Accelerator Operation Summary
Calendar Week # 03
NuMI Weekly Integrated Intensity 2.74 E18 protons Beam Hours To NuMI 41.3 hours BNB Weekly Integrated Intensity 0.0 E14 protonsBeam Hours To BNB 0.0 hours NMuon Weekly Integrated Intensity 9.53 E15 protonsBeam Hours To NMuon 49.7 hours
MTest Weekly Integrated Intensity 9.21 E13 protonsBeam Hours To MTest 10.0 hours
From : January 12, 2015 (0000 hours)To: January 19, 2015 (0000 hours)
![Page 4: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/4.jpg)
![Page 5: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/5.jpg)
Accelerator Operation Summary
Calendar Week # 04
NuMI Weekly Integrated Intensity 1.24 E18 protons Beam Hours To NuMI 27.6 hours
BNB Weekly Integrated Intensity 0.0 E14 protonsBeam Hours To BNB 0.0 hours NMuon Weekly Integrated Intensity 6.62 E15 protonsBeam Hours To NMuon 21.9 hours
MTest Weekly Integrated Intensity 2.16 E13 protonsBeam Hours To MTest 2.9 hours
From : January 19, 2015 (0000 hours)To: January 26, 2015 (0000 hours)
![Page 6: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/6.jpg)
![Page 7: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/7.jpg)
![Page 8: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/8.jpg)
![Page 9: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/9.jpg)
![Page 10: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/10.jpg)
![Page 11: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/11.jpg)
![Page 12: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/12.jpg)
![Page 13: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/13.jpg)
![Page 14: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/14.jpg)
![Page 15: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/15.jpg)
![Page 16: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/16.jpg)
Are there more like this?
• We have seen 2 of 36– One bad– One good
• Can they be inspected?– Fire foam makes it difficult for a
visual inspection of the pvc coupler• Trying to look for other indicators
– Turn on order– Ground current
• What we learned– We understand the problem, process
and how to recover more quickly
![Page 17: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/17.jpg)
Complex Status– Accelerators
• Recovering from MI ground fault• Monitoring systems during Kautz Road SubStation
test• Investigating issues, understanding, planning• No plans to switch back to Master SubStation
– Would like to see slip stacking – Maybe in February 2015
– NuMI• Beam to experiments
– Switchyard• Beam to experiments
– SeaQuest• Beam to experiments
– Meson Test• Intermittent users
– Meson Center• No users
– BNB• Horn replacement
![Page 18: All Experimenters’ Meeting January 26, 2015. Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam](https://reader035.vdocuments.mx/reader035/viewer/2022062412/5a4d1ad97f8b9ab059974044/html5/thumbnails/18.jpg)
Schedules and Links:• Schedule can be accessed from the
Operations Home Page– - Schedules -> Operations Schedule
• Direct link to schedule– - http://www-ad.fnal.gov/ops/schedule.html