integrated para-xylene & purified terephthalic acid (px-pta

470
EIA Report 1 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051 ENVIRONMENTAL IMPACT ASSESSMENT REPORT For Integrated Para-Xylene & Purified Terephthalic Acid (PX-PTA) Project within the existing Refinery Complex At IOCL Paradip Refinery & Petrochemical Complex, Paradip Village: Abhaychandrapur P.O. Jhimani - Kujang Taluk: Kujang District: Jagatsinghpur State: Odisha [Project termed under Schedule 5(c) Category ‘A’ – Petro-chemical complexes (industries based on processing of petroleum fractions & natural gas and/or reforming to aromatics” as per EIA Notification 2006 and its Amendments] Submitted by: INDIAN OIL CORPORATION LIMITED, PARADIP REFINERY EIA CONSULTANT: M/s. Hubert Enviro Care Systems (p) Limited June 2021

Upload: khangminh22

Post on 18-Jan-2023

0 views

Category:

Documents


0 download

TRANSCRIPT

EIA Report

1 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

ENVIRONMENTAL IMPACT ASSESSMENT REPORT

For

Integrated Para-Xylene & Purified

Terephthalic Acid (PX-PTA) Project within

the existing Refinery Complex At

IOCL Paradip Refinery & Petrochemical Complex, Paradip

Village: Abhaychandrapur

P.O. Jhimani - Kujang

Taluk: Kujang

District: Jagatsinghpur

State: Odisha

[Project termed under Schedule 5(c) Category ‘A’ – Petro-chemical

complexes (industries based on processing of petroleum fractions & natural

gas and/or reforming to aromatics” as per EIA Notification 2006 and its

Amendments]

Submitted by:

INDIAN OIL CORPORATION LIMITED, PARADIP REFINERY

EIA CONSULTANT:

M/s. Hubert Enviro Care Systems (p) Limited

June 2021

EIA Report

2 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Declaration by the Head of the Accredited Consultant Organization

I, Dr. J. R. Moses hereby, confirm that the below mentioned experts prepared the EIA/EMP

for the “Integrated Para-Xylene & Purified Terephthalic Acid (PX-PTA) Project within

the existing Refinery Complex” at Abhaychandrapur village, Jagatsinghpur District,

Odisha State by M/s. Indian Oil Corporation Limited and also confirms that I shall be

fully accountable for any misleading information mentioned in this statement.

Signature:

Date: 24-06-2021

Name: Dr. J.R Moses

Designation: CEO

Name of the EIA Consultant Organization: Hubert Enviro Care Systems (p) Ltd., Chennai.

NABET Certificate No & Validity: NABET/EIA/1922/RA 0172 Valid up to 13/10/2022.

EIA Report

3 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Declaration of Experts contributing to the EIA

I hereby certify that I was involved in the preparation of EIA/ EMP for the “Integrated

Para-Xylene & Purified Terephthalic Acid (PX-PTA) Project within the existing

Refinery Complex” at Abhaychandrapur village, Jagatsinghpur District, Odisha State

by M/s. Indian Oil Corporation Limited as EIA Coordinator with the support of the

following Functional Area Experts.

EIA Co-ordinator

Name: Dr. J R Moses

Signature:

Date:24-06-2021

Contact Information:

Hubert Enviro Care Systems (p) Ltd.,

# A-21, Phase III, Behind Lions Club School,

Thiru-vi-ka Industrial Area, Guindy,

Chennai –600032.

Tamil Nadu, India.

Email: [email protected]

Website: www.hecs.in

Functional Area Experts (FAEs):

S. No.

Functional Areas

Name of the Expert Signature Duration of Involvement

1. AP FAEDr. J R Moses

Sep 2018 till date

Mr. Vamsee Krishna Navooru Sep 2018 till

date

2. AQ FAE Dr. J R Moses Sep 2018 till

date

3. WP FAE

Dr. J R Moses Sep 2018 till

date

Mr. Vamsee Krishna Navooru Sep 2018 till

date

FAA Mr. Chengalvarayan Sep 2018 till

date

4. SHW FAE Mr. A. Manoharan Sep 2018 till March 2021

EIA Report

4 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No.

Functional Areas

Name of the Expert Signature Duration of Involvement

Mr. Vamsee Krishna Navooru Sep 2018 till

date

5. SE FAE Mr. V. Dhivakar Sep 2018 till

date

6. EB FAEDr.. Sundararajan

Sep 2018 till date

Dr. Rajkumar Samuel Sep 2018 till

date

7. HG FAE Mr. MallikarjunaRao Sep 2018 till

date

8. Geo FAE Mr. MallikarjunaRao Sep 2018 till

date

9. NV FAEMr. Vivek P. Navare

Sep 2018 till date

Mr. Vamsee Krishna Navooru Sep 2018 till

date

10. LU FAE Mr. VenkateswarluRachala Sep 2018 till

date

11. RH FAE Dr. J R Moses Sep 2018 till

date

12. SC FAEMr. A. Manoharan

Sep 2018 till March 2020

Dr.B.C.Nagaraja Feb 2020 till March 2021

AP - Air pollution monitoring, prevention and control

AQ - Meteorology, air quality modeling and prediction

EB - Ecology and biodiversity

HG - Hydrology, ground water and water conservation

LU - Land use

NV - Noise & Vibration

RH - Risk assessment and hazards management

SC - Soil conservation

SE - Socio-economics

SHW - Solid and hazardous waste management

WP - Water pollution monitoring, prevention and control

EIA Report

5 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Acknowledgement

The following personnel are gratefully acknowledged for their fullest support in collection,

compilation of needful data regarding the project and kind cooperation in fulfilling the report

on Environmental Impact Assessment (EIA)/EMP for “Integrated Para-Xylene & Purified

Terephthalic Acid (PX-PTA) Project within the existing Refinery Complex” at

Abhaychandrapur village, Jagatsinghpur District, Odisha State by M/s. Indian Oil

Corporation Limited

M/s. Indian Oil Corporation Limited

1) Mr. BR Malik – Chief General Manager (HSE)

2) Mr. Sarvesh Kumar – Deputy General Manager (HSE)

3) Mr. SF Hashmy – Chief Manager (HSE)

4) Mr. B.Barla – Senior Manager (HSE)

M/s Hubert Enviro Care System Private Limited

1) Dr. J R Moses (CEO and EIA Coordinator)

2) Dr. Raj Kumar Samuel (Director- Technical)

3) Mr. Vamsee Krishna Navooru (Consultancy Head)

4) Mr. Manoj Kumar (Risk Engineer)

5) Ms. S. Rekha (Trainee Engineer)

6) Mr.M. Rabik Raja (Trainee Engineer)

EIA Report

6 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Contents

CHAPTER 1 ................................................................................................................... 26

1 INTRODUCTION ..................................................................................................... 27

1.1 Introduction to Project & Project Proponent .......................................................... 27

1.2 Purpose of the EIA report ...................................................................................... 30

1.3 Brief description of the Project .............................................................................. 30

1.4 EIA cost ................................................................................................................ 31

1.5 Scope of the study & Methodology adopted .......................................................... 31

1.5.1 Objectives of the EIA Report .......................................................................... 32

1.5.2 Scope of Work ................................................................................................ 32

1.5.3 EIA Process .................................................................................................... 34

1.6 Objectives of the Study ......................................................................................... 35

1.7 Applicable Regulatory Framework ........................................................................ 36

1.8 ToR Compliance ................................................................................................... 41

Material Handling, Storage and Transportation ................................................................ 82

CHAPTER 2 ................................................................................................................. 101

2 PROJECT DESCRIPTION ...................................................................................... 102

2.1 Project Description.............................................................................................. 102

2.1.1 Type of Project ............................................................................................. 103

2.2 Need of the project .............................................................................................. 103

2.3 Site Location ....................................................................................................... 103

2.4 Existing Environmental Setup ............................................................................. 111

2.5 Project Cost ........................................................................................................ 112

2.6 Proposed Schedule for Approval and Implementation ......................................... 112

2.7 Project Details ..................................................................................................... 112

2.7.1 Existing Facility ............................................................................................ 112

2.7.2 Size & Magnitude of Operation ..................................................................... 114

2.7.3 Existing Utilities .............................................................................................. 116

2.7.3.1 Existing Gas Monitoring System ..................................................................... 121

2.7.3.2 Existing Fire protection system ........................................................................ 122

2.7.4 Proposed Facility ............................................................................................. 125

2.7.4.1 Technology & Process Description .................................................................. 125

2.7.4.1.1 Paraxylene (PX) ........................................................................................... 125

EIA Report

7 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.7.4.1.2 Purified Terephthalic Acid (PTA) ................................................................. 135

2.7.4.2 Raw Material and products .............................................................................. 158

2.7.5 Proposed Offsite Facilities ............................................................................... 162

2.7.6 Proposed unit facilities and Utilities ................................................................ 164

2.7.7 Proposed Gas Monitoring System .................................................................... 168

2.7.7.1 Mitigation Measures ........................................................................................ 169

2.7.7.2 Precaution & Safety Measures against Fire Hazards ........................................ 170

2.7.7.3 Assessment of new & untested Technology ..................................................... 170

2.7.8 Sulphur Balance .............................................................................................. 171

2.8 Plot area .............................................................................................................. 171

2.8.1 Site Photographs ........................................................................................... 171

2.8.2 Land Area Breakup ....................................................................................... 175

2.9 Manpower ........................................................................................................... 180

2.10 Power and Fuel Requirements ............................................................................. 180

2.11 Water requirements ............................................................................................. 181

2.12 Source of water Supply ....................................................................................... 185

2.13 Project schedule .................................................................................................. 186

2.14 Air Pollution Control Measures ........................................................................... 186

2.15 Green Belt ........................................................................................................... 186

2.16 Water Pollution Control Measures ...................................................................... 190

2.17 Proposed Effluent Treatment Plant ...................................................................... 194

2.17.1 PX Effluent Treatment .................................................................................. 195

2.17.2 PTA Effluent Treatment ................................................................................ 195

2.18 Solid waste Management .................................................................................... 199

2.19 Hazardous Waste Management ........................................................................... 199

CHAPTER 3 ................................................................................................................. 205

3 DESCRIPTION OF ENVIRONMENT .................................................................... 206

3.1 Preamble ............................................................................................................. 206

3.2 Study Area .......................................................................................................... 206

3.3 Description of Study Area ................................................................................... 206

3.4 Environmentally/Ecologically Sensitive areas ..................................................... 210

3.5 Physical Conditions of PIA district ..................................................................... 216

3.5.1 PIA District Profile ............................................................................................... 216

EIA Report

8 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.5.2 Climatic Conditions .............................................................................................. 216

3.5.3 Natural Resources of PIA District ......................................................................... 217

3.5.3.1 Flora & Fauna .................................................................................................... 217

3.5.3.2 Forest Resources ................................................................................................ 217

3.5.3.3 Irrigation ............................................................................................................ 218

3.5.3.4 Agricultural Resources ....................................................................................... 219

3.5.3.5 Mineral Resources ............................................................................................. 219

3.5.4 Land Use & Land Cover ....................................................................................... 221

3.5.4.1 Land Use and Land Cover of the Study Area ...................................................... 225

3.5.5 Topography .................................................................................................. 228

3.5.6 Geomorphology of PIA district ..................................................................... 230

3.5.7 Geomorphology of the Study Area ................................................................ 230

3.5.8 Hydrogeology of PIA district ........................................................................ 235

3.5.9 Drainage Pattern in PIA district ..................................................................... 236

3.5.10 Geology ........................................................................................................ 238

3.5.11 Seismicity ..................................................................................................... 238

3.5.12 Soils in PIA District ...................................................................................... 240

3.5.13 Natural Hazards in PIA District ..................................................................... 241

3.6 Air Environment ...................................................................................................... 242

3.6.1 Meteorological Conditions ............................................................................ 243

3.6.2 Meteorological Data Collection ..................................................................... 243

3.6.3 General Meteorological Scenario based on IMD Data ................................... 243

3.6.4 Meteorological Scenario during Study Period ............................................... 245

3.6.5 Atmospheric Inversion .................................................................................. 246

3.7 Ambient Air Quality ........................................................................................... 247

3.7.1 Ambient Air Quality Monitoring Stations ..................................................... 247

3.7.2 Ambient Air Quality Monitoring Techniques and Frequency ........................ 250

3.7.3 Results and Discussions ................................................................................ 251

3.7.4 Observations ................................................................................................. 256

3.8 Noise Environment ............................................................................................. 256

3.8.1 Results and Discussions ................................................................................ 256

3.8.2 Observations ................................................................................................. 257

3.9 Water Environment ............................................................................................. 259

EIA Report

9 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.9.1 Surface Water Resources ...................................................................................... 259

3.9.1.1 Surface Water Quality Assessment ................................................................ 259

3.9.1.2 Results and Discussions ................................................................................ 268

3.9.2 Ground Water Resources .............................................................................. 268

3.9.2.1 Ground Water Quality ................................................................................... 269

3.9.2.2 Results and Discussions ................................................................................ 276

3.10 Soil as a resource and its quality .......................................................................... 276

3.10.1 Results and Discussions ................................................................................ 282

3.11 Biological Environment ...................................................................................... 282

3.11.1 Flora ............................................................................................................. 283

3.11.2 Fauna ............................................................................................................ 287

3.11.3 Management in and around Project area ........................................................ 293

3.11.4 Summary ...................................................................................................... 294

3.12 Socio Economic Profile ....................................................................................... 295

3.12.1 Socio Economic Profile of PIA District ......................................................... 295

3.12.1.1 Socio Economic Aspects ............................................................................... 295

3.12.1.2 Population and Household Size ..................................................................... 296

3.12.1.3 Sex Ratio ...................................................................................................... 297

3.12.1.4 Scheduled Castes and Scheduled Tribes ........................................................ 297

3.12.1.5 Education & Literacy .................................................................................... 297

3.12.1.6 Health Facilities ............................................................................................ 298

3.12.1.7 Employment and Livelihood ......................................................................... 299

3.12.2 Socio Economic Profile of study area ............................................................ 299

3.12.2.1 Employment and livelihood ............................................................................. 307

3.12.2.2 Educational infrastructure within study area ..................................................... 308

3.12.2.3 Dwelling within study area ............................................................................... 316

3.12.2.4 Health facilities within the study area ............................................................... 316

3.12.3 Observations ................................................................................................. 317

CHAPTER 4 ................................................................................................................. 318

4 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES . 319

4.1 Introduction ........................................................................................................ 319

4.2 Proposed Project Activities ................................................................................. 319

4.3 Construction Phase.............................................................................................. 319

EIA Report

10 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.3.1 Impacts during Construction Phase .................................................................. 320

4.3.2 Mitigation Measures for Construction Phase .................................................... 320

4.3.3 Land environment............................................................................................ 321

4.3.4 Air environment .............................................................................................. 323

4.3.5 Water environment .......................................................................................... 324

4.3.6 Noise environment .......................................................................................... 324

4.3.7 Waste generation ............................................................................................. 325

4.3.8 Ecology ........................................................................................................... 326

4.3.9 Social environment .......................................................................................... 326

4.4 Operation Phase .................................................................................................. 326

4.4.1 Impacts during Operational Phase .................................................................... 326

4.5 Air Environment ................................................................................................. 327

4.5.1 Meteorological data ...................................................................................... 327

4.5.2 AERMET Process ......................................................................................... 328

4.5.3 AERMOD Process ........................................................................................ 329

4.5.4 Emissions ..................................................................................................... 330

4.5.4.1 Point Source Emission (Proposed Stack Emission) ........................................ 332

4.5.4.2 Summary on Stack Emission ......................................................................... 340

4.5.4.3 Line source emission (Transportation) .......................................................... 341

4.5.4.4 Summary on Transportation Emission ........................................................... 348

4.5.4.5 Cummulative Emission ................................................................................. 349

4.5.4.6 Summary on Cummulative Emission ............................................................ 355

4.5.4.7 Other Emission-Storage Tank vent & PX-Process vent emmission ................ 356

4.5.4.8 Summary on Other Emission-Storage Tank vent & PX-Process vent emmission363

4.5.4.9 Other Emission-PTA Process vent & Silo vent emmission ............................ 364

4.5.4.10 Summary on Other Emission- PTA Process vent & Silo vent emmission ...... 378

4.5.5 Impacts due to Traffic and Transportation ..................................................... 379

4.6 Noise Environment ............................................................................................. 379

4.6.1 Impact ........................................................................................................... 379

4.6.2 Mitigation Measure ....................................................................................... 380

4.7 Water Environment ............................................................................................. 381

4.7.1 Mitigation Measures ..................................................................................... 382

4.7.2 Waste Water Quality, Quantity and Treatment Method ................................. 382

EIA Report

11 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.8 Land Environment .............................................................................................. 383

4.8.1 Potential Impact Due to Location .................................................................. 383

4.8.2 Impacts Due to Changes in Land Use Pattern ................................................ 383

4.8.3 Mittigation Measures .................................................................................... 383

4.9 Marine Environment ........................................................................................... 383

4.10 Solid Waste Management .................................................................................... 384

4.10.1 Impact Due to Solid Waste Generation .......................................................... 384

4.10.2 Mitigation Measures ..................................................................................... 384

CHAPTER 5 ................................................................................................................. 385

5 ANALYSIS OF ALTERNATIVES ......................................................................... 386

5.1 Introduction ........................................................................................................ 386

5.2 Site Alternative ................................................................................................... 386

5.3 Water Supply Alternative .................................................................................... 386

5.4 Technology Alternative ....................................................................................... 386

CHAPTER 6 ................................................................................................................. 387

6 ENVIRONMENTAL MONITORING PROGRAM ................................................. 388

6.1 Introduction ........................................................................................................ 388

6.2 Environmental Effects Monitoring in EIA ........................................................... 388

6.2.1 Post Project Environment Monitoring Program ............................................. 389

6.2.2 Monitoring Methodologies ............................................................................ 390

6.3 Reporting & Documentation ............................................................................... 391

6.4 Budget for Environmental Monitoring Plan ......................................................... 391

CHAPTER 7 ................................................................................................................. 393

7 ADDITIONAL STUDIES ....................................................................................... 394

7.1 Public Consultation ............................................................................................. 394

7.1.1 Reply to the issues raised by the public during Public Hearing on 02.03.2021 398

7.2 Risk Assessment ................................................................................................. 415

7.3 Applicability of Environmental Clearance ........................................................... 416

7.4 Consent for Existing Operation ........................................................................... 416

7.5 TOR issued by MoEF ......................................................................................... 417

7.6 Copy of Standard TOR........................................................................................ 418

CHAPTER 8 ................................................................................................................. 424

8 PROJECT BENEFITS ............................................................................................. 425

EIA Report

12 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

8.1 Project Benefits ................................................................................................... 425

CHAPTER 9 ................................................................................................................. 427

9 ENVIRONMENTAL COST AND BENEFIT ANALYSIS ...................................... 428

CHAPTER 10 ................................................................................................................ 429

10 ENVIRONMENTAL MANAGEMENT PLAN ....................................................... 430

10.1 Introduction ........................................................................................................ 430

10.2 Objectives of EMP .............................................................................................. 430

10.3 EMP Structure and Organization ......................................................................... 431

10.4 EMP Roles and Responsibilities .......................................................................... 432

10.5 Environmental Management Plan for Construction Phase ................................... 434

10.5.1 Air Quality .................................................................................................... 434

10.5.2 Noise Environment ....................................................................................... 435

10.5.3 Water Quality and Water Resources .............................................................. 435

10.5.4 Solid Waste ................................................................................................... 435

10.5.5 Land Environment ........................................................................................ 436

10.5.6 Ecology ........................................................................................................ 436

10.5.7 Socio Economic ............................................................................................ 436

10.6 Environmental Management Plan for Operation Phase ........................................ 436

10.6.1 Air Pollution Management ............................................................................ 437

10.6.1.1 Gaseous Waste Emissions ............................................................................. 439

10.6.2 Waste Water Management ............................................................................ 442

10.6.3 Solid Waste Management .............................................................................. 445

10.6.4 Noise Environment ....................................................................................... 446

10.6.5 Material Handling Storage and Transportation .............................................. 446

10.6.6 Green Belt Development ............................................................................... 449

10.6.7 Rain Water Harvesting Plan .......................................................................... 451

10.7 Occupational Health and Safety .......................................................................... 454

10.7.1 Safety Measures ............................................................................................ 456

10.7.2 Precaution & Safety Measures Against Fire Hazards ..................................... 457

10.8 Environmental Management Cell ........................................................................ 458

10.9 Corporate Environmental Policy ......................................................................... 458

10.10 Budgetary Provision for Environmental Management Plan .............................. 460

10.11 Corporate Social Responsibility ....................................................................... 460

EIA Report

13 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

10.12 Corporate Environmental Responsibility (CER) .............................................. 460

CHAPTER 11 ................................................................................................................ 462

11 SUMMARY & CONCLUSION .............................................................................. 463

CHAPTER 12 ................................................................................................................ 465

12 DISCLOSURE OF CONSULTANTS ....................................................................... 466

12.1 Brief Profile of Hubert Enviro Care Systems (P) Limited (HECS) ....................... 466

12.2 QCI-NABET - EIA Accreditation ....................................................................... 468

12.3 Copy of QCI NABET Accreditation .................................................................... 469

EIA Report

14 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

List of Tables

Table 1-1 Chronology of Environmental clearances & CRZ clearance ................................ 29

Table 1-2Applicable Acts and Rules for the proposed Refinery project ............................... 37

Table 2-1Geographical coordinates of the project site ....................................................... 103

Table 2-2 Existing Environmental Setup of the study region ............................................. 111

Table 2-3List of major Industries within 10km Radius from the project site ...................... 112

Table 2-4 Time Schedule for completion of the proposed project ...................................... 112

Table 2-5 Existing /Approved/Proposed Units ................................................................... 114

Table 2-6 List of Existing utilities at PDR ......................................................................... 116

Table 2-7 Existing storage tanks ........................................................................................ 117

Table 2-8 Pipelines to South Loading Jetty ........................................................................ 120

Table 2-9 Pipeline crossing Santra Creek for the Proposed PX PTA project ...................... 120

Table 2-10 Limits of Gas Detector Type ........................................................................... 121

Table 2-11 List of firefighting facility available ................................................................ 122

Table 2-12 Equipment List- PX Process Unit .................................................................... 137

Table 2-13 Equipment List- PTA Process Unit .................................................................. 147

Table 2-14 Existing and proposed product ......................................................................... 158

Table 2-15 Details of Proposed Chemicals and Catalyst for PX and PTA .......................... 158

Table 2-16 Equipment List- Offsite & Utilities .................................................................. 162

Table 2-17 Major facilities in the proposed PX unit with Capacity .................................... 164

Table 2-18 Major facilities in the proposed PTA unit with Capacity .................................. 165

Table 2-19 Major facilities in the proposed New ETP ....................................................... 166

Table 2-20 Proposed Utilities ............................................................................................ 166

Table 2-21 Upcoming Storage Facilities ............................................................................ 167

Table 2-22 Sulphur balance for Proposed Facility ............................................................. 171

Table 2-23 Land use planning of the Project Site ............................................................... 175

Table 2-24 Manpower Requirement .................................................................................. 180

Table 2-25 Power and Fuel Requirement ........................................................................... 181

Table 2-26 Existing and Proposed Water Requirements .................................................... 182

Table 2-27 Green Belt Area Breakup................................................................................. 187

Table 2-28 Summary of Plantation for the year 2007-2020 ................................................ 189

Table 2-29 Characteristics of Effluent Generated .............................................................. 193

Table 2-30 Characteristics Final effluent discharge to sea .................................................. 193

Table 2-31 Solid Waste in Operational Phase .................................................................... 199

Table 2-32 Existing Hazardous Wastes Generation ............................................................ 200

Table 2-33 Proposed Hazardous Wastes Generation ........................................................... 200

Table 3-1 Environmentally Sensitive Areas within 15km from Project Boundary .............. 210

Table 3-2 Source wise Irrigation potential created during the year 2009-10 & 2010-11 ..... 218

Table 3-3 District land use/land cover statistics (2011-12) for Jagatsinghapurdistrict......... 221

Table 3-4 Land Use Pattern of the Study Area ................................................................... 225

Table 3-5Geomorphology of the Study Area ..................................................................... 230

Table 3-6 Climatological Summary -Paradip port (1971-2000).......................................... 244

Table 3-7 Meteorological Data for the Study Period (March - May 2019) ......................... 245

EIA Report

15 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

.Table 3-8 Details of Ambient Air Quality Monitoring Locations ...................................... 247

Table 3-9 Analytical Methods for Analysis of Ambient Air Quality Parameters ................ 250

Table 3-10 Summary of the average baseline concentrations of pollutants ......................... 252

Table 3-11 Day and Night Equivalent Noise Levels .......................................................... 257

Table 3-12 Test methods used for the analysis of water quality parameters ....................... 259

Table 3-13 Details of Surface water sampling locations ..................................................... 261

Table 3-14: Surface water Monitoring Results ................................................................... 263

Table 3-15: Dynamic ground water resources of Jagatsinghapur District ........................... 268

Table 3-16 Details of Groundwater Quality Monitoring Locations .................................... 269

Table 3-17 Ground Water Monitoring Results ................................................................... 271

Table 3-18 Soil & Sediment Quality Monitoring Locations ............................................... 276

Table 3-19 Soil & Sediment Quality Monitoring Results ................................................... 279

Table 3-20 List of flora reported/observed in the study area .............................................. 283

Table 3-21 List of Mangroves in the study area ................................................................. 286

Table 3-22 List of Fauna observed in the study area .......................................................... 287

Table 3-23 Social Indicators of Jagatsinghapur District ..................................................... 296

Table 3-24Education Infrastructures in the Jagatsinghapur District .................................... 298

Table 3-25 Medical Facilities available in JagatsinghapurDistrict ...................................... 298

Table 3-26 Population profile within study area ................................................................ 300

Table 3-27 Summary of Socioeconomic indicators within the study area ........................... 307

Table 3-28 Classification of workers within study area ...................................................... 307

Table 3-29 Details of Literacy population in the study area ............................................... 309

Table 3-30 Health facilities available in the study area ...................................................... 316

Table 4-1 Existing Stack Emission details ......................................................................... 330

Table 4-2Proposed Stack Emission details......................................................................... 334

Table 4-3 Estimated Top 10 Highest Concentrations of PM Obtained Through Modeling on

stack emission ................................................................................................................... 335

Table 4-4 Estimated Top 10 Highest Concentrations of Sulphur Dioxide obtained through

modeling on stack emission ............................................................................................... 336

Table 4-5 Estimated Top 10 Highest Concentrations of oxide of Nitrogen obtained through

modeling on stack emission ............................................................................................... 337

Table 4-6 Estimated Top 10 Highest Concentrations of Carbon Monoxide obtained through

modeling on stack emission ............................................................................................... 338

Table 4-7 Estimated Top 10 Highest Concentrations of Carbon Dioxide obtained through

modeling on stack emission ............................................................................................... 339

Table 4-8 Total Maximum GLCs from the Point Source (Stack Emissions) ....................... 340

Table 4-9 Proposed Transportation Emission details ......................................................... 344

Table 4-10 Estimated Top 10 Highest Concentrations of Particulate Matter obtained through

modeling on Transportation emission ................................................................................ 345

Table 4-11 Estimated Top 10 Highest Concentrations of oxide of Nitrogen obtained through

modeling on Transportation emission ................................................................................ 346

Table 4-12 Estimated Top 10 Highest Concentrations of Carbon Monoxide obtained through

modeling on Transportation emission ................................................................................ 347

EIA Report

16 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 4-13 Total Maximum GLCs from the transportation Emissions ............................... 348

Table 4-14 Proposed Cumulative Emission details (Point source emission and Line source

emission) .......................................................................................................................... 349

Table 4-15 Estimated Top 10 Highest Concentrations of Particulate Matter obtained through

modeling on Cummulative emission .................................................................................. 350

Table 4-16 Estimated Top 10 Highest Concentrations of Sulphur Dioxide obtained through

modeling on Cummulative emission .................................................................................. 351

Table 4-17 Estimated Top 10 Highest Concentrations of oxide of Nitrogen obtained through

modeling on Cummulative emission .................................................................................. 352

Table 4-18 Estimated Top 10 Highest Concentrations of Carbon Monoxide obtained through

modeling on Cummulative emission .................................................................................. 353

Table 4-19 Estimated Top 10 Highest Concentrations of Carbon Dioxide obtained through

modeling on Cummulative emission .................................................................................. 354

Table 4-20 Total Maximum GLCs from the Cummulative Emissions (point source emission

& line source emission) ..................................................................................................... 355

Table 4-21 Proposed Storage tank vents and PX-process vent Emission details ................. 358

Table 4-22 Estimated Top 10 Highest Concentrations of VOC obtained through modeling on

other vent emission ........................................................................................................... 359

Table 4-23 Estimated Top 10 Highest Concentrations of Benzene obtained through modeling

on other vent emission....................................................................................................... 360

Table 4-24 Estimated Top 10 Highest Concentrations of Toluene obtained through modeling

on other vent emission....................................................................................................... 361

Table 4-25 Estimated Top 10 Highest Concentrations of Carbon Dioxide obtained through

modeling on other vent emission ....................................................................................... 362

Table 4-26 Total Maximum GLCs from the Storage Tank vent & PX-Process vent

emmission ......................................................................................................................... 363

Table 4-27 Proposed PTA Process vent & Silo vent emission details ................................. 366

Table 4-28 Estimated Top 10 Highest Concentrations of Benzene obtained through modeling

on other vent emission....................................................................................................... 367

Table 4-29 Estimated Top 10 Highest Concentrations of Toluene obtained through modeling

on other vent emission....................................................................................................... 368

Table 4-30 Estimated Top 10 Highest Concentrations of Xylene obtained through modeling

on other vent emission....................................................................................................... 369

Table 4-31 Estimated Top 10 Highest Concentrations of Acetic Acid obtained through

modeling on other vent emission ....................................................................................... 370

Table 4-32 Estimated Top 10 Highest Concentrations of Methanol obtained through

modeling on other vent emission ....................................................................................... 371

Table 4-33 Estimated Top 10 Highest Concentrations of MethylAcetate obtained through

modeling on other vent emission ....................................................................................... 372

Table 4-34 Estimated Top 10 Highest Concentrations of Bromide obtained through modeling

on other vent emission....................................................................................................... 373

Table 4-35 Estimated Top 10 Highest Concentrations of Methyl Bromide obtained through

modeling on other vent emission ....................................................................................... 374

EIA Report

17 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 4-36 Estimated Top 10 Highest Concentrations of Carbon Monoxide obtained through

modeling on other vent emission ....................................................................................... 375

Table 4-37 Estimated Top 10 Highest Concentrations of PTA Dust obtained through

modeling on other vent emission ....................................................................................... 376

Table 4-38 Estimated Top 10 Highest Concentrations of Nitrogen obtained through modeling

on other vent emission....................................................................................................... 377

Table 4-39 Total Maximum GLCs from the Process & Silo Vent Emissions ..................... 378

Table 4-40 Existing & proposed vehicular movement per Hour (Peak Hour) ..................... 379

Table 4-41 Traffic Volume after Implementation of the Project ......................................... 379

Table 6-1 Post Project Environmental Monitoring Plan ..................................................... 389

Table 6-2 Budgetary allocation for Environmental Monitoring .......................................... 391

Table 10-1 Responsibility for EMP Implementation .......................................................... 432

Table 10-2 Proposed Pollution control scheme .................................................................. 437

Table 10-3 Standards for Emissions from Furnaces, heaters and Boilers ............................ 438

Table 10-4 Gaseous Waste Emissions from PX Plant ........................................................ 440

Table 10-5 Gaseous Waste Emissions from PTA Plant ...................................................... 441

Table 10-6 Waste Effluents from PX Plant ........................................................................ 442

Table 10-7 Waste Effluents from PTA Plant ..................................................................... 444

Table 10-8 Liquid Waste Effluents from Offsite and Utilities ............................................ 445

Table 10-9 Raw Material Storage and Dispatch Facilities ................................................... 447

EIA Report

18 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

List of Figures

Figure 1-1 EIA Process ....................................................................................................... 35

Figure 2-1 Index map of the project site ............................................................................ 107

Figure 2-2 Google image showing salient features within 0- 1 Km radius ......................... 108

Figure 2-3 Google image showing salient features within 0- 5 Km radius .......................... 109

Figure 2-4 Google image showing salient features 0- 10 Km Radius Map around the study

region ................................................................................................................................ 110

Figure 2-5 Schematic diagram of Existing Refinery .......................................................... 114

Figure 2-6 Fire Water Network South ............................................................................... 123

Figure 2-7 Fire Water Network in North............................................................................ 124

Figure 2-8 Process Flow Diagram ..................................................................................... 154

Figure 2-9 Schematic representation of Process of PX unit ................................................ 155

Figure 2-10 Schematic representation of Process of PTA Unit-Sheet 1 .............................. 156

Figure 2-11 Schematic representation of Process of PTA Unit-Sheet 2 .............................. 157

Figure 2-12Material Balance across PX Process Unit ........................................................ 161

Figure 2-13Material Balance across PTA Process Unit ...................................................... 162

Figure 2-14 Site Photographs of Existing Refinery Complex ............................................. 172

Figure 2-15 Site Photographs of Proposed facility ............................................................. 173

Figure 2-16 Photographs of Existing ETP ......................................................................... 173

Figure 2-17 Photographs of Existing STP .......................................................................... 174

Figure 2-18 Existing Refinery Layout ............................................................................... 177

Figure 2-19 Proposed Layout ............................................................................................ 178

Figure 2-20 Existing and proposed plot plan...................................................................... 179

Figure 2-21 Water Balance Diagrams of Existing Refinery ............................................... 183

Figure 2-22 Water Balance Diagrams of Proposed Refinery .............................................. 184

Figure 2-23 Water Balance Diagrams for after expansion of Refinery ............................... 185

Figure 2-24 Green Belt Layout .......................................................................................... 188

Figure 2-25 Flow diagram of Effluent Treatment plant (Existing) ..................................... 192

Figure 2-26 Flow diagram of Effluent Treatment plant (Proposed) .................................... 192

Figure 2-27 Flow Diagram of WRP Plant (Existing) ......................................................... 193

Figure 2-28 Effluent Treatment plant (Proposed Layout) ................................................... 198

Figure 2-29 Google Earth demarcation of SLF area in IOCL Paradip Refinery .................. 201

Figure 2-30 Photograph of Secured Landfill Area with Geotextile Membrane around it in

IOCL Paradip Refinery ..................................................................................................... 202

Figure 2-31 Lablelling of Hazardous waste Containers ...................................................... 202

Figure 2-32 Hazardous Waste labelsdisplayed on packaging ............................................. 203

Figure 2-33 Hazardous Waste Storage area ....................................................................... 204

Figure 3-1Map showing the Satellite Image of the study area of Project ............................ 208

Figure 3-2Topo Map of Study area .................................................................................... 209

Figure 3-3 Environmental sensitive areas covering within 15 km from project boundary ... 215

Figure 3-4 Mineral Map of Odisha (Orissa) ....................................................................... 220

Figure 3-5Land use pattern of the Jagatsinghapur District ................................................. 223

Figure 3-6Land use map of the Jagatsinghapur District ..................................................... 224

EIA Report

19 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-7 Land Use Pattern of the Study Area ................................................................. 226

Figure 3-8 Land Use Map of the Study Area ..................................................................... 227

Figure 3-9Physical Map of Odisha .................................................................................... 228

Figure 3-10Contour Map of Study Area ............................................................................ 229

Figure 3-11Geomorphology Pattern of the Study Area ...................................................... 232

Figure 3-12Geomorphology Map of Jagatsinghapur District ............................................. 233

Figure 3-13Geomorphology Map of the Study Area .......................................................... 234

Figure 3-14Hydrogeology Map of Jagatsinghapur District ................................................ 236

Figure 3-15Drainage map of the study area ....................................................................... 237

Figure 3-16Geology Map of Orissa ................................................................................... 238

Figure 3-17 Seismicity Map of India ................................................................................. 239

Figure 3-18 Soil map of India ............................................................................................ 241

Figure 3-19 Wind hazard Map of India .............................................................................. 242

Figure 3-20 Wind rose during study period (March - May 2019) ....................................... 246

Figure 3-21Atmospheric inversion level at the project site ................................................ 247

Figure 3-22Map showing the Air monitoring locations ...................................................... 249

Figure 3-23: Trends of Measured Ambient Concentrations in the Study Area .................... 255

Figure 3-24 Map showing the Noise Monitoring locations ................................................ 258

Figure 3-25: Map showing the surface water monitoring locations .................................... 262

Figure 3-26 Map showing the groundwater monitoring locations ...................................... 270

Figure 3-27 Map showing the soil monitoring locations .................................................... 278

Figure 4-1 Wind rose diagram of Meteorological data considered for Modelling (March to

May 2019) ........................................................................................................................ 328

Figure 4-2 Project layout with proposed stack coordinates ................................................ 332

Figure 4-3 Google earth demarcation of proposed stack with coordinates .......................... 333

Figure 4-4 Predicted 24-Hrs’ GLC’s of PM within 10 km Radius of the Study Area on stack

emission ............................................................................................................................ 335

Figure 4-5 Predicted 24-Hrs’ GLC’s of SO2within 10 km Radius of the Study Area on stack

emission ............................................................................................................................ 336

Figure 4-6 Predicted 24-Hrs’ GLC’s of NOx within 10 km Radius of the Study Area on stack

emission ............................................................................................................................ 337

Figure 4-7 Predicted 1-Hr GLC’s of CO within 10 km Radius of the Study Area on stack

emission ............................................................................................................................ 338

Figure 4-8 Predicted 24-Hrs’ GLC’s of CO2 within 10 km Radius of the Study Area on stack

emission ............................................................................................................................ 339

Figure 4-9 Project layout with PTA truck Route ................................................................ 341

Figure 4-10 Project layout with Toluene truck Route ......................................................... 342

Figure 4-11 Google earth demarcation of proposed truck route with coordinates ............... 343

Figure 4-12 Predicted 24-Hrs’ GLC’s of PM within 10 km Radius of the Study Area on

Transportation emission .................................................................................................... 345

Figure 4-13 Predicted 24-Hrs’ GLC’s of NOx within 10 km Radius of the Study Area on

Transportation emission .................................................................................................... 346

EIA Report

20 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-14 Predicted 1-Hr GLC’s of CO within 10 km Radius of the Study Area on

Transportation emission .................................................................................................... 347

Figure 4-15 Predicted 24-Hrs’ GLC’s of PM within 10 km Radius of the Study Area on

Cummulative emission ...................................................................................................... 350

Figure 4-16 Predicted 24-Hrs’ GLC’s of SO2 within 10 km Radius of the Study Area on

Cummulative emission ...................................................................................................... 351

Figure 4-17 Predicted 24-Hrs’ GLC’s of NOx within 10 km Radius of the Study Area on

Cummulative emission ...................................................................................................... 352

Figure 4-18 Predicted 1-Hr GLC’s of CO within 10 km Radius of the Study Area on

Cummulative emission ...................................................................................................... 353

Figure 4-19 Predicted 24-Hrs’ GLC’s of CO2 within 10 km Radius of the Study Area on

Cummulative emission ...................................................................................................... 354

Figure 4-20 Project layout with proposed storage tank vent & PX-process vent coordinates

......................................................................................................................................... 356

Figure 4-21 Google earth demarcation of proposed storage tank vent & PX-process vent

coordinates ........................................................................................................................ 357

Figure 4-22 Predicted 24-Hrs’ GLC’s of VOC within 10 km Radius of the Study Area on

other vent emissions .......................................................................................................... 359

Figure 4-23 Predicted 24-Hrs’ GLC’s of Benzene within 10 km Radius of the Study Area on

other vent emissions .......................................................................................................... 360

Figure 4-24 Predicted 24-Hrs’ GLC’s of Toluene within 10 km Radius of the Study Area on

other vent emissions .......................................................................................................... 361

Figure 4-25 Predicted 24-Hrs’ GLC’s of CO2 within 10 km Radius of the Study Area on other

vent emissions ................................................................................................................... 362

Figure 4-26 Project layout with proposed PTA Process vent & Silo vent coordinates ........ 364

Figure 4-27 Google earth demarcation of proposed PTA Process vent & Silo vent coordinates

......................................................................................................................................... 365

Figure 4-28 Predicted 24-Hrs’ GLC’s of Benzene within 10 km Radius of the Study Area on

other vent emissions .......................................................................................................... 367

Figure 4-29 Predicted 24-Hrs’ GLC’s of Toluene within 10 km Radius of the Study Area on

other vent emissions .......................................................................................................... 368

Figure 4-30 Predicted 24-Hrs’ GLC’s of Xylene within 10 km Radius of the Study Area on

other vent emissions .......................................................................................................... 369

Figure 4-31 Predicted 24-Hrs’ GLC’s of Acetic Acid within 10 km Radius of the Study Area

on other vent emissions ..................................................................................................... 370

Figure 4-32 Predicted 24-Hrs’ GLC’s of Methanol within 10 km Radius of the Study Area on

other vent emissions .......................................................................................................... 371

Figure 4-33 Predicted 24-Hrs’ GLC’s of MethylAcetate within 10 km Radius of the Study

Area on other vent emissions ............................................................................................. 372

Figure 4-34 Predicted 24-Hrs’ GLC’s of Bromide within 10 km Radius of the Study Area on

other vent emissions .......................................................................................................... 373

Figure 4-35 Predicted 24-Hrs’ GLC’s of Methyl Bromide within 10 km Radius of the Study

Area on other vent emissions ............................................................................................. 374

EIA Report

21 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-36 Predicted 1-Hr GLC’s of CO within 10 km Radius of the Study Area on other

vent emissions ................................................................................................................... 375

Figure 4-37 Predicted 24-Hrs’ GLC’s of PTA Dust within 10 km Radius of the Study Area on

other vent emissions .......................................................................................................... 376

Figure 4-38 Predicted 24-Hrs’ GLC’s of Nitrogen within 10 km Radius of the Study Area on

other vent emissions .......................................................................................................... 377

Figure 7-1 Public Hearing Advertisements(Odisha) ........................................................... 395

Figure 7-2 Public Hearing Advertisements(English) .......................................................... 396

Figure 7-3 Public Hearing Announcement in nearby villages ............................................ 397

Figure 7-4 Public Hearing photographs ............................................................................. 397

Figure 10-1 Typical HSE Department Organogram ........................................................... 431

Figure 10-2Mode of Transport for Product materials ......................................................... 447

Figure 10-3 Green Belt Photographs ................................................................................. 450

Figure 10-4 Ecological park in Paradip Refinery ............................................................... 451

Figure 10-5 Rain water harvesting integrated with ecological park .................................... 452

Figure 10-6 Storm water pond for collecting surface runoff inside Refinery ...................... 453

Figure 10-7 Organogram for OHC .................................................................................... 456

Figure 10-8 EHS Policy .................................................................................................... 459

EIA Report

22 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

List of Annexure

ANNEXURE No. Documents

1 Land documents

2 Latest EC and its certified compliance report

3

Latest CTO with all CTO’s and CTE’s since inception with chronology

table & Self certified compliance report of latest CTO submitted to

SPCB, Odisha

4 PESO license

5 Earlier EC’s and its certified compliance report

6 Overall plan of PDR & Proposed ETP layout

7 Approval for Water Extraction

8 Green Belt Demarcation with the species of trees planted & Green belt

Layout

9 Water Balance Chart

10 Risk Assessment

11 ERDMP

12 Material Safety Data Sheet

13 Raw Data for AAQ

14 Hazardous Waste Authorization

15 Heath Monitoring Report

16 LDAR Report

17 Fire Protection Management

18 CSR Activity

19 Latest Safety audit report

20 Wildlife conservation plan

21 Latest Daily Environmental Safety Report

22 Occupational Hazardous Toxic gas monitoring data

EIA Report

23 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

ANNEXURE No. Documents

23 Approval target group for Pre Medical Check-up for Toxic Exposure

24 No litigation Affidavit

25 Flood risk assessment

26 Monitoring reports

27 Noise Survey Report

28 Medical Facilities within IOCL Paradip Refinery

29 Land allocation for proposed green belt

30 Executive Summary

31 Flare Management System

32 Latest Analysis report of effluent characteristics discharging into sea

33 Recommendation from OCZMA for laying pipeline across santra creek

34 MoM for FG/NG from GAIL

EIA Report

24 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

List of Abbrevations

EIA Environmental Impact Assessment

IOCL Indian Oil Corporation Limited

FCCU Fluidized Catalytic Cracking Unit

CDU Crude Distillation Unit

VDU Vacuum Distillation Unit

PET Polyethylene Terephthalate

PSF Poly Sulfone

PFY Phenol Formaldehyde

AIT Auto Ignition Temperature

LPG Liquefied Petroleum Gas

HAZOP Hazard and Operability Study

CPP Captive Power plant

VOC Volatile Organic Carbon

ETP Effluent Treatment Plant

HC Hydrocarbon

HPVGT High Pressure Vent Gas Treatment

OLIC Odisha lift Irrigation Corporation

OAIC Odisha Argo Industries Corporation

IMD Indian Meteorological Department

TDS Total Dissolved Solids

BOD Biochemical Oxygen Demand

COD Chemical Oxygen Demand

PUC Pollution Under Control

GLC Ground Level Concentration

SBL Stable Boundary Layer

CBL Convective Boundary Layer

LOS Level of service

DM Demineralised Water

LTD Low Tide line

EIA Report

25 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

ToR Terms of Reference

OISD Oil Industry safety Directorate

PLC Programmable Logic Controller

ALARP As Low as reasonably Practicable

ESC Enterprise Social Commitment

EMP Environmental Management plan

PM Particulate Matter

SO2 Sulphur Dioxide

NO2 Oxides of Nitrogen

H2S Hydrogen Sulphide

ISBL Inside Battery Limit

LDAR Leak Detection And Repair

OSHA Occupational Safety and Health Administration

VAUs Ventilation Air Units

EAUs Exhaust Air Units

IBR Indian Boiler Regulation

EIA Report

26 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CHAPTER 1

INTRODUCTION

EIA Report

27 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

1 INTRODUCTION

1.1 Introduction to Project & Project Proponent

Indian Oil Corporation Limited (IOCL) is India's largest commercial enterprise engaging in

the business of refining, pipeline transportation, marketing of petroleum products and also

involving in exploration production of crude oil gas, marketing of natural gas and

petrochemicals. IOCL accounts for nearly half of India’s petroleum products market share

owning 11 refineries. It is the 11th refinery of IOCL. Hon’ble Prime Minister Shri Narendra

Modi dedicated the refinery cum Petrochemical Complex to Nation on 7th Feb 2016.

