Defining Capacity Changes
Trigger:
Concept
You can do capacity modifications and can add or delete a day, or add or reduce capacity for a
shift through the Capacity Changes page. If you are adding or reducing capacity, you must also
enter a date and time on which the change is no longer in effect.
In this topic, you will define capacity changes.
Required Field(s) Comments
Output - Result(s) Comments
Additional Information
Last changed on: 1/18/2010 09:34:00 AM Page 1
-
8/14/2019 Defining Capacity Changes_SPD
2/36
-
8/14/2019 Defining Capacity Changes_SPD
3/36
System Process DocumentDefining Capacity Changes
Step Action
2. Click the Manufacturing and Distribution Manager link.
Last changed on: 1/18/2010 09:34:00 AM Page 3
-
8/14/2019 Defining Capacity Changes_SPD
4/36
System Process DocumentDefining Capacity Changes
Step Action
3. Click the vertical scrollbar.
Step Action
4. Click the Departments link.
Page 4 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
5/36
System Process DocumentDefining Capacity Changes
Step Action
5. Use the Organizations page to select your organization.
Last changed on: 1/18/2010 09:34:00 AM Page 5
-
8/14/2019 Defining Capacity Changes_SPD
6/36
System Process DocumentDefining Capacity Changes
Step Action
6. Click the M1 Seattle Manufacturing list item.
Step Action
7. Click the OKbutton.
orPress [Alt+O].
Page 6 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
7/36
System Process DocumentDefining Capacity Changes
Step Action
8. Use the Departments page to find the department that you had already created.
Last changed on: 1/18/2010 09:34:00 AM Page 7
-
8/14/2019 Defining Capacity Changes_SPD
8/36
System Process DocumentDefining Capacity Changes
Step Action
9. Click the Departments list item.
Step Action
10. Press [F11].
Page 8 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
9/36
System Process DocumentDefining Capacity Changes
Step Action
11. Enter the desired information into the Department field. Enter "ASSEMBLY".
Last changed on: 1/18/2010 09:34:00 AM Page 9
-
8/14/2019 Defining Capacity Changes_SPD
10/36
System Process DocumentDefining Capacity Changes
Step Action
12. Press [Ctrl+F11].
Step Action
13. Click the Resources button.
orPress [Alt+o].
Page 10 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
11/36
System Process DocumentDefining Capacity Changes
Step Action
14. Use the Resources page to select a resource.
Last changed on: 1/18/2010 09:34:00 AM Page 11
-
8/14/2019 Defining Capacity Changes_SPD
12/36
System Process DocumentDefining Capacity Changes
Step Action
15. Click in the Resource field.
Step Action
16. Click the Shifts button.
orPress [Alt+i].
Page 12 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
13/36
System Process DocumentDefining Capacity Changes
Step Action
17. Use the Shifts page to navigate to the Capacity Changes page to define capacity
changes.
Last changed on: 1/18/2010 09:34:00 AM Page 13
-
8/14/2019 Defining Capacity Changes_SPD
14/36
System Process DocumentDefining Capacity Changes
Step Action
18. Click the Capacity Changes button.
orPress [Alt+C].
Step Action19. Use the Capacity Changes page to add or delete a day, or add or reduce capacity
for a shift.
Page 14 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
15/36
System Process DocumentDefining Capacity Changes
Step Action
20. Click in the Simulation Set field.
Last changed on: 1/18/2010 09:34:00 AM Page 15
-
8/14/2019 Defining Capacity Changes_SPD
16/36
System Process DocumentDefining Capacity Changes
Step Action
21. Enter the desired information into the Simulation Set field. Enter "AS_Sim_Set".
Step Action
22. Click the Change list.
Page 16 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
17/36
System Process DocumentDefining Capacity Changes
Step Action
23. You can add, delete, add or reduce capacity for the department resource.
Add: Adds a workday and capacity changes.
Delete: Deletes a workday for this department resource.
Add or Reduce Capacity: Add or reduce capacity for a resource shift.
