ISBT Anand Vihar– Proposal finally approved in the UTTIPEC governing
body meeting after many revisions/modifications by UTTIPEC on 28 Aug ‘09.
– NOC received from AAI.– Authority approved & granted the project for
Environment Clearance on 18.01.10.– NOC from DPCC is received.– Applied for Tree cutting permission. Modified drawings
also submitted on 29.3.10.– Drawings and Documents resubmitted to DDA for
approval on 5 Oct ‘09 after incorporating all the observation/comments from DDA.
– Pre-qualification of contractors for construction-finalized. ADB requirement to Pre Q contractors as per ADB norms .ADB norms .
– Loan sanctioned from NCRPB.– The weekly review meeting with Architect on 19.01.10,
for EOT to be coordinated/obtained by TD & DIMTS to pursue DDA approval process further.
– Meeting with ADB consultants held on 29 Jan ‘10 and 15Feb ‘10.
– Draft copy of tender sent to ADB-Consultants as per ADB and got back their comments.
– EFC has been sent to GM-ISBT.– Proposed date of NIT for construction Mar ‘10 (Dec’09).– Proposed Completion Date : Aug ’11. (Mar ’11).
c
ISBT Sarai Kale Khan– Concept Plan submitted to UTTIPEC on 24 Apr ’09.– To retain the ITDR on its existing location, the entire
proposal has been modified & resubmitted on 18 Sep ‘09 & again on 23 Sep ‘09 for consideration.
– Proposal approved by LG during the Governing body meeting on 15 Jan ‘10.
– NOC from AAI received.– Applied for DPCC & EIA. EIA presentation has been re-
submitted .– Modified Drawings submitted to MCD on 9 Jun ’09. Now
the drawings need to be resubmitted as the proposal entirely modified by UTTIPEC. Drawings are ready for resubmission inthis week.
– Loan sanctioned from NCRPB– Draft copy of tender sent to ADB-Consultants as per ADB
and got back their comments.– Required documents, drawings & reports submitted for
NCR-PB on 30 Oct ‘09.NCR-PB on 30 Oct ‘09.– Documents required by NCR-PB/ADB submitted on 18
Dec ‘09. – Meeting with ADB consultants held on 29 Jan ‘10 & 15
Feb ‘10.– Pre-Qualification of contractors finalized. ADB
requirement to Pre Q contractors as per ADB norms. – EFC has been sent to GM-ISBT.– Likely date for NIT for construction : May’10 (Jun ’10, Feb
’10)
– Likely Completion date : Oct ‘11. (Jun ’11)
ccc
TO BE DEMOLISHED
TO BE RETAINED
ISBT KASMERE GATE
PLAN INDICATING AREAS TO BE DEMOLISHED / RETAINED
DATA CENTRE CONTROL CENTRE
FOB at Mother Teresa
FOB at Mathura Road
FOB at Africa Avenue
FOB at Pushp vihar