Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Project History
2001
Corridor Study
defined preferred alternative and right of way
preservation
2008
Preliminary design,
environmental documentation,
final design
SEP 2009
Phase I construction (realign Bass Lake Road / CSAH 101)
JUL 2010
Phase I complete and
open to traffic
APR 2011
Phase II construction (reconstruct
from CSAH 101
east to Vicksburg
Lane)
JUN - JUL 2011
State
Shutdown
NOV 2012
Project complete
![Page 3: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/3.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Why Reconstruct?
• Upgrade Bass Lake Road (CSAH 10) to
support area development and expansion
- Need to accommodate growing traffic volumes
- Convert 3.5 miles of two-lane roadway to
four-lane urban corridor
- Correct narrow shoulders, steep side slopes,
limit access points, improve roadway
vertical/horizontal curvature, add new facilities
for non-motorized users
![Page 4: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/4.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Existing & Proposed
Alignments for Bass
Lake Road from CSAH
101 to Vicksburg Lane
Bass Lake Road
Recommended
Concept Layout
Bass Lake Road
Final Layout
![Page 5: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/5.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Funding Sources
• American Recovery Reinvestment Act (ARRA)
- First ARRA project in Twin Cities metropolitan area to be
administered by a local agency
• Surface Transportation Program (STP)
• State, County and Local monies
- Metropolitan Council Environmental Services, Hennepin
County, City of Maple Grove’s Trunk Transportation & Utilities
and Park Dedication
![Page 6: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/6.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Keeping Residents in the Know
![Page 7: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/7.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
SHPO
After construction
Before construction After construction
![Page 8: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/8.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
State Shutdown Contingency Plan
• Developed a Detailed Plan for Each Project Phase
- Ensure all MnDOT oversight and independent assurance
tasks were covered by private consultants
- Tasks included materials testing, proper certifications, plant
inspections
• Plans in place continued project momentum seamlessly
• Project completed on time
![Page 9: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/9.jpg)
DESIGNING THE DETAILS
Minimizing environmental impacts through design.
![Page 10: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/10.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Bass Lake Road / CSAH 101
Signalized Intersection
Bass Lake Road / CSAH 101 “T”
intersection before construction
After construction After construction
![Page 11: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/11.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Bass Lake Road Corridor Improvements
![Page 12: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/12.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Environmental Considerations
Endangered Species
Curb sloped for turtle crossing
![Page 13: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/13.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Wall Benefits
![Page 14: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/14.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Bridge Box Culverts
After construction
Before construction
During construction
![Page 15: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/15.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Elm Creek Bridge/Trail/Creek Crossing
• Three-in-One Structure
- Overcome increased roadway elevation
- Provide new trail connections
- Maintains existing flow characteristics of the creek by using
the existing box culverts
- Environmental considerations in preferred alternative
- Dramatic cost savings by incorporating existing box culverts
into design
![Page 16: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/16.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
Tricking Mother Nature: Net Zero Loading
36,400 tons
(21,600 cubic yards)
unsuitable soils 7,800 tons
of expanded shale
=
PAVEMENT SECTION 28,150 tons of
pavement
450 tons (28,000 cubic yards)
of lightweight expanded polystyrene (EPS)
+
+
![Page 17: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/17.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
During construction During construction
During construction During construction
![Page 18: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/18.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
During construction During construction
During construction During construction
![Page 19: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/19.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
![Page 20: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/20.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
![Page 21: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/21.jpg)
A SUCCESSFUL OUTCOME
A modern and safe facility for all users.
![Page 22: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/22.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
• Bass Lake Road Reconstruction
- Completes upgrades of Bass Lake Road from
CSAH 101 to I-494
- Improves corridor mobility and maintains
necessary access
- New facilities for non-motorized users
- Construction created jobs for Minnesotans
- Innovative design and construction techniques
serve as a model for other agencies
![Page 23: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/23.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
After construction After construction
![Page 24: CSAH 101 TO VICKSBURG LANE | CITY PROJECT NO. 2007-17 - …D96B0887-4D81-47D5-AA86-9D2FB8B… · Endangered Species Curb sloped for turtle crossing . Bass Lake Road Reconstruction](https://reader035.vdocuments.mx/reader035/viewer/2022081408/605c7fa329769a0cd14b925f/html5/thumbnails/24.jpg)
Bass Lake Road Reconstruction CSAH 101 to Vicksburg Lane | City Project No. 2007-17
After construction