technical report templates
TRANSCRIPT
1
Final Report
Phase 2 Cost-Benefit Analysis:
Waste Collection Services in
Pembrokeshire
This document describes the financial, environmental and social costs and benefits associated with the delivery of kerbside waste collection services to households in Pembrokeshire.
Project code: WAL005-000 ISBN: 1-84405-449-7
Research date: August to December 2010 Date: March 2011
Phase 2 Cost-Benefit Analysis: Pembrokeshire 2
WRAP‟s vision is a world without waste, where resources are used sustainably. We work with businesses and individuals to help them reap the benefits of reducing waste, develop sustainable products and use resources in an efficient way. Find out more at www.wrap.org.uk
Written by: Eunomia Research & Consulting, Resource Futures and HCW Consultants
Front cover photography: Recyclable materials
WRAP and Eunomia Research & Consulting believe the content of this report to be correct as at the date of writing. However, factors such as prices, levels of recycled
content and regulatory requirements are subject to change and users of the report should check with their suppliers to confirm the current situation. In addition, care
should be taken in using any of the cost information provided as it is based upon numerous project-specific assumptions (such as scale, location, tender context, etc.).
The report does not claim to be exhaustive, nor does it claim to cover all relevant products and specifications available on the market. While steps have been taken to
ensure accuracy, WRAP cannot accept responsibility or be held liable to any person for any loss or damage arising out of or in connection with this information being
inaccurate, incomplete or misleading. It is the responsibility of the potential user of a material or product to consult with the supplier or manufacturer and ascertain
whether a particular product will satisfy their specific requirements. The listing or featuring of a particular product or company does not constitute an endorsement by
WRAP and WRAP cannot guarantee the performance of individual products or materials. This material is copyrighted. It may be reproduced free of charge subject to the
material being accurate and not used in a misleading context. The source of the material must be identified and the copyright status acknowledged. This material must not
be used to endorse or used to suggest WRAP‟s endorsement of a commercial product or service. For more detail, please refer to WRAP‟s Terms & Conditions on its web
site: www.wrap.org.uk
Phase 2 Cost-Benefit Analysis: Pembrokeshire 3
Contents
1.0 Introduction ................................................................................................................................ 5 2.0 Project aims ................................................................................................................................ 5 3.0 Methodology ............................................................................................................................... 6
3.1 Methodological issues .......................................................................................................... 6 4.0 Current service overview ............................................................................................................ 7 5.0 Financial analysis ........................................................................................................................ 8
5.1 Resources currently employed for kerbside services ............................................................... 8 5.2 Net costs of collection ........................................................................................................ 10
5.2.1 Reported 09/10 actuals ......................................................................................... 10 5.2.2 Authority-specific issues ........................................................................................ 12 5.2.3 Normalised costs – dry recycling service and refuse service ...................................... 13
6.0 Environmental modelling ......................................................................................................... 15 6.1 Material mass flows ........................................................................................................... 15
6.1.1 Generic case study approach to producing mass flows.............................................. 15 6.1.2 Material mass flows for Pembrokeshire ................................................................... 18
6.2 Merchants, intermediate processors and reprocessors .......................................................... 25 6.2.1 Material reprocessed ............................................................................................. 26
6.3 Environmental impacts....................................................................................................... 27 7.0 Social impacts ........................................................................................................................... 29
7.1 Health and safety .............................................................................................................. 31 7.1.1 Summary of data received ..................................................................................... 31
8.0 Combined cost-benefit analysis (CBA) ..................................................................................... 32 8.1 Individual authority results ................................................................................................. 32 8.2 Comparison with other case study authorities ...................................................................... 33
8.2.1 Fate of materials ................................................................................................... 33 8.2.2 Financial costs ...................................................................................................... 37 8.2.3 Environmental performance ................................................................................... 39 8.2.4 Combined financial and environmental performance ................................................. 41 8.2.5 Health and safety .................................................................................................. 42
8.3 Case studies: Overall results and conclusions ....................................................................... 43
Phase 2 Cost-Benefit Analysis: Pembrokeshire 4
Glossary Compositional categories – The classification system used to describe individual materials. The categories used in this project have been derived from various compositional studies. Contraries – Materials that are sent to a MRF, intermediate processor or reprocessor that are not within the scope of materials desired by that part of the recycling chain. At the primary MRF stage, contraries will only comprise non-target materials. However, at subsequent stages of the chain, contraries may include target material that has been miss-sorted into the wrong product stream. Cross-contamination – The miss-sorting of target material into the wrong product stream. Intermediate processors – Facilities that sort material subsequent to the primary MRF process but before the reprocessing stage. MRF – A materials recovery facility (MRF) is a facility at which components of a mixed waste stream, in this case primarily either co-mingled or two-stream collected dry recyclables, are extracted by the use of mechanical and manual separation techniques. Primary MRF(s) – The first sorting location(s) for co-mingled and two-stream systems and the first point of bulking and sorting of plastics and cans for some kerbside sort systems. Process loss – Any material(s) collected from the MRF/ bulking facility within a product stream, but not reprocessed into a new product. This excludes material rejected for residual disposal at the Primary MRF. Process loss rate – The amount of material(s) collected but not reprocessed into a new product, divided by the amount of material collected from the MRF/ bulking facility as a product.
Product/product streams – Materials that are shipped as a specific post MRF/bulking facility product or grade. Each has an assumed composition which includes various components, some of which are specified by onward reprocessors and some of which are contrary items. Some products have the same name as compositional categories such as news and pams. The news and pams product will contain news and pams, but will also contain other compositional categories such as grey and white board. Reject rate – This term is used in this report to describe the material sent for residual disposal from the Primary MRF(s) and is equivalent to the reject rate methodology required for WasteDataFlow reporting. RCV – Rear compaction vehicle. RIDDOR – Reporting of Injuries, Diseases and Dangerous Occurrences Regulations.
Target material – The materials that are targeted by a collection system for ultimate recycling.
Acknowledgements
Particular thanks are due to the six case study authorities for providing data, attending meetings to discuss their
services with us and for showing us around the facilities related to their collection services. This entailed a
significant commitment of officer time and effort for which we are grateful. Thanks also to the Technical Advisory
Group for their input into the project and to the MRF operators and reprocessors for taking the time to speak to
us, providing access to sites for primary research and observation and for providing valuable information to
support our understanding of the flow of materials from the point of collection to the end destination.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 5
1.0 Introduction
This report has been commissioned by WRAP (Waste & Resources Action Programme) on behalf of the Welsh
Assembly Government (Assembly Government) to examine the relative merits of the options that are available to
local authorities in Wales for the collection and sorting of dry recyclable materials. The central aim of the work
has been to inform the long-running debate on the relative performance of co-mingled, two-stream and kerbside
sort dry recycling collection systems in relation to the Assembly Government‟s sustainability objectives. In
addition, it is also important to highlight the underlying context for this work. Towards Zero Waste, the
overarching waste strategy document for Wales, sets a target of 70% for household waste recycling by 2025.
Legislation that will establish statutory targets for local authorities to ensure that this national target is met is
currently being finalised and it is hoped that findings from this study will contribute towards efforts by the
Assembly Government and Welsh local authorities to achieve these objectives.
The project as a whole was split into three key phases as follows:
Phase 1: a desk-based study to evaluate secondary evidence from data and publicly available reports on the
comparative performance of dry recycling collection systems, including in relation to the health and safety
performance of the systems;
Phase 2: primary research to determine the financial and environmental costs of the dry recycling systems in
six case study authorities in Wales which cover the range of kerbside collection systems; and
Phase 3: application of the evidence and understanding obtained in Phase 1 and Phase 2 to model whole
system costs and performance for all Welsh authorities and to draw together the findings of all three Phases.
This report is an output of Phase 2 of the study; it outlines the key costs and benefits associated with the
kerbside collection systems currently employed in Pembrokeshire. It demonstrates the approach to ensuring that
the costs of the service are as comparable to the other case study authorities as possible and identifies any local
factors which influence the costs obtained. It then highlights the findings from the „doorstep to destination‟
analysis of the kerbside collected material, and discusses any potential social impacts that may be taken into
consideration in the comparison of schemes to be undertaken in Phase 3. Fundamentally, it sets the scene as to
our understanding of the financial, environmental and social aspects of the three types of dry recycling system
that need to be taken into consideration when comparing the performance of the systems in Phase 3.
2.0 Project aims
The overall aim of this study is to identify with greater certainty which of the following options for collecting dry
recyclables perform relatively better or worse in relation to the Assembly Government‟s sustainability objectives:
sorting materials at the kerbside;
two-stream collection, with material separated into two streams at the point of collection, with further sorting
at a MRF being required; or
single-stream co-mingled collection of materials, with sorting at a MRF.
Within the study, the specific aims of Phase 2 are to:
undertake a „doorstep to destination‟ analysis of two kerbside sort schemes, two co-mingled schemes and two
two-stream schemes operating in Wales to determine the financial and environmental (including carbon) costs
of each scheme;
develop appropriate metrics to compare the social aspects of the different approaches to collecting
recyclables; and
provide the foundations from which a comparison of the relative performance of each scheme type can
subsequently be made in Phase 3.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 6
3.0 Methodology
The methodology employed in order to determine the financial and environmental costs associated with
Pembrokeshire‟s existing kerbside collection systems is outlined in this section. Further details of the specific
methodology employed for each section are provided later in the report. Fundamentally, the approach for Phase 2
has involved the following key steps:
1 For each of the six case study authorities, the financial outturns were analysed for waste services for 2009/10
or, where there has been a significant change in service in the last 24 months, the most recent budget
figures (2010/11) were analysed instead. In addition, a general overview was obtained of the resources
deployed across the kerbside collection services in each authority. The cost calculations and cost
apportionment methods were subsequently harmonised between services and authorities, to ensure costs
were as directly comparable as possible.
2 Mass flow models were produced for each case study authority to demonstrate the fates determined for
various material streams and to quantify the flow of materials from kerbside collection to their fates. We
started with WasteDataFlow (WDF) tonnages for 2009/10 and then estimated the arisings of different
components for each product stream through applying compositional profiles for each stream to the relevant
WDF tonnage. These profiles were based on our findings from a combination of MRF sampling in Cardiff and
Pembrokeshire and from previous research. The fate for each component was subsequently determined
through interviewing merchants, intermediate processors and reprocessors that deal with the material
collected by each authority.
3 The climate change and air quality impacts associated with the flow of materials from each authority were
subsequently calculated, with an external cost applied (in financial terms) to those impacts, using an
environmental model that employs well-established assumptions regarding environmental impacts.
4 The potential social issues associated with the different collection systems were explored; it was determined
that only qualitative discussion is possible for this aspect of analysis. Health and safety data was obtained
from each case study authority, which will feed into overall conclusions drawn in Phase 3.
5 In order to undertake a cost-benefit analysis (CBA) for each case study authority, the external cost
associated with the environmental impact of each system was then combined together with the financial cost
of operating that service. The overall output of the process provides a total net financial plus environmental
cost of the service, as well as a cost per household and a cost per tonne of dry recycling collected.
3.1 Methodological issues
A study of this kind, which seeks to understand at a detailed level (and to some extent compare) six different
waste collection services in six very different authorities presents a number of obvious challenges. Inevitably, the
methodology that was developed is something of a compromise. In particular, it is worth noting the following:
In order to aid comparison between the schemes, we have used a technique of cost „normalisation‟ (described
in Section 5.2.3) through which adjustments are applied to some costs (or budget figures) reported by the
case study authorities. This is intended to address differences in circumstances (e.g. authorities in receipt of
grant funding not available to other councils) or accounting convention (e.g. the treatment of overhead
recharges or shared resources such as depot) that would otherwise make the financial comparison of the
authorities less meaningful. It is therefore important to bear in mind, when considering the comparisons of
cost presented here, that these are based on normalised costs, not on costs as they have been reported by
the authorities, and as such may not reflect the service costs actually experienced by each authority.
Appendix 4 includes a comparison of normalised and non-normalised information for recycling and refuse
collection costs, which provides an idea of the overall magnitude of the adjustments made. As is the case
across Wales at the moment, significant service changes have been implemented in recent times (or are in
the process of being rolled out) in most of the case study authorities. In addition, some are planning further
change, either in terms of collection system or in working practice. All of these changes are likely to impact on
both cost and performance. To deal with this evolving picture, our general approach has been to adopt data
sources that best reflect the current or near future position, provided these sources were considered to be
adequately reliable. This means, for example, that in most cases we have used 2010/11 budgets as our
primary source of cost information, rather than 2009/10 „actuals‟, as the older data often reflected a service
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 7
profile that has changed significantly. This clearly presents a number of issues regarding comparability. Most
obvious of these relates to the fact that we have used WDF outturns for 2009/10 as our primary waste flow
data source in all cases, due to the consistency, reliability and ready availability of that data. However,
although we have applied adjustments to these to make them more reflective of current practice, in some
cases there are likely to be significant differences between the waste flows we have assumed and the real
outturn for 2010/11. This potential inaccuracy has the most significant implications for the „cost per tonne‟
metrics reported, as in several cases these compare tonnages for 2009/10 with budgeted costs for 2010/11.
Where possible, adjustments have been made to reflect the expected impacts of service changes on tonnage,
but there is clearly uncertainty as to the reliability of these assumptions. Even beyond the service change
issue, other factors (some well understood, some not even identified) impact on waste arisings in different
parts of collection systems. For these reasons, we would view the „cost per household‟ metric as being more
reliable in terms of accuracy than the „cost per tonne‟ metric.
4.0 Current service overview
Pembrokeshire County Council provides an in-house waste service to around 57,822 households, representing a
population of approximately 118,807 people. The highest proportion of households (41%) live in detached
houses, with 26% living in semi-detached and 21% in terrace housing. 7% live in purpose built flats with the
remainder living in shared housing or mobile temporary housing. Total household kerbside arisings of 35,526
tonnes were collected in 2009/10, with total municipal solid waste (MSW) arisings amounting to 69,158 tonnes in
2009/10 across the county. According to the authority this is forecast to reduce by 0.7% in 2010/11, returning to
0% growth in future years.
The service configuration currently operated by Pembrokeshire is described as follows:
Dry recycling; all households in Pembrokeshire receive a weekly collection of dry recyclables, and are asked
to present their recycling in orange coloured bags which are provided by the council. Residents are able to
recycle newspaper, magazines and office paper, cardboard, cans and aluminium foil and plastic bottles via
the orange bag scheme. Collections are made using seven RCVs (15 tonne) and three cage tipper vehicles
(3.5 tonne). In addition, three 26 tonne 70/30 split-back RCVs are also used by the authority to collect
orange bagged dry recycling and food waste. Once collected, the dry recycling is delivered to one of two
privately operated MRFs (materials recovery facility). One, which received approximately 80% of the dry
recycling tonnage in 2009/10 is located at Withyhedge and operated by SITA; the other which received the
remainder of the orange bags is located at Boncath and operated by A J Recycling Waste Management. A
total of 7,730 tonnes of dry recyclables were collected at the kerbside in 2009/10.
