Download - D1,L8 Critical Path Gantt Diagrams.ppt
-
Gantt diagrams Example 1The table below shows the tasks involved in a project, with their durations and immediate predecessors.
TaskDurationImmediate predecessorsA3-B4-C6-D5AE1BF6BG7C, D, E
-
Gantt diagrams Example 1The precedence network for this project, shown below, was found in Section 1.
-
Gantt diagrams - Example 1246810121416HoursThe critical activities, A, D and G are placed at the top of the chart.
-
Gantt diagrams - Example 1The earliest that activity B can start is at time 0, and the latest that it can finish is at time 7.246810121416Hours
-
Gantt diagrams - Example 1The earliest that activity C can start is at time 0, and the latest that it can finish is at time 8.246810121416Hours
-
Gantt diagrams - Example 1The earliest that activity E can start is at time 4, and the latest that it can finish is at time 8.246810121416Hours
-
Gantt diagrams - Example 1The earliest that activity F can start is at time 4, and the latest that it can finish is at time 15.246810121416Hours
-
Gantt diagrams Example 1A and B both require the use of the same piece of equipment. Can the project still be completed in 15 hours?Problem 1
-
Gantt diagrams - Example 1At present, A and B are both scheduled at the same time.Since A is a critical activity, moving A would result in the project being delayed.Moving B means that E and F must also move.246810121416Hours
-
Gantt diagrams - Example 1The project can still be completed in 15 hours.246810121416Hours
-
Gantt diagrams Example 1A and C must both be done by a qualified person. There is only one qualified person available. Can the project still be completed in 15 hours?Problem 2
-
Gantt diagrams - Example 1At present, A and C are scheduled at the same time.Again, as A is a critical activity, it is better to move C.Neither E nor F depend on C, but G does depend on C.246810121416HoursC can be moved by two hours
-
Gantt diagrams - Example 1246810121416HoursAt present, A and C are scheduled at the same time.Again, as A is a critical activity, it is better to move C.Neither E nor F depend on C, but G does depend on C.C can be moved by two hoursbut if it moves a further hour to avoid overlap with A, then G must also move.
-
Gantt diagrams - Example 1The project can be completed in 16 hours.246810121416Hours
-
Gantt diagrams and schedulingThe table below shows the tasks involved in a project, with their durations, immediate predecessors and number of workers required.How many workers are needed if all activities are scheduled to start as early as possible?
TaskDurationImmediate predecessorsNumber of workersA2-2B3-1C5-2D6A, B2E8C2F2C2G4D, E2
-
Gantt diagrams and schedulingThe precedence network shown below was found in Section 1.
-
Gantt diagrams and schedulingPut the critical activities along the top.C (2) E (2)G (2)(The numbers in brackets show the number of workers required)
-
Gantt diagrams and schedulingThe earliest start time for activity A is at time 0, and the latest finish time is at time 7.C (2) E (2)G (2)A (2)
-
Gantt diagrams and schedulingThe earliest start time for activity B is at time 0, and the latest finish time is at time 7.C (2) E (2)G (2)A (2)B (1)
-
Gantt diagrams and schedulingThe earliest start time for activity D is at time 3, and the latest finish time is at time 13.C (2) E (2)G (2)A (2)B (1)D (2)
-
Gantt diagrams and schedulingThe earliest start time for activity F is at time 5, and the latest finish time is at time 17.C (2) E (2)G (2)A (2)B (1)D (2)F (2)If this schedule is used, 6 workers are needed. (6 are needed on days 6 and 7).
-
Gantt diagrams and schedulingProblemOnly four workers are available.Is it possible to complete the project in the same amount of time?
-
Gantt diagrams and schedulingWe need to move some tasks so that only four workers are needed at any given time.At present 5 workers are needed for the first two days. Task B can be moved so that it starts after A has finished. This means that D must also move.C (2) E (2)G (2)A (2)F (2)
-
Gantt diagrams and schedulingWe need to move some tasks so that only four workers are needed at any given time.At present 6 workers are needed for days 6 and 7. Task F can be moved so that it starts after D has finished.C (2) E (2)G (2)A (2)F (2)
-
Gantt diagrams and schedulingNow only four workers are needed at any given time.C (2) E (2)G (2)A (2)F (2)Workers 1 and 2 could do activities C, E and G.Worker 3 could do A, B, D and FWorker 4 could do A, D and F (with 3 days off between A and D).