Basic Training:Basic Training:
Stormwater Controls Stormwater Controls for Development Projectsfor Development Projects
Jill Bicknell, P.E., EOA, Inc.
May 22, 2013
![Page 2: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/2.jpg)
Outline of PresentationOutline of Presentation Why include stormwater controls in
development projects?
Regulatory background
What’s the difference between construction and post-construction controls?
Defining post-construction controls
Current municipal stormwater permit requirements
Test your knowledge
![Page 3: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/3.jpg)
Why include stormwater controls Why include stormwater controls in development projects?in development projects?
Uses of San Francisco Bay and many local creeks are impaired for numerous pollutants
Stormwater runoff is the largest pollutant conveyance
Stormwater discharge regulations require pollutant and flow controls
![Page 4: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/4.jpg)
Why include stormwater controls Why include stormwater controls in development projects?in development projects?
Little runoff before development Lots of runoff after development
![Page 5: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/5.jpg)
Regulatory BackgroundRegulatory Background
US EPA – Federal Clean Water Act
National Pollutant Discharge Elimination System (NPDES) Permits
Phase I & II Municipal Stormwater Regulations
Cal EPA / State Water Resources Control Board – issues statewide permits
Construction General Permit
Industrial General Permit
Municipal Phase II General Permit
![Page 6: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/6.jpg)
Regulatory BackgroundRegulatory Background
Regional Water Quality Control Boards
Municipal Phase I Stormwater Permits
Wastewater Treatment Plant Permits
Individual Industrial Permits
San Francisco Bay Regional Water Board
Bay Area Municipal Regional Stormwater Permit (covers San Mateo County)
SF Bay wastewater treatment plant permits
![Page 7: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/7.jpg)
Bay Area Municipal Regional Permit Bay Area Municipal Regional Permit (MRP)(MRP)
Consolidates six Phase 1 municipal permits into one regional permit (76 permittees): San Mateo, Santa Clara,
Alameda, and Contra CostaCounties, Fairfield-Suisun, and Vallejo
Effective date: Dec. 1, 2009
Provision C.3 covers requirements for new development and redevelopment projects, and inspection and reporting requirements
![Page 8: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/8.jpg)
What’s the difference between construction and post-construction
controls?
Example of a construction best management practice (BMP)
Example of a post-construction stormwater control measure
![Page 9: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/9.jpg)
Construction controls or “best management practices”
(BMPs) Implemented during construction only
Control sediment and erosion (straw wattles, silt fences, hydroseeding, storm drain inlet filters …)
Good housekeeping practices to keep pollutants out of stormwater
Required by State Construction General Permit if one acre or more is disturbed
Municipalities must require construction BMPs in smaller projects, per municipal stormwater permit
![Page 10: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/10.jpg)
Post-Construction Post-Construction ControlsControls
Permanent features of the project design
Types of post-construction controls required by Municipal Regional Permit (Provision C.3)
Low Impact Development Source control measures Site design measures Stormwater treatment
Hydromodification management (HM)
![Page 11: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/11.jpg)
Low Impact Development (LID)Low Impact Development (LID) Reduce runoff and mimic a site’s predevelopment
hydrology: Minimize disturbed areas and impervious surfaces
Use infiltration, evapotranspiration, or rainwater harvesting to retain and treat stormwater runoff
Use biotreatment where these methods are infeasible
![Page 12: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/12.jpg)
Source Control MeasuresSource Control Measures Structural Source Controls
are permanent design features that reduce pollutant sources.
Examples include: Covered trash enclosures
Non-stormwater discharges drain to landscaping or to sanitary sewer
Drought-tolerant native or adapted plants
Encourage in all projects.
Require in projects that must implement stormwater treatment.
![Page 13: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/13.jpg)
Source Control MeasuresSource Control Measures Operational Source Controls
are practices to be conducted on an ongoing basis after construction is completed.
Examples: Integrated pest management
Street sweeping
Require in projects that must implement stormwater treatment.
Encourage in all other projects.