The refinery was commissioned in the year 2015with a capacity of 15 MMTPA has been set

up at an estimated cost of Rs. 34,555 crores. The major processing units provided were

Fluidized Catalytic Cracking Unit (FCCU) 4.2 MMTPA, Crude/ Vacuum Distillation unit

(CDU/ VDU) 15 MMTPA, Delayed Coking unit 4.1 MMTPA, Diesel Hydro Treating Unit of

5.2 MMTPA, VGO hydro treatment Unit 5.4 MMTPA, Sulfur Recovery Unit 2 x 525 TPD +

1 TGTU.

Paradip Refinery has a unique INDMAX Unit technology, which is indigenously been

developed by Indian Oil's R&D Centre. The INDMAX (FCC) Unit has designed to produce

44% LPG, the highest yield from such plants. The commissioning of INDMAX Unit at

Paradip marks a major milestone in the history of Indian refining. With this, Indian Oil has

been recognized globally as a technology licensor. The other first-time technological features

of the Refinery include Flue Gas Desulphurisation facilities, Vapour Recovery system from

jetty loading and an alkylation process to get octane-rich low-benzene MS blend component,

etc.

The refinery can process 100% high Sulphur and heavy crude oil to produce various

petroleum products like Petrol and diesel BS-IV quality, kerosene, Aviation Turbine fuel,

Propylene, Sulphur and Petroleum Coke. The refinery has also designed to produce Euro-IV

premium quality Motor Spirit and other green auto fuel variants for export to advanced

countries. The products from the Refinery meet the energy demands of the domestic market

and partly the South-East Asia export market. The finished petroleum products from Paradip

Refinery being shipped to as far as Asia Pacific, Europe, USA, and to the demand centers in

the east of India, northeast and to some southern states like Andhra Pradesh and Telangana.

EIA Report

28 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Paradip Refinery has spread over a total area of 3,345 acres, including about 314 acres for

Residential and about 240 acres of land for other office and buildings. The area of 355 acres

is utilized for the connecting road in the total area. Land documents enclosed as Annexure 1.

The refinery is equipped with crude oil tanks to store High-Sulphur heavy crude, with

petroleum product & intermediate tanks (including for liquid Sulphur storage tanks). Apart

from these liquid storage facilities, there are LPG storage mounded bullets, propylene storage

mounded bullets, Hydrogen and alkylation feed mounded bullets. An elaborate infrastructure

is in place for pumping crude oil to the Paradip Refinery and for smooth, safe and efficient

movement of the finished products. This includes a crude oil unloading facility at Paradip

offshore with the first Single Point Mooring (SPM) facility on the east coast of India; a

complex cross-country product pipeline network; a marketing terminal with truck loading

bays and tank-wagon gantry; and an LPG terminal with facilities for road dispatch. But the

biggest crude receipt and product dispatch infrastructure of Paradip Refinery is the captive

South Oil Jetty, the first-of-its-kind in India made for a greenfield coastal refinery. The

products are dispatched through pipelines (20-25%), rail (20-25%), road (15-20%) & coastal

(40-50%) movements.

With an aim to add more value, a 0.680 MMTPA capacity Polypropylene (PP) Plant, based

on Propylene recovered from Cracked LPG generated from INDMAX Plant, is under

implementation and is scheduled for completion by 2019. The refinery also has plans to setup

an Ethylene Recovery Unit /Mono-Ethylene Glycol (MEG) These units are expected to be

completed by 2020-21.

The existing refinery obtained several Environmental Clearances since 1997.Summary of

EC’s obtained enclosed as with latest EC obtained from MoEF vide: J-11011/344/2016-IA.

II(I) dated 11thOct 2018, enclosed as Annexure-2. The existing plant is under operation with

OPCB consent for Air and water obtained vide: 5543/IND-I-CON-6414 dated 31.03.2021

valid till 31.03.2022 copy enclosed as Annexure 3.

PESO license obtained vide P/HQ/OR/15/1163 (P223845) dated 29.12.2020 Valid Up to:

31.12.2023 enclosed as Annexure-4.

Mr. Sarvesh Kumar, Deputy General Manger (HSE) of IOCL Paradip Refinery is the Project

Proponent with the registered office address: IOCL Paradip Refinery P.O. Jhimani, Paradip

Dist., Jagatsinghpur- 754141.

EIA Report

29 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 1-1 Chronology of Environmental clearances & CRZ clearance

S.

No MoEF File No Units

Date of

issue

Status of

Project

1 J-11011/26/97-IA.II(I) EC for Setting up grass root

Petroleum Refinery of 9MMTPA24.12.1997* Deferred

2 J-11011/26/1997-IA.II(I) EC for Setting up grass root

Petroleum Refinery of 9MMTPA28.04.2003* Deferred

3 J-11011/70/2007-IA. II(I)

EC for Grass Root Refinery

cum Petrochemical Complex

of 15 MMTPA

06-07-2007 Commissioned

4 J-11011/395/2012-IA.

II(I)

Extension of validity of

Environmental Clearance for

Grass Root Refinery cum

Petrochemical Complex of 15

MMTPA

18-09-2014 Commissioned

5 J-11011/395/2012-IA.

II(I)

EC Ammendment with Rapid

Railway Loading System

(RRLS) for Pet Coke

Evacuation and Minor revision

in Secondary Unit Capacities

06-01-2015 Commissioned

6 J-11011/344/2016-IA.

II(I)

EC and CRZ for Ethylene

Recovery Unit, Mono Glycol

Unit & BS VI facilities

11-10-2018Under

Construction

7 J-11011/395/2012-IA

II(I)

EC for Integrated Paraxylene&

Purified Terephthalic

Acid(PX-PTA) within the

existing Refinery Complex

Ongoing Applied now

CRZ Clearances

8 11-86/2011-IA.III

CRZ for laying Storm Water

outfall pipelines to sea for

Paradip Refinery Project

21-02-2012 Commissioned

9 11-30/2015-IA.IIICRZ for Pet Coke Evacuation

Unit11-02-2016 Commissioned

*Note :The project was deferred as withdrawl of tax incentives from Govt. Orissa and

viability of the project affected.

Later on the capacity is revised to 15 MMTPA for improving economic viability after

agreement with Govt. of Orissa on tax incentives. Accordingly, DFR is prepared for with

revised project details and EC obtained in 2007.

EIA Report

30 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

The proposed project warrants CRZ clearance for the pipeline transfer from south part

to north part of the refinery. Also the recommendation from OCZMA vide.,

F.No.OCZMA/37/2021143/OCZMA dt.10.05.2021 . The recommendation is attached as

Annexure 33.

1.2 Purpose of the EIA report

The Government of India, Ministry of Environment Forest and Climate Change

(MoEF&CC), New Delhi, vide notification no. S. O. 1533 dated 14th September, 2006, and

its amendments, has made it mandatory to obtain ‘Prior Environmental Clearance (EC) ’ for

New projects listed in the schedule, Expansion and Modernization of existing projects listed

in the schedule, any change in product mix in the existing manufacturing unit falling within

the schedule to that notification from MoEF&CC (for Category A projects) or from SEIAA

(for Category B projects).

The EIA submission at MoEF&CC pertains to Proposed “Integrated Para-Xylene &

Purified Terephthalic Acid (PX-PTA) Project within the existing Refinery Complex,

Odisha. The Project falls under Schedule 5 (c) - “Petro-chemical complexes (industries based

on processing of petroleum fractions & natural gas and/or reforming to aromatics” Category

A, since all the projects under this schedule falls under “A” category as per EIA Notification

2006 and its subsequent amendments.

1.3 Brief description of the Project

Nature:M/s. IOCL, Paradip Refinery and Petrochemical Complex as a part of the compliance

to the regulatory requirement i.e., to obtain Environmental Clearance from MoEF& CC has

appointed M/s. Hubert Enviro Care Systems Private Limited, as EIA Consultant who is

accredited by National Accreditation Board for Education and Training (NABET)- Quality

Council of India (QCI), New Delhi for Schedule 5(c) - “Petro-chemical complexes (industries

based on processing of petroleum fractions & natural gas and/or reforming to aromatics”

Category A.

Size:

The 15.0 MMTPA Paradip Refinery Project (PDRP) has commissioned in Fuel- Refinery

mode. The original configuration of PDRP included production of Petrochemical products,

viz. Polypropylene (PP), Paraxylene (PX) and Styrene Monomer (SM) based on Refinery

streams, in addition to fuel products. Considering the encouraging demand growth of Purified

Terephthalic Acid (PTA), IOCL planned to install Integrated Paraxylene (PX) Units of 0.8

EIA Report

31 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

MMTPA and PTA Units of 1.2 MMTPA capacity at Paradip and associated utilities and

offsite facilities at Paradip Refinery.

Location:

The existing complex is located at Abhaychandrapur village, Jagatsinghpur District, Odisha

State. The site is located 3.6 Km from Paradip city towards NNE.

Importance to the Country & Region:

Eastern India does not have any economic size of PSF, PFY or PET resin plants. The first

PTA plant at IOCL Paradip can provide steady supply of feedstock PTA to PSF, PYF and

PET resin plants. The polyester resins/chips will further have processed to produce audio/

video tapes, x-ray films, photographic films, tapes, aseptic bottles for packing mineral water,

carbonated drinks, vegetable oil, cosmetics, toiletries, tea, coffee etc. Thus using PTA from

Paradip refinery plant at Odisha, a number of secondary and tertiary downstream industries

could be set-up by entrepreneurs who could bring large investment to the state of Odisha and

to Eastern India as a whole. This in turn would also help in generating larger employment

potential in the region.

1.4 EIA cost

EIA & CRZ study was undertaken by HECS for an amount of Rs.53,00,000 Lakhs (Inclusive

of GST).

1.5 Scope of the study & Methodology adopted

EIA is the process of identifying, predicting, evaluating and mitigating the biophysical, social

and other relevant effects of development proposals prior to major decisions being taken and

commitments made. These studies integrate the environmental concerns of developmental

activities into the process of decision – making.

An Environmental Impact Assessment (EIA) is an assessment of the possible impact, whether

positive or negative, that a proposed project may have on the environment, together

consisting of the natural, social and economic aspects, i.e., aiming at “Sustainable

Development” due to the project activities.

EIA Report

32 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

1.5.1 Objectives of the EIA Report

To ensure environmental considerations are explicitly addressed and incorporated into

development and decision-making process.

To anticipate and avoid, minimize or offset the adverse significant biophysical, social

and other relevant effects of the above project proposal.

To protect the productivity and capacity of natural systems and the ecological

processes which maintain their respective functions.

To promote development that is sustainable and optimizes resource use as well as

management opportunities.

To fully recognize the scope and requirements of the Terms of Reference and comply

it.

1.5.2 Scope of Work

The scope of the work mentioned includes an assessment study of proposed refinery unit and

their impact on the region. This study puts forward the most effective ways to protect the

environment form increasing pollution caused by the burgeoning industrial development and

recommendations for environmental-friendly development initiatives in the region.

An Environmental Impact Assessment (EIA) is an assessment of the possible impact, whether

positive or negative, that a proposed project may have on the environment, together

consisting of the natural, social and economic aspects, i.e., aiming at “Sustainable

Development” due to the project activities.

This EIA report presents the existing baseline scenario and the assessment and evaluation of

the environmental impacts that may rise during the construction and operational phases of the

project. This report also highlights the Environmental Monitoring Program during the

construction and operation phases of the project and the post-project monitoring program. In

terms of the EIA Notification of the MoEF&CC dated 14th September 2006 and subsequent

amendments the generic structure of the EIA document will be as under:

Chapter 1: Introduction

Introductory information is present in this Chapter. The introduction chapter provides

background to the project, project proponent and describes the objective of this document.

The purpose and organization of the report is present in this chapter.

Chapter 2: Project Description

EIA Report

33 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

This Chapter includes Project Description and Infrastructure Facilities delineating all the

industrial and environmental aspect of the industry of Paradip Refinery expansion project as

well as process details of proposed products.

Chapter 3: Description of the Environment

This Chapter provides baseline environmental status of Environmental Components (Primary

data) delineating meteorological details of the project site and surrounding area.

Chapter 4: Anticipated Environmental Impacts & Mitigation Measures

This Chapter presents the analysis of impacts on the environmental and social aspects of the

project as a result of establishment of plan and thereby suggesting the mitigation measures.

Chapter 5: Analysis of Alternatives (Technology and Sites)

This chapter includes the justification for the selection of the project site from Environmental

point of view as well as from economic point of view.

Chapter 6: Environmental Monitoring Program

This chapter will include the technical aspects of monitoring, the effectiveness of mitigation

measures which will include the measurement methodologies, frequency, location, data

analysis, reporting schedules etc.

Chapter 7: Additional Studies

This chapter will detail about the Public Consultation sought regarding the project. It will

also identify the risks of the Project in relation to the public and the surrounding environment

during construction and operation phases of the plant and thereby presents Disaster

Management Plan, Social impact assessment and R&R action plans.

Chapter 8: Project Benefits

This chapter deals with improvement in physical and social infrastructures, employment

potential and other tangible benefits.

Chapter 9: Environmental Cost Benefit Analysis

This chapter summarizes the cost benefit analysis if it is available in scoping stage.

Chapter 10: Environmental Management Plan

This is the key Chapter of the report and presents the mitigation plan, covers the institutional

and monitoring requirements to implement environmental mitigation measures and to assess

their adequacy during project implementation.

EIA Report

34 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Chapter 11: Summary and Conclusion

This chapter summarizes the information given in Chapters in this EIA/EMP report and the

conclusion based on the environmental study, impact identification, mitigation measures and

the environmental management plan.

Chapter 12: Disclosure of the Consultant

Names of consultants engaged in the preparation of the EIA/EMP report along with their

brief resume and nature of Consultancy rendered are included in this Chapter.

1.5.3 EIA Process

The EIA process followed for this EIA report is composed of the following stages:

1. Study of project information

2. Screening & Scoping environmental pre-feasibility study & application for approval

of ToR

3. Collection of detailed project management plan/report

4. Baseline data collection

5. Impact identification, Prediction & Evaluation

6. Mitigation measures & delineation of EMP

7. Risk assessment and safety & disaster management plan

8. Review & finalization of EIA Report based on the ToR requirements.

9. Public consultation

10. Submission of Final EIA report for implementation of mitigation measures & EMP

as well as necessary clearances from relevant Authority

The EIA Cycle based on the above stages has been illustrated as per the ToR dated 30th Sept

2018, in Figure 1.1.

EIA Report

35 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 1-1 EIA Process

1.6 Objectives of the Study

The major objective of this study is to prepare a detailed Environmental Impact Assessment

Study within the study area i.e. 10 km radius from the project.

EIA Report

36 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

1.7 Applicable Regulatory Framework

The following are some of the acts and rules related to environment that are applicable for the

proposed project:

1. EIA Notification 2006 and its amendments

2. Manufacture Storage and Import of Hazardous Chemicals Rules,1989 and its

amendments

3. Water (Prevention and Control of Pollution) Act,1974 and its amendments

4. Air (Prevention and Control of Pollution) Act,1981 and its amendments

5. Hazardous Waste (Management, Handling and Transboundary movement)

Rules,2008 and its amendments

6. Public Liability InsuranceAct,1991 and its amendments

7. Environmental (Protection)Rules,1986 and its amendments

8. The Noise Pollution (Regulation and control) rules, 2000

9. Factories Rules 1950 and its amendments

10. Petroleum Act, 1934

11. Explosive Act,1884

12. Central Motor Vehicle Act, 1988

The details of applicable Acts and Rules and the applicability to the project is given in Table

1-2

EIA Report

37 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 1-2Applicable Acts and Rules for the proposed Refinery project

S.

No

Act and Rules

applicable Purpose Objective Applicability

1. EIA Notification

2006 and its

amendments

New projects,

Expansion

modernization,

change of product

mix of the existing

project

Protection and

Improvement of

the Environment

As the proposal is for

compliance to

petrochemical

manufacturing,

Environmental

clearance from

Ministry of

Environment, Forest

and Climate Change

(MoEF&CC) is

applicable

2. The Manufacture,

Storage and

Import of

Hazardous

Chemicals Rules,

1989 and its

amendments

Handling of

Hazardous

Chemicals

Regulate the

manufacture,

storage and

import of

Hazardous

Chemicals

Preparation/ update of

On-site Emergency

Preparedness Plan and

submission to Factory

inspectorate

Preparation/ update of

Safety Report and

submit to Factory

inspectorate.

Preparation of Material

Safety Data Sheet

3. The Water

(Prevention and

Control of

Pollution) Act,

1974 and its

amendments

New projects,

Expansion

modernization,

change of product

mix of the existing

project, Existing

plants

Prevention,

control and

abatement of

water pollution

Consent to Establish

and Consent to

Operate from State

Pollution Control

Board to be obtained

for expansion

EIA Report

38 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

No

Act and Rules

applicable Purpose Objective Applicability

4. The Air

(Prevention and

Control of

Pollution) Act,

1981 and its

amendments

New projects,

Expansion

/modernization,

change of product

mix of the existing

project, Existing

industries

Prevention,

control and

abatement of air

pollution

Consent to Establish

and Consent to

Operate from State

Pollution Control

Board to be obtained

for expansion

5. The Hazardous

and other wastes

(Management,

Handling and

Transboundary

Movement Rules)

2016 and Solid

Waste

Management

Rules 2016

Management,

Handling and

Transboundary

Movement of

Hazardous waste

Prevention,

Control and

abatement of

pollution

Hazardous waste

Authorization from

State Pollution Control

Board to be obtained

for expansion

6. The

Environmental

(Protection)Rules,

1986 and its

Amendments

New projects,

Expansion/moderni

zation change of

product mix of the

existing project,

Existing industries

Protection and

Improvement of

the Environment

Environmental

Standards as specified

are to be complied.

Submission of

Environment

Statement on yearly

basis to PCB

7. The Noise

Pollution

(Regulation and

Control) Rules,

2000

New projects,

Expansion/moderni

zation change of

product mix of the

existing project,

Existing industries

To protect the

workers and

public from

noise related

problems

Noise control measure

Comply with Noise

standards and

submission of monthly

report to PCB

EIA Report

39 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

No

Act and Rules

applicable Purpose Objective Applicability

8. The Public

Liability

Insurance Act,

1991 and its

amendments

Transportation of

Hazardous

Substance

To provide

immediate relief

to persons

affected by

accident

involving

hazardous

substances and

also for

Establishing an

Environmental

Relief fund

Provision of Liability

Insurance Policy

9. Factories Rules

1950 and its

amendments

New projects,

Expansion/moderni

zation change of

product mix of the

existing project,

Existing industries.

Control of

workplace

environment,

and providing

for good health

and safety of

workers

Factory License from

Factory inspectorate

10. The Petroleum

Act, 1934

New projects,

Expansion/moderni

zation change of

product mix of the

existing project,

Existing industries

Production,

Storage and

import of

petroleum and

provides the

regulations for

the safety and

environmental

measures

License to be acquired

for storage and

adequate safety

measures are in place.

EIA Report

40 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

No

Act and Rules

applicable Purpose Objective Applicability

11. The Explosive

Act, 1884

New projects,

Expansion/moderni

zation change of

product mix of the

existing project,

Existing industries

Production,

Storage and

import of

explosive

substance in and

around the

project and

provides the

regulations for

the safety and

environmental

measures

Safety measures are to

be complied for the

storage of chemicals in

the plant as per PESO

guidelines.

12. The Central

Motor Vehicle

Act, 1988

New projects,

Expansion/moderni

zation change of

product mix of the

existing project,

Existing industries

Check the

pollution load of

vehicles inside

the plant

Adequate

environmental

measures are put in

place to check the

vehicular emissions.

EIA Report

41 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

1.8 ToR Compliance

S. No

Terms of Reference Compliance

STANDARD TERMS OF REFERENCE FOR CONDUCTING ENVIRONMENT IMPACT ASSESSMENT STUDY FOR PETRO- CHEMICAL COMPLEXES (INDUSTRIES BASED ON PROCESSING OF PETROLEUM FRACTIONS &NATURAL GAS AND/OR REFORMING TO AROMATICS) AND INFORMATION TO BE INCLUDED IN EIA/EMP REPORT

Standard TOR 1 Executive Summary Brief executive summary is provided as a Separate booklet which is enclosed as Annexure 30

2 Introductioni. Details of the EIA Consultant

including NABET accreditation M/s. Hubert Enviro Care Systems (P) Ltd., Chennai

NABET Accredited Number: NABET/EIA/1922/RA 0172 Valid up to 13/10/2022

ii. Information about the Project Proponent

M/s. INDIAN OIL CORPORATION LIMITED,

IOCL Paradip Refinery, Survey no: 218, Abhaychandrapur village, Jhimani P.O., Kujang Taluk, Jagatsinghpur Dist.,

Paradip, Odisha -754141

iii. Importance and Benefits of the Project

Importance of the project: 1. The project is of national importance and will reduce import dependence to the tune of 1.2 million MT per year

PTA product through domestic production and reduction in foreign exchange outgo. 2. The project of Indian Oil is one of significant projects under the Govt. of India’s “Make in India” Initiative for the

Manufacturing Sector. 3. The proposed project is to meet the market potential having a deficit of about 2.2 MMTPA PTA in India by 2024. 4. An important project under the Petroleum Chemicals and Petrochemicals Investment Region (PCPIR) in Odisha

and spur industrial investment and development of the region. 5. Expand Petrochemical Production footprint of Indian Oil, Paradip Refinery in Odisha. 6. The PTA plant project along with under construction MEG Plant at Paradip, will accelerate the development of

Textile Industry in the Eastern Region of India. Leading to additional employment opportunities.

Benefits of the project: 1. The project will propel industrial development, downstream industry revolution in Odisha and eastern regions of

India, which will support consequential development of entrepreneurship, MSMEs in nearby locality and state of Odisha.

2. The project will help India in attaining Self Sufficiency in PTA product demand as feedstock for industries in value addition chain of products like Polyester fiber, Yarn, Textiles, PET polymer production.

3. Employment opportunities about 5000 people directly /indirectly during construction period and about 200 persons

EIA Report

42 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

during Operating period. 4. The project will spur further investments in the downstream industries, Textile Industries and provide better socio-

economic benefits, direct and indirect employment opportunities. 3 Project Description

i. Cost of project and Time of completion The cost of the project is Rs.11783 Crores.

Time of completion: Expected by December, 2024.

ii. Products with capacities for the proposed project

S.No. Name of the UnitProposed Capacity

(MMTPA)

1 Para Xylene (PX) 0.8

2 Purified Terepthalic Acid (PTA) 1.2

iii. If expansion project, details of existing products with capacities and whether adequate land is available for expansion, reference of earlier EC if any.

S.No. Streams Quantity – TMT/Year EC Details

Existing Proposed

Refinery Products

1 Naphtha Exports 0 --

J-11011/344/2016-IA-II(I) dated

11thOct 2018

Under Construction

2 BS-IV MS 0 --

3 BS-VI MS 3260 --

4 Reformate 96 --

5 SKO 312 --

6 ATF Domestic 463 --

7 BS-IV HSD 0 --

8 BS-VI HSD 6017 --

9 Sulphur 350 --

10 PetCoke 1253 --

11 LPG 932 --

12 Poly-Propylene 678 --

13 Fuel & Loss 1641 --

Petro-chemical Products

EIA Report

43 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

14 Mono-Ethylene Glycol

(MEG) 332 KTA --

J-11011/344/2016-IA-II(I) dated

11thOct 2018

Under Construction

15 Para Xylene 0 800600TPA Feed to PTA as a Raw material

16 Purified Terepthalic Acid

(PTA) 0 1200000TPA Proposed Product

Associated Products

17 Di-ethylene Glycol 24 KTA -- J-11011/344/2016-IA-II(I) dated

11thOct 2018

Under Construction 18 Tri-ethylene Glycol 1 KTA --

19 Toluene 0 50000TPA Proposed Product

No additional land required. The total land area is 3345 Acres. Adequate land is available for expansion & Land document attached as Annexure 1

iv. List of Raw materials and their source with mode of transportation

S. No. Raw

Material Quantity Unit

Source Mode of Transport

1 Reformate 310000 kg/h Internal Pipeline

2 Hydrogen 651 (PX) +31 (PTA) kg/h Internal Pipeline

3 Paraxylene 97200 kg/h Internal Pipeline

Further details are given in Chapter 2, Section 2.7.3 of EIA report v. Other chemicals and materials

required with quantities and storage capacities

S. No. Chemicals/ Catalyst Quantity UnitMode of

Storage Storage Capacity

1. Acetic Acid 4200 kg/h Storage tank 2x 425 m3

2. Hydrogen Bromide 80 kg/h Drums ~ 100 T

3. Sodium Formate 56 kg/h Drums ~ 100 T

4. Sodium Carbonate 1843 kg/h Drums ~ 1000T

5. Conc Caustic Soda flakes 109 kg/h Bags ~ 300 T

6. Hydrogen Peroxide 4.2 kg/h Drums ~ 10 T

EIA Report

44 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

7. Amine 1 kg/h Tank ~ 2T

8. Antifoam 1500 kg Drums ~1.5 T

9. Sulfolane 96630 kg Drums ~ 80 T

10. Monoethanolamine 44 kg Tanker / Drum ~ 0.05 T

11. DimethayDisulfide 257 kg Tanker / Drum ~ 0.3 T

12. Perchloroethylene 930 kg Drum ~ 1 T

13.Liquid Catalyst-

Cobalt/Manganese solution 1597

kg/h Tanker ~ 50 T

14. R-450 PTA Reactor 69.4 m³ Drum ~ 35 T

15. R-820 Catalytic Oxidizer 22.3 m³ Bag / box ~ 20 T

16. R-880 LP Catalytic Oxidizer 0.98 m³ Bag / box ~ 1 T

17. Clay Catalyst – Activated Clay 108 m³ Bag ~ 1200 m3

18. Clay Catalyst – Activated Clay 760 m³ Bag

19. Clay Catalyst – Activated Clay 291 m³ Bag

Details given in Chapter 2, Section 2.7.3.2 Table 2-15 of EIA report

Details of emission, effluents,

hazardous waste generation and

their management

1. Emission:

a. Existing:

S.No Stack details Fuel Type

used

Flue gas Flow

Rate (Nm3/hr)

Emission per stack (g/s)

PM SO2 NOx CO

1 DHDT Gas Fired 31128 0.03 0.13 1.04 0.05

2 Utility Boiler - 3

Gas + Oil

Fired 285793 0.32 0.66 7 0.83

3 Utility Boiler - 4

Gas + Oil

Fired 285793 0.33 1.53 7.21 0.81

EIA Report

45 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4

Gas Turbine – 1- HRSG-

1 Naptha 1062841 0.76 12.64 47.59 2.95

5

HDT Reactor Feed

Heater

Gas + Oil

Fired 15834 0.02 0.1 0.12 0.03

6

Vacuum Charge Heater

of AVU

Gas + Oil

Fired 112108 0.07 5.57 4.21 0.82

7 FCC Regenerator NA 320000 2.69 75.56 0.78 7.52

8 Reformer of HGU Naphtha 175222 0.004 2.02 4.6 1.6

9

Fresh Feed Preheater of

FCC

Gas + Oil

Fired 61013 0.05 4.63 0.49 0.67

10 CCR Gas Fired 523959 0.06 1.43 3.5 5.2

11

MHC 1st Train Reactor

Feed Heater of VGO-

HDT Gas Fired 64717 0.07 0.36 0.37 0.32

12

Atmospheric Distillation

Heater of VGO-HDT Gas Fired 15834 0.01 0.01 0.15 0.03

13 Gas Turbine – 2-HRSG-2 Naptha 1062841 0.84 9.03 42.68 5.47

14

Gas Turbine – 3- HRSG-

3 Naptha 1062841 0.87 4.28 55.38 3.65

15 Coker Heater - Stack-1

Gas + Oil

Fired 78412 0.04 0.34 0.87 0.1

16 AVU-CDU Gas Fired 201847 0.1 7.06 3.81 1.34

EIA Report

46 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

17 Coker Heater - Stack-2

Gas + Oil

Fired 78412 0.16 3.52 1.54 0.4

18 SRU Acid gas 106499 0.02 12.64 1.07 2.38

19 Charge Heater of NHDT Gas Fired 48778 0.02 0.09 0.62 0.15

20 Utility Boiler - 1

Gas + Oil

Fired 285793 0.42 11.09 10.51 1.82

21 Utility Boiler - 2

Gas + Oil

Fired 285793 0.29 17.78 5.29 2.2

Total (g/s) 7.18 170.48 198.8 38.35

b. Proposed:

Point source Emission:

S.No Stack details

Fuel Rate

(Natural

Gas) (kg/hr)

Flue gas

Flow Rate

(Nm3/hr)

Emission per stack (g/s)

PM SO2 NOx CO CO2

Tatory

Furnace 433 4679 - 0.0257 0.1688 - 451.53

ISOMAR

Furnace 2747 29708 - 0.0833 0.6052 - 1402.36

XFU 1 7594 82116 - 0.5597 2.7983 - 9553.61

XFU 2 4840 52339 - 0.4396 2.1955 - 7495.03

EIA Report

47 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Utility Boiler

– 5

(Standby)*

19973 325061 0.4528 4.5139 22.575 1.6931 -

Flare 15 162 0.0002 0.0023 0.0113 0.0008 -

Total (g/s) 0.453 5.6245 28.3541 1.6939 18902.53

Note:

The data is obtained from Section 7.1.2.1 of Detailed Feasibility Report prepared by Toyo Engineering India Pvt. Ltd. and

integration of flow rate of fuel.

Utility Boiler -5 is standby and will be in intermittent operation only for the PTA plant start up

Line Source Emission:

S.No

Vehicle type

No.of.Vehicle per day (Based on maximum operation capacity) based on BS-VI type of

vehicles

Emission (g/s)

PM NOX CO

1 4W 5 0.000004 0.000104 0.000617 2 HW 1-PTA 164 0.000137 0.006287 0.054667

3 HW 2-

Toluene 7 0.000010 0.000447 0.003889

Total (g/s) 0.000150 0.006838 0.059172

Cumulative Emission:

Pollutant

Max. Base

line Conc.

(µg/m3)

Estimated Incremental

Conc. (µg/m3) Total Conc. (µg/m3)

NAAQ

standard

(µg/m3)

% increase

PM 95.7 0.10 95.8 100 0.10

EIA Report

48 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

SO2 15.7 1.16 16.86 80 7.39

NOx 30.06 5.89 35.95 80 19.59

CO 50 78.69 128.69 4000 157.38

CO2 - 8099.82 8099.82 - -

Other emissions:

Storage Vents & process vent Emission:

PX Vents:

S.No Storage Tank Vent details Emission per vent (g/s)

VOC Benzene Toluene CO2

1 Toluene day tank- 045-TK-001A 0.078125 - - -

2 Toluene day tank- 045-TK-001B 0.078125 - - -

3 Plant inventory tank- 044-TK-001 - 0.0167 0.00755 -

4 Paraxylene day tank- 049-TK-001 A 0.220486 - - -

5 Paraxylene day tank- 049-TK-001 B 0.220486 - - -

6 Desorbent storage tanks-049-TK-002 0.451389 - - -

7 Plant inventory storage tanks- 049-TK-003 0.451389 - - -

8 Aromatic tank-048-TK-001 1.006944 - - -

9 Light reformate storage tank-048-TK-002 1.145833 - - -

EIA Report

49 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

10 Isomer Regeneration Vent - - - 97.222

PTA Vents

S.N

o

Process

& Silo

Vent

details

Flue

gas

Flow

Rate

(Nm3/

hr)

Emission (g/s)

Benze

ne

Tolue

ne

Xyle

ne

Acet

ic

Acid

Metha

nol

Meth

yl

aceta

te

Bromi

ne

Methy

l

bromi

de

Carbo

n

monox

ide

PT

A

Dus

t

Nitrog

en

1.

G1-

Process

Inert

Vents-

051-C-

175

29200

0 0.3 0.487 0.73

0.16

2 0.406 6.489 0.406 0.73 3.244 0 -

2.

G2/G3/

G4-

PTA

Day silo

A/B

Off-

Spec

PTA

Silo-

051-M-

600A/B

/C

13400 0.004 0.005 0.006 0.00

1 0.003 0.051 0.004 0.009 0.051

0.02

5 -

13400 0.004 0.005 0.006 0.00

1 0.003 0.051 0.004 0.009 0.051

0.02

5 -

13400 0.004 0.005 0.006 0.00

1 0.003 0.051 0.004 0.009 0.051

0.02

5 -

3.

PSV

Vent

Scrubbe

r Stack

55 - - - - - - - - - - 19.16

67

EIA Report

50 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Total (g/s) 0.312 0.502 0.748 0.16

5 0.415 6.642 0.418 0.757 3.397

0.07

5

19.166

7

Further details on emissions & sources are provided in chapter 4, Section 4.5 of EIA report

2. Effluents details:

a. Existing:

S. No Description

Existing (m3/hr)

Total

Water

Fresh

Water

ETP

Treated

Water

Used

Conden

sate

Used

Use of

outlet Outlet

Effluent

/

Sewage

Generat

ed

Loss

(a+b) (a) (b)

1

Cooling

tower 1482 1482 0 0 0 0 323 1159

2

DM Water

Makeup 1334.8 586.8 748 0 0 0 175 0

3

Service

Water 465.2 465.2 0 0 0 372.16 0 93.1

4

Refinery

unit 0 0 0 0 372.16 0 372.16 0

5

PX-PTA

unit 0 0 0 0 0 0 0 0

6 Project 100 100 0 0 0 0 80 20

EIA Report

51 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

7 Others 5 5 0 0 0 0 4 1

8 Domestic 110 110 0 0 0 0 88 22

9 Boiler 0 0 0 1119.8 0 0 40 0

Total 3497 2749 748 1119.8 372.16 372.16 1082.2 1295.1

b. Proposed:

S. No Description

Proposed (m3/hr)

Total

Water

Fresh

Water

ETP

Treated

Water

Used

Condens

ate Used

Use of

outlet Outlet

Effluent/

Sewage

Generat

ed

Loss

(a+b) (a) (b)

1

Cooling

tower 930.5 911 19.5 0 0 0 213.6 716.9

2

DM Water

Makeup 286 0 286 0 0 0 21.2 0

3

Service

Water 60 60 0 0 0 48 145.5 12

4 Refinery unit 0 0 0 0 0 0 0 0

5 PX-PTA unit 0 0 0 0 48 0 145.5* 0

6 Project 0 0 0 0 0 0 0 0

7 Others 20 20 0 0 0 0 16 4

EIA Report

52 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

8 Domestic 3 3 0 0 0 0 2.4 0.6

9 Boiler 0 0 0 264.8 0 0 9.3 0

Total 1299.5 994 305.5 264.8 48 48 408 733.5

3. Hazardous waste materials will be properly disposed as per the Hazardous Wastes (Management, Handling and

Transboundary Movement) Rules 2016;

Hazardous waste authorization has been made with SPCB, Odisha- IND-IV-HW-930/5028 dated 24.05.2019 valid till

31.03.2024 is enclosed as Annexure-14.

a.Existing Hazardous waste

S.No

.

Details of

Waste

Scheduled as

per HWM

rules

Existing

Quantity

TPY

Approved

Quantity TPY Frequency of

disposal Storage and Disposal

1 Spent

catalyst Schedule-I 4.2 2484.4 2500 Within 90 days

Stored in intermediate

storage facility (covered

warehouse with impervious

floor and shed)

Disposal in SLF -1497.4 /

Co-processing in cement

industry - 987

2 Spent Clay Schedule-I 4.5 145.5 720 Within 90 days Directly sent to SLF

3 Ash Schedule-I 36.0 - Within 90 days Directly sent to SLF

EIA Report

53 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

37.2

4 Oily Sludge Schedule-I 4.1 1456.1

2748 (Oil

sludge/

Emulsion/

Slop Oil)

Within 90 days Directly sent to DCU for

processing

5 Oily Sludge Schedule-I 4.1 74.2 Within 90 days

Stored in impervious

metallic containers before

unloading in melting pit for

oil recovery

Sludge is disposed in HW

incinerator

6 Coke Schedule-I 4.4 16.7 180

Within 90 days Sent to incinerator for

disposal

b.Proposed Hazardous waste

S.No. Details of Waste Scheduled as per HWM rules

Proposed Quantity TPD

Frequency of disposal

Storage and Disposal

PX

1 Spent Clay from Clay Treaters

Schedule-I 4.5 0.12 Within 90 days Captive SLF

2 Spent Catalyst from Reactor

Schedule-I 1.6 0.01 Within 90 days Metals Recovery or Landfill in Captive SLF

3 Spent Clay from Clay Treater

Schedule-I 4.5 1.44 Within 90 days Captive SLF

4 Spent Adsorbent from Adsorbent Chambers

Schedule-I 1.6 0.24 Within 90 days Captive SLF

5 Catalyst from Reactor Schedule-I 1.6 0.04 Within 90 days Metal recovery by authorized recycler

6 Spent Clay fromClay Treater

Schedule-I 4.5 0.26 Within 90 days Captive SLF

EIA Report

54 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

PTA

7 PTA Spent Catalyst Schedule-I 1.6 0.0438 Within 90 days Recovery by catalyst manufacturer

8 Filters, Oils Schedule-I 3.3/5.1

0.0685 Within 90 days Disposal in authorized HW incinerator / Sale to authorized users

9 Pails, Corrosion, Paint Schedule-I 21.1 0.0137 Within 90 days Sale to authorized users

10 Laboratory Solvents Schedule-I 20.2 0.0003 Within 90 days Disposal in ETP

11 Waste Solvents Schedule-I 20.2 0.0110 Within 90 days Disposal in ETP

vi. Requirement of water, power, with source of supply, status of approval, water balance diagram, man-power requirement (regular and contract)

a. Requirement of water

S. No. Water Source Required Quantity (m3/hr)

Extraction Approval Existing Proposed After Expansion

1 Mahanadi

River 2749 994 3743

Government of Odisha has approved

3950m3/hr which is issued by

Government of Odisha & valid upto:

Oct 2021 is attached as Annexure7

EIA Report

55 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

b.Water balance diagram

Water Balance Diagrams of Existing Refinery

EIA Report

56 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Water Balance Diagram of Proposed facility

EIA Report

57 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Water Balance Diagram for after expansion of Refinery

The Water Balance diagram is given in Chapter 2, Figure 2-23.

EIA Report

58 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

c. Requirement of power

S. No.

Power Source Required Quantity Extraction Approval Existing Proposed After Expansion

1 Existing Gas Turbine 240.5 MWh (190.5+50) 30.5 MWh

271 MWh Internally

d. Requirement of manpower

Operation Phase:

S. No Description Regular Contractual Total

1 Existing (Nos) 975 547 1522

2 Proposed (Nos) 200 200 400

3 After Expansion (Nos) 1175 747 1922

Construction phase : 5421 Nos.

vii.Process description along with major equipment’s and machineries, process flow sheet (quantitative) from raw material to products to be provided

a.Process descriptionFeed for the proposed PX-PTA plant will be Reformate, which is produced by processing Naphtha in CCRU. Reformate will be processed in the PX plant to produce PX, toluene & other products, which will further be processed in the PTA plant for production of PTA Detailed process description in given in Chapter 2, Section 2.7.4.1 of EIA report

b.Major equipment and machineries for PX:

S. No.

Equipment Tag No. Equipment Description

Sulfolane Process Unit (Extractive Distillation) 1 044-C-001 Extractive Distillation Column 2 044-C-002 Recovery Column

Benzene-Toluene Fractionation Unit (Unit-045) 1 045-C-001 Benzene-Toluene Column No 1 2 045-C-002 Benzene-Toluene Column No 2

Tatoray Process Unit (Unit-046) 1 046-F-001 Charge Heater

EIA Report

59 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2 046-R-001 Reactor 3 046-K-001 Recycle Gas Compressor

Xylenes Fractionation Unit (Unit -048) 1 048-F-001 Raffinate Column No 2 Reboiler Heater 2 048-F-002A/B Xylene Column No 2 Reboiler Heaters 3 048-C-002 Xylene Column No 1 4 048-C-003 Xylene Column No 2

Parex Process Unit (Unit-049) 1 049-C-001 Raffinate Column No 1 2 049-C-002 Raffinate Column No 2 3 049-V-001 Adsorbent Chamber No 1 4 049-V-002 Adsorbent Chamber No 2

Isomar Process Unit(Unit-050) 1 050-F-001 Charge Heater 2 050-C-001 Deheptanizer 3 050-C-002 Stabilizer 4 050-R-001 Reactor 5 050-K-001 Recycle Gas Compressor

c.Major equipments and machineries for PTA:S. No. Equipment Tag No. Equipment Description

1 051-A-220 Oxidation Reactor Agitator 2 051-A-310 1st PTA Crystallizer Agitator 3 051-A-320 2nd PTA Crystallizer Agitator 4 051-A-330 3rd PTA Crystallizer Ag 5 051-K-151 Off-Gas Expander 6 051-K-901 Steam Turbine 7 051-R-220 Oxidation Reactor 8 051-R-450 PTA Reactor 9 051-R-820 Catalytic Oxidizer

10 051-R-880 LP Catalytic Oxidizer 11 051-T-600 A/B PTA Day Silos

The process flow diagram of PX and PTA is given in Chapter 2, Figure 2-8

EIA Report

60 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

d.Process flow diagram of PX

EIA Report

61 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

e.Process flow diagram of PTA

viii. Hazard identification and details of proposed safety systems

Further details of proposed safety systems are detailed in Chapter 7, Section 7.2 of EIA report & Rapid Risk Assessment is attached as Annexure 10.

EIA Report

62 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

1.Identification of Hazardous Areas

The procedure for RRA starts with identification of major risk areas are as follows: Toxic chemical storage area Process Plant involving hazardous chemicals

The Major Hazards will be as described below Possibility of injury during chemicals handled, during operations and due to intoxication. Possibilities of fire hazards at transformers, switchgear and other electrical equipment etc.

2.Hazard Identification – Paraxylene

HEALTH ENVIRONMENTAL PHYSICALAcute Toxicity –Inhalation : Category 4 Acute Toxicity -Oral– Category 4 Skin Irritation Category: 2

Aquatic Toxicity : Category- 2 Flammable : Category 3 flammable

STUDY/

HAZARD

STATEMENT

CATEGORY 1 CATEGORY2 CATEGORY3 CATEGORY4 CATEGORY5

AcuteOral <5mg/kg >5 <50mg/kg >50<300mg/kg >300<2000 >2000<

LD50 Fatalifswallowed Fatalifswallowed Toxic ifswallowed mg/kg 5000mg/kg

Harmfulif May beharmful

swallowed ifswallowed

Acute Dermal < 50 mg/kg > 50 < 200 mg/kg > 200 < 1000 > 1000 < 2000 > 2000 < 5000

LD50 Fatal in contact with Fatal in contact mg/kg mg/kg mg/kg May be

skin with skin Toxic in contact

with skin

Harmful in contact

with skin

harmful in contact

with skin

Acute See footnote

Inhalation below this table

Dust LC50 < 0.05 mg/L > 0.05 < 0.5 mg/L > 0.5 < 1.0 mg/L > 1.0 < 5 mg/L

Gases LC50 < 100 ppm/V > 100 < 500 ppm/V > 500 < 2500 >2500 < 20000

Vapours LC50 <0.5 mg/L >0.5 < 2.0 mg/L ppm/V ppm/V

EIA Report

63 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Fatal if inhaled Fatal if inhaled > 2.0 < 10 mg/L > 10 < 20 mg/L

Toxic if inhaled Harmful if inhaled

Flammable

liquids

Flash point < 23

degrees C and initial

Flash point < 23

degrees C and

Flash point > 23

degrees C< 60

Flash point > 60

degrees C < 93

Not Applicable

boiling point < 35 initial boiling point degrees C. degrees C.

degrees C. Extremely

flammable liquid

and vapour

> 35 degrees C.

