Download - Construction Update 09-29-2010
Building the Future
Current Activities this Week:
Foundations:
Area 4 Field Level – Foundations for “infill” area
between Column Lines 39-1 are ongoing.
Concrete Flatwork:
Area 3 Field Level –Lower dock slab-on-grade is complete.
Prep work for flatwork between column lines 6-4 is
ongoing.
Masonry:
Area 1 – Field level masonry installation is ongoing in
Area H, G, F, E and D. Area 2/3 – Concourse building
masonry installation is ongoing.
Steel Erection:
Area 4 – Steel erection for “infill” area will begin
9/30/2010 (Sequence 3-3). Area 2 – Steel joist and
metal decking installation for concourse buildings
is ongoing. Canopy decking installation is ongoing.
Canopy gutter enclosure framing installation is ongoing.
Roofing and Sheetmetal:
Area 1 – Permanent roofing installation at West
Building is ongoing. Area 2 – Canopy gutter installation
is ongoing.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 9.29.2010
Re: Wizards Stadium Project
Update – Week of
9.27.2010
Field Level Area 3 – Concrete slab-on grade
is placed at lower dock area.
Concourse Level Area 1 – Steel joist and roof
decking being installed at southwest
concourse buildings.
Field Level Area 1 – Subroof, storm line,
framing and ceiling hanger installation
continues on Field Level.
Building the Future
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels are ongoing. Exterior metal stud framing
and sheathing installation is ongoing at Field, Suite, and
Press Levels.
Glass:
Area 1 - Curtainwall framing and glass installation is
ongoing at West Building on west, south and east
elevations.
MEP Rough-in:
Area 3 – Underground MEP rough-in is ongoing.
West Building - Ductwork installation on
Concourse, Suite and Press Levels are ongoing.
Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection rough-in is ongoing on
Concourse, Suite and Press Levels. Electrical rough-in is
ongoing on Concourse, Suite and Press Levels.
Projected Activities occurring next Week:
Foundations:
Area 3/4 Field Level – Foundations for “infill” area between
Column Lines 29-1 will be complete.
Concrete Flatwork:
Area 3 Field Level – Concrete placement for Slab-on
Grade from lower dock area to Column Line 4.
Area 3 and 4 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Masonry:
Area 1 – Field level masonry installation will continue in
Area H, G, F, E and D. Area 2/3 – Concourse building
masonry installation will continue.
Area 1 – Shot of the Canopy decking, gutter
installation and gutter enclosure framing at
column lines 23-20.
Concourse Level Area 1 – Curtainwall
framing installation has started at field side
of Main Club.
Roof Level Area 1 – Permanent roofing is
being installed on the West Building.
Building the Future
Structural Steel Erection:
Area 4 – Structural steel erection for “infill” area will
be ongoing. Area 2 – Steel joist and metal decking
installation for concourse buildings will continue.
canopy decking installation will continue. Canopy gutter
enclosure framing installation will continue.
Roofing and Sheetmetal:
Area 1 – Permanent roofing installation at West
Building will continue. Area 2 – Canopy gutter installation
will continue.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels will continue. Exterior Framing and
sheathing installation will continue.
Glass:
Area 1 – Curtain Framing and Glass installation around West
Building will continue. Curtainwall framing on Suite and
Press Level balconies will continue. Curtainwall framing
at Field Side of Main Concourse will continue.
MEP Rough-in:
MEP Rough-in at Concourse, Suite and Press Levels will
continue. Ductwork installation on Concourse, Suite, and
Press Level will continue. Fire Sprinkler installation will
continue on Concourse, Suite and Press Levels.
Area 4 – Shot of north elevation roof
structure and on-grading seating progress
below.
Area 1 – Shot of the west building showing
the progress of the exterior envelope.
Building the Future
Additional Photos:
Area 2 – Concession/Restroom building
CMU installation is ongoing.
Area 4– Foundation work has started in “fill-
in” area between Column Lines 39-1.
Area 1 – Field side of West Building showing
progress of exterior sheathing.
Concourse Level Area 4 – Reinforcing,
formwork and electrical rough-in is ongoing.
Area 1 – Shot of the West Building from the
southeast concourse.
Field Level Area 1 – Metal stud framing and
drywall is ongoing.