southern regional power committee bengaluru - srpc

14

Upload: khangminh22

Post on 24-Jan-2023

0 views

Category:

Documents


0 download

TRANSCRIPT

Anusha
Text Box
8. Chief Engineer, APSLDC, Vidyut Soudha, Eluru Road, Vijayawada, AP

Minutes of the Meeting held on 02.03.2021 to finalise Simhadri Islanding Scheme 1/3

Southern Regional Power Committee

Bengaluru

Minutes of the Meeting held on 02.03.2021 in on-line mode to finalise

Simhadri Islanding Scheme

A meeting to finalise Simhadri Islanding Scheme was conducted on 02.03.2021 in on-line

mode under the chairmanship of Member Secretary (MS), SRPC. The list of participants is given

at Annexure-I.

2. MS, SRPC welcomed all the participants to the meeting. He stated that Islanding

schemes gained much attention in the wake of recent Mumbai Islanding scheme

incidence. Accordingly, fine tuning of settings and implementation of the proposed and

new islanding schemes were to be taken up expeditiously. He requested for active

participation from all stakeholders and hoped that fruitful deliberations in the meeting

would enable finalisation of the scheme to be put in place.

3. Superintending Engineer (P&SS) informed the forum that Simhadri Islanding Scheme had

its genesis way back in 2019, and the implementation details of the scheme were

thoroughly discussed in the meeting held in January, 2020. Subsequently, APTRANSCO

had also got the scheme approved by their management. However, due to Covid-19

pandemic, its field-level implementation could not be followed up. Now that another

year had elapsed in the process, it was thought appropriate to verify the scheme finalized

in January, 2020 w.r.t the present conditions, and take up its implementation without

further delay. Accordingly, APTRANSCO was requested in January, 2021 to furnish all

updated details including anticipated generation, anticipated load, and transmission lines

to be tripped for forming the proposed Simhadri Islanding Scheme. All the requisite

details including the converged PSSE Basecase considered for forming the Simhadri Island

were furnished by APTRANSCO in February, 2021.

4. Then, APTRANSCO presented the details considered for forming the proposed Simhadri

Island (copy enclosed at Annexure-II) including anticipated generation, anticipated load,

df/dt & AUFR & LI loads, and peripheral transmission lines to be tripped for forming the

desired Island. APTRANSCO also informed that in the islanded model, power flow study

was converging and all flows were under thermal limits.

5. On this, SRPC sought certain clarifications w.r.t. auxiliary power consumptions of the

participating generators, PLF considered, non-inclusion of the IPPs in the islanded

network, quantum of renewable generation within the islanding area and the reliability

of co-generators considered; and the following were noted w.r.t. the proposed Simhadri

Island:

The considered auxiliary consumption for various Generators have been confirmed to

be in order by APTRANSCO/ APGENCO/ NTPC.

The generation from private generators, viz., Sarda & Girija, is dependable.

Renewable generation within the Island is insignificant (of about 13 MW), hence not

considered.

Minutes of the Meeting held on 02.03.2021 to finalise Simhadri Islanding Scheme 2/3

Generation availability through HVDC-Gajuwaka not considered, in view of the

uncertainty/ unreliability of supply from Jeypore side under distressed conditions

such as that warrant Island formation.

The considered Anticipated Generation and Anticipated Load at various stations are

based on the past one-year data.

6. To above, SRLDC mentioned that the envisaged islanding scheme is covering important

installations like Naval Dockyard, Ports, etc., and stated that in the earlier islanding study

conducted by them (presented in the Islanding review meeting held in January, 2020),

the uncertainty in IPP’s generation and variations in loads at various stations were

generally found to be high; as such, there was a need to arrive at actual/realistic load and

generation within the island by considering the corresponding SCADA data for the last

two to three years. Further, it may also be prudent to maintain supply to gas based

generating stations for meeting their start-up power & other gas pressurization

requirements so as to bring them on to bar, if required, after formation of the Island.

7. W.r.t. Line loadings and Voltage profile of various nodes in the Island, SRLDC observed

that line loadings, as per the APTRANSCO presentation, were not alarming, and voltage

profile in the island would be stable owing to exclusion of 765 kV lines. It was also noted

that availability of several reactive energy resources within the island would provide

leeway for ensuring proper voltage profile.

