ECO LATRINES--ECO LATRINES--Brook of Lake Atitlán, Sololá
“Todos por el Lago” & Rotary Club AssociationOctober, 2013
![Page 2: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/2.jpg)
Main ideaMain idea Implementation of dry latrines to provide
the surrounding communities of lake Atitlán - in the developing process - of decent and efficient services that also contribute to clean the villages and natural wealth.
The eco latrine model doesn’t use water and substitutes the cesspool (highly polluted) with containers that decompose the solid excretes making them less contaminant or, in the best of cases, takes advantage and uses them as a fertilizer.
![Page 3: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/3.jpg)
ObjectivesObjectives
Avoid contamination of the phreatic cloak in lake Atitláns basin.
Improve the life conditions of rural inhabitants.
Create a volunteer program to install and control the sanitary units.
![Page 4: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/4.jpg)
GoalGoalDevelop the Project in 3 phases:
◦Phase 1: installation + training.◦Phase 2: change of deposit + use control.
◦Phase 3: use control + residue stock. Install an average of 100 units’ semi annually.
Favor a population of 1200 people annually.
![Page 5: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/5.jpg)
Why use an eco Why use an eco latrine? latrine?
Is it similar to a Is it similar to a conventional conventional one?one?Why isn’t better to Why isn’t better to
install latrines with install latrines with water?water?
FREQUENTLY ASKED FREQUENTLY ASKED QUESTIONS…QUESTIONS…
![Page 6: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/6.jpg)
Actual situation of beneficiaries:Actual situation of beneficiaries:
What conventional latrine may carry:What conventional latrine may carry:
Water contamination
.
Consumption of contaminated
water.
Intestinal illness.
Underground water contamination.
Consumption of
contaminated water.
Intestinal illness.
![Page 7: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/7.jpg)
Hygene conditions at home:Hygene conditions at home:
Hans contaminated with microbes.
Food consumptio
n.
Intestinal illness.
Hans contaminated with microbes.
Food consumptio
n.
Intestinal illness.
![Page 8: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/8.jpg)
Hygene conditions at home:Hygene conditions at home:
Insects in waste contaminated with microbes.
Insects at home, dished, glasses and
food.
Intestinal illness.
Animals inside the house near
waste.
Person or objetc contamination in the
house.
Intestinal illness.
![Page 9: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/9.jpg)
PHYSICAL MODEL GENERATIONPHYSICAL MODEL GENERATION
![Page 10: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/10.jpg)
Local manufacturer that favors labor and transportations costs.
Cost : Q3,200.00 (incluides cabin, toilet, deposit and
shipping*)
Set up time: 1.5 horas
Hours per unit. Staff: 2 people.
(semi-trained) Guarantee: 1 year due to
faulty production. Durability: 10 years.
THE THE PROTOTYPEPROTOTYPE
![Page 11: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/11.jpg)
THE CABINTHE CABIN•Rectangular•Fiber glass•4 parts + roof•Easy to install next to the house.
THE BOWLTHE BOWL
THE DEPOSITTHE DEPOSIT
With similar characteristics as a conventional bowl with an additional compartment that separates liquids from solids. It is integrated to the floor platform.
A fiber glass base with capacity of 0.70 m3. Designed to be underground and reinforced to support the cabin.
![Page 12: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/12.jpg)
INSTALLATION PROCESSINSTALLATION PROCESS
![Page 13: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/13.jpg)
INSTALLATION PROCESSINSTALLATION PROCESS
Dig holes in the floor to locate deposits.
DigDig Introduction of
deposits in the floor and consolidation in the surroundings.
PlantPlant Setting with the
toilet over the depost and anchorage.
FloorFloor
![Page 14: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/14.jpg)
Integration of 3 lateral panes using bolts (over the floor.)
WallsWalls With the walls integrated,
the cover is set over the cabin and fastened with bolts.
CoverCover
INSTALLATION PROCESSINSTALLATION PROCESS
Door installation (alrealdy with higes and bolt.)
DoorDoor
![Page 15: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/15.jpg)
The ventilation tube is set followed by the protective cover in the outside
VentilationVentilation The flexible tube for
urine drainage is set and a small French drainage is practiced in one side of the toilet.
DrainageDrainage
INSTALLATIONS PROCESSINSTALLATIONS PROCESS
With the cabin is integrated, it is set over the floor and fastened with bolts to the deposit.
FasteningFastening
![Page 16: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/16.jpg)
RESPONSERESPONSE
Cantón Racantacaj Note the integration
with the natural and rural environment.
NahualáNahualá
Note the original toilet at the back, next to the Training Center of “Todos por el Lago”
San Lucas San Lucas TolimánTolimán
![Page 17: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/17.jpg)
INSTALLATION AND USE INSTALLATION AND USE MANUALMANUAL
![Page 18: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/18.jpg)
REALITIES OF THE REALITIES OF THE COMMUNITIESCOMMUNITIES
Space limitations Space limitations and lack of and lack of resources.resources.
Drainage lack.Drainage lack.
![Page 19: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/19.jpg)
UP TO DATE RESULTSUP TO DATE RESULTS
![Page 20: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/20.jpg)
UP TO RESULTSUP TO RESULTS
BEFOREBEFORE AFTERAFTER
![Page 21: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/21.jpg)
UP TO DATE RESULTSUP TO DATE RESULTS
Solid condition Solid condition after 5 months.after 5 months. Stratification Stratification
inside the inside the deposit.deposit.
![Page 22: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/22.jpg)
UP TO DATE RESULTSUP TO DATE RESULTS
Hygene Hygene conditions of the conditions of the
toiletstoilets
![Page 23: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/23.jpg)
UP TO DATE RESULTSUP TO DATE RESULTS
•Aware users of the compromise over the cleanliness practices.
•Dry solids. In this case, sifted dry soil is used as drying material.
![Page 24: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/24.jpg)
SIGNS OF APPROPIATIONSIGNS OF APPROPIATION
•Clean, with a small rug.
•Toilet paper hanger and illumination installed.
![Page 25: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/25.jpg)
MONITORING AND ANALYSISMONITORING AND ANALYSIS
Sample Sample recollection by recollection by
specialized specialized Techs.Techs.
![Page 26: Eco latrines October 2013](https://reader036.vdocuments.mx/reader036/viewer/2022062710/5593560f1a28ab415c8b45ce/html5/thumbnails/26.jpg)
Thank you.Thank you.