Half Yearly EC Cornplicance Report, Khottadih OCP, Pandaveswar Area (Cluster l2),Eastern Coalfields Limited
Period:October 2015 -March 2016
Half Yea"lv co-pliance Repo"t fo" Khottadih ocp(Cluster 12)
Easter4 Coalfields Limited
EC Ref. No: J-1101517612011-1A-II.(M) Dated: 9th February,2015
Period: October ,2A1.5 - March ,2016S,
No.General Condition Compliance
I Grant of EC is only for non-forest area plus theforest area within the mining lease for which FC isavailable. No mining activities will be allowed inforest area for which FC is not available as per thelollowing tablen
S.
NoName of Mine Forest Clearance
not available (Ha.)
I Jhanjra UGP(Expansion)
99.0 Ha.
2. Tilaboni UGP(Expansion)
64.8 Ha
3. Rangamati A UGP 91.0 Ha.
4. Sonepur-Bazari
OCP32.65Ha
Total 287.45Ha
Khottadih OCP is an open cast project. The minedoes not include any forest land and no forest landexist in the nearby areas.
2. The maximum production from the mine at anygiven time shall not exceed the limit as prescribedin the EC.
Production did not exceed at any point th;specified EC Capacity. Production details fromOctober 2015 to March 2016 is given below:-
Half Yearly Production : 1162485 tonnesPeak Capacity as per EC(MTI: 2.20
I Month I proOu"tionffonn"sl I
---;€'*:6{''N-oaut Ofhcer ( Eni i ron ment)Pandaveswar Area
ir:\V, ,*
Dy. G.M.(M*&.\;.t Xhottadih OeP
t^#/ N. NathtY tr,ge4Khottadih o'c'P'
Half Yearly EC Complicance Repoft, Khottadih OCP, Pandaveswar Area (Cluster l2),E,astern Coalfi elds Limited
Period : October 2015 - March 2016
-=
Pandaveswar Area
o
Dy.G.M.(rM, j ,Khottadih ONp
firoa EfigplgerJe ivifl!Fandads*firuA.ea,;
" i . ," *{; i* t, s,},ji{
4ulrl v\l
AqentKhottadih O.c'P"
i.
October 210660November 210840December 219135January 206745February 1611 rsMarch 153990
J. rne valtolry oI me trU rs tor the lif-e of the Mine oras specified in the EIA Notification, 2006,whichever is earlier.
Noted and agreed.
4. Arr sarery measures shall be taken as per cMR,1957 &. related Circulars
All safety measures are taken@and related Circulars
5. r ne prooucrlon snatl be wrthin the same MiningLease area.
Being complied with.
6" Coal shall be transported Uy -ait onty. Coaftransportation from mine to siding should be byconveyor belt. The loading to siding bV pi1loaders into railway wagons.
uoat ls transported by trucks covered bl,tarpaulinover fully metalled roads from mine to railrvavsiding located at a distance of 3 km.
7. rnqepenoenr network ot railway sidings insidecluster will be developed. Railway sidings shouldbe constructed at the earliest and till then theproponent may use mechanically covered trucksfor transportation of coal.
Independent railway siding f@exists. At present tarpaulin covered trucks arebeing used for coal transportation for mine torailway siding.
8. Three tier green belts shall bffirailway sidings and along the road sides to preventdust and noise pollution.
wlll be comphed.
9. Stowing and depillaring shult-U" a, pe. tt erecommendations of the DGMS.
lhe mlne rs an open cast project.
10. The proponent must comply w-ttr *" naniganjAction Plan. The unstable areas within the clusterwill be brought under plantation after thepopulation residing over these areas isrehabilitated under the Master plan for Raniganj
Not applicable .Since the mine is an open casrproject.
),4
frl ottra
Half Yearly EC Complicance Report, Khottadih OCP, Pandaveswar Area (Cluster 12),
Eastern Coalfi elds LimitedPeriod : October 2015 - March 2016
Coalfield to be implemented by ADDA.
t1 Trees with deep rooted system should be planted
so as to prevent soil erosion.
Trees with deep rooted system are being plantedevery year over the OB dumps of mine. In the year
2013-14, 2014-15 and 2015-16 plantation was
done over areas of 2 Ha, 10 Ha and 20 Ha of OBdumps respectively.