Highly flammable

liquid and vapour

Flammable liquid

and vapour

Combustible liquid

STUDY/ HAZARD

STATEMENT

CATEGORY 1 CATEGORY 2 CATEGORY 3

Eye Irritation Effects on the cornea, iris or conjunctiva that are not expected to reverse or that have not fully reversed within 21 days. Causes severe eye damage.

2A: Effects on the cornea, iris or conjunctiva that fully reverse within 21 days. Causes severe eye irritation. 2B : Effects on the cornea, iris or conjunctiva that fully reverse within 7 days. Causes eye irritation.

Not applicable

Skin Irritation Destruction of skin tissue, with sub categorization based on exposure of up to 3 minutes (A), 1 hour (B), or 4 hours (C). Causes severe skin burns and eye damage.

Mean value of >2.3 > 4.0 for erythema / eschar or edema in at least 2 of 3 tested animals from gradings at 24, 48, and 72 hours (or on 3 consecutive days after onset if reactions are delayed); inflammation that persists to end of the(normally 14-day) observation period. Causes skin irritation.

Mean value of >1.5 < 2.3 for erythema / eschar or edema in at least 2 of 3 tested animals from gradings at 24, 48, and 72 hours (or on 3 consecutive days after onsetif reactions are delayed). Causes mild skin irritation.

Environment: Acute Toxicity Category

96 hr LC50 (fish) <1 mg/L 48 hr EC50 (crustacea) < 1 mg/L, 72/96 hr ErC50 (aquatic plants) < 1 mg/L Very toxic to aquatic life

96 hr LC50 (fish) >1< 10 mg/L 48 hr EC50 (crustacea) >1< 10 mg/L 72/96 hr ErC50 (aquatic plants) >1< 10 mg/L Toxic to aquatic life

96 hr LC50 (fish) >10< 100 mg/L 48 hr EC50 (crustacea) >10< 100 mg/L 72/96 hr ErC50 (aquatic plants) >10< 100 mg/L Harmful to aquatic life

Flammable Aerosol

Extremely flammable aerosol Flammable aerosol Not Applicable

EIA Report

64 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Flammable solidsUsing the burning rate test, substances or mixtures other than metal powders: (a) wetted zone does not stop fire and (b) burning time < 45 seconds or burning rate > 2.2 mm/secondUsing the burning rate test, metal powders that have burning time < 5 minutes Flammable solid

Using the burning rate test, substances or mixtures other than metal powders:(a) wetted zone does not stop fire for at least 4 minutes and (b) burning time < 45 seconds or burning rate > 2.2 mm/second Using the burning rate test, metal powders that have burning time > 5 < 10 minutes Flammable solid

Not Applicable

Flammable gases Gases, which at 20 degrees C and a standard pressure of 101.3 kPA: are ignitable when in a mixture of 13% or less by volume in air; or have a flammable range with air of at least 12 percentage points regardless of the lower flammable limit. Extremely flammable gas

Gases, other than those of category 1, which, at 20 degrees C and a standard pressure of 101.3 kPA, have a flammable range while mixed in air. Flammable gas

Not Applicable

Hazard Ratings

NFPA HAZARD CODES RATING SYSTEM Health : 2 0 – No Hazard

Flammability : 3 1 – Slight Hazard Reactivity : 0 2 – Moderate Hazard

3 – Serious Hazard 4 – Severe Hazard

SKINCONTACT SKINABSORPTION EYECONTACT INHALATION INGESTION

Yes Yes Yes Yes Yes

3.Hazard Identification – Purified Terephthalic Acid

Terephthalic Acid is a sand-like white powder. It is used as a reagent to neutralize alkali in wool, as an additive to

poultry feeds, and to increase the effectiveness of certain antibiotics.

EIA Report

65 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

The following acute (short-term) health effects may occur immediately or shortly after exposure to Terephthalic Acid:

Contact can irritate the skin and eyes. Breathing Terephthalic Acid can irritate the nose, throat and lungs causing coughing, wheezing and/or

shortness of breath.

Chronic Health Effects Cancer Hazard Repeated exposure to Terephthalic Acid may affect the kidneys.

Improper use of respirators is dangerous

Fire Hazards Terephthalic Acid may burn, but does not readily ignite. Use dry chemical, CO2, water spray, alcohol or polymer foam extinguishers. Poisonous gases are produced in fire.

HAZARDRATING NFPA

Flammability 1

Reactivity 0

HazardRatingKey:0=minimal;1=slight;2=moderate;3=serious; 4=severe

Following are the proposed safety measures in the plant. Emergency isolation valves are to be provided/online monitoring via DCS PLC monitoring that will closely

monitor the process flow and parameters in a safe place and auto mode through gas/fire detector system. Passive fire protection such as fire proofing shall be recommended. Appropriate detection measures such as fire and gas detectors are recommended and the same to be deep-rooted

throughout the plant area. ix. Expansion/ modernization proposals

(a) Copy of all Environmental Clearance(s) including amendments thereto obtaining for the project from MoEF&CC/SEIAA shall be attached as an Annexure. A certified copy of the latest monitoring report of the Regional office of the Ministry

Expansion Note: (In Form 1 in has been mentioned as Modernization based on the interpretation while applying on the form-1)

a.

S. No MoEF&CC File No Units Date of issue Status of

Project

Status of

compliance

1 J-11011/26/97-IA.II(I)EC for Setting up grass root

24.12.1997* Deferred Deferred

EIA Report

66 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

of Environment and Forests as per circular dated 30th May, 2012 on the status of compliance of conditions stipulated in all existing environmental clearances including Amendments shall be provided. In addition, status of compliance of Consent to Operate for the ongoing existing operation of the project from SPCB shall be attached with the EIA-EMP report

(b) In case the existing project has not obtained environmental clearance, reasons for not taking EC under the provisions of the EIA notification 1994 and/or EIA notification 2006 shall be provided. Copies of Consent to Establish / No objection certificate and Consent to Operate (in case of units operating in prior to EIA notification 2006, CTE and CTO of FY 2005-2006) obtained from the SPCB shall be submitted. Further compliance report to the conditions of Consents from the SPCB shall be submitted.

Petroleum Refinery of

9MMTPA

2 J-11011/26/1997-

IA.II(I)

EC for Setting up grass root

Petroleum Refinery of

9MMTPA

28.04.2003* Deferred Deferred

3 J-11011/70/2007-IA.

II(I)

EC for Grass Root Refinery

cum Petrochemical Complex

of 15 MMTPA

06-07-2007 CommissionedPartially

Complied

4 J-11011/395/2012-IA.

II(I)

Extension of validity of

Environmental Clearance

for Grass Root Refinery

cum Petrochemical

Complex of 15 MMTPA

18-09-2014 Commissioned

Partially

Complied-

Same condition

as in EC-2007

5 J-11011/395/2012-IA.

II(I)

EC Ammendment with

Rapid Railway Loading

System (RRLS) for Pet Coke

Evacuation and Minor

revision in Secondary Unit

Capacities

06-01-2015 Commissioned

Partially

Complied-

Same condition

as in EC-2007

6 J-11011/344/2016-IA.

II(I)

EC and CRZ for Ethylene

Recovery Unit, Mono

Glycol Unit & BS VI

facilities

11-10-2018Under

Construction

Partially

Complied

7 J-11011/395/2012-IA

II(I)

EC for Integrated

Paraxylene& Purified

Terephthalic Acid(PX-PTA)

Ongoing Applied now -

EIA Report

67 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CRZ Clearances

S. No MoEF&CC File No Units Date of issue Status of Project

8 11-86/2011-IA.III

CRZ for laying Storm Water

outfall pipelines to sea for

Paradip Refinery Project

21-02-2012 Commissioned

9 11-30/2015-IA.IIICRZ for Pet Coke

Evacuation Unit11-02-2016 Commissioned

Note : 1. J-11011/70/2007-IA. II(I) dt.06-07-2007- Partially complied for which the action taken report- IOCL /PDR/HSE/MoEFCC/EC/2021-22/002 dated 29.04.2021 has been attached along with Annexure-2.

2. Latest EC- J-11011/344/2016-IA. II(I) dt.11-10-2018- Partially complied on the below points.

For not installating the webcam with night vision capability at the effluent discharge point. (Specific condition no.

xx)

For not publishing the EC,2018 within 7days from the date of issue of clearance letter. (General condition no.xv)

For which the Action taken report – IOCL /PDR/HSE/MoEFCC/EC/2021-22/003 dated 04.06.2021 is attachéd along with

Annexure 2.

In which the Night vision Web cam will be installed within Oct,2021.

The EC publishing in newspaper was inadvertly missed, however the same was published later on 18.09.2020 and

noted the general condition in future.

Earlier EC’s Attached as Annexure 5.

Certified Earlier EC’s Complaince report Attached along with Annexure 5.

Lateste EC- J-11011/344/2016-IA-II(I) dated 11th Oct 2018

Attached as Annexure 2.

Certified Latest EC’s Complaince report with the Action taken report.

Attached along with Annexure 2.

EIA Report

68 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No Latest CTO No. Date of issue Valid till Status of compliance

1 Ref No.- 5543/IND-I-CON-6414 31.03.2021 31.03.2022 Complaied

Latest CTO- Ref No.- 5543/IND-I-CON-6414 dated 31.03.2021 valid till 31.03.2022 with all CTO’s and CTE’s since inception along with chronology table

Attached as Annexure 3.

Self certified compliance report of latest CTO submitted to SPCB,Odisha

Attached along with Annexure 3.

4 Site Detailsi. Location of the project site

covering village, Taluka/Tehsil, District and State, justification for selecting the site. Whether other sites were considered

The project site is situated at IOCL Paradip Refinery, Survey no: 218, Abhaychandrapur village, Jhimani P.O., Kujang Taluk, Jagatsinghpur Dist., Paradip, Odisha -754141.

Alternate sites were not considered since the proposed expansion is within the existing refinery complex. Adequate land is available with IOCL Paradip for the proposed expansion.

ii. A Topo sheet of the study area of radius of 10 km and site location on 1:50,000/ 1:25,000 scale on an A3/A2 sheet (including al eco-sensitive areas and environmentally sensitive places)

EIA Report

69 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Topomap of the study area in 1:50000 scale

No notified Eco-sensitive areas and environmentally sensitive places within 10km radius from the project boundary.

Topo map in 1:50,000 scale for the study area on an A3 sheet including environmental sensitive areas/ eco-sensitive areas is given in Chapter 3, Section 3.5.5, Figure 3-2 of EIA report.

iii. Details w.r.t option analysis for selection of site

Alternate sites were not considered since the proposed expansion is within the existing refinery complex. Adequate land is available with IOCL Paradip for the proposed expansion.

iv. Co-ordinates (lat-long) of all four corners of the site S. No

Co-ordinates of all four corners of the site

Latitude Longitude

EIA Report

70 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

1 20°15'57.9''N 86°34'48.89''E

2 20°14'39.63''N 86°37'5.97''E

3 20°16'8.3''N 86°36'24.62''E

4 20°16'42.52''N 86°36'5.11''E

v. Google map Earth downloaded of the project site

Google map Earth downloaded of the project site

EIA Report

71 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

vi. Layout maps including existing unit as well as proposed unit indicating storage area, plant area, greenbelt area, utilities etc. If located within an industrial area/Estate/Complex, layout of Industrial indicating location of unit within the Industrial area/Estate.

The layout indicating storage area, plant area, greenbelt area, utilities etc is appended in Chapter 2, Section 2.8.2 of EIA

report and the layout including existing unit as well as proposed unit enclosed as Annexure-6. The Greenbelt layout is

attached in the Annexure-8.

The project site is situated outside industrial area/Estate/Complex.

vii. Photographs of the proposed and existing (if applicable) plant site, existing, show photographs of plantations/greenbelt, in particular.

Photographs of the proposed and existing plant site, existing, plantation/greenbelt are appended in Chapter 2, Section 2.8.1, Figure 2-14 and Figure 2-15.

viii. Land use break-up of total land of the project site (indicate and acquired), government/ private- agriculture, forest, wasteland, water bodies, settlements, etc shall be included (not required for industrial area)

Classification of landuse of Project Site: Builtup, Urban (As per Bhuvan 2011-12)

Description Existing (Acres)

Proposed (Acres)

After Expansion (Acres) Percentage, %

a. Refinery Project areaBuilt Up area 1748 75 1823 65.32%Roads 355 0 355 12.72%Green Belt 580 0 580 20.78%Vacant Land 108 0 33 1.18%Subtotal (a) 2791 75 2791 100%b. Residential Areai.Plot Area 204 0 204 64.97ii.Green Belt 110 0 110 35.03Subtotal (b) 314 0 314 100.00c.Other Office and Buildingi.Plot Area 155 0 155 64.58ii.Green Belt 85 0 85 35.42Subtotal (c) 240 0 240 100.00Total Area(a+b+c) 3270 75 3345 d. On other's land Green belt (d) 75 0 75 Total Green belt Area from a,b,c and d

850 0 850 30.46

Note: The proposed 75 acres is utilized from the existing vacant land inside the IOCL Paradip Refinery Complex.

EIA Report

72 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Details given in Chapter 2, Section 2.8.2 of EIA report

ix. A list of major industries with name and type within the study area (10 km radius) shallbe incorporated. Land use details of the study area)

List of major industries within the study area (10 km radius)

S. No Description Distance (~km) Direction

1. Hindustan Petroleum Corporation Limited 1.68 N

2. IOCL Paradip Marketing Terminal 1.72 N

3. Paradip Power plant Limited 3.17 NNE

4. Adani Wilmar Limited (Edible oil) 3.28 NE

5. Arcelor Mittal Nippon Steel India Limited 5.24 NE

6. IFFCO Plant 6.3 NE

x. Geological features and Geo-hydrological status of the study area shall be included.

a.Geological features Geologically the study area including the site consisting of Alluvial formations of Recent geological age. These alluvial formations are developed by the action of Mahanadi river and Bay of Bengal sea. The alluvium developed due to the river action is designated as Fluvial alluvium. Similarly, the alluvium developed due to the sea action is named as Coastal Alluvium. The basement rocks are existing below 100m from the existing ground level. The geological formation of this district is entirely alluvium of recent origin. The entire district comes under Mahanadi Delta Division and Cuttack Coastal Plain.

b.Geo-hydrological status The study area including the project site is part of coastal and fluvial alluvium developed due to the deltaic nature

of Mahanadi River with Bay of Bengal. The area is covered with thick pile of younger and older alluvial formations to an extent of more than 100m bgl. Below the alluvium there are sandstone formations with intercalation of clay beds are reported which are part of

ParadeepTechtonic Depression of Mahanadi Basin. These sedimentary formations are extended more than 900m thickness which are successively underlined with

basement crystalline rocks. Groundwater occurs in semi-confined to unconfined nature in the alluvial formations within the study area. There are potential shallow fresh water aquifers existing within the study area at 10 to 20m depth from the existing

ground levels. The existing bore wells it is understood that the groundwater level is between 3 to 4 mbgl. Below the fresh water aquifers there are saline water aquifers which are present at 40 to 50m bgl within the alluvial

formations. The deeper aquifer system is also present within the Paradeep Depression in deep seated sedimentary formations.

EIA Report

73 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Further detailed Geological features and Geo-hydrological status is provided in Chapter 3, Section 3.5.10, Section 3.5.8 of EIA report

xi. Details of drainage of the project upto 5km radius of the study area. If the site is within 1Km radius of any major river, peak and lean season river discharge as well as flood occurrence frequency based on peak rainfall data of the past 30 years. Details of Flood Level of the project site and maximum of Flood of the river shall also be provided (mega green field projects)

Drainage Map showing the study area

1. Mahanadi River is the one of the major perennial river flowing from west to east of the project site at a

distance of ~6.18km (NNE) merging into Bay of Bengal.

2. Santara Nadi, one of the tributaries of Mahanadi River which bifurcate the refinery complex and merges

into Bay of Bengal.

3. Jatadharmuhan Nadi is flowing at a distance of ~2km (SSW) which merge into Bay of Bengal.

4. Dhenkiagalia Nadi is flowing adjacent to the southern part of refinery complex which merges into Santara

EIA Report

74 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Nadi.

5. Taladanda is a lined canal, which is at a distance of ~4.87km (ENE).

Based on 30 years rainfall data, the highest HFL recorded was 3.91m MSL during 1999 Super Cyclone.

The Refinery Site itself does not flood in any of the flood scenarios tested. The HPP level of 4.06m MSL exceeds the 1999 Cyclone high water level of 3.91m MSL by 150mm.

S. No Description Distance (~km) Direction 1 Bay of Bengal 0.55 SE 2 DhenkiagaliaNadi(adjacent to project site) 0.03 W 3 Santara Nadi(adjacent to project site) 0.08 E 4 AtharabankiNadi 1.03 E 5 MahangaNadi 1.21 W 6 JatadharmuhanNadi 2 SSW 7 Taladanda canal 4.87 ENE

Flood risk assessment report prepared by URS scott wilson for IOCL Paradip Refinery is also enclosed as Annexure 25. xii. Status of acquisition of land. If acquisition is not complete, stage of the acquisition process and expected time of complete procession of the land.

Land acquisition is not required as the proposed expansion is within the existing facility.

Land Documents are enclosed as Annexure 1

Note: As per form-1 16 acre has to acquired for the proposed project based on the preliminary project feasibility study carried out. Based on the Detailed feasibility study it is identified, as the land acquisition is not required

xiii. R&R details in respect of land in line with state Government policy

Not applicable, since no land acquisition involved.

5 Forest and wildlife related issues (if applicable):i. Permission and approvals for the use of forest land (forestry clearance), if any, and recommendations of the State Forest Department (if applicable)

Not Applicable, since no forest land involved.

ii. Land use map based on High resolution satellite imagery (GPS) of

Not Applicable, since no forest land involved.

EIA Report

75 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

the proposed site delineating the forest land (in case of projects involving forest land more than 40 Ha) iii. Status of application submitted for obtaining the stage I Forestry Clearance along with latest status shall be submitted

Not Applicable, since no forest land involved.

iv. The projects to be located within 10 Km of the National parks, Sanctuaries, Biosphere Reserves, Migratory Corridors of Wild Animals, the project proponent shall submit the map duly authenticated by Chief Wildlife Warden showing these features vis-à-vis the project location and the recommendations or comments of the Chief Wildlife Warden-thereon.

Not Applicable since no National parks, Sanctuaries, Biosphere Reserves, Migratory Corridors of Wild Animals in 10km radius from the project boundary.

v. Wildlife Conservation Plan duly authenticated by the Chief Wildlife Warden of the State Government for conservation of schedule I fauna, if any exists in the study area.

There are two Schedule-I Species in study area i.e., reptiles named Nilssoniahurum (Gray 1831) and Lissemyspunctata (Bonnaterre 1789) habitats. There are two Schedule-I- Part-IV Species in study area i.e Butterfly-Hypolimnas misippus and Castalius rosimon

Action plan for conservation of Marine life including Olive Ridley Turtle has been prepared in 2013 by Mangrove Forest

Division (Wildlife), Rajnagar, Odisha and approved by Principal Cheif Conservator Forest(WL) & CheiWildlife Warden,

Odisha. The fund allocation by IOCL of INR 20.04Cr.for the conservation of Marine life over a period of implantation of

10yrs.

The Wildlife conservation plan prepared by Mangrove Forest Division (Wildlife), Rajnagar, Odisha is enclosed as

Annexure 20.

vi. Copy of application submitted for clearance under the Wildlife (Protection) Act, 1972 to the Standing Committee of the National Board for Wildlife.

Not applicable since no notified Sanctuaries/ National Parks/ Eco-sensitive zones/ areas within the 15km radius from the project boundary.

6 Environmental Status

EIA Report

76 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

i. Determination of atmospheric inversion level at the project site and site- specific micrometeorological data using temperature, relative humidity, hourly wind speed and direction and rainfall

The daily inversion level at the project site varies from 50 to 1750m during 6 AM to 6 PM, the maximum recorded at 5 PM, March 2019. Further details are given in Chapter 3, Section 3.6.2 and Section 3.6.5

Meteorological Data for the Study Period (March - May 2019) S. No Parameter Observation

1. Temperature Max. Temperature: 43°C Min. Temperature: 19°C Avg. Temperature: 29.83°C

2. Hourly Average Relative Humidity

80.05%

3. Hourly Average Wind Speed 3.04m/s 4. Predominant Wind Direction South

ii. AAQ data (except monsoon) at 8 locations for PM10, PM2.5, SO2, NOX, CO and other parameters relevant to the project shall be collected. The monitoring stations shall be based on CPCB guidelines and take into account the pre-dominant wind direction, population zone, sensitive receptors including reserved forests.

The ambient air quality have been monitored at 8 locations for 14 parameters as per NAAQS/CPCB guidelines within the study area. The average baseline levels of PM10 (55.35 – 80.53µg/m³), PM2.5 (27.72 – 38.16µg/m³), SO2(8.63 – 13.21µg/m³), NO2(16.15 – 25.30µg/m³), the nearest CPCB AAQ monitoring station is PPL Guest House in which the annual average for the year 2018: PM10 (113 µg/m³), PM2.5 (37 µg/m³), SO2(19 µg/m³), NO2(11 µg/m³). All the parameters are well within the National Ambient Air Quality Standards for Industrial, Commercial and Residential areas at all monitoring locations during the study period from March 2019 - May 2019.

AAQ monitoring locations are provided in the Chapter 3, Section 3.7and monitoring results are provided in the Chapter 3,Section 3.7

iii. Raw data of all AAQ measurement for 12 weeks of all stations as per frequency given in the NAAQM notification of Nov. 2009 along with- min-max, average and 98% values for each of the AAQ parameters from data of all AAQ stations should be provided as an annexure to the EIA report

Raw data of all AAQ measurement for 12 weeks of all stations as per frequency given in the NAAQM notification of Nov. 2009 along with- min-max, average and 98% values for each of the AAQ parameters from data of all AAQ stations are provided as Annexure 13

iv. Surface water quality of nearby River (100m upstream and downstream of discharge point) and other surface drains at eight locations as per CPCB/ MoEF&CC guidelines.

Surface water sampling locations

S. No

Water bodies Location

code Distance from project

boundary (~km) Direction from project

boundary

1 Stream near Udayabat SW1 4.04 N 2 Mahanadi d/s near Musharhia SW2 7.56 NNE

EIA Report

77 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3 Marine sample near Port SW3 4.77 E 4 Santara nadi d/s SW4 0.16 E 5 Marine sample near project site SW5 0.64 E 6 Mahanga Nadi SW6 1.34 SW 7 Mahanadi u/s near Balaramapur SW7 8.59 NW 8 Sanatara nadi u/s SW8 0.1 W

Surface water quality of nearby River

Parameter Surface water

sample Marine

sample ranges Standard Limit

Class A Class B Class C Class D Class E pH 6.76 to 7.84 7.94 to 7.98. 8.5 8.5 8.5 8.5 8.5 Total Dissolved Solids (TDS)

2640 mg/l to 19128 mg/l

32040 mg/l to 34677 mg/l .

500 - 1500 - 2100

Hardness 320.2 mg/l – 3875.6 mg/l

5602.4 mg/l – 6401.6 mg/l

300 - - - -

BOD 1 mg/l and

19mg/l 3 to 5 mg/l 2 3 3 - -

COD 4 to 154 mg/l 18 to 36 mg/l - - - - -

Surface water quality of nearby River and other surface drains at eight locations as per CPCB/ MoEF&CC guidelines are collected & analyzed and the details are provided in the Chapter 3, Section 3.9.

v. Whether the site falls near to polluted stretch of river identified by the CPCB/MoEF& CC, if yes give details

No Polluted stretch of river identified as per CPCB within 10km radius from the project site.

vi. Ground water monitoring at minimum 8 locations shall be included

Ground water monitoring results at 8 locations

Parameter Range of Results Standard Limit

Acceptable Limit Permissible

Limit

pH 7.02 and 8.21 6.5-8.5 No

Relaxation Total Dissolved Solids (TDS) 406mg/l –868 mg/l 500mg/l 2000 mg/l Chloride 94.03 mg/l – 251.21 mg/l 250mg/l 1000 mg/l Sulphate 32.03mg/l – 108.31 mg/l 200mg/l 400 mg/l Hardness 143 mg/l – 301mg/l 200mg/l 600 mg/l

EIA Report

78 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Ground water monitoring at minimum 8 locations are collected & analyzed. Futher detailed Ground water monitoring results were provided in the Chapter 3, Section 3.9

vii.Noise levels monitoring at 8 locations within the study area.

Noise levels monitoring results at 8 locations within the study area

Site Day Time (dB(A)) Night Time (dB(A))

Results Standards Results Standards

Industrial areas (Project site) 53.8 75 47.1 70

Commercial areas (Paradip, Coast Guard) 64.8 65 54.2 55

Residential area (Paradipgarh, Dochakki, Musadiha, Dhinkia, Sunadiakandha and Gandakipur)

50.9-58.6

55 42.6-47.5

45

Noise levels monitoring at 8 locations within the study area are collected & analyzed. Further detailed Noise level monitoring results were provided in the Chapter 3, Section 3.8

viii. Soil characteristics as per CPCB guidelines

Soil characteristics as per CPCB guidelines The pH of the soil samples ranged from 5.63 to 7.94. Indicating that the soils are moderately acidic to moderately

alkaline in nature. Conductivity of the soil samples ranged from195 to280 μmhos/cm. Nitrogen content ranged from 165.42 mg/kg to 313.8 mg/kg. Phosphorous ranged from 133.17 mg/kg to 296.71 mg/kg. Potassium content ranges from 69.9 mg/kg to 144.69 mg/kg.

Futher detailed Soil characteristicsare analyzed as per CPCB guidelines are provided in the Chapter 3, Section 3.10, Table 3-19 of EIA report.

ix. Traffic study of the area, type of vehicles, frequency of vehicles for transportation of materials, additional traffic due to proposed project, parking arrangement etc.

Traffic study is carried out including type and frequency of vehicles, transportation of materials and additional traffic due to the proposed project based on IRC:106-1990- Guideline for capacity of urban road in plain area. Details are given in Chapter 4, Section 4.5.5 of EIA report. The existing parking arrangements are sufficient for the proposed project.

Existing & proposed vehicular movement per Hour (Peak Hour)

S. No

Type of Vehicle

Existing vehicles

Existing PCU

Proposed vehicles

Proposed PCU

Total vehicles after project

implementation

PCU Factors IRC (SP

41)

Total PCU after project

implementation

1 2 wheeler 124 93 0 0 127 0.75 93 2 3 wheelers 48 96 0 0 48 2 96

3 4 wheelers/ cars

91 91 5 5 96 1 96

EIA Report

79 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4 truck/Lorry 79 292.3 17 62.9 96 3.7 355.2

5 agricultural tractor

11 44 0 0 11 4 44

6 light emission vehicle

9 12.6 0 0 9 1.4 12.6

Total 362 628.9 22 67.9 384 696.8

Traffic Volume after Implementation of the Project

For the Road Volume of

Traffic Volume

(V)

Road Capacity

(C) V/C Ratio

LOS Category*

Traffic Classification

Existing 362 628.9 1500 0.42 “B” Stable Traffic Flow

After implementation

384 696.8 1500 0.47 “B” Stable Traffic Flow

*LOS (Level of Service) categories are A-Free Flow, B- Reasonably Free Flow, C-Stable Flow, D-Approaching unstable

flow, E- Unstable flow, F- Forced or breakdown flow.

Due to propose project there will be slight increment in the vehicle movement but the level of service (LOS) anticipated will

be Stable Traffic Flow.

x. Detailed description of flora and fauna (terrestrial and aquatic) existing in the study area shall be given with special reference to rare, endemic and endangered species. If Schedule-I fauna and found within the study area, a Wildlife Conservation plan shall be prepared and furnished

Flora and Fauna study is carried out found within the 10km radius study area and the details are provided in Chapter 3, Section 3.5.3.1 and Section 3.11

a.FloraThere is a vulnerable herbs in the study area i.e., named Acanthephippium silhetense and Coelogyne trinervisThere is a vulnerable tree in the study area i.e., named Lagerstroemia minuticarpaThere is a endangered Shrub Mangrove in the study area i.e., named Acanthus volubilis Wall There are three endangered Tree Mangrove in the study area i.e., named Bruguiera sexangula, Heritiera kanikensis Majumdar and Heritiera littoral is Dryand b.Fauna There is a vulnerable Amphibian in the study area i.e., named Philautus garo (Boulenger 1919) There is a endangered bird in the study area i.e., named Baer’s PochardThere is a vulnerable bird in the study area i.e., named Lesser Adjutant

EIA Report

80 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

There is a near threatened fish in the study area i.e., named Indian butter Cat fish There are two Schedule-I Species in study area i.e., reptiles named Nilssoniahurum (Gray 1831) and Lissemyspunctata (Bonnaterre 1789) habitats.There are two numbers of Schedule-I-Part-IV in study area i.e., Hypolimnas misippus and Castalius rosimon

Summary on Flora in the Study area

Not yet assessedData

DeficientLeast

ConcernEndangered

Near Threatened

VulnerableCritically

Endangered

Trees — — 65 3 — 1 —

Grasses — — 7 — — — —

Herbs — — 33 — — 2 —

Shrubs — — 11 1 — — —

Climber — — 7 — — — —

Sedges — — 8 — — — —

Fern __ __ 1 __ __ __ __

Summary on Fauna in the Study area

Not yet assessed

Data Deficient

Least Concern

EndangeredNear

ThreatenedVulnerable Near Threatened

Mammals — — 16 — — — —

Reptiles — — 6 — — 1 6

Amphibians — 4 17 — — 1 —

Butterfly 52 — 4 — — — —

Birds — — 59 1 1 1 —

Fish — — 7 — 1 — —

Action plan for conservation of Marine life including Olive Ridley Turtle has been prepared in 2013 by Mangrove Forest Division (Wildlife), Rajnagar, Odisha and approved by Principal Cheif Conservator Forest(WL) & CheiWildlife Warden, Odisha. The fund allocation by IOCL of INR 20.04Cr.for the conservation of Marine life over a period of implantation of 10yrs. Wildlife conservation plan along with the cost breakup is attached as Annexure-20

xi. Socio-economic status of the study area

Socio-economic profile of the study area

S.No Particulars Study Area Unit

1 Number of villages and Town in the Study Area 102 Nos.

2 Total Households 80839 Nos.

EIA Report

81 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3 Total Population 358725 Persons

4 Children Population (0-6 Years Old) 36501 Persons

5 SC Population 75330 Persons

6 ST Population 3603 Persons

7 Total Working Population 118859

Persons

8 Main Workers 95224 Persons

9 Marginal Workers 23635

Persons

10 Cultivators 27679 Persons

11 Agricultural Labourers 18768

Persons

12 Household Industries 5087

Persons

13 Other Workers 67325

Persons

14 Literates population 279756 Persons

Further detailed socio-economic status of the study area is provided in the Chapter 3, Section 3.12

7 Impact and Environmental Management Plani. Assessment of ground level

concentration of pollutants from the stack emission based on site-specific meteorological features. In case the project is located on a hilly terrain, AQIP modeling shall be done using inputs of the specific terrain characteristics for determining the potential impacts of the project on the AAQ. Cumulative impact of all sources of emissions (including transportation) on the AAQ of the area shall be assessed. Details of the model used and the input data

The ground level concentration of pollutants (PM10, PM2.5, SO2&NOx) using AERMOD software were assessed and presented in Chapter 4 Section 4.5 of EIA report.

AERMOD Software Version 8.0.5 was used for air dispersion modeling and is applicable to a wide range of buoyant or neutrally buoyant emissions up to a range of 10 km. The air quality contours shall be plotted on a location map showing the location of the project site are shown in GLCs for proposed is given in Chapter 4 Section 4.5 of EIA report

Total Maximum GLCs from the Stack Emissions including transportation

Pollutant Max. Base line Conc. (µg/m3) **

Estimated Incremental Conc. (µg/m3)

Total Conc. (µg/m3) NAAQ

standard (µg/m3)

% increase

PM 95.7 0.10 95.8 100 0.10 SO2 15.7 1.16 16.86 80 7.39 NOx 30.06 5.89 35.95 80 19.59 CO 50 78.69 128.69 4000 157.38

EIA Report

82 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

used for modelling shall also be provided. The air quality contours shall be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any.

CO2 - 8099.82 8099.82 - -

Note:

1. CO2 parameter is not available for NAAQ standards

2.*Since the maximum base line concentration of CO is below detectable limit, the detectable limit of CO 50 µg/m3 is considered 3.** Max. Base line values were observed at Paradwip (Coast guard) at a distance ~4.91km, E from

the project boundary.

ii. Water Quality modelling - in case of discharge in water body.

The refinery effluent are treated in Effluent Treatment Plant followed by RO Plant and the final reject water after treatment meeting MINAS Standards is disposed into the sea.

The Water Quality Modeling is not done in the marine disposal area.The treated effluent is being discharged into deep sea. No other effluent is being discharged into the river.

The existing and proposed effluent disposal into deep sea is 190.88 m3/hr and 86.18 m3/hr respectively. After expansion, 277.06m3/hr will be discharge into deep sea that it is observed to be within the marine discharge approval limit of 350m3/hr as per the OPCB consent for Air and water obtained vide: 5543/IND-I-CON-6414 dated 31.03.2021 valid till 31.03.2022. The industrial effluent is discharged into deep sea through the pipeline where its outlet of pipe is at a distance of 3km from the Low Tide Line (LTL).

Impact of the transport of raw

material and end products on the

surrounding environment shall be

assessed and provided. In this

regard, options for transport of raw

materials and finished products and

wastes (large quantities) by rail or

rail-cum road transport or conveyor-

cum-rail transport shall be

examined.

Material Handling, Storage and Transportation

Hazardous chemicals will be stored in closed tanks and drums with appropriate blanketing systems.

All transfers from drums / tanks will be done through pumps in closed pipelines.

The loading of finished products to trucks and drums will be done through automated filling systems

with overflow protections.

All key raw materials will be charged to the reactors through closed pipeline systems including

pneumatic systems for solid handling.

Raw materials/ intermediates/ products will be stored in closed tanks/drums provided with breather

arrangements to avoid fugitive emissions.

Further detailes are given in Chapter 10 Section10.6.5 of EIA report.

EIA Report

83 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

iii. A note on treatment of waste water from different plant operations, extent recycled and reused for different purposes shall be included. Complete scheme of effluent treatment, characteristics of untreated and treated effluent to meet the prescribed standards of discharge under E(P) rules.

a.Wastewater management

Unit Existing (m3/hr) Proposed (m3/hr) After expansion (m3/hr)

Effluent generation 1082.1 408 1490.1

ETP treatment capacity 1580 408 1988

Recycled water 748 305.5 1053.5

Existing

Approx. 1082.1 m3/hr of effluent is generated in the existing facility of which 190.88 m3/hr rejects from RO is disposed to

Deep Sea, 50 m3/hr rejects from RO is sent to Coke Dust Suspension and 50 m3/hr rejects from RO is sent to Coke Cutting..

Remaining 748m3/hr from RO is reused back in the system for DM Water Makeup.

Proposed

In the proposed expansion Approx. 408 m3/hr of effluent is generated in the proposed facility of which 78% of effluent is

processed in RO plant and its rejects of 86.18 m3/hr is disposed into deep sea. The remaining RO processed water of

305.5m3/hr is reused back in the system for DM Water Makeup and cooling tower.

New ETP is proposed for installation to process effluent @ 408 m3/hr with 10% design Margin (Maximum capacity with

high TOC)

b.Characteristics of effluent being generated

ETP inlet (effluent generated) data in Jan’21

S. NO. PARAMETER TEST METHOD UoM RESULT

FLOW (m3/hr)1 pH IS 3025 (P:11) - 9.9

2 BOD IS 3025 (P:44) mg/l 180

3 COD IS 3025 (P:58) mg/l 1370

4 Oil & Grease IS 3025 (P:39) mg/l 264

5 TSS IS 3025 (P:17) mg/l 84

6 Sulphide IS 3025 (P:29) mg/l 4.3

EIA Report

84 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

7 DO IS 3025 (P:38) mg/l ND

8 Alkalinity IS 3025 (P:23) mg/l 191

9 NH3 IS 3025 (P:34) mg/l 29.5

10 Conductivity IS 3025 (P:14) μs/cm 1117

11 ORP APHA 2580 mV 20

c.Characteristics of effluent before discharge

Sl

NoParameters Test Method UoM

Limits as per

MINASResults

1 pH IS 3025 (P:11) - 6.0 -8.5 8

2 BOD IS 3025 (P:44) mg/l 15 9

3 COD IS 3025 (P:58) mg/l 125 78

4 Oil &Grease

IS 3025 (P:39) mg/l 5 <4.0

5 TSS IS 3025 (P:17) mg/l 20 <4

6 Sulphide IS 3025 (P:29) mg/l 0.5 <0.10

7 Phenol IS 3025 (P:43) mg/l 0.35 0.09

8 Cyanide IS 3025 (P:27) mg/l 0.2 <0.02

9 NH3 IS 3025 (P:34) mg/l 15 1.2

10 Alkalinity IS 3025 (P:23) mg/l 172

11 Chloride IS 3025 (P:32) mg/l 973

12 TDS IS 3025 (P:16) mg/l 1001

13 Turbidity IS 3025 (P:10) NTU <0.1

14 TKN ASTM D3590 A mg/l 40 2.1

15 P IS 3025 P:31 b mg/l 3 0.068

16 Cr(VI) IS 3025 P:52 a mg/l 0.1 <0.1

17 Cr total APHA 23rd edition 3125 A & B mg/l 2 <0.1

18 Pb APHA 23rd edition 3125 A & B mg/l 0.1 <0.001

19 Hg APHA 23rd edition 3125 A & B mg/l 0.01 <0.001

20 Zn APHA 23rd edition 3125 A & B mg/l 5 0.016

21 Ni APHA 23rd edition 3125 A & B mg/l 1 0.011

22 Cu APHA 23rd edition 3125 A & B mg/l 1 0.003

23 V APHA 23rd edition 6200 B. mg/l 0.2 <0.001

EIA Report

85 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

24 Benzene USEPA 8260C using capillarycolumn and MSD with Purge & Trap device (USEPA 5030C)

mg/kg 0.1 <0.005

Effluent generated from Purified Terephthalic Acid (PTA), Paraxylene (PX) and & offsite and utilities plant are to be collected, segregated and treated in ETP to meet applicable regulatory requirements before final disposal. RO based treatment is envisaged for final disposal. Rejects from RO plant to be transfer in sea.

ZLD is not being followed whereas the OPCB consent obtained vide:5543/IND-I-CON-6414 dated 31.03.2021 valid till

31.03.2022 approved marine disposal is 350 m3/hr And the actual discharge into the Deep sea in 277.06 m3/hr.

The effluent treatment scheme is given in Chapter 2 Section 2.16 and Section 2.17 of EIA report.

Wastewater treatment and disposal details are provided in the Chapter 10, Section 10.6.2 of EIA report.iv. Details of stack emission and

action plan for control of emissions to meet standards. S.No Stack details

Fuel Rate (Natural

Gas) (kg/hr)

Flue gas Flow Rate (Nm3/hr)

Emission per stack (g/s)

PM SO2 NOx CO CO2

1.Tatory

Furnace 433 4679 - 0.0257 0.1688 - 451.53

2.ISOMAR Furnace

2747 29708 - 0.0833 0.6052 - 1402.36

3. XFU 1 7594 82116 - 0.5597 2.7983 - 9553.61

4. XFU 2 4840 52339 - 0.4396 2.1955 - 7495.03

5.Utility Boiler

– 5 (Standby)*

19973 325061 0.4528 4.5139 22.575 1.6931 -

6. Flare 15 162 0.0002 0.0023 0.0113 0.0008 -

Total (g/s) 0.453 5.6245 28.3541 1.6939 18902.53

EIA Report

86 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Further details of stack emission are provided in the Chapter 4 Section4.5.4 of EIA report.

Details of action plan for control of emissions: Use of clean burning fuel gas and natural gas in PX-PTA unit. Installation of low NOx burners in all the furnaces and boilers Tall stacks for better dispersion of flue gases. Online monitoring of SOx, NOx, CO and PM emissions from furnaces/boilers. Monitoring of ambient air quality as per revised MoEF&CC Installation of internal floating roof with double seals in all Class-A tanks for reduction of fugitive emissions. Provision of mechanical seals in all the hydrocarbon pumps for reduction of fugitive emissions. Reduction of hydrocarbon losses and to attain zero leakage status. All the proposed tanks are of Internal floating roof type minimizing the fugitive emissions in comparison to

External floating roof tanks All the tanks will be under Nitrogen blanketing

v. Measures for fugitive emission control

Details of action plan for control of fugitive emissions Installation of floating roof with double seals in all Class-A tanks for reduction of fugitive emissions. Provision of mechanical seals in all the hydrocarbon pumps for reduction of fugitive emissions. All the proposed tanks are of Internal floating roof type minimizing the fugitive emissions in comparison to

External floating roof tanks All the tanks will be under Nitrogen blanketing

vi. Details of hazardous waste generation and their storage, utilization and management, Copies of MOU regarding utilization of solid and hazardous waste in cement plant also be included. EMP shall include the concept of waste-minimization, recycle/ reuse/recover techniques, Energy conservation, and natural resource conservation.

Hazardous waste materials will be properly disposed as per the Hazardous Wastes (Management, Handling and

Transboundary Movement) Rules 2016;

Hazardous waste authorization has been made with SPCB, Odisha- IND-IV-HW-930/5028 dated 24.05.2019 valid till

31.03.2024 is enclosed as Annexure-14.

Existing Hazardous Waste:

S.No.

Details of Waste

Scheduled as per HWM

rules

Existing Quantity

TPY

Approved Quantity TPY

Frequency of disposal

Storage and Disposal

1 Spent

catalyst Schedule-I 4.2 2484.4 2500 Within 90 days

Stored in intermediate storage facility (covered

warehouse with impervious

EIA Report

87 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

floor and shed)

Disposal in SLF -1497.4 / Co-processing in cement

industry - 987 2 Spent Clay Schedule-I 4.5 145.5 720 Within 90 days Directly sent to SLF

3 Ash Schedule-I

37.2 36.0

- Within 90 days Directly sent to SLF

4 Oily Sludge Schedule-I 4.1 1456.1

2748 (Oil sludge/

Emulsion/ Slop Oil)

Within 90 days Directly sent to DCU for

processing

5 Oily Sludge Schedule-I 4.1 74.2 Within 90 days

Stored in impervious metallic containers before

unloading in melting pit for oil recovery

Sludge is disposed in HW incinerator

6 Coke Schedule-I 4.4 16.7 180

Within 90 days Sent to incinerator for

disposal

Proposed Hazardous Waste:

S.No. Details of Waste Scheduled as per

HWM rules

Proposed Quantity

TPD

Frequency of disposal

Storage and Disposal

PX

1 Spent Clay from Clay Treaters

Schedule-I 4.5 0.12 Within 90 days Captive SLF

2 Spent Catalyst from Reactor

Schedule-I 1.6 0.01 Within 90 days Metals Recovery or Landfill in Captive

SLF

3 Spent Clay from Clay Treater

Schedule-I 4.5 1.44 Within 90 days Captive SLF

4 Spent Adsorbent from Adsorbent Chambers

Schedule-I 1.6 0.24 Within 90 days Captive SLF

5 Catalyst from Reactor Schedule-I 1.6 0.04 Within 90 days Metal recovery by authorized recycler

6 Spent Clay fromClay Treater

Schedule-I 4.5 0.26 Within 90 days Captive SLF

PTA

EIA Report

88 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

7 PTA Spent Catalyst Schedule-I 1.6 0.0438 Within 90 days Recovery by catalyst

manufacturer

8 Filters, Oils Schedule-I

3.3/5.1 0.0685 Within 90 days

Disposal in authorized HW incinerator / Sale

to authorized users

9 Pails, Corrosion, Paint Schedule-I 21.1 0.0137 Within 90 days Sale to authorized

users

10 Laboratory Solvents Schedule-I 20.2 0.0003 Within 90 days Disposal in ETP

11 Waste Solvents Schedule-I 20.2 0.0110 Within 90 days Disposal in ETP

vii. Proper utilization of fly ash shall be ensured as per Fly Ash notification, 2009. A detailed plan of action shall be provided.

No generation of flyash as Natural Gas will be used as fuel for the boilers.

viii. Action plan for the green belt development plan in 33% area i.e., land with not less than 1500 trees per Ha. Giving details of Species, width of plantation, planning schedule etc. shall be included. The green belt shall be around the project boundary and a scheme for greening of the roads used for the project shall also be incorporated.

Refinery has developed existing greenbelt area of 580 Acres in refinery area while in total it occupies about 850acres of green belt. The green belt occupies about 30.46% only More than 8 lakh trees have been planted by IOCL. This is ongoing job and PDR has the commitment to plant @5000 trees every year towards environment management and preserve eco system. Survival rate is 95%. As per Paradip refinery project’s EC condition for green belt (GB) development was on 580 acres land and green belt on the same has been developed in full. Additional tree plantation has been done on land in and around residential township, along access roads, village schools, panchayats, coastal villages etc. IOCL Paradip refinery till now has done plantation of suitable species trees about 8.5 Lakh including GB covering about 800 acres area. Further plantation of 100000 trees is under execution.

