responding to bridge hits in mndot's metro district
TRANSCRIPT
Responding to Bridge Hits in MnDOT’s Metro District
Sarah Sondag, PE | Bridge Inspection Engineer Mark Pribula, PE | Bridge Inspection Engineer
1,478 BridgesOver 27 Million SF of Bridge
Deck Area1,800 Overhead Signs900 Retaining Walls120 Miles of Noise Walls
Metro Structural Assets
District Split into Six Bridge Sub Areas
Forest Lake, Maplewood, Mendota, Eden Prairie, Plymouth, & Spring Lake Park
Each Sub Area Responsible for approximately:60 Interstate95 US & State Trunk Highway60 Municipal & County State-Aid
Crew size: 7 - 9 including Supervisor
Metro Bridge Personnel
Bridge Inspection Team LeaderCertified by MnDOT to conduct
inspections of in-service bridgesMust be present at the bridge
site at all times during a bridge inspection
Inspection Roles and Responsibilities
Program AdministratorCertified Professional Engineer
appointed to oversee the bridge inspection program
Review and approve all bridge inspection reports
Respond to inspection findingsReport critical findings to the
MnDOT Bridge Office
Inspection Roles and Responsibilities
Incident Defined as anything that could affect structural integrity
ResponseDispatching appropriate personnel and equipmentFirst call is to Bridge Maintenance Supervisor Certified Team Leader
Activating the appropriate communication linksDocumenting and reporting findingsDamage ReportCritical Deficiency Report (if needed)
Preparing and implementing any necessary repair actions
Incident Response Procedures
Documentation and Reporting Damage InspectionAssess structural damageReport:DateLocationEquipment RequirementsInspection Procedures,
Components, Findings and Recommendations
Incident Response Procedures
Documentation and Reporting Critical DeficiencyAsset condition is deemed critical as defined in the NBIS
Incident Response Procedures
Documentation and Reporting Critical Deficiency Reporting
Part I – InspectorLocation and Description of the Critical Deficiency
Part II - Program AdministratorAnticipated Plan for the Bridge
Part III & IV – MnDOT Bridge OfficeDescription of Final Action Taken
Incident Response Procedures
Repair OptionsRepair by In-House Bridge
Maintenance Forces
Repair by ContractNegotiated ContractDesign-Bid-Build ContractState Contract (Retainer)Emergency Contract
Incident Response Procedures
Bridge 9039 (W 86th St. over I-35W)
Structure Background Four Span Steel Continuous Multi-beam with Cover Plates Simple Span Approaches, Continuous Center SpanBuilt in 1957 & Refurbished in 1996
First Hit 01/19/2015
Low-boy carrying Back-hoe traveling Southbound right lane, impacted Beams 9, 2 & 1.
Rotated Beam 9 out of alignment over 28 – 34 FTHooked the beam’s bottom flange, causing a semi-
circular web tear at the vertical stiffener and propagation of an existing cover plate weld crack.
Third Hit 06/30/2015
Low-boy carrying back-hoe traveling Southbound right Lane impacted Beam 9
Rotated Beam 9 out of alignment over 28 – 34 FTBeam stool crushed and shear connectors lost
composite action
Low-boy carrying back-hoe traveling Southbound right lane
Back-hoe’s “knuckle” struck Beams 9, 8, 7, 2, & 1
Virtually identical location as 3rd hit, causing extensive impact damage
Fourth Hit 02/20/2016
Fourth Hit Cont.
Further rotated Beam 9 out of alignmentFull length deck “stool” failure along Beam 9 Shear stud connectors lost composite action
Fourth Hit Cont.
CenterPoint Energy 10" Natural Gas-line fractured above Pier 1
Pipeline capped that day and removed 3/03/16
Low-boy convey carrying storage tanks traveling Southbound Right Lane impacted Beam 1
Rotated Beam 1 out of alignment over 34 FT with vertical stiffener tearing
Beam stool crushed and shear connectors lost composite action
Fifth Hit 04/23/2017
Two BridgesBr. 9213 & 9039
Bridge 9213 (W 82nd St. over I-35W)
Structure Background
Four span steel multi-beam structure
Simple span approaches, continuous center span with welded cover plates
Built in 1957 & refurbished in 1995
Vertical Clearance 15.3'
Initial Response
Bridge 9039 (W 86th St.)Reported as a Critical Deficiency after the 4th hitClosed outside lanes above damaged fascia beamsClosed bridge after 5th hit
Contract in place to replace the bridge in July 2017
Bridge 9213 (W 82nd St.)Reported as a Critical Deficiency Closed eastbound lane above damaged fascia beam
Repair
Bridge 9213 Repair OptionsAdd repair to existing Bridge 9039 Replacement
ProjectJust outside of the project limits
Heat Straightening by State Contract
Beam replacement identified as best fix to restore full structural capacity
Replace Beam by Emergency AuthorizationNew beam or salvaged beam?
Repair
Emergency AuthorizationWorked with Contractor
on Bridge 9039 replacement contract to develop a rough work plan and estimate
Ordered a new steel beam due to schedule restraints for salvaging
Repair
Emergency AuthorizationRemoval Weekend closure (July 2017)
Beam PlacementNight closure (September 2017)
Deck PourNight closure (October 2017)
Over height roll-off container truck traveling Westbound Left Lane impacted Beam 1
Damage: girder fracture, spalling, delamination, stirrup bars & pre-stressing strands cut
Bridge 9733 I-35W over Lake St.
Semi-truck forced to avoid carBroke through guardrail & collided with
west pylon Semi-truck’s tractor caught on fire,
completely engulfed
Overhead Sign BridgeI-35W