I 12. Proponent should plant additional 10 Ha./Year
over the next 10 years at various locations in this
Cluster.
In the year 2013-14, 2014-15 and 2015-16plantation was done over areas of 2 Ha, 10 Ha and20Haof OB dumps.
r3. Riverinallahs shall be desilted and resorted back to
functional state.
River or nallahs exist in the command zone/leasehold area of the mine and are being desiltedregularly and resorted back to functional state.
14. Wildlife conservation plan be prepared and
submitted to the MOEFCC with the approval ofthe State Govt.
Not applicable as the mine does not include anyforest land and no forest land exist in the nearbyareas
15" Proponent shall use high resolution image of all
clusters for evaluating land use, plantation etc.
Baseline land-use study was based on highresolution satellite imagery of 2011. Furtherchanges in land use and plantation will be trackedby carrying out satellite imaginary at every threeyear' interval starting 2015.
t6. Separate drainage pattern be provided. Being complied with.
17. Sand stowing must be used as recommended by
CMPDI.
This condition is not applicable as the mine is an
open cast project.
18. Action plan for prevention and mitigation ofsubsidence be prepared and implemented.
This condition is not applicable as the mine is an
open cast project.
19. The OC patches to be operated yill be completely
filled-up after exhaustion of reseryes and
reclaimed with plantation.
Noted and agreed.
20. The OB'shall be completely re-handled at the end
of the mining.
It will be done as per the mine closure plan.
21 There shall be no residual OB dump after the It will be done as per the mine closure plan..
lu
Nodal O t-fi c-er lEnvi ron ment)Pandaveswar Area
ov. c.r.,r.ok,,,r ,*.trottaalhbcP
hY' N. NathlY Agent
Khottadih o'c 'pArea Engineer {Civiif'--PandauesY{ar Aiea
Half Yearly EC Complicance Report, Khottadih oCP, pandaveswar Area (clus ter l2),Eastern Coalfields Limited
Period : October 2015 _ March 2016
After completion of mining ffiareas shall be graded and planted upon.
This condition is not appliffi
Coal Extraction shall ulro b"@where agricultural production is continuing. Somepillars shall be left below the agricultural land. Nodepillaring & coal extraction should be carried outbelow habitation, H.T. Lines & beneath road,water bodies.
This conditionopen cast project.
Rehabilitation of the t orset@cluster to be carried out in two phases within l0years.
Noted and agreed.
The land excavatedback to original condition foragricultural/plantation purpo se.
Itwillbecomplieaaft@
Water discharged from tfr@as surface drinking water.
The discharged mine *@for parameters namely pH, TSS, TiS, Oil &Grease and COD and conforms to the MoEFSchedule-Vl Standards.The domestic water supplied conforms to the IS10400 standards. Monitoring reports are enclosedin Annexure I.
Final mine void 453 rta@more than 204Am. The void area will beconverted into water body. The mine void shouldbe used for pisciculture purpose.
Being complied with.
Regular monitoring of srffithe surface over and around the working area andimpact on natural drainage pattern, *uL. bodies,vegetation, structure, roads and surroundings shallbe continued till movement ceases completely. In
This condition
c 6ll{Nodal Offi cer (Environment)Pandaveswar Area
pl'N'."$Iffi?oDy. G.M.(M)idgent
-&qet"tAr:, Engineer (Civitf
PandaveswarAreaKhottaa-ih o'c'ir"
Half Yearly EC Cornplicance Report, Khottadih OCP. Pandaveswar Area (Cluster 12),Eastern Coalfields Limited
Period : October 201 5 - March 2016
case ofobservation of any high rate of subsidence
movement, appropriate effective measures shall be
taken to avoid loss of life and material. Cracks
shall be effectively plugged with ballast and
clayey soil/suitable material "
19. If subsidence is found exceeding the permitted
limits. then the landowners shall be adequately
compensated with mutual agreement of the
Iandou,ners.
This condition is not applicable as the mine is an
open cast project.
30. Water sprinkling system shall be provided tocheck fugitive emissions from loading operations,
conveyor system, haulage roads, transfer points,
etc. Major approach roads shall be black topped
and properly maintained.
