Presented by: Stephen DeMatteo
Engineering Technology, Construction
ET- 494 Fall 2014
Advisors: Ed Rode Cris Koutsougeras
Residential Fourplex Design
![Page 2: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/2.jpg)
Cost Analysis
Site Survey
Floor Plan and Elevation Drawings
Deliverables
![Page 3: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/3.jpg)
Comparable #14132 Georgia Ave, Kenner La
Townhome/ 2-Plex 900 sq. ft 2 bed 2 bath
Rent Price = $850 $100/sq ft = $180,000 Yearly income = $20,400
Pay off investment = 9 years
Cost Analysis
![Page 4: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/4.jpg)
Comparable #2 4045 Idaho Dr, Kenner La
4-Plex 1,128 sq. ft 2 bed 2 bath
Rent Price = $900 $100/sq ft = $451,200 Yearly income = $43,200
Pay off investment = 10.5 years
Cost Analysis
![Page 5: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/5.jpg)
Comparable #3 2916 Tennessee St, Kenner La
4-Plex 1,100 sq. ft 2 bed 1 full bath 1 half bath
Rent Price = $850 $100/sq ft = $440,000 Yearly income = $40,800
Pay off investment = 11 years
Cost Analysis
![Page 6: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/6.jpg)
My Complex 4-Plex 912 sq. ft 2 bed 1 full bath
Rent Price = $1000 $100/sq ft = $364,800 Yearly income = $48,000
Pay off investment = 7.5 years
For this project each unit will consist of two bedrooms, one bath, a kitchen, living room, and dining room.
Without going into details of the finishes we can expect each unit to see anywhere between $900 to $1050 per month.
This is considering it is new construction and a highly desirable area.
Assessment
![Page 7: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/7.jpg)
Kenner, LA 70065
37th Street and Connecticut Ave
Lot size: 60’x80’
Total of 4 lots
Projected Site
![Page 8: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/8.jpg)
Survey
![Page 9: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/9.jpg)
1st Floor
![Page 10: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/10.jpg)
2nd Floor
![Page 11: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/11.jpg)
Front Elevation
![Page 12: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/12.jpg)
Right Side Elevation
![Page 13: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/13.jpg)
Left Side Elevation
![Page 14: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/14.jpg)
Back Elevation
![Page 15: Presented by: Stephen DeMatteo Engineering Technology, Construction ET- 494 Fall 2014 Advisors: Ed Rode Cris Koutsougeras](https://reader036.vdocuments.mx/reader036/viewer/2022062401/5a4d1b697f8b9ab0599b241d/html5/thumbnails/15.jpg)
February 21st – Finish Foundation Drawings
March 7th – Finish Detailed drawings
March 21st – Finish Electrical Drawings
April 14th – Complete Material Takeoff
April 25th – Finish Construction Schedule
Spring 2014 Semester