![Page 14: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/14.jpg)
Site Design MeasuresSite Design Measures
Permanent design features that: Reduce impervious surfaces Disconnect impervious
surfaces Preserve/protect natural
features
Examples include: Direct runoff to landscaping Pervious paving
“Disconnected” downspout
“Disconnected” downspout
Pervious walkway
Pervious walkway
![Page 15: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/15.jpg)
Site Design MeasuresSite Design Measures
Require in projects that must implement stormwater treatment
Require in certain small projects not subject to treatment requirements
Encourage site design measures in all other projects
Disconnected downspout
Disconnected downspout
![Page 16: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/16.jpg)
Stormwater Treatment MeasuresStormwater Treatment Measures
Engineered systems that remove pollutants from stormwater Hydraulically sized to
treat stormwater runoff from frequent, small storms
Provision C.3.d of the MRP specifies numeric sizing criteria for water quality design
Maintenance agreement required
Bioretention areaBioretention area
![Page 17: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/17.jpg)
New LID Treatment RequirementsNew LID Treatment Requirements
LID treatment methods required since 12/1/11
LID treatment defined as: Rainwater
harvesting/reuse,
Infiltration,
Evapotranspiration,
Or, if these are infeasible, biotreatment.
Harvesting for rainwater for indoor toilet flushing
Harvesting for rainwater for indoor toilet flushing
![Page 18: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/18.jpg)
How How MuchMuch Runoff Must Be Runoff Must Be Treated?Treated? Projects must treat runoff
from 100% of project: 80% of average annual runoff
(for volume-based treatment measures)
Flow of runoff from a rain event of 0.2 inches per hour intensity (flow-based treatment measure)
This is in Provision C.3.d of the MRP, so it’s called the “C.3.d amount of runoff”
OR “water quality design volume or flow”
![Page 19: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/19.jpg)
Stormwater Treatment MeasuresStormwater Treatment MeasuresWhen are they required? (“Regulated Projects”)When are they required? (“Regulated Projects”)
Required for projects that create and/or replace 10,000 sq. ft. or more of impervious surface
Required for the following types of projects that create and/or replace 5,000 sq. ft. or more of impervious surface:
– Restaurants
– Retail gasoline outlets
– Auto service facilities
– Parking lots
![Page 20: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/20.jpg)
Other C.3 Regulated ProjectsOther C.3 Regulated Projects
Road and trail projects that create and/or replace 10,000 sq. ft. of contiguous impervious surface
– New roads, and sidewalks and bike lanes built as part of new roads
– Widening of existing roads with traffic lane(s)
– Trails >10 feet wide or < 50 feet from creek bank
![Page 21: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/21.jpg)
New Requirements for Small and New Requirements for Small and Single Family Home ProjectsSingle Family Home Projects
Single family homes (>2,500 sq. ft. of impervious area) and small projects (between 2,500 and 10,000 sq. ft. of impervious area) must implement one of six site design measures:
– Direct roof runoff into cisterns or rain barrels– Direct roof runoff onto vegetated areas– Direct sidewalk and patio runoff onto vegetated areas– Direct driveway and parking lot runoff onto vegetated areas– Construct sidewalks and patios with permeable surfaces– Construct bike lanes, driveways, and parking lots with
permeable surfaces
![Page 22: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/22.jpg)
The following are NOT Regulated The following are NOT Regulated Projects:Projects:
– Detached single family home;
– Roadway reconstruction within same footprint;
– Road widening that does not add a travel lane;
– Sidewalks and bike lanes along existing roads;
– Impervious trails <10’ wide and >50’ from creek;
– Sidewalks, bike lanes and trails that drain to vegetated areas or made of permeable paving;
– Interior remodels;
– Routine maintenance and repair;
– Pavement resurfacing within existing footprint.
![Page 23: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/23.jpg)
Stormwater Treatment MeasuresStormwater Treatment MeasuresWhat are the different types?