Regular sprinkling of water is carried out over thesurface through fixed and mobile sprinklers tocheck fugitive emissions at Railway Siding,Transfer Points, Haulage Roads etc. All the majorapproach roads and coal transportation road isblack topped and fully metalled.
31" The CSR cost should be Rs. 5 per Tonnes of Coal
produced which sh'ould be adjusted as per the
annual inflation. Rs 1358 Lakh/annum shall be
phased out after expiry of the current mining lease
and after reclamation of mined over area. The
operating mines may be analysed and monitored
for compliance of conditions, bearing withmovement of wildlife and until such time they are
closed/phased out.
CSR works (with expenditure of at least two percent of the average net profits of the companymade during the three immediately precedingfinancial years) are carried out as per Company'sAct,2013.
)L.
I
The mining in the existing mines should be phased
out after expiry of the current mining lease and
after reclamation of mined over area. The
operating mines may be analyzed and monitored
for compliance of conditions, bearing withmovement of wildlife and until such time they are
closed/phased out.
Will be followed as per the Mine Closure Plan.
JJ. Everybody in the core area should be provided Protection against dust is provided as per the
ls,uDy" G.M.(Mffint, d ,Khottadih OCPY N. Nath
*o.uffi"o'c'P'
Pandaveswar Area
7E
Half Yearly EC Complicance Report, Khottadih OCP. Pandaveswar Area (Cluster 12),
Eastern Coalfields LimitedPeriod : October 2015 - March 2016
with mask for protection against fugitive dust
emissions.
Regulation 123 of CMR, 1957
34. Dust mask to be provided to everyone working inthe mining area.
Protection against dust is provided as per theRegulation 123 of CMR,1957
35. The supervisory staff should be provided withmask for protection against fugitive dust
emissions.
Protection against dust is provided as per theRegulation 123 of CMR,1957
36. People working in the core area should be
periodically tested for the lung diseases and the
burden of cost on account of working in the coal
mine area.
Periodic health check up for the workers in thecore areas are carried out regularly forPneumoconiosis, Permanent Hearing loss andother associated diseases.
37. The mining area should be surrounded by green
belt having thick closed thick canopy of the tree
cover"
Yearly plantation is being carried out in thesurrounding areas available.
38. Besides carrying out regular periodic health check-
up of their workers, l\Yo of the workers identifiedfrom workforce engaged in active miningoperations shall be subjected to health check-up
for occupational diseases and hearing impairment,if any, through an specialized agency/institutionwithin the District/State and the results reported tothis Ministry and to DGMS.
After the periodic health check up in last 6months, no such cases have been found during theperiod.
39. The embankment constructed along the riverboundary shall be of suitable dimensions and
critical patches shall be strengthened by stone
pitching on the river front side and stabilized'withplantation so as to withstand the peak water flowand prevent mine inundation.
This condition is not applicable as no river existswithin the leasehold.
Pandaveswar Area
0
ov c rv tJfr6",r , Khottadihbcp-
, -l]./ N. NatnY Agent'' *oott"iii* O 'e 'P"
Nodal (Environment)
--{tttt0r'
Half Yearly EC Complicance Report, Khottadih
{"ultaNodal Officer (Environment)
OCP, Pandaveswar Area (Cluster 12)'
Eastern Coalfi el<is Limited
Period : October 2015 - March 2016
ffiicable as no river exists
within the leasehold.Tfiere st att Ue no oreiflow of OB into the river
and into the agricultural fields and massive
plantation of native species shall be taken up in the
area between the river and the project'
Being complied with.ffiion ponds of aPProPriate
size shall be constructed to arrest silt and sediment
flows from soil, OB and mineral dumps' The water
so collected shall be utilized regularly desilted for
watering the mine atea) roads, green belt
development, etc" The drains shall be regularly
desilted and maintained properly' Garland drains
(size, gradient and length) and sump capacity shall
be designed keeping 50% safety margin over and
above the peak sudden rainfall and maximum
discharge in the area adjoining the mine site'
Sump capacity shall also provide adequate
retention period to allow proper settling of silt
material.
g"irg complied with.ffiient and length) around
the safety areas such as mine shaft and low lying
areas and sump capacity shall be designed keeping
50% safety margin over and above the peak
sudden rainfall and maximum discharge in the area
adjoining the mine sites' Sump capacrty shall also
provide adequate retention period to allow proper
settling of silt material.