The capacity change can fall outside a shift time, so you can add time to a shift. To
reduce capacity, enter negative numbers.
Last changed on: 1/18/2010 09:34:00 AM Page 17
-
8/14/2019 Defining Capacity Changes_SPD
18/36
System Process DocumentDefining Capacity Changes
Step Action
24. Click the Add Day list item.
Page 18 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
19/36
System Process DocumentDefining Capacity Changes
Step Action
25. Click in the From field.
Step Action
26. Use the Calendar page to select a date.
Last changed on: 1/18/2010 09:34:00 AM Page 19
-
8/14/2019 Defining Capacity Changes_SPD
20/36
System Process DocumentDefining Capacity Changes
Step Action
27. Click the 27 button.
Page 20 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
21/36
System Process DocumentDefining Capacity Changes
Step Action
28. Click the OKbutton.
orPress [Alt+O].
Step Action29. Click in the Reason field.
Last changed on: 1/18/2010 09:34:00 AM Page 21
-
8/14/2019 Defining Capacity Changes_SPD
22/36
System Process DocumentDefining Capacity Changes
Step Action
30. Enter the desired information into the Reason field. Enter "Breakdown".
Page 22 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
23/36
System Process DocumentDefining Capacity Changes
Step Action
31. Click in the Simulation Set field.
Step Action
32. Enter the desired information into the Simulation Set field. Enter "Q3 Crunch".
Last changed on: 1/18/2010 09:34:00 AM Page 23
-
8/14/2019 Defining Capacity Changes_SPD
24/36
System Process DocumentDefining Capacity Changes
Step Action
33. Click the Change list.
Page 24 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
25/36
System Process DocumentDefining Capacity Changes
Step Action
34. Click the Reduce Capacity list item.
Step Action
35. Click the horizontal scrollbar.
Last changed on: 1/18/2010 09:34:00 AM Page 25
-
8/14/2019 Defining Capacity Changes_SPD
26/36
System Process DocumentDefining Capacity Changes
Step Action
36. Click in the Capacity field.
Page 26 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
27/36
-
8/14/2019 Defining Capacity Changes_SPD
28/36
System Process DocumentDefining Capacity Changes
Step Action
39. Click in the From field.
Page 28 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
29/36
System Process DocumentDefining Capacity Changes
Step Action
40. Use the Calendar page to select a date.
Step Action
41. Click the 28 button.
Last changed on: 1/18/2010 09:34:00 AM Page 29
-
8/14/2019 Defining Capacity Changes_SPD
30/36
-
8/14/2019 Defining Capacity Changes_SPD
31/36
System Process DocumentDefining Capacity Changes
Step Action
43. Click the horizontal scrollbar.
Step Action
44. Click in the From field.
Last changed on: 1/18/2010 09:34:00 AM Page 31
-
8/14/2019 Defining Capacity Changes_SPD
32/36
System Process DocumentDefining Capacity Changes
Step Action
45. Enter the desired information into the From field. Enter "15:00:00".
Page 32 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
33/36
System Process DocumentDefining Capacity Changes
Step Action
46. Click in the To field.
Step Action
47. Enter the desired information into the To field. Enter "23:00:00".
Last changed on: 1/18/2010 09:34:00 AM Page 33
-
8/14/2019 Defining Capacity Changes_SPD
34/36
System Process DocumentDefining Capacity Changes
Step Action
48. Click in the Reason field.
Page 34 Last changed on: 1/18/2010 09:34:00 AM
-
8/14/2019 Defining Capacity Changes_SPD
35/36
System Process DocumentDefining Capacity Changes
Step Action
49. Enter the desired information into the Reason field. Enter "Scheduled
Maintenance".
Step Action
50. Click the Save button.
Last changed on: 1/18/2010 09:34:00 AM Page 35
-
8/14/2019 Defining Capacity Changes_SPD
36/36
System Process DocumentDefining Capacity Changes
Step Action
51. You have completed the Defining Capacity Changes procedure.