The details of Species along with the green belt demarcation are provided in Annexure 8.

SNO Description Existing Proposed Total1 Total area of Green

Belt343.983 113 343.983

2 Percentage of total project area

30.46 10 40.46

3 No. of Plants 809624 282500 1092124

4 Funds allocated 80962400 30000000 110962400

The land allocation for proposed green belt area is given in Annexure 29.

Further details are given in Chapter 2, Section 2.15 of EIA report.

EIA Report

89 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

ix. Action plan for rain water harvesting measures at plant site shall be submitted to harvest rainwater from the roof tops and storm water drains to recharge the ground water and also to use for the various activities at the project site to conserve fresh water and reduce the water requirement from other sources.

Two (02 nos) storm water reservoirs (Capacities: 2,96,000 KL and 3,13,000 KL) have been developed to store rain water in monsoon in the refinery premises. The Storm water pond for collecting surface runoff inside the Refinery is given in Chapter 10, Figure 10-6 of EIA report. The Rain water harvesting integrated with ecological park is given in Chapter 10, Figure 10-5 of EIA report.

Further details are given in Chapter 10, Section 10.6.7 of EIA report.

x. Total capital cost and recurring cost /annum for environmental pollution control measures shall be included.

Capital cost and Recurring cost /annum for environmental pollution control measures

S.

No. Description

Capital Cost

in Crores

Recuring Cost,

in Crores

1. Air Pollution

i.Stack 22.4 2.4

ii.APC equipments 1.7 0.17

2. Water Pollution

i.ETP 336 3.9

3. Noise Pollution

i. Acoustic enclosure 1.7 0.17

4. Solid Waste management - 0.1

5. Storm Water management/ Rain water harvesting - -

6. Green belt development 3 0.3

Total 364.8 7.04

xi. Action plan for Post-project environmental monitoring shall be submitted

Action plan for Post-project environmental monitoring S. No

Particulars Frequency of

monitoring Parameters for Monitoring

1. Air pollution monitoring Ambient air quality within the premises

Continuous PM, SOx, NOX, NO2, CO, O3, VOC

EIA Report

90 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Ambient air quality within the premises

Twice in a week All 12 parameters as given in NAAQS

Ambient air quality at 1 location in Prevalent Down Wind Direction

Twice in a week All 12 parameters as given in NAAQS

Ambient air quality at 1 location in Up Wind Direction

Twice in a week All 12 parameters as given in NAAQS

2. Noise monitoring At two locations within the premises Once in a month Noise Levels in dB(A)

3. Ground water quality monitoring One location at site Quaterly Physicochemical properties and Heavy

Metals The groundwater results are compared with the acceptable and permissible water quality standards as per IS: 10500 (2012)

4. Soil Quality monitoring One location near Hazardous waste storage area at site and one location outside site

Annually Physicochemical properties, Nutrients, Heavy metals as per IS 2720 (All Parts)

5. Effluent Quality Monitoring Inlet and outlet of ETP Once a month pH, Temp, TDS, TSS, Chloride, Sulphide,

Sulphate, fluoride, ammoniacal Nitrogen, Sodium, Copper, Zinc, Phenolic compounds, Oil and Grease, Boron, BOD, COD, Total Residual Chlorine, Arsenic, Cadmium, Total Chromium, Hexavalent Chromium, Lead, Selenium, Mercury, Pesticides, Alpha emitters, Free Ammonia, Dissolved Phosphates, Total Kjeldhal nitrogen, Cyanide, Nickel, Residual Sodium Carbonate. All the Parameters are to be verified as per CPCB Standard Guidelines.

Inlet and out let of STP Once a month Sewage is Biologically treated as a part of the ETP and standards are met through the pH, Temp, TDS, TSS, BOD, COD, Oil and grease. All the Parameters are to be verified as per CPCB Standard Guidelines.

EIA Report

91 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

6. Work place Monitoring Quarterly Noise, VOC, Lux levels

xii. Onsite and offsite Disaster (natural and Man-made) preparedness and Emergency Management Plan including Risk Assessment and damage control. Disaster Management Plan should be linked with District Disaster Management Plan.

The Risk Assessment has been carried out by using the PHAST software . Risk Assessment report and is attached as Annexure-10

On-site emergency plans and offsite Disaster management with ERDMP enclosed as Annexure 11.

8 Occupational Health

i. Plan and fund allocation to ensure the occupational health & safety of all contract and casual workers

All the occupational health related expenditure of casual & contract workers incorporated in the scope of contractor and compliance to the statutory rules in this regard is ensured. Approximate cost for OHC checkup is Rs. 2200 per person.

IOCL officials OHC checkup is carried out under composite contract with the VK hospitals.

M/s IOCL, PDR, Safety, Health and Environment Policy (SHE) provided in Chapter 10, Section 10.9 of EIA report.ii. Details of exposure specific health

status evaluation of worker. If the worker’s health is being evaluated by pre-designed format, chest x-rays, Audiometry, Spirometry, Vision testing (Far and near vision, color vision and any other ocular defect), ECG, during pre-placement and periodical examinations give the details of the same. Details regarding last month analyzed data of above mentioned parameters as per age, sex, duration of exposure and department wise.

The specific health status evaluation of worker’s medical report is enclosed as Annexure 15.

The medical facities available within the IOCL Paradip Refinery is enclosed as Annexure 28.

iii. Details of existing Occupational & Safety Hazards. What are the exposure levels of hazards and

Main Hazards identified within the refinery complex are 1.Fire Hazard 2.Electrical Hazards

EIA Report

92 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

whether they are Permissible Exposure level (PEL) if these are not within PEL, what measures the company has adopted to keep them within PEL. So that health of the workers can be preserved.

3.Thermal Hazard 4.Occupational Hazards etc., Environmental monitoring is being carried out within the refinery shop floors and the parameters are mainly VOCs, H2S, CO and HCs . In addition to the above Noise and illumination levels are also being carried out on regular intervals. Same will be continued even after expansion. Occupational Hazardous Toxic gas monitoring data are attached as Annexure 22. For other prominent toxic gas hazards (NH3, Cl2, SO2), gas detectors are installed in the production blocks for early detection of any abnormal / accidental presence with audio-visual alarming systems. For rest of the chemical hazards, any exposure and subsequent adverse health effect is assessed through periodical medical check-up of employees as per the unit wise chemical hazards identification. The test consists of Blood test, urine test, PFT, KFT, urine phenol etc. The details unit wise chemicals /hazards with possible health risk and prescribed test for periodical Medical check-ups are enclosed as Annexure 23.

iv. Annual report of health status of workers with special reference to Occupational Health and Safety

Periodic medical examination is the same as the pre-employment screening and may be modified according to current conditions, such as changes in the employee's symptoms, site hazards or exposures. Medical reports of few Employees of IOCL Paradip Refinery are attached as Annexure 15.

9 Corporate Environment Policy i. Does the company have a well laid

down Environmental Policy approved by its Board of Directors? If so, it may be detailed in the EIA report

Yes, the company have a well laid down Environmental Policy approved by its Board of Directors.

M/s. IOCL, PDR, Environment, Health & Safety Policy (EHS) provided in Chapter 10, Section 10.9 of EIA report.

ii. Does the Environment Policy prescribe for standard operating process/procedures to bring into focus any infringement/ deviation/ violation of the environemnt or forest norms/ conditions? If so, it may be detailed in the EIA

Yes A dedicated Environmental Management Cell (EMC) will be in force to bring into focus of any infringement/ deviation/ violation of the environemnt. Details provided in Chapter 10, Section 10.8 of EIA report.

iii. What is the hierarchical system or Administrative order of the company to deal with the environmental issues and for ensuring compliance with the environmental clearance conditions? Details of this system may be given.

Hierarchical system or Administrative order of the company to deal with the environmental issues and for ensuring compliance is provided in Chapter 10, Section 10.3 of EIA report.

EIA Report

93 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

iv. Does the company have system of reporting of non-compliances/ violations of environemntal norms to the Board of Directors of the company and/or Stakeholders or stakeholders at large? This reporting mechanism shall be detailed in the EIA report

System of reporting of non-compliances/ violations of environemntal norms & the Board Hierarchical system or Administrative order of the company to deal with the environmental issues and for ensuring compliance is provided in Reporting mechanism detailed in Chapter 10, Section 10.3 of EIA report.

Daily report signed by Unit Head to Head Quarter on compliance to the HSE parameters are enclosed in Annexure-21

10 Details regarding infrastructure facilities such as sanitation, fuel, restroom etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

The site layout indicating all the facilities is enclosed as Annexure 6.

Infrastructure facilities such as sanitation, restroom etc. shall be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

11 Enterprise Social Commitment (ESC) i. Adequate funds (at least 2.5% of

the project cost) shall be earmarked towards the Enterprise Social Commitment based on public Hearing issues and item-wise details along with the bound action plan shall be included. Socio-Economic development activities need to be elaborated upon.

As per OM F. No: 22-65/2017-IA.III dated 1st May 2018 M/s IOCL will Allocate 0.125% of the project cost (11783 Crores) towards CER i.e. 0.125% of 11783 Crores = 14.72Crores

As per CEPI compliance for SPA 1.5 times of slab to be allotted(1.5 * 14.72)=22.093 Crores

12 Any litigation pending against the project and/ or any direction/ order passed by any Court of Law against the project, if so, details thereof shall also be included. Has the unit received any notice under the section 5 of Environment (Protection) Act, 1986 or relevant Sections of Air and Water Acts? If so, details thereof and compliance /ATR to the notice(s) and

No litigation and the affidavit is attached as Annexure

EIA Report

94 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

present status of the case. 13 A tabular chart with index for point

wise compliance of above TOR Point wise ToR compliance is provided in provided in Chapter 1 & Section 1.8 of EIA Report.

SPECIFIC TERMS OF REFERENCE FOR EIA STUDIES FOR PETRO- CHEMICAL COMPLEXES (INDUSTRIES BASED ON PROCESSING OF

PETROLEUMFRACTIONS&NATURALGASAND/ORREFORMINGTO AROMATICS)

1

Details on requirement of raw

material (naphtha /gas

feedstock), its source of supply

and storage at the plant.

S. No.

Raw

Material/

Fuel

Quantity Unit Source Modeof

Transport

Mode of

storage

Storage

capacity

1 Reformate 310000 Kg/h Internal Pipeline Tanks 15000 m3

2 Hydrogen 651 (PX) +

31 (PTA) Kg/h

Internal Pipeline No storage -

3 Paraxylene 97200 Kg/h Internal Pipeline Tanks 2x 9730 m3

4 FG/NG 374 KTPA Internal Pipeline No storage -

Further details of raw material and product given in Chapter 2, Section 2.7.4.2 of EIA report.

2 Complete process flow diagram for all products with material balance.

Complete process flow diagram for PX and PTA unit with material balance given in Chapter 2, Section 2.7.4.2.

3 Brief description of equipments for various process (cracker, separation, polymerization etc)

Brief description of equipments for various process for PX and PTA is given in Chapter 2, Section 2.7.4and Section 2.7.5

4

Details of proposed source-specific pollution control schemes and equipments to meet the national standards

S.N

o Stack details

Pollution control scheme

1. Tatory Furnace Installation of low NOx burners in all the furnaces and

boilers Adequate stack height APH will be provided

2. ISOMAR Furnace

3. XFU 1

4. XFU 2

5. Utility Boiler – 5 (Standby)*

6. Flare Tall flare stack for better dispersion of flue gases.

Storage vents:

7. Toluene day tank- 045-TK-001A Installation of floating roof with double seals for

EIA Report

95 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

8. Toluene day tank- 045-TK-001B reduction of fugitive emissions

Provision of mechanical seals in all the hydrocarbon pumps for reduction of fugitive emissions.

All the proposed tanks are of Internal floating roof type minimizing the fugitive emissions in comparison to External floating roof tanks

All the tanks will be under Nitrogen blanketing

9. Plant inventory tank- 044-TK-001

10. Paraxylene day tank- 049-TK-001 A

11. Paraxylene day tank- 049-TK-001 B

12. Desorbent storage tanks-049-TK-002

13. Plant inventory storage tanks- 049-TK-003

14. Aromatic tank-048-TK-001

15. Light reformate storage tank-048-TK-002

16. Isomer Regeneration Vent

Further details are given in Chapter 10, Section 10.5and Section 10.6

5

Details on VOC emission

control system from vents,

stacks, fugitive emissions and

flare management, etc.

Installation of floating roof with double seals for reduction of fugitive emissions

Provision of mechanical seals in all the hydrocarbon pumps for reduction of fugitive emissions All the proposed tanks are of Internal floating roof type minimizing the fugitive emissions in comparison to External

floating roof tanks All the tanks will be under Nitrogen blanketing Primary as well as secondary sealsfor all storage tanks will be provided. LDAR program will be done frequently to identify any leaksresulting in fugitive emissions. Adequate water sprinkling will bedone to reduce road dust due tovehicular movement. Details on Fire Protection Management enclosed as Annexure17 Flare Management system is enclosed as Annexure 31.

6 Details on proposed LDAR protocol LDAR monitoring is done by third party in every quarter and the LDAR report taken is enclosed as Annexure 16

7

Ambient air quality should

include hydrocarbon (methane

and non-methane), VOC and

VCM (if applicable).

Raw data of all AAQ measurement is provided as Annexure 13

AAQ locations detail is provided in the Chapter 3, Section 3.7 and monitoring results include hydrocarbon (methane and non-methane), VOC are provided in the Chapter 3, Section 3.7, Table 3-10 of EIA report.

8

Action plan to meet the standard prescribed under EPA for petro chemical complex

APC Measures Installation of low NOx burners in all the furnaces and boilers Adequate stack height of maximum 81.1m will be provided in XFU-1 Air pre heater(APH) along with balance draft (ID fan & FD fan) will be provided as per the furnaces duties. Tall flare stack for better dispersion of flue gases of stack height 140m will be provided. Installation of floating roof with double seals for reduction of fugitive

EIA Report

96 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

emissions Provision of mechanical seals in all the hydrocarbon pumps for reduction of fugitive emissions All the proposed tanks are of Internal floating roof type minimizing the fugitive emissions in comparison to External

floating roof tanks All the tanks will be under Nitrogen blanketing Water Pollution Control Measures Waste water will be treated in ETP followed by RO and treated effluent will be discharged to deep sea. Solid and Hazardous Waste Disposal. Inorganic waste will be given to authorized OSPCB vendors. Municipal solid waste will be used in the existing organic waste converter and the resultant solid is used as manur Spent Catalyst is being stored in intermediate storage facility (covered warehouse with impervious floor and shed) and

disposal in SLF & Co-processing in cement industry within 90 days as per Hazardous waste authorization from OSPCB.

Adequate number of continues monitoring system will be installed.

9

Risk Assessment & Disaster Management Plan

i. Identification of hazards ii. Consequence Analysis

iii. Measures for mitigation of risk

The Risk Assessment has been carried out by using the PHAST software. Risk Assessment report and is attached as Annexure 10 and the Disaster Management Plan as Annexure 11.

i.Identification of hazards

The procedure for RRA starts with identification of major risk areas are as follows: Toxic chemical storage area Process Plant involving hazardous chemicals

The Major Hazards will be as described below Possibility of injury during chemicals handled, during operations and due to intoxication. Possibilities of fire hazards at transformers, switchgear and other electrical equipment etc.

1.Hazard Identification – Paraxylene

HEALTH ENVIRONMENTAL PHYSICALAcute Toxicity –Inhalation : Category 4 Acute Toxicity -Oral– Category 4 Skin Irritation Category: 2

Aquatic Toxicity : Category- 2 Flammable : Category 3 flammable

STUDY/

HAZARD

STATEMENT

CATEGORY 1 CATEGORY2 CATEGORY3 CATEGORY4 CATEGORY5

EIA Report

97 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

AcuteOral <5mg/kg >5 <50mg/kg >50<300mg/kg >300<2000 >2000<

LD50 Fatalifswallowed Fatalifswallowed Toxic ifswallowed mg/kg 5000mg/kg

Harmfulif May beharmful

swallowed ifswallowed

Acute Dermal < 50 mg/kg > 50 < 200 mg/kg > 200 < 1000 > 1000 < 2000 > 2000 < 5000

LD50 Fatal in contact with Fatal in contact mg/kg mg/kg mg/kg May be

skin with skin Toxic in contact

with skin

Harmful in contact

with skin

harmful in contact

with skin

Acute See footnote

Inhalation below this table

Dust LC50 < 0.05 mg/L > 0.05 < 0.5 mg/L > 0.5 < 1.0 mg/L > 1.0 < 5 mg/L

Gases LC50 < 100 ppm/V > 100 < 500 ppm/V > 500 < 2500 >2500 < 20000

Vapours LC50 <0.5 mg/L

Fatal if inhaled

>0.5 < 2.0 mg/L

Fatal if inhaled

ppm/V

> 2.0 < 10 mg/L

ppm/V

> 10 < 20 mg/L

Toxic if inhaled Harmful if inhaled

Flammable

liquids

Flash point < 23

degrees C and initial

Flash point < 23

degrees C and

Flash point > 23

degrees C< 60

Flash point > 60

degrees C < 93

Not Applicable

boiling point < 35 initial boiling point degrees C. degrees C.

degrees C. Extremely

flammable liquid

and vapour

> 35 degrees C.

Highly flammable

liquid and vapour

Flammable liquid

and vapour

Combustible liquid

STUDY/ HAZARD

STATEMENT

CATEGORY 1 CATEGORY 2 CATEGORY 3

Eye Irritation Effects on the cornea, iris or conjunctiva that are not expected to reverse or that have not fully reversed within 21 days. Causes severe eye damage.

2A: Effects on the cornea, iris or conjunctiva that fully reverse within 21 days. Causes severe eye irritation. 2B : Effects on the cornea, iris or conjunctiva that fully reverse within 7 days. Causes eye irritation.

Not applicable

Skin Irritation Destruction of skin tissue, with sub categorization based on exposure of

Mean value of >2.3 > 4.0 for erythema / eschar or edema in at least 2 of 3

Mean value of >1.5 < 2.3 for erythema / eschar or edema in

EIA Report

98 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

up to 3 minutes (A), 1 hour (B), or 4 hours (C). Causes severe skin burns and eye damage.

tested animals from gradings at 24, 48, and 72 hours (or on 3 consecutive days after onset if reactions are delayed); inflammation that persists to end of the(normally 14-day) observation period. Causes skin irritation.

at least 2 of 3 tested animals from gradings at 24, 48, and 72 hours (or on 3 consecutive days after onset if reactions are delayed). Causes mild skin irritation.

Environment: Acute Toxicity Category

96 hr LC50 (fish) <1 mg/L 48 hr EC50 (crustacea) < 1 mg/L, 72/96 hr ErC50 (aquatic plants) < 1 mg/L Very toxic to aquatic life

96 hr LC50 (fish) >1< 10 mg/L 48 hr EC50 (crustacea) >1< 10 mg/L 72/96 hr ErC50 (aquatic plants) >1< 10 mg/L Toxic to aquatic life

96 hr LC50 (fish) >10< 100 mg/L 48 hr EC50 (crustacea) >10< 100 mg/L 72/96 hr ErC50 (aquatic plants) >10< 100 mg/L Harmful to aquatic life

Flammable Aerosol

Extremely flammable aerosol Flammable aerosol Not Applicable

Flammable solidsUsing the burning rate test, substances or mixtures other than metal powders: (a) wetted zone does not stop fire and (b) burning time < 45 seconds or burning rate > 2.2 mm/second Using the burning rate test, metal powders that have burning time < 5 minutes Flammable solid

Using the burning rate test, substances or mixtures other than metal powders:(a) wetted zone does not stop fire for at least 4 minutes and (b) burning time < 45 seconds or burning rate > 2.2 mm/second Using the burning rate test, metal powders that have burning time > 5 < 10 minutes Flammable solid

Not Applicable

Flammable gases Gases, which at 20 degrees C and a standard pressure of 101.3 kPA: are ignitable when in a mixture of 13% or less by volume in air; or have a flammable range with air of at least 12 percentage points regardless of the lower flammable limit. Extremely flammable gas

Gases, other than those of category 1, which, at 20 degrees C and a standard pressure of 101.3 kPA, have a flammable range while mixed in air. Flammable gas

Not Applicable

Hazard Ratings

NFPA HAZARD CODES RATING SYSTEM Health : 2 0 – No Hazard

EIA Report

99 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Flammability : 3 1 – Slight Hazard Reactivity : 0 2 – Moderate Hazard

3 – Serious Hazard 4 – Severe Hazard

SKINCONTACT SKINABSORPTION EYECONTACT INHALATION INGESTION

Yes Yes Yes Yes Yes

2.Hazard Identification – Purified Terephthalic Acid Terephthalic Acid is a sand-like white powder. It is used as a reagent to neutralize alkali in wool, as an additive to

poultry feeds, and to increase the effectiveness of certain antibiotics.

The following acute (short-term) health effects may occur immediately or shortly after exposure to Terephthalic Acid:

Contact can irritate the skin and eyes. Breathing Terephthalic Acid can irritate the nose, throat and lungs causing coughing, wheezing and/or

shortness of breath.

Chronic Health Effects Cancer Hazard Repeated exposure to Terephthalic Acid may affect the kidneys.

Improper use of respirators is dangerous

Fire Hazards Terephthalic Acid may burn, but does not readily ignite. Use dry chemical, CO2, water spray, alcohol or polymer foam extinguishers. Poisonous gases are produced in fire.

HAZARDRATING NFPA

Flammability 1

Reactivity 0

HazardRatingKey:0=minimal;1=slight;2=moderate;3=serious; 4=severe

ii.Consequence AnalysisThe Risk Assessment has been carried out by using the PHAST software. Consequence Analysis of the Risk Assessment is attached as Annexure 10 - in the below following APPENDIX's

EIA Report

100 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

APPENDIX 1 – PTA – VAPOUR CLOUD DISPERSION – CONSEQUENCE ANALYSIS APPENDIX 2 – PTA – FLASH FIRE – CONSEQUENCE ANALYSIS APPENDIX 3 – PTA – JET FIRE – CONSEQUENCE ANALYSIS APPENDIX 5 – PTA – POOL FIRE – CONSEQUENCE ANALYSIS APPENDIX 8 – PX – VAPOUR CLOUD DISPERSION – CONSEQUENCE ANALYSIS APPENDIX 9 – PX – FLASH FIRE – CONSEQUENCE ANALYSIS APPENDIX 10 – PX – JET FIRE – CONSEQUENCE ANALYSIS APPENDIX 12 – PX – POOL FIRE – CONSEQUENCE ANALYSIS

iii.Measures for mitigation of risk

Following are the proposed safety measures in the plant. Emergency isolation valves are to be provided/online monitoring via DCS PLC monitoring that will closely

monitor the process flow and parameters in a safe place and auto mode through gas/fire detector system. Passive fire protection such as fire proofing shall be recommended.

Appropriate detection measures such as fire and gas detectors are recommended and the same to be deep-rooted throughout the plant area.

EIA Report

101 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CHAPTER 2

PROJECT DESCRIPTION

EIA Report

102 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2 PROJECT DESCRIPTION

2.1 Project Description

Indian Oil Corporation Limited (IOCL) has set up grass root refinery at Paradip with a crude

processing capacity of 15.0 MMTPA. The 15.0 MMTPA Paradip Refinery Project (PDRP) has

commissioned in Fuel- Refinery mode. The original configuration of PDRP included production

of Petrochemical products, viz. Polypropylene (PP), Paraxylene (PX) and Styrene Monomer

(SM) based on Refinery streams, in addition to fuel products. Considering the encouraging

demand growth of Purified Terephthalic Acid (PTA), IOCL planned to install Integrated

Paraxylene (PX) Units of 0.8 MMTPA and PTA Units of 1.2 MMTPA capacity at Paradip and

associated utilities and offsite facilities at Paradip Refinery.

Paradip Refinery ventured into Petrochemical segment with inclusion of 0.680 MMTPA capacity

Polypropylene (PP) Plant, 332 KT MEG plant and the proposed 1.2 MMTPA capacity Purified

Terephthalic Acid (PTA) plant.

PTA is a non-hazardous, solid white powder, which is the preferred raw material and the basic

building block to produce Polyester Staple Fibre (PSF), Polyester Filament Yarn (PFY), bottle

and industrial grade polyester resin, polyester chips and so on. PSF and PFY are substitutes for

natural cotton and widely used for production of textiles and garments. Eastern India does not

have any economic size of PSF, PFY or PET resin plants. The first PTA plant at IOCL Paradip

can provide steady supply of feedstock PTA to PSF, PYF and PET resin plants. The polyester

resins/chips will further have processed to produce audio/ video tapes, x-ray films, photographic

films, tapes, aseptic bottles for packing mineral water, carbonated drinks, vegetable oil,

cosmetics, toiletries, tea, coffee etc. Thus using PTA from Paradip refinery plant at Odisha, a

number of secondary and tertiary downstream industries could be set-up by entrepreneurs who

could bring large investment to the state of Odisha and to Eastern India as a whole. This in turn

would also help in generating larger employment potential in the region.

Monoethylene Glycol (MEG) plant is also being set-up at Paradip Refinery and used as a raw

material to manufacture items like polyester fibre, textiles. The above PP, MEG and PTA plant

products shall be building blocks for envisaged Plastic & Textile Park respectively in Odisha.

EIA Report

103 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.1.1 Type of Project

M/s Indian Oil Corporation limited, Paradip Refinery proposes “Integrated Para-Xylene &

Purified Terephthalic Acid (PX-PTA) Project at IOCL Paradip Refinery & Petrochemical

Complex, Paradip, Odisha. The Project is under Schedule 5 (c) - “Petro-chemical complexes

(industries based on processing of petroleum fractions & natural gas and/or reforming to

aromatics” Category A, since all the projects under this schedule falls under “A” category.

2.2 Need of the project

The 15.0 MMTPA Paradip Refinery Project (PDRP) had commissioned in Fuel Refinery mode.

The original configuration of PDRP included production of Petrochemical products, viz.

Polypropylene (PP), Para-xylene (PX) and Styrene Monomer (SM) based on Refinery streams, in

addition to fuel products. Considering the encouraging demand growth of Purified Terephthalic

Acid (PTA), feasibility study had carried for Integrated PX and PTA Units of 1.2 MMTPA

capacity each at Paradip. As per Market Report, there is a deficit of about 2.2 MMTPA PTA in

India by 2024. So in order to meet the market potential IOCL proposed the above project.

2.3 Site Location

The existing complex is located at Abhaychandrapur village, Jagatsinghpur District, Odisha

State. The site is located 3.6 Km from Paradip city towards NNE. Index map of the project site is

given in Figure 2-1. Base map showing area within 15Km, 10Km (Figure 2-4), 5Km (Figure

2-3) and 1 Km (Figure 2-2). Geographical coordinates of the project site given below in Table

2-1. Project Site Layout is given in Figure 2-19.

Table 2-1Geographical coordinates of the project site

S. No Location Latitude (N) Longitude (E)

South Block

1 Site Center 1 20°14'52.12"N 86°35'45.19"E

2 A 86°34'48.89''N 20°15'57.9''E

3 B 86°35'6.09''N 20°15'47.51''E

4 C 86°35'5.94''N 20°15'44.78''E

5 D 86°35'10.39''N 20°15'41''E

EIA Report

104 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No Location Latitude (N) Longitude (E)

6 E 86°35'11.1''N 20°15'39.42''E

7 F 86°35'20.39''N 20°15'34.84''E

8 G 86°35'20.39''N 20°15'34.84''E

9 H 86°35'40.87''N 20°15'23.81''E

10 I 86°35'36.28''N 20°15'26.48''E

11 J 86°36'4.59''N 20°15'0.52''E

12 K 86°36'8.38''N 20°15'0.39''E

13 L 86°36'31.25''N 20°14'49.62''E

14 M 86°36'37.13''N 20°14'44.33''E

15 N 86°36'37.13''N 20°14'44.33''E

16 O 86°36'48.89''N 20°14'42.95''E

17 P 86°36'53.57''N 20°14'43.04''E

18 Q 86°37'1.45''N 20°14'43.51''E

19 R 86°37'5.97''N 20°14'39.63''E

20 S 86°37'5.97''N 20°14'39.63''E

21 T 86°37'5.97''N 20°14'39.63''E

22 U 86°37'0.63''N 20°14'33.97''E

23 V 86°37'0.63''N 20°14'33.97''E

24 W 86°36'47.53''N 20°14'32.75''E

25 X 86°36'47.53''N 20°14'32.75''E

26 Y 86°36'47.53''N 20°14'32.75''E

27 Z 86°36'42.42''N 20°14'25.71''E

28 A1 86°36'46.29''N 20°14'20.92''E

29 A2 86°36'46.29''N 20°14'20.92''E

30 A3 86°35'26.24''N 20°14'22.32''E

31 A4 86°35'36.47''N 20°14'27.85''E

32 A5 86°35'32.01''N 20°14'31.65''E

33 A6. 86°35'32.87''N 20°14'50.36''E

34 A7 86°35'32.87''N 20°14'50.36''E

EIA Report

105 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No Location Latitude (N) Longitude (E)

35 A8 86°35'28.02''N 20°15'0.21''E

36 A9 86°35'28.02''N 20°15'0.21''E

37 A10 86°35'24.08''N 20°15'8.26''E

38 A11 86°35'24.08''N 20°15'8.26''E

39 A12 86°35'7.27''N 20°15'18.09''E

40 A13 86°35'5.12''N 20°15'22.23''E

41 A14 86°34'59.65''N 20°15'25.41''E

42 A15 86°34'59.65''N 20°15'25.41''E

43 A16 86°34'59.65''N 20°15'25.41''E

44 A17 86°34'59.65''N 20°15'25.41''E

45 A18 86°34'59.65''N 20°15'25.41''E

46 A19 86°34'54.47''N 20°15'26.98''E

47 A20 86°34'54.47''N 20°15'26.98''E

48 A21 86°34'54.47''N 20°15'26.98''E

49 A22 86°34'51.12''N 20°15'29.76''E

50 A23 86°34'47.82''N 20°15'33.05''E

51 A24 86°34'50.42''N 20°15'34.14''E

52 A25 86°34'52.38''N 20°15'37.72''E

53 A26 86°34'47.4''N 20°15'46.68''E

North Block

54 Site Center 2 20°15'45.49"N 86°36'10.08"E

55 B1 20°15'53.57''N 86°35'16.57''E

56 B2 20°15'58.67''N 86°35'17.54''E

57 B3 20°16'6.96''N 86°35'25.49''E

58 B4 20°16'12.94''N 86°35'27.17''E

59 B5 20°16'15.65''N 86°35'35.22''E

60 B6 20°16'22.8''N 86°35'35.26''E

61 B7 20°16'23.38''N 86°35'40.7''E

62 B8 20°16'26.24''N 86°35'40.7''E

EIA Report

106 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No Location Latitude (N) Longitude (E)

63 B9 20°16'26.39''N 86°35'46.18''E

64 B10 20°16'41.94''N 86°36'1.68''E

65 B11 20°16'42.52''N 86°36'5.11''E

66 B12 20°16'41.26''N 86°36'9.76''E

67 B13 20°16'26.36''N 86°36'16.3''E

68 B14 20°16'15.93''N 86°36'19.35''E

69 B15 20°16'14.24''N 86°36'19.81''E

70 B16 20°16'11.84''N 86°36'20.79''E

71 B17 20°16'9.24''N 86°36'23.2''E

72 B18 20°15'32.44''N 86°36'29.82''E

73 B19 20°15'32.68''N 86°36'46.61''E

74 B20 20°15'10.86''N 86°36'49.06''E

75 B21 20°15'9.51''N 86°37'16.16''E

76 B22 20°16'8.3''N 86°36'24.62''E

77 B23 20°15'2.14''N 86°37'16.09''E

78 B24 20°15'2.14''N 86°37'12.81''E

79 B25 20°14'58.26''N 86°37'11.07''E

80 B26 20°14'58.24''N 86°37'9.38''E

81 B27 20°14'57.3''N 86°37'3.17''E

82 B28 20°14'55.72''N 86°37'1.94''E

83 B29 20°14'52.73''N 86°36'52.53''E

84 B30 20°14'52.66''N 86°36'46.36''E

85 B31 20°15'15.5''N 86°36'11.23''E

86 B32 20°15'25.06''N 86°36'0.19''E

87 B33 20°15'32.76''N 86°35'50.22''E

EIA Report

107 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-1 Index map of the project site

EIA Report

108 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-2 Google image showing salient features within 0- 1 Km radius

EIA Report

109 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-3 Google image showing salient features within 0- 5 Km radius

EIA Report

110 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-4 Google image showing salient features 0- 10 Km Radius Map around the study region

EIA Report

111 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.4 Existing Environmental Setup

The site details and the surrounding features is summarized in Table 2-2

Table 2-2 Existing Environmental Setup of the study region

S. No Particulars Details

1. Geographical Location 20°14'52.12"N, 86°35'45.19"E

2.Elevation above Mean Sea

Level 1-5 m MSL

3. Present Land Use Industrial

4. Nearest Railway Station Description

Distance

(~km) Direction

Paradip 1.75 E

5. Nearest Airport Bhubaneswar Airport 78.1 W

6. Nearest Highway NH5A 3.61 N

7. Nearest habitation /Village Trilochanbur ~0.050 W

Abhaychandpur ~0.143 W

8. Nearest Town Rangiagarh 0.17 NNE

9. Nearest City Bhubaneswar 78.1 W

10. Densely populated area Paradwipagarh 3.71 NNE

11. Inland water bodies Santara River 0.08 NNE

Mahanadi River 6.18 NNE

12.

Reserved Forests/Protected

Forests/Notified Wildlife

Sanctuary/Notified national

parks/Ecologically sensitive

areas

Mangroves are present in Santara creek which

bifurcate the refinery into North & South parts

14. Defense Installations None -- --

15. Archeologically Important

places/sites None -- --

16. Interstate/ National

Boundaries None -- --

17. Hills/Valleys None -- --

EIA Report

112 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 2-3List of major Industries within 10km Radius from the project site

S. No Description Distance (km) Direction

1 Paradip Port Trust 4.98 E

2 PPL Plant 3.17 E

3 IOCL Paradip Marketing Terminal 1.72 E

4 Adani Wilmar Limited (Edible oil) 3.28 NE

5 Arcelor Mittal Nippon Steel India Limited 5.24 NE

6 IFFCO Plant 6.3 NE

2.5 Project Cost

The estimated cost for the proposed projects Integrated Para-Xylene & Purified Terephthalic

Acid (PX-PTA) Project in approx. as Rs.11783 crores.In Form 1 the project cost has given as

913700lacs based on preliminary project feasibility study. Based on the Detailed feasibility

study for the project for the final project estimate is arrived as Rs.11783 crores.

2.6 Proposed Schedule for Approval and Implementation

The Time Schedule for completion of the proposed project is given in Table 2-4

Table 2-4 Time Schedule for completion of the proposed project

S. No. Particulars Time Schedule

1 EC July 2021

2 Consent to Establish from OPCB August 2021

3 Commissioning expected 2024

4 Consent to Operate from OPCB 2024

2.7 Project Details

2.7.1 Existing Facility

Crude Oil is processed in Crude and Vacuum Distillation Unit (CDU/VDU). In CDU, crude

oil is the first heated in a heat exchanger train. It is then heated in a furnace; fractionated in

Crude Distillation Column where physical separation takes place based on boiling point

difference. The top product is LPG (Liquefied Petroleum Gas), which is splitted in C3 and C4

components. C4 component is further processed in Alkylation Unit (Sulphuric Acid as

catalyst) consisting of acid regeneration facility and n-butane Isomerisation, for production of

Alkylate which is used for boosting octane value of Motor Spirit (MS).

EIA Report

113 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

The 2nd fraction from CDU is Naphtha which is hydrotreated and splitted into Light and

Heavy Naphtha. The Heavy Naphtha along with Coker Heavy Naphtha and FCC Heavy

Naphtha is sent to PX Complex for production of Para Xylene. The PX complex comprises of

Naphtha Hydrotreating Unit, Continuous Catalytic Reformer. The Light Naphtha is sent as

feed to Hydrogen Generation Unit/Naphtha Pool.

The 3rd fraction from CDU is Kero Cut, which is treated in ATF Treatment Unit to remove

undesirable sulphurous compounds to produce Superior Kerosene and ATF.

The 4th fraction from CDU is Diesel cut which is hydrotreated in DHDT to produce 10 ppm

‘S’ HSD and 50 ppm ‘S’ HSD.

The reduced crude oil from CDU is processed in Vacuum Distillation Unit (VDU). VGO

(Vacuum Gas Oil) from VDU is hydrotreated in VGOHDT Unit and then processed in FCC

(Fluidised Catalytic Cracker). The VGOHDT Unit processes a VGO feed with around 3%

sulphur and 0.7% Conradson Carbon Residue (CCR) and produces low sulphur and low CCR

feed for FCC through hydrotreatment. FCC produces petrochemical feed stocks such as

Ethylene, FCC LPG containing Propylene, and also FCC Naphtha, FCC Light Cycle Oil

(HSD component) and Clarified Oil, a component routed to (Delayed Coker Unit) DCU or

blended in Internal Fuel Oil. The Hydrogen requirement of DHDT and VGO-HDT unit is

met from its production in Hydrogen Generation Unit (HGU).

Residue from VDU is processed in DCU (Delayed Coker Unit), which is a secondary

processing unit to improve distillate yield besides producing coke. Part residue is used as

High Sulphur Fuel Oil in utility boilers with Flue gas desulphurisation in refinery operations.

Propylene is separated from C3/ C4 stream from FCC to produce Propylene, which is further

processed to produce Polypropylene.

MEG will be produced from ethylene and oxygen. Ethylene is recovered from FCC off gas

via Ethylene Recovery Unit and Oxygen from air through Air Separation Unit.

Gases from cracking units & hydrotreatment units are amine treated and H2S rich gas is

processed in SRU (Sulphur Recovery Units) to produce Sulphur. The Schematic diagram of

Existing Refinery is given in Figure 2-5

EIA Report

114 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-5 Schematic diagram of Existing Refinery

2.7.2 Size & Magnitude of Operation

The size & Magnitude of Operation in terms of existing/approved/proposed units and year of commissioning at IOCL, Paradip is given in Table 2-5

Table 2-5 Existing /Approved/Proposed Units

S. No

Plant / Equipment / Facility Units Existing

Configuration

Proposed

Configuration

Final configuration

after expansion

Remark

1 Crude/ Vacuum Distillation Unit MMTPA 15 - 15

2 Delayed Coking Unit MMTPA 4.1 - 4.1

3 Diesel Hydrotrating Unit MMTPA 5.2 - 5.2

4 VGO Hydrotreatment Unit MMTPA 5.4 - 5.4

5 Fluidised Catalytic Cracking Unit MMTPA 4.2 - 4.2

6 Sulphur Recovery Unit MMTPA

2 x 0.191625, -

2 x 0.191625,

1 TGTU 1 TGTU

6a Standby SRU MMTPA 0.191625 - 0.191625 Upcoming

7 Hydrogen Plant MMTPA 0.07258 - 0.07258

8 Alkylation Unit MMTPA 0.65 - 0.65

9 Polypropylene Unit MMTPA 2 x 0.340 - 2 x 0.340

EIA Report

115 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No

Plant / Equipment / Facility Units Existing

Configuration

Proposed

Configuration

Final configuration

after expansion

Remark

10 Captive Power Plant & Cooling Tower

-

GT with HRSG

UB-5 – 300TPH

GT with HRSG

3 x 102 MW 3 x 102

MW

STG 2 x 30 MW

STG 2 x 30 MW

UB 4 x 300 TPH

UB 5 x 300 TPH

1 UB will be unter PX-PTA project

Standby GT with HRSG 1 x 30 MW

Standby GT with

HRSG 1 x 30 MW

(366MW, 1200 TPH)

(366MW, 1200 TPH)

11 LPG Treater MMTPA 0.21 - 0.21

12 LPG Treater (Cracked LPG) MMTPA 1.85 - 1.85

13 LPG Treater (Coker LPG) MMTPA 0.165 - 0.165

14 ATF (Merox) MMTPA 1.2 - 1.2

15 SWS 1 + SWS II KLPH 227 + 398 =

625 -

227 + 398 = 625

16 ARU KLPH 1353 - 1353

17 Continues Catalytic Reformer MMTPA 3.941 - 3.941

18 Pet Coke Evacuation Through Rapid Railway Loading System (RRLS)

MMTPA 1.3 - 1.3

19 MEG MMTPA 0.332 - 0.332 Ongoing

20 ERU MMTPA 0.18 - 0.18 Ongoing

21 DEG MMTPA 0.024 - 0.024 Ongoing

22 TEG MMTPA 0.001 - 0.001 Ongoing

23 ISOM MMTPA 1.1 - 1.1 Deferred

24 HGU – New MMTPA 2 x 0.060 - 2 x 0.060 Ongoing

25 Kero De Sulfurization Unit MMTPA 0.3 - 0.3 Ongoing

26 Air Separation Unit (ASU) under MEG

MMTPA 0.21 - 0.21 Ongoing

27 IGHDS (Indmax Gasoline Desulphurization)

MMTPA 1.15 - 1.15 Deferred

28

Para – Xylene Complex

MMTPA - 0.8 0.8

(Includes Sulfolane Extraction Unit, BT (Benzene Toluene Fractionation Unit, Tatoray unit, Xylene Fractination Unit (XFU) Parex unit and Isomar Unit

29 PTA (Purified Terephthalic Acid) MMTPA - 1.2 1.2

EIA Report

116 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.7.3 Existing Utilities

Existing utilities of Paradip Refinery is given in the Table 2-6and the storage facility

available in the refinery is given in the

Table 2-7. The Crude Oil and Product Pipelines to South Loading Jetty in listed in Table 2-8

Table 2-6 List of Existing utilities at PDR

S.

No Description Working Standby Total Capacity

1 Gas Turbine Generators

(GTG) 2 1 3 102 MW Each

2 Heat Recovery Steam

Generators (HRSGs) 2 1 3

220 TPH HHP

Steam

3 Steam Turbines

Generators (STGs) 2 - 2 30 MW Each

4 Utility Boilers (UBs) 3 1 4 300 TPH HHP

5 Cooling Tower

CT 1

CT 2

CT 3

CT 4

CT-5

- 4

16000 KLPH

16000 KLPH (PP)

28000 KLPH

44000 KLPH

25200 KLPH

6 DM Water Plant

1 UF - 1 UF = 1170 TPH

5 DM

Trains 5 385 TPH each

7 Air Compressor LP -5

HP - 2 7

13000 Nm3/hr each

250 Nm3/hr Each

8 Nitrogen Generation Plant 1 - 1 14600/16000

Nm3/hr

9 Raw Water Reservoirs 2 - 2 265000 KL Each

10 Storm Water Reservoirs 2 - 2 312000 KL

296000 KL

11 ETP 1 - 1 1580 m3/hr

EIA Report

117 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 2-7 Existing storage tanks

PDR Crude Tanks

Tank Service Type Dia(m)Ht (m)

SFH(m)SFV (m3)

201-Tk-001

Crude Floating

Roof

79 13.61 11.701 55440201-Tk-002 79 13.61 11.726 55387201-Tk-003 79 13.61 11.701 55422201-Tk-004 79 13.61 11.726 55884201-Tk-005 79 13.61 11.623 55999201-Tk-006 79 13.61 11.745 54977201-Tk-007 79 13.61 11.716 55341201-Tk-008 79 13.61 11.701 55523201-Tk-009 79 13.61 11.711 55377201-Tk-010 79 13.61 11.726 55216201-Tk-011 79 13.61 11.708 55216201-Tk-012 79 13.61 11.708 55216 201-Tk-013 79 13.61 11.708 55216201-Tk-014 79 13.61 11.708 55216

PDR Product Tanks and Bullets

Tank Product Type Dia (m) Ht (m) SFH (m)

SFV (m3)

1 205-Tk-004

Naphtha Flaoting

Roof

58 16 14.024 37523

2 205-Tk-005 58 16 14.014 37496

3 205-Tk-006 58 16 14.004 37530

4 205-Tk-007 58 16 14.019 37544

5 205-Tk-008

MS Flaoting

Roof

40.7 15.5 13.501 17837

6 205-Tk-011 50.5 16 14.019 28534

7 205-Tk-012 50.5 16 14.014 28562

8 205-Tk-013 50.5 16 14.014 28580

9 205-Tk-014 50.5 16 14.032 28613

10 205-Tk-019

HSD Flaoting

Roof

46.3 16 14.011 23877

11 205-Tk-022 52.3 16 13.999 30621

12 205-Tk-023 52.3 16 14.009 30634

13 205-Tk-024 52.3 16 13.99 30478

14 205-Tk-025 52.3 16 13.99 30791

15 205-Tk-026 52.3 16 13.99 30692

16 205-Tk-027 52.3 16 14.009 30616

17 205-Tk-015 Dual Purpose

Kero (DPK)

CRIF

49.5 17 13.726 26912

18 205-Tk-016 49.5 17 13.717 26913

19 205-Tk-017 49.5 17 13.721 26913

20 205-Tk-018 49.5 17 13.737 26913

21 205-Tk-038 SKO Flaoting

Roof 49.5 15.5 13.506 26482

22 205-Tk-051 Sulphur Coned 15.3 13 11.887 2197

EIA Report

118 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Tank Product Type Dia (m) Ht (m) SFH (m)

SFV (m3)

23 205-Tk-052 Roof 15.3 13 11.956 2197

24 205-Tk-053 15.3 13 11.977 2197

25 203-Tk-017 PCK Floating

Roof 35 15.3 13.31 13022

Bullet Product SFV (m3) Dia (m) Length (m)

1 205-V-003

LPG

2478

6.4 93

2 205-V-004 2474

3 205-V-005 2475

4 205-V-007 2476

5 205-V-008 2474

6 205-V-009 2475

7 205-V-012 2484

8 205-V-013 2478

9 205-V-014 2480

10 205-V-006

PROPYLENE

2475

11 205-V-010 2478

12 205-V-011 2472

13 205-V-015 2486

14 205-V-016 2490

15 205-V-017 2489

PDR-Intermediate Storage Tanks

Tank Service Type Dia (m) Ht (m) SFH (m)

SFV (m3)

1 126-TK-001 FLO Floating

Roof 24 15 13.50 5930

2 203-TK-001 NHT FEED

CRIF; N2 blanket

49.5 17.5 13.37 24682 3 203-TK-002 49.5 17.5 13.37 24986

4 203-TK-005 DHDT FEED

CRIF; N2 blanket

49.5 17.5 13.50 25204 5 203-TK-006 49.5 17.5 14.00 26100 6 203-TK-007

VR Coned Roof 51.1 15.5 13.40 27804

7 203-TK-008 51.1 15.5 13.40 27829 8 203-TK-010 VGO HDT

FEED Coned Roof; N2 blanket

78.2 15.5 13.30 65294 9 203-TK-011 78.2 15.5 13.30 64556

10 203-TK-015 HGU FEED CRIF; N2

blanket 20.2 17.51 13.55 4285

11 203-TK-020 LT.

