McKenney’s overcame obstacles to install a process chiller and industrial package cooling unit

at a packaging manufacturing plant.

THE CHALLENGEThe manufacturer’s cooling system was no longer reliable. At the worksite, there was not reasonable access to the plant’s rooftop to install the new air handling unit (AHU) and chiller on the side of the building. Also, careful

coordination was needed to install the package unit and chiller simultaneously—with the plant’s production levels dependent on chilled water.

THE SOLUTIONTo gain access to the rooftop, the McKenney’s team coordinated with a neighboring facility and a local crane company to position a crane on the neighboring property. To install the chiller, McKenney’s met the customer’s last-minute request to reconfigure the piping necessary

for other long-term maintenance and opera-tion goals. Then, the team shut down the system during a short 36-hour window to quickly disconnect and reconnect piping without significantly disrupting production.

THE RESULTSBy leveraging its design/build expertise and coordination skills, McKenney’s completed the installation on time and under budget while exceeding the customer’s expectations.

Addressing Unique Job Site DemandsPROJECT NAME

� Industrial Chiller and Air Handling Change-Out

PROJECT LOCATION

� Charlotte, North Carolina

PROJECT TEAM

� Owner: Packaging Industry Manufacturer

� Contractor: McKenney’s, Inc.

SPECIALIZATIONS

Design/Build

MARKETS

� Industrial

The content of this document is not intended as an endorsement.

www.mckenneys.com© 2015 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A.

McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners.

404-622-5000 [email protected] 1056 Moreland Industrial Boulevard Atlanta, Georgia 30316

704-357-1200 [email protected]

3601 Performance Road Charlotte, North Carolina 28214

Top Related