• Placed roof deck grid 7-1 on Wednesday 12.16.09.
• Removing reshores on level 2 east and west wings.
• Wrecking forms and pans on roof level grids 16-11.5 and reshoring.
• Completed slab on carton forms at Visitor’s Center.
• Pans complete for Visitor’s Center second floor scheduled to pour Tuesday.
• Reinforcing on going at Visitor’s Center second floor.
• West stair (stair #1) at 60% complete at HQ building.
• Continue framing exterior and interior walls on the 1st floor @ HQ.
• Second floor ductwork delivered and installation ongoing.
• Cast iron tested and passed in crawlspace of HQ.
• Energy Recovery Units delivered to the jobsite.
• Completed domestic cold water riser through third floor.
• Temporary power energized at building.
• Thermal piping installation ongoing
Texas A&M University Agriculture Headquarters
We e k l y R e p o r t : 1 2 / 1 4 / 0 9 - 1 2 / 1 8 / 0 9
ERU Delivery Visitor’s Center First Floor West Overhead
Southeast Elevation North Elevation First Floor West Overhead