Being comPlied with.ffigwallatthetoeof the
dumps and OB benches within the mine to check
run-off and siltation shall be based on the rainfall
data.
ffied and being oPerated at
the siding of OCP'ffiequate caPacitY for the
expansion project shall be operated with high
Pandaveswar Area
/
.
Half Yearly EC Complicance Report, Khottadih OCP, Pandaveswar Area (Cluster 12),Eastern Coalfields Limited
Period : October 2015 - March 201 6
crushing operations, conveyor system, haulageroads, transfer points, etc.
45. Mine discharge water outside the Ml, shall bemonitored, particularly for TDS and treated toconform to prescribed levels before discharge intothe natural environment.
Mine discharge water is analysed on regular basisby CMPDIL and found to be within the specifiednoffns of CPCB. Fortnightly environmentalmonitoring reports are enclosed.
46. Drills shall be wet operated. Being followed.
47. The project authorities shall undertake regularrepairing and tarring of roads used for mineraltransportation. A 3-tier green belt comprising of amix of native species shall be developed all alongthe major approach roads.
The roads are regularly repaired and properlytarred. Avenue plantation will be done in thecoming months wherever the land is available..
48. Controlled blasting shall be practiced with use ofdelay detonators and only during daytime. Themitigative measures for control of groundvibrations and to arrest the fly rocks and bouldersshall be implemented.
Being complied with.
49. A Progressive afforestation plan shall beimplemented covering an area of 6215.5 ha at theend of mining, which includes reclaimed externalOB dump area (404.74 ha), internal dump area(1856.54 ha) and Green belt land (364.57 ha) andin township located outside the lease by plantingnative species in consultation with the local DFOIAgriculture Department. The density of the treesshall be around 2500 plants per ha. Massiveplantation shall be carried out in open spaces inand around the mine and a 3-tier avenue plantationalong the main approach roads to the mine.
Trees with deep rooted system are being plantedevery year in the OB dumps of mine. In the year2013-14, 2014-15 and 2015-16 plantation wasdone over areas of 2 Ha, 10 Ha and 20 Ha of OBdump.
50. The proponent should prepare restoration andreclamation plan for the degraded area. The landbe used in a productive and sustainable manner.
Mine closure Plan has already been prepared forthe purpose. Restoration and reclamation shall bedone accordingly.
Pandaveswar Area
Area Engineer (eivil)PandaveswarAr*a
Half Yearly EC Complicance Report, Khottadih ocP, Pandaveswar Area (cluster 12)'
Eastern Coalfields Limited
Period : October 2015 * March 2016
It will be carried out
mining.
ifter the comPletion of
breaking open the land be carried out'
@al & Restoration of waste
land, other degraded land and OB dumps in lieu of
used for miningNo ground *ater shall be used for mining
Backfilled a."a coming- rnde. Khottadih OCP willbe reclaimed with plantation by planting native@ackfilled quarry area of
tgSO'FIu shall be reclaimed with plantation by
planting native plant species in consultation with
iocat OiOlAgriculture Department' The density of
the trees shall be around 2500 plants per ha'
Being complied with.@ groundwater level and
quitity shall be carried out by establishing
u n.t*ott of existing wells and construction ofnew peizometers' The monitoring for
quantity shall be done four times a year in pre-
monsoon (May), monsoon (August), post-
monsoon (November) and winter (January)
seasons und fo, quality in May. Data thus collected
shall be submiued to the Ministry of Environment
&. Forests and to the Central Pollution
Control Board quarterly within one month of
Ptopotal for Rooftop rain water harvesting system
in Pandaveswar Area Office is under process' No
case of declining of ground water table and drying
of wells of villagers has been found'
@p artificial groundwater
recharge measures for augmentation
of groindwater resource if the monitoring
indlcates a declining trend of groundwater table'
The project authorities shall meet water
requirernent of nearby village(s) in case the village
due to dewatering of mine'
Sewage treat"rent plant shall be installed in the
existiig colony. ntp stratt also be provided for
@d oustees will be as Per
the normi laid out in R&R Policy of CIL'L"rd o,;CA-th"tl b" compensated as per the
norrns laid out R&R Policy of CIL or the National
R&R Policy or R&R Policy of the State
Government whichever r4 triglgr'F".;"rlt""irg lu@
Pandaveswar Area
Arga fiig"1;,.^ .t,ii+l (:-mtGPPandavesi//ar Ar"ea'
Dy. G.M.(
Half Yearly EC Complicance Report, Khottadih oCP, Pandaveswar Area (Clus ter l2),Eastern Coalfields Limited
Period : October Z0l5 -March 2016
ofthe core zone and buffer zone, from the start ofthe project until end of mine life shall be preparedonce in 3 years (for any one particular seasonwhich is consistent in the time series), and thereport submitted to MOEF and its Regional officeat Bhubaneshwar.