REFORMATECRIF; N2

blanket35 17.5 14.07 13088

12 203-TK-026 WET SLOPS Coned Roof 20.2 15.5 12.50 4031

13 203-TK-027 LT. DRY SLOPS

Coned Roof 20.2 16.5 13.50 4279

14 203-TK-028 HVY DRY

SLOP Coned Roof 31.9 15.5 13.00 10470

15 203-TK-056 CCR FEED CRIF; N2

blanket 20.2 17.5 13.77 4318

EIA Report

119 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

PDR-Intermediate Storage Tanks

Tank Service Type Dia (m) Ht (m) SFH (m)

SFV (m3)

16 203-TK-042 ALKYLATE Floating

Roof33.5 16.5 13.40 11468

17 203-TK-048 FCC LCN CRIF; N2

blanket24.7 17.5 13.94 6347

18 203-TK-049 LT. HDT.

NAPHTHA CRIF; N2

blanket 20.2 17.5 13.99 4262

19 105-TK-001 HSFO Coned Roof

30 15 13.00 9154 20 105-TK-002 30 15 13.00 9133 21 105-TK-003 30 15 13.00 9108 22 110-TK-001 GTG

NAPHTHA CRIF

22.6 17.5 14.18 5618 23 110-TK-002 22.6 17.5 14.18 5616 24 110-TK-004

GTG HSD Floating

Roof 22.6 16.5 14.18 5635

25 110-TK-005 22.6 16.5 14.18 5641 26 124-TK-001

IFO Floating

Roof 30 30 11.75 8819

27 124-TK-002 30 15 11.75 8819 28 190-TK-855

HSD DAY TANK

Fixed cum floating roof

12 15 11.00 1074 29 190-TK-856 12 15 11.00 1074 30 190-TK-857 12 15 11.00 1074 31 190-TK-858 12 15 11.00 1074 32 190-TK-851 HSFO DAY

TANK Fixed roof

11 14.3 12.40 1401 33 190-TK-852 11 14.3 12.30 1392 34 190-TK-853 NAPHTHA

DAY TANK Fixed cum

floating roof 12 15 11.30 1073.5

35 190-TK-854 12 15 11.30 1073.5 36 230-TK-010 ETP SLOP

OIL TANK Fixed roof

15.3 12.4 11.67 2137 37 230-TK-011 15.3 12.4 11.67 2137

PDR-Alkylation and Hydrogen Bullets Tank Service SFV (m3) Dia (m) Length (m)

1 203-V-003 nC4, iC4

2262 6.4 85 2 203-V-004 2310

3 203-V-005 2272

SFV (m3) Dia (m) Length (m) 1 203-V-027A

H2 2262

4 20 2 203-V-027B 2310 3 203-V-027C 2272

EIA Report

120 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 2-8 Pipelines to South Loading Jetty

S. No Service Size

(inches)

Flow Rate

(KLPH)

Design Pressure

(kg/Cm2)

1 HSD (Export) 30 3930 36.67

2 HSD (Domestic) 30 3930 36.67

3 DPK (ATF) 30 3930 34.23

4 MS (Premium) 30 3930 3994

5 MS (Regular) 26 2900 37.42

6 Naphtha 34 5360 36.45

7 Propylene 10 360 46.09

8 Propylene (Vapor return to

Refinery) 8 2996 37.41

9 Utilities Line (Instrument Air,

Nitrogen and Service Water) 4 - -

10 Crude 38 4000 27.2

11 Propane 16 600 TPH -

12 Butane 16 600 TPH -

13 MEG 20 1100 -

Table 2-9 Pipeline crossing Santra Creek for the Proposed PX PTA project

S. No Service Size (inches)

1 Fire Water 24

2 Cooling tower make up 20

3 DM Water 12

4 Instrument Air 8

5 Plant Air 6

6 Steam Condensate out 8

7 Boiler BlowDown 4

8 BFW(MP) 4

9 MP Steam Export 16

10 HHP Steam 20

EIA Report

121 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No Service Size (inches)

11 Fuel Gas 16

12 Fuel oil 6

13 Closed Blowdown and Hydracarbon slop

14 Hydrogen 3

15 Raffinate 4

16 Reformate 10

2.7.3.1 Existing Gas Monitoring System

Gas detectors are installed at critical locations throughout the plant areas to detect the

presence of flammable/combustible gas or hydrocarbon vapors and toxic gas.

Toxic gas detectors (including but not limited to Cl2) detectors with associated audio-visual

alarms shall be provided:

i) In process / O&U areas where toxic gases are potentially present

ii) In buildings containing or handling toxic gases

iii) In HVAC inlets for buildings in process / O&U areas where toxic gases are

potentially present and in adjacent units.

The Gas Detection System (GDS) will sound sounders and flash either yellow or blue

beacons automatically depending on the type of leakage (flammable / toxic), the annunciation

shall be unit wide based on any detector in alarm (i.e. lool). The Lower Explosion limit of

various Gas detector is given in Table 2-10

Table 2-10 Limits of Gas Detector Type

Gas Detector Type Alarm Points

Min LEL Max. LEL

Point Type Combustible 20% 40%

HC Detectors 1 10%

H2S Detectors 10 15

Chlorine 1 3

CO 50 PPM 300 PPM

SO2 2 PPM 5 PPM

NH3 25 35

EIA Report

122 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

O2 Depletion <19% --

2.7.3.2 Existing Fire protection system

Fire hydrant pipelines used to supply water under pressure to various places within Terminal

and parking area.

The fire hydrant system consists of:

(a) Double Fire hydrant posts and monitors

(b) Diesel driven fire water pumps

(c) Fire water storage tanks

The fire hydrant mains cover the entire Terminal. The number of fire monitors and hydrant

points provided are given in Table 2-11

Table 2-11 List of firefighting facility available

Item Terminal Facilities

Fire Tenders/ Fire Fighting Engines 4 FT + 2 FN + 1 DCP Tender + 1 HP +

1 ERT

Water Storage Capacity 28000 KL

Fire Hoses 400

Jet/ Fog/ Spray Nozzles 321

Foam branch -

Jumbo jet Nozzles -

Foam Compound -

Clean Agent Fire Extinguishers:2 Kg,4 Kg, 6 Kg & 10 Kg capacity 2.5 Kgs

-

EIA Report

123 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-6 Fire Water Network South

EIA Report

124 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-7 Fire Water Network in North

EIA Report

125 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.7.4 Proposed Facility

2.7.4.1 Technology & Process Description

Feed for the proposed PX-PTA plant will be Reformate, which is produced by processing

Naphtha in CCRU. Reformate will be processed in the PX plant to produce PX, which will

further be processed in the PTA plant for production of PTA.The Overall Process flow diagram

of PX-PTA unit is given in Figure 2-8

2.7.4.1.1 Paraxylene (PX)

Reformate is utilized for production of MS as well as PX. By-products of the PX plant viz.

Raffinate and Heavy Aromatics will be blend in MS/Naphtha pools. The other product, Toluene

from PX plant will be sold to merchants. The process diagram of PX unit is given in Figure 2-9

Fuel gas from the PX complex will be routed to the refinery Fuel Gas header

Paraxylene Unit has a capacity of 0.8 MMTPA. Brief description of the unit is given below:

Paraxylene Unit consists of the following blocks:

Xylene Fractionation Unit

Sulfolane Unit (Extractive Distillation)

Benzene-Toluene Fractionation Unit

Tatoray Unit

Parex Unit

Isomar Unit

a) Xylenes Fractionation Unit

Feed to the Xylenes Fractionation Unit emanates from three sources, coming in the form of

Debutanizer bottoms from the CCR Platforming Unit, Toluene Column bottoms from the

Benzene-Toluene Fractionation Unit and Deheptanizer bottoms from the Isomar Unit.

The Plat forming Unit’s Debutanizer bottoms is feed to the Reformate Splitter. The Light

Reformate, i.e. the Reformate Splitter overhead liquid product, is pumped to the Feed Surge

Drumin the ED Sulfolane Unit. The Reformate Splitter net bottoms, consisting of C8+aromatics,

EIA Report

126 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

are heated in the Clay Treater Feed Heater prior to entering the Clay Treaters. The Clay Treaters

are responsible for removing olefinic material from the feed to the Xylene Columns. The

effluent flow from the Clay Treaters is divided into two equally flowing streams; each acting as

a feed to one of the two Xylene Columns. The flow rate of each of these two streams is reset by

the level in the bottom of the Reformate Splitter.

In order to mitigate flare loads, this unit design employs the use of two identical Xylene

Columns with identical overhead systems. In addition to receiving an equal amount of

Reformate Splitter bottoms feed, each Xylene Column also receives an equal amount of

Deheptanizer bottoms feed and an equal amount of Toluene Column bottoms feed, both of

which consist primarily of mixed xylenes. The Deheptanizer bottoms are fed to the Xylene

Column at the upper feed tray location. The Toluene Column bottoms combine with the

Reformate Splitter bottoms prior to entering the Xylene Column at the lower feed tray location.

Overhead vapors from Xylene Column No 1 are condensed in the hot (shell) sides of Parex

Raffinate Column Reboiler A, Parex Extract Column Reboiler A, and Isomar Deheptanizer

Reboiler A. Similarly, overhead vapors from Xylene Column No 2 are condensed in the hot

(shell) sides of Parex Raffinate Column Reboiler B, Parex Extract Column Reboiler B, and

Isomar Deheptanizer Reboiler B. Condensed material from each train is pressured up to each

system’s respective Xylene Column Receiver. From here, the net overhead liquid is pumped

from each receiver to one of two Parex Feed Surge Drums.Each surge drum effluent stream is

fed to the Parex Unit by two pumps operating in parallel. Prior to feeding the Parex Unit,

however, the pump discharge streams combine into a single stream that is cooled by the

Deheptanizer Feed-Parex Feed Exchanger in the Isomar Unit.

Each Xylene Column employs the use of two fired heaters operating in parallel to reboil the

circulating bottoms material. There is a large degree of heat integration involved with the

Xylene Column circulating bottoms systems. During normal operation, the circulating bottoms

from Xylene Column No 1 are used as heat transfer media for the Parex Desorbent Rerun

Column Reboiler, Clay Treater Feed Heater, Heavy Aromatics Column Reboiler, and Parex

Raffinate Column Auxiliary Reboiler A. Meanwhile, the circulating bottoms from Xylene

Column No2 are used as heat transfer media for the Tatoray Stripper Reboiler and Parex

Raffinate Column Auxiliary Reboiler B. Although this describes the flow scheme during normal

EIA Report

127 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

operation, the circulating bottoms systems were designed such that each train is capable of

providing 100 percent of the duty required by any heat user, with the exception of the Parex

Raffinate Column Auxiliary Reboilers. In the case of these heat users, Auxiliary Reboiler A will

only accommodate flow from train one and Auxiliary Reboiler B will only accommodate flow

from train two.

The Xylene Column net bottoms material is comprised of C9+aromatics.Netbottoms streams

from each Xylene Column combine into a single stream prior to feeding the Heavy Aromatics

Column. Here, the C9 and C10 aromatics are taken overhead, condensed, and pumped to the

Feed Surge Drumin the Tatoray Unit. Overhead vapors from the Heavy Aromatics Column are

condensed both by an air cooler and by the Reformate Splitter Feed Heater, as hell and tube

exchanger responsible for heating the Debutanizer bottoms feed from the Plat forming Unit.

Heavier C11+aromatics are pumped from the bottom of the Heavy Aromatics Column to the

Fuel Oil System.

b) Sulfolane Process Unit (Extractive Distillation)

The Sulfolane process uses extractive distillation to recover high purity aromatics from a light

reformates feed stock.

Feed to the unit is obtained from the overhead of the Reformate Splitter in the Xylenes

Fractionation Unit, and from the bottoms stream of the Stripper in the Isomar Process unit.

Extractive distillation is the method used to separate close-boiling components using a solvent

that alters the volatility between the components. The solvent is generally a polar compound

having a boiling point higher than the mixture. When applied to extractive distillation, the

volatility of the aromatics is depressed relative to the other components in the mixture such that

the non-aromatics can be distilled overhead in the Extractive Distillation Column.

There are two primary columns in the extractive distillation unit, they are the Extractive

Distillation Column and the Recovery Column (or solvent stripper column). Aromatic feed,

typically pre-fractionated, is directed to the Extractive Distillation Column.

It exchanges heat with the lean solvent and enters a central stage of the trayed column. The lean

solvent is introduced near of top of the Extractive Distillation column.

EIA Report

128 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Combining solvent and feed alters the relative volatilities of the components to be separated

because of the non-ideal behavior of the mixture. This is the key to the process. The selectivity

of the solvent renders aromatics relatively less volatile than the non-aromatics.

As the hydrocarbon vapor stream flows up the Extractive Distillation column, counter- current

to the descending solvent, the aromatics are selectively absorbed.

The function of the upper section of the Extractive Distillation Column is to maximize aromatic

recovery. The overhead vaporis non-aromatic and is referred to as the raffinate. These vapors

are condensed and sent to storage. A portion of the raffinate liquid is used as column reflux to

rectify entrained solvent out of the overhead product. Overhead water is collected in the

Extractive Distillation Column Receiver water boot and returned to the column. The Extractive

Distillation Column is reboiled with steam. There is are boiler preheater to recover heat from the

lean solvent to reduce steam consumption in the reboiler.

In the lower section of the Extractive Distillation Column, the non-aromatics are preferentially

stripped out of the liquid and enter the upper portion of the column as a vapor phase due to the

solvents electivity, which has made the saturates relatively more volatile than the aromatics.

Again, because of finite selectivity, some aromatics, primarily benzene, are stripped into the

upper section of the column where they must be re-absorbed. The lower section of the Extractive

Distillation Column serves the function of aromatics purification.

The Extractive Distillation Column bottoms will contain solvent and highly purified aromatics.

This material is sent to the Recovery Column (solvent stripper column). In this column,

aromatics are separated from solvent under vacuum with steam stripping. The overhead aromatic

product, depending on the composition (BorBT) is condensed and sent to storage or to clay

treating prior to product fractionation. A portion of the extract liquid is used as reflux to remove

residual solvent from the extract vapors. The Recovery Column is reboiled with steam. Water is

collected in the Recovery Column Receiver water boot and is directed to the steam generator.

This generator (heated by exchange with the Recovery Column bottoms) produces the stripping

steam that is returned to the bottom of the Recovery Column via the Solvent Regenerator.

Solvent is purified of residual hydrocarbons as it flows down the Recovery Column.At the

bottom of the Recovery Column the solvent is essentially pure Sulfolane with a small amount of

EIA Report

129 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

water. This is then returned to the Extractive Distillation Column as lean solvent. A slip stream

of lean solvent is directed to a Solvent Regenerator to remove any degradation products.

c) Benzene-Toluene Fractionation Unit

The Benzene-Toluene Fractionation Unit consists of two fractionation columns, the Benzene

Column and the Toluene Column, and a set of two Clay Treaters. The purpose of this unit is to

separate a purified benzene product from the C7+ aromatics, as well as separating toluene from

C8+ aromatics so that the toluene can be sent to the Tatoray unit and to gasoline blending and

the C8+ material can feed the Xylene Fractionation Unit. There are three separate feed streams

that enter the Benzene Toluene Fractionation Unit. They consist of the overhead material from

the ED Sulfolane Recovery Column, the overhead material from the Parex Finishing Column,

and the bottoms material from the Tatoray Stripper.

Overhead material from the ED Sulfolane Recovery Column is preheated by the Clay Treater

Charge Exchanger then heated to the Clay Treater process temperature by the Clay Treater

Charge Heater. Feed flows downward through the Clay Treaters where olefins are removed. The

effluent from the Clay Treaters is cooled in the Clay Treater Charge Exchanger before mixing

with overhead material from the Parex Finishing Column and the Stripper Bottoms product from

the Tatoray Unit. The combined feed stream then enters the Benzene Column. The Benzene

Column feed from the Clay Treater Charge Tank contains saturated water, which is removed in

the Benzene Column Receiver.

The Benzene Column produces a side-draw benzene product, which is cooled and sent to

storage. The toluene-rich Benzene Column bottoms product is heat exchanged with the Toluene

liquid from the Toluene Column Receiver and fed the Toluene Column. The Toluene Column

overhead vapor stream is condensed and the net product is sent to the Tatoray Unit and gasoline

blending. The Toluene Column bottoms stream feeds the Xylene Column in the Xylenes

Fractionation Unit.

d) Tatoray Process Unit

The Tatoray Process Unit flow scheme consists of a fixed-bed reactor and a product separation

section. The fresh feed to the Tatoray unit comes from the overhead of the Toluene Column in

the Benzene-Toluene Fractionation Unit and the overhead of the Heavy Aromatics Column in

EIA Report

130 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

the Xylenes Fractionation Unit. Feed is first combined with hydrogen-rich recycle gas in the

Combined Feed Exchanger where it is preheated and vaporized by exchange with the hot reactor

effluent. The feed is heated to reaction temperature in the Charge Heater before entering the

Reactor. Feed flows down-flow over the catalyst bed. There act or effluent is then cooled by

exchange with the combined feed, condensed, and sent the Separator.

Hydrogen-rich recycle gas leaves the top of the Separator and is compressed in the Recycle

Compressor. The recycle gas is mixed with makeup gas from the hydrogen central distribution

system. The combined recycle gas joins the liquid feed upstream of the Combined Feed

Exchanger.

A portion of the gas from the top of the Separator is vented to remove accumulated light ends

from the recycle gas loop. This vent is sent to the fuel gas header.

Liquid from the bottom of the Separator is preheated in the Stripper Feed-Overhead Exchanger

and Stripper Feed-Bottoms Exchanger before entering the Stripper. The light ends and a small

portion of the benzene go overhead from the Stripper and are cooled and separated into gas and

liquid products.

The Stripper Vent Condenser on the Stripper Receiver maximizes benzene recovery. The

Stripper overhead vapor is sent to fuel gas.

The benzene and xylene products, together with the unreacted toluene and C9/C10Aromatics,

come from the bottom of the Stripper, are cooled in the Stripper Feed- Bottoms Exchanger, and

finally go to the Benzene Column in the Benzene-

TolueneFractionationUnit.TheStrippernetoverheadliquidissenttotheIsomarStripperto remove the

light ends.

e) Parex Process Unit

The purpose of the Parex unit is to separate Paraxylene from all other C8 Aromatics. The Parex

process belongs to the UOP family of adsorption separation technologies based on the Sorbex

separation concept.

The mixed Xylenes feed from the Xylene Fractionation Unit is first heated in the Deheptanizer

Feed- Parex Feed exchanger located in the Isomar unit. A temperature controller adjusts the flow

EIA Report

131 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

through the heat exchanger to hold the temperature of the Parex feed at the desired value of 147

ºC.

This unit has two parallel adsorption trains and a common Fractionation Section.

The total feed enters the unit and then splits equally into two streams going to identical adsorbent

trains. The feed then passes through the Feed Filter. The filter, remove any particulate matter that

may damage the rotary valve or plug the adsorbent bed internals. The feed from the feed filter

passes through the feed flow controller and into the Rotary valve. The Rotary Valves control the

flow of feed, Desorbent, Extract and Raffinate streams to and from each set of Adsorbent

Chambers.

The separation takes place in the adsorbent chambers. Each adsorbent chamber is divided into

twelve adsorbent “beds”. Each bed of adsorbent is supported from below by a specialized grid,

which also contains highly engineered flow distributors to inject or withdraw liquid from the

individual adsorbent beds, or redistribute the liquid over the cross-sectional area of the adsorbent

chamber. Each flow distributor is connected to the Rotary valve by a bed line piping.

Each train has 24 adsorbent beds with grids and 24 bed lines connecting the grids to the Rotary

Valve. Due to practical construction considerations, the 24 adsorbent beds are contained in two

adsorption chambers in series with 12 beds in each chamber.

At any given time, only four of the bed lines are active, carrying the net streams into and out of

the adsorbent chamber. The Rotary Valve is used to periodically switch the positions of the

liquid feed and withdrawal points as the composition profile moves down the adsorbent chamber.

Chamber Circulation pumps provide the liquid circulation from the bottom of one adsorbent

chamber to the top of the other.

The dilute extract from the Rotary Valve is heated in the Extract Column Feed- Bottoms

exchanger before feeding the Extract Column. The overhead vapor from the Extract Column is

condensed in the Extract Column Condenser and collected in the Extract Column Receiver,

which floats on the flare header through the Parex Vent Drum.

During normal operation the pressure drop through the Extract Column Condenser, the overhead

vapor line, and the line from the condenser to the receiver will be stable enough that additional

EIA Report

132 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

control of the extract column pressure is not required. A nitrogen purge is provided to the vent

from the receiver to prevent material from returning from the vent to the receiver as the level in

the receiver changes.

The Extract Column Overhead Pumps provide reflux to the top of the column and also the net

overhead liquid, which is sent to the Finishing Column after getting preheated in the Finish

Column Feed-Bottoms exchanger. The Extract Column is reboiled using heat from the Xylene

Column overhead vapors in the Extract Column Reboiler. Desorbent from the Extract Column

Bottoms Pumps is cooled in the Extract Column Feed-Bottoms Exchanger and the Desorbent

Cooler.

A temperature differential transmitter is used between two of the Extract Column trays to

monitor the temperature profile of the column. Adjusting the flow of the net extract stream

enables the control of the composition for the extract.

An on-line analyzer monitors the overhead content of desorbent and helps in monitoring the

desorbent loss with the extract.

The net overhead liquid from the Extract Column is heated in the Finishing Column Feed-

Bottoms exchanger and passes to the Finishing Column. The column is reboiled using

desuperheated MP steam in the Finishing Column Reboiler. The para-xylene product leaves the

Finishing Column Bottoms Pumps under level control in finishing column and is cooled in the

Finishing Column Feed-Bottoms Exchanger, the Para xylene Cooler and the Para xylene Trim

Cooler and is stored in Para xylene day tank.

It would then intermittently be pumped out to Paraxylene product storage tank in offsites through

Paraxylene Transfer Pumps. The overhead vapor from the Finishing Column is condensed in the

Finishing Column Condenser. From the Finishing Column condenser, the liquid flows into the

Finishing Column Receiver.

The Finishing Column Overhead Pumps provide the reflux to the top of the column and also the

net overhead toluene, which is sent to the Benzene Column in the B-T Fractionation Unit.

EIA Report

133 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Similar to the extract column the overhead receiver pressure floats with the relief header and a

nitrogen purge line is provided to the vent line from the receiver to prevent material from

returning from the vent to the receiver as the level in the receiver changes.

The Rotary Valves direct the raffinate from the Adsorbent Chambers to the Raffinate Column

Feed-Bottoms Exchanger where it is heated upstream of the Raffinate Column (049-C-001).

Vapors from the Desorbent Rerun Column are also directed to the feed tray of the Raffinate-

column. The column is reboiled using the Xylene Column overhead vapors in the Raffinate

Column Reboiler and circulating bottoms from Xylene column in the Raffinate Column

Auxiliary Reboiler. The desorbent leaves the Raffinate Column Bottoms Pumps and is cooled in

the Raffinate Column Feed-Bottoms Exchanger and the Desorbent Cooler and is returned to the

Adsorbent Chambers through the Rotary Valve after being filtered in the Desorbent Filter.

The overhead vapor from the Raffinate Column is condensed in the Raffinate Column Condenser

and the liquid is collected in the Raffinate Column Receiver. Any uncondensed vapor leaves the

receiver and is further cooled in the Raffinate Column Vent Condenser and the liquid is collected

in the Raffinate Column Vent Drum, which floats on the Parex Vent Drum. Liquid from the vent

drum runs back to the receiver and the total reflux is provided to the column using the Raffinate

Column Reflux Pumps. Any water collected in the receiver is sent to the wastewater treatment

plant (By others).

A Raffinate side cut is taken from near the top of the column and collected in the Raffinate

Column Sidecut Surge Drum before going to the Isomar Unit.

During operation of the unit the heavy contaminants present in the feed will accumulate in the

desorbent. To prevent this accumulation part of the desorbent leaving the Raffinate column is

directed to Desorbent Rerun Column. The column is reboiled using Circulating bottoms from

Xylene Column in the Desorbent Rerun Column Reboiler The overhead vapors are directed to

the Raffinate column. Heavy contaminants are removed from the bottom of the column.

Bottoms material from the Desorbent Rerun Column is removed on an intermittent basis. The

heavy aromatics stream will be routed to the Heavy Aromatics Column Bottoms Cooler in the

Xylene fractionation unit and then routed to the fuel oil system.

EIA Report

134 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

The Desorbent Rerun Column Bottoms Pumps, which are of proportioning type, withdraw a

fixed quantity of heavy aromatics from the Desorbent rerun column. The Desorbent Rerun

Column bottom level is maintained by regulating the duty of the Desorbent Rerun Column

Reboiler through the LIC/FIC control.

The Desorbent Storage Tank provides the storage capacity for the desorbent makeup. The

desorbent storage tank is an atmospheric tank which is nitrogen blanketed. The makeup

desorbent is routed to the Desorbent Rerun column using the Desorbent Makeup Pump.

A Plant Inventory Storage Tank is provided to store the material in the unit in the event of a

shutdown or a period of maintenance. Desorbent mixed with other process fluids are stored in the

plant inventory tank. This tank is an atmospheric tank that is nitrogen blanketed.

The Parex Sump Tank is provided to collect the material vented and drained from the equipment

during the normal operation and maintenance to conserve the valuable desorbent. The desorbent

sump tank is a horizontal vessel located below grade to facilitate draining of process equipment.

The Parex Sump Tank Pump provides the necessary hydraulic head to move the material in the

sump tank to the plant inventory tank. The Parex Sump Tank Pumpout Cooler cools the material

before being routed to the Plant Inventory Storage Tank.

The Desorbent Pumpout Cooler and Desorbent Pumpout Trim Cooler cools the material from the

Parex Unit sufficiently for storage in an atmospheric tank. This is also used during startup and

commissioning operations.

f) Isomar Process Unit

An Isomar unit is always associated with the recovery of one or more xylene isomers. In this

case the Isomar Unit is combined with the UOP Parex process for recovery of para- xylene.

Fresh mixed xylene feed is first sent to a Xylene Column in the Xylene Fractionation Unit,

which rejects C9+ aromatic components in order to meet feed specifications to the Parex unit.

The Xylene Column overhead, containing less than 500 ppm C9+ aromatics, is then directed to

the Parex unit where para-xylene is recovered. The raffinate from the Parex unit, containing less

than 1 wt% para-xylene, is then sent to the Isomar unit which produces para-xylene from the

EIA Report

135 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

other C8 aromatics. This C8 aromatics stream, Deheptanizer bottoms, is recycled back to the

Xylene Column completing the loop.

The feed to the Isomar unit is first cooled by exchange with the Deheptanizer feed. By lowering

the feed temperature, the duty on the Combined Feed Exchanger increases and the duty on the

Product Condenser is decreased, thus reducing its size. The feed is then combined with

hydrogen-rich recycle gas and make-up gas to replace the small amount of hydrogen consumed

in the Isomar reactor. The combined feed is then vaporized by exchange with reactor effluent in

the Combined Feed Exchanger and then heated to reactor operating temperature in the Charge

Heater. The hot vapor feed is then sent to the Reactor where it is passed radially through a fixed

bed of catalyst. The reactor effluent is cooled by exchange with the combined feed, condensed in

the Product Condenser and then sent to the Separator. To maintain the correct catalyst hydration

level required for optimum catalyst performance, water is injected into the reactor feed upstream

of the Combined Feed Exchanger.

Hydrogen-rich gas is taken off the top of the Separator and recycled back to the Reactor using a

motor driven Recycle Compressor. A small portion of the recycle gas is sometimes purged to

remove accumulated light ends from the recycle gas loop. Liquid from the bottom of the

Separator is heated on its way to the Deheptanizer by two exchangers: The Deheptanizer Feed

Isomar Feed Exchanger, and the Deheptanizer Feed-Parex Feed Exchanger.

The C7- overhead from the Deheptanizer is cooled and separated into gas and liquid products.

The Deheptanizer overhead gas is chilled and separated with the chilled vapor exported to a low

pressure fuel gas system while chilled liquid is returned to the column overhead receiver. The

receiver liquid, along with Tatoray Stripper overhead liquid is sent to the Stripper to remove

water and light hydrocarbons from the overhead product before it is sent to the ED Sulfolane

Unit. The C8+ fraction from the bottom of the Deheptanizer is then recycled back to the Xylene

Column.

2.7.4.1.2 Purified Terephthalic Acid (PTA)

Purified Terephthalic Acid (PTA) Unit has a capacity of 1.2 MMTPA. Brief description of the

unit is given below;

EIA Report

136 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Terephthalic acid is produced by oxidizing para-xylene with air in an acetic acid solvent. The

unique catalyst system contains ionic forms of cobalt, manganese, and bromine. Although other

catalyst systems can be used, they do not provide the same conversion and reaction selectivity.

The reaction releases a large amount of heat, which can be removed by allowing some of the

solvent to boil. Water is a co-product. The process diagram of PTA unit is given in Figure 2-10

and Figure 2-11

Process Reaction: -

PTA Plant consists of the following two section:

TA Slurry Section

Purified Terephthalic Acid Section

a) TA Slurry Section

The Oxidation Plant is designed for continuous operation and consists of five main sections:

Reaction, TA Slurry Crystallisation, TA Solvent Interchange, Catalyst Feed and Solvent

Treatment.

In the Reaction section paraxylene feedstock is mixed with acetic acid solvent and catalyst

solution and reacted with air. The major proportion of the terephthalic acid produced in the

exothermic reaction is precipitated in the reactor to form slurry. The reactor vapours pass

through a two stage rectifier column which allows recovery of acetic acid, and excess reactor

water is withdrawn from the overheads aqueous condensate.

In the TA Crystallisation section the reactor exit slurry is depressurised and cooled in a series of

three crystallising vessels. The precipitated terephthalic acid product is recovered and transferred

directly to the Purification Plant by continuous filtration incorporating Solvent Interchange. A

EIA Report

137 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

proportion of the mother liquor generated in this stage is purged to the Solvent Stripper via the

TA Mother Liquor Filter.

In the Catalyst Feed section, fresh catalyst is imported and the flow adjusted to produce a

catalyst solution for feed to the Reaction Section.

In the Solvent Treatment Section, impure solvent recovered from the Reaction and TA Solvent

Interchange Sections, is processed to remove acetic acid and water from the higher boiling

reaction by-products. The recovered solvent is fractionated to remove low boiling impurities, and

produces clean acetic acid solvent for re-use in the Oxidation Plant. The higher-boiling by-

products are quench cooled in water and the resulting slurry transferred to a TA Residues

Recovery Unit for recovery of catalyst, intermediates and by-products from the residues. The

equipment list of PX process unit in given the Table 2-12

Table 2-12 Equipment List- PX Process Unit

S. No.

Equipment Tag No. Equipment Description

Sulfolane Process Unit (Extractive Distillation)

1 044-P-007A/B Antifoam Injection Pumps

2 044-P-001A/B Charge Pumps

3 044-A-001 Chemical Injection Conservation Vent

4 044-V-004 Ejector Condensate Drum

5 044-C-001 Extractive Distillation Column

6 044-P-003A/B Extractive Distillation Column Bottoms Pumps

7 044-AC-001 Extractive Distillation Column Condenser

8 044-P-005A/B Extractive Distillation Column Overhead Pumps

9 044-P-006A/B Extractive Distillation Column Overhead Water Pumps

10 044-E-004 Extractive Distillation Column Reboiler

11 044-E-003 Extractive Distillation Column Reboiler Preheater

12 044-P-004A/B Extractive Distillation Column Reboiler Pumps

13 044-V-002 Extractive Distillation Column Receiver

14 044-V-001 Feed Surge Drum

15 044-P-012A/B Inventory Transfer Pumps

EIA Report

138 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No.

Equipment Tag No. Equipment Description

16 044-E-001 Lean Solvent - Feed Exchanger

17 044-E-002 Lean Solvent Cooler

18 044-P-010A/B Lean Solvent Pumps

19 044-P-002A/B MEA Injection Pumps

20 044-TK-001 Plant Inventory Tank

21 044-F-001 Plant Inventory Tank Heater

22 044-E-005 Raffinate Cooler

23 044-C-002 Recovery Column

24 044-E-006 Recovery Column Condenser

25 044-EJ-001A/B Recovery Column Ejectors

26 044-P-008A/B Recovery Column Overhead Pumps

27 044-P-009A/B Recovery Column Overhead Water Pumps

28 044-E-007 Recovery Column Reboiler

29 044-V-003 Recovery Column Receiver

30 044-RD-001 A/B Rupture Disc

31 044-RD-002 A/B Rupture Disc

32 044-RD-003 A/B Rupture Disc

33 044-E-011 Solvent Cooler

34 044-V-005 Solvent Regenerator

35 044-E-009 Solvent Regenerator Reboiler

36 044-E-010 Stripping Steam Generator

37 044-V-006 Sulfolane Sump

38 044-P-011A/B Sulfolane Sump Pump

Benzene-Toluene Fractionation Unit (Unit-045)

1 045-P-002A/B Benzene Sidedraw No 1 Pumps

2 045-P-006A/B Benzene Sidedraw No 2 Pumps

3 045-C-001 Benzene-Toluene Column No 1

4 045-P-004A/B Benzene-Toluene Column No 1 Bottoms Pumps

5 045-AC-001 Benzene-Toluene Column No 1 Condenser

EIA Report

139 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No.

Equipment Tag No. Equipment Description

6 045-E-003 Benzene-Toluene Column No 1 Reboiler

7 045-V-002 Benzene-Toluene Column No 1 Receiver

8 045-P-001A/B Benzene-Toluene Column No 1 Reflux Pumps

9 045-C-002 Benzene-Toluene Column No 2

10 045-P-008A/B Benzene-Toluene Column No 2 Bottoms Pumps

11 045-AC-002 Benzene-Toluene Column No 2 Condenser

12 045-E-005 Benzene-Toluene Column No 2 Reboiler

13 045-V-003 Benzene-Toluene Column No 2 Receiver

14 045-P-005A/B Benzene-Toluene Column No 2 Reflux Pumps

15 045-E-001 Clay Treater Charge Exchanger

16 045-E-002 Clay Treater Charge Heater

17 045-V-001A/B Clay Treaters

18 045-TK-001A/B Toluene Day Tanks

19 045-E-004 Toluene Product Cooler

20 045-P-003A/B Toluene Product Pumps

21 045-P-007A/B Toluene Sidedraw Pumps

22 045-P-009A/B Toluene Transfer Pumps

Tatoray Process Unit (Unit-046)

1 046-F-001 Charge Heater

2 046-P-001A/B Charge Pumps

3 046-E-001 Combined Feed Exchanger

4 046-A-001A/B Detonation Arrestor

5 046-EJ-001 Ejector

6 046-V-001 Feed Surge Drum

7 046-AC-001 Product Condenser

8 046-R-001 Reactor

9 046-K-001 Recycle Gas Compressor

10 046-A-002 Refrigerant System

11 046-V-002 Separator

EIA Report

140 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No.

Equipment Tag No. Equipment Description

12 046-C-001 Stripper

13 046-AC-002 Stripper Condenser

14 046-E-002 Stripper Feed-Bottoms Exchanger

15 046-E-004 Stripper Feed-Overhead Exchanger

16 046-P-002A/B Stripper Overhead Pumps

17 046-E-003 Stripper Reboiler

18 046-P-003A/B Stripper Reboiler Pumps

19 046-V-003 Stripper Receiver

20 046-E-005 Stripper Vent Condenser

Xylenes Fractionation Unit (Unit -048)

1 048-AC-002 Aromatics Cooler

2 048-TK-001 Aromatics Tank

3 048-P-015A/B Aromatics Transfer Pumps

4 048-E-012 Aromatics Trim Cooler

5 048-E-008 Clay Treater Feed Heater

6 048-V-003A/B Clay Treaters

7 048-E-003 Gasoline Cooler

8 048-C-004 Heavy Aromatics Column

9 048-P-013A/B Heavy Aromatics Column Bottoms Pumps

10 048-P-014A/B Heavy Aromatics Column Overhead Pumps

11 048-E-011 Heavy Aromatics Column Reboiler

12 048-V-008 Heavy Aromatics Column Receiver

13 048-TK-002 Light Reformate Storage Tank

14 048-P-018A/B Light Reformate Transfer Pumps

15 048-A-001 MP Steam Desuperheater

16 048-P-012A/B Parex Feed Pumps

17 048-V-007 Parex Feed Surge Drum

18 048-F-001 Raffinate Column No 2 Reboiler Heater

19 048-P-009A/B/C Raffinate Column No 2 Reboiler Pumps

EIA Report

141 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No.

Equipment Tag No. Equipment Description

20 048-V-005 Raffinate Column No 2 Reboiler Separator

21 048-P-001A/B Reformate Feed Charge Pumps

22 048-V-001 Reformate Feed Surge Drum

23 048-E-002 Reformate Feed-Combined Gasoline Exchanger

24 048-C-001 Reformate Splitter

25 048-E-004 Reformate Splitter Auxiliary Reboiler

26 048-P-003A/B Reformate Splitter Bottoms Pumps

27 048-AC-001 Reformate Splitter Condenser

28 048-E-001 Reformate Splitter Feed Heater

29 048-P-002A/B Reformate Splitter Gasoline Sidedraw Pumps No 1

30 048-P-004A/B Reformate Splitter Gasoline Sidedraw Pumps No 2

31 048-P-005A/B Reformate Splitter Overhead Pumps

32 048-E-005 Reformate Splitter Reboiler No 1

33 048-E-006 Reformate Splitter Reboiler No 2

34 048-V-002 Reformate Splitter Receiver

35 048-E-007 Reformate Splitter Sidedraw Cooler

36 048-E-013 Reformate Splitter Start-up Reboiler

37 048-C-002 Xylene Column No 1

38 048-P-006A/B Xylene Column No 1 Bottoms Pumps

39 048-P-008A/B Xylene Column No 1 Net Overhead Pumps

40 048-E-009A/B Xylene Column No 1 Reboilers

41 048-V-004 Xylene Column No 1 Receiver

42 048-P-007A/B Xylene Column No 1 Reflux Pumps

43 048-P-016 Xylene Column No 1 Sample Pump

44 048-C-003 Xylene Column No 2

45 048-P-010A/B/C/D Xylene Column No 2 Bottoms Pumps

46 048-E-010 Xylene Column No 2 Feed-Net Overhead Exchanger

47 048-P-011A/B/C Xylene Column No 2 Overhead Pumps

48 048-F-002A/B Xylene Column No 2 Reboiler Heaters

EIA Report

142 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No.

Equipment Tag No. Equipment Description

49 048-V-006 Xylene Column No 2 Receiver

50 048-P-017 Xylene Column No 2 Sample Pump

Parex Process Unit (Unit-049)

1 049-V-001 Adsorbent Chamber No 1

2 049-V-002 Adsorbent Chamber No. 2

3 049-P-001A/B/C Chamber Circulation Pumps

4 049-ME-001 Coplanar Manifolding Indexer

5 049-AC-002 Desorbent Cooler

6 049-A-002 Desorbent Filters

7 049-P-015A/B Desorbent Makeup Pumps

8 049-AC-005 Desorbent Pumpout Cooler

9 049-E-015 Desorbent Pumpout Trim Cooler

10 049-C-005 Desorbent Rerun Column

11 049-E-017 Desorbent Rerun Column Bottoms Cooler

12 049-P-014A/B Desorbent Rerun Column Net Bottoms Pumps

13 049-E-013 Desorbent Rerun Column Reboiler

14 049-TK-002 Desorbent Storage Tank

15 049-P-016A/B Desorbent Transfer Pumps

16 049-EJ-001 Ejector

17 049-C-003 Extract Column

18 049-P-009A/B Extract Column Bottoms Pumps

19 049-E-008 Extract Column Feed-Bottoms Exchanger

20 049-P-008A/B Extract Column Overhead Pumps

21 049-E-009A/B Extract Column Reboiler

22 049-V-008 Extract Column Receiver

23 049-P-018A/B Extract Pumps

24 049-V-011 Extract Surge Drum

25 049-A-001 Feed Filters

26 049-C-004 Finishing Column

EIA Report

143 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No.

Equipment Tag No. Equipment Description

27 049-E-011 Finishing Column Auxiliary Reboiler

28 049-P-012A/B Finishing Column Bottoms Pumps

29 049-AC-003 Finishing Column Condenser

30 049-P-011A/B Finishing Column Overhead Pumps

31 049-E-010 Finishing Column Reboiler

32 049-V-009 Finishing Column Receiver

33 049-V-006 Isomar Feed Surge Drum

34 049-P-002A/B Line Flush Pumps

35 049-AC-004 Paraxylene Cooler

36 049-TK-001 A/B Paraxylene Day Tanks

37 049-F-001A/B Paraxylene Day Tanks Heater

38 049-P-013A/B Paraxylene Transfer Pumps

39 049-E-012 Paraxylene Trim Cooler

40 049-V-010 Parex Sump

41 049-P-017A/B Parex Sump Pump

42 049-E-016 Parex Sump Pumpout Cooler

43 049-V-007 Parex Water Injection Drum

44 049-TK-003 Plant Inventory Storage Tank

45 049-C-001 Raffinate Column No 1

46 049-E-004 Raffinate Column No 1 Reboiler

47 049-C-002 Raffinate Column No 2

48 049-E-005A/B Raffinate Column No 2 Feed-Bottoms Exchanger

49 049-E-007 Raffinate Column No 2 Steam Generator

50 049-P-005A/B Raffinate Column No1 Bottoms Pumps

51 049-E-001A/B Raffinate Column No1 Cold Feed Exchanger

52 049-AC-001 Raffinate Column No1 Condenser

53 049-E-002A/B Raffinate Column No1 Hot Feed Exchanger

54 049-V-003 Raffinate Column No1 Receiver

55 049-P-003A/B Raffinate Column No1 Reflux Pumps

EIA Report

144 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No.

Equipment Tag No. Equipment Description

56 049-P-004A/B Raffinate Column No1 Sidecut Pumps

57 049-E-003 Raffinate Column No1 Vent Condenser

58 049-V-004 Raffinate Column No1 Vent Drum

59 049-P-006A/B Raffinate Column No2 Bottoms Pumps

60 049-P-007A/B Raffinate Column No2 Overhead Pumps

61 049-E-006A/B/C/D Raffinate Column No2 Reboiler

62 049-V-005 Raffinate Column No2 Receiver

63 049-E-014 Start-Up Heater

64 049-V-012 Steam Separator

65 049-P-010A/B Water Injection Pumps

Isomar Process Unit(Unit-050)

1 050-P-008 Caustic Circulation Pump

2 050-F-001 Charge Heater

3 050-A-003 Chemical Injection Conservation Vent

4 050-P-007A/B Chemical Injection Pump

5 050-V-002 Clay Treater

6 050-E-005 Clay Treater Charge Exchanger

7 050-E-006 Clay Treater Charge Heater

8 050-E-001 Combined Feed Exchanger

9 050-C-001 Deheptanizer

10 050-P-002A/B Deheptanizer Bottoms Pumps

11 050-P-003A/B Deheptanizer Overhead Pumps

12 050-AC-002 Deheptanizer Condenser

13 050-E-002 Deheptanizer Feed-Isomar Feed Exchanger

14 050-E-003 Deheptanizer Feed-Parex Feed Exchanger

15 050-E-004 Deheptanizer Reboiler

16 050-V-003 Deheptanizer Receiver

17 050-E-007 Deheptanizer Trim Condenser

18 050-K-002 Deheptanizer Vent Gas Compressor

EIA Report

145 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No.