8. It was noted that APTRANSCO, APGENCO, PGCIL-SR1 and NTPC-Simhadri have to install

Under Frequency relays on their respective lines as detailed at Annexure-II, to form the

desired Island by tripping them at 47.9 Hz. On this, MS, SRPC emphasised that as

Visakhapatnam is the important capital city of AP in the island, the implementation of the

scheme needs to be fast tracked. Procurement of required relays should be done

expeditiously, and the islanding scheme should be in place within a month.

9. Finally, tripping frequency of Lift Irrigation (LI) loads and enablement of back-up

under-frequency feature of df/dt relays at suitable frequency were also discussed.

10. After detailed deliberations, the following decisions were taken:

For arriving at anticipated generation, APTRANSCO to consider all generating stations

physically present within the proposed Simhadri Island (i.e., in addition to the 11 Gen.

Stations that have already been considered, HNPCL and all Gen. Stations present in

Vemagiri area shall be considered), and arrive at their actual generation by

considering past 2-3 years SCADA data.

The Loads considered at various nodes to be checked by verifying their power factor,

and validated by considering past 2-3 years SCADA data.

APTRANSCO to study Island stability with the above validated anticipated generation

& load, and furnish the details within 10 days.

Accordingly, to conduct a review meeting within 10 days to finalise the scheme.

APTRANSCO, APGENCO, PGCIL-SR1 and NTPC-Simhadri to start procuring and

installing required UF relays on the identified peripheral feeders to be tripped for

forming the proposed Simhadri Island, and complete the same in one month time.

All Lift Irrigation & Pumped Loads to be tripped at the tripping frequency of 48.5 Hz.

Back-up Under-Frequency feature of df/dt relays to be enabled at 48.4 Hz.

Minutes of the Meeting held on 02.03.2021 to finalise Simhadri Islanding Scheme 3/3

It was also agreed to call for another meeting for finalizing Simhadri Islanding Scheme

immediately after receipt of requisite details from APTRANSCO.

****

Annexure-I

Sl. No. Name Designaton Organisation Phone Email1 Sh Diwakar kaushik Head of the Plant NTPC