LID Treatment Measures (required since 12/1/11)
Infiltration, evapotranspiration, and harvesting and use
Where this is infeasible, biotreatment is allowed
Non-LID Treatment Measures
High rate media filters and tree well filters
Allowed only for “Special Projects”
![Page 24: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/24.jpg)
““Special Projects”Special Projects” Special Projects are high density and transit
oriented development projects that may receive LID treatment reduction credit
Regional Water Board adopted Special Projects criteria in November 2011 (now part of MRP)
Some projects willqualify for limited use of “non-LID”measures, e.g.,media filters and tree box filters
![Page 25: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/25.jpg)
LID Treatment OptionsLID Treatment Options
LID Technique CategoryRainwater cisterns Harvest and use
Landscaped detention, street trees
Evapotranspiration, infiltration
Pervious paving Infiltration
Infiltration basin Infiltration
Infiltration trenches Infiltration
Bioretention areas (unlined, no underdrain)
Evapotranspiration, infiltration
Bioretention areas (lined, with underdrain)
Biotreatment
Flow-through planters Biotreatment
![Page 26: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/26.jpg)
Rainwater Harvesting and UseRainwater Harvesting and Use
Water used for non-potable uses, such as: Toilet flushing
Irrigation
Cisterns installed underground
Cisterns installed underground
![Page 27: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/27.jpg)
Infiltration FacilitiesInfiltration Facilities
Store water in void space of rocks, allowing it to infiltrate to surrounding soils
Requires infiltrative soils
Infiltration TrenchInfiltration Trench
![Page 28: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/28.jpg)
Biotreatment MeasuresBiotreatment Measures
Most Common Bioretention areas/rain
gardens
Linear bioretention areas (bioretention swales)
Flow-through planters
Flow-through planter
Flow-through planter
![Page 29: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/29.jpg)
Bioretention Area/Rain GardenBioretention Area/Rain Garden
Concave landscaped area of any shape.
Engineered biotreatment soil with specified infiltration rate (5 to 10 inches/hour).
Underdrain required if clayey underlying soils.
Raise underdrain to maximize infiltration, if conditions allow.
![Page 30: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/30.jpg)
Flow-through PlanterFlow-through Planter
No infiltration to underlying soils.
Planter box with engineered soils and underdrain.
Stormwater filters through biotreatment soil with specified infiltration rate (5 to 10 inches/hour).
OK along face of building, if waterproofing is used.
![Page 31: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/31.jpg)
No Longer Allowed* as Stand-alone No Longer Allowed* as Stand-alone Stormwater Treatment MeasuresStormwater Treatment Measures
Media filters*
Manufactured tree well filters*
Hydrodynamic separator Vortex units, “CDS” units
Vegetated swales and detention basins (unless designed to filter stormwater through bioretention soil)Media Filter CartridgeMedia Filter Cartridge
* Limited use of media filters and manufactured tree well filters allowed in “Special Projects”
![Page 32: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/32.jpg)
Media FiltersMedia Filters(Limited use ONLY in “Special Projects”)
Example of a Media Filter Cartridge
Example of a Media Filter Cartridge
Vault system: Fine particles are filtered
by filter media (see example cartridge)
The system may be designed to allow settling of large particulates before water is filtered through the media.
![Page 33: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/33.jpg)
Manufactured Tree Well FiltersManufactured Tree Well Filters(Limited use ONLY in “Special Projects”)
Example of a Manufactured Tree Well Filter
Example of a Manufactured Tree Well Filter
Tree well filter with proprietary planting media and underdrain
Planting media has extremely high infiltration rate.
Now available with biotreatment soil to meet LID requirements (but treats smaller area).
![Page 34: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/34.jpg)
Hydrodynamic Separators Hydrodynamic Separators (NOT a stand-alone treatment measure)(NOT a stand-alone treatment measure)
Vault system
Settling or separation unit to remove sediments
Effective for trash and large particles
Not designed to remove finer particles
![Page 35: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/35.jpg)
Vegetated SwaleVegetated Swale (NOT a stand-alone treatment measure measure unless stormwater filtered through bioretention soils))
Linear, shallow, vegetated channel
Used to be allowed to filter stormwater through dense vegetation
OK if allows stormwater to infiltrate downward through biotreatment soil
![Page 36: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/36.jpg)
Extended Detention BasinExtended Detention Basin (NOT a stand-alone treatment measure measure unless stormwater filtered through bioretention soils))
Basin with specially designed outlet to detain stormwater for at least 48 hours.
Used to be allowed to treat stormwater by settling.
Ok if used for storage upstream of LID measure or hydromodification control.
![Page 37: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/37.jpg)
Hydromodification ManagementHydromodification Management Purpose: Reduce
erosive flows in creeks.