Equipment Tag No. Equipment Description

19 050-A-001 Desuperheater

20 050-EJ-001 Ejector

21 050-P-001A/B Isomar Charge Pumps

22 050-P-005A/B Knockout Pumps

23 050-AC-001 Product Condenser

24 050-R-001 Reactor

25 050-K-001 Recycle Gas Compressor

26 050-A-002 Refrigeration Package

27 050-V-001 Separator

28 050-A-004 Silencer

29 050-C-002 Stabilizer

30 050-E-009 Stabilizer Bottoms Cooler

31 050-AC-003 Stabilizer Condenser

32 050-P-004A/B Stabilizer Overhead Pumps

33 050-E-008 Stabilizer Reboiler

34 050-V-004 Stabilizer Receiver

35 050-E-010 Stabilizer Vent Chiller

36 050-V-005 Vent Knockout Drum

37 050-V-006 Water Injection Drum

38 050-P-006A/B Water Injection Pumps

Miscellaneous Equipment for PX Process Unit

1 050-V-060 ATM Flash Drum

2 050-AC-051 ATM Flash Drum Condenser

3 050-M-051 BD Sump

4 050-P-059A/B BD Sump Pump

5 050-P-051A/B CBD Pumps-1

6 050-P-053A/B CBD Pumps-2

7 050-V-051 Closed Blowdown Drum-1

8 050-V-053 Closed Blowdown Drum-2

EIA Report

146 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No.

Equipment Tag No. Equipment Description

9 050-E-051 Condensate Cooler

10 050-P-057A/B Condensate Pumps

11 050-M-052A/B CRWS Pit-1/2/3/4

12 050-P-056A/B/C CRWS Transfer Pump-1/2/3/4

13 050-P-063 Dewatering Pump for CBD-1 Pit

14 050-P-064 Dewatering Pump for CBD-2 Pit

15 050-P-065A/B/C/D Fire Water Booster Pump-1/2/3/4

16 050-V-054 Flare KOD-1

17 050-V-056 Flare KOD-2

18 050-G-051 Fuel Gas Filter/Coalescer

19 050-E-052 Fuel Gas Heater

20 050-V-064 Fuel Gas KOD

21 050-V-059 LP Flash Drum

22 050-A-052 LP Vent Silencer

23 050-A-051 MP Vent Silencer

24 050-P-061A/B Oil Side Pump for OWS Pit-1

25 050-P-062 Oil Side Pump for OWS Pit-2

26 050-M-053 OWS Pit-1

27 050-M-054 OWS Pit-2

28 050-V-061 Steam Continuous Blowdown Drum

29 050-V-062 Steam Intermittent Blowdown Drum

30 050-V-057 Waste Water Sump-1

31 050-V-063 Waste Water Sump-2

32 050-P-054A/B Waste Water Transfer Pumps-1

33 050-P-058A/B Waste Water Transfer Pumps-2

34 050-P-055A/B Water Side Pump for OWS Pit-1

35 050-P-060 Water Side Pump for OWS Pit-2

EIA Report

147 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

b) Purified Terephthalic Acid (PTA Section)

TA Slurry (TA) product from the Oxidation Plant contains a small quantity of impurities which

must be removed before the material can be used in the manufacture of polyester products. This

is achieved in the Purification Plant by selective catalytic hydrogenation of an aqueous solution

of TA slurry at elevated temperature and pressure. Purified Terephthalic Acid (PTA) is

subsequently crystallised and recovered by employing solid/liquid separation and drying steps.

The principal impurity, 4 Carboxy- Benzaldehyde (4CBA), is hydrogenated to para- Toluic Acid.

The para-Toluic Acid, being more soluble in water than PTA, remains in aqueous solution during

the subsequent crystallisation and product recovery stages. The equipment list of PTA process

unit in given the Table 2-13

Table 2-13 Equipment List- PTA Process Unit

S. No. Equipment Tag No. Equipment Description

1 051-V-903 0.8 Kg/Cm2g Steam Separator

2 051-M-235 051-E-235 Mist Eliminator

3 051-H-N235 051-E-235 Silencer

4 051-M-245 051-E-245 Mist Eliminator

5 051-H-N245 051-E-245 Silencer

6 051-M-255 051-E-255 Mist Eliminator

7 051-H-N255 051-E-255 Silencer

8 051-C-230 1st Dehydration Tower

9 051-E-280 1st Hpvgt Preheater

10 051-M-270 1st Pass Reverse Osmosis Unit

11 051-V-274 1st Pass RO Effluent Drum

12 051-P-270 A/B 1st Pass RO High Pressure Feed Pumps

13 051-S-501 1st Pressure Filter Outlet Screw

14 051-V-455 1st PTA Crystallizer

15 051-A-310 1st PTA Crystallizer Agitator

16 051-A-455 1st PTA Crystallizer Agitator

17 051-E-415 1st PTA Preheater

18 051-G-271 A/B 1st RO Feed Oil Filters

19 051-E-101 1st Stage Compressor Intercooler

20 051-V-350 1st Stage Wash Drum

21 051-P-350 A/B 1st Stage Wash Pumps

22 051-V-310 1st TA Crystallizer

23 051-E-314 1st TA Crystallizer 2nd Condenser

EIA Report

148 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No. Equipment Tag No. Equipment Description

24 051-E-312 1st TA Crystallizer Hot Condenser

25 051-V-902 2.0 Kg/Cm2g Steam Separator

26 051-C-232 2nd Dehydration Tower

27 051-P-232 A/B 2nd Dehydration Tower Bottom Pumps

28 051-E-285 2nd Hpvgt Preheater

29 051-M-275 2nd Pass Reverse Osmosis Unit

30 051-P-277 A/B 2nd Pass RO High Pressure Effluent Pumps

31 051-P-274 A/B 2nd Pass RO High Pressure Feed Pumps

32 051-S-502 2nd Pressure Filter Outlet Screw

33 051-V-460 2nd PTA Crystallizer

34 051-A-320 2nd PTA Crystallizer Agitator

35 051-A-460 2nd PTA Crystallizer Agitator

36 051-E-420 2nd PTA Preheater

37 051-G-272 2nd RO Feed Oil Filter

38 051-E-102 2nd Stage Compressor Intercooler

39 051-V-360 2nd Stage Wash Drum

40 051-P-360 2nd Stage Wash Pump

41 051-V-320 2nd TA Crystallizer

42 051-E-323 2nd TA Crystallizer Hot Condenser

43 051-V-972 32.6 Kg/Cm2g Steam Separator

44 051-V-465 3rd PTA Crystallizer

45 051-A-330 3rd PTA Crystallizer Agitator

46 051-A-465 3rd PTA Crystallizer Agitator

47 051-E-425 3rd PTA Preheater

48 051-G-273 3rd RO Feed Oil Filter

49 051-E-103 3rd Stage Compressor Intercooler

50 051-V-330 3rd Ta Crystallizer

51 051-V-974 4.8 Kg/Cm2g Steam Flash Drum

52 051-V-901 4.8 Kg/Cm2g Steam Separator

53 051-V-470 4th PTA Crystallizer

54 051-A-470 4th PTA Crystallizer Agitator

55 051-E-430 4th PTA Preheater

56 051-V-475 5th PTA Crystallizer

57 051-A-475 5th PTA Crystallizer Agitator

58 051-E-435 5th PTA Preheater

59 051-M-1205 Air Compressor Condensate Sump

60 051-P-1205 A/B Air Compressor Condensate Sump Pumps

61 051-P-913 Amine Pump

EIA Report

149 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No. Equipment Tag No. Equipment Description

62 051-V-923 Atmospheric Condensate Flash Drum

63 051-H-N103 Blow-Off Silencer

64 051-G-733 A/B Carbonate Filter

65 051-R-820 Catalytic Oxidizer

66 051-E-807 Catox Start-Up Heater

67 051-M-1210 Clean Run-Off Sump

68 051-P-1210 Clean Runoff Sump Pump

69 051-P-1202 Compressor Building Sump Pump

70 051-P-1094 A/B Concentrated Caustic Large Transfer Pumps

71 051-P-1090 A/B Concentrated Caustic Small Transfer Pumps

72 051-T-1090 Concentrated Caustic Storage Tank

73 051-P-1091 Concentrated Caustic Unloading Pump

74 051-T-902 Condensate Collection Tank

75 051-P-905 A/B Condensate Collection Tank Pumps

76 051-E-436 Condensate Preheater

77 051-P-902 A/B Condensate Pumps

78 051-V-1159 A/B Conveying Gas Dryer

79 051-G-1161 A/B Conveying Gas Dryer Afterfilter

80 051-M-1159 Conveying Gas Dryer Package

81 051-M-601 Conveying Gas Dryer Package

82 051-G-1160 A/B Conveying Gas Dryer Prefilter

83 051-V-492 Crystallizer KO Drum

84 051-E-267 A÷C Dehydration Tower Condensate Reheaters

85 051-P-265 A/B Dehydration Tower Final Condenser Reflux Pumps

86 051-E-265 Dehydration Tower Overhead Final Condenser

87 051-V-258 Dehydration Tower Reflux Drum

88 051-E-238 Dehydration Tower Reflux Heater

89 051-P-258 A/B Dehydration Tower Reflux Pumps

90 051-P-1054 A/B Demineralized Water Large Booster Pumps

91 051-P-1050 A/B Demineralized Water Small Booster Pumps

92 051-E-259 DHT Condensate Cooler

93 051-V-239 DHT Condensate Flash Drum

94 051-P-239 A/B DHT Condensate Flash Drum Pumps

95 051-E-235 DHT Overhead 1st Condenser

96 051-E-245 DHT Overhead 2nd Condenser

97 051-E-255 DHT Overhead 3rd Condenser

98 051-M-1090 /, 051-M-1091 Dilute Caustic Static Mixers

99 051-S-503 Dryer Inlet Screw

EIA Report

150 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No. Equipment Tag No. Equipment Description

100 051-V-530 Dryer Steam Condensate Drum

101 051-P-530 A/B Dryer Steam Condensate Drum Pumps

102 051-E-873 Dryer Vent Catox Preheater

103 051-V-871 Dryer Vent KO Drum

104 051-K-871 Dryer Vent Liquid Ring Pump

105 051-KM-101 Dryer Vent Liquid Ring Pump

106 051-M-871 Dryer Vent Liquid Ring Pump Package

107 051-E-550 Dryer Vent Scrubber Condenser

108 051-P-540 A/B Dryer Vent Scrubber Pumps

109 051-E-871 Dryer Vent Seal Flush Cooler

110 051-P-871 A/B Dryer Vent Seal Flush Pumps

111 051-E-902 Ejector Condenser

112 051-E-155 Expander Re-heater

113 051-G-731 Fe/Cr Filter

114 051-H-M731 Fe/Cr Purge Pipe

115 051-V-440 Feed Heater Condensate Pot

116 051-P-570 H2O2 Metering Pump

117 051-P-201 A/B HBr Pumps

118 051-T-201 HBr Storage Tank

119 051-P-200 HBr Unloading Pump

120 051-M-900 HHP Steam Desuperheater Package

121 051-C-275 High Pressure Absorber

122 051-E-755 High Pressure Absorber Reflux Cooler

123 051-C-840 High Pressure Bromine Scrubber

124 051-P-260 A/B High Pressure Seal Pumps

125 051-V-950 HP Condensate Flash Drum

126 051-M-1130 HP Nitrogen Generation Package

127 051-V-971 HP Steam Let Down Flash Drum

128 051-M-1202 ISBL Compressor Building Sump

129 051-M-1262 Jet Mixer for Main ISBL Sump

130 051-P-202 A/B Liquid Catalyst Pumps

131 051-T-202 Liquid Catalyst Storage Tank

132 051-P-203 Liquid Catalyst Unloading Pump

133 051-C-750 Low Pressure Absorber

134 051-V-750 Low Pressure Absorber Drum

135 051-P-750 A/B Low Pressure Absorber Hac Pumps

136 051-R-880 LP Catalytic Oxidizer

137 051-E-875 LP Catox Heater

EIA Report

151 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No. Equipment Tag No. Equipment Description

138 051-M-160 LP Catox Quench Contactor

139 051-E-872 LP Vent Catox Preheater

140 051-V-870 LP Vent KO Drum

141 051-K-870 LP Vent Liquid Ring Pump

142 051-M-870 LP Vent Liquid Ring Pump Package

143 051-E-870 LP Vent Seal Flush Cooler

144 051-P-870 A/B LP Vent Seal Flush Pumps

145 051-M-1201 Main IABL Sump

146 051-P-1201 A÷D Main ISBL Sump Pumps

147 051-P-205 A/B Mother Liquor Reactor Feed Pumps

148 051-V-973 MP Steam Flash Drum

149 051-P-973 A/B MP Steam Flash Drum Pumps

150 051-E-975 MP Steam Superheater

151 051-A-730 Neutralization Reactor Agitator

152 051-V-730 Neutralization Reactor Drum

153 051-P-730 A/B Neutralization Reactor Drum Pumps

154 051-K-151 Off-Gas Expander

155 051-V-620 Off-Spec PTA Reslurry Drum

156 051-A-620 Off-Spec PTA Reslurry Drum Agitator

157 051-P-620 Off-Spec PTA Reslurry Pump

158 051-T-601 Off-Spec PTA Silo

159 051-H-603 Off-Spec PTA Silo Discharge Bin

160 051-S-601 Off-Spec PTA Silo Transfer Rotary Feed Valve

161 051-M-1261 Oil Skimmer for ISBL Compressor Building Sump

162 051-C-780 Ox Unit PSV Scrubber

163 051-V-780 Ox Unit PSV Sump

164 051-E-740 Oxidation Feed Mix Preheater

165 051-R-220 Oxidation Reactor

166 051-A-220 Oxidation Reactor Agitator

167 051-G-735 Polishing Filter

168 051-V-732 Precipitation Reactor

169 051-A-732 Precipitation Reactor Agitator

170 051-P-732 A/B Precipitation Reactor Pumps

171 051-V-509 A/B/C Pressure Filter Discharge Chutes

172 051-P-475 A/B Pressure Filter Feed Pumps

173 051-G-510 A/B/C Pressure Filters

174 051-G-101 Process Air Compressor Filter And Silencer

175 051-G-266 Process Condensate Oil Filter

EIA Report

152 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No. Equipment Tag No. Equipment Description

176 051-G-265 Process Condensate Solids Filter

177 051-C-175 Process Inerts Vent

178 051-C-160 Process Vent Scrubber

179 051-P-160 A/B Process Vent Scrubber Recirculation Pumps

180 051-M-650 PTA Conveying System

181 051-E-480 PTA Crystallizer Vent Condenser

182 051-H-601 A/B PTA Day Silo Discharge Bin

183 051-M-600 A/B PTA Day Silo Dust Collectors

184 051-H-600 A/B PTA Day Silo Target Box

185 051-S-600 A/B PTA Day Silo Transfer Rotary Feed Valves

186 051-T-600 A/B PTA Day Silos

187 051-DR-530 PTA Dryer

188 051-V-515 PTA Dryer Inerts Separator

189 051-S-504 A/B PTA Dryer Outlet Rotary Feed Valves

190 051-V-531 PTA Dryer Seal Pot

191 051-V-540 PTA Dryer Vent Scrubber

192 051-G-410 A/B PTA Feed Booster Pump Suction Filters

193 051-P-410 A/B PTA Feed Booster Pumps

194 051-V-410 PTA Feed Mix Drum

195 051-A-410 PTA Feed Mix Drum Agitator

196 051-V-520 PTA Mother Liquor Drum

197 051-M-520 PTA Mother Liquor Drum Jet Mixer

198 051-P-520 A/B PTA Mother Liquor Drum Pumps

199 051-H-602 PTA Off Spec Silo Target Box

200 051-R-450 PTA Reactor

201 051-E-440 PTA Reactor Feed Heater

202 051-P-411A÷C PTA Reactor Feed Pumps

203 051-G-605 A/B PTA Silo Solid Screen

204 051-M-551 PTA Transfer Line Jacket

205 051-V-490 PTA Vent Knock Out Drum

206 051-E-490 PTA Vent Knockout Drum Condenser

207 051-P-490 A/B PTA Vent KO Drum Circulation Pumps

208 051-E-845 Quench Cooler

209 051-V-734 Reconstitution Drum

210 051-A-734 Reconstitution Drum Agitator

211 051-E-736 Reconstitution Drum Heater

212 051-P-734 A/B Reconstitution Drum Pumps

213 051-V-906 Recovery Condensate Pot

EIA Report

153 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No. Equipment Tag No. Equipment Description

214 051-P-906 A/B Recovery Condensate Pumps

215 051-E-805 Recuperative Heater

216 051-E-269 RO Feed Exchanger

217 051-G-269 A/B RO Feed Solids Filters

218 051-V-272 RO Purge Drum

219 051-P-272 A/B Ro Purge Drum Pumps

220 051-P-840 A/B Scrubber Quench Pumps

221 051-G-260 A/B Seal Flush Filters

222 051-T-780 Sodium Carbonate Storage Tank

223 051-P-780 A/B Sodium Carbonate Storage Tank Pump

224 051-P-782 Sodium Carbonate Unloading Pump

225 051-T-860 Sodium Formate Storage Tank

226 051-P-860 A/B Sodium Formate Storage Tank Pump

227 051-P 861 Sodium Formate Unloading Pump

228 051-E-745 Solvent Condenser

229 051-V-322 A/B/C Solvent Exchange Filter Discharge Chutes

230 051-G-320 A/B/C Solvent Exchange Filters

231 051-E-215 Start-Up Heater

232 051-E-261 Steam Condensate Preheater

233 051-E-906 Steam Condensate Trim Cooler

234 051-K-901 Steam Turbine

235 051-T-905 Steam Turbine Condensate Collection Tank

236 051-P-901 A/B Steam Turbine Condensate Pumps

237 051-E-901 Steam Turbine Condenser

238 051-H-N906 Steam Vent Silencer

239 051-E-705 Stripper Reboiler

240 051-P-710 Stripper Reboiler Pump

241 051-C-710 Stripper Tower

242 051-P-330 A/B TA Filter Feed Pumps

243 051-V-340 TA Mother Liquor Drum

244 051-M-340 TA Mother Liquor Drum Jet Mixer

245 051-P-380 A/B TA Mother Liquor Purge Pumps

246 051-V-380 Ta Mother Liquor Purge Receiver

247 051-J-905 A÷E Vacuum Ejector

248 051-M-720 Wiped Film Evaporator

EIA Report

154 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-8 Process Flow Diagram

EIA Report

155 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-9 Schematic representation of Process of PX unit

EIA Report

156 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-10 Schematic representation of Process of PTA Unit-Sheet 1

EIA Report

157 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-11 Schematic representation of Process of PTA Unit-Sheet 2

EIA Report

158 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.7.4.2 Raw Material and products

The Overall Material Balance across PX and PTA Process Unit is given in Figure 2-12 and

Figure 2-13 respectively.

Table 2-14 Existing and proposed product

S.No. Streams Quantity – TMT/Year EC Details

Existing Proposed

Refinery Products

1 Naphtha Exports 0 --

J-11011/344/2016-IA-II(I) dated

11thOct 2018

Under Construction

2 BS-IV MS 0 --

3 BS-VI MS 3260 --

4 Reformate 96 --

5 SKO 312 --

6 ATF Domestic 463 --

7 BS-IV HSD 0 --

8 BS-VI HSD 6017 --

9 Sulphur 350 --

10 PetCoke 1253 --

11 LPG 932 --

12 Poly-Propylene 678 --

13 Fuel & Loss 1641 --

Petro-chemical Products

14 Mono-Ethylene Glycol

(MEG) 332 KTA --

J-11011/344/2016-IA-II(I) dated

11thOct 2018

Under Construction

15 Para Xylene 0 800600TPA Feed to PTA as a Raw material

16 Purified Terepthalic Acid

(PTA) 0 1200000TPA Proposed Product

Associated Products

17 Di-ethylene Glycol 24 KTA -- J-11011/344/2016-IA-II(I) dated

11thOct 2018

Under Construction 18 Tri-ethylene Glycol 1 KTA --

19 Toluene 0 50000TPA Proposed Product

Table 2-15 Details of Proposed Chemicals and Catalyst for PX and PTA

S. No.

Chemicals/

CatalystQuantity Unit Source

Modeof

Transport

Mode

of

Storage

Storage Capacity

1.Acetic Acid 4200 Kg/h External Road

Storage

tank 2x 425 m3

EIA Report

159 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.Hydrogen Bromide 80 Kg/h External Road Drums ~ 100 T

3.Sodium Formate 56 Kg/h External Road Drums ~ 100 T

4.Sodium Carbonate 1843 Kg/h External Road Drums ~ 1000T

5.

Conc Caustic Soda

flakes 109 Kg/h External Road Bags ~ 300 T

6.Hydrogen Peroxide 4.2 Kg/h External Road Drums ~ 10 T

7.Amine 1 Kg/h External Road Tank ~ 2T

8.Antifoam 1500 Kg External Road Drums ~1.5 T

9.Sulfolane 96630 Kg External Road Drums ~ 80 T

10.Monoethanolamine 44 Kg External Road

Tanker

/ Drum ~ 0.05 T

11.DimethayDisulfide 257 Kg External Road

Tanker /

Drum ~ 0.3 T

12.Perchloroethylene 930 Kg External Road Drum ~ 1 T

13.

Liquid Catalyst-

Cobalt/Manganese

solution

1597 Kg/h External Road Tanker ~ 50 T

14.R-450 PTA Reactor 69.4 m³ External Road Drum ~ 35 T

15.

R-820 Catalytic

Oxidizer 22.3 m³ External Road Bag /

box ~ 20 T

16.

R-880 LP Catalytic

Oxidizer 0.98 m³ External Road Bag /

box ~ 1 T

17.

Clay Catalyst –

Activated Clay 108 m³ External Road Bag

~ 1200 m3

18.

Clay Catalyst –

Activated Clay 760 m³ External Road Bag

19.

Clay Catalyst –

Activated Clay 291 m³ External Road Bag

EIA Report

160 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

I. Paraxylene (PX) Process Unit

a) Feed

Reformate (Existing CCR-Platforming unit)

Each unit in the Aromatic Complex will be designed for TWO (2) Design Feed Cases. Feed to

the Aromatic Complex is a depentanized reformate from the existing CCR-Platforming unit.

Hydrogen

During the start-up and normal operation, make-up hydrogen to the Tatoray Unit and Isomar

Unit will be supplied from Hydrogen Generation Unit (HGU) Source-1 or existing CCR

Platforming Unit. Aromatic Complex Units shall be designed for both quality of Make-up

hydrogen.

b) Product

Para-Xylene

The project shall also produce Toluene, Heavy Aromatics (MS Blend Stock), Raffinate.

c) Catalyst & Chemical

The catalyst and chemicals required for the operation of Para-Xylene Unit in given in Table 2-15

II.Purified Terepthalic Acid (PTA) Process Unit

a) Feed

Paraxylene from PX Unit

Acetic Acid

Cobalt Manganese Acetate Catalyst Solution

Hydrobromic Acid (HBr)

Sodium Formate

Sodium Carbonate

Sodium Hydroxide (NaOH)

Hydrogen Peroxide

Palladium On Carbon Catalyst

b) Product

Purified Terepthalic Acid (PTA)

EIA Report

161 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

c) Catalyst & Chemical

The Catalyst and Chemical required for the operation of Purified Terepthalic Acid Unit is given

in Table 2-15.

Figure 2-12Material Balance across PX Process Unit

EIA Report

162 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-13Material Balance across PTA Process Unit

2.7.5 Proposed Offsite Facilities

The equipment list of offsite and utilities are given the Table 2-16

Table 2-16 Equipment List- Offsite & Utilities

S. No. Equipment Tag No. Equipment Description

1 135-A-001 Aux Boiler Package

2 221-P-001A/B CBD DRUM PUMP (FLARE KOD AREA)

3 104-A-002 CLO2 Generator Package

4 221-V-003 Closed Blow down drum

5 104-CT-001A/B/ C/D/E/F/G/H/I/J/K/L

Cooling Tower Cells

6 104-A-003 Cooling tower chemical injection package

7 104-A-001 Cooling Tower Package

8 104-A-004 Cooling tower Side stream filter Package

9 104-P-004A/B Cooling tower SSF back wash transfer pump

10 104-SU-001 Cooling Tower Sump

11 104-P-001A/B/C/ D/E/F/G

Cooling water circulation Pumps

12 104-P-002A/B Cooling water Emergency Pump

13 208E-P-005A/B CRWS Pit Pump (PX OSBL Tankage Area)

14 221-P-003 Dewatering Pump for CBD drump pump (flare KOD area)

EIA Report

163 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No. Equipment Tag No. Equipment Description

15 208E-P-009A/B Dewatering pump for Hydrocarbon CBD drum pump no. 1 (PX-OSBL Tankage area)

16 208E-P-010 Dewatering pump Hydrocarbon CBD drum pump no. 2 (Toluene gantry area)

17 236-A-001 Effluent Treatment Plant package

18 221-SU-001 Flare pit

19 221-P-002A/B Flare pit Pump

20 104-TK-003 HCL Storage Tank

21 135-DS-001 HHP to HP let down

22 135-DS-003 HHP to LP let down

23 135-DS-002 HHP to MP let down

24 122A-V-002F HP air receiver

25 104-P-008A/B Hydro Chloride (HCL) loading cum unloading Pump

26 208E-V-001 Hydrocarbon CBD drum no. 1 (PX-OSBL Tankage Area)

27 208E-V-002 Hydrocarbon CBD drum no. 2 (Toluene gantry Area)

28 208E-P-001A/B Hydrocarbon CBD drum pump no. 1 (PX OSBL Tankage Area)

29 208E-P-002A/B Hydrocarbon CBD drum pump no. 2 (Toluene gantry Area)

30 221-E-001 Main Flare KOD Cooler

31 221-V-001 MAIN Flare KOD Drum

32 221-P-004A/B MAIN FLARE KOD PUMP

33 221-A-001 Main Flare Package

34 104-SU-002 Neutralisation Pit (Cooling Tower Area)

35 104-P-005A/B Neutralisation Pit Pump (cooling Tower Area)

36 104-P-009 Oil side pump for OWS pit (Cooling Tower Area)

37 208E-P-004A/B Oil side pump for OWS sump No. 01 (PX OSBL Tankage Area)

38 208E-P-008 Oil side pump for OWS sump No. 02 (Toluene gantry Area)

39 104-SU-003 OWS pit

40 104-P-003A/B OWS Pit Pump (Cooling Tower Area)

41 208E-SU-004 OWS SUMP no. 1 (PX-OSBL Tankage Area)

42 208E-SU-005 OWS SUMP no. 2 (Toluene gantry Area)

43 208D-TK-002A/B PX storage tank

44 208D-P-002A/B PX transfer pumps

45 208A-TK-001 Raffinate storage tank

46 208A-P-001A/B Raffinate transfer pump

47 208A-TK-002 Reformate tank

48 208A-P-002A/B Reformate transfer pumps

49 104-SU-004 Side stream filter backwash sump

EIA Report

164 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No. Equipment Tag No. Equipment Description

50 104-P-007A/B Sodium chlorite loading cum unloading Pump

51 104-TK-002 Sodium chlorite Storage tank

52 104-P-006A/B Sulphuric acid loading cum inloading Pump

53 104-TK-001 Sulphuric Acid storage tanks

54 208D-TK-001A/B Toluene Storage tank

55 208D-P-001A/B Toluene Transfer pump (For Tanker Loading)

56 135-SL-001 Vent silencer for HP

57 135-SL-003 Vent silencer for LP

58 135-SL-002 Vent silencer for MP

59 208E-P-003A/B Water side pump for OWS sump No. 01 (PX OSBL Tankage Area)

60 208E-P-006 Water side pump for OWS sump No. 2 (Toluene gantry Area)

61 Natural Gas (NG) receipt Terminal and Distribution network

2.7.6 Proposed unit facilities and Utilities

Major facilities in the proposed PX unit, PTA unit & ETP with Capacity is given in Table 2-17,

Table 2-18 and Table 2-19 respectively.The proposed utilities for Paradip PX-PTA Unit is

given in the Table 2-20. The Upcoming Storage Facilities is given in Table 2-21.

Table 2-17 Major facilities in the proposed PX unit with Capacity

S.NO. DESCRIPTION SIZE / CAPACITY

1 Paraxylene (PX) 0.8 MMTPA*

2 PX Sub-station 41 m x 135 m

3 PX – PTA Centralized Control Room 46 m x 52.5 m

4 PX Satellite Rack Room. 46 m x 51 m

5 Pre ETP Unit Peak: 3 m3/hr

6 Capacity enhancement of existing CCRU Hydrogen PSA

Revamp of existing CCRU PSA Systemfrom 12 Beds in MS mode to 16 beds in Aromatics Mode

7 Flare Capacity : 1674 TPH

8 PX ISBL TANKFARM

PX Area (over and above the ISBL tanks) (nominal capacities) -Aromatic Tank-7390 m3 m -Ligh reformate storage tank-7390m3

EIA Report

165 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.NO. DESCRIPTION SIZE / CAPACITY

-Plant inventory tank-260m3

-Paraxylene day tank-2 x 3900m3

-Desorbent storage tank- 2810m3

-Plant Inventory storage tank-2810m3

-Toluene day tank- 2 x 320m3

9 (PX OSBL TANKFARM)

PX OSBL Area (nominal capacities) -Reformate Storage tank-15000m3

- Paraxylene tank-2 x 9730m3

- Toluene storage tank-2 x 1049m3

- Raffinate storage tank – 6430m3

10 PX-PTA Lab Building 52 m x 31 m

11 Operator Shelter for PX Unit 10 m x 21 m

12 Fire Water Booster Pump House for PX Unit

21 m x 9 m

Note:* In Form-1 it has been mentioned as 0.78MMTPA based on the preliminary project feasibility study. Based on the Detailed feasibility study the capacity has been given as 0.8MMTPA.

Table 2-18 Major facilities in the proposed PTA unit with Capacity

S.NO. DESCRIPTION SIZE / CAPACITY

1 Purified Terephthalic Acid (PTA) 1.2 MMTPA

2 N2 Unit including Storage and Vaporizer

HP Nitrogen - Normal- 55 Nm3/h Peak - 10115 Nm3/h LP Nitrogen - Normal - 145 Nm3/h Peak - 18209 Nm3/h Liquid Nitrogen working storage: 126 Ton

3 PTA Day Silos and Off-spec Silos 2 Day Silo – 2100 m3 each1 Off-spec Silo – 2100 m3

4 PTA Product Silos 4 x 3238 m3 each working volume

5

PTA Automatic Storage & Retrieval System (ASRS) Warehouse and along with PTA loading facility to Trucks and associated office and other buildings

ASRS for 1,00,000 nos. of FIBC Bags Overall block area – 310 m x 230 m

EIA Report

166 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.NO. DESCRIPTION SIZE / CAPACITY

6 Product Bagging System

Total Bagging Rate – 300 TPH Total 8 no of Machines 6 No’s Working (Bagging Rate – 50 TPH) 2 No’s Standby (Bagging Rate – 50 TPH)

7 Fire water booster pumps 4 x 350 m3/hr each

8 Mother Liquor and Acetic acid Day tanks

ML – 1 x 1558 m3 (nominal) AA –2 x 425 m3 (nominal)

9 PTA Sub-station 122 m x 38 m

10 PTA Satellite Rack room 46 m x 51 m

11 DG and DG room 6 MW DEG, 20 m x 36 m

12 Operator Shelter 20 m x 10 m

Table 2-19 Major facilities in the proposed New ETP

S.NO. DESCRIPTION SIZE / CAPACITY

1 ETP with Anaerobic and Aerobic Treatment with integerated RO

408 m3/hr

2 ETP Substation, SRR & Control Room will be one building with G+2 structure

50 m x 35 m

Table 2-20 Proposed Utilities

S. No Description Size/Capacity Units

1 Utility Boiler-5* 300 TPH

2 Substation and SRR Building for UB-5 61.6 x 17 m

3 Cooling water Makeup 910 TPH

4 Cooling Tower Area for PX-PTA 75 x 200 m

5 Sub-Station for Cooling Tower 36 x 24 m

6 Demineralized Water peak 264.9 TPH

7 Steam (HHP) peak 194 TPH

8. Instrumentation Air 3618 Nm3/hr

9 Nitrogen 18594 Nm3/hr

EIA Report

167 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

10 Power 30.5 MWH

11 Natural Gas/Fuel Gas in PX unit 18 TPH

12 Natural Gas/Fuel Gas in New Boiler 20 TPH

13 NG RECEIPT TERMINAL and distribution network 240 TPH

14 PP and PTA container storage yard and Rail Loading

facility 32 x 843 m

15 Maintenance and Staff Building 19 x 7 m

16 Local GIS Room 32 x 12 m

17 Product Loading Gantry for Toluene - Area 148 x 38 m

18 Product Loading Gantry for Toluene- 2 Loading Arm 45 m3/hr

19 PX-PTA Hub Distribution Substation North 35 x 24 m

Note:

In Form-1 it is mensioned as that, the desalination plant is proposed based on the

preliminary project feasibility study. However, the unit dropped during detailed

feasibility study

In Form-1 Utility Boiler-5 is not mentioned based on the preliminary project feasibility

study. However, the Utility Boiler-5is included during detailed feasibility study.

In Form-1 it is proposed to have new housing facility for 200 operational employees.

However, Housing facility dropped during detailed feasibility study for the project

Table 2-21 Upcoming Storage Facilities

Tank Service Type Dia(m) Ht (m) 203-TK-009 VR Coned Roof 51.1 15.5

201-TK-015

Crude Floating Roof

79 13.61 201-TK-016 79 13.61 201-TK-017 79 13.61 201-TK-018 79 13.61 205-TK-028

HSD Floating Roof 52.3 16

205-TK-029 52.3 16 205-TK-030 52.3 16

BS-VI

Tank Service Type Dia(m) Ht (m)

203-TK-018 HGU Feed Dome Roof

203-TK-019

205-TK-037 SKO Floating Roof 40.7 15.5

MEG ERU

EIA Report

168 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Tank Service Type

207-Tk-003A/B/C/D/E MEG Fixed Roof m3 42,940

207-Tk-004A/B DEG Fixed Roof m3 4,528

207-Tk-005A/B TEG Fixed Roof m3 636

207-HS-002 A/B/C/D ETHYLENE Horton Sphere m3 4x3053

PDR 10 Additional Tanks

Tank Service Type Dia(m) Ht (m)

203-TK-003 NHT Feed CRIF; N2 blankering 49.5 17.5

203-TK-004 DHDT Feed CRIF; N2 blankering 49.5 17.5

203-TK-012 VGO-HDT Feed Coned Roof; N2 blanketing

78.2 15.5

205-TK-039 MS Floating Roof

50.5 16 205-TK-040 50.5 16 205-TK-043

Alkylate Floating Roof 50.5 16

205-TK-044 50.5 16 205-TK-050 PCK Floating Roof 35 15.3 205-TK-054

Sulphur Coned Roof -- --

205-TK-055 -- --

2.7.7 Proposed Gas Monitoring System

Pumps handling LPG or hydrocarbons above Auto Ignition Temperature (AIT) or within or

above 80 C of flashpoint, hydrocarbon gas detectors located between pump pairs and at the end

of the pump row. Pumps handlings Toxic products, toxic gas detectors located between pump

pairs and at the end of the pump row. Pumps handling fluids where there may be a risk of a gas

leak aadditionally have gas detectors located with one meter of the pump seal area Compressors

handling LPG and Hydrogen, these units fitted with flame detectors.

Columns rated as HIGH or MEDIUM risk, flame detectors located to view the base. Vessels

handling fluids above AIT or over 3150 C rated as HIGH RISK, flame detectors located to cover

the ground under vessels. Reactors operating at high temperature, flame detectors located to

cover the ground under reactors. Reactors which may cause an exothermic or runaway reaction,

flame detectors located to cover the ground under reactors

EIA Report

169 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.7.7.1 Mitigation Measures

The highest standards of safety are being implemented by examining the potential hazards,

accessibility, constructability, operability and maintainability to ensure a safe and

environmentally sound plant and facilities.

Eye-wash and safety showers are provided in all appropriate locations.

All hazardous and hydrocarbon drains are routed to closed systems.

Definition of environmental requirements, Noise studies and associated

recommendations, Dispersion calculations and associated recommendations

Escape Routes, Accessibility, Operability and Constructability reviews and

implementation of recommendations.

All safety requirements of Indian Boiler Regulations (IBR) will be complied in the

design.

Fire water sprinkler systems will be implemented for applicable equipment, as per OISD

code requirements.

Safety insulation is provided for all pipes/surfaces operating at temperature higher than

60°C.

Pressure safety valves are provided for over-pressure protection of equipment and piping

in all applicable locations.

Double isolation valves are provided for high pressure streams and hydrogen services.

HAZOP study has been performed for PX-PTA units during FEED phase. HAZOP

recommendations from the HAZOP study shall be incorporated into the design of these

systems.

Detailed HAZOP and SIL study for all units are envisaged during detailed engineering

phase of the project. All HAZOP recommendations will be complied and

recommendations from the studies will be implemented.

Compliance to all National and Local rules and regulations by statutory bodies will be

ensured.

EIA Report

170 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.7.7.2 Precaution & Safety Measures against Fire Hazards

IOCL has taken lot of safety measures against Fire hazards in course of the design &operation of

two plants. They are as follows:

N2 Blanketing in flammable storage tanks

Breather Valves

Earthing Continuity

Lightening Arrester as per IS specification & monitoring of Earth Pit

Flame proof electrical fittings

Periodic Tank Inspection

Storage & handling of Bulk Chemicals & Plant Operations through DCS System

Periodic Checking of Critical Instruments

In addition to the above measures the new technology has the following measures embedded in

its design- following are the safety measures in the new unit:

Process Design and Engineering is such that it can cater to any emergency happening in

the Plant.

Provision of nitrogen blanketing of the reactor on occasion of a reactor trip

Critical trips are implemented in the system

Better Process Control System

Safety Critical Alarms are implemented for the new unit

Automated Safety Instrumented System.

Over/Under Pressure Relief Protection

Overfill Containment.

Emergency Response

2.7.7.3 Assessment of new & untested Technology

Paradip Refinery has a unique INDMAX Unit technology, which is indigenously been

developed by Indian Oil's R&D Centre. The INDMAX (FCC) Unit has designed to produce

44% LPG, the highest yield from such plants. The commissioning of INDMAX Unit at Paradip

marks a major milestone in the history of Indian refining. With this, IndianOil has now

recognized globally as a technology licensor. The other first-time technological features of the

Refinery include Flue Gas Desulphurisation facilities, Vapour Recovery system from jetty

EIA Report

171 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

loading and an alkylation process to get octane-rich low-benzene MS blend component, etc. So

no alternative technologies available.

2.7.8 Sulphur Balance

Detailed Sulphur balance is given in Table 2-22.

Table 2-22 Sulphur balance for Proposed Facility

Total crude to be Processed T/day Post BS VI &

MEG Post PX/PTA

Average sulphur content in the crude % 2.9 2.9

Total sulphur input through crude TMTPA 435 435

Total sulphur in products TMTPA 431.5 431.5

Total Sulphur emissions from process stacks and heaters

TMTPA 3.5 3.58

Total SO2 emissions into atmosphere Kg/hr 875 895.2

Total SO2 emissions into atmosphere Kg/Ton of

crude 0.467 0.477

From PX PTA, additional pollution load of SO2 emission will be 0.162 TMTPA

2.8 Plot area

The proposed project is planned within the existing facility of IOCL located at Abhaychandrapur

village, Jagatsinghpur District, Odisha State. The total land area is 3345 Acres. Plot plan is

shown below as Figure 2-18 also attached as Annexure -6 and Green Belt demarcation and the

species planted is enclosed as Annexure- 8.

2.8.1 Site Photographs

Site Photographs of Existing facility and proposed facility is enclosed as Figure 2-14 and Figure

2-15 respectively. The ETP and STP Photographs are given in Figure 2-16 and Figure 2-17

respectively.

EIA Report

172 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-14 Site Photographs of Existing Refinery Complex

23.08.2019

23.08.2019 23.08.2019

23.08.2019

EIA Report

173 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-15 Site Photographs of Proposed facility

Figure 2-16 Photographs of Existing ETP

19.06.2021

Proposed PX Site-19.06.2021 Proposed PTA Site-19.06.2021

19.06.2021

EIA Report

174 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-17 Photographs of Existing STP

23.08.2019 23.08.2019 23.08.2019

23.08.2019 23.08.2019 23.08.2019

EIA Report

175 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.8.2 Land Area Breakup

Detailed Land breakup is summarized in Table 2-23. The Existing and Proposed Refinery

Layout is given in Figure 2-18 and Figure 2-19 respectively. The Overall Existing and proposed

plot plan is given in Figure 2-20.

Table 2-23 Land use planning of the Project Site

Description Existing (Acres)

Proposed (Acres)

After Expansion (Acres)

Percentage, %

a. Refinery Project area

Built Up area 1748 75 1823 65.32%

Roads 355 0 355 12.72%

Green Belt 580 0 580 20.78%

Vacant Land 108 0 33 1.18%

Subtotal (a) 2791 75 2791 100%

b. Residential Area

i.Plot Area 204 0 204 64.97

ii.Green Belt 110 0 110 35.03

Subtotal (b) 314 0 314 100.00

c.Other Office and Building

i.Plot Area 155 0 155 64.58

ii.Green Belt 85 0 85 35.42

Subtotal (c) 240 0 240 100.00

Total Area(a+b+c) 3270 75 3345

d. On other's land

Green belt (d) 75 0 75

Total Green belt Area from a,b,c and d

850 0 850 30.46

Note: As per form-1 16 acre has to acquired for the proposed project based on the preliminary project feasibility study carried out. Based on the Detailed feasibility study it is identified, as the land acquisition is not required.

1.Proposed PX PTA site area 75 acre is utilized from the existing vacant land inside the IOCL Paradip Refinery Complex. Land acquisition is not applicable. 2.Paradip refinery project’s Latest EC granted in 2018- -J-11011/344/2016-IA. II(I)

dt.11.10.2018 the condition for green belt (GB) development was 748.72 acres land. Accordingly

Green belt has been developed to comply the EC condition. In subsequent year the plantation has

been increased and as of now 850 acre of land is planted.

3.A per Latest EC granted in 2018- J-11011/344/2016-IA. II(I) dt.11.10.2018 the existing land area mention is 1194 ha(2950.30acre) which is excluding the township area. In proposed project, the total land area with township is 3345 acre.

EIA Report

176 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.IOCL Paradip refinery has already done tree plantations of suitable species about 8.5 Lakh including GB area. Further plantation of 100000 trees is under execution.

5.Pardip is industrial area and IDCO Government of Odisha do not have any land for allocating to any industry.

6.Paradip Area is under SPA CEPI 2018 (NGT order OA 1038/2018 heariing date 10.07.2019) and Greenbelt coverage is required 33% or 40 % .

7.IOCL will explore land for plantation from others e.g. District administration, Forest department of Odisha, NHAI, SH / PWD etc. to meet the balance Green belt.

8.Residential area - Township, CISF Colony etc.

9.The Green belt alloted in section d(others land) is the land area near by schools and villages

10.Additional tree plantation has been done on land in peripheral villages, along access roads,

schools, panchayats, nearby district areas etc.

EIA Report

177 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-18 Existing Refinery Layout

EIA Report

178 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-19 Proposed Layout

EIA Report

179 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-20 Existing and proposed plot plan

EIA Report

180 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.9 Manpower

The existing refinery has a total of 996 permanent employees and 547 contract workers.

Approximately temporary employment for ~5400 persons provided during construction phase

based on various skills and 1922 persons including temporary and permanent staff during

operation phase. The Breakup of manpower details in given in Table 2-24

Table 2-24 Manpower Requirement

During Construction Phase

S. No. Description Proposed

1 Contract workers Approx 5400 (considering 5 million man hours in

three years’ construction phase)

2 Permanent workers 21 RHQ+site

Total 5421

During Operation Phase

S.

No. Description

Existing Proposed Total

Permanent CISF Others Permanent Contract

1 Manpower

850+75+50

Present+MEG+BS-

VI)

395 152 200 200 1922

2.10 Power and Fuel Requirements

The power requirement for the existing facility is met from Captive Power plant (CPP). For

proposed project the power requirement will be 30.5 MW to be sourced from Existing Gas

Turbine. The Breakup of power and fuel details in given in

Table 2-25. In Form-1 it is proposed to source the power from New GT of 102MW capacity of

proposed quantity 80MW. Based on the detailed feasibility study the source of power is

identified to be taken from existing gas turbine which has sufficient capacity and also the

proposed quantity is also reduced to 30.5MW.