Garden waste; Pembrokeshire County Council actively discourages residents from leaving out garden waste
for collection. If residents are unable to compost green waste at home or take it to Civic Amenity and
Recycling Centres, the council will collect this waste with residual waste provided that it is placed at the
kerbside in approved compostable green bags which can be purchased from the council.
Residual waste; all households receive a weekly residual waste collection presented in black bags. The
residual waste is collected using ten 26 tonne RCVs and three 15 tonne RCVs. A total of 25,511 tonnes of
residual waste was collected at the kerbside in 2009/10 at the SITA-operated Withyhedge landfill site.
Food waste; the weekly food waste scheme began in September 2009, initially rolling out to 11% of
households in Pembrokeshire. In October 2009 this roll out was extended to 26% of households, and in
November 2009 it was further extended to cover 40% of the households in Pembrokeshire. Since then a
further 6,500 households have been added to the food waste scheme, with coverage currently at 50% of
households across Pembrokeshire, and with plans to extend the roll out to 100% of households early in the
2011/12 financial year. Residents are provided with a 23ltr food waste bin, a 5ltr food waste caddy and a
year‟s supply of compostable caddy liners. Food waste is collected alongside dry recycling using three 70/30
split-back RCVs and a food-only 15 tonne RCV. A total of 720 tonnes of food waste was collected at the
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 8
kerbside in 2009/10 and this waste is tipped at the SITA MRF in Withyhedge. In 2009/10 food waste was
treated by two contractors, Bryn Composting and Cwm Environmental at in-vessel composting (IVC) facilities.
Since September 2010 the authority has been in contract with Agrivert who treat the waste at their
anaerobic digestion (AD) facility.
5.0 Financial analysis
The resources and associated costs presented in this section have been calculated based on 2009/10 financial
outturns for Pembrokeshire. Due to the timing of service change in the other five case study authorities, 2010/11
budgets have been used and this clearly means that there is some methodological inconsistency with the
treatment of Pembrokeshire. However, although Pembrokeshire is the only authority for whom actual 2009/10
outturns have been used, we would view the other five authorities as the exceptions, in as much as actual
outturns are a more accurate data source and also relate to the most recent full year of tonnage data available.
In the case of Pembrokeshire, the 2009/10 outturns will reflect the change in costs associated with several stages
of roll out of food waste collections during 2009/10; the use of 70/30 split back vehicles to collect food waste and
dry recycling on the same pass will also thus be factored into the financial outturns provided for both the food
waste and dry recycling collection services. This should mean that 2009/10 represents an accurate reflection of
underlying costs and can be most easily analysed in conjunction with actual tonnage data for the same period. In
the case of the other authorities, due to recent significant service change not reflected in 2009/10 actuals,
2010/11 budgets have had to be used in order to provide an accurate picture of „current service design‟ costs.
The methodological differences that have been required in order to provide as accurate a picture of the costs of
each case study authority have led to a need for a number of adjustments to be made in order to make costs as
comparable as possible. There are discussed in detail later in the report.
5.1 Resources currently employed for kerbside services
Table 1 summarises the resources that are currently employed for household kerbside collections in
Pembrokeshire. 27 vehicles are currently employed across the kerbside collection services; the vehicles are
predominantly RCVs, though three cage tippers are also used and are shared between the dry recycling and
residual waste services. Three 26 tonne split-body (70:30) RCVs are used to collect both dry recycling and food
waste on the same pass and a further 15 tonne RCV is used to collect food waste only. In those instances where
garden waste is left out for collection, this waste is collected as part of the residual waste service. The authority
also has one spare 26 tonne RCV for residual collection. The cage tipper vehicles are owned by Pembrokeshire
with the RCVs being a mixture of owned and contract hire. The 70/30 RCV used for orange bag dry recycling and
food waste collections is spot hire. Once the food waste scheme is rolled out to 100% of households, officers
have advised that they will be looking to review vehicles for food waste collection, and will probably look to use
RCVs with a food waste pod.
As demonstrated in Table 2, Pembrokeshire outsources its treatment requirements. Dry recycling is sent firstly to
the SITA MRF at Withyhedge, before being sent to A J Recycling at Boncath, where it is subsequently sold to
reprocessors. A smaller volume of dry recycling goes directly to A J Recycling. Pembrokeshire receives some of
the income from the sale of this material (see Table 3). Food waste was sent to IVC facilities owned by Bryn
Composting and Cwm Environmental, and is now sent to an AD facility owned by Agrivert whilst residual waste is
sent to SITA‟s landfill site, located next to the MRF at Withyhedge.
Pembrokeshire has recently (January 2010) entered into a contract with Neath Port Talbot (NPT) to send MRF
contaminant to their Materials Recovery and Energy Centre (MREC) at Crymlyn Burrows for incineration.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 9
Table 1 Vehicles and crew employed for household waste collections in Pembrokeshire
Dry Recycling Garden Waste Food Waste Residual Waste
Vehicle Type 3.5 tonne cage
tipper
N/A (collected with
residual waste)
26 tonne 70/30 split
RCV
3.5 tonne cage
tipper
Number of
Vehicles
3 (shared 50/50
with residual) 3 (dry plus food)
3 (shared 50/50
with residual)
Number of Crew 1-2 3 1-2
Vehicle Type 15 tonne RCV 15 tonne RCV 26 tonne RCV
Number of
Vehicles 7 1 10
Number of Crew 2 2 20-30
Vehicle Type 26 tonne 70/30 split
RCV 15 tonne RCV
Number of
Vehicles 3 (dry plus food) 3
Number of Crew 3 2
Total Number
Vehicles 13
1 (70/30 split
included under dry)
13 (cage tippers
included under dry)
Total Number
Crew 26-29
3 (70/30 split RCV
crews included
under dry)
26-36 (cage tipper
crews included
under dry)
Table 2 Bulking, transfer, treatment and disposal of household waste in Pembrokeshire
Dry Recycling Garden Waste Food Waste Residual Waste
Treatment Type MRF
Bring and Civic
Amenity site
composted,
Kerbside collection
landfilled.
IVC Landfill
Ownership
SITA – Withyhedge
A J Recycling -
Boncath
Bryn Composting
Cwm Environmental SITA
The income received in 2009/10 net of the gate fee charged by SITA for dry recycling is listed in Table 3; these
material income prices are also net of transport costs. The gate fee charged by SITA is relatively high, with net
values remaining substantially negative (i.e. an overall cost to the authority) for all materials except aluminium.
The payment arrangements for the sorting of dry recyclables in Pembrokeshire is somewhat unusual compared to
the other case study authorities and also compared to wider co-mingled practice in Wales, with materials passing
between two privately-owned MRFs before sale. For all materials except glass, material prices vary from month to
month; for glass (both source-separated and mixed) the price is fixed over the financial year.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 10
Table 3 Materials income
Material Income net of gate fee for all co-mingled items, glass collected as a
source segregated material with a reduced gate fee per tonne (09/10)
News and pams £38.24
Cardboard £52.83
Glass, colour separated -£7.04
Glass, no colour separation £9.96
Cans steel £28.74
Cans aluminium -£411.84
Aluminium foil -£411.84
Plastic bottles £0.23
Note that a positive figure relates to a cost, and a negative figure to an income.
5.2 Net costs of collection
As noted above, costs presented in this section are based on 2009/10 actuals. In this section, we first illustrate
the key budget lines which form part of the overall waste services budget and any items which are particular to
an individual authority and which would not be easily compared between authorities. We then attempt to
normalise the cost of the dry recycling service based on a number of key assumptions, in order that comparison
can be made between the case study authorities in Phase 3 of the study.
5.2.1 Reported 09/10 actuals
Table 4 summarises the key elements which comprise the overall waste services budget in Pembrokeshire. Costs
are broken down into those associated with household waste collection, commercial waste collection, and other
waste services, including the treatment and disposal of all waste which is collected across Pembrokeshire. Note
that „service provider cost‟ (intended to allow comparison between in-house and contracted out services) refers
primarily to the cost of crews and vehicles associated with the particular service, but in some cases also include
some depot and bulking facility costs.
The following elements of the reported 09/10 actuals for Pembrokeshire need to be considered when attempting
to compare this authority to the other case study authorities:
The materials income includes a significant income obtained from the large network of bring banks in
Pembrokeshire (167 bring sites in total and six civic amenity sites).
The MRF gate fee shown is particularly high, but is partly counterbalanced by the materials income obtained.
Depot costs are included as part of the service provider costs.
There are no costs for garden waste collection as this is included as part of the residual waste collection
costs.
Note that the 09/10 actuals reflect the roll out of food waste as detailed in Section 4 – food waste, at the
time of writing standing at 50% of households in Pembrokeshire.
The costs of the split back RCVs used to collect dry recycling and food waste are all currently apportioned to
the food waste service provider costs.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 11
Table 4 Summary of Pembrokeshire 2009/10 financial outturns
£k
Household Waste
Collection Costs
Income
Material Sales -480
Charged Collection Income -19
Income from Container Sales -23
Other Income -230
Total Income -752
Expenditure
Service Provider Costs - Bulky Waste 142
Service Provider Costs - Clinical Waste 10
Service Provider Costs - Refuse 1,879
Service Provider Costs - Dry Recycling 1,184
+MRF/Bulking/Sorting Facility Costs (net of gate fees income)
+MRF gate fee 767
Service Provider Costs - Food Waste 323
Service Provider Costs - Green Waste
Service Provider Costs - Bring Sites 308
Refuse Containment Purchase 137
Recycling Containment Purchase 378
Depot Rent 0
Other Associated Depot Costs 0
Other Expenses 42
Total Expenditure 5,170
Net Cost of Hhld Collection Service 4,418
Net Cost per Hhld £77
Net Cost per Tonne Dry Recycling £588
Net Cost per % Recycling/Composting (£k) £18,480
Commercial
Waste Collections
Income -550
Expenditure (Commercial Waste Service Provider Cost) 550
Net Cost of Commercial Waste Service (excluding disposal) 0
Other Waste
Services
Other Income
(Non-MRF Gate Fees) 0
Grants
For Collection Service -2,599
Waste Awareness
Other (Commercial, HWRC, Compost, IVC etc) -154
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 12
Total Other Income and Grants -2,753
Other Expenditure
Back Office 523
Waste Education and Marketing Campaigns 51
Waste Transfer 29
Treatment 43
Disposal 2,883
HWRC 1,248
Capital Charges 49
Overheads 582
Total Other Expenditure 5,407
Net Cost Non-Collection 2,654
Overall
Net Cost of Waste Service (excluding grants) 9,825
Net Cost per Hhld (excluding grants) £171
Net Cost of Waste Service (including grants) 7,072
Net Cost per Hhld (including grants) £123
Note that a negative figure relates to an income, a positive figure to a cost.
5.2.2 Authority-specific issues
Several key factors in Pembrokeshire make it difficult to directly compare the cost of this co-mingled dry recycling
service to the costs of other dry recycling services across Wales. The following service features are specific to
Pembrokeshire:
The use of two MRFs, one to sort the majority of the dry recyclables, the other to market materials. The
costs of using the MRFs are not straight-forward, with a high gate fee paid for the first MRF, but some
materials income received back, with materials prices varying from month to month for all except glass.
Pembrokeshire is the only case study authority not to offer a garden waste service, although the Council
does have plans to introduce one in the near future.
Pembrokeshire is the only authority not to collect glass at the kerbside; instead, the authority offers a
substantial network of bring sites for the collection of glass and other materials across the authority. In order
to normalise the collection costs across the six case studies as much as possible, some account will need to
be taken of the costs of the bring site collection of glass in Pembrokeshire as part of the overall dry recycling
service provider cost.
Pembrokeshire are in the middle of rolling out a weekly food waste collection with approximately 50% of
their households covered by the scheme so far. Completing the roll out will impact on their cost base; hence
the net cost of the service will change from that identified above, which is based on the 09/10 financial
outturn. The current collection method of using 70/30 split RCVs is an interim solution whilst the food service
is rolled out.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 13
5.2.3 Normalised costs – dry recycling service and refuse service
Following on from the authority-specific issues identified above, this section presents any adjustments we would
make to the costs associated with both the dry recycling and refuse services in order that resultant CBA for each
authority is as comparable as possible. Refuse costs are included alongside dry recycling costs because of the
related avoided disposal environmental benefits that result from increased recycling of materials. Organic costs
are, however, excluded, with appropriate adjustments made to other service provider costs where required, as
not all authorities currently collect both garden and food waste, and due to the added complication of most of the
case study authorities being only part way through roll outs of separate food waste collections.
The adjustments that have subsequently been made to the dry recycling collection costs for Pembrokeshire are as
follows:
Reduction in total materials income based on the proportion of each material collected through bring sites
and Household Waste Recycling Centres (HWRC) compared to at the kerbside in 2009/10.
Given that Pembrokeshire is the only case study authority not to collect glass at the kerbside, in order to
make the basket of materials collected through the dry recycling system as comparable as possible, we have
accounted for the glass collected in bring sites in Pembrokeshire as part of the overall dry recycling costs. We
have thus added into the costs in Table 5 the proportionate glass-related materials income and the additional
cost required to cover the collection of glass from bring sites in Pembrokeshire. The costs of the collection of
glass are based on the total bring site service provider costs highlighted in the budget, with the glass-specific
cost calculated based on the proportion of the total bring site tonnage that is glass.
Adjustment of containment costs to ensure that costs are annualised; rather than annualising these costs,
containment costs for local authorities tend to vary annually depending on when stocks need replenishing,
and to match new service roll outs. Hence costs which may show in one year‟s budget may not be included
in the following year. In order to make containment costs as comparable as possible between authorities, we
have annualised the costs of containment in Pembrokeshire based on the average household using three
bags every week to present their dry recycling for collection. Unit costs are based on bulk purchase prices of
clear single-use bags.
The normalised costs for the dry recycling service are presented in Table 5. The overall cost of the kerbside dry
recycling service in Pembrokeshire is thus calculated at £35 per household, or £268 per tonne of dry recycling
collected.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 14
Table 5 Normalised costs – dry recycling service (based on 2009/10 budget)
Item £k
Income
Budgeted Income -480
Adjustment for Bring Site/HWRC Income 79
Adjustment to Include Bring Site Glass Materials Income -51
Total Income -451
Expenditure
Budgeted Service Provider Cost 1,183
Adjustment for Bring Site Collection Cost (Glass) 155
Budgeted MRF Gate Fee Cost 767
Budgeted Containment Cost 378
Adjustment for Annualised Containment -17
Total Expenditure 2,466
Net Kerbside Dry Recycling Service Cost 2,014
Net Cost per Household £35
Net Cost per Tonne Dry Recycling Collected £268
Note that a negative figure relates to an income, a positive figure to a cost.