2 Prasanta Kumar Jena AGM NTPC 9650990836 [email protected]

3 K Ravivarma DGM NTPC 9493174808 [email protected]

4 J S N V Prasad Sr Manager NTPC 9428815820 [email protected]

5 ANIL KUMAR PINNINTI Sr Manager NTPC 9425219262 [email protected]

6 KODANDA PANI VUDUGUNDLA Dy.EE APGENCO 9493121742 [email protected]

7 V A Raju AEE APGENCO 9492510888 [email protected]

8 K. Sudhakar Rao Sr.DGM POWERGRID, SRTS-1 9490611112 [email protected]

9 Y. Ananth Srinivas Superintending Engineer – Grid Operation APTRANSCO 9490153134 [email protected]

10 P.S.S.Anjaneya Prasad Superintending Engineer – Power Systems APTRANSCO 8333886160 [email protected]

11 P.Chinna Kondala Rao Excutive Engineer-System Studies APTRANSCO 9491049370 [email protected]

12 Ch. Sreenivasa Rao Excutive Engineer-System Studies APTRANSCO 9440811159 [email protected]

13 S.P.Kumar CGM SRLDC, POSOCO 9449599163 [email protected]

14 Goodelli Madhukar Chief Manager SRLDC, POSOCO 9449599194 [email protected]

15 M. Pradeep Reddy Manager SRLDC, POSOCO [email protected]

16 L Sharath Chand Manager SRLDC, POSOCO [email protected]

17 A. BALAN Member Secretary SRPC [email protected]

18 N R L K PRASAD Superintendenting Engineer SRPC [email protected]

19 LEN. J.B Executive Engineer SRPC 9449682204 [email protected]

20 BETSY SEBASTIAN Assistant Executive Engineer SRPC [email protected]

SRPC

Meeting to Finalise Simhadri Islanding Scheme

held on 02.03.2021List of Participants

|

|

|

|

||

|

|

|

|

||

|

|

||

||

|

|

|

|

||

|

|

||

|

|

GUDIVADA-220/132

BHMDOLU-220/132

VIJSWRM-I-220

JEGRPADU-220

VIJSWRM-II-220

LOWRSLRU-220

RAMPCHODVRM-220

BHIMVARM-220/132

VEMAGIRI-400/220

SPECTRUM-220

REL-BSES-220

SMHDRI-II-400

KALPAKA-400/220

GMR-400

GAUTAMI-400

GVK-II-400

GANGVRAM-220

GAZUWAKA-220/132

MRS_VSP-220

DRYFRM-220/132

LVS-220

GARIVIDI-220/132

DONKARAI-220

TEKKALI-220/132

GZW-EAST-400

765 kV

400 kV

230/220 kV

132/110 kV

66 kV

33/11/6.6 kV

Tripped Lines

THERMAL/ GAS POWER STATION

HYDRO POWER STATION

LEGENDDESCRIPTION

POWER MAP OF SIMHADRI ISLAND

SRPC, BENGALURU

(March, 2021)[NOT TO SCALE]

SRI-GIRIJA-220

|

|

|

|

|

|

BRANDIX-220/132

|

|

ANRAKU-220

HNPCL-400

VTPS-220/132

BALIMELA-220

|

| |

|

PATTSEEMA-220/11

PALNTLA-220/132

||

BMNDUR-220

BOBBILI-220/132

|

|

NIDADVOLU-220/132

|

|

|

|

|

|

||

||

NUNNA-400/220/132

VEMGR-PG-765/400

SRIKAKULAM-765/400

|

|

|

|PENDRTI-220/132

||

KVKOTA-132

SAMRLKOTA-220/132

ASWRPET-132

KVKOTA-220/132

DUVVA-220/132

RAMVRM-220

PURSTPTNM-220

BAVOJIPET-220

|

|

|

|

|

|

|

|

|

|

|

|

SRDAL-NEW-220

|

|

||

|

|

ABHJEET-220

ACYUTPRM-220

|

|

|

|

PYDBHIMVRM-220

|

|

|

|

|

ASUPAKA-400/220

|

|

||

|

|

|

|

||

||

|

|

|

|

KVKOTA-400/220

||

||

SATTNPALLI-400/220

SURYAPET-400/220/132

VTS-IV-400/220

KTPS-V-220

UPRSLRU-220

PEDVEGI-132

ELURU-132

KANUMOLU-132

BOMMUR-220/132

GMRBARGE-220

MARADAM-400/220

GAZ'WKA-PG-400/220

PARWADA-220/132

SIMHADRI-400

KAKINADA-220/132

KONSEEMA-400

KHAMMAM-400/220/132

Annexure-II

Page 1 of 8

Simhadri Island Draft Feeder Tripping Frequency for Islanding: 47.9 Hz

Methodology: Total Generators participating = Gp (This is based on Installed Capacity) Anticipated Generation = G [This is “Plant Load Factor (PLF) x Gp ”] Total Loads participating = Dp (This is based on Average Peak Loads at various Stations) Combined Load Relief from AUFR and df/dt Relays = Dr

Lift Irrigation & Pumped Load = Dl

Anticipated load = D

= DFI * (Dp – Dr - Dl) Here DFI (Diversity Factor for Load) may be arrived at by considering SCADA plots over a period of time in the past or may be suitably assumed based on experience] Note:- As per guidelines, Islanded Electrical System should have 15-20% more Generation than Load. Thus, it shall be ensured that ‘G’ = 1.15 times ‘D’. In case, G is more than 1.2*D, then the utility may propose for tripping few generating units to satisfy this requirement. Accordingly, the details of Anticipated Generation and Anticipated Load for the proposed Simhadri Island are given below:

Annexure-II

Page 2 of 8

Simhadri Islanding Scheme:

1. Schematic

2. Synopsis

Generators Participating: Gp 3292

Anticipated Generation: G = PLF*Gp 1646 Total Load Participating (Dp) 2899

AUFR + df/dt Average Load relief

(Dr)

1692

Lift Irrigation & Pumped Load (Dl) 53

Net Load 2899-1692-53 = 1154

Anticipated Load, D [DFI *(Dp-Dr-

Dl)]

(1.208*1154)

1394

Sum of the individual Station Max. Loads during the year 2020:

4152.25MW

Maximum Load reached so far (22-05-2020): 3437 MW

Diversity Factor = 4152.25/3437 = 1.208

Ratio between Anticipated Generation and Anticipated Load = 1.18

i.e. Anticipated Generation is 18% more than Anticipated Load.

