EXPLANATION OF TCEQ COST ESTIMATE
FOR REMEDIATION AT THE
ASARCO COPPER SMELTER
EL PASO, TEXAS
May 11, 2009
![Page 2: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/2.jpg)
THE ASARCO SITE
422 Acres
![Page 3: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/3.jpg)
THE CURRENT LAND USE IS COMMERICAL/INDUSTRIAL
![Page 4: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/4.jpg)
CLEAN UP STANDARD USED FOR THE ASARCO SITE IS
COMMERCIAL/INDUSTRIAL
This is determined by comparison to existing land use in accordance with 30 TAC Chapter 350, Texas Risk Reduction Program (TRRP).
![Page 5: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/5.jpg)
CHEMICALS OF CONCERN• The elements which comprise the
Chemicals of Concern (COCs) at the ASARCO site include arsenic (As), cadmium (Cd), chromium (Cr), copper (Cu), iron (Fe), lead (Pb), selenium (Se) and zinc (Zn).
• The most prevalent COCs are arsenic, lead, and cadmium.
![Page 6: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/6.jpg)
REMEDIATION VS
RESTORATION• Remediation is the act of eliminating or
reducing the concentration of chemicals of concern in environmental media.
• Restoration is returning an area to an unimpaired condition.
![Page 7: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/7.jpg)
TCEQ COST ESTIMATE FOR REMEDIATION AT ASARCO SITE
$ 52.0 MillionTotal$ 2.2 MillionOther Expense$ 3.3 MillionPost Closure Care$ 21.9 MillionGroundwater Remediation$ 5.9 MillionConstruct Fourth Cell & Fence$ 9.8 MillionAsphalt Paving (75.50 acres)$ 8.9 MillionDemolition of Structures
![Page 8: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/8.jpg)
CATEGORY I MATERIAL
Cell # 3
Cell # 2
Cell # 120,000 cubic yards to be placed in proposed Cell # 4
Defined as material that could impact human healthand the environment
Sample EP 93 (5’ bgs): 7,100 ppm (As), 14,000 ppm (Cd), 54,000 ppm (pb)
![Page 9: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/9.jpg)
EXCESS MATERIAL WILL BE RELOCATED TO PROPOSED
CELL # 4
Existing Cell # 3
![Page 10: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/10.jpg)
PROPOSED CELL # 4• Same design as current cells with a liner
and drainage layer to prevent water from coming in contact with the buried material.
• 303,000 cubic yard capacity.• Additional engineering study is needed to
determine the proper location.
![Page 11: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/11.jpg)
CATEGORY II MATERIAL
16 Acres to be paved
22 Acres already paved
Defined as material that could impact the groundwater.
![Page 12: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/12.jpg)
DEMOLITION & PAVING
Asphalt Pavement
Building Demolition
![Page 13: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/13.jpg)
GROUNDWATER PLUMEDrinking Water Standards
Arsenic = 0.010 mg/l
Lead = 0.015 mg/l
Cadmium = 0.005 mg/l
EP 49: 62.5 ppm (As)
![Page 14: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/14.jpg)
GROUNDWATER CONTAINMENT
3000 ft slurry wall
A network of 80 extraction wells to contain the groundwater plume
![Page 15: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/15.jpg)
ASARCO Property• Prior Approval - the agreement with any
custodial trustee will require the approval of TCEQ and DOJ before any sale, lease, or other disposition of the property.
• Additional Funds - the settlement agreement allows for funds from the proceeds of any sale of the property to be used for the remediation of the site as well as for administrative costs of the custodial trust.
![Page 16: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/16.jpg)
Custodial Trustee• ASARCO will appoint a trustee chosen by
TCEQ and DOJ.• In conjunction with DOJ, TCEQ is currently in
the process of selecting a trustee. Please see the TCEQ ASARCO website for more information.
• The custodial trustee will implement & oversee the remediation at the site as well as manage the property in the custodial trust.
![Page 17: EXPLANATION OF TCEQ COST ESTIMATE FOR REMEDIATION … · ASARCO Property • Prior Approval - the agreement with any custodial trustee will require the approval of TCEQ and DOJ before](https://reader030.vdocuments.mx/reader030/viewer/2022040818/5e636c8ce8121c3f8833d92f/html5/thumbnails/17.jpg)
ASARCO WEB SITE
http://www.tceq.state.tx.us/remediation/sites/asarco.html
Don’t forget to sign up