For the refuse service, the containment costs for the refuse service were annualised, with the calculations based
on each householder being provided with one bag each week in which to present their residual waste. The
disposal cost associated with the kerbside collected residual waste was also calculated based on the tonnages of
residual waste collected in 2009/10 and with landfill tax set at £48 per tonne. We note that the landfill tax applied
relates to the financial year 2010/11 rather than 2009/10. In the case of the other five case study authorities,
significant recent service change meant that greater accuracy could be obtained by basing our analysis on
2010/11 budgets rather than 2009/10 financial outturns. Given the significant impact that an £8 per tonne lower
tax calculation would have had on Pembrokeshire‟s residual waste cost in comparison to the other case study
authorities, and that this is significantly greater than any increase in inflation costs between the two years, we
modelled all authorities at the same landfill tax cost per tonne (i.e. the 2010/11 figure). It is important to note
that the overall CBA to which these figures will contribute subsequently excludes landfill tax altogether from the
financial cost calculations to avoid double-counting environmental costs (see Section 8.1).
The resultant normalised kerbside refuse service costs are presented in Table 6. The calculated net collection cost
for refuse in Pembrokeshire is £33 per household, £75 per tonne of refuse collected, and the overall refuse cost
(including disposal) equates to £65 per household or £147 per tonne of refuse collected. Alongside the costs
calculated in Table 5 for dry recycling, it is these costs which we have used as part of the CBA model for
Pembrokeshire‟s kerbside collection services.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 15
Table 6 Normalised costs – refuse service (based on 2009/10 financial outturns)
Item £k
Collection Expenditure
Budgeted Service Provider Cost 1,879
Budgeted Containment Cost 137
Adjustment for Annualised Containment -107
Net Refuse Collection Cost 1,909
Net Cost per Household £33
Net Cost per Tonne Refuse Collected £75
Disposal Expenditure
Disposal Cost 604
Landfill Tax* 1,225
Total Refuse Service Expenditure 3,738
Net Service Cost per Household £65
Net Service Cost per Tonne Refuse Collected £147
Note that a negative figure relates to an income, a positive figure to a cost.
*The landfill tax calculation was undertaken based on £48 per tonne.
6.0 Environmental modelling
This section firstly presents the quantified flow of materials from kerbside collection to their fates (i.e. the
material mass flows). The calculation of the environmental impact of these material flows is then outlined both in
terms of carbon and also the wider impacts on air quality.
6.1 Material mass flows
This section of the report describes:
how we have approached calculating how much material is produced by householders;
how much of each material is captured by the dry recycling system;
how the materials are separated from co-mingled materials into reprocessable grades;
where materials go and what they are made into; and
how much of the collected materials are made into new products.
6.1.1 Generic case study approach to producing mass flows
Mass flow models were produced for each of the six case study authorities to demonstrate the fates determined
for various material streams and quantify the flow of materials from kerbside collection to their fates. WDF
tonnages for 2009/10 reported by each of the authorities were used as the starting point in the mass flow. WDF
tonnages for the following streams were input for each authority:
kerbside household refuse;
kerbside household dry recycling;
kerbside household organics collections; and
bring sites.
Tonnages for bring sites were included since authorities not targeting a particular material at kerbside for
recycling (glass for example) are likely to have considerably higher tonnages of this material captured at bring
sites in comparison to authorities which do target the material at kerbside. This was important in order to sense
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 16
check recycling yields for the various authorities, with consideration of bring sites being required alongside
kerbside recycling in order be able to consistently assess comparative recycling yields.
The composition of all waste streams was reconciled with the following category list, used throughout the model:
news and pams;
non-target fibre;
brown board;
grey and white board;
cartons;
plastic film (LDPE);
plastic bottles;
other dense plastic packaging;
other dense plastic (non-packaging);
textiles;
glass;
ferrous cans;
other ferrous;
aluminium cans (used beverage cans (UBC));
other non-ferrous;
garden waste;
food waste;
hazardous;
WEEE; and
other: miscellaneous / fines.
In designing the categories it was necessary to keep the list reasonably simple, in order to avoid unnecessary
levels of detail within the material flows (which would have made the design of the models excessively complex)
and to account for limited data availability in terms of detailed compositional profiles for many waste streams. On
the other hand, it was necessary to be able to distinguish between categories of material that would be
associated with significantly different outputs with respect to fate of materials in the mass flow models, in
particular those likely to significantly impact the environmental modelling. For example, it was important to
distinguish between ferrous and non-ferrous metals, due to the significantly different environmental benefits
associated with recycling ferrous and non-ferrous metals.
The arisings of different components for each product stream were estimated through applying compositional
profiles for each stream to the relevant WDF tonnage. Arisings within kerbside refuse of the various components
in the category list was determined by applying compositional profiles for kerbside residual waste (derived from
data from the WastesWork and AEA on behalf of the Welsh Assembly Government‟s The Composition of Municipal
Solid Waste in Wales, 2010 project) to WDF tonnages. Arisings for kerbside organics and bring sites were
expressed in terms of the common category list through analysing separate tonnages for recycling streams
reported in WDF. Where insufficient data was available on the breakdown of WDF tonnages, reference data from
the Resource Futures on behalf of Defra, WR0119 Review of Municipal Waste Component Analyses, 2009 project
were applied. Once the compositional breakdown of each kerbside dry material stream had been estimated in this
way, the fate for each component was determined. Tonnage arisings for each component in the various kerbside
dry product streams were subsequently produced for each relevant fate. These tonnages are arranged in a
systematic array within the model and represent the outputs for the mass flow modelling.
The main focus of the model was on determining the composition and fates of materials collected for kerbside dry
recycling. The methodology applied for the various collection system types (kerbside sort, single and two-stream
co-mingled) was essentially the same, though the methodology for kerbside sort is the simplest to describe and is
therefore addressed first.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 17
Modelling of kerbside dry material flows for kerbside sort systems
The kerbside sort authorities (Newport and Gwynedd) both reported separate tonnages for the different dry
recycling streams targeted at the kerbside. Each type of material was treated as a separate product stream, i.e.
news and pams, glass containers, etc. The arisings of different components for each product stream were
estimated through applying compositional profiles for each stream to the relevant WDF tonnage. This is illustrated
in Table 7, which presents, as an example, the arisings allocation for the news and pams product stream for
Newport. A tonnage of 4,655 was reported by Newport for news and pams kerbside dry recycling, as derived
from WDF 2009/10. The compositional profile is derived from reference data, in this case a compositional analysis
of news and pams carried out by Resource Futures for another local authority; (comments on the general use of
reference or fieldwork data in the modelling are included below). In Table 7 we can see that the estimated arising
of news and pams type materials within Newport‟s kerbside collected news and pams was 95.23% of the material
stream, equating to 4,433 tonnes; we can also see that non-target fibre was estimated to constitute 3.60% of the
material stream, equating to 168 tonnes; and so forth.
Table 7 Example of arisings allocation in a material (news and pams)
NEWS and PAMS
% arising Tonnes per annum
News and pams 95.23% 4,433
Non-target fibre 3.60% 168
Brown board 0.13% 6
Grey and white board 0.72% 34
Cartons 0.04% 2
Plastic film (LDPE) 0.03% 1
Plastic bottles 0.00% 0
Other dense plastic packaging 0.01% 1
Other dense plastic (non-packaging) 0.01% 0
Textiles 0.00% 0
Glass 0.10% 5
Ferrous cans 0.04% 2
Other ferrous 0.00% 0
Aluminium cans (UBC) 0.01% 1
Other non-ferrous 0.00% 0
Garden waste 0.00% 0
Food waste 0.00% 0
Hazardous 0.08% 4
WEEE 0.00% 0
Other: misc / fines 0.00% 0
TOTAL 100.00% 4,655
Once the compositional breakdown of each kerbside dry material stream had been estimated in this way, the fate
for each component was determined. The fates used across all the models consisted of the following:
recycling (with different types of recycling specified for materials with more than one recycling fate; for
example the fates for paper fibres included newsprint, soft mix and old corrugated cardboard (OCC)
packaging);
landfill cover;
landfill disposal;
energy from waste (EfW);
combustion without energy recovery (materials transported to a separate facility to be incinerated, but with
no energy recovery taking place); and
incinerated during the recycling process (materials incinerated in situ during the recycling process itself, i.e.
burning off combustible components during the smelting of metals).
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 18
Continuing with the example of news and pams in Newport, it was determined that the fate of the various
components were:
news and pams, brown board, grey and white board: 100% recycling as newsprint; and
all other components: 100% landfill disposal.
For some components in some material streams in the various authorities, the fate of a particular component was
split over several fates. For example, for the kerbside dry collected glass product stream in Newport it was
determined that 84% of glass was sent to re-melt, whilst the remaining 16% was recycled as aggregates. The
model includes various checks to ensure that the fates for each component equal 100%. From the
aforementioned procedures, tonnage arisings for each component in the various kerbside dry product streams
were produced for each relevant fate. These tonnages are arranged in a systematic array within the model and
represent the outputs for the mass flow modelling.
Modelling kerbside dry material flows: single and two-stream co-mingled systems
The modelling for co-mingled systems followed the same procedures as described above, essentially applying
compositional profiles to different product streams and assigning fates for each component in each product
stream. However, there were additional challenges, including determining the relative arisings of different product
streams and accounting for residue arisings at MRFs. Many of the single and two-stream co-mingled authorities
reported some or all of their kerbside dry tonnages within the co-mingled materials category, with no indication
as to the relative concentrations of the materials targeted. The relative magnitudes of product streams and the
MRF residue stream(s) relating to the kerbside dry materials collected and sent to one or more MRFs were
determined through a combination of examining WDF tonnages (where separate material tonnages were
reported), tonnage data from the MRFs themselves and discussions with relevant contacts at the local authorities
or MRFs.
The use of reference data was more challenging for the single and two-stream co-mingled authorities, due to the
wide variation in product stream compositional profiles at MRFs. Greater variations can be expected in
comparison to compositional profiles for kerbside sort material streams, since a wide range of input streams and
separation technologies or procedures are used at MRFs. In particular, the compositional profile of MRF residues
can be expected to vary greatly between facilities. In light of this, it was decided to focus the fieldwork data
gathered on two of the authorities with co-mingled collection systems (Cardiff and Pembrokeshire), for which
there was reasonable confidence that the samples sorted would relate to material collected by the authority in
question (i.e. not mixed with inputs from other local authorities, or from commercial sources). Further details on
the sampling approach undertaken for the Cardiff and Pembrokeshire MRFs are presented in Appendix A.1.0.
Nonetheless, it was not possible to sample all the product and residue streams for all the case study authorities.
Therefore it was necessary, in many cases, to refer to reference data from compositional assessments carried out
at other MRFs.
The specific approach to calculating the material mass flows for the kerbside services in Pembrokeshire is
presented below.
6.1.2 Material mass flows for Pembrokeshire
Pembrokeshire County Council reported material specific tonnage for kerbside dry recycling in WDF 2009/10.
These were reconciled with the operational tonnage data reported for the two MRFs processing material in
Pembrokeshire. The model includes the arisings for each of the two MRFs.
The composition of the product being produced at each of the MRFs is modelled on fieldwork data gathered as
part of this project. Time was spent at both the SITA (four days) and A J Recycling (two days) MRFs carrying out
compositional analysis of all the product and residual streams. The sorting process at both MRFs is primarily
based on a positive handpick system. The material arrives bagged and is opened (mechanically at SITA and by
hand at A J Recycling) before entering a picking cabin. The paper, card and plastics products are all positively
picked by hand off the line. The steel is removed by an overband magnet and the aluminium is recovered through
an EC system. In total over 55 samples were sorted over the two facilities.
In both MRFs the fibre is collected in two separate bays with the big items (whole newspapers etc.) being pulled
off first and then smaller items (sheets of paper and newspaper etc.) pulled off further down the line. Samples of
material were taken from each of the bays and sorted separately. The composition of the fibre was based on
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 19
apportioning the profiles of each bay based on conversations with the MRF operators as to their contribution to
the whole. This method was also applied to the residue in the SITA MRF.
All materials are marketed by A J Recycling. Paper and glass (note glass is collected only from bring sites in
Pembrokeshire) is transported direct from the SITA MRF; all other materials from the SITA MRF are baled and
transported to A J Recycling.
The residual waste from both MRFs is baled and sent to the Neath Port Talbot, Materials Recovery & Energy
Centre (MREC). News and pams are being shipped direct to UPM Shotton. We were informed by A J Recycling
that there are 1 to 2 loads per year that are shipped as soft mix from the A J Recycling MRF; these go via Parry &
Evans for cleaning before going on to UPM Shotton. We have not modelled this small tonnage flow.
A J Recycling uses Monoworld for plastics and cardboard. It has been difficult to get any substantive information
from Monoworld on the processes that they use and the fates of the materials; we have, therefore, assumed
similar recovery rates to other reprocessors.
Table 8 provides a summary of the current reprocessing locations for outputs from the SITA and A J Recycling
MRFs.
Table 8 Summary of processing and reprocessing locations for outputs from the SITA and A J Recycling MRFs
Material Product Intermediate Processor Final Reprocessor
News and pams UPM Shotton
Soft mixed papers Via Parry & Evans for
cleaning then to UPM Shotton
Not known but assumed to be mixed into
packaging
OCC (old corrugated
cardboard) Monoworld
Process unknown, Monoworld believed to act as
merchants, fate of material unknown.
Steel cans None Tata Steel – Port Talbot
Aluminium UBC (used
beverage cans)
Undefined – currently being
stockpiled. Have previously
supplied Novelis
Unknown
Mixed rigid plastic packaging Monoworld Process and fate of material unknown
Plastic films Monoworld Process and fate of material unknown
Residues None Neath Port Talbot MREC RDF/SDF burnt at plant
The following additional assumptions regarding the composition and fates of various materials were applied in
calculating the mass flows for each of the case study authorities:
1 Non-target fibre
These were genuinely identified in the reference or field data informing the compositional profiles.
2 Fibre losses through the pulping process
We also questioned the rationale that no fibre was lost through the pulping process i.e. is it correct that
100% of the recyclable fibre sent for reprocessing gets turned into new product? Looking at all the profiles
for the fibre products and thinking through the pulping process, we took the decision that for each one tonne
of contamination, one tonne of fibre was lost from the reprocessing system as a result of being screened off
with the contamination. This assumption was applied to all fibre streams with the exception of the SCA soft
mix for Monmouthshire, which is going to the Far East. For the SCA material, we assumed that less fibre loss
would occur, as the material would be cleaned by hand before processing, meaning that less contamination
would enter the process. A ratio of one tonne contamination to half a tonne of lost fibre was applied in this
instance.