EIA Report

181 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 2-25 Power and Fuel Requirement

Details Capacity

Source Existing Proposed Total

Power

Requirement

240.5 Mwh

(190.5+50) 30.5 Mwh 271 Mwh

Existing Gas

Turbine

FO 32.99 KTPA 0 32.99 KTPA From existing storage

HSFO 310 KTPA

(114.9+196) 0

310 KTPA From existing storage

Naphtha 574.4 KTPA 0 574.4 KTPA From existing storage

FG/NG 64.7TPH 240TPH 304.7TPH GAIL- Form Proposed

Pipeline

Existing utility data is as per AOR 2019-20 + the proposed utility load of MEG and BS VI

project.

The MoU with the concernerd will be executed prior to commissioning of the facility. Tthe MoM

with GAIL is attached as Annexure 34.

2.11 Water requirements

a. Existing facility

Total water requirement of the existing facility is 3497 m3/hr of which fresh water requirement is

2749m3/hr and Effluent generation is 1082.1 m3/hr.

b. Proposed

Total water requirement of the proposed facility is 1299.5 m3/hr of which fresh water

requirement is 994m3/hr and Effluent generation is 408 m3/hr.

In Form-1 the proposed effluent generation has been given as 300m3/hr based on the preliminary

project feasibility study. Based on detailed feasibility study for the project the effluent generation

is 408m3/hr.

Existing and proposed water consumption details given in Table 2-26

EIA Report

182 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 2-26 Existing and Proposed Water Requirements

S. No

Description

Existing (m3/hr) Proposed (m3/hr) Total after expansion (m3/hr)

Tot

al W

ater

Fre

sh W

ater

ET

P T

reat

ed

Wat

er U

sed

Con

den

sate

Use

d

Use

of

outl

et

Ou

tlet

Eff

luen

t/ S

ewag

e G

ener

ated

Los

s

Tot

al W

ater

Fre

sh W

ater

ET

P T

reat

ed

Wat

er U

sed

Con

den

sate

Use

d

Use

of

outl

et

Ou

tlet

Eff

luen

t/ S

ewag

e G

ener

ated

Los

s

Tot

al W

ater

Fre

sh W

ater

ET

P T

reat

ed

Wat

er U

sed

Con

den

sate

Use

d

Use

of

outl

et

Ou

tlet

Eff

luen

t /

Sew

age

Gen

erat

ed

Los

s

(a+b)

(a) (b)

(a+b)

(a)

(b) (a+b

) (a) (b)

1 Cooling tower

1482

1482

0 0 0 0 323 1159

930.5

911

19.5

0 0 0 213.

6 716.9

2412.5

2393

19.5 0 0 0 536.

6 1875.9

2

DM Water Makeup

1334.8

586.8

748

0 0 0 175 0 286 0 286 0 0 0 21.2 0 1620.8

587

1034

0 0 0 196.

2 0

3 Service Water

465.2

465.2

0 0 0 372.16

0 93.1 60 60 0 0 0 48

145.5

12 525.

2 525

0 0 0 420

0 105.

1

4 Refinery unit

0 0 0 0 372.16

0 372.16

0 0 0 0 0 0 0 0 0

0 0 0 0 420

0 517.66

0

5 PX-PTA unit

0 0 0 0 0 0 0 0 0 0 0 0 48

0 145.5*

0

6 Project 100 100 0 0 0 0 80 20 0 0 0 0 0 0 0 0 100

100

0 0 0 0 80 20

7 Others 5 5 0 0 0 0 4 1 20 20 0 0 0 0 16 4 25 25 0 0 0 0 20 5

8 Domestic

110 110 0 0 0 0 88 22 3 3 0 0 0 0 2.4 0.6 113 113

0 0 0 0 90.4 22.6

9 Boiler 0 0 0

1119.8

0 0 40 0 0 0 0 264.8

0 0 9.3 0 0 0 0 1362.8

0 0 49.3 0

Total 3497

2749

748

1119.8

372.16

372.16

1082.2

1295.1

1299.5

994

305.5

264.8

48

48 408

733.5

4796.5

3743

1053.5

1362.8

420

420

1490.2

2028.6

Note: * In proposed water balance, the additional water generated within the PX-PTA process (97.5 m3/hr) is added to the effluent along with the effluent from service

water(48 m3/hr).

EIA Report

183 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-21 Water Balance Diagrams of Existing Refinery

EIA Report

184 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-22 Water Balance Diagrams of Proposed Refinery

EIA Report

185 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-23 Water Balance Diagrams for after expansion of Refinery

2.12 Source of water Supply

The total water requirement will be met from Mahanadi River through pipeline with a

distance from the sourse to refinery receiving point is around 93km( actual length of pipeline)

while the radial distance of the same is 75km as per the Latest CTO 5543/IND-I-CON-6414

EIA Report

186 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

dated 31.03.2021 valid till 31.03.2022. Approval for extraction of water enclosed as

Annexure.7

2.13 Project schedule

Proposed project will be implemented in a period of around 37 months.

2.14 Air Pollution Control Measures

Paradip Refinery has adopted various measures for control of gaseous emissions. These

include:

Use of clean burning fuel gas and natural gas in PX-PTA unit

Installation of low NOx burners in all the furnaces and boilers

Tall stacks for better dispersion of flue gases

Online monitoring of SOx, NOx, CO and PM emissions from furnaces/boilers

Monitoring of ambient air quality as per revised MoEF

Installation of internal floating roof with double seals in all Class-A tanks for

reduction of fugitive emissions

Provision of mechanical seals in all the hydrocarbon pumps for reduction of fugitive

emissions

Reduction of hydrocarbon losses and to attain zero leakage status

All the proposed tanks are of Internal floating roof type minimizing the fugitive

emissions in comparison to External floating roof tanks

All the tanks will be under Nitrogen blanketing

2.15 Green Belt

Refinery has developed greenbelt in 580 acres area in and around Refinery. Approximately

more than 8 lac trees have been planted by Refinery. This is ongoing job and PDR has the

commitment to plant at 5000 trees every year towards environment management and preserve

eco system. Survival rate is 95%. Green belt demarcation and species planted is enclosed as

Annexure-08. The Summary of Plantation from the year 2007 to 2020 is given in Table

2-28. The green belt occupies about 30.46% only. The green belt area breakup is given in

Table 2-27.

EIA Report

187 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 2-27 Green Belt Area Breakup

Description Existing (Acres)

Proposed (Acres)

After Expansion

(Acres)

Percentage, %

a. Refinery Project area-2791acre

Green Belt(a) 580 0 580 20.78

b. Residential Area-314acre

Green Belt(b) 110 0 110 35.03

c.Other Office and Building-240acre

Green Belt (c) 85 0 85 35.42

d. On other's land

Green belt (d) 75 0 75

Total Green belt Area (a+b+c+d) 850 0 850 30.46

Note:

1.Paradip refinery project’s Latest EC granted in 2018- - J-11011/344/2016-IA. II(I) dt.11.10.2018 the condition

for green belt (GB) development was 748.72 acres land. Accordingly Green belt has been developed to comply the

EC condition. In subsequent year the plantation has been increased and as of now 850 acre of land is planted.

2.Additional tree plantation has been done on land in peripheral villages, along access roads, schools, panchayats,

nearby district areas etc.

3.IOCL Paradip refinery has already done tree plantations of suitable species about 8.5 Lakh including GB area.

Further plantation of 100000 trees is under execution.

4.Pardip is industrial area and IDCO Government of Odisha do not have any land for allocating to any industry.

5.Paradip Area is under SPA CEPI 2018 (NGT order OA 1038/2018 heariing date 10.07.2019) and Greenbelt

coverage is required 33% or 40 % .

6.IOCL will explore land for plantation from others e.g. District administration, Forest department of Odisha,

NHAI, SH / PWD etc. to meet the balance Green belt.

7.The Green belt alloted in section d(others land) is the land area near by schools and villages

SNO Description Existing Proposed Total

1 Total area of Green Belt (Ha) 343.983 113 343.983

2 Percentage of total project area

30.46 10 40.46

3 No. of Plants 809624 282500 1092124

4 Funds allocated 80962400 30000000 110962400

The land allocation for proposed green belt area is given in Annexure 29.

EIA Report

188 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-24 Green Belt Layout

EIA Report

189 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 2-28 Summary of Plantation for the year 2007-2020

SUMMARY OF PLANTATION

2007-08

2008-09

2009-10

2010-11

2011-12

2012-13

2013-14*

2014-15*

2015-16

2016-17

2017-18

2018-19

2019-20

2020-21

Total

Refinery 260750 215000 111250 - - - - - 3350 16000 19000 34783 3298 3065 666496

Township + CISF

50682 - 5000 5000 6000 3000 - 11460 - - 1000 - 500 2696 85338

Zero point - - - - - - - - - - - - 1560 - 1560

Jagatsinghpur (Balia)

- - - - - - - 32000 - - - - - - 32000

Cuttack (Kisanagar)

- - - - - - - 18630 - - - - - - 18630

PPT - - - - - - - - - - - - 5600 - 5600

TOTAL 311432 215000 116250 5000 6000 3000 0 62090 3350 16000 20000 34783 10958 5761 809624

EIA Report

190 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.16 Water Pollution Control Measures

In Paradip Refinery, to treat waste water, a state-of-the-art ETP with VOC capture system has

been installed. The typical configuration of ETP of Paradip Refinery consists of:

American Petroleum Institute (API) separator

Tilted Plate Interceptor (TPI)

Oily Dissolved Air Floatation (Oily-DAF)

Bio Tower

Aeration Tank and Clarifier

Biological Dissolved Air Floatation (Bio-DAF)

VOC Removal Facility

Reverse Osmosis (RO)

Waste water collection systemAPI/TPI Equalization tank Oily DAF Bio Tower

Aeration Tank Clarifier Bio DAF Final collection Basin. Oil recovered in API/TPI

is collected in Slop tank. VOC system is installed all the oil laden sources like Slop Tank,

Brine Tank, Equalization Tank and Oily DAF.

The Refinery Effluents contains pollutants like oil (Free and Emulsified) BOD, COD and

suspended solids, which are required to be removed before discharging the effluent for

further reuse. Primary treatment is provided for the part removal of free oil in the influent in

the units like API separator followed by TPI separator. Emulsified oil will be removed in the

secondary Oil Separation units like DAF System. Here coagulant and flocculent used for

better separation.

After Secondary Oil removal the influent is led into biological treatment for removal of BOD.

Here, Bio Tower (attached growth process) and Aeration (suspended growth process) are two

biological treatment system. Oil free water undergoes bacteriological treatment under aerobic

condition for removal of COD and BOD. Then suspended flocs from aeration tank are

removed in the clarifier. Clear supernatant routed to bio DAF wherein suspended solids

removed with pressurized stream from treated effluent. This effluent is collected in the check

basin which is a feed to RO system.

There is also sludge treatment facility. The Sludge is categorized as Oily Sludge and Bio-

Sludge and is treated separately. The Bio Sludge is thickened and dewatered separately and

then sent for final disposal as manure. The Oily Sludge will be thickened and pumped to

DCU unit for further processing

EIA Report

191 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

After primary and secondary treatment completed in ETP section, treated effluent collected in

check basin is sent for tertiary treatment for achieving maximum recycle. Tertiary treatment

comprises the following:

Treated effluent from check basinRGSF Basket Strainer UF Skid Cartridge filter

RO skid RO Permeate tank UCR for reuse

During the process of filtration in RGSF (Rapid Gravity Sand Filter), the impurities are

removed from water. They precipitate in the voids between the grains of the filter bed. The

specific grain size is 0.5 mm to 2 mm.

After filtration, basket strainers are provided for trapping any sand particles that may leak out

and go into ultra-filtration system thus causing choking in the UF system.

Ultra-filtration is a membrane process in which a porous membrane is used to separate or

reject colloidal and particulate matter.

UF permeate then enter into the Micron cartridge filter for removal of particle of size upto 5

micron. Then the output enters into the Reverse Osmosis (RO) system. Two stage RO system

having 5 skids is installed to get the desired output @ 78% recovery.

Then finally RO permeate passed through the degasser tower to reduce CO2 before sending it

to UCR for reuse in DM plant and CT make up. The Flow diagram of ETP and WRP is given

in Figure 2-26 and Figure 2-27 respectively. The Treated effluent characteristics is given in

Table 2-29. Latest Analysis report of effluent characteristics discharging into sea is enclosed

in Annexure 32.

Inlet to ETP

Desalter brine and OWS/CRWS water treated in API/TPI

Stripped Sour water treated in OILY DAF

Steam Blow down and CT Blow down directly to water recovery through check basin

Landfill leachate and SCTP treated oxidized spent caustic to Bio Tower

Domestic sewage in aeration tank

ETP drain to API/TPI

EIA Report

192 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-25 Flow diagram of Effluent Treatment plant (Existing)

Figure 2-26 Flow diagram of Effluent Treatment plant (Proposed)

EIA Report

193 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-27 Flow Diagram of WRP Plant (Existing)

Table 2-29 Characteristics of Effluent Generated

ETP inlet (effluent generated) data in Jan’21

S. NO. PARAMETER TEST METHOD UoM RESULTFLOW (m3/hr)

1 pH IS 3025 (P:11) - 9.92 BOD IS 3025 (P:44) mg/l 1803 COD IS 3025 (P:58) mg/l 13704 Oil & Grease IS 3025 (P:39) mg/l 2645 TSS IS 3025 (P:17) mg/l 846 Sulphide IS 3025 (P:29) mg/l 4.37 DO IS 3025 (P:38) mg/l ND8 Alkalinity IS 3025 (P:23) mg/l 1919 NH3 IS 3025 (P:34) mg/l 29.510 Conductivity IS 3025 (P:14) μs/cm 111711 ORP APHA 2580 mV 20

Table 2-30 Characteristics Final effluent discharge to sea

SlNo Parameter

sTest Method UoM

Limits as per MINAS Results

1 pH IS 3025 (P:11) - 6.0 -8.5 8

2 BOD IS 3025 (P:44) mg/l 15 9 3 COD IS 3025 (P:58) mg/l 125 78

4 Oil &Grease

IS 3025 (P:39) mg/l 5 <4.0

5 TSS IS 3025 (P:17) mg/l 20 <4

EIA Report

194 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

SlNo

Parameters

Test Method UoMLimits as

per MINAS Results

6 Sulphide IS 3025 (P:29) mg/l 0.5 <0.10

7 Phenol IS 3025 (P:43) mg/l 0.35 0.09

8 Cyanide IS 3025 (P:27) mg/l 0.2 <0.02

9 NH3 IS 3025 (P:34) mg/l 15 1.2

10 Alkalinity IS 3025 (P:23) mg/l 172

11 Chloride IS 3025 (P:32) mg/l 973

12 TDS IS 3025 (P:16) mg/l 1001

13 Turbidity IS 3025 (P:10) NTU

<0.1

14 TKN ASTM D3590 A mg/l 40 2.1

15 P IS 3025 P:31 b mg/l 3 0.068

16 Cr(VI) IS 3025 P:52 a mg/l 0.1 <0.1

17 Cr total APHA 23rd edition 3125 A &B

mg/l 2 <0.1

18 Pb APHA 23rd edition 3125 A &B

mg/l 0.1 <0.001

19 Hg APHA 23rd edition 3125 A &B

mg/l 0.01 <0.001

20 Zn APHA 23rd edition 3125 A &B

mg/l 5 0.016

21 Ni APHA 23rd edition 3125 A &B

mg/l 1 0.011

22 Cu APHA 23rd edition 3125 A &B

mg/l 1 0.003

23 V APHA 23rd edition 6200 B. mg/l 0.2 <0.001

24 Benzene USEPA 8260C usingcapillarycolumn and MSD with

mg/kg 0.1 <0.005

2.17 Proposed Effluent Treatment Plant

Effluent generated from Purified Terephthalic Acid (PTA), Paraxylene (PX) and & offsite

and utilities plant are to be collected, segregated and treated in ETP to meet applicable

regulatory requirements before final disposal. RO based treatment is envisaged for final

disposal. Rejectsfrom RO plant to be transfer in sea. The Layout of Proposed Effluent

Treatment Plant is given in Figure 2-28.

Effluent Treatment Plant Configuration for PX-PTA integrated Complex have complete

Effluent Treatment Plant including WWT plant and effluent & disposal facilities includes the

following sections

Surge & Equalization System

Anaerobic Treatment System

Aerobic Treatment Section

Water Filtration Section (Tertiary treatment)

Sludge Handling & Separation System

EIA Report

195 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

New ETP is proposed for installation to process effluent @ 408 m3/hr with 10% design

Margin (Maximum capacity with high TOC).

2.17.1 PX Effluent Treatment

PX effluent at first treated in Pre-Treatment plant due to high aromatic content. The purpose

of PRE-TREATMENT PLANT is to reduce Benzene and other Aromatics in the feed to the

effluent treatment plant.

The following effluent streams are to be routed to the Pre treatment Plant for removal of

Benzene and other Aromatics:

HC contaminated effluent shall be treated by combination of distillation operation on

continuous mode followed by carbon bed adsorption as guard bed.

The PX (ISBL) effluent streams are routed to the Pre-treatment Plant for removal of

Benzene and other Aromatics:

Distillation column diameter shall be adequate to handle the surge flow.

Downstream carbon bed adsorption system shall be designed for 5% of wastewater

feed hydrocarbon load.

Adsorption system shall act as a guard bed and shall be designed for hydraulic load

Suitable filters shall be provided for removal of grease upstream of the distillation

column.

Pre-treated effluent / Off spec Tank shall be provided downstream the carbon bed

adsorption system as a buffer tank for absorbing shock to ETP.

During normal operation of EPTP, pretreated effluent will be collected in this tank and will

be transferred to ETP for further treatment.

Treated effluent from Pre-treatment Plant shall have benzene concentration less than 10 ppm

and total Aromatics (including Benzene) less than 20 ppm

2.17.2 PTA Effluent Treatment

a) Equalization section

PTA plant process wastewater streams are piped to the Surge Tank and then to Equalization

Tank. The surge tank collects the relatively high and periodic flows from the sources. The

holding / storage provided by the surge tank allows for controlled, reduced flow transfer to

the equalization tank

EIA Report

196 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

b) Anaerobic Treatment System

The equalized effluent is pumped to a conditioning tank. Chemicals are added into the

conditioning tank (mostly neutralized chemicals and nutrients etc.). From the conditioning

tankthe neutralized effluent is then fed to the proposed Anaerobic Reactor, UASB (Upflow

Anaerobic Sludge Blanket Digester) by use of reactor feed pumps. Target COD reduction in

anaerobic reactor is >80% (After complete stabilization). The anaerobically treated

wastewaterwith reduced COD load from the reactor top is allowed to flow by gravity to the

aerobic wastewater treatment system. Methane rich biogas collected in reactor top is

conveyed to BiogasHandling System. Condensate traps to be provided at the inlet line of

Biogas Handling Systemto remove condensate from biogas. From the biogas zone of the

anaerobic reactor, the biogasis drawn through biogas compressors/ liquid ring pump

pressurized and then sent to flaresystem for flaring.

c) Aerobic Treatment Section

After treatment in anaerobic section, the process waste water will be routed to effluent

treatment & disposal facilities for final treatment. Treated wastewater from anaerobic section

iscombined with boiler; cooling tower and demineralized water blow down streams and are

routed to effluent treatment & disposal facilities for final treatment. Along with process water

effluent streams, the other liquid effluents stream like contaminated rain water streams shall

also be separately routed to effluent treatment and disposal facilities for final treatment. The

effluents pass through aeration tank and clarifier before moving to water filtration section.

Aerobic section shall be designed to handle Cooling Tower blowdown and sider stream filter

waste water.

d) Tertiary Treatment:

Water filtration section is located in downstream the Aerobic Treatment Units. The aerobic

effluent coming from aeration & clarification systems contains a significant amount of

suspended solids that need to be removed by means of a tertiary treatment. Tertiary treatment

section includes:

Filtration system through pressure sand filter

Activated carbon Filters

Ultra filtration and RO based system

EIA Report

197 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

e) Sludge Handling & Dewatering System

Dewatering system for sludge generated from plant will be done by using belt presswhich

will be a common facility for all streams. Hopper and sludge loading facilities will also be

provided. The sludge will be dewatered from inlet consistency of 3-4% solids to ~22% solids

in the belt press. The filtrate from belt press will be recycled back to aeration tank. Solid

collection with necessary trolley, handling and disposal from the RO unit will be done

suitably.

EIA Report

198 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-28 Effluent Treatment plant (Proposed Layout)

EIA Report

199 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2.18 Solid waste Management

a) During Construction Phase

During construction phase 2.4394 TPD of solid waste is envisaged. It will be the scope of the

contractor to collect and dispose the solid waste generated during construction phase as per

PCB norms.

b) During Operation Phase

During Operation Phase Total of 864.9 Kg/day of solid waste is generated of which 518.94

kg/Day of organic waste will be used in the existing organic waste converter and remaining

Inorganic waste will be disposed through authorized vendors. The existing and proposed

waste generated is given in Table 2-31

Table 2-31 Solid Waste in Operational Phase

S.

No

List of

Items

Quantity (Kg/day) Treatment / disposal method

Existing ProposedAfter

Expansion

1 Organic

waste 410.94 108 518.94

Will be used in the existing

organic waste converter and the

resultant solid is used as manure

2 Inorganic

waste 273.96 72 345.96 Authorized OSPCB vendors

Total 684.9 180 864.9

As per CPCB 0.45 kg/ capita/ day

2.19 Hazardous Waste Management

The hazardous wastes generated from the ISBL Process Plant mainly consist of spent. The Existing & Proposed Hazardous waste generation is given in Table 2-32

Table 2-32 & Table 2-34 respectively. The Secured ladfill area photography is given in Figure

2-28 and the getextile membrane provided around the SLF area is given in Figure 2-30. The

location of SLF in IOCL Paradip Refinery is 20°16'5.25"N, 86°36'20.51"E. The Hazardous

waste authorization- IND-IV-HW-930/5028 dated 24.05.2019 valid till 31.03.2024 is attached

in Annexure 14.

EIA Report

200 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 2-32 Existing Hazardous Wastes Generation

S.No.

Details of Waste

Scheduled as per HWM rules

Existing Quantity TPY

Approved Quantity

TPY Frequency of disposal

Storage and Disposal

1 Spent

catalyst Schedule-I

4.2 2484.4 2500

Within 90 days

Stored in intermediate storage facility

(covered warehouse with impervious floor

and shed)

Disposal in SLF -1497.4 / Co-

processing in cement industry - 987

2 Spent Clay

Schedule-I 4.5

145.5 720 Within 90

daysDirectly sent to SLF

3 Ash Schedule-I

37.2 36.0

- Within 90 days

Directly sent to SLF

4 Oily

Sludge Schedule-I

4.1 1456.1

2748 (Oil sludge/

Emulsion/ Slop Oil)

Within 90 days

Directly sent to DCU for processing

5 Oily

Sludge Schedule-I

4.1 74.2

Within 90 days

Stored in impervious metallic containers before unloading in melting pit for oil

recovery Sludge is disposed in

HW incinerator

6 Coke Schedule-I

4.416.7

180 Within 90 days

Sent to incinerator for disposal

Table 2-33 Proposed Hazardous Wastes Generation

S.No. Details of Waste Scheduled as

per HWM rules

Proposed

Quantity TPD

Frequency of disposal

Storage and Disposal

PX

1 Spent Clay from Clay Treaters

Schedule-I 4.5

0.12 Within 90

daysCaptive SLF

2 Spent Catalyst from Reactor

Schedule-I 1.6

0.01 Within 90

days

Metals Recovery or Landfill in Captive SLF

3 Spent Clay from Clay Treater

Schedule-I 4.5

1.44 Within 90

daysCaptive SLF

EIA Report

201 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4 Spent Adsorbent from Adsorbent Chambers

Schedule-I 1.6

0.24 Within 90

days Captive SLF

5 Catalyst from Reactor

Schedule-I 1.6

0.04 Within 90

days

Metal recovery by authorized

recycler

6 Spent Clay fromClay Treater

Schedule-I 4.5

0.26 Within 90

days Captive SLF

PTA

7 PTA Spent CatalystSchedule-I

1.6 0.0438

Within 90 days

Recovery by catalyst

manufacturer

8 Filters, Oils Schedule-I

3.3/5.1 0.0685

Within 90 days

Disposal in authorized HW

incinerator / Sale to authorized

users

9 Pails, Corrosion, Paint

Schedule-I 21.1

0.0137 Within 90

days Sale to authorized

users

10 Laboratory Solvents

Schedule-I 20.2

0.0003 Within 90

days Disposal in ETP

11 Waste Solvents Schedule-I

20.20.0110

Within 90 days

Disposal in ETP

Figure 2-29 Google Earth demarcation of SLF area in IOCL Paradip Refinery

EIA Report

202 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-30 Photograph of Secured Landfill Area with Geotextile Membrane around it

in IOCL Paradip Refinery

Figure 2-31 Lablelling of Hazardous waste Containers

EIA Report

203 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-32 Hazardous Waste labelsdisplayed on packaging

19.06.2021 19.06.2021

19.06.2021

EIA Report

204 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 2-33 Hazardous Waste Storage area

19.06.2021 19.06.2021

19.06.2021 19.06.2021

EIA Report

205 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CHAPTER 3

DESCRIPTION OF ENVIRONMENT

EIA Report

206 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3 DESCRIPTION OF ENVIRONMENT

3.1 Preamble

This chapter depicts the establishment of baseline for valued environmental

components, as identified in and around the proposed project with an area of 3,345 Acres

(1353.673 Hectare) located at IOCL Paradip Refinery, Paradip, Jagatsinghapur District,

Odisha state. The primary baseline data monitored covered three (3) months i.e., from March

to May 2019, and secondary data was collected from government and semi-government

organizations published data. The primary baseline data has been generated by m/s. Hubert

Enviro Care Systems (p) ltd, Chennai, a MoEF&CC approved environmental testing

laboratory for the following terrestrial environmental components.

Meteorology: Temperature, Relative Humidity, Rainfall, Wind Speed & Direction-

Refer Section - 3.6.1

Ambient Air Quality: Particulate matter <10-micron size (PM10), Particulate matter

<2.5-micron size (PM2.5), Sulphur Dioxide (SO2), Nitrogen Dioxide (NO2), Carbon

Monoxide (CO), Lead (Pb), Ozone (O3), Benzene (C6H6), Benzo (a) pyrene (C20H12),

Arsenic (As), Nickel (Ni), Ammonia (NH3) & VOC- Refer Section - 3.7

Ambient Noise Levels: Day equivalent noise levels, Night equivalent noise levels -

Refer Section - 3.8

Inland Water Quality: Groundwater Quality, Surface Water Quality - Refer Section

- 3.9

Soil Quality - Refer Section - 3.10

Biological Environment - Refer Section - 3.11

Social Economic Status - Refer Section - 3.12

3.2 Study Area

A 10 Km radial distance with the project site boundary as the epicentre has been identified as

the General study area for assessing the baseline environmental status. The core study area is

the project area and its immediate surroundings to the tune of 1.0 Km radius from the

boundary. Further the Project Impact/Influence Area (PIA) is 10Km from the boundary of the

core area covering IOCL Paradip Refinery, Paradip, Jagatsinghapur District, Odisha State.

3.3 Description of Study Area

As Described in Chapter 1, M/s IOCL Paradip Refinery project site is located at Paradip,

Jagatsinghapur district, Odisha state. The project site is well connected with road, rail and

EIA Report

207 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

water ways, where Paradip Railway station is located at a distance0.54 Km WNW from the

project boundary and Biju Patnaik International Airport, Bhubaneshwar is located at a

distance of 79.03 Km towards W from project boundary and Paradip Port is located at a

distance of 5.77 Km towards E from project boundary. An overall idea of the study area

with reference to the physical conditions are presented for better understanding in the

following sections before proceeding into the section on the prevailing environmental

conditions of the study area. The map showing the satellite image of the study area is given

in Figure 3-1and Topo Map of the study area is given in Figure 3-2.

EIA Report

208 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-1Map showing the Satellite Image of the study area of Project

EIA Report

209 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-2Topo Map of Study area

EIA Report

210 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.4 Environmentally/Ecologically Sensitive areas

This section details with the environmentally sensitive areas present within the project site

and surrounding environs. It included national parks, state forest, essential habitats etc. The

environmental sensitive areas covering an aerial distance of 15 km from the project boundary

is given in Table 3-1 and Figure 3-3

Table 3-1 Environmentally Sensitive Areas within 15km from Project Boundary

S.

No. Areas Distance & Direction from project boundary

1 Areas protected under

international conventions,

national or local

legislation for their

ecological, landscape,

cultural or other related

value

Nil

2 Areas which are important

or sensitive for ecological

reasons – Wetlands,

Watercourses or other

water bodies, coastal zone,

biospheres, mountains,

forests

Sl. No

Description Distance (~Km) Direction

Ocean, Rivers and Canals 1 Bay of Bengal 0.55 SE 2 Mahanadi River 6.18 NNE 3 Paika River 8.62 NW 4 Taladanda canal 4.87 ENE

Forests 5 BhitarKharinasi R.F 12.58 NE6 Protected Forest 0.76 SSW 7 Jatadharbaratanda P.F 6.09 SSW 8 Jogidhankud P.F 9.68 ENE 9 Saralikud P.F 11.45 ENE

10 Sanatubi P.F 12.09 NE 11 Petachhola P.F 13.15 NNE 12 P.F 14.76 ENE

Nadi

13 Dhenkiagalia Nadi (adjacent to project site) 0.03 W

14 Santara Nadi (adjacent to project site) 0.08 E

15 AtharabankiNadi 1.03 E 16 MahangaNadi 1.21 W 17 JatadharmuhanNadi 2 SSW 18 GarhigirhiNadi 6.89 NNW 19 NunaNadi 7.02 N 20 PaunshiapatNadi 7.15 NNW

EIA Report

211 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

No. Areas Distance & Direction from project boundary

21 GuptiNadi 7.46 NNE 22 BoitaraNadi 8.26 ENE 23 Kula Nadi 9.04 NNW 24 AkharhaahallNadi 9.27 NNE25 ArholNadi 9.28 NNE 26 KharinasiNadi 9.34 NE27 PotaNadi 9.65 WSW 28 KaduamadoliNadi 9.83 ENE 29 KholaNadi 9.86 NE30 GuptagiriNadi 12.01 NNE 31 SonakhodaNadi 12.03 NNE32 Nara Nadi 14.82 SW 33 MajurahiJor 12.94 ENE34 Bruddha N 13.82 W 35 Haldia N 13.87 WSW 36 Saunlia N 13.33 SW37 Harhua N 8.16 W

Nala38 MusharhiaNala 6.27 ENE 39 ChandapurNala 6.56 WNW39 BarhatubiNala 10.3 NE 40 SanatubiNala 11.18 NE 41 GaliaNala 11.59 NE42 BatigharGaliaNala 12.31 ENE 43 ShalijangaNala 13.08 NW

3 Areas used by protected,

important or sensitive

species of flora or fauna

for breeding, nesting,

foraging, resting, over

wintering, migration

Mahanadi Delta has extensive mangrove forests located at a

distance 6.93km(NE) from the project site

The Kujang Coast and Hetamundia Seashore Village is

predominant turtle nesting area.

Mangroves are present in Santara creek which bifurcates

the refinery into North & South parts

There are two Schedule-I Species in study area i.e., reptiles

named Nilssoniahurum (Gray 1831) and Lissemyspunctata

(Bonnaterre 1789) habitats.

4 Inland, coastal, marine or

underground waters

Sl. No

Description Distance (~Km)

Direction

Inland

1Dhenkiagalia Nadi (adjacent to project site) 0.03 W

2Santara Nadi (adjacent to project site) 0.08 E

3 AtharabankiNadi 1.03 E 4 MahangaNadi 1.21 W 5 JatadharmuhanNadi 2 SSW

EIA Report

212 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

No. Areas Distance & Direction from project boundary

6 Taladanda canal 4.87 ENE 7 Mahanadi River 6.18 NNE8 GarhigirhiNadi 6.89 NNW 9 NunaNadi 7.02 N 10 PaunshiapatNadi 7.15 NNW 11 GuptiNadi 7.46 NNE 12 BoitaraNadi 8.26 ENE13 Paika River 8.62 NW 14 Kula Nadi 9.04 NNW15 AkharhaahallNadi 9.27 NNE 16 ArholNadi 9.28 NNE 17 KharinasiNadi 9.34 NE 18 PotaNadi 9.65 WSW 19 KaduamadoliNadi 9.83 ENE20 KholaNadi 9.86 NE 21 GuptagiriNadi 12.01 NNE22 SonakhodaNadi 12.03 NNE 23 MajurahiJor 12.94 ENE 24 Nara Nadi 14.82 SW

Coastal 25 Bay of Bengal 0.55 SE

5 State, National boundaries Nil

6 Routes or facilities used

by the public for access to

recreation or other tourist,

pilgrim areas

NH 5A (Chandikhol – Paradip Port highway), ~3.67 Km, N

7 Defence installations Coast Guard Dist. HQ~4.11km, ENE

8 Densely populated or

built-up area

(Nearest Town, City,

District)

Paradip (Population: ~68585 nos.), ~3.05 Km, E

9 Areas occupied by

sensitive man-made land

uses (hospitals, schools,

places of worship,

community facilities)

Sl.

NoDescription

Distance

(~Km) Direction

Hospital1 Vivekananda Hospital 2.76 NNE 2 Loyal Health Care Paradip 4.18 ENE 3 Port hospital 4.42 ENE4 ESI Hospital 4.8 NE 5 Biju Patnaik Memorial Hospital 5.06 ENE

Schools & Colleges1 Orissa Maritime Academy 2.34 ENE 2 Delhi Public School, IOCL 2.38 NNE

EIA Report

213 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

No. Areas Distance & Direction from project boundary

Township 3 NAC Municipal High School 3.04 NE 4 port school 3.19 ENE 5 Bethany Convent School 3.33 ENE6 V Point KG School 3.38 ENE 7 Saraswati Sishu Mandir 3.42 ENE8 Kendriya Vidyalaya Paradip Port 3.96 ENE

9 S.K.Academy English Medium School

4 NNE

10 Sagarika Kala Niketan 4.08 NNE11 Twinkle Twinkle 4.08 ENE 12 D.A.V Public School 4.54 ENE 13 St.Xavier's High School 4.55 ENE14 Maa Ambika High School 5.09 NNE 15 DAV Public School, IFFCO 6.59 NE16 B.B High School 8.29 WNW

Religious Places1 MaaRamachandiTemple 0.72 ENE 2 BasudebaTemple 1.71 WNW 3 Hanumantemple 1.94 WNW4 SetalaTemple 2.31 ENE 5 HanumanTemple 2.47 ENE6 JagannathMandir 2.6 ENE 7 LodGopalajiuTemple 3.75 WNW 8 MaaSantoshiTemple 4.09 ENE 9 BhadrakaliTemple 4.17 ENE

10 PandavTemple 4.22 ENE11 TariniTemple 4.22 ENE 12 MaaMangalaTemple 4.33 WSW13 MukteswarTemple 4.33 ENE 14 LordShivaTemple 4.75 WNW 15 RamGhatHanumanTemple 4.92 ENE 16 MaaBajraBudhiTemple 7.2 WNW 17 LaxminarayanTemple 7.74 WNW

10 Areas containing

important, high quality or

scarce resources,

(groundwater resources,

surface resources, forestry,

agriculture, fisheries,

tourism, minerals)

Fishing Harbour Paradip, ~9.5km NE

11 Areas already subjected to

pollution or environmental

Paradip Industrial area attracts CEPI score of 60.61 (CPCB

monitoring during 2018) (NGT proceedings)

EIA Report

214 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

No. Areas Distance & Direction from project boundary

damage (those where

existing legal

environmental standards

are exceeded)

12 Areas susceptible to

natural hazard which could

cause the project to

present environmental

problems, (earthquakes,

subsidence, landslides,

erosion or extreme or

adverse climatic

conditions)

Project site is located at seismic zone-III,

Paradip coast is prone to Cyclone and Tsunami.

EIA Report

215 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-3 Environmental sensitive areas covering within 15 km from project boundary

EIA Report

216 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.5 Physical Conditions of PIA district

In this section, the physical conditions of PIA district are discussed in general and

wherever possible references to the conditions prevailing in the study area in particular are

also provided. The physical conditions are discussed as under:

District profile

Drainage, land use, geology, Physiographic profile

Natural resources

Climatic conditions, seismic zone characteristics and natural hazard

3.5.1 PIA District Profile

Jagatsinghapur District is one of the coastal district of Odisha. It lies between 19°58’ and

20°23’N latitude and 86°30’ and 86°45’E longitude. The district is surrounded by the Bay of

Bengal in the East, Kendrapada District in the North, Cuttack District in the West and Puri

District in the South. It occupies an area of 1668 sq.kms which accounts for 1.07% of the

total area of the state.

This district is situated in the delta region of the river Mahanadi. The district comprises two

district tracts. The first being marshy and swampy stripes along with the coast covered with

wild growth of reeds and tropical jungle. The second tract covers fertile plain land. Since

1870, two big canals were built which supply water to this area. Also in the year 1960, a

natural sea port i.e., Paradip port was built on the Bay of Bengal.

Source:http://censusindia.gov.in/2011census/dchb/DCHB_A/21/2111_PART_A_DCHB_JAG

ATSINGHAPUR.pdf

3.5.2 Climatic Conditions

The south-west monsoon is the principal source of rainfall in the district. The district is

characterized by a Topical monsoon climate having three distinct seasons in a year viz.

winter, summer and rainy seasons. The Bay of Bengal, which forms the eastern boundary of

the district, plays a vital role in controlling the climate of the district. The Normal rainfall of

the district is 1501.3 mm. The annual average rainfall in last seven years is 1436 mm. About

75% of the total rainfall occurs during the period from June to September. In the period

between April and May 3 to 4 cyclonic rains generally occur in the district that causes a drop

in the temperature. The temperature varies from 15 to 37ºC. The relative humidity varies

from 74 to 86 percent during the year.

Source: http://cgwb.gov.in/District_Profile/Orissa/jagasingpur.pdf

EIA Report

217 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.5.3 Natural Resources of PIA District

3.5.3.1 Flora & Fauna

The forest area is only 8% of total geographical area. There is no natural forest worth

its name in this district. Hental (phoenix paludosa) grows here abundantly in clusters, which

is scattered and confined to the sea-coast. The mangrove forests are locally called ‘Hental

Van’ or Hental forests. Rich vegetation accounts for widespread of wildlife. Among the

animal’s crocodiles are common. Also varieties of birds are seen along the coastal areas.

Flora and Fauna of PIA are discussed in Section 3.11.

Source:

http://censusindia.gov.in/2011census/dchb/DCHB_A/21/2111_PART_A_DCHB_JAGATSING

HAPUR.pdf

3.5.3.2 Forest Resources

The little forests found in Jagatsinghapur District are of moist mixed deciduous Forests,

North tropical deciduous forest. Forest Type prevalent in this district is the Sal dominated

mixed deciduous forest. The forest cover area of the district is 133 Sq.Km., out of

geographical area of 1668 sq.km which is a moderately dense forest, and 127 sq.km is open

forest. The district is having 132.92 km of DLC forest area. However, on introduction of

Forest Rights Act, 2006, 47 titles have been distributed to the forest dwellers involving about

31.83 acres of forest land. The Dhartang Garh PRF comprising an area of 112.92 ha. of forest

stands for scenic beauty and an excellent habitat for wildlife. Its radius is 07 Km. This forest

is surrounded by Gopalpur G.P of Jagatsinghapur district. This forest consists of variety of

flora and fauna and some rare species of medicinal plants such as Satabari, bishalyakarani,

Patalgaruda, kochila, Karanja, Ashok, Amla, Bela and tree species like Teak, Bamboo,

Mahagani, Deodaru, Panasa etc. and wildlife like deer, monkey, jungle mouse, fox, hyna and

different types of birds such as, koel, chilla, jhinka, pecha, Rajamani, Haladibasanta,

Kumbhatua, Badudi etc. Visitor immunity and recreational facilities have been developed for

casual visitors to the forest and for wild life lovers. Local villagers have been motivated to

help forest people immensely in tracking down the poachers to control the wildlife crime and

ensure forest protection. Hence a VSS has been formed comprising local inhabitants from

Goplapur village and Pandra village. The Kilipal PRF comprises an area of 161.98 ha of

forest. Its radius is 11.60km. This forest is protected by Paruna VSS. They keep a constant

watch on the forest arranging roster duty, as a result of which, forest density is showing an

upward trend.

EIA Report

218 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Source:

http://gopabandhuacademy.gov.in/sites/default/files/gazetter/Jagatsinghapur_Gazetteer.pdf

3.5.3.3 Irrigation

Water is an important factor than soil. An ample and well distributed rainfall is a matter of

vital importance to cultivators. In most of the years the amount of rainfall is sufficient, the

average being 58 inch per annum. But it is unevenly distributed causing deficiency in critical

months to crops. That is why artificial irrigation becomes absolutely necessary. Now-a-days

the country has started implementing bold economic reforms in the agriculture sector. The

Odisha Lift irrigation Corporation (OLIC) hydrologist assesses the water potential in the

district. The Odisha Agro Industries Corporation (OAIC) also undertakes the work of digging

bore well by private enterprises. Under watershed development project for rain fed,

agriculture, mini watersheds are identified. Under this scheme, cultivators are motivated to

switch over to the cropping pattern by providing inputs under crop demonstration

programme. The Source wise Irrigation potential created during the year 2009-10 & 2010-11

is given in Table 3-2

Table 3-2 Source wise Irrigation potential created during the year 2009-10 & 2010-11

Year

Major/Medium

Irrigation

Project

(Hectares)

Minor

Irrigation

Project

(Flow)

(Hectares)

Lift

Irrigation

Project

(Hectare)

Other

Sources

(Hectare)

Total

(Hectare)

Kharif Rabi Kharif Rabi Kharif Rabi Kharif Rabi Kharif Rabi

2009-

10 34.77 17.17 0.0 0.0 11.77 6.13 25.83 13.52 72.37 36.82

2010-

11 34.77 17.17 0.0 0.0 11.85 6.17 28.98 28.86 75.6 52.2

Source:

http://censusindia.gov.in/2011census/dchb/DCHB_A/21/2111_PART_A_DCHB_JAGATSING

HAPUR.pdf

EIA Report

219 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.5.3.4 Agricultural Resources

Agriculture starts just before monsoon. The cultivators plough their fields in the month of

May and sowing of grain starts from Akshaya Trutiya i.e., last part of May. There are two

seasonal crops namely Kharif and Rabi. Growing and harvesting in rainy, autumn and winter

season is known as Kharif crop whereas the said operation after winter and in summer is

known as Rabi crop throughout all the districts of Odisha. Paddy is the main crop. In addition

to this coconut, mango, banana, pineapple etc. and another cash crop pan (betel leaf) are also

cultivated in this district. Among other cereals wheat, maize etc. pulses like mung, oilseeds

like groundnut, tin, sunflower etc. and sugarcane are also produced in the district. During the

year 2010-11, out of 111 thousand hectares’ cultivable land, Kharif and Rabi paddy covered

88 thousand hectares, which were 47.37% of gross cropped area of 179.60 thousand hectares.

The paddy production was 138.96 thousand MT. The Net area sown and Gross cropped area

during 2010-11 were 91 and 186 thousand hectares respectively and the cropping intensity

was 204%.

Source:

http://censusindia.gov.in/2011census/dchb/DCHB_A/21/2111_PART_A_DCHB_JAGATSING

HAPUR.pdf

3.5.3.5 Mineral Resources

Heavy minerals: The beach and sand dune deposit, along the coast, contains heavy minerals

like monazite, rutile, illeminite and zircon etc. Such deposits are seen around Dhenkia-

Nuagaon sector of the district covering 8km coastal length and having 17.35 Million Tonnes

of total heavy mineral deposit with a grade of 5.90% of heavies. The Mineral Map of Odisha

(Orissa) is given in Figure 3-4

River Sand deposits: The river sand deposits have been reported around Alipingal, Nuapada,

Hazipur-Nuapari, Erada, Madhysasan, Sikhar, Tarpur-Gokulpukr, Mundilo and Jaipur area

along the Devi and Mahanadi rivers of the district and suitable for sand mining.

Clay: Silty clay of Upper deltaic deposit is used for brick kiln industry.

Source:http://gopabandhuacademy.gov.in/sites/default/files/gazetter/Jagatsinghapur_Gazette

er.pdf

EIA Report

220 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-4 Mineral Map of Odisha (Orissa)

EIA Report

221 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.5.4 Land Use & Land Cover

Total geographic area of Jagatsinghapur district is 1668 Sq.Km. Urban Builtup area is

52.12 Sq.Km and Rural Builtup area is 253.25 Sq.Km. Details of land use/land cover

statistics for Jagatsinghapur district were given in Table 3-3. Land Use pattern of

Jagatsinghapur district is given in Figure 3-5and Land use map of Jagatsinghapur district is

given in Figure 3-6

Table 3-3 District land use/land cover statistics (2011-12) for Jagatsinghapurdistrict

S.N

o. Division of Land Use/Land Cover

Area in

Sq.Km.

