![Page 1: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/1.jpg)
Agile In Action
Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project
@PMIGLC@MPUG@LewisCindy
7:30-8:30 pm December 12, 2016
![Page 2: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/2.jpg)
This was MPUG Affiliate night
For more details visit www.mpug.com or visit our table at the
PMIGLC Spring Symposium in April
Note: Cindy is on the MPUG Detroit board and is happy to answer any questions as well.
Note 2: MPUG offers regular member discounts. Ask to get added to the mailing list for more details.
Added Slide
![Page 3: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/3.jpg)
Connect with me: linkedin.com/in/cindylewis2
4pillarsofsuccess.com(to learn about my services)
616.446.8569 mobile/text@LewisCindy
Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project
![Page 4: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/4.jpg)
Matching Exercise
Creating User Stories
Planning Poker
Risk/Value Quadrant Mapping
Advanced Burndown
Interpretation
Interactive Agile Exercises
![Page 5: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/5.jpg)
Artprize Video with 10,000 Chinese Lanterns
Youtube has lots of videos
![Page 6: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/6.jpg)
Introduction to Agile
@PMIGLC@MPUG@LewisCindy
![Page 7: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/7.jpg)
Agile Pronunciation
Long a – aaagil
Long i - agiiiile
![Page 8: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/8.jpg)
“
”
One division of a non-profit book printing
company doubled their output in 90
days doing all agile
approaches
![Page 9: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/9.jpg)
87% see improvement
with Agile
![Page 10: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/10.jpg)
Increased Team Morale/Motivation
Better Delivery Predictability
Enhanced Quality
Faster Time to Market
Reduced Project Risk
![Page 11: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/11.jpg)
#1 Reason for failure is –
Lack of experience with Agile Methods
![Page 12: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/12.jpg)
Table Exercise
![Page 13: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/13.jpg)
Agile
![Page 14: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/14.jpg)
Agile Approach Traditional Scheduling
individuals and interactions processes and tools
estimating by size - story points estimating by task - duration/work
user stories phases & detailed task list
progress is measured by features delivered in an iteration
progress is measured by tasks accomplished in a specific timeframe
decisions made by team or customerdecisions made by team or project manager
![Page 15: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/15.jpg)
Agile Approach Traditional Schedulingcustomer is flexible and is ready to give up features when needed
customer may or may not be flexible with deliverables
end date is always presented as a range end date is clearly defined
Sponsor or customer is shown results as frequently as possible, sometimes after each iteration
Sponsor or customer is shown results at specific phase ending points
high-level tasks are created by the team and individuals define the specific tasks they will be working on
defined tasks are assigned to individuals
![Page 16: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/16.jpg)
Creating User Stories
@PMIGLC@MPUG@LewisCindy
![Page 17: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/17.jpg)
User Stories
Who (often called role) and what
Why (optional)
Easy to understand
Short
Indicates measures of success
![Page 18: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/18.jpg)
User Stories Examples (1 of 2)
• As a smart phone user, I want to be able to install the application.
• As a smart phone user, I want to be able to uninstall the application.
• As a business owner, I want to be able to accept credit cards.
• As a business owner, I want to be able to receive confidential customer feedback.
![Page 19: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/19.jpg)
User Stories Examples (2 of 2)
• As a dog owner, I want the dog to notify me when it needs to go out.
• As a dog owner, I want the dog to sit when asked.
• As a dog owner, I don’t want the dog to bite humans.
• As a dog owner, I want the dog to come when called.
![Page 20: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/20.jpg)
Table Exercise
![Page 21: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/21.jpg)
Planning Poker
@PMIGLC@MPUG@LewisCindy
![Page 22: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/22.jpg)
Story Points
Story points are a measure of size
Is one story larger or smaller than another
![Page 23: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/23.jpg)
Review Your User Stories
As a dog owner, I want the dog to notify me when it needs to go out
As a dog owner, I want the dog to sit when asked
As a dog owner, I don’t want the dog to bite humans
As a dog owner, I want the dog to come when called
![Page 24: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/24.jpg)
Planning Poker
1. Create a scale and generate voting cards for each member
2. One person in the group describes a story (Moderator)
3. Group may ask questions about the story
4. Group votes
5. High and low votes explain their reasoning
6. Group revotes and repeats process above if wide range
7. Moderator eventually helps group settle on a number
![Page 25: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/25.jpg)
Table Exercise
![Page 26: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/26.jpg)
Risk/Value Quadrant Mapping
@PMIGLC@MPUG@LewisCindy
![Page 27: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/27.jpg)
4 Quadrants of Risk/Value
High Value
![Page 28: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/28.jpg)
Kano’s Model of Customer Satisfaction
![Page 29: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/29.jpg)
Table Exercise
![Page 30: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/30.jpg)
Advanced Burndown Interpretation
@PMIGLC@MPUG@LewisCindy
![Page 31: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/31.jpg)
0
5
10
15
20
25
30
35
40
45
1 2 3 4
Story Points Completed
Iterations
![Page 32: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/32.jpg)
40
20
10
00
5
10
15
20
25
30
35
40
45
1 2 3 4 Iterations
Revised estimate indicates more work
New work/scope added
![Page 33: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/33.jpg)
Table Exercise
![Page 34: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/34.jpg)
100
80
90
70
40
30
100
20
40
60
80
100
120
1 2 3 4 5 6 7
Table Exercise
![Page 35: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/35.jpg)
Agile Estimating and Planning by Mike Cohn
Read the case study first!!
Rated 4.6/5.0 on Amazon
Preferred text for PM college students
![Page 36: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/36.jpg)
Scrum Template Example from MPUG
![Page 37: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/37.jpg)
Burndown Example from MS Project
![Page 38: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/38.jpg)
https://blogs.office.com/2015/09/22/introducing-office-365-planner/
Planner Example from Office 365
![Page 39: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/39.jpg)
Planner Example from Office 365
![Page 40: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/40.jpg)
Agile
![Page 41: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/41.jpg)
Agile estimates by size with user stories and story points
Customer and team are flexible in the agile approach
Features are more important than tasks in agile
Key Concepts
![Page 42: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/42.jpg)
Get Started in Agile!
Start talking Agile
Try just 1 agile technique mentioned today
Seek out more information
![Page 43: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/43.jpg)
What is Agile Project Management article by Cindy Lewishttp://www.mpug.com/what-is-agile-project-management/
or
http://tinyurl.com/jbd7hyp
www.mpug.com
An example of a free resource
![Page 44: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/44.jpg)
Cindy’s webinar was awarded a top 99 webinar by MPUG and it is a virtual delivery of this presentation.
http://www.mpug.com/webnlearn-recordings/key-agile-concepts-illustrated
![Page 45: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/45.jpg)
Connect with me: linkedin.com/in/cindylewis2
4pillarsofsuccess.com(to learn about my services)
616.446.8569 mobile/text@LewisCindy
Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project
![Page 46: Agile In Action - PMIGLC · Agile In Action Led by: Cindy Lewis, PMP, PMI-SP, MOS, MCTS, MS, MCT, MVP-Project @PMIGLC @MPUG @LewisCindy 7:30-8:30 pm December 12, 2016. This was MPUG](https://reader034.vdocuments.mx/reader034/viewer/2022042316/5f055c3c7e708231d4129426/html5/thumbnails/46.jpg)