3 Plastic film losses
These arise from compositional profiles, the majority of which we are pretty confident about, and the relative
arisings of product/residue streams. In particular, there is a lot of film that ends up in residue.
4 Rigid plastics
The same argument is applied here as for films. Where non-bottle dense plastic does arise in plastic bottles
or mixed plastics streams, we are assuming that the majority gets recycled. However, according to our
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 20
compositional profiles, a lot does end up in the residue. Having looked at SCA, there is some uncertainly
about the compositional profiles (we have applied Enviros profiles); nonetheless, we have no better data
upon which to base SCA.
5 Steel and aluminium losses
For the co-mingled authorities, a fair amount of steel ends up in plastic film (crushed cans wrapped around
film), and where star screens are used for metals, 2D elements (lids) tend to get through to the residue. The
highest losses are for Pembrokeshire, probably due to the „positive hand sort‟ MRF designs, where our
fieldwork gives us pretty good confidence in the compositional profiles.
The assumed composition of materials exiting the MRFs is detailed in Appendix A.2.0 and A.3.0 for the SITA and
A J Recycling MRFs respectively. Diagrams of known and assumed process flows are detailed from Figure 1
onwards, with a supporting summary of intermediate processor and reprocessors‟ processes detailed in Section
6.3. Note that the key for the process flow diagrams can be found in Appendix A.3.0.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 21
Figure 1 SITA MRF
Pembrokeshire
orange sacks
Trade waste
Input Hall+ve pick
CabinBag Splitter
film
Disc screen
Broken
glass
(small
paricles)
News and
PamsCardboard A
A
FilmOCC
UBC
Mixed
rigid
plastics
N&P
Mixed
plastic
bottles
Overband magnet
Steel
Cans
Baled
Al UBC
and foil
mixed
Baled
ECS
Steel
Residue EFW
baled
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 22
Figure 2 A J Recycling MRF
Pembrokeshire
orange sacks
Trade waste
Input Hall+ve pick
Cabin
Manual bag
splitting off floor
filmNews and
PamsCardboard A
A
Film OCC
UBC
Mixed
rigid
plastics
N&P
Mixed
plastic
bottles
Overband magnet
Steel
Cans
Baled
Al UBC
and foil
mixed
Baled
ECS
Steel
Residue EFW
g
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 23
Figure 3 News and pams process
UPM- Shotton,
Screening in
pulping plant
Residues that
don’t pass the
pulping
screens plus
some fibres
NewsprintN&PPaper
pulpN&P
Landfill
Figure 4 Old corrugated cardboard (OCC) process
Monoworld
OCCOCCOCCOCC
Process Unknown,
believed to act as
merchants fate of
material unknown
Export
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 24
Figure 5 Plastics processes
FilmsFilmsFilmsFilms
Mixed
rigid
plastics
FilmsFilmFilmFilm
Mixed
rigid
plastics
Next stage
unknownFilmsFilmsFilms
Mixed
rigid
plastics
Mixed
rigid
plastics
Monoworld - Bedfordshire
Next stage
unknown
Figure 6 Used beverage cans (UBC) process
UBC
Location currently undefined – currently being stockpiled
Have previously supplied Novelis
Chipping ECSAluminium
Chips
Waste to
landfill
Landfill
Aluminium ingot to be sent
for can manufactureUBC
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 25
Figure 7 Steel process
Steel
Cans
Tata Steel Port Talbot
Steel Melt
Process Slag
Steel
Recycled
6.2 Merchants, intermediate processors and reprocessors
This section summarises what we have been able to find out about the processes employed by merchants,
intermediate processors and reprocessors for material derived from the SITA and A J Recycling MRFs.
UPM Shotton
UPM Shotton is a reprocessor that takes fibres from A J Recycling (some via Parry & Evans). Every load is visually
inspected and there is a rolling programme of weight-based composition testing. All the non-fibre is screened off
via the drum pulpers and is landfilled.
Parry and Evans
Parry and Evans is a merchant that takes cardboard and plastic bottles from A J Recycling, but this is only on an
occasional basis. A J Recycling will go wherever they are getting the best price. Inspections are made for
moisture and unwanted material. Card handled by Parry & Evans is estimated at 1,000-1,500 tonnes per annum,
all going for export to China; plastic bottles estimated to be 90 tonnes per annum being sold on to Viridor and the
UK market. Parry and Evans stated that the quality from A J Recycling is impeccable and in the last 12 months
they have not had any problems, with all material simply being reshipped.
Monoworld Recycling
Monoworld is a merchant for some materials and a reprocessor for plastics. They have a MRF and a plastic flaking
facility. Some plastics are taken from Monmouthshire and cardboard, mixed plastics and plastic film are taken
from Pembrokeshire to the Monoworld plant in Bedfordshire and are sorted further, subsequently producing
plastic flake in HDPE and PET grades. These grades are then sold on to various manufacturers (e.g. fleeces from
PET, wheelie bins from HDPE), though Monoworld would not disclose the specific destination manufacturers.
There is also a mixed plastics output from Monoworld‟s plant which is then sold on for export to Europe/Far East
for further sorting.
Regarding cardboard, Monoworld handle the haulage of this material and sell it on to various paper mills, the
details of which they were unable to disclose.
Tata Steel
Tata Steel (previously Corus) reprocesses steel packaging, and takes material from Cardiff (via Thamesdown
Recycling, Swindon), Pembrokeshire (via A J Recycling), Gwynedd, RCT and Newport (via Pontypool Steel). Visual
inspections are undertaken at accumulation centres such as Pontypool and Thamesdown. The material is rejected
if it is more than 5% non-steel by weight. Tata Steel commonly expects material to be 98% by weight steel. The
process involves all material being melted for steel at Port Talbot. This process produces three outputs: new
steel, a slag used in cement processing and gas emissions.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 26
6.2.1 Material reprocessed
Figure 8 shows the combined reject tonnages that occur at both the Sita and A J Recycling MRFs for each of the
main components found in the dry recycling material collected, and Figure 9 illustrates the reject rates for each
component being processed through the MRFs. The combined overall reject rate for Pembrokeshire equates to
8.4% of the total collected kerbside dry recycling material. The rejects are incinerated at an EfW facility.
Following processing at the MRFs, the resultant product streams are then sent for reprocessing into new
products. In a number of the product streams, there will be some contraries i.e. materials that are not wanted by
the reprocessor which, during reprocessing, will become a „process loss‟ rather than a new product. Figure 10
shows the process losses in tonnes that are subsequently incurred during reprocessing. The overall process loss
rate for Pembrokeshire is 3.0%. The majority of this loss is sent to landfill, with only losses associated with the
steel product stream being partly incinerated during the recycling process itself.
The final combined reject and process loss rate for the authority is calculated at 11.4%.
Figure 8 Kerbside dry recycling material MRF rejects (tonnes per annum)
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
Kerb
side D
ry R
ecy
clate
Tonnes
Rejected 225 24 79 71 41 100 4 12 16 7 55
Taken as Products 4,029 822 505 91 722 23 0 470 83 25 106
News
and
Pams
Brown
Board
Grey &
White
Board
Plastic
Film
Plastic
Bottles
Other
Dense
Plastic
GlassFerrous
Cans
Al Cans
(UBC)
Other
Non
Ferrous
Other
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 27
Figure 9 Kerbside dry recycling material MRF reject rates (%)
5.3%2.8%
13.5%
43.8%
5.3%
80.9%
94.5%
2.5%
16.5%
21.5%
34.2%
8.4%
0.0%
20.0%
40.0%
60.0%
80.0%
100.0%
News
and
Pams
Brown
Board
Grey &
White
Board
Plastic
Film
Plastic
Bottles
Other
Dense
Plastic
Glass Ferrous
Cans
Al Cans
(UBC)
Other
Non
Ferrous
Other Total
Dry Recycling Components
Reje
ct R
ate
(%
)
Figure 10 Process losses incurred during reprocessing of product streams (tonnes per annum)
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
Tonnes
Process Loss 56 2 119 33 9 1 5
Recycled 3,990 48 1,238 465 76 726 94
Paper Side Cardboard MRF Cardboard Steel Cans Aluminium Cans Plastic Bottles Plastic Sacks
6.3 Environmental impacts
The methodology used within our assessment of the performance of each local authority‟s recycling and residual
waste collection/treatment system combines the external cost associated with the environmental impact of each
system together with the financial cost of operating that service. In economics, an external cost – also known as
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 28
an externality – arises when the social or economic activities of one group of persons has an impact on another
group and when that impact is not fully accounted for or compensated for (in financial terms), by the first group.
Particularly in the case of waste treatment facilities, our experience indicates that it is the climate change and
local health impacts of these plant that cause most concern for local residents and the wider community.
Eunomia‟s preferred approach is therefore to apply monetary values or external costs to both the climate change
and air quality impacts.
The impacts of the major air pollutants – NOx, SOx, PM, and VOCs – are attributed an external monetary value
which measures the extent of the damage to health associated with the quantity of pollutant being released into
the air. Impacts associated with the emission of greenhouse gases are calculated on the basis of the cost of
mitigating the effects of climate change. Air quality impacts are calculated based on the external costs of key air
pollutants known to have a local or regional impact1. In both cases impacts can be estimated on a £ per tonne
basis, with a higher figure thus representing greater damages. The methodology thus described is widely used in
impact assessments carried out by UK governments.
Our methodology for assessing the environmental impacts accounts for emissions from the following:
those resulting from the collection and transportation of both dry recyclate and residual waste (this includes
the shipping of recyclate overseas for reprocessing);
impacts associated with sorting and transfer facilities;
avoided emissions resulting from the reprocessing of recyclate;
impacts associated with the rejected material throughout the collection, sorting and reprocessing cycle; and
impacts associated with the treatment and disposal of residual waste. This includes a consideration of
avoided emissions resulting from the generation of energy by incineration facilities.
It should be noted that, for the purposes of the Phase 2 modelling, organic costs (both financial and
environmental) have been excluded from the analysis, as not all authorities currently collect both garden and
food waste, and because of the added complication whereby most of the case study authorities are currently part
way through roll outs of separate food waste collections.
The assessment of the environmental impacts uses the mass flow and transport data provided by each local
authority, as has already been described earlier in this report. The approach to the calculation of the
environmental impacts can be summarised as follows:
environmental impacts are based on those associated with air pollution only – impacts to soil and water are
not considered. The impacts associated with air pollution are much better understood than those of soil and
water pollution;
climate change impacts are monetised using the methodology recently developed by the UK Government2;
air pollution impacts are monetised using the UK-specific damage costs taken from the Clean Air for Europe
(CAFE) programme3. The dataset includes both the impact of pollution originating in the UK on European air
quality as well as damage costs for pollution occurring in the oceans – this is required when considering
emissions associated with shipping recyclate overseas;
for the climate change impacts we consider results both excluding and including the biogenic CO2 emissions.
Whilst the exclusion of the biogenic CO2 impacts is typical when a life cycle analysis (LCA) approach is taken
in this type of analysis, analyses undertaken using the CBA framework typically include these emissions. We
1 These external costs include those associated with days lost to ill-health, and costs resulting from hospital admissions, etc.
2 DECC (2009) Carbon Valuation in UK Policy Appraisal: A Revised Approach. Climate Change Economics, Department of Energy and Climate Change, July 2009
3 M. Holland and P. Watkiss (2002) Benefits Table Database: Estimates of the Marginal External Costs of Air Pollution in Europe, Database Prepared for European Commission DG Environment; AEAT Environment (2005) Damages per tonne Emission of
PM2.5, NH3, SO2, NOx and VOCs from Each EU25 Member State (excluding Cyprus) and Surrounding Seas, Report to DG Environment of the European Commission, March 2005
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 29
present results excluding the biogenic CO2 in the central case, with sensitivity analysis considering any
variation in the results that would occur as a consequence of the inclusion of this impact;
in modelling the behaviour of landfill, we assume a landfill gas capture rate of 50%;
for the Phase 2 models, incineration facilities are assumed to generate only electricity at a gross generation
efficiency of 24%. The incinerator is assumed to meet the requirements of the Waste Incineration Directive
with respect to the pollution abatement equipment installed;
we assume the electricity generated by incinerator offsets the production of electricity that would otherwise
have been generated using combined cycle gas turbine (CCGT) plant in line with UK government guidance4.
Our model considers both the climate change and air quality impacts associated with this avoided
generation;
the environmental benefits associated with reprocessing the recycled material are based on data provided by
WRATE. We consider only the impacts associated with climate change as the impacts on air quality (both
positive and negative) are likely to happen outside Wales in many cases;
we assume energy use at the MRF to be 35kWh of electricity per tonne of material treated and 2 litres of
diesel per tonne; energy requirements for the treatment of recyclate at a transfer station are assumed to be
4kWh of electricity and 1 litre of diesel. In both cases our estimates have been developed based on data
provided by currently operating facilities obtained through the course of this project;
with regard to the financial costs, we exclude both the impact of fuel duty and landfill tax from the final
totals that combine the financial and environmental costs. The duty and the tax are intended to offset some
or all of the environmental impact associated with the pollution from road transport and landfilling waste.
Both types of pollution are separately accounted for in the consideration of environmental damages; thus the
duty and the tax are excluded from the final total to avoid double-counting this part of the impact.
The results of the environmental modelling are presented as part of the overall CBA in Section 8.0.
7.0 Social impacts
Increasingly, importance is being placed on consideration of the social costs and benefits associated with
alternative management routes for waste. While the methodological approach to incorporating environmental
costs and benefits using monetised damage costs in the framework of CBA is well established and widely
accepted, there is no such consensus on the approach to social impacts.
One recent study undertaken for Defra used an approach called the Social Return on Investment (SROI) to try
and integrate the environmental, economic and social impacts associated with a number of case studies of third
sector involvement in waste management5. The report demonstrates that the SROI is effective at ensuring that all
the stakeholders who may benefit from specific activity are identified, but in so doing, the approach can involve
double counting.
In one example of this, the approach counts as benefits:
avoided landfill tax; plus
avoided greenhouse gas impacts of landfill; plus
reduced external environmental impacts of landfill.
In addition, it is stated in the report that „it is not possible to directly compare the SROI ratios generated for the
case study projects as they describe value generated in different activities and different contexts‟. This is clearly
not acceptable if seeking to compare alternative collection routes. For this, it is necessary to use an approach,
such as CBA, which does not bias the analysis in favour of one or other of the approaches under comparison.