Area in

acres

Area in

Ha Area (%)

1 Builtup, Urban 52.12 12879.11 5212 3.125

2 Agriculture, Crop Land 1090.61

269495.1

8 109061 65.384

3 Agriculture, Fallow 2.68 662.24 268 0.161

4 Forest, Forest Plantation 0.36 88.96 36 0.022

5 Forest, Swamp/ Mangroves 6.54 1616.07 654 0.392

6 Barren/ unculturable/ Wastelands,

scrub land 5.65 1396.14 565 0.339

7 Wetlands/Water Bodies, Inland

Wetland 16.36 4042.64 1636 0.981

8 Wetlands/water Bodies, River

stream/Canals 134.31 33188.67 13431 8.052

9 Builtup, Rural 253.25 62579.34 25325 15.183

10 Agriculture, Plantation 1.94 479.38 194 0.116

11 Forest,Deciduous 22.17 5478.32 2217 1.329

12 Forest,Scrub Forest 0.69 170.50 69 0.041

13 Barren/Unculturable/Wastelands, Salt

Affected land 10.62 2624.26 1062 0.637

14 Barren/unculturable/Wastelands,

Sandy Area 10.08 2490.82 1008 0.604

15 Wetlands/Water Bodies, coastal

Wetland 23.84 5890.98 2384 1.429

16 Wetlands/Water Bodies, 36.78 9088.52 3678 2.205

EIA Report

222 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.N

o. Division of Land Use/Land Cover

Area in

Sq.Km.

Area in

acres

Area in

Ha Area (%)

Reservoir/Lakes/Ponds

Total1668.00

412171.1

4 166800 100

EIA Report

223 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-5Land use pattern of the Jagatsinghapur District

EIA Report

224 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-6Land use map of the Jagatsinghapur District

EIA Report

225 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.5.4.1 Land Use and Land Cover of the Study Area

Total Project Study area is 490.48 Sq.Km. The Land Use Pattern is given in Table 3-4. The

Land Use Pattern and Land Use Map of the Study area are given in Figure 3-7and Figure

3-8 respectively.

Table 3-4 Land Use Pattern of the Study Area

S.No. Description Area (Sq.

km)

Area

(Acres)

Area

(Hectares)

Percentage

(%)

1 Fallow land 80.69 19938.90 8069 16.45

2 Cropland 78.02 19279.13 7802 15.91

3 River/ Stream/ Canals 46.63 11522.51 4663 9.51

4 Urban 40.06 9899.03 4006 8.17

5 Rural 27.68 6839.87 2768 5.64

6 Coastal wetland 17.48 4319.40 1748 3.56

7 Deciduous 10.30 2545.18 1030 2.10

8 Salt affected land 7.16 1769.27 716 1.46

9 Reservoirs/ Lakes/

Ponds 4.96 1225.64 496 1.01

10 Sandy area 2.62 647.42 262 0.53

11 Scrub land 2.26 558.46 226 0.46

12 Swamp/ mangrove

forest 2.00 494.21 200 0.41

13 Inland Wetland 1.61 397.84 161 0.33

14 Scrub Forest 1.21 299.00 121 0.25

15 Forest plantation 0.25 61.78 25 0.05

16 Plantation 0.08 19.77 8 0.02

17 Ocean 167.47 41382.92 16747 34.14

Total 490.48 78925.34 49048 100

EIA Report

226 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-7 Land Use Pattern of the Study Area

EIA Report

227 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-8 Land Use Map of the Study Area

EIA Report

228 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.5.5 Topography

The district comprises two distinct tracts, the first being marshy and swampy strips along

with the coast covered with wild growth of reeds and tropical jungle. The second tract covers

fertile plain land. The soil is of alluvial type. Mahanadi, Kathajodi, Devi, Biluakhai are the

main rivers of the district. These rivers and two main canal Taladanda and Machhagaon are

irrigating the district. Physical map of Odisha is given as Figure 3-9 and Topo map of study

area is given as Figure 3-2 and contour map of the study area is given as Figure 3-10.

Source:http://dcmsme.gov.in/dips/2016-17/DIPS%20of%20Jagatsinghapur%202016-17.pdf

Figure 3-9Physical Map of Odisha

EIA Report

229 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-10Contour Map of Study Area

EIA Report

230 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.5.6 Geomorphology of PIA district

Physiographically the district can broadly have divided into two distinct units, viz. i. The

saline marshy tract along the coast ii. The very gently sloping plain

(i). The saline marshy tract forms a long and narrow strip along the coast. The width of this

tract varies from 3 to 15 km and is intersected by tidal streams and shrubby vegetation. Sand

dunes of varied relief extend continuously for kilometres parallel to the coast. These sand

dunes usually forming 5 to 6 chains are gently sloping on the bay side and steeply sloping on

the inland side, due to their Aeolian origin. The gently sloping alluvial plain occurs to the

west of the saline marshy tract and forms the most fertile part of the district.

(ii). The general slope of this tract is towards east and southeast and varies from 0.50 to 1.60

m/km. The distribution of different soil types in the district depends much on its

physiographic and lithologic variations. The Geomorphology Map of the Jagatsinghapur

District is shown as Figure 3-12.

Source:http://cgwb.gov.in/District_Profile/Orissa/jagasingpur.pdf

3.5.7 Geomorphology of the Study Area

Geomorphologically the study area within 10km radius of the site consisting three major

units such as Coastal Plains, Flood Plains and Estuarine zone. Based on the nature and age of

deposition the first two units viz., Coastal Plains & Flood Plains are divided into three and

two sub-units respectively. The coastal plains are classified as Younger coastal plains, older

coastal plains and Younger deltaic plains. The flood plains, which are developed due to the

impact of Mahanadi and its tributaries on the pre-existing landforms, are classified as

Younger flood plain, which is currently in active development stage and an older flood plain.

There is a zone of estuarine plains, where the Mahanadi river merges with sea, existing in the

northeastern part of the study area, which is typically, express the intermixing nature of beach

sands with river sands

The total Geographical area of the study area is 490.48 Sq.Km. The Geomorphology of the

study area is given in Table 3-5 and Geomorphology pattern and Geomorphology Map of the

study area is given in Figure 3-11and Figure 3-13respectively.

Table 3-5Geomorphology of the Study Area

S.No. Geomorphology Area in Sq.KmArea in

Acres

Area in

HectaresTotal Area %

1 Coastal Origin - Younger Coastal plain 91.86 22699.07 9186 18.73

EIA Report

231 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2 Coastal Origin - Older Coastal plain 76.56 18918.36 7656 15.61

3 Coastal Origin - Younger Deltaic plain 70.34 17381.37 7034 14.34

4 Fluvial Origin- Older flood plain 20.23 4998.93 2023 4.12

5 Fluvial Origin- Active flood plain 8.06 1991.67 806 1.64

6 Water bodies 219.06 54130.82 21906 44.66

Estuarine Plain 4.37 1079.85 437 0.89

Total 490.48 121200.06 49048 100

EIA Report

232 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-11Geomorphology Pattern of the Study Area

EIA Report

233 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-12Geomorphology Map of Jagatsinghapur District

EIA Report

234 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-13Geomorphology Map of the Study Area

EIA Report

235 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.5.8 Hydrogeology of PIA district

Recent Alluvium 0.57mbgl to 5.05mbgl 0.35mbgl to 4.82mbgl,

pre-monsoon shows rise of 0-2m in 37.5% of wells, and fall of 0-2m in 56.3% and 2-

4m in 6.3%of the wells.

post-monsoon shows rise of 0-2m in 57.1% of wells, fall of 0-2m in 42.9 % of the

wells.

The State is underlain by diverse rock types ranging in age from Archaean to Recent. The

State can be hydro geologically sub divided into consolidated, semi-consolidated &

unconsolidated formations. The consolidated formations include hard crystallines and

compact sedimentary rocks whereas semi consolidated formations include weathered and

friable Gondwana sedimentaries and loosely cemented Baripada beds. The unconsolidated

formations include laterites and recent alluvium. The yield of tubewells tapping granite

gneisse ranges between 10-35 m3/hr whereas other consolidated formations, it ranges

between 5-18 m3/hr. The yield of tubewells in semi-consolidated formations range between

20-115 m3/hr.The hydrogeology map of Jagatsinghapur District is given in Figure 3-14

Source:http://cgwb.gov.in/District_Profile/Orissa/jagasingpur.pdf

Geo-hydrological Status of the Study Area

The study area including the project site is part of coastal and fluvial alluvium developed due

to the deltaic nature of Mahanadi River with Bay of Bengal. The area is covered with thick

pile of younger and older alluvial formations to an extent of more than 100m bgl. Below the

alluvium there are sandstone formations with intercalation of clay beds are reported which

are part of ParadeepTechtonic Depression of Mahanadi Basin. These sedimentary formations

are extended more than 900m thickness which are successively underlined with basement

crystalline rocks.

Groundwater occurs in semi-confined to unconfined nature in the alluvial formations within

the study area. There are potential shallow fresh water aquifers existing within the study area

at 10 to 20m depth from the existing ground levels. Based on the observations made in the

existing bore wells it is understood that the groundwater level is between 3 to 4 mbgl.

Below the fresh water aquifers there are saline water aquifers which are present at 40 to 50m

bgl within the alluvial formations. The deeper aquifer system is also present within the

Paradeep Depression in deep seated sedimentary formations

EIA Report

236 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-14Hydrogeology Map of Jagatsinghapur District

3.5.9 Drainage Pattern in PIA district

The main rivers flowing in the district are Mahanadi, Saunlia, Alaka and Devi. The branches

of Devi river are Biluakhai, Gobari river where as the branches of Mahanadi are Paika,

Chirotpala and Hansua river. All the rivers and its branches fall into the Bay of Bengal. 1 The

problem of drainage becomes acute towards the lower reaches of the deltas. The coastal

ridges offer an effective barrier to a free discharge of the flood water. Sometimes the huge

sand deposits create marshy conditions and affect the production of crops. Due to its

geographical situation, the district is congenial and prone to occurrence of various natural

calamities like flood, cyclone and drought. To prevent the calamities, many river dam

projects, canal construction works and irrigation works were made in and nearby district.

Two main canals i.e. Taladanda and Machhagaon provide water for irrigation in the district.

The drainage map of the Study Area is given as Figure 3-15.

Source:http://censusindia.gov.in/2011census/dchb/DCHB_A/21/2111_PART_A_DCHB_J

AGATSINGHAPUR.pdf

EIA Report

237 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-15Drainage map of the study area

3.5.10 Geology

Geologically the study area including the site consisting of Alluvial formations of Recent

geological age. These alluvial formations are developed by the action of Mahanadi river and

Bay of Bengal sea. The alluvium developed due to the river action is designated as Fluvial

alluvium. Similarly, the alluvium developed due to the sea action is named as Coastal

Alluvium. The basement rocks are existing below 100m from the existing ground level. The

geological formation of this district is entirely alluvium of recent origin. The entire district

comes under Mahanadi Delta Division and Cuttack Coastal Plain. The region is formed over

the estuary of the Mahanadi. Geological map of Orissa is given as Figure 3-16.

Source:http://censusindia.gov.in/2011census/dchb/DCHB_A/21/2111_PART_A_DCHB_J

AGATSINGHAPUR.pdf

Figure 3-16Geology Map of Orissa

3.5.11 Seismicity

As per Vulnerability Atlas of India- 3rd Edition, the project location/study area falls in Zone

III, which is categorized as a Moderate Risk Zone. The seismicity map of India is shown in

Figure 3-17

EIA Report

239 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

.

Figure 3-17 Seismicity Map of India

EIA Report

240 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.5.12 Soils in PIA District

Based on the physical and chemical characteristics, mode of origin and occurrence, soils of

the district may be classified into three groups namely Alfisols, Aridisols and Entisols.

i.Alfisols: This includes deltaic alluvial soils and this type of soils occupies nearly 90% of the

entire district area. The deltaic alluvial soils are generally deficient in phosphate (P2O5) and

nitrogen (N). Both the total and available potassium are fairly adequate and PH varies

between 7.38 and 8.16.

ii.Aridisols: These are saline and saline alkali soils and occur in small pockets in the north

eastern and south eastern corner of the district near coast. These are rich in calcium,

magnesium and also consist of half decomposed organic matter.

iii.Entisols: This includes coastal sandy soils and occurs as narrow elongated ridge along the

coast line. The soils are deficient in nitrogen, phosphoric acid and humus, but not in potash

and lime.

Soil map of India is given in Figure 3-18.

Source: http://cgwb.gov.in/District_Profile/Orissa/jagasingpur.pdf

EIA Report

241 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-18 Soil map of India

3.5.13 Natural Hazards in PIA District

As per Odisha wind hazard map Jagatsinghapur district is falling under very high damage risk

zone B. Wind Hazard Map of India is given in Figure 3-19.

EIA Report

242 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-19 Wind hazard Map of India

3.6 Air Environment

Baseline ambient air quality assessment gives the status in the vicinity of site and is an

indispensable part of environmental impact assessment studies. Significant changes, in

EIA Report

243 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

predominant winds and weather conditions are observed in winter, summer and post-

monsoon seasons apart from the local topographic influences. The baseline status of air

environment in the study area is assessed through a systematic air quality surveillance

programme.

3.6.1 Meteorological Conditions

The regional air quality is influenced by the meteorology of that region. The principal

weather parameters that influence the concentration of the air pollutants in the surroundings

are wind speed, wind direction and temperature. The meteorological data is useful for proper

interpretation of the baseline data. It is used as input for air quality dispersion models for

predicting the post project environmental scenario i.e. ground level concentrations due to

proposed utilities like Boilers &DG sets etc.

3.6.2 Meteorological Data Collection

Available secondary data pertaining to the meteorological parameters was obtained from the

IMD Climatological tables. In addition, baseline meteorological data (primary data) was

generated during the study period (March to May 2019). The methodology adopted for

monitoring surface observations is as per the standard norms laid down by Bureau of Indian

Standards (BIS) i.e. IS:8829 and Indian Meteorological Department (IMD).

3.6.3 General Meteorological Scenario based on IMD Data

The nearest Indian Meteorological Department (IMD) station located to project site is Paradip

port. The Climatological data of Paradip port (20 18’ N and 86o 41’ E), published by the

IMD, based on daily observations at 08:30 and 17:30 hour IST for a 30 year period (1971-

2000), is presented in the following sections on the meteorological conditions of the region.

The monthly variations of the relevant meteorological parameters are reproduced in Table

3-6.

EIA Report

244 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 3-6 Climatological Summary -Paradip port (1971-2000)

Month

Temp (°C) Rainfall

(mm)

Relative

Humidity

(%)

Vapour

Pressure

hPa

Mean

Wind

Speed

(kmph)

Predominant

Wind

Directions

(From)*

Daily

Max.

Daily

Min. Total

No.

of

days

08:30 17:30 08:30 17:30 08:30 17:30

Jan 26.9 15.8 10.8 0.6 78 70 19.1 19.9 9.4 N E

Feb 28.5 19.2 23.6 1.8 78 74 23.1 23.9 10.7 N S

Mar 30.9 22.8 36.4 1.5 78 79 28.4 29.2 12.1 SW S

Apr 31.9 25.1 32.1 2.1 80 83 32.4 33 15.3 SW SW

May 32.6 26.1 97 3.9 81 83 34.6 35 16 SW SW

Jun 32.5 26.3 219.2 9.6 82 83 34.5 34.8 14.4 SW SW

Jul 31.3 25.5 243.4 13.1 86 85 33.8 33.9 13.3 SW SW

Aug 31.2 25.5 343.8 14.7 86 85 33.6 33.8 12.5 SW SW

Sep 31.6 25.6 256.2 10.6 83 82 33.3 33.1 11.5 SW SW

Oct 31.5 24 161.9 5.9 79 77 30.2 30 8.6 N S

Nov 29.9 19.9 85 2.5 77 72 24.2 24.3 8.4 N NE

Dec 27.6 16 11.6 0.5 75 68 18.9 19.6 8.3 N NE

Max. 32.6 26.3 343.8 14.7 86 85 34.6 35 16 Annual Wind

Predominant

direction is

South West

Min. 26.9 15.8 10.8 0.5 75 68 18.9 19.6 8.3

Annual

Total /

Mean

30.5 22.7 1521.0 66.8 80 79 28.8 29.2 11.8

As per the above IMD climatological Data given in Table 3-6, the observations drawn are as

follows

Highest Mean daily maximum temperature is32.6oC and the Lowest mean daily minimum

temperature is 15.8oC were recorded in the months of May and January respectively

Maximum and minimum relative humidity of 86% and 68% were recorded in the months of

July & August and December respectively.

EIA Report

245 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Maximum and minimum rainfall of 343.8 mm and 10.8 mm was recorded in the months of

August and January respectively.

Maximum and minimum Mean wind speed is 16km/hr and 8.3km/hr was recorded in the

months of May and December respectively. Annual Wind predominant pattern is South

West.

3.6.4 Meteorological Scenario during Study Period

The meteorological scenario in and around the project site is an essential requirement during

study period for proper interpretation of baseline air quality status. Meteorological data was

collected during the study period (March -May 2019) and is presented in Table 3-7. The

wind rose for the study period is given as Figure 3-20.

Table 3-7 Meteorological Data for the Study Period (March - May 2019)

S. No Parameter Observation 1. Temperature Max. Temperature: 43°C

Min. Temperature: 19°C Avg. Temperature: 29.83°C

2. Average Relative Humidity

80.05%

3. Average Wind Speed 3.04m/s4. Predominant Wind

Direction South

EIA Report

246 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-20 Wind rose during study period (March - May 2019)

3.6.5 Atmospheric Inversion

Atmospheric inversion level at the project site was monitored; the results observed at the site

during the study period are as follows.

Average atmospheric temperature: 29.83°C

Average Relative humidity:80.05%

Average Wind speed: 3.04 m/s

The daily inversion level calculated based on the average temperature and average wind

speed at the project site and the maximum inversion height is derived by the graph plotted

based on the average temperature and average wind speed. The daily inversion level at the

project site varies from 50 to 3849 m during 5 AM to 4 PM, the maximum recorded at 3849

m during 2nd May 2019 at 4 pm. This is shown in the following Figure 3-21.

EIA Report

247 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-21Atmospheric inversion level at the project site

3.7 Ambient Air Quality

The selection criteria for monitoring locations are based on the following:

Topography/Terrain

Meteorological conditions – Upwind and Downwind locations

Residential and sensitive areas within the study area

Representatives of regional background air quality/pollution levels and

Representation of likely impacted areas

3.7.1 Ambient Air Quality Monitoring Stations

To evaluate the baseline air quality of the study area, Eight (08) monitoring locations have

been identified as per Meteorological data during the study period (March –May 2019).As

per IMD, The wind predominance during study period is from South West to North East.

AAQ monitoring locations are selected based on study period wind predominance, map

showing the air monitoring locations is given in Figure 3-22 and the details of the locations

are given in Table 3-8.

.Table 3-8 Details of Ambient Air Quality Monitoring Locations

Station

Code Location Type of Wind

Distance (km) from

Project boundary

Azimuth

Directions

A1 Project Site - Within Site

A2 Paradwipgarh c/w 4.41 NNE

EIA Report

248 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Station

Code Location Type of Wind

Distance (km) from

Project boundary

Azimuth

Directions

A3 Dochhaki d/w 4.08 NE

A4 Musharhia d/w 6.9 NE

A5 Paradwip (Coast Guard) c/w 4.91 E

A6 Dhinkia c/w 2.11 W

A7 Sunadiakandha c/w 2.46 W

A8 Gandakipur c/w 3.35 NNW

Figure 3-22Map showing the Air monitoring locations

EIA Report

250 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.7.2 Ambient Air Quality Monitoring Techniques and Frequency

Ambient air quality was monitored twice in a week for One (01) season (shall cover 12

weeks), i.e. 3 months (March 2019 – May 2019). PM10, PM2.5, SO2, NOx, Pb, NH3, C6H6,

C20H12, As, Ni, TVOC, Methane and Non-Methane Hydrocarbon were monitored. Sampling

was carried out as per Central Pollution Control Board (CPCB) monitoring guidelines at each

location. Analytical methods used for analysis of parameters are given in Table 3-9.

Table 3-9 Analytical Methods for Analysis of Ambient Air Quality Parameters

S.N

o Parameters Analytical method

NAAQ standards:

2009

Samplin

g Time

1 Sulphur Dioxide

(SO2), μg/m3

IS:5182(Part-2):2001

(Reaff:2006)

50

(Annual)

80 (24

Hours)

24

Hours

2 Nitrogen Dioxide

(NO2), μg/m3 IS: 5182 (Part - 6): 2006 40

(Annual)

80 (24

Hours)

24

Hours

3 Particulate Matter

(PM2.5), μg/m3 IS: 5182 (Part - 23): 2006 40

(Annual)

60 (24

hours)

24

Hours

4 Particulate Matter

(PM10), μg/m3 IS:5182 (Part– 23): 2006 60

(Annual)

100 (24

hours)

24

Hours

5 CO mg/m3 IS:5182(Part–10):1999

(Reaff:2006)

2

(8 hours) 4 (1hour) 8 Hours

6 Pbμg/m3 IS:5182(Part–22):2004

(Reaff:2006)

0.5

(Annual)

1(24

hours)

24

Hours

7 O3, μg/m3 IS: 5182 (Part – 9): 1974 100

(8hours)

180

(1hour) 8 Hours

8 NH3, μg/m3 APHA(air) 2nd edition

(Indophenol-blue method)

100

(Annual)

400(24

hours) 8 Hours

9 Benzene, μg/m3 IS:5182(Part–11):1999

(RA:2009)

5

(Annual)

5

(Annual)

24

Hours

10 Benzo (a) pyrene,

ng/m3

IS:5182(Part–12):2004

(RA:2009)

1

(Annual)

1

(Annual)

24

Hours

EIA Report

251 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.N

o Parameters Analytical method

NAAQ standards:

2009

Samplin

g Time

11 Arsenic, ng/ m3 APHA (air) 2nd edition 6

(Annual)

6

(Annual)

24

Hours

12 Nickel ng/ m3

In house method (AAS

method) based on CPCB

guidelines volume 1

20

(Annual)

20

(Annual)

24

Hours

13 TVOC HECS/AIR/AMBIENT/SOP/

018:2013 - - 8 Hours

14 Methane

Hydrocarbon IS 5182 (Part 17) - - 8 Hours

15 Non-Methane

Hydrocarbon IS 5182 (Part 17) - - 8 Hours

3.7.3 Results and Discussions

The variations of the pollutants PM10, PM2.5, SO2, NO2, CO, Pb, O3, NH3, C6H6, C20 H12, As

and Ni are compared with National Ambient Air Quality Standards (NAAQS), MoEF&CC

Notification, November, 2009. Ambient Air Quality Monitoring Data (March 2019 – May

2019) for the study area is given in Table 3-10 and trends of measured ambient concentration

in the study area were graphically represented in Figure 3-23

.

EIA Report

252 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 3-10 Summary of the average baseline concentrations of pollutants

Parameters Conc. NAAQ

Standards

Locations

Project Site Paradwipg

arh Dochhaki

Musharhi

a

Paradwip

(Coast

Guard)

Dhinkia Sunadiaka

ndha

Gandakip

ur

A1 A2 A3 A4 A5 A6 A7 A8

PM10 Conc.

(µg/m³)

Min.

100

(24 Hours)

52.72 50.19 47.73 51.65 67.15 48.71 46.16 46.90

Max 75.14 71.53 68.02 73.61 95.70 69.42 65.78 66.84

Avg. 63.22 60.19 57.24 61.94 80.53 58.42 55.35 56.25

98th

‘tile 74.70 71.12 67.63 73.19 95.14 69.02 65.40 66.45

PM2.5 Conc.

(µg/m3)

Min.

60

(24 Hours)

27.04 24.60 23.81 25.61 31.82 24.33 23.11 23.57

Max 38.53 35.06 33.94 36.50 45.35 34.68 32.94 33.59

Avg. 32.43 29.50 28.56 30.71 38.16 29.18 27.72 28.27

98th

‘tile 38.31 34.85 33.74 36.29 45.09 34.48 32.75 33.40

SO2 Conc.

(µg/m3)

Min.

80

(24 Hours)

7.19 10.74 8.73 9.34 11.01 7.99 8.38 7.63

Max 10.25 15.30 12.44 13.30 15.70 11.39 11.94 10.88

Avg. 8.63 12.88 10.47 11.20 13.21 9.59 10.05 9.16

98th 10.19 15.21 12.36 13.23 15.61 11.32 11.87 10.81

EIA Report

253 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Parameters Conc. NAAQ

Standards

Locations

Project Site Paradwipg

arh Dochhaki

Musharhi

a

Paradwip

(Coast

Guard)

Dhinkia Sunadiaka

ndha

Gandakip

ur

A1 A2 A3 A4 A5 A6 A7 A8

‘tile

NO2 Conc.(µg/m3)

Min.

80

(24 Hours)

13.46 20.63 16.57 17.82 21.09 15.16 15.96 14.40

Max 19.18 29.40 23.61 25.39 30.06 21.61 22.74 20.53

Avg. 16.15 24.75 19.87 21.37 25.30 18.19 19.14 17.28

98th

‘tile 19.07 29.23 23.47 25.25 29.89 21.49 22.61 20.41

Pb (μg/m3) Avg. 1

(24 hour)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

CO (mg/m3) Avg. 4

(1hour)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

BLQ (LOQ

0.05)

O3 (μg/m3) Avg. 180

(1hour) 19.24 15.65 13.39 16.99 21.53 13.19 11.87 12.53

NH3 (μg/m3) Avg. 400

(24 hours) 12.39 14.51 10.74 11.53 16.49 9.43 8.39 7.58

Benzene (μg/m3) Avg. 5

(Annual)

BLQ (LOQ

1)

BLQ (LOQ

1)

BLQ (LOQ

1)

BLQ (LOQ

1)

BLQ (LOQ

1)

BLQ

(LOQ 1)

BLQ (LOQ

1)

BLQ

(LOQ 1)

EIA Report

254 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Parameters Conc. NAAQ

Standards

Locations

Project Site Paradwipg

arh Dochhaki

Musharhi

a

Paradwip

(Coast

Guard)

Dhinkia Sunadiaka

ndha

Gandakip

ur

A1 A2 A3 A4 A5 A6 A7 A8

Benzo (a) pyrene,

(ng/m3) Avg.

1

(Annual)

BLQ (LOQ

1)

BLQ (LOQ

1)

BLQ (LOQ

1)

BLQ (LOQ

1)

BLQ (LOQ

1)

BLQ

(LOQ 1)

BLQ (LOQ

1)

BLQ

(LOQ 1)

Arsenic (ng/ m3) Avg. 6

(Annual)

BLQ (LOQ

2)

BLQ (LOQ

2)

BLQ (LOQ

2)

BLQ (LOQ

2)

BLQ (LOQ

2)

BLQ

(LOQ 2)

BLQ (LOQ

2)

BLQ

(LOQ 2)

Nickel (ng/m3) Avg. 20

(Annual)

BLQ (LOQ

10)

BLQ (LOQ

10)

BLQ (LOQ

10)

BLQ (LOQ

10)

BLQ (LOQ

10)

BLQ

(LOQ 10)

BLQ (LOQ

10)

BLQ

(LOQ 10)

TVOC (ppm) Avg. - BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

Methane HC

(µg/m3) Avg. -

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

Non-Methane HC

(µg/m3) Avg. -

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

BLQ (LOQ

0.1)

Note: BDL (Below detectable limit), DL (Detectable limit), BLQ (Below Detectable Limit), LOQ (Limit Of Quantification)

EIA Report

255 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-23: Trends of Measured Ambient Concentrations in the Study Area

EIA Report

256 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.7.4 Observations

The ambient air quality has been monitored at 8 locations for 14 parameters as per

NAAQS/CPCB guidelines within the study area. The average baseline levels of PM10 (55.35

– 80.53µg/m³), PM2.5 (27.72 – 38.16µg/m³), SO2(8.63 – 13.21µg/m³), NO2(16.15 –

25.30µg/m³), the nearest CPCB AAQ monitoring station is PPL Guest House in which the

annual average for the year 2018: PM10 (113 µg/m³), PM2.5 (37 µg/m³), SO2(19 µg/m³),

NO2(11 µg/m³).

All the parameters are well within the National Ambient Air Quality Standards for Industrial,

Commercial and Residential areas at all monitoring locations during the study period from

March 2019 - May 2019.

3.8 Noise Environment

The prevailing ambient noise level at a particular location is nothing but the resultant (total)

of all kinds of noise sources existing at various distances around that location. The ambient

noise level at a location varies continuously depending on the type of surrounding activities.

Ambient noise levels have been established by monitoring noise levels at Eight(08) locations

in and around 10Km distance from project area during the study period using precision noise

level meter. The noise monitoring locations in the study area were selected after giving due

consideration to the various land use categories. The land use categories include commercial,

residential, rural and sensitive areas. Noise levels were recorded on an hourly basis for one

complete day at each location using pre- calibrated noise levels. A map noise showing the

noise monitoring locations is given in Figure 3-24.

3.8.1 Results and Discussions

Based on the recorded hourly noise levels at each monitoring location, the day equivalent

(Ld) and night equivalent (Ln) were calculated;

Ld: Average noise levels between 6:00 hours to 22.00 hours.

Ln: Average noise levels between 22:00 hours to 6.00 hours.

The comparison of day equivalent noise levels (Ld) and night equivalent noise levels (Ln)

with the respective CPCB stipulated noise standards for various land use categories are

shown in the Table 3-11.

EIA Report

257 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 3-11 Day and Night Equivalent Noise Levels

S. No

Location Location

Code

Distance (km)

from Project

boundary

Azimuth

Direction

Noise level in

dB(A) Leq CPCB Standard

Environmental

Setting Day Night

Lday

(Ld)

LNight

(Ln)

1 Project Site N1 Within Site 53.8 47.1 75 70 Industrial

2 Paradwipgarh N2 4.41 NNE 53.7 44.2 55 45 Residential

3 Dochhaki N3 4.08 NE 51.3 42.6 55 45 Residential

4 Musharhia N4 6.9 NE 58.6 47.5 55 45 Residential

5 Paradwip (Coast Guard) N5 4.91 E 64.8 54.2 65 55 Commercial

6 Dhinkia N6 2.11 W 52.4 43.7 55 45 Residential

7 Sunadiakandha N7 2.46 W 50.9 43.2 55 45 Residential

8 Gandakipur N8 3.35 NNW 53.3 43.1 55 45 Residential

3.8.2 Observations

The observations of day equivalent and night equivalent noise levels at all locations are given below

In Industrial areas (Project site) day time noise levels was about 53.8 dB(A) and 47.1 dB(A) during night time, which is within prescribed

limit given by CPCB (75 dB(A) Day time & 70 dB(A) Night time).

In Commercial areas (Paradwip (Coast Guard)) day time noise levels was about 64.8 dB(A) and night time noise levels was about 54.2

dB(A), which is within the prescribed limit given by CPCB (65 dB(A) Day time & 55 dB(A) Night time).

In residential area (Paradwipgarh, Dochhaki, Musharhia, Dhinkia, Sunadiakandha and Gandakipur) day time noise levels varied from

50.9 dB(A) to 58.6 dB(A) and night time noise levels varied from 42.6 dB(A) to 47.5 dB(A) across the sampling stations. The field

observations during the study period indicate that the ambient noise levels in some residential area is exceeding the prescribed limit given

by CPCB (55 dB(A) Day time & 45 dB(A) Night time).

EIA Report

258 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-24 Map showing the Noise Monitoring locations

EIA Report

259 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.9 Water Environment

3.9.1 Surface Water Resources

The main rivers flowing in the district are Mahanadi, Saunlia, Alaka and Devi. The branches

of Devi River are Biluakhai, Gobari River where as the branches of Mahanadi are Paika,

Chirotpala and Hansua River. All the rivers and its branches fall into the Bay of Bengal. The

problem of drainage becomes acute towards the lower reaches of the deltas. The coastal

ridges offer an effective barrier to a free discharge of the flood water. Sometimes the huge

sand deposits create marshy conditions and affect the production of crops. Due to its

geographical situation, the district is congenial and prone to occurrence of various natural

calamities like flood, cyclone and drought. To prevent the calamities, many river dam

projects, canal construction works and irrigation works were made in and nearby district.

Two main canals i.e. Taladanda and Machhagaon provide water for irrigation in the district.

Source:

http://censusindia.gov.in/2011census/dchb/DCHB_A/21/2111_PART_A_DCHB_JAGATSING

HAPUR.pdf

3.9.1.1 Surface Water Quality Assessment

To establish the baseline status of water environment, the representative sampling locations

for surface water within a radial distance of 10Km from project site have been selected as per

CPCB guidelines of Water Quality Monitoring through an adequate survey of the project

area. Test methods used for the analysis of water quality parameters is given in Table 3-12.

Table 3-12 Test methods used for the analysis of water quality parameters

Sl. No Parameter Measured Test Method

1 Colour IS:3025 (Part- 4) 1983 (Reaff 2006)

2 Turbidity IS 3025(Part - 10):1984

3 pH IS:3025 (Part - 11): 1983 (Reaff: 2006)

4 Conductivity IS:3025 (Part - 14): 1983 (Reaff: 2006)

5 Total Dissolve Solids IS: 3025:1(Part - 16) 1984 (Reaff 2006)

6 Total Suspended Solids IS 3025 (Part - 17) 1984 (Reaff 1996)

7 Alkalinity as CaCO3 IS:3025,1 (Part - 23) 1986 (Reaff 2009)

8

Total Hardness as

CaCo3 IS:3025 (Part - 21) 1983 (Reaff 2006)

EIA Report

260 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl. No Parameter Measured Test Method

11 Sodium IS:3025,5(Part - 45) 1993 (Reaff 2006)

12 Potassium IS:3025,5(Part - 45) 1993 (Reaff 2006)

9 Calcium as Ca IS 3025 (Part - 40):1991

10 Magnesium as Mg IS 3025 (Part - 46) 1994

13 Carbonate IS 3025, (Pt 23) 1986 (R 2006)

14 Bi carbonate IS 3025, (Pt 23) 1986 (R 2006)

15 Chloride IS 3025 (Part - 32):1988

16 Sulphate SO4 IS 3025(Part - 24):1986

17 Nitrate as NO3 ASTM (Part - 31)1978

18 Phosphate IS 3025 (Pt 45) 1993 (R 2006)

19 Fluorides as F IS 3025 (Part - 60):2008

20 Cyanide IS 3025 (Part-27):1986

21 Arsenic IS 3025:(Part-37):1988(Reaff 2009)

22 Boron IS:3025 (Part - 57):2003

23 Cadmium IS 3025 (Part - 41)1991

24 Chromium, Total IS:3025 (Part - 52) 2003 (Reaff 2009)

25 Copper IS:3025 (Part - 42)1992 (Reaff: 2009)

26 Iron IS 3025 (Part - 53):2003

27 Lead IS:3025 (Part - 47) 1994 (Reaff 2009)

28 Manganese IS 3025:(Part - 59):2006

29 Mercury IS 3025 (Part48):1994 RA 1999

30 Nickel IS 3025:(Part-54):2003(Reaff 2009)

31 Selenium IS 3025 Part (56)2003

32 Zinc IS:3025 (Part - 49) 1994 (Reaff 2009)

33 Dissolved Oxygen IS:3025 (Part - 38)1989 (Reaff 2009)

34 BOD 5210B APHA22nd Edn 2012

35 COD IS:3025 (Part-58)-2006

The prevailing status of surface water quality has been assessed during the study period.

Surface water quality results are provided in Table 3-14. A map showing the surface water

monitoring locations is given in Figure 3-25. The Details of the surface water monitoring

locations is given in Table 3-13

EIA Report

261 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 3-13 Details of Surface water sampling locations

S.

NoWater bodies

Location

code

Distance from

project boundary

(~Km)

Direction from

project boundary

1 Stream near Udayabat SW1 4.04 N

2 Mahanadi d/s near Musharhia SW2 7.56 NNE

3 Marine sample near Port SW3 4.77 E

4 Santara nadi d/s SW4 0.16 E

5 Marine sample near project

site SW5 0.64 E

6 Mahanga Nadi SW6 1.34 SW

7 Mahanadi u/s near

Balaramapur SW7 8.59 NW

8 Sanatara nadi u/s SW8 0.1 W

EIA Report

262 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-25: Map showing the surface water monitoring locations

EIA Report

263 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 3-14: Surface water Monitoring Results

Sl.N

o Parameter Unit

Surface

water

Standards

(IS 2296

Class – A)

Stream

near

Udayab

at

Mahanadi

d/s near

Musharhi

a

Marine

sample

near

Port

Sanatar

a nadi

d/s

Marine

sample

near

project

site

Mahang

a Nadi

Mahana

di u/s

near

Balaram

apur

Sanatara

nadi u/s

SW1 SW2 SW3 SW4 SW5 SW6 SW7 SW8

1 Turbidity NTU - 1 16 28 7 12 6 4 4

2 pH (at 25°C) -- 6.5-8.5 6.98 6.76 7.98 6.92 7.94 7.08 7.84 6.86

3 EC µS/cm - 4386 24685 50174 27451 52341 29345 9946 25972

4 Total Dissolve

Solids mg/l 500 2640 16934 32040 19128 34677 18556 6734 17124

5 Total Suspended

Solids mg/l - 2 36 78 16 36 13 18 11

6 Total Alaklinity as

CaCO3

mg/l - 213.1 221.3 344.3 90.2 98.4 259.0 138.5 72.1

7 Total Hardness as

CaCO3

mg/l 200 320.2 3201.2 5602.4 2898.7 6401.6 3875.6 1238.7 2714.7

8 Sodium as Na mg/l - 660 4418 8551 5148 9406 4843 1734 4137

EIA Report

264 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.N

o Parameter Unit

Surface

water

Standards

(IS 2296

Class – A)

Stream

near

Udayab

at

Mahanadi

d/s near

Musharhi

a

Marine

sample

near

Port

Sanatar

a nadi

d/s

Marine

sample

near

project

site

Mahang

a Nadi

Mahana

di u/s

near

Balaram

apur

Sanatara

nadi u/s

SW1 SW2 SW3 SW4 SW5 SW6 SW7 SW8

9 Potassium as K mg/l - 46 309 598 302 658 361 121 283

10 Calcium as Ca mg/l - 40.08 240.48 480.96 181.2 320.64 284.16 96.19 163.4

11 Magnesium as Mg mg/l - 53.46 631.8 1069.2 594.3 1360.8 769.15 242.56 560.4

12 Chloride as Cl mg/l 250 1375.77 9204.81 17815.75 9122.4 19597.3

3 9867.15 3612.64 8469.2

13 Sulphate as SO4 mg/l 400 147.4 1521.42 2469.18 1402.3 2530.72 1745.64 617.98 1392.7

14 Nitrate as NO3 mg/l 20 2.48 4.12 4.56 4.1 1.24 3.48 5.7 3.6

15 Phosphate as PO4 mg/l - 1.59 0.99 0.06 0.28 0.26 0.62 0.12 0.19

16 Fluorides as F mg/l 1.5 0.34 0.76 0.68 0.81 0.72 0.87 0.12 0.65

17 Cyanide mg/l 0.05

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

18 Arsenic mg/l 0.05 BLQ BLQ BLQ BLQ BLQ BLQ BLQ BLQ

EIA Report

265 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.N

o Parameter Unit

Surface

water

Standards

(IS 2296

Class – A)

Stream

near

Udayab

at

Mahanadi

d/s near

Musharhi

a

Marine

sample

near

Port

Sanatar

a nadi

d/s

Marine

sample

near

project

site

Mahang

a Nadi

Mahana

di u/s

near

Balaram

apur

Sanatara

nadi u/s

SW1 SW2 SW3 SW4 SW5 SW6 SW7 SW8

(LOQ

0.005)

(LOQ

0.005)

(LOQ

0.005)

(LOQ

0.005)

(LOQ

0.005)

(LOQ

0.005)

(LOQ

0.005)

(LOQ

0.005)

19 Boron as B mg/l -

BLQ

(LOQ

0.1)

BLQ

(LOQ 0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

20 Cadmium as Cd mg/l 0.01

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

21 Chromium, Total mg/l 0.05

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

22 Copper as Cu mg/l 1.5

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

23 Lead as Pb mg/l 0.1 BLQ BLQ BLQ BLQ BLQ BLQ BLQ BLQ

EIA Report

266 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.N

o Parameter Unit

Surface

water

Standards

(IS 2296

Class – A)

Stream

near

Udayab

at

Mahanadi

d/s near

Musharhi

a

Marine

sample

near

Port

Sanatar

a nadi

d/s

Marine

sample

near

project

site

Mahang

a Nadi

Mahana

di u/s

near

Balaram

apur

Sanatara

nadi u/s

SW1 SW2 SW3 SW4 SW5 SW6 SW7 SW8

(LOQ

0.005)

(LOQ

0.005)

(LOQ

0.005)

(LOQ

0.005)

(LOQ

0.005)

(LOQ

0.005)

(LOQ

0.005)

(LOQ

0.005)

24 Manganese as Mn mg/l 0.5

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

25 Mercury mg/l 0.001

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

26 Nickel as Ni mg/l -

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

27 Selenium as Se mg/l 0.01

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

28 Zinc mg/l 15 BLQ BLQ BLQ BLQ BLQ BLQ BLQ BLQ

EIA Report

267 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.N

o Parameter Unit

Surface

water

Standards

(IS 2296

Class – A)

Stream

near

Udayab

at

Mahanadi

d/s near

Musharhi

a

Marine

sample

near

Port

Sanatar

a nadi

d/s

Marine

sample

near

project

site

Mahang

a Nadi

Mahana

di u/s

near

Balaram

apur

Sanatara

nadi u/s

SW1 SW2 SW3 SW4 SW5 SW6 SW7 SW8

(LOQ

0.1)

(LOQ 0.1) (LOQ

0.1)

(LOQ

0.1)

(LOQ

0.1)

(LOQ

0.1)

(LOQ

0.1)

(LOQ

0.1)

29 Dissolved Oxygen mg/l 6 6.1 5.9 6.3 5.8 6.1 6.7 6.2 6

30 Chemical Oxygen

Demand as O2

mg/l - 4 86 18 91

36 68 72 154

31 BOD, 3 days @27°C

as O2

mg/l 2 1 14 3 17 5 11 12 19

(Note: BLQ – Below Limit of Quantification; LOQ – Limit Of Quantification)

EIA Report

268 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.9.1.2 Results and Discussions

Surface water sample results as presented in Table 3-14 are discussed below:

Surface water sampling results except marine sample are compared with Surface

water standards IS 2296:1992.

pH in the collected surface water samples varies between 6.76 to 7.84 which is within

the limit of IS 2296:1992, where pH value of marine sample ranges from 7.94 to 7.98.

The Total Dissolved Solids (TDS) value of collected surface water sample ranges

from 2640 mg/l to 19128 mg/l. TDS value of marine sample ranges from 32040 mg/l

to 34677 mg/l.

The Total hardness value of the collected surface water sample ranges between 320.2

mg/l – 3875.6 mg/l. Total hardness value of marine sample ranges between 5602.4

mg/l – 6401.6 mg/l.

BOD values of the collected surface water samples are ranges between 1 mg/l and

19mg/l. BOD value of the marine sample ranges between 3 mg/l to 5 mg/l.

COD value of the collected surface water varies from 4 to 154 mg/l. COD value of the

marine sample ranges between 18 mg/l to 36 mg/l.

The concentration of heavy metals like As, Cd, Cr, Pb, Mn, Hg, Ni and Se are within

the limits of IS 2296:1992.

3.9.2 Ground Water Resources

The ground water resources of the district have been assessed adopting the methodology

recommended by the ground water Estimation Committee (1997), constituted by Govt. of

India. The task was jointly carried out by the central Ground Water Board and Ground Water

Survey and Investigation, Department of Water Resources, Govt. of Orissa. The block wise

computation of ground water resources in the district has been meager and all the blocks fall

under the safe category. The stage of ground water development varies from 31.53% to

67.26% in different blocks. The overall stage of ground water development of the district is

47.37%. The ground water resources of Jagatsinghapur district are as given in Table 3-15.

Table 3-15: Dynamic ground water resources of Jagatsinghapur District

Attribute Potential

/Quantity

Annual Replenishable Ground Water Resources 45029 Ham

EIA Report

269 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Attribute Potential

/Quantity

Net Ground Water Draft 21332 Ham

Projected Demand for domestic and industrial uses up to

2005

2463 Ham

Stage of Ground Water Development 14.57 %

(Source:http://cgwb.gov.in/District_Profile/Orissa/jagasingpur.pdf)

3.9.2.1 Ground Water Quality

Total Eight (08) ground water monitoring locations were identified for assessment in

different villages around the project site based on the usage of sub surface water by the

settlements/ villages in the study area. The groundwater results are compared with the

acceptable and permissible water quality standards as per IS: 10500 (2012) for drinking

water. Groundwater quality monitoring locations and results are given in Table 3-16 and

Table 3-17. A map showing the groundwater monitoring locations is given in Figure 3-26.

Table 