Annexure-II

Page 3 of 8

3. Details of Generators Participating

Sl.

No. Generator Entity

Installed

Capacity (MW)

Auxiliary

Consump

(%)

Ex-Bus

Generation,

MW

PLF G(Gp*PLF),

MW

1 Simhadri Thermal 4*500 6 1880 0.70 1316

2 Vijeswaram-

1 Gas 2*33+1*34

2 98

0.2 19.6

3 Vijeswaram-

2 Gas 1*112.5+1*59.5

2 168.56 0.2

33.7

4

Godavari

Gas

(Jegurupadu)

Gas 2*45.8 + 1*48.9

+ 1*75.5

2

211.68

0.2 42.2

5 Sarda Co-gen 1*80 10 72 0.3 21.6

6 Girija Co-gen 2*36 10 64.8 0.3 19.4

8 Lower Sileru Hydro 4*115 1 455.4 0.2 91.1

9 Upper Sileru Hydro 4*60 1 237.6 0.2 47.5

10 Machkund Hydro 84 1 79.8 0.6 47.9

11 Donkarai Hydro 1*25 1 24.75 0.3 7.4

Generators Participating, Gp 3292.59

Anticipated Generation, G

(Gp*PLF)

1646

4. Details of Loads Participating

Sl. No.

Bus Number

Name of the SS Entity

Total P (Load in MW) [This is total avg. of

periodic peak load at the

station including AUFR & df/dt &

LI Loads]

