AMS-02 tracker mechanicsstatus of assembly and integration
Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field sensors - Shells closing and flanges mounting - ToolingPreparations for pre-integration: - Test of evaporators (cooling loops) integration + tools
- Pre-assembly of outer planes with inner tracker + tools - Cabling issues studies - Jigs for transport and storage at CERN
- Tracker configuration for LBBX (TAS) mounting - Integration sequence - Issues to be solved
Divic RAPIN, UniGe AMS TIM July 2007
![Page 2: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/2.jpg)
General view of Silicon tracker• 5 planes, 8 layers
• Plane 1, layer 1• Plane 2, layers 2&3• Plane 3, layers 4&5• Plane 4, layers 6&7• Plane 5, layer 8
• 192 ladder modules• 1024 electronic channel/module
200’000 channels
Planes are supported by shells and conical flanges. (not shown)
![Page 3: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/3.jpg)
Ladder Assembly (Perugia-Geneva)
• ASSEMBLY• ~ 210 ladders build
• PHASE 2 hybrid box & legs gluing
• EMI SHIELDING ( kapton foil wrapping)
• Full test at each step with RA source and noise control
![Page 4: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/4.jpg)
Installation of ladders on support planes (UniGe clean room)
Plane 3 being stored (under Nitrogen)
Details of fixation on both sides
![Page 5: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/5.jpg)
Assembly of the inner tracker in the Durga jig
• Set-up for storage & insertion into the magnet.
• Cables must be installed before the supporting shells and extra length must be attached to temporary supports.
![Page 6: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/6.jpg)
Tracker with cables but without closing and supporting shells
Temporary storage of cables
384 flat cables from ladders to electronics
![Page 7: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/7.jpg)
Temperature (Dallas) and B-field sensors have been tested before closing of the inner tracker (A.Lebedev and U.Roeser)
B-field sensor
T-sensors
![Page 8: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/8.jpg)
Closing inner tracker and disconnection from Durga jig
![Page 9: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/9.jpg)
Removing inner tracker from Durga assembly jig
![Page 10: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/10.jpg)
Complete installation and assembly jigOuter ring assembly
and installation jig
Inner ring assembly and installation jig
Cooling loops are fragile and not self supporting. They need to be kept in jigs for fabrication, storage, transport and assembly
Tests of integration of cooling loops on outer plane (1) and on inner tracker (top)
![Page 11: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/11.jpg)
Outer cooling loop on plane 1
Jigs and support pieces were developed in order to manipulate the plane and to install cables and cooling loop at the same time
![Page 12: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/12.jpg)
Test integration of the inner cooling loop
![Page 13: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/13.jpg)
Test integration of the inner cooling loop
Real life will be less easy due to dimensions of vacuum tank
![Page 14: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/14.jpg)
Test integration of the inner cooling
loop
![Page 15: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/15.jpg)
Test integration of the inner cooling loop
It fits perfectly
![Page 16: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/16.jpg)
Test integration of outer plane on inner tracker (with loops)
Jig for cable storage and crane manipulation of outer planes (compatible with loop)
![Page 17: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/17.jpg)
Test integration of outer plane on inner tracker (with loops)
Guiding spacers to prevent damaging contacts between ladders and conical flange during approach of the outer plane.
Device allowing safe and precise approach of the outer plane for the last 25 mm.
![Page 18: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/18.jpg)
Study of cabling related issues
Star tracker support region
Tracker feet regions
![Page 19: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/19.jpg)
Inner tracker support for storage and transportation (AMS01 test beam frame)
The present state of the tracker (no loops, both outer planes mounted) is convenient for LBBX (TAS) adjustment and installation. (not for transportation)
![Page 20: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/20.jpg)
TRACKER (MECHANICAL) INTEGRATION SEQUENCE
(simplified)
- Sequence dictated by topology
- Up or upside down position not specified hereafter
![Page 21: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/21.jpg)
Start: four separate boxes
Two outer planes with:- cables, loop, LBBX+fibers
Inner tracker with:- cables, upper inner loop
Lower inner loop
![Page 22: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/22.jpg)
Step 1: insertion (lower flange removed)
![Page 23: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/23.jpg)
Step 2: four upper feet installation
Next: prepare lower conical flange
![Page 24: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/24.jpg)
Step 3: lower conical flange installation
![Page 25: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/25.jpg)
Step 4: four lower feet installation
After this operation, tracker and vacuum case can be rotated
![Page 26: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/26.jpg)
Step 5: unfold and secure cables (and remove supports)
Prepare lower inner loop
From this step, TOP and BOTTOM operations are independent
![Page 27: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/27.jpg)
Step 6: Install lower inner loop
Next: outer planes
![Page 28: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/28.jpg)
Step 6: Install outer plane (connect loops)
![Page 29: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/29.jpg)
Step 7: unfold and secure cables (and remove supports)
Connect to crates
![Page 30: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/30.jpg)
Next operations and open issues
• Cooling loop modification + new connectors (Splinter meeting this TIM)
• VC metrology (Splinter meeting this TIM)
• Balcony design (already started by F.Cadoux) and production (TBD).
• Detailed cable routing (in progress)
• LBBX installation (WW during August).
• Containers for outer planes and covers for inner tracker frame (UniGe)
• Outer planes: Installation of cooling loop, cables and test (UneGe
• Light tightness (UniGe)
• Revision and completion of detailed procedures (E.P. and D.R.)
•
•
![Page 31: AMS-02 tracker mechanics status of assembly and integration](https://reader035.vdocuments.mx/reader035/viewer/2022062408/56814385550346895db00359/html5/thumbnails/31.jpg)
Near future integration operations at UniGe•Design of storage and transport jigs for inner tracker and outer planes (re-use of Alu frame used for AMS01 beam test) (in progress)
•Design and construction of outer plane installation jig.
•Supporting shells installation and remove inner tracker from Durga.
•Pre-assembly of inner evaporator on inner tracker (check mountability).
•Pre-assembly of outer planes (check mountability) on inner tracker.
•Time requested by TAS for laser beam alignment/installation.
•Orbital welding of new connectors is needed for upper/lower inner/outer evaporators (on critical path)
Conclusion of the April 2007 TIM presentation of D.R.