04-May-11 / 1
Information You Can Use: Successful Handoffs of Information
Michael Kenig, Holder Construction, COAA COBie Case Study Manager
Sam Westbrook, Senior Manager, information exchange services, Holder Construction
Draft
Today:
1. Review of COBie Case Study and “What is COBie?”
2. COAA COBie Case Study
3. Challenges/ Lessons/ Discussion
04-May-11 / 3
COBie: overview
presented by:
Bill East, PhD, PE, F.ASCEEngineer Research and Development Center, Champaign, IL
Baltimore – May 4, 2011
04-May-11 / 4
04-May-11 / 5
SpacesScheduled
EquipmentWarranties and Spares
Approved Submittals
Layout DrawingsPerformance
Standards
COBieSpecifiers’ Propertiesinformation exchange
(SPie)
Equipment Layoutinformation exchange
(ELie)
04-May-11 / 6
“this all sounds great, now prove it…”
04-May-11 / 7
COBie case study: approach
presented by:
Bill East, PhD, PE, F.ASCEEngineer Research and Development Center, Champaign, IL
04-May-11 / 8
new process
plan
do
check
act
clearly stated, measurable goals
partnering, contract agreements document and
compare actual
lessons learned,recommendations
04-May-11 / 9
implementation plan
public commitmentMay 2011 – IntroductionNov 2011 – Update
public distributionprocesses and metricsupdated contractspoints of contact
“the good, the bad, and the ugly”
YouTube:COBie CollegeHighly recommend
Class 1, Overview- Part 3!
COBieAir Handler Unit COBie standard AHU
What I thought…(COBie is a spreadsheet):
Design/Manufacturer
Data
FM System
What is COBie?A concept or idea?A process? (as in the “COBie process”?)
A spreadsheet? (as in “COBie spreadsheet”?)
A specification? (as in “COBie specification”?)
A data format? (as in “COBie data”?)
A model? (as in “COBie model”?)
A solution? (to the “COBie problem statement”?)
Mike Kenig
Gathering the data:• Job crawl• Manually gather as
it comes in• File Transfer• Automatic Transfer
– IFC (spff or XML)
Transferring the data:• Manually enter it• Import file
– Custom interface– Spreadsheet
• Automatic Transfer– IFC (spff or XML)
The Problem
Information Exchange: Manual
Design
Manufacturing Construction
Operation
Data is gathered through manual input
The Solution
Information Exchange: Example Spreadsheet
Spreadsheet: human readable REQUIRES
human interaction
Information Exchange:
COBie
Design/ PreconstructionManufacturing
Construction
Operation
Speak the same
language throughout
the process
您好 Hola
Hello
(required)
您好 HolaHello Hello
What is COBie?An idea?A format?A standard?A process?
All of these! The Solution!
COBie Case Study Reflection
Project
Green
04-May-11 / 24
Problem• Manual Process
– Constant Recollection of Data• Lack of Uniformity
– Design Team, Subcontractors, Facility Operator
• Inefficiencies from Commissioning to FM OPS
• Inefficient Access to Documents (Warranty, StartUp, etc…)
04-May-11 / 25
Metrics – Anticipated Effects• Reduction in Data Entry Time
• Accessibility of Documentation Improved
• Time Reduction from Commissioning to full FM Operations
• More Efficient Use of FTE’s = $ Savings
• Improved Data Uniformity and Quality
04-May-11 / 26
Process Before
27
“The Hard Work”Process Change & Implementation
• Engaged 3rd Party - Maximo (MEA) Integration
• Determined Data Attributes to be Collected
• Modified Maximo to Accommodate New Attribute Types Collected
• Assessed COBie Spreadsheet and Aligned with Business Needs
• Planned for Data Collection, Exchange and Quality Assurance
28
“The Hard Work”Process Change & Implementation• Commissioned Subs for Data Collection
• Tested: Import / Collection Processes– Assessed and Modified as Needed– Repeated (Multiple Times)
• Launched Live Data Uploads
New Process
30
Metrics/Results/Conclusions1) Time/Financial Savings
2) Data Quality / Uniformity Improvements
3) Repeatable Process - Efficiencies Generating Savings to be Invested in Future Growth.
Recommendations1) Collect SN’s and Barcode at Dock Receiving
2) Partner with Vendor - SN’s in Advance of Shipment
3) Engage 3rd Party Software Support Early
4) Allow Ample Time for Import Testing
Challenges & Lessons
Discussion?
Information Exchange lessons…• How you “gather” AND how you “transfer”
• Spreadsheet vs. IFC? (may vary by stage)
• More effort initially for future benefit
More Information Exchange lessons…• It’s not about the BIM model (it’s the data!)
• It takes a village… have to have multiple champions (including IT!)
• And, the BIG ONE: Is it all or nothing?!