Power Factor

AUFR Load, MW

df/dt Load, MW

LI/ Pumped

Load, MW

1 411088 TEKKALI 132.00 APTRANSCO 16 0.95 16

2 411098 ELURU 132.00 APTRANSCO 62 0.95 62

3 411181 NALLAJERLA 132.00 APTRANSCO 40 0.95 40

4 411107 PTDP 132.00 APTRANSCO 52 0.95 52

5 411189 CHINTALAPUDI132.00 APTRANSCO 42 0.95 42

6 411008 BBLI 132.00 APTRANSCO 31 0.95 31

7 411032 GARIVIDI 132.00 APTRANSCO 25 0.95 25

8 411049 KORUPROLU 132.00 APTRANSCO 46 0.95 46

9 411077 RAMACHANDPRM132.00 APTRANSCO 122 0.95 122

10 411112 TUNI 132.00 APTRANSCO 50 0.95 50

11 411115 VIZIANAGARAM132.00 APTRANSCO 35 0.95 35

12 411237 RVK 132.00 APTRANSCO 53.11 0.95 53.11

13 411055 MALLAIAHPETA APTRANSCO 42.5 42.5

Annexure-II

Page 4 of 8

132.0

14 411048 KOVVURU 132.00 APTRANSCO 39 0.95 39

15 411129 SAGGONDA 132.00 APTRANSCO 25 0.95 25

16 411192 ICHAPURAM 132.00 APTRANSCO 10 0.95 10

17 411196 PEDAVEGI 132.00 APTRANSCO 30 0.95 30

18 411003 AMALAPURAM 132.00 APTRANSCO 38.86 0.95 38.86

19 411081 SIMHACHALAM 132.0 APTRANSCO 40 40

20 411101 KASIMKOTA 132.00 APTRANSCO 39 0.95 39

21 411111 TNK 132.00 APTRANSCO 54 0.95 54

22 411120 PALAKONDA 132.00 APTRANSCO 22 0.95 22

23 411247 PITAPURAM 132.00 APTRANSCO 18 0.95 18

24 411255 PRATAPNAGAR 132.00 APTRANSCO 30 0.95 30

25 411016 CHILAKAPALEM132.00 APTRANSCO 35 0.95 35

26 411050 KVKOTA 132.00 APTRANSCO 48 0.95 48

27 411058 NIDADAVOLU 132.00 APTRANSCO 35 0.95 35

28 411106 PRATHIPADU 132.00 APTRANSCO 22 0.95 22

29 421275 ASWARAOPET 132.00 TSTRANSCO 56 0.95 56

30 411067 PEDAPURAM 132.00 APTRANSCO 28 0.95 28

31 411100 JANGAREDDYG 132.00 APTRANSCO 48 0.95 48

32 411148 NARSAPURAM 132.00 APTRANSCO 40.8 0.95 40.8

33 411193 PATHAPATNAM 132.00 APTRANSCO 8 0.95 8

34 411009 BHIMAVARAM 132.00 APTRANSCO 68 0.95 68

35 411010 BHIMADOLE 132.00 APTRANSCO 54 0.95 54

36 411011 BOMMURU 132.00 APTRANSCO 48 0.95 48

37 411038 KAKINADA 132.00 APTRANSCO 46 0.95 46

38 411084 TB VARA 132.00 APTRANSCO 11 0.95 11

39 411155 RAZOLE 132.00 APTRANSCO 30 0.95 30

40 411173 PARAWADA 132.00 APTRANSCO 99 0.95 99

41 411231 PYDIBHEMAVRM132.00 APTRANSCO 53 0.95 53

42 412065 RAMPACHDAVAM220.00 APTRANSCO 6.6 0.95 6.6

43 412147 BAVOJIPETA 220.00 APTRANSCO 13.2 0.95 13.2

44 412148 PURUSHOTAPAT220.00 APTRANSCO 15 0.95 15

45 412181 RAMAVARAM 220.00 APTRANSCO 18.1 0.95 18.1

46 411134 ARABIND 132.00 APTRANSCO 22.8 0.95

47 411321 BRANDI_AA 132.00 APTRANSCO 40.36 0.95

48 411320 NAVW_APC 132.00 APTRANSCO 6.14 0.95

49 411048 KOVVURU 132.00 APTRANSCO 0.87 0.95

50 411176 BBLI_BFA 132.00 APTRANSCO 30.7 0.95

51 411363 SRSL 132.00 APTRANSCO 5.25 0.95

52 411319 NAVW_ES 132.00 APTRANSCO 9.71 0.95

53 411072 VIZAG PORT 132.00 APTRANSCO 1.56 0.95

54 411175 GVD_JFA 132.00 APTRANSCO 10.52 0.95

55 411122 NAKAVANIPALM132.00 APTRANSCO 26.03 0.95

56 412133 ABHIJEET 220.00 APTRANSCO 110.18 0.95

57 411318 KRPL_MH 132.00 APTRANSCO 0.87 0.95