mining land use, a time series oa talld use mapqbased on satellite imagery (on a scale of l: 501i0)
resolution satellite imffichanges in land use and plantation will be trackedby carrying out satellite imagery at every threeyears interval starting 2015..
A Final Mine Closure plan along with details ofCorpus Fund shall be submitted to the Ministryof Environment, Forests & Climate Change within6 months of grant of Environmental Clearance.
Final Mine Closure elan h@Khottadih OCP by CMPDIL.
The project authorities shall ln "on
uttution ,"ittthe Panchayats of the local villages andadministration identify socio-economic andwelfare measures under CSR to be carried out overthe balance life of the mine.
CSR works are being carried ort time to ti,"e inaccordance with the Company,s Act,2013.
Corporate Environment Responsibilitlra) The company shall have a w"il taid aorrn
Environment Policy approved by the Boardof Directors.
"Corporate Environmental policj-0D; of CoalIndia Limited has already been formulated.
b) The Environment policy shall prescriUe forstandard operating process/procedures tobring into focus anyinfringements/deviation/violation of theenvironmental or forest norms/conditions.
"Corporate Environmental policj.O 17if CoalIndia Limited. has prescribed standard operatingprocess/procedures to bring into focus anyinfringements/deviation/violation of th;environmental or forest norms/condition.
c) The hierarchical system or AdminGtrativeOrder of the company to deal withenvironmental issues and for ensuringcompliance with the environmentalclearance conditions shall be furnished.
of the company to deal with environmental issuesand for ensuring compliance with theenvironmental clearance conditions has been
lr.n]9.h.!_in "Corporate Environmental policy2012" of Coal India Limited
The hierarchical syste* o.ffi
vDy. G.M.(M)/,\gent
,,1/Kno"flf:\PehY Agent' *oottaa-ltt o'c'P'
Pandaveswar Area
Half Yearly EC Complicance Report, Khottadih OCP, Pandaveswar Area (Clustet 12),
Eastern Coalfi elds LirnitedPeriod: October 2015 - March 2016
The company is having a well laid down system ofreporting of non-compliances/violations ofenvironmental norms to the Board of Directors ofthe company.
d) To have proper checks and balances, the
company shall have a well laid down
system of reporting of non-
compliances/violations of environmental
norrns to the Board of Directors of the
company and/or shareholders or
stakeholders at large.
ComplianceGeneral Conditions
Being strictly followed.No change in mining technology and scope
working shall be made without prior approvalthe Ministry of Environment and Forests.
ofof
There shall be no change in the calendar plan ofproduction for quantum of mineral coal.
No change in the calendar plan includingexcavation, quantum of mineral coal and waste
shall be made.Air quality monitoring is caried out by CMPDILon fortnightly basis and all desired parameters are
well within the prescribed limits. Fortnightlymonitoring reports are enclosed
Four ambient air quality monitoring stations shall
be established in the core zone as well as in the
buffer zofle for PMto, PMz.s, SOz, and NOxmonitoring" Location of the stations shall be
decided based on the meteorological data,
topographical features and environmentally and
ecologically sensitive targets in consultation withthe State Pollution Control Board. Monitoring ofheavy metals such as Hg, As, Ni, Cd, Cr, etc.
carried out atleast once in six months.Air quality monitoring is carried out by CMPDILfortnightly and data on ambient air quality shall be
regularly submitted to the Ministry including itsconcemed Regional Officer and to the State
Pollution Control Board and the Central PollutionControl Board once in six months.