Goal: Match post-project runoff rates, volumes and durations to pre-project condition for a range of storms.
Required for projects that: Create/replace 1 acre or more of impervious area, Increase impervious area over pre-project condition, AND Drain to creeks susceptible to erosion.
![Page 38: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/38.jpg)
San Mateo County HM Applicability Map
![Page 39: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/39.jpg)
Hydromodification Management Hydromodification Management Control MeasuresControl Measures
Hydrologic source controls Site design measures to
reduce imperviousness
LID treatment measures
Detention basinDetention basin Flow duration controls
Pond, detention basin, tank or vault
Specialized outlet to control rate and duration of flow
![Page 40: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/40.jpg)
Municipal Regional Permit (MRPMunicipal Regional Permit (MRP)) Provision C.3 OverviewProvision C.3 Overview
Requires post-construction controls for new development and redevelopment projects
MRP effective date was 12/1/09
Major new MRP requirements took effect 12/1/11:
– LID Requirements
– Threshold dropped to 5,000 SF impervious surface for some projects
![Page 41: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/41.jpg)
Test Your Knowledge!Test Your Knowledge!
What are source control measures?
Permanent design features or post-construction operational activities that reduce pollutant sources
What size projects need to include appropriate source control measures?
You must encourage the implementation of appropriate source controls in all projects regardless of size.
You must require appropriate source controls in projects that are subject to stormwater treatment requirements.
![Page 42: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/42.jpg)
Test Your Knowledge!Test Your Knowledge! What are site design measures?
Permanent design features that reduce impervious surfaces, disconnect impervious surfaces from the storm drain system, or preserve/protect natural features.
![Page 43: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/43.jpg)
Test Your Knowledge!Test Your Knowledge! What size projects need to include
appropriate site design measures?
You must encourage the implementation of appropriate site design measures in all projects regardless of size.
You must require single family homes (>2,500 sq. ft. of impervious area) and small projects (2,500-10,000 sq. ft. of impervious area) to implement one of six site design measures.
You must require appropriate site design measures in projects that are subject to stormwater treatment requirements.
![Page 44: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/44.jpg)
Test Your Knowledge!Test Your Knowledge! What are stormwater treatment measures?
Permanent engineered systems that remove pollutants from stormwater.
Which projects must include stormwater treatment measures? Projects that create and/or replace 10,000 sq. ft. or more
of impervious surface (stand-alone home exempt) Projects in the following categories that create and/or
replace 5,000 sq. ft. or more of impervious surface: – Restaurants,
– Retail gasoline outlets,
– Auto service facilities,
– Parking lots (stand-alone or part of other use)
![Page 45: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/45.jpg)
Test Your Knowledge!Test Your Knowledge! Which road and trail projects must include
stormwater treatment measures? Road and trail projects that create and/or replace
10,000 sq. ft. of contiguous impervious surface
– New roads, and sidewalks and bike lanes built as part of new roads
– Widening of existing roads with traffic lane(s)
– Trails >10 ft wide or < 50 ft from creek bank
![Page 46: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/46.jpg)
Test Your Knowledge!Test Your Knowledge! What types of treatment measures must be used at
almost all Regulated Projects?
LID treatment measures
What kinds of projects can install high rate media filters and tree well filters? Special Projects only
![Page 47: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/47.jpg)
Test Your Knowledge!Test Your Knowledge! What is the goal of hydromodification
management? Match post-project runoff rates, volumes and
durations to the pre-project condition for a range of storms.
Which projects must implement hydromodification management? Projects that:
– Create and/or replace 1 acre or more of impervious surface, and
– Increase impervious surface over pre-project condition, and
– Drain to creeks susceptible to erosion.
![Page 48: Basic Training: Stormwater Controls for Development Projects](https://reader036.vdocuments.mx/reader036/viewer/2022062422/56813532550346895d9c9874/html5/thumbnails/48.jpg)
For More Information:For More Information: SMCWPPP C.3 Technical Guidance
www.flowstobay.org (Click on “Municipalities”, then “New Development”)
Municipal Regional Permitand associated documents
http://www.waterboards.ca.gov/sanfranciscobay/water_issues/programs/stormwater/Municipal/index.shtml (Google “SF Bay Municipal Regional Permit”)