58 411324 KDA_NFCL 132.00 APTRANSCO 1.2 0.95

59 411072 VIZAG PORT 132.00 APTRANSCO 0.87 0.95

60 411072 VIZAG PORT 132.00 APTRANSCO 0.87 0.95

61 411313 ARK_GRAIL 132.00 APTRANSCO 0.87 0.95

62 411312 ARK_TRAIL 132.00 APTRANSCO 2.62 0.95

63 411311 BRANDI_SA 132.00 APTRANSCO 9.31 0.95

Annexure-II

Page 5 of 8

64 411322 BMR_RAIL 132.00 APTRANSCO 4.37 0.95

65 411325 ELUR_RTSS 132.00 APTRANSCO 1.74 0.95

66 411315 KSMK_RAIL 132.00 APTRANSCO 3.71 0.95

67 411108 NAVPADA 132.00 APTRANSCO 9.31 0.95

68 411326 PTDP_RAIL 132.00 APTRANSCO 1.91 0.95

69 411323 SAMRLA_RAIL 132.00 APTRANSCO 4.2 0.95

70 411314 SMHC_RTSS 132.00 APTRANSCO 15.17 0.95

71 411135 TBV_SKRAIL 132.00 APTRANSCO 1.74 0.95

72 411316 TUNI_RAIL 132.00 APTRANSCO 3.5 0.95

73 411317 VSEZ_RAIL 132.00 APTRANSCO 2.78 0.95

74 411164 VZNG_RTSS 132.00 APTRANSCO 5.58 0.95

75 411188 PRTPRM 132.00 APTRANSCO 11.31 0.95

76 411366 AMPOLU 132.00 APTRANSCO 19 0.95

77 411166 ANANDAPURAM 132.00 APTRANSCO 31.84 0.95

78 411128 APSUGARS 132.00 APTRANSCO 23.76 0.95

79 411006 ARAKU 132.00 APTRANSCO 1.48 0.95

80 411269 BARC 132.00 APTRANSCO 0.87 0.95

81 411293 BARUVA 132.00 APTRANSCO 4.64 0.95

82 411307 BICCAVOLU 132.00 APTRANSCO 19.73 0.95

83 411167 BIRLA 132.00 APTRANSCO 21.93 0.95

84 411198 BRANDIX 132.00 APTRANSCO 34.03 0.95

85 411015 CFL 132.00 APTRANSCO 8.76 0.95

86 411378 CHODAVARAM 132.00 APTRANSCO 23.46 0.95

87 411019 COMMON POINT132.00 APTRANSCO 19.3 0.95

88 411170 DAIRYFARM 132.00 APTRANSCO 22.45 0.95

89 411264 DFAL 132.00 APTRANSCO 6.65 0.95

90 411392 DGNP_GIS 132.00 APTRANSCO 11.46 0.95

91 411383 DUVA1 132.00 APTRANSCO 17.31 0.95

92 411228 EDITHA 132.00 APTRANSCO 26.32 0.95

93 411023 FACR 132.00 APTRANSCO 16.66 0.95

94 411256 GANGAVARAM 132.00 APTRANSCO 18.85 0.95

95 411387 GARBHAM 132.00 APTRANSCO 4.72 0.95

96 411033 GAZUWAKA 132.00 APTRANSCO 21.93 0.95

97 411434 GOLLAPALEM 132.00 APTRANSCO 11.66 0.95

98 411036 HPCL 132.00 APTRANSCO 6.52 0.95

99 411394 HSL 132.00 APTRANSCO 1.75 0.95

100 411379 KMTP RTSS 132.00 APTRANSCO 0.42 0.95

101 411246 KOTHAPETA 132.00 APTRANSCO 21.04 0.95

102 411149 KVLS 132.00 APTRANSCO 8.94 0.95

103 411301 MALKAPURAM 132.00 APTRANSCO 8.5 0.95

104 411429 MOR ALLOYS 132.00 APTRANSCO 6.14 0.95

105 411436 MUMMADIVARAM132.00 APTRANSCO 15.78 0.95

106 411245 NARASANNAPET132.00 APTRANSCO 14.91 0.95

107 411299 NARSINGBILLI132.00 APTRANSCO 7.89 0.95

108 411285 NARSIPATNAM 132.00 APTRANSCO 24.7 0.95

109 411057 NAVAL WHARF 132.00 APTRANSCO 1.56 0.95

110 411195 NCS 132.00 APTRANSCO 0.87 0.95

111 411433 PADERU 132.00 APTRANSCO 3.5 0.95

112 411121 PALASA 132.00 APTRANSCO 18.94 0.95

113 411374 PEDA WALTAIR132.00 APTRANSCO 33.92 0.95

114 411104 PENDURTHI 132.00 APTRANSCO 10.25 0.95

Annexure-II

Page 6 of 8

115 411248 PNGD 132.00 APTRANSCO 20.08 0.95

116 411163 PONDURU 132.00 APTRANSCO 4.41 0.95

117 411188 PRTPRM 132.00 APTRANSCO 16.74 0.95