Data on ambient air quality (PMto, PMz.s, SO2 and
NOx) and heavy metals such as Hg, As, Ni, Cd, Crand other monitoring shall be regularly submittedto the Ministry including its concerned RegionalOffice and to the State Pollution Control Boardand the Central Pollution Control Board once insix months. Random variation of samples throughanalysis from independent laboratories recognised
under the EPA rules, 1986 shall be furnished as
of compliance report.Noise level monitori is carried out by CMPDILAdequate measures shall be taken for control of
General Conditions
ffirrtl-Nodal Officer (Environment)Pandaveswar Area
rl
tQCP
l'
Half Yearly EC Complicance Report, Khottadih OCP, Pandaveswar Area (Cluster 12),
Eastern Coalfields LimitedPeriod:October 2015 - March 2016
noise levels below 85 dBA in the workenvironment. Workers engaged in blasting and
drilling operations, operation of HEMM, etc shall
be provided with ear plugs/muffs.
on fortnightly basis. Noise level has always been
below 85 dBA. Reports are enclosed
6 Industrial wastewater (workshop and wastewaterfrom the mine) shall be properly collected, treatedso as to conform to the standards prescribed underGSR 422 (E) dated lgthMay 1993 and 31'tDecember 1993 or as amended from time to timebefore discharge. Oil and grease trap shall be
installed before discharge of workshop effluents.
Mine discharge water samples are tested inlaboratory at CMPDI on fortnightly basis. Minewater quality conforms to the standards prescribed
under GSR 422(E) dated 19th May 1993 and 3lstDecember 1993.
7 Vehicular emissions shall be kept under controland regularly monitored. Vehicles used fortransporting the mineral shall be covered withtarpaulins and optimally loaded.
Vehicular emissions are kept under control and
regularly monitored. Coal transportation at
Khottadih OCP from mine to railway siding is
being done by tarpaulin covered trucks. Theloaded trucks are made wet at first and thencovered with tarpaulins for transportation.
8 Monitoring of environmental quality parameters
shall be carried out through establishment ofadequate number and type of pollution monitoringand analysis equipment in consultation with theState Pollution Control Board and data gotanalysis through a laboratory recognised underEPA Rules, 1986.
Monitoring of environmental parameters is carriedout fortnightly by CMPDIL. Laboratory at
CMPDIL, Asansol is having all necessary
facilities.
9 Personnel working in dusty areas shall wearprotective respiratory devices and they shall also
be provided with adequate training and
information on safety and health aspects.
Protective respiratory devices are provided to theworkers near the dust generating sources.
Adequate training and information on safety and
health aspects to workers is provided periodically.
l0 Occupational health surveillance programme ofthe workers shall be undertaken periodically toobserve any contractions due to exposure to dustand to take corrective measures, if needed and
records maintained thereof. The quality ofenvironment due to outsourcing and the health and
safety issues of the outsourced manpower shouldbe addressed by the company while outsourcing.
Periodic Medical Examination is carried out forthe workers periodically.
11 A separate environmental management cell withsuitable qualified personnel shall be set up under
A separate environmental management cell withqualified personnel exists in Pandaveswar Area
ll; t)ov arvr-ffi;.,*, il,4<houadihbcP
l*#" Nh*thrtrottilii o 'c'P'
\
Pandaveswar Area
Half Yearly EC Complicance Report, Khottadih OCP' Pandaveswar Area (Cluster 12),
Eastern Coalfields Limited
October 2Ol5 -March 2016Period :
General Manager
Pandaveswar Area.e, who will rePort
directly to the Heud PIlh" rolqpg!ffiotection as kePt in
LrJg" each year ate not diverted for otherental Protection
measures shall be kept in separate account and
,f',utt no, be diverted fbr other purpose' Year-wise
..p.nOitrr. shall be reported to this Ministry and
its Resional Offr"e at Bh,ban"sh*neing comPlied with.vertise at least in
nvo local newspapers widely circulated around the
& Forests at hl&l&ry&lgEj
fro.j..,, on. oi which shall be in the vernacular
iungrug. of the locality concern^ed within seven
;;;r ;f the clearance letter informing that the
pro.lect has been accorded environmental clearance'und u .opy of the clearance letter is available with
the State i'ollution control Board and may also be
seen at the website of the ministry of Environment
Being comPlied with.
the company's website.
letter shallA copy of the envir<
be marked to concerned Panchayat/ local NGO' ifany, from whom any suggestion/representation has
i.Ln ,.."ired whiie processing the proposal' A
copy of the clearance letter shall be displayed on
Being comPlied with.