4 See, for example: DECC (2009) Carbon Valuation in UK Policy Appraisal: A Revised Approach. Climate Change Economics, Department of Energy and Climate Change, July 2009
5 Defra (2009) Benefits of Third Sector Involvement in Waste Management, Defra Waste and Resources R&D project WR0506
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 30
However, even though social impacts are not always so amenable to inclusion within a monetised approach, this
does not mean that such impacts do not exist or are not valid, especially for decision-makers who may find
themselves under pressure to consider social factors. Our approach, therefore, is to discuss the social impacts,
and present relevant data alongside cost and environmental data, but without seeking to place a monetary value
on these impacts.
There are a number of different social impacts that may arise from the way in which waste is collected. These
may include:
the nature of the employment, i.e. total levels, the location, and whether full or part time, directly employed
or via an agency, indoors/outdoors;
the way in which collection vehicles may affect traffic flow under differing approaches, possibly causing
congestion;
potential visual disamenity and inconvenience associated with on street containers for different approaches
to collection.
Increased employment is intuitively of social value to the individual employed, the local authority area, and to
Wales and the UK as a whole through increasing the tax base. However, attributing any kind of monetary value
to employment is not a straightforward matter. Guidance has been sought from the Welsh Assembly Government
economists on whether there is a particular monetary value that might be used in assessments looking at
employment and job creation and whether this varies by location. Guidance was also sought on the use of
multiplier effects. However, the response was that there are no such values or indeed distributional weights
applied in Assembly Government analysis, and that the more appropriate way to deal with employment and other
social impacts is as we have proposed, through a narrative approach6.
It is worth noting that the costs of employment will already be incorporated within the CBA, alongside the other
relevant costs. By placing the full time equivalent (FTE) figures alongside, it will be possible to present and
compare the net cost:gross jobs ratio of the competing options. The qualitative distinction will also be made
between the proportion in permanent posts, those on fixed term contracts, and those employed on a more casual
basis such as via agencies. A distinction could also be made between the number working indoors, and those
outdoors. Again, this will be presented alongside the CBA rather than incorporated within it.
In Phase 3, comment will be made as to the employment characteristics of the competing approaches, based on
the crewing levels outlined in Section 5.0.
Another potential impact is that relating to traffic congestion from alternative collection methods. The Department
of Transport uses an approach based on the value of travel time savings to evaluate the potential benefits from
road schemes in the expectation that they will reduce travel time, which is taken to be unproductive time7.
Following this approach, different values of time are used based on whether travel is undertaken within working
time, or outside, with working time having the greater value. While such an approach could theoretically be
applied to consideration of the alternative collection routes, the data requirements would be considerable. It
would be necessary to know how the impacts of collection on traffic congestion might vary between alternative
systems, and to know how many people might have their journey times increased, and by how long, and indeed
the proportion of road users who might be travelling during working hours. Accordingly, this analysis will present
a description of the collection requirements in terms of how the vehicles are operated rather than seeking such
data on impacts.
Alternative collection systems will also have differing requirements in terms of the number of containers placed
outside the household. To the extent that they vary, there may be differing impacts in terms of obstruction and
the perceived unsightliness of such containers. This potential „disamenity‟ could theoretically be captured through
ascertaining people‟s marginal „willingness-to-pay‟ (WTP) for a reduction in the level of „clutter‟ outside their
6 Personal communication with Andrew Hobden, Welsh Assembly Government Economist, 19 November 2010.
7 DfT (2009) Values of Time and Operating Costs, Transport Analysis Guidance Unit 3.5.6, April 2009. Available at http://www.dft.gov.uk/webtag/documents/expert/pdf/unit3.5.6.pdf
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 31
homes. However, again the research requirements would be significant, and therefore the approach will be to
describe the number of containers required in each instance, alongside the cost data for each scheme.
7.1 Health and safety
Health and Safety data was requested from the authority for the three year period from April 2007 to March 2010
for both the collection of dry recyclables at the kerbside and the handling and sorting of dry recyclables either at
a bulking depot or MRF. An electronic template was supplied which requested the following information:
the number and category of RIDDOR (Reporting of Injuries, Diseases and Dangerous Occurrences
Regulations) incidences that have taken place;
the format by which RIDDOR incidences have been recorded and copies of those records where applicable;
the number and category of non-reportable accidents that have taken place;
the format by which non-reportable accidents have been recorded and copies of those records where
applicable;
the number and category of non-reportable near misses that have taken place;
the format by which non-reportable near misses have been recorded and copies of those records where
applicable;
how the data the authority has recorded on accidents, near misses, sickness and absence is used within the
waste department and the authority as a whole;
the numbers of employees (FTE) by category of task – drivers, loaders, sortline operatives etc.;
the number of frontline staff days lost through work related and non-work related sickness including the
nature of the operation to which any work related sickness was related;
the number of frontline staff days lost through work related and non-work related absence including the
nature of the operation to which any work related absence was related.
7.1.1 Summary of data received
A partially completed questionnaire was received from Pembrokeshire County Council. Numbers of reportable and
non-reportable accidents were provided for all waste collection services as Pembrokeshire where unable to
separate out the dry recycling kerbside collection service data from other waste collection services data. Staff
numbers were provided for the dry recycling collection service while sickness data was provided for both dry
recycling and the other waste collection services. No data was provided for the handling and sorting of dry
recyclables by either the authority or the two MRF contractors.
Although it will not be possible to draw any conclusions from the data regarding accident rates in relation to
collection methodology, the following initial high level conclusions can be drawn from the data supplied:
the number of RIDDOR incidences reported has dropped from 14 in 2007/08 to nine in 2008/09 and then to
seven in 2009/10;
the total number of non-reportable accidents recorded was 43 in 2007/08. This decreased by 58% to 18 in
2008/09 but increased by 61% to 29 in 2009/10;
the most frequently occurring category of non-reportable accident recorded was „slips, trips and falls‟ at 41%
of all recorded accidents followed by „other manual handling related injuries not involving cuts and grazes‟ at
33% and „struck by a moving object‟ at 19%; and
no near misses were recorded.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 32
8.0 Combined cost-benefit analysis (CBA)
This section presents the combined impact of the external cost associated with the environmental impact of each
system together the financial cost of operating that service. Given the difficulties associated with trying to
quantify the social impacts of the kerbside collection systems, social costs are not included in the results
presented here. The section first presents results specific to Pembrokeshire, before discussing these results
alongside those found for the other five case study authorities that have contributed to this phase of work.
8.1 Individual authority results
Table 9 presents the headline results for Pembrokeshire, whilst Table 10 provides a breakdown of the climate
change (greenhouse gas) environmental impacts, based on the approach detailed in Section 6.3. Details on the
breakdown of the financial costs have already been provided in Section 5.2.3. An adjustment has been made to
the overall combined net cost of the dry recycling and residual waste services in order to ensure that there is no
double counting between the financial costs and the environmental costs. Fuel duty and the landfill tax are
intended to offset some or all of the environmental impact associated with the pollution from road transport and
landfilling waste. Hence both types of pollution are separately accounted for in the consideration of environmental
damages, and need to be excluded from the financial costs that form part of the overall CBA.
Table 9 Headline results (excluding biogenic CO2 emissions)
Annual Total Per-household Per-tonne
FINANCIAL
Total Net Cost £5,752,123 £99.48 £174.20
Total Net Adjusted for Tax and Duty £4,296,377 £74.30 £130.11
ENVIRONMENTAL
Climate Change Impact £1,603,070 £27.72 £48.55
Air Quality Impact £434,864 £7.52 £13.17
Total Environmental Impact £2,037,934 £35.24 £61.72
TOTAL
Total Environmental + Financial Cost £6,334,311 £109.55 £191.83
Table 10 Breakdown of greenhouse gas environmental impacts
£
RESIDUAL WASTE
Collection £24,974
Residual Waste Treatment £1,626,728
SUB-TOTAL £1,651,702
DRY RECYCLING
Collection £23,216
Onward Transport £5,527
MRF Treatment £4,016
Bulking Depot £0
Benefits of Dry Recycling -£121,059
Treatment of Rejects £39,668
SUB-TOTAL -£48,632
TOTAL £1,603,070
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 33
8.2 Comparison with other case study authorities
Individual authority reports equivalent to this report have been provided to and reviewed by each case study
authority. This section highlights the key findings across the case studies and summarises the information that
has subsequently been used to develop the Phase 3 Wales-wide modelling of the different collection systems.
8.2.1 Fate of materials
A detailed program of research attempted to trace the path of all collected dry recycling from the point of
collection to the point of the material being reprocessed or sent for disposal. This assessment reveals a complex
pattern for all the case study authorities. In the case of co-mingled and two-stream authorities, the material
passes through MRF facilities where in many cases it is mixed with material from other authorities and/or
commercial waste. Material rejected from primary MRFs is in some cases further sorted at a secondary MRF,
along with substantial amounts of material from other sources. Kerbside sort material is bulked at collection
depots. However, in both kerbside sort case studies some processing of metal and plastic containers is conducted
before the material is shipped onwards. In all case studies, some grades of material are sold on through a chain
of merchants and/or intermediate processors before the material arrives at a reprocessor. In many cases material
from various sources is mixed with the case study material during these transfers. The following sections detail
some of the findings from this part of the research.
Types of MRF
Four of the authorities use primary MRFs. The range of materials dealt with by these MRFs is broadly similar, with
two key exceptions. Pembrokeshire do not specify glass as a permissible material and RCT collect dry recycling
sacks co-mingled with garden waste in the same vehicle compartment, with the garden waste therefore requiring
separation at the MRF. As noted above, the case study authorities that specify two-stream set out from
householders, Monmouthshire and RCT, treat the material as a single-stream co-mingled material from the point
of collection onwards. Two authorities, Cardiff and Monmouthshire, utilise medium to large sized MRFs that are
relatively mechanised. Cardiff operates its own facility and Monmouthshire hauls its co-mingled material to SCA in
Southampton. Pembrokeshire and RCT both use smaller facilities. Pembrokeshire utilises two MRFs, one operated
by SITA and another by A J Recycling. RCT operates its own MRF and sends material from part of the authority to
a small facility operated by Siteserv. All the smaller MRFs studied have similarities in that they are relatively non-
mechanised and for many materials rely on positive hand picking from conveyor belts.
MRF reject rates
All the co-mingled and two-stream authorities report a reject rate to WDF, representing the amount of material
that is sent for disposal from the primary MRF. In general, we have used the values stated in WDF for 2009/10.
However, the following exceptions to this have also been applied. In the case of Cardiff, we also noted the MRF
reject rate from the secondary MRF used by the authority as part of the overall reject rate for Cardiff. In the case
of Monmouthshire, we have used more recent management data from SCA Recycling, which indicates a lower
reject rate than that reported in WDF.
Merchants, intermediate processors and reprocessors
The majority of material identified in the case studies is reprocessed in the UK and for some materials the end
destinations are similar for specific materials. Examples where case studies differ and examples of material
streams that differ between systems are as follows:
The paper and cardboard material collected from Cardiff and Monmouthshire results in three grades of paper
product; news and pams, soft mixed and OCC cardboard, with soft mixed accounting for more material than
the other grades. This is typical for larger MRFs. Gwynedd is unusual for a kerbside sort collection in that the
only paper product shipped from their depots is a soft mixed grade.
All paper grades from Monmouthshire are exported. The soft mixed paper from Gwynedd is bought by Palm
Paper, who did not clarify end reprocessing destinations. News and pams from all other case study authorities
is reprocessed at the UPM-Kymmene plant at Shotton. The soft mixed paper produced by Cardiff is bought by
Severnside and reprocessed in Kent.
All glass is collected on a colour mixed or co-mingled basis. Glass from the kerbside sort schemes is sent for
mechanised colour separation at either the Recresco plant in Ellesmere Port or the Viridor plant in Sheffield.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 34
These processes result in a significant proportion of input material being sent for reprocessing into container
glass. Positively picked glass from the RCT MRF is sent via the same process. The remaining glass from the
RCT MRF is either „composted‟ along with a predominantly organic fine fraction and used as landfill cover or
occasionally is sent for aggregates. The glass from Monmouthshire and Cardiff is sent for processing into
aggregates at the Nationwide facility in Llandarcy. Pembrokeshire does not collect glass from the kerbside.
The majority of rigid plastic packaging is sent to one of four plastic recycling facilities (PRFs) where the
material is re-sorted into separate polymers, with any metals present being reclaimed. The operators of the
PRFs stated that the majority of separated polymers are reprocessed in the UK.
Plastic films are shipped as a grade from all the co-mingled authorities and in all cases this material is
exported and the end destination is unknown.
Steel containers are all reprocessed in the UK at the Tata plant in Port Talbot, apart from material from
Monmouthshire which is purchased by EMR and sent to various reprocessors across Europe. Tata only accept
steel via accredited aggregation centres, so in all cases the material is sent via a third party. In the case of
Gwynedd and RCT, the material is sent via Pontypool Steel where it may be resorted.
Aluminium Cans (UBCs) from Cardiff, Newport and RCT are reprocessed at the Novelis plant in Warrington.
UBCs from Monmouthshire are sent to Alutrade where they may be resorted. UBCs from Gwynedd are sent to
Tom Martin and Co to be sold on to various reprocessors. In both cases, the final reprocessor is unknown.
Material quality
All participating authorities, MRF operators, merchants, intermediate processors and reprocessors were asked
about their procedures for assessing material quality. Two reprocessors reported that they conduct sampling of
incoming material where material is sorted and weighed. All other reprocessors and intermediate processors
reported that they rely on visual inspections to assess the quality of material. Previous work by Resource Futures
for WRAP8 tested the efficacy of visual assessment of material by conducting a visual assessment and then
sorting and weighing the material. This work found that visual assessments are an inaccurate method of
determining material quality and only suitable for identifying extreme levels of certain contrary materials.
All merchants, intermediate processors and reprocessors reported that they did not have any problems with
material quality from the case study authorities that were currently supplying material and that no loads had been
rejected. In a few cases there were reports that they had previously dealt with a case study authority, but no
longer purchased this material, which was attributed to poor quality.
We had planned to use reprocessor quality monitoring data to estimate the composition of products from each
case study authority which in turn would inform Phase 3 of the study. The small amount of data that was made
available to the project was used, but in general we were not as successful as we had hoped in obtaining credible
data from reprocessors. The project relied primarily on previous compositional work conducted by WRAP and
specific compositional assessments conducted for this project.
End uses of materials
Each product being sent from a MRF contains materials that are wanted by reprocessors and will be reprocessed
into new materials and also materials that are not wanted and are termed contraries in this report. This section
describes the fate of the materials, including contraries, for each product stream.
News and pams when shipped as a product from all case study authorities was reprocessed into newsprint.
There was no secondary sorting of this material prior to entering the reprocessing process. During this
process, the material is pulped and screened. The fibre items that are not specified (excess grey and white
board, brown board and some other fibre materials) are pulped and pass through screens to become
newsprint. Non-pulpable materials are generally caught on the screens and removed to become a process
residue. During this process the contrary items are coated in fibres and therefore there is loss in fibre material
to residue which is proportionate to the amount of contraries. All process residues are currently landfilled.
