPC Monitoring Logging Surveillance
For short circuit tests
CIET Supervision Cryo plant supervision
Cool down
QPS Expert Tool QPS Supervision Circuit Synoptic PM Tools New Sequencer
PIC and P2N
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 11
Console Manager Screenshot
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 12
Old Sequencer Screenshot
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 13
PIC Supervision Screenshot
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 14
Cryo Process Supervision Screenshot
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 15
Logging Client Screenshot, supplier UNICOS
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 16
SOC Editor Screenshot
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 17
Reporting and Specifying Bodies
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 18
Latest plan
AB-CO TC 8th February 2007 Hardware Commissioning Tools - RJL 19
Last words
Plenty of room to screw up during commissioning, the control system must guide the operator to help avoid mistakes
After commissioning the safety systems the control system must reduce the stress on them