Page 1: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 1

COMPASS FRC

Novembre 29, 2013

• COMPASS – phase II• MoU • Technical Coordinator• Preparations for 2014 run• Publications

Page 2: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 2

Bochum, Bonn (ISKP & PI), Erlangen, Freiburg, Mainz, München TU

USA (UIUC)

Saclay (CEA-DSM)

Tel Aviv

Calcutta (Matrivian)

Torino(University,INFN),Trieste(University,INFN)

Warsaw (NCBJ), Warsaw (TU) Warsaw (U)

CERN

Yamagata

Prag (CU/CTU)Liberec (TU) Brno (ISI-ASCR)

Dubna (LPP and LNP), Moscow (INR, LPI, StateUniversity),Protvino

Lisboa/Aveiro

COMPASS in 2013

Taipei (AS) New groups since 2012:

USA-IUIC, Taipei-AS & Portugal-Aveiro

Page 3: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 3

COMPASS Collaboration in 2013

12 Countries + CERN

23 institutes

217 Members: 141 paying members

43 PhD students

24 Diploma students

7 Rotation JINR

2 Exceptions

Page 4: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 4

COMPASS – phase II

Schedule of program approved by Research Board :

2012 Primakoff run p A p A g

DVCS run m p m p g

2013

2014 Oct.15-Dec.15: Drell-Yan test

(Magnet – Polarized target - Absorber)

2015 Polarized Drell-Yan p p mmX

2016 DVCS m p m p g

2017 DVCS “ “

Page 5: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 5

MoU

MoU • was agreed upon at the last FRC meeting, dec.2012• signed by CERN Directorate S.B. in February 2013• sent for signature to funding agencies in February 2013

• already signed by:

Czech Republic Italy

Japan Poland

Russia-JINR USA

• not yet signed by:

France-CEA Germany-BMBF

Portugal-FTP Russia (for Protvino IHEP)

Page 6: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 6

MoU – Signatures of funding agencies

Table as of July 2013

Page 7: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 7

Costs planning

Changes versus original tables in MoU:

- US: Only one drift chamber is funded, instead of two.

Part of existing straws will be kept. This is fine for 2014-2015.

- Germany : 57 kCHF for the ECAL1 upgrade were paid from the Collaboration funds, and

consequently are removed from the German contribution

(see Table Sub-detector B, MoU page 30)Spending profile unchanged

Page 8: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 8

Technical Coordinator

The Collaboration Board has identified a candidate, J. Bernhard,and proposed him to CERN, for the role of Technical Coordinator.

J.B. would be ready to start the job by March 1st, 2014.

We are confident that the issue is close to be solved.This is an important step for the forthcoming installations and runs.

Page 9: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 9

Plans during the shutdown

Preparation of the 2014 run (Polarized Drell-Yan)

- Magnet repair and instrumentation- Displacement of Polarized target by 2.3m- Insertion of Drell-Yan absorber- New Drift Chamber DC5

Everything on track

We thank the funding agencies for funding on time COMPASS phase-II

Page 10: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 10

Further constructions for 2016

• ECAL0 calorimeter for DVCS run in 2016

• Rest of DVCS setup as in 2012, including long LH2 target

Page 11: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 11

Publications in 2013• Leading order determination of the gluon polarisation from DIS events with high-pT

hadron pairs, PLB 718 (2013) 922

• Measurement of the Cross Section for High-pT Hadron Production in Scattering of 160 GeV/c Muons off Nucleons, PRD 88 (2013) 091101

• Leading and Next-to-Leading Order Gluon Polarisation in the Nucleon and Longit. Double Spin Asymmetries from Open Charm Muoproduction, PRD 87 (2013) 052018

• Study of Σ(1385) and Ξ(1321) hyperon and antihyperon production in deep inelastic scattering, EPJC 73 (2013) 2581

• Hadron transverse momentum distributions in muon deep inelastic scattering at 160 GeV/c , EPJC 73 (2013) 2531

• Transverse target spin asymmetries in exclusive ρ0 muoproduction,

CERN-PH-EP/2013-191, subm. PLB

More than 10 papers still in the pipeline. Trying to publish while no beam.

Page 12: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 12

Spares

Page 13: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 13

Investment tableUpdated Nov. 2013

Page 14: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 14

MoU- Investment table

Funding Agency Sub-det Sub-det Sub-det Sub-det Sub-det Sub-det Sub-det Sub-det TotalA B C D E F G H

Germany 367 285 212 60 67 22 1013USA 918 918France 344 46 418 808Italy 461 293 754CERN 100 110 100 80 260 650JINR 510 510Japan 25 250 275Poland 109 91 200Portugal 37 31 31 99Czech Rep. 49 18 24 91Russia 70 70China Taipei 45 45India 30 30Israel 20 20Common Projects 100 365 465

Total 1774 1130 125 721 266 607 404 921 5948

Subdetectors:

A: Tracking

B: Electromagnetic Calorimetry

C: LH2 Target

D: Recoil Proton CAMERA Detector

E: DAQ/Trigger/DCS

F: Particle Identification

G: Absorber

H: Polarized Target

Original table-Feb. 2013 Updated Nov. 2013

Page 15: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 15

Projected spending – I

Page 16: COMPASS FRC – November 29, 2013 1 COMPASS FRC Novembre 29, 2013 COMPASS – phase II MoU Technical Coordinator Preparations for 2014 run Publications

COMPASS FRC – November 29, 2013 16

Projected spending- II