8 Report commercial sensitive and not publically available.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 35
Soft mixed from one authority (Cardiff) is reprocessed into plasterboard lining; for the remainder, the fate is
either unknown or assumed to be reprocessed into packaging items such as the internal fluting in corrugated
cardboard or fibre moulded packaging inserts. We have assumed that the process involves the material being
pulped and therefore non-pulpable contraries will be removed and a corresponding amount of fibre will be
lost. With the one known UK reprocessor, the fate of contraries is landfill. For exported material the fate of
contraries has also been assumed to be landfill.
OCC (cardboard) when shipped as a product has various destinations, but in all known cases is shipped to
mills producing corrugated cardboard. We have assumed that the process involves the material being pulped
and therefore non-pulpable contraries will be removed and a corresponding amount of fibre will be lost. The
fate of contraries has been assumed to be landfill.
Glass, in all cases, is shipped as a mixed colour grade to one of two distinct processes. Where material is
shipped to the reprocessors that mechanically colour sort a proportion of the material, then several possible
mass flows were noted by the reprocessors. One of the colour sorting reprocessors deals with incoming
material from source segregated glass schemes (kerbside sort and bring schemes) separately from glass from
other sources (MRF glass). This reprocessor reported a high recovery rate of glass to re-melt into glass
packaging production (85% to 90%). The remaining glass (mostly that with a particular size lower a 20mm) is
sent for a variety of reprocessing applications such as aggregates, filtration media and fibreglass production.
For environmental modelling purposes we have allocated this latter group of material to an aggregates fate,
which seems to be the predominant end use for this material. Metal contraries are removed as aluminium and
steel grades and sent for reprocessing. We have assumed a 90% recovery of these materials. The remaining
residue is sent to a MRF for further sorting. We have assumed a 50% recovery of these materials. The
remainder of contraries have been assumed to be landfilled. The other glass sorting facility reported a facility
average recovery for re-melt into packaging glass at 85% and this is the value that was used for the relevant
case study authorities. The remaining glass is used for a variety of reprocessing applications such as
aggregates, filtration media and fibreglass production. For modelling purposes we have allocated all this group
of material to an aggregates fate. Residues are sent to EfW (incineration process). In a number of cases,
glass was sent to an intermediate process which mechanically grades the material for aggregate production.
This process involves the material being left outside for a period of time where some organic materials
present in the initial product stream will degrade. The material is then screened. Material that does not pass a
5mm screen is sent via an overband magnet and eddy current separator where steel and aluminium is
recovered. The glass material and any contraries passing the 5mm screen are used as aggregates, and the
remaining material is assumed to be landfilled.
Rigid plastic packaging. The majority of this material is sent to plastic reclamation facilities (PRFs) where the
material is sorted into polymers and any metal contraries are recovered for recycling. The facilities that
responded claim all plastics that enter the facility are either graded into polymers or a small amount is
shipped as mixed plastics for recycling abroad. We have modelled a 100% reclamation of plastics. The
remaining non-metal contraries have been assumed to be sent to EfW (incineration).
Plastic film is, in all cases, exported to the Far East where little is known about its ultimate fate. We have
assumed 99% recovery of plastic materials to a recycling fate and 90% recovery of metal contraries. The
remaining materials we have assumed are sent for EfW (incineration).
Steel packaging is virtually all reprocessed at Tata Steel, Port Talbot. When the material arrives at this facility
there is no further sorting. All steel is processed into steel, the contraries are incinerated in the process which
results in either a gas emission or they contribute to the formation of a process slag. The process slag is
recycled in cement manufacturing.
Aluminium cans (UBCs) are mostly sent to Novelis in Warrington. The aluminium is all recycled into aluminium
ingots for the manufacture of aluminium packaging. The aluminium recovery process involves some removal
of contraries at the beginning of the process, which are sent to landfill. We have assumed that 50% of paper
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 36
contraries and 80% of other contraries are removed. The remaining contraries are incinerated in the paint de-
coating process.
Summary
As shown in Figure 11, MRF rejects occur in all co-mingled and two-stream authorities. The lowest reject rate is
for Cardiff, which is a relatively automated process and utilises a secondary MRF for the sorting of the reject from
its primary facility. The remaining facility reject rates are broadly similar. Process losses, however, differ distinctly
between the authorities. The most significant process losses are attributable to relatively high levels of contraries
in soft mixed paper. The two facilities that produce soft mixed, Cardiff and SCA (Monmouthshire) show the
highest process losses. The three other MRFs that do not produce soft mixed show markedly lower process
losses, though they are still higher than the process losses calculated for kerbside sort systems. Process losses
are also made more significant due to the difference in sorting techniques between the large, highly automated
MRFs and smaller, simpler facilities. In larger MRFs, material is primarily mechanically sorted, with contraries
removed by hand, whereas in smaller MRFs it is common to find products are sorted with a positive hand pick,
whereby the targeted materials are removed from the line, leaving the unwanted materials to pass. This latter
approach generally produces less contaminated product streams and therefore lower process losses further down
the reprocessing line. It also generally produces higher MRF reject rates, as more contraries are captured into this
stream and some of the targeted material is missed and is inadvertently rejected. The two authorities using less
mechanised MRF processes are Pembrokeshire and RCT, and although these authorities show slightly higher MRF
reject rates than the others, they are not markedly so.
It is worth noting that the process losses for all glass accepting MRFs are likely to be understated. The MRF reject
rates and process loses for RCT are likely to understate the real picture, as the end of line rejects are trommelled
and the fines either composted or sometimes reprocessed as aggregates. The contraries in this material are not
counted as disposed to landfill or EfW and therefore do not appear as a loss. Similarly, where contraries pass into
aggregates they are not counted as being sent for disposal and therefore do not appear as losses.
A small quantity of contrary items ends up being reprocessed into a product, but the majority are removed either
as MRF reject or as process losses. It is notable in the co-mingled and two-stream systems that the removal of
contraries only accounts for part of the overall loss. For example of the 16% loss calculated for Monmouthshire,
only 6% of the loss comprises of contraries, whereas 10% relates to the loss of targeted recyclables, most of
which have ended up in the wrong product stream.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 37
Figure 11 Case study MRF reject rates and process losses
6.8%8.0% 8.4%
9.4%
8.4%
2.8%
7.9%
1.9%
3.0%
3.6%
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
Cardiff Gwynedd Monmouthshire Newport Pembrokeshire RCT
MR
F R
eje
ct R
ate
and P
roce
ss L
oss
es
(%)
Process Loss Rate
MRF Reject Rate
8.2.2 Financial costs
Table 11 and Table 12 summarise the net costs for the kerbside dry recycling and residual waste services for
each of the case study authorities. Details on how these costs have been calculated can be found in Appendix 4.
The net cost of the dry recycling service varies from £14 per household in Newport to £50 per household in
Gwynedd, and the pattern is similar when looking at the cost of the service per tonne of dry recycling collected,
with costs varying from £79 to £371 per tonne of dry recycling collected. Given that the two kerbside sort
services provide the lowest and the highest overall cost, it appears that collection system type is not the key
driver for the pattern of costs across the authorities. The urban authorities have the lowest collection costs,
though part of the lower cost for Cardiff is likely to be due to its fortnightly collection frequency, with all other
authorities operating a weekly service. In addition, a number of key factors vary between the authorities that also
help to drive the differential in costs; these include:
The materials income received by those authorities who market their own materials; this is likely to be driven
by, for example, whether or not an authority sells on the spot market or has entered into longer-term
contracts (and if so, the nature of those contracts). Fundamentally, it is likely that ability to negotiate high
values in the market place varies between authorities, although taking a one-year view of this (as we have)
may not provide a complete picture, as authorities currently exploiting high spot market values may be more
exposed to the risk of a downturn in commodity markets in future.
MRF gate fees/operating costs; depends on factors such as what infrastructure is present and therefore how
much capacity needs to be filled by the MRF (and the gate fee that is subsequently offered), and how the
facility is run (scale of operation, value being obtained for material at end of MRF process etc.).
Differences in unit labour costs between authorities; driven by location, historical circumstances and, to some
extent, by whether the staff are permanently employed or are agency temps (and the impact of this on staff
on-costs).
The efficiency of the collection services; this will depend on factors such as vehicle technology, round
configuration, crewing levels, shifts employed and management systems.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 38
It is considered unlikely that the low per household cost achieved in Newport could be replicated across Wales.
Newport‟s collection partner Wastesavers is a not-for-profit social enterprise. Lower running costs and the
absence of shareholders mean all surplus profits are reinvested into service delivery to reduce unit costs. It
should also be noted that with increased recycling towards 70% the “per tonne” based payment mechanism used
will also increase the cost per household.
The collection costs for residual waste are less variable than the collection costs for dry recycling, with costs
varying from £20 per household in Monmouthshire to £34 in RCT. Thus, unlike the dry recycling service, the
urban authorities do not necessarily have the lowest residual waste collection costs. The collection costs are
cheaper where the service is predominantly fortnightly (Monmouthshire, Gwynedd and Newport) compared to
where it is predominantly a weekly service. When disposal costs for residual waste are also considered, total
residual waste costs vary from £50 per household in Gwynedd to £76 per household in RCT, and from £116 per
tonne of waste collected in Gwynedd to £147 per tonne in Pembrokeshire.
Table 11 Dry recycling and residual waste net costs (£ per household)9
Cardiff10 Gwynedd Monmouthshire Newport Pembrokeshire RCT
Dry Recycling Net
Cost
£26 £50 £32 £14 £35 £34
Residual Waste
Collection Cost
£28 £26 £20 £26 £33 £34
Residual Waste
Disposal Cost
£35 £24 £35 £45 £32 £41
Residual Waste
Total Cost
£63 £50 £56 £70 £65 £76
Total Net Cost £89 £100 £87 £84 £99 £110
Total (adj for LF
tax & duty)
£65 £75 £65 £60 £74 £77
Table 12 Dry recycling and residual waste net collection costs (£ per tonne waste collected)
Cardiff Gwynedd Monmouthshire Newport Pembrokeshire RCT
Dry Recycling Net
Cost (£ per Tonne
Dry Recycling
Collected)
£133 £371 £166 £79 £268 £156
Residual Waste
Net Cost (£ per
Tonne Residual
Waste Collected)
£144 £116 £143 £145 £147 £118
Table 11 also shows the adjusted combined net cost of the dry recycling and residual waste services that is used
when both the financial and environmental costs are considered in the cost benefit analysis that follows in Section
8.2.4. This ensures that there is no double counting between the financial costs presented in this section and the
environmental costs described in Section 8.2.3. The fuel duty and the landfill tax are intended to offset some or
all of the environmental impact (externalities) associated with the pollution caused by road transport and
landfilling waste. Hence both types of pollution are separately accounted for in the consideration of environmental
damages, and need to be excluded from the financial costs that form part of the overall CBA. The total cost,
9 As noted above, the cost figures reported in this section are based on normalised costs. See Appendix 4 for a comparison of normalised and non-normalised costs for recycling and refuse collection.
10 Cardiff is currently forecasting a considerable underspend versus the 2010/11 budget, with a significant proportion of this relating to MRF operations and material sales income. Therefore, it seems likely that the figures we have analysed represent an overstatement of Cardiff‟s actual costs, in this year at least.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 39
adjusted for landfill tax and fuel duty, varies from £60 to £77 per household, with Newport running the service at
the lowest overall cost, and RCT at the highest overall cost.
8.2.3 Environmental performance
Figure 12 demonstrates the overall climate change emissions which result from the combined dry recycling and
residual waste collection and treatment services in each authority. Results are ranked in order from left to right,
from the highest emissions to the lowest emissions produced per 50,000 households. Despite a relatively high
emissions offset from the dry recycling service, the overall service in RCT produces the highest tonnes of CO2
equivalent overall, due to the more significant emissions associated with the residual waste service. Similarly, the
service in Monmouthshire produces the lowest overall emissions, with the lowest overall residual waste emissions
and a relatively high offset associated with the dry recycling service. The overall emissions associated with the
residual waste service are three to four times greater than those associated with the dry recycling service, and
this is driven primarily by the impact of residual waste disposal by landfill (which contributes around 97 to 99% of
the total residual waste service emissions).
Figure 12 Climate change emissions from dry recycling and residual waste collection and treatment (tonnes CO2
equivalent per 50,000 households).
-10,000
-5,000
0
5,000
10,000
15,000
20,000
25,000
RCT Cardiff Newport Gwynedd Pembrokeshire Monmouthshire
GH
G Im
pact
s (t
onnes
CO
2e p
er 50,0
00 h
hld
s)
Residual Dry Recycling Total
Figure 13 illustrates a breakdown of the factors that contribute to the overall environmental impact of the dry
recycling system in each authority including, in this instance, impacts associated with air quality as well as
greenhouse gas impacts. Results are again ranked in order from left to right, demonstrating the lowest to highest
overall benefit derived from the dry recycling system. Similarly to the financial costs discussed above, there is no
apparent pattern in climate change emissions according to the dry recycling collection system employed. The
schemes will be likely to include a number of sub-optimal components, including collection productivity (related in
part to technology) and the fate of materials (for instance, news and pams going into soft mix product rather
than being reprocessed into news and pams), making them difficult to compare.
The benefits of dry recycling outweigh any increase in emissions resulting from the collection and processing of
dry recycling material, and it is this which drives the overall order of results obtained in Figure 13. In addition, the
combined reject and process losses requiring subsequent disposal are also particularly significant for Cardiff and
RCT in reducing the overall benefit obtained from the system. Onward transport is also particularly significant for
Monmouthshire, with a notable amount of material (and in particular news and pams, soft mix and card) being
exported for reprocessing from SCA.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 40
Figure 13 Breakdown of environmental damage costs (excluding biogenic CO2 emissions but including air quality
impacts) per 50,000 households
-6,000
-5,000
-4,000
-3,000
-2,000
-1,000
0
1,000
Cardiff Gwynedd Monmouthshire Pembrokeshire RCT Newport
Dry
Recy
clin
g T
onnes
CO
2e p
er
50,0
00 h
hld
s
Collection
Onward transport
MRF treatment
Bulking materials
Benefits of dry recycling
Treatment of rejects/ process losses
Cardiff Gwynedd Monmouthshire Pembrokeshire RCT Newport
Total Dry Recycling
GHG Impacts (tonnes
CO2e per 50,000 hhlds
-1,675 -2,621 -2,826 -2,934 -3,450 -4,570
In order to provide a financial cost comparable metric, air pollution impacts were monetised using the UK-specific
damage costs taken from the Clean Air for Europe (CAFE) programme11 and climate change impacts were
monetised using the methodology recently developed by the UK Government12. It is important to note that the
climate change impacts methodology includes two prices of carbon, a „traded‟ price, which relates to the
European Union Emission Trading Scheme and covers anything involving electricity generation, and a „non-traded‟
price, which is applied to other impacts, including to methane produced by landfill and to diesel. The non-traded
price is more than double the cost per tonne of carbon relative to the traded price. As demonstrated in Figure 12,
the majority of climate change emissions relate to residual waste disposal. Given that all authorities use landfill as
their primary means of disposal, and that the emissions related to this are factored in at the higher non-traded
price of carbon, the overall impact of residual waste disposal is further emphasised when the emissions are
monetised. This is demonstrated in Table 13; although Newport is the highest performer in terms of reduced
tonnes of CO2 equivalent from its dry recycling service, it produces more residual waste per household than most
other authorities (except RCT), which drives up the overall environmental cost for this authority, so that only RCT
generates at a higher overall carbon emissions cost than Newport.