Office/Tehsildu.'s Offi"" fot 30 days'
nce letter shallA copy of the envir<
U. tttutt also be displayed on the website of the
"orr..tr"O State Pollution Control Board' The EC
letter shall also be displayed at the Regional
Offi"., District Industry Sector and Collector's
Witt Ue comPlied.'i uPloaded on the
"o*puny't website. The compliance status :lth:
tr*Ui*O and critical sectoral parameters shall
)iro u. iisplayed at the entrance of the project
rtiprfut.a environmental clearance conditions
rt rtt utto be uploaded by the project authorities on
it .i. *eUrite and updated at least once every six
months so as to bring the same in public domain'
if," -onitoring data of environmental quality
farameter (air, water, noise and soil)^and critical
iollutants such as PM10, PM2'5, SOZ,ana fii
hsDy. G.Jvl.(M)ffint
o .)wn'n"o-1f"'ofdrnY -
RqerJ" - ';i:'}t 0
x'io ur o fn c.$ r 1i nv iionm ent;
,Randayeswar Area
I
=
Half Yearly EC Complicance Report, Khottadih oCP, Pandaveswar Area (Clus ter l2),Eastern Coalfields Limited
Period : October 2015 _ March 201 6
premises and mine office and in-@oraG officegld on company's website.The project proponent shall @compliance reports on status of compliance of thestipulated environmental clearance conditions(both in hard copy and in e-mail) to the respectiveRegional Office of the Ministry, respective ZonalOffice's of CPCB and the SPCB.
The compliance repoftr on stut@the stipulated environmental clearance conditions(both in hard copy and in e-mail) shall besubmitted six monthly to the respective RegionalOffice of the Ministry, respective Zonal Offices ofCPCB and the SPCB.
The Regional Office of this Milist.y located in ttreRegion shall monitor compliance of the stipulatedconditions. The Project authorities shall extend fullcooperation to the office(s) of the Regional Officeby furnishing the requisite
The Environmental Statement f". e""1, f*r"r*rlyear ending 31 March in For-V is mandated to besubmitted by the project proponent for theconcerned State pollution Control Board asprescribed under the Environment (protection)Rules, 1986, as amended subsequently, shall alsobe uploaded on the company,s website along withthe status of compliance of EC conditions andshall be sent to the respective Regional Offices of
Complied with.
Annex I
MONITORING REPORTS
Pandaveswar Area
S,reg Errgg-:*=P&r;dsves,r*,
(Civil)Area
-6'5r'€ll
(Environment)
HalfYearly EC Complicance Report, Khottadih OCP, Pandaveswar Area (Cluster l2),Eastern Coalfi elds Limited
Period : October 2015 -March 2016
Annexure - II
Plantation Details.
Year of plantation No. of saplings Total area Covered(Ha)
Species Planted Cost Of Plantation
(Rs. in lakhs)
2013-14 5000 2Ha Miscellaneous s.06
2014-15 25000 10 Ha Miscellaneous 16.67
2015-16 50000 20IJ.z Miscellaneous 33.34
Pandaveswar Area
?1g\t'
Dy. G.M.(M/n&,r Khottadih OCP
\^iL N. Nath,,- - f,!r:b.c.p.Ebottadih
Area Engineer (Civil)
PandaveswarArea
7
Half Yearly EC Complicance Report, Khottadih OCP, Pandaveswar Area (Cluster 12),Eastern Coalfi elds Limited
Period : October 20 l5 - March 201 6
Plantation over 10 Ha OB Dump area of Khottadih OCP durine the vear 2014-15
Nodal Offrcer (Environment)Pandaveswar Area
Area,Engineer (0iv*rye
PandaveswarArea'$F;,
fiP{'ltt"
Half Yearly EC complicance Report, Khottadih ocp, pandaveswar Area (cluster l2),Eastern Coalfields Limited
Period : October 2015 _ March 2016