118 411281 RAJAM 132.00 APTRANSCO 11.38 0.95

119 411218 RAJANAGARAM 132.00 APTRANSCO 30.87 0.95

120 411183 RAK 132.00 APTRANSCO 2.96 0.95

121 411304 RAMCO 132.00 APTRANSCO 3.5 0.95

122 411430 RICHMOND 132.00 APTRANSCO 6.14 0.95

123 411382 SALR1 132.00 APTRANSCO 11.22 0.95

124 411289 SARVARAYA 132.00 APTRANSCO 0.16 0.95

125 411417 SBC_DGNP 132.00 APTRANSCO 25.08 0.95

126 411363 SRSL 132.00 APTRANSCO 1.48 0.95

127 411202 UNDI 132.00 APTRANSCO 50.36 0.95

128 411072 VIZAG PORT 132.00 APTRANSCO 16.78 0.95

129 411225 VIZAG SEZ 132.00 APTRANSCO 27.82 0.95

130 411146 YANM 132.00 APTRANSCO 5.69 0.95

131 411371 YERNAGUDEM 132.00 APTRANSCO 20.91 0.95

Loads Participating, Dp 2899

AUFR Load Relief

962.47

df/dt Load Relief

729.8

AUFR + df/dt Load Relief, Dr

1692.29

Lift Irrigation & Pumped Load (Dl)

52.9

Note: The following Inter-state feeders would get tripped under df/dt 1 132kV 1 411050 KVKOTA APTransco 421275 ASWARAOPET TSTransco

2 110kV 1 411209 KVKOTA2 APTransco 421275 ASWARAOPET TSTransco

5. Details of Island-forming Feeders & ICT’s (i) Feeders’ Details:

[These are to be tripped at From Bus End (the one inside the Island) at the

Islanding Frequency, 47.9 Hz]

Sl. No.

Voltage level

No. of

Ckts (D/C

or S/C)

From Bus No.

From Bus Name From Bus Entity

To Bus No.

To Bus Name To Bus Entity

1 400kV Q1 414039 SRIKAKULAM APTransco 414045 MARADAM APTransco

2 400kV Q2 414039 SRIKAKULAM APTransco 414045 MARADAM APTransco

3 400kV T2 414011 KALPAKKA APTransco 424004 KHAMMAM TSTransco

4 400kV T1 414011 KALPAKKA APTransco 424020 ASUPAKA TSTransco

5 400kV Q1 414042 K V KOTA APTransco 424016 SURYAPET TSTransco

6 400kV Q2 414042 K V KOTA APTransco 424016 SURYAPET TSTransco

7 400kV T2 414014 VEMAGIRI APTransco 414040 VEMAGIRI_PG PGCIL-SR1

8 400kV T1 414014 VEMAGIRI APTransco 414040 VEMAGIRI_PG PGCIL-SR1

9 400kV T1 414014 VEMAGIRI APTransco 414021 SATTENAPALLI APTransco

10 400kV T3 414014 VEMAGIRI APTransco 414008 NUNNA PGCIL-SR1

11 400kV T1 414009 GAZUWAKA PGCIL-SR1 414040 VEMAGIRI_PG PGCIL-SR1

12 400kV T1

414020 SIMHADRI-II NTPC-Simhadri

414040 VEMAGIRI_PG PGCIL-SR1

Annexure-II

Page 7 of 8

13 400kV T2

414020 SIMHADRI-II NTPC-Simhadri

414040 VEMAGIRI_PG PGCIL-SR1

14 220kV 1 412005 BHIMADOLE APTransco 412038 NUNNA APTransco

15 220kV 1 412064 BHEEMAVARAM APTransco 412050 GUDIVADA APTransco

16 220kV 2 412064 BHEEMAVARAM APTransco 412050 GUDIVADA APTransco

17 220kV 1 412017 LOWERSILERU APGENCO 422107 Asupaka TSTransco

18 220kV 1 412017 LOWERSILERU APGENCO 422085 KTPS-V TSTransco

19 220kV 1 412067 K.V.KOTA APTransco 412025 VTS APTransco

20 220kV 1 412087 UPPERSILERU APGENCO 252001 BALIMELA OSTransco

21 132kV 1 411098 ELURU APTransco 411047 KANUMOLU APTransco

22 132kV 1 411196 PEDAVEGI APTransco 411047 KANUMOLU APTransco

23 HVDC Gazuwaka Pole 1 & 2 PGCIL-SR1

Annexure-II

Page 8 of 8