11 M. Holland and P. Watkiss (2002) Benefits Table Database: Estimates of the Marginal External Costs of Air Pollution in
Europe, Database Prepared for European Commission DG Environment; AEAT Environment (2005) Damages per tonne Emission
of PM2.5, NH3, SO2, NOx and VOCs from Each EU25 Member State (excluding Cyprus) and Surrounding Seas, Report to DG Environment of the European Commission, March 2005
12 DECC (2009) Carbon Valuation in UK Policy Appraisal: A Revised Approach. Climate Change Economics, Department of Energy and Climate Change, July 2009
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 41
Table 13 Climate change external costs (£ per household)
Cardiff Gwynedd Monmouthshire Newport Pembrokeshire RCT
Residual Waste £28.7 £30.4 £24.8 £33.3 £28.6 £38.3
Dry Recycling £0.5 £-0.8 £-0.5 £-2.2 £-0.8 £-0.7
Total £29.2 £29.6 £24.3 £31.1 £27.7 £37.6
The overall environmental cost of the dry recycling and residual waste services across each authority is presented
on a per household basis in Table 14. Aside from RCT, whose total environmental cost is £47 per household, the
environmental costs for the remaining five authorities are similar, ranging from £32 to £38 per household.
Table 14 Environmental cost £ per household (dry recycling and residual waste services)
Cardiff Gwynedd Monmouthshire Newport Pembrokeshire RCT
Greenhouse Gases £29 £30 £24 £31 £28 £38
Air Quality £6 £8 £8 £6 £8 £9
Total £35 £38 £32 £37 £35 £47
8.2.4 Combined financial and environmental performance
The overall net costs presented in Table 11 are added to the total environmental costs in Table 14 to give the
combined financial and environmental performance per household presented in Figure 14. Newport provides the
cheapest overall dry recycling and residual waste service when both financial and environmental performance are
considered, due to its low financial cost, driven primarily by the £14 per household dry recycling collection cost.
The lower environmental cost associated with the Cardiff and Monmouthshire collection systems brings the
overall cost for these two authorities close to that of Newport, though this reflects the lower residual waste per
household in these authorities rather than a greater offset in emissions from the dry recycling services. RCT is the
most expensive service both financially and environmentally, and also had the highest overall greenhouse gas
emissions (Figure 12).
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 42
Figure 14 Combined financial and environmental cost per household (financial costs adjusted for landfill tax and
fuel duty)
£-
£20.00
£40.00
£60.00
£80.00
£100.00
£120.00
£140.00
RCT Gwynedd Pembrokeshire Cardiff Monmouthshire Newport
Cost
per hhld
(£)
Total Environmental
Total Financial
RCT Gwynedd Pembroke-
shire Cardiff
Monmouth-
shire Newport
Financial Cost £77.33 £75.16 £74.30 £65.42 £65.13 £59.61
Environmental Cost £46.83 £37.87 £35.24 £35.13 £32.24 £37.15
Total Cost £124.16 £113.03 £109.55 £100.56 £97.37 £96.75
8.2.5 Health and safety
Each of the case study authorities provided data relating to health and safety for both the collection of dry
recyclables at the kerbside and the handling and sorting of dry recyclables either at a bulking depot or MRF.
Although data was requested from the authorities in a standard format, the data obtained was not useable for
any meaningful comparison between the different systems in operation. In some cases, data was only available
at an overall waste services/directorate level. In Monmouthshire, there had been a switch from a kerbside sort to
a co-mingled service part way through 2009/10, with no data yet available for the current co-mingled service. In
all cases, even where data was available for handling and sorting operations, no data was available for the MRF
operations. Authorities do not typically differentiate their own data in terms of operational differences. Data tends
to be collected by departments, so that, for example, street cleansing accidents are included along with refuse
collection and recycling operations. Injuries to loaders are typically generically collated, and attributing them to
either refuse collection or recycling operations retrospectively cannot easily be done. As such, differences within a
system are also not discernable.
In itself, this is of interest as it suggests that those managing these operations do not see the collation of these
statistics at such a detailed level as an operational tool with which to investigate underlying causes of incidents.
This is perhaps a reflection of the way that in the UK accident statistics required by RIDDOR are the benchmark
by which operators gauge themselves. As this is first and foremost a tool to assist the Health and Safety
Executive (HSE) in accident investigation it has to be, by necessity, generic in its application.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 43
It is thus difficult to draw any meaningful conclusions about the relative merits of the different dry recycling
collection schemes in terms of safety and health from the case study data supplied.
8.3 Case studies: Overall results and conclusions
Examining six case study authorities in detail has enabled us to gain insight into:
the flow of dry recycling materials and the associated environmental costs from the point of collection through
to the end destination in six Welsh authorities; and
the financial costs for the initial collection and sorting of those dry recyclables.
Although the costs for collection and sorting of dry recyclables were found to vary quite significantly between the
case studies, this variation could not be attributed to variation in collection system type. The urban authorities
were found to have the lowest collection costs, probably driven in part by the collection frequency for Cardiff,
with this being the only authority not to collect dry recycling on a weekly basis. A number of additional factors
also made it difficult to directly compare system costs, including variations in materials income received, MRF
gate fees or operating costs incurred, unit labour cost variations paid and efficiency of collection services.
Regarding the environmental performance of the dry recycling systems, there was again no apparent pattern in
greenhouse gas or air quality emissions according to the collection system employed. Each case study authority
scheme will be likely to include a number of sub-optimal components, including collection productivity (related in
part to technology) and the fate of materials, making them difficult to compare. The benefits of dry recycling
outweighed any increase in emissions resulting from the collection and processing of dry recycling material, and it
is this which most significantly influenced overall environmental performance of the dry recycling system.
There was less variation in financial costs for the residual waste system, with cost differences driven primarily by
disposal costs incurred rather than by differences in collection costs. Differences in the overall environmental
performance of the combined dry recycling and residual waste collections were primarily driven by the impacts
associated with disposing of residual waste; therefore, those authorities that collected more residual waste per
household were the worst overall environmental performers.
It was also difficult to draw any conclusions in relation to differential health and safety performance of the
different dry recycling systems from the data obtained from the authorities. Given that health and safety data is
only reported at a high level for most authorities, and is primarily based on RIDDOR sub-coding, data on the
differences between methods will be likely to remain elusive.
The work undertaken in Phase 2 thus illustrates the limitations of a comparison of dry recycling systems
employed by a small sample of very different authorities and schemes. Although it provides insight into some of
the factors that may be driving the overall differential in financial and environmental costs, it is difficult to unpick
local differences such as productivity levels, salaries, gate fees paid, and whether materials are going to the
optimal end destination, from any cost differential that might be associated with the dry recycling system per se.
Hence, it is not surprising that no meaningful pattern has emerged as to which is the highest performing
collection system.
Nonetheless, Phase 2 has provided useful insight into the key factors for consideration in modelling the waste
flows for Phase 3 of this project (the Wales-wide modelling), in particular those relating to fate of material after
collection, which is a key area where data availability has been a barrier to meaningful analysis in the past. It has
also provided essential data regarding the general logistics involved in operating services for urban, rural and
valleys authorities in Wales and this has been used as a basis from which the Phase 3 financial and environmental
performance has subsequently been determined.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 44
A1.0 Appendix A.1.0 MRF Sampling
Cardiff MRF
Between 19 and 21 September 2010, Resource Futures collected samples from each of the major MRF output
streams other than paper (for which data was already available) and glass (due to a problem with the glass
sorting equipment while the analysis was being conducted).
The materials sampled, sample collection method, target weight for each sample and number of samples sorted
are shown below.
Material Collection method Target kg Samples
Aluminium cans Split 2 bales of material 25kg 7
Steel cans Diverted from baler chamber 25kg 6
HDPE Split bale 25kg 1
Mixed plastics Diverted from baler chamber 25kg 1
Plastic film Diverted from baler chamber 15kg 1
Residual picked at bag splitter cabin Collected from stillage under cabin 25kg 4
Residual picked at paper cabin Collected from skip under cabin 25kg 4
End of line material (for H.W. Martin) Brushed directly from end of line 25kg 3
Samples were collected with the aid of site staff, and were sorted by a two-person team using a wooden sort
table. The end of line material was sorted using a 40mm screen, and the sub-40mm fraction sub-sampled using a
coning and quartering method. All other materials were sorted in their entirety.
The materials were hand sorted into containers according to a pre-agreed list of material categories, and then
weighed off using digital scales. The results were recorded on paper for input into Excel spreadsheets.
Pembrokeshire County Council
Resource Futures collected samples from two MRFs in Pembrokeshire. Between 25 and 28 October, material was
sampled from the SITA Withyhedge Landfill MRF, while material was sampled on 29 October and 1 November
from the A J Recycling MRF at Boncath. Samples were collected from all the major output streams at both
facilities.
The materials sampled, sample collection method, target weight for each sample and number of samples sorted
at each MRF are shown below.
SITA Landfill MRF, Withyhedge
Material Collection method Target kg Samples
Paper – large Hand collected from bay under sort cabin 50kg 4
Paper – small Hand collected from bay under sort cabin 25kg 4
Aluminium cans Diverted from picked aluminium 25kg 7
Steel cans Hand collected from bay under sort cabin 25kg 7
Cardboard Hand collected from bay under sort cabin 50kg 2
Plastic bottles Hand collected from bay under sort cabin 25kg 1
Plastic film Hand collected from bay under sort cabin 25kg 2
Residual bay 1 – screenings Hand collected from bay under sort cabin 10kg 5
Residual bay 2 - pick Hand collected from bay under sort cabin 20kg 5
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 45
A J Recycling MRF, Boncath
Material Collection method Target kg Samples
Paper – large Hand collected from bay under sort cabin 50kg 2
Paper – small Hand collected from bay under sort cabin 25kg 2
Aluminium cans Diverted from picked aluminium 25kg 4
Steel cans Hand collected from bay under sort cabin 25kg 4
Cardboard Hand collected from bay under sort cabin 20kg 1
Plastic bottles Hand collected from bay under sort cabin 20kg 2
Residual Hand collected from bay under sort cabin 10kg 4
Samples were collected by hand from bays beneath the sorting cabin and sorted by a two-person team using a
wooden sort table. The fine residual material (Boncath residual and Withyhedge residual from the screens) was
sorted using a 40mm screen, and the sub-40mm fraction subsampled using a coning and quartering method. All
other materials were sorted in their entirety.
The materials were hand sorted into containers according to a pre-agreed list of material categories, and then
weighed off using digital scales. The results were recorded on paper for input into Excel spreadsheets.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 46
A2.0 Appendix A.2.0 Assumed Material Compositions from MRF NEWS & PAMS MIXED PAPER CARDBOARD STEEL CANS ALUMINIUM CANS PLASTIC BOTTLES MIXED PLASTICS PLASTIC FILM GLASS RESIDUE
News and Pams 91.15% 66.87% 5.40% 0.91% 0.23% 0.81% 4.05% 4.31% 0.37% 19.60%
Non-Target Fibre 1.26% 1.78% 4.13% 0.38% 0.04% 0.16% 0.89% 0.17% 0.02% 3.59%
Brown Board 2.03% 10.68% 68.98% 0.34% 0.05% 0.21% 0.86% 0.81% 0.00% 4.27%
Grey and White Board 3.18% 10.41% 17.24% 0.59% 0.12% 0.61% 2.25% 1.19% 0.01% 4.93%
Cartons 0.16% 1.19% 0.44% 0.15% 0.03% 0.14% 0.70% 0.06% 0.00% 0.88%
Plastic Film (LDPE) 0.34% 0.70% 0.64% 0.92% 0.16% 1.11% 1.64% 60.55% 0.00% 12.60%
Plastic Bottles 0.27% 1.45% 0.55% 0.55% 0.11% 87.60% 63.38% 16.00% 0.00% 6.02%
Other Dense Plastic Packaging
0.20% 0.52% 0.53% 0.36% 0.11% 3.37% 12.95% 8.15% 0.19% 6.49%
Other Dense Plastic (Non-Packaging)
0.13% 0.34% 0.36% 0.24% 0.08% 2.25% 8.63% 5.44% 0.12% 4.33%
Textiles 0.06% 0.08% 0.05% 0.04% 0.00% 0.04% 0.28% 0.05% 0.00% 12.35%
Glass 0.02% 0.43% 0.01% 0.02% 0.01% 0.20% 0.15% 0.00% 98.54% 2.21%
Ferrous Cans 0.15% 0.77% 0.23% 92.64% 0.27% 0.19% 0.13% 0.75% 0.00% 1.51%
Other Ferrous 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Aluminium Cans (UBC) 0.08% 0.47% 0.21% 0.65% 96.18% 0.30% 0.78% 0.42% 0.03% 0.98%
Other Non-Ferrous 0.01% 0.03% 0.02% 0.12% 2.03% 0.01% 0.36% 0.10% 0.32% 0.26%
Garden Waste 0.04% 0.16% 0.05% 0.08% 0.02% 0.11% 0.11% 0.08% 0.02% 0.75%
Food Waste 0.45% 2.03% 0.58% 0.99% 0.27% 1.43% 1.41% 0.95% 0.19% 9.48%
Hazardous 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
WEEE 0.04% 0.16% 0.05% 0.08% 0.02% 0.11% 0.11% 0.08% 0.02% 0.76%
Other: Misc / Fines 0.43% 1.93% 0.55% 0.94% 0.26% 1.35% 1.34% 0.90% 0.18% 9.00%
TOTAL 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
NOTES
Adapted from Enviros Type 1
MRF profile (from published
report).
Adapted from Enviros Type 1
MRF profile (from
published report).
Adapted from Enviros Type 1 MRF
profile (from published
report).
Adapted from Enviros Type 1 MRF
profile (from published
report).
Adapted from Enviros Type 1 MRF
profile (from published report).
Adapted from Enviros Type 1
MRF profile (from published report).
Adapted from Enviros Type 1
MRF profile (from published
report).
Adapted from
Enviros Type 1
MRF profile (from
published report).
Adapted from Enviros Type 1
MRF profile (from published report).
Adjusted to account for arising
of plastic film found in Kerbside
Dry materials from Monmouthshire
sampled.
A3.0 Appendix A.3.0 Key to Process Maps
Glass = A connector, to another process location
Key
Landfill
Cardiff green
sacks = The authority’s input material
Trade waste = Other input material
Trade
waste -
cardboard
removal
= Manual hand pick
Input Hall = Location or Mechanical Process
+ve pick
film
A
= Stream description
= On page description
Landfill
= The established final fate of a material
= Final reprocessor not established but no further work proposed
A4.0 Appendix 4: Impact of Normalisation
The table below shows a comparison of cost per household for the net dry recycling service cost and the refuse
collection cost, comparing un-normalised data (U) as supplied directly by the authorities and our normalised data
as reported in Table 11.
Table 15 Comparison of un-normalised (U) and normalised (N) costs
Cardiff Gwynedd Monmouth. Newport Pembs. RCT
U N U N U N U N U N U N
Dry Recycling
Net Cost £23 £26 £50 £50 £33 £32 £11 £14 £32 £35 £47 £34
Residual Waste
Collection Cost £27 £28 £27 £26 £21 £20 £25 £26 £35 £33 £33 £34
A number of adjustments were made to the costs associated with both the dry recycling and refuse services in
order that resultant CBA for each authority was as comparable as possible. Refuse costs are included alongside
dry recycling costs because of the related avoided disposal environmental benefits that result from increased
recycling of materials. Organic costs are, however, excluded, with appropriate adjustments made to other service
provider costs where required, as not all authorities currently collect both garden and food waste, and due to the
added complication of most of the case study authorities being only part way through roll outs of separate food
waste collections.
It should be noted that no adjustments were made to the following components of the service:
The materials income received by those authorities who market their own materials; this is likely to be driven
by, for example, whether or not an authority sells on the spot market or has entered into longer-term
contracts (and if so, the nature of those contracts). Fundamentally, it is likely that ability to negotiate high
values in the market place varies between authorities, although taking a one-year view of this (as we have)
may not provide a complete picture, as authorities currently exploiting high spot market values may be more
exposed to the risk of a downturn in commodity markets in future.
MRF gate fees/operating costs; depends on factors such as what infrastructure is present and therefore how
much capacity needs to be filled by the MRF (and the gate fee that is subsequently offered), and how the
facility is run (scale of operation, value being obtained for material at end of MRF process etc.).
Differences in unit labour costs between authorities; driven by location, historical circumstances and, to some
extent, by whether the staff are permanently employed or are agency temps (and the impact of this on staff
on-costs).
The efficiency of the collection services; this will depend on factors such as vehicle technology, round
configuration, crewing levels, shifts employed and management systems.
These elements of the services genuinely vary between authorities and can be considered legitimate
differentiators which could not easily be replicated elsewhere. To adjust, for instance, the unit labour costs would
be to suggest that an authority could readily adjust what it pays its staff, and this would prove difficult in
practice.
The adjustments that were subsequently been made to the dry recycling collection costs are listed below, those
authorities to which each adjustment was applied given in brackets:
Materials income (Cardiff, Gwynedd, Newport, Pembrokeshire). A reduction in the total materials income was
applied to account for the collection of some material through bring sites and HWRCs. This apportionment
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 49
was based on the proportion of each material collected through bring sites and HWRCs compared to at the
kerbside in 2009/10. It should be noted that given that Pembrokeshire is the only case study authority not to
collect glass at the kerbside, in order to make the comparison between the basket of materials collected
through the dry recycling system as comparable as possible, we have accounted for the glass collected in
bring sites in Pembrokeshire as part of the overall dry recycling costs. We have thus added into
Pembrokeshire‟s costs the proportionate glass-related materials income and the additional cost required to
cover the collection of glass from bring sites in Pembrokeshire. The costs of the collection of glass are based
on the total bring site service provider costs highlighted in the budget, with the glass-specific costs calculated
based on the proportion of the total bring site tonnage that is glass.
Depot costs (Cardiff, Gwynedd, Monmouthshire). Where depot costs were identified separately to other
service provider costs, a proportion of the depot costs was subsequently added to the overall costs of the dry
recycling service. The costs for depots for Cardiff and Monmouthshire were apportioned based on the relative
service provider costs for the individual services. Given that less detail was supplied in the budget return
from Monmouthshire, depot costs for this authority were apportioned based on the number of vehicles used
in each service as a proxy for service provider cost apportionment.
Bulking/sorting facility costs at Caernarfon (Gwynedd). Part of the site at Caernarfon is shared by the Council
with Antur Waunfawr, a community-based reuse and recycling group that does not deal with household
waste. We have used only those costs that are considered directly related to the dry recycling service.
Food waste collection on same pass as dry recycling (Newport, Pembrokeshire). A reduction in the service
provider cost was applied to account for food waste being collected on the same pass as dry recycling in this
system. Newport Council funds the cost of the food waste collection undertaken by Wastesavers on a per
tonne collected basis, hence was able to separate the costs specifically related to food waste from those
associated with the Wastesavers dry recycling service. Pembrokeshire provided separate service provider
costs for the dry recycling and food waste parts of their service based on the additional vehicle cost required
to collect food waste on top of the existing dry recycling vehicle costs.
Cardboard not collected on dry recycling pass (Newport). An adjustment to costs was made to account for
cardboard being collected in the garden waste stream rather than as part of the dry recycling service in
Newport. In order to ensure that the dry recycling collection costs are as comparable across authorities as
possible, it is important to analyse costs over the same basket of materials. All other case study authorities
collect the majority of card as part of their dry recycling service. Hence we have included the collection and
treatment costs of the cardboard element of the garden waste service in the costs presented here. The costs
of garden waste collection are based on collecting an average of 27.5kg per household per annum from a
free garden waste service, to give a relative proportion of cardboard in terms of tonnage, which has then be
applied to the garden waste service provider cost. The treatment cost is based on the gate fee provided for
the open windrow facility and the tonnage based on 27.5kg per household per annum; this cost is subtracted
from the overall service provider cost, as in all other authorities this material would not be included as part of
the organic treatment cost and would accrue an income.
Garden waste co-collection with dry recycling (RCT). A reduction in service provider costs for RCT was
applied to remove the additional costs associated with garden waste being co-collected with the dry
recycling; this adjustment was calculated based on tonnages collected.
Trade waste dry recycling co-collection (RCT). A small reduction in costs was applied to RCT to account for
the dry recycling trade waste tonnage that is collected as part of the overall dry recycling service; this
adjustment was calculated based on tonnages collected.
Infrastructure capital costs (Cardiff, Newport). An annualised capital cost associated with the building of the
MRF in Cardiff and Wastesavers depot in Newport was added to the collection costs for these two authorities.
The MRF in Cardiff and depot in Newport were both partially paid for by a European grant; a grant which
would not be accessible to other authorities across the country should they wish to build their own MRF or
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 50
depot in future. Hence a cost has been factored in to adjust for this grant. In reality, the capital cost might
be covered as a one-off cost or financed over a number of years; however, in order to be representative of
the overall costs incurred in running a dry recycling service with a MRF, an annualised cost of capital is
included in the costings presented.
Non-operational waste management costs (Monmouthshire). A reduction in employment-related costs was
applied in order to account for six non-operational waste management staff that spend around half of their
combined time on waste services and whose costs were included as part of the service provider costs
provided. This cost was split equally between the refuse, recycling and organic services.
Annualised containment costs (all six case studies). Containment costs were adjusted to ensure that costs
are annualised and do not include costs associated with the provision of food waste caddies and bio-liners;
rather than annualising these costs, containment costs for local authorities tend to vary annually depending
on when stocks need replenishing, and to match new service roll outs. Hence costs which may show in one
year‟s budget may not be included in the following year. In order to make containment costs as comparable
as possible between authorities, we annualised the costs of containment as follows:
o Gwynedd and Newport; costs were calculated based on the average household being provided
with two boxes, costing £4 per unit with an annual replacement rate of 10%.
o Cardiff; costs were based on the average household using five bags every fortnight to present
their dry recycling for collection, costing 4p per unit for clear single-use bags.
o Monmouthshire, Pembrokeshire and RCT; costs were calculated based on the average
household using three bags every week to present their dry recycling for collection. Unit costs
at 4p per single-use bag.
The normalised costs for the dry recycling service for each case study authority are presented in Table 16. The
adjustments that were subsequently been made to the refuse costs are listed below:
Depot costs (Cardiff, Gwynedd, Monmouthshire). Where depot costs were identified separately to other
service provider costs, a proportion of the depot costs was added to the overall costs of the refuse collection
service. The costs for depots in Cardiff and Monmouthshire were apportioned based on the relative service
provider costs for the individual services. Given that less detail was supplied in the budget return from
Monmouthshire, depot costs for this authority were apportioned based on the number of vehicles used in each
service as a proxy for service provider cost apportionment.
Annualised containment costs (all six case studies). Containment costs were again adjusted to ensure that
costs are annualised. In order to make containment costs as comparable as possible between authorities, we
annualised the costs of containment so that wheeled bins were costed at £1.80 per household per annum
(based on a unit cost of £18 per bin), with a 2% replacement rate for those households with wheeled bins to
account for lost/damaged bins. Costs for those authorities providing black sacks for collection were calculated
based on 1p per unit, with Pembrokeshire costs based on providing one sack per week to all households and
the small percentage of households in Cardiff, Gwynedd and RCT each provided with four bags per week.
Where an authority provides both wheeled bin and sack collections, costs were calculated based on the
proportion of households provided with each containment type. For Monmouthshire containment costs are
zero as residents are required to provide their own black bags for refuse collection.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 51
Table 16 Normalised dry recycling collection costs (£k)
Item Cardiff Gwynedd Monmouth-
shire Newport
Pembroke-
shire RCT
2010/11
budget
2010/11
budget
2010/11
budget
2010/11
budget
2009/10
actuals
2010/11
budget
Income
Budgeted Income -1,038 -371 0 0 -480 0
Adjustment for Bring Site/HWRC
Income 25 54 0 0 79 0
MRF Gate Fees Income -450 0 0 0 -51 0
Total Income -1,463 -317 0 0 -451 0
Expenditure
Budgeted Service Provider Cost 1,630 2,827 714 917 1,183 1,641
Depot Costs 98 24 21 0 0 0
Budgeted Operational Cost of
Bulking/Sorting Facility 0 443 0 0 0 0
Budgeted MRF Cost 2,466 0 300 0 767 1,653
Adjustment for Build Cost of MRF* 356 0 0 130 0 0
Adjustment for Build Cost Bulking
Depot** 0 0 0 0 0 0
Adjustment for Back-Office Staff
Costs 0 0 -38 0 0 0
Adjustment for Food Waste Co-
Collection 0 0 0 -297 0 0
Adjustment for Cardboard being
Collected in Organic Stream 0 0 0 113 0 0
Adjustment for Cardboard Compost
Cost 0 0 0 -75 0 0
Adjustment for Bring Site Collection
Cost (Glass) 0 0 0 0 155 0
Adjustment for Garden Waste Co-
Collection 0 0 0 0 0 -305
Adjustment for Trade Waste Co-
Collection 0 0 0 0 0 -21
Budgeted Containment Cost 802 68 250 408 378 1,642
Adjustment for Annualised
Containment -103 -20 -4 -358 -17 -1,036
Total Expenditure 5,249 3,343 1,243 837 2,466 3,573
Net Kerbside Dry Recycling
Service Cost 3,786 3,026 1,243 837 2,014 3,573
Net Cost per Household £26 £50 £32 £14 £35 £34
Net Cost per Tonne Dry
Recycling Collected £133 £371 £166 £79 £268 £156
Notes
*Based on build cost of £5.5 million, financed over 25 years at 4.8% (10 year average 50 month + fixed rate figure from the
Public Works Loan Board.
**Based on build cost of £2 million, financed over 25 years at 4.8% (10 year average 50 month + fixed rate figure from the
Public Works Loan Board.
Phase 2 Cost-Benefit Analysis: Waste Collection Services in Pembrokeshire 52
The disposal cost associated with the kerbside collected residual waste was calculated based on the tonnages
of residual waste collected in 2009/10, the gate fees supplied by each authority and with landfill tax set at £48
per tonne.
o It should be noted that Monmouthshire changed from a weekly refuse to a fortnightly refuse
service in 2009/10 at the same time as making significant changes to the dry recycling scheme;
Monmouthshire‟s residual waste tonnage has therefore been adjusted to account for the
authority‟s estimate of the increase in recycling performance (and reduction in residual waste
tonnage).
o We also note that the landfill tax applied relates to the financial year 2010/11 rather than
2009/10. in the case of all authorities apart from Pembrokeshire, 2010/11 budgets rather than
2009/10 financial outturns were used in the analysis, in order to more accurately account for
the impact on costs of recent service changes. Given the significant impact that an £8 per
tonne lower tax calculation would have had on Pembrokeshire‟s residual waste cost in
comparison to the other case study authorities, and that this is significantly greater than any
increase in inflation costs between the two years, we modelled all authorities at the same
landfill tax cost per tonne i.e. the 2010/11 figure. It is important to note that the overall CBA to
which these figures will contribute subsequently excludes landfill tax altogether from the
financial cost calculations to avoid double-counting environmental costs.
The normalised costs for the dry recycling service for each case study authority are presented in Table 17.
Table 17 Normalised refuse costs (£k)
Item Cardiff Gwynedd Monmouth-
shire Newport
Pembroke-
shire RCT
2010/11
budget
2010/11
budget
2010/11
budget
2010/11
budget
2009/10
actuals
2010/11
budget
Collection Expenditure
Budgeted Service Provider
Cost 3,668 1,467 813 1,488 1,879 3,380
Adjustment for Back-Office
Staff Costs 0 0 -38 0 0 0
Depot Costs 221 12 24 0 0 0
Budgeted Containment Cost 90 131 0 38 137 110
Adjustment for Annualised
Containment 194 -22 0 76 -107 92
Net Refuse Collection
Cost 4,173 1,591 799 1,602 1,909 3,582
Net Cost per Household £28 £26 £20 £26 £33 £34
Net Cost per Tonne
Refuse Collected £64 £61 £52 £53 £75 £53
Disposal Expenditure
Disposal Cost 2,088 182 729 1,316 604 1,139
Landfill Tax 3,120 1,248 820 1,440 1,225 3,216
Total Refuse Service
Expenditure 9,381 3,021 2,186 4,358 3,738 7,937
Net Service Cost per
Household £63 £50 £56 £70 £65 £76
Net Service Cost per
Tonne Refuse Collected £144 £116 £143 £145 £147 £118