Extension of the Riverwalk
Dylan Brown, Connor Hughes, Steve Deeb, & James Riel
Background: Existing Riverwalk Original Idea Collaborative effort
Construction Timeline Construction Cost
Pocket Park
Pedestrian Bridge: 12ft. Wide
Walkway Along EBSCO Side
Shade Shelters
Benches & Planters
Why
Why build this? Community Benefits Environmental Benefits
Extension Details
Path & Edging
10” by 10” Stone Pavers: Coffee Creek
Pave Edge Keep pavers in place
Planter & Landscaping
Same pavers as path 6’ Diameter 2’-6 Tall
Graded slightly for path
Trim branches
Benches & Railing: Same as Existing Dumor #58 8’ long, Black O’brien & Sons
O’brien & Sons
Lighting: Solar Illuminations
10’ Radius, spaced 15’ apart. 3’ Tall 3 hours in sunlight until full
charge Bolted to footing Will still charge in partial light Batteries replaced once per
year
CostMaterials: Cost:
Stone Pavers & Edging $9,400
Subsurface materials $1,300
Lighting $5,300
Benches $7,200
Headwall Railing $750
Backfill $350
Prep $3,000
Installation $8,900
Total: $36,200
Long-term Maintenance: Seasonal? Flooding Impact
Environmental Impacts
Tree protection River protection Construction impacts
Possible Extension
People
Glen Gibbs Kathy Connor David Pancost – Conservation Agent Jim Butler – EBSCO Maintenance Larry Graham – Engineer