Barriers to Distributed Renewable Energy
John Farrell, Senior Researcher
efficient | economical | equitable
![Page 2: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/2.jpg)
Total Installed Capacity
4,034 MW
47,000 MW
Together = 3.3% of U.S. sales
![Page 3: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/3.jpg)
How Much Community-Owned?
4,034 MW
47,000 MW
5%? 10%? 25%?
![Page 4: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/4.jpg)
1%
Community-Owned
just
![Page 5: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/5.jpg)
Community-Owned = distributed2
(distributed generation) x (distributed ownership)
Why Community-Owned?
![Page 6: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/6.jpg)
Barriers to Distributed Generation
• Tradition
• Capital
• Cash Flow
• Legal
• Utility
![Page 7: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/7.jpg)
Centralized Power
Utility Perspective
Transmission network
Distribution network
House
Storage
Local CHP plant
Commercialbuilding
Factory
Storage
Storage
Storage
Solar PV power plant
Windpowerplant
House with domestic CHP
Clean, local power
RealityTradition
![Page 8: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/8.jpg)
Barriers to Distributed Generation
• Tradition
• Capital
• Cash Flow
• Legal
• Utility
![Page 9: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/9.jpg)
Capital
How can they...
...buy this?
![Page 10: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/10.jpg)
Rules for Raising Capital
• Full registration
• Regulation D
• Regulation A
• Intra-State
• Private
![Page 11: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/11.jpg)
Type of registration
Upfront Cost
Compliance Costs Restrictions
Full SEC $100,000-125,000 Over $400,000/yr None
Regulation D $30,000-50,000 $10,000/yr Accredited investors;
prior relationship
Regulation A $50,000-75,000 $10,000/yr $5 million offering
Intra-State $50,000-75,000 $10,000/yr (MN) In-state only
Private Minimal Minimal Prior relationship; no advertising
![Page 12: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/12.jpg)
Type of registration
Upfront Cost
Compliance Costs Restrictions
Full SEC $100,000-125,000 Over $400,000/yr None
Regulation D $30,000-50,000 $10,000/yr Accredited investors;
prior relationship
Regulation A $50,000-75,000 $10,000/yr $5 million offering
Intra-State $50,000-75,000 $10,000/yr (MN) In-state only
Private Minimal Minimal Prior relationship; no advertising
9%3%
Project CostUpfrontCompliance
![Page 13: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/13.jpg)
Type of registration
Upfront Cost
Compliance Costs Restrictions
Full SEC $100,000-125,000 Over $400,000/yr None
Regulation D $30,000-50,000 $10,000/yr Accredited investors;
prior relationship
Regulation A $50,000-75,000 $10,000/yr $5 million offering
Intra-State $50,000-75,000 $10,000/yr (MN) In-state only
Private Minimal Minimal Prior relationship; no advertising
59% 19%
Project CostUpfrontCompliance Too costly for small projects
![Page 14: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/14.jpg)
Type of registration
Upfront Cost
Compliance Costs Restrictions
Full SEC $100,000-125,000 Over $400,000/yr None
Regulation D $30,000-50,000 $10,000/yr
Accredited investors; prior relationship w/
investors
Regulation A $50,000-75,000 $10,000/yr $5 million offering
Intra-State $50,000-75,000 $10,000/yr (MN) In-state only
Private Minimal Minimal Prior relationship; no advertising
![Page 15: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/15.jpg)
Type of registration
Upfront Cost
Compliance Costs Restrictions
Full SEC $100,000-125,000 Over $400,000/yr None
Regulation D $30,000-50,000 $10,000/yr
Accredited investors; prior
relationship
Regulation A $50,000-75,000 $10,000/yr $5 million offering
Intra-State $50,000-75,000 $10,000/yr (MN) In-state only
Private Minimal Minimal Prior relationship; no advertising
![Page 16: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/16.jpg)
Type of registration
Upfront Cost
Compliance Costs Restrictions
Full SEC $100,000-125,000 Over $400,000/yr None
Regulation D $30,000-50,000 $10,000/yr
Accredited investors; prior
relationship
Regulation A $50,000-75,000 $10,000/yr $5 million offering
Intra-State $50,000-75,000 $10,000/yr (MN) In-state only
Private Minimal Minimal Prior relationship; no advertising
≤ 2 turbines
![Page 17: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/17.jpg)
Type of registration
Upfront Cost
Compliance Costs Restrictions
Full SEC $100,000-125,000 Over $400,000/yr None
Regulation D $30,000-50,000 $10,000/yr
Accredited investors; prior
relationship
Regulation A $50,000-75,000 $10,000/yr $5 million offering
Intra-State $50,000-75,000 $10,000/yr (MN) In-state only
Private Minimal Minimal Prior relationship; no advertising
5%27%
Project CostUpfrontCompliance
Still costly for small projects
![Page 18: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/18.jpg)
Type of registration
Upfront Cost
Compliance Costs Restrictions
Full SEC $100,000-125,000 Over $400,000/yr None
Regulation D $30,000-50,000 $10,000/yr
Accredited investors; prior
relationship
Regulation A $50,000-75,000 $10,000/yr $5 million offering
Intra-State $50,000-75,000 $10,000/yr (MN) In-state only
Private Minimal Minimal Prior relationship; no advertising
![Page 19: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/19.jpg)
Type of registration
Upfront Cost
Compliance Costs Restrictions
Full SEC $100,000-125,000 Over $400,000/yr None
Regulation D $30,000-50,000 $10,000/yr
Accredited investors; prior
relationship
Regulation A $50,000-75,000 $10,000/yr $5 million offering
Intra-State $50,000-75,000 $10,000/yr (MN) In-state only
Private Minimal Minimal Prior relationship; no advertising
5%27%
Project CostUpfrontCompliance
Still costly for small projects
![Page 20: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/20.jpg)
Type of registration
Upfront Cost
Compliance Costs Restrictions
Full SEC $100,000-125,000 Over $400,000/yr None
Regulation D $30,000-50,000 $10,000/yr
Accredited investors; prior
relationship
Regulation A $50,000-75,000 $10,000/yr $5 million offering
Intra-State $50,000-75,000 $10,000/yr (MN) In-state only
Private Minimal Minimal Prior relationship; no advertising
![Page 21: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/21.jpg)
Capital is HARD
• Full = EXPENSIVE
• Regulation D = RICH FOLKS
• Regulation A = SIZE/COST
• Intra-State = COSTLY
• Private = LIMITED
![Page 22: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/22.jpg)
Hope: Crowdfunding• 2012 federal JOBS Act
• $1 million limit
• Minimal compliance
• Lower upfront cost: $10-15k
![Page 23: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/23.jpg)
Private Placement
Example
![Page 24: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/24.jpg)
Barriers to Distributed Generation
• Tradition
• Capital
• Cash Flow
• Legal
• Utility
![Page 25: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/25.jpg)
complex...
![Page 26: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/26.jpg)
0% 25% 50% 75% 100%
20%25%25%30%
Minnesota Commercial Solar Project Cash Flow
Federal tax credit DepreciationState rebate Net metering
![Page 27: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/27.jpg)
0% 25% 50% 75% 100%
100%
Germany/Ontario Commercial Solar Project Cash Flow
Feed-In Tariff
![Page 28: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/28.jpg)
Feed-In Tariff
• Long-term, fixed price contract
• Guaranteed, simple grid connection
• Price sufficient for small profit
![Page 29: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/29.jpg)
Risk
Policy Shapes CostR
etur
n
Germany
U.S.
Ontario
Low
Hig
h
Low High
![Page 30: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/30.jpg)
Policy Shapes Participation
80%
of German solar is on small rooftops
![Page 31: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/31.jpg)
U.S. Exception
University Park community solar
![Page 32: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/32.jpg)
Barriers to Distributed Generation
• Tradition
• Capital
• Cash Flow
• Legal
• Utility
![Page 33: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/33.jpg)
Which Makes Sense for Community Solar?
A.Nonprofit
B.City
C. County
D.Cooperative
E.All of the Above
![Page 34: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/34.jpg)
Which Makes Sense for Community Solar?
A.Nonprofit
B.City
C. County
D.Cooperative
E.All of the Above
![Page 35: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/35.jpg)
Which One Works?
A.Nonprofit
B.City
C. County
D.Cooperative
E.All of the Above
![Page 36: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/36.jpg)
Which One Works?
A.Nonprofit
B.City
C. County
D.Cooperative
E.All of the Above
F.None of the Above
![Page 37: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/37.jpg)
0% 25% 50% 75% 100%
20%25%25%15%15%
Minnesota Nonprofit Solar Project Cash Flow
Federal tax credit MiddlemanDepreciation State rebateNet metering
![Page 38: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/38.jpg)
Exception
Group purchase, no legal entity
Mt. Pleasant Solar Cooperative
![Page 39: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/39.jpg)
ExceptionSouth Dakota Wind Partners
7 turbines, 600 owners, 1 expired cash grant
![Page 40: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/40.jpg)
Barriers to Distributed Generation
• Tradition
• Capital
• Cash Flow
• Legal
• Utility
![Page 41: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/41.jpg)
True or false?
In 2012, most utilities measure how much electricity is used during peak periods and during minimum use periods on their own grid.
![Page 42: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/42.jpg)
True or false?
In 2012, most utilities measure how much electricity is used during peak periods and during minimum use periods on their own grid.
FALSE
![Page 43: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/43.jpg)
≤?
1. A Limit on Local Power GenerationUtilities always want local power generation to be less than local minimum electricity demand so that electricity will not flow out of neighborhoods and back onto the grid.*
2. A Guesstimate of Minimum Demand Whoops! Utilities assume minimum demand is about 30% of peak demand, because they don’t measure minimum demand.
3. An Arbitrary Safety MarginUtilities take this 30% threshold and divide by 2 to get a 15% cap on local solar.
*Also addressed with 2-way electrical equipment
How Local Solar Gets Capped
15%
Peak use
“Minimum”(30%)
÷2
Percent of peak power allowed from local solar
Default cap of
÷2
![Page 44: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/44.jpg)
1. A Daytime MinimumHow much solar power is produced at 4 AM? None. But that’s the time of day utilities used for their minimum demand calculation.
Hawaii solar advocates negotiated a change: to estimate minimum demand when the sun is up (Sundays at noon).
Even though utilities maintain the arbitrary “division by 2” safety margin, this change could allow nearly twice as much local solar on the grid.
How States Can Raise the Cap (Hawaii)
“Daytime min.”
÷2
~25%
Hawaii’s Update (2011)Hawaii estimates the minimum demand during daytime.
Cap is raised toPercent of peak power allowed from local solar
![Page 45: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/45.jpg)
Daytime minimum
~50%Cap is raised toPercent of peak power allowed from local solar
÷
California’s Update (2012)Measured daytime demand
No “division by 2”
How States Can Raise the Cap (California)
1. A Measured Daytime MinimumUtilities must actually measure the minimum demand on a power line between 9 AM and 4 PM and no longer use peak demand as a proxy.
2. No “Division by 2”Utilities can’t arbitrarily divide the cap by 2, now that the power line capacity is actually measured.
The result could nearly triple the original 15% cap on local solar power.
2
![Page 46: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/46.jpg)
LEGENDno statutory net metering limitaggregate limit higher than 1% of peak demandaggregate limit 1% of peak demand or less
Utilities also Want Limits on Total Net Metering
Lets customers pay “net” of own use and own generation
![Page 47: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/47.jpg)
Exception
Replicable community solar!
![Page 48: Barriers to Distributed Renewable Energy](https://reader030.vdocuments.mx/reader030/viewer/2022020410/58a36b0c1a28aba4138b61c5/html5/thumbnails/48.jpg)
Distributed Generation
• Tradition• Capital• Cash Flow• Legal• Utility
• Mt. Pleasant Solar Coop• Clean Energy Collective• Maryland Solar LLC• SD Wind Partners
Learn more at EnergySelfReliantStates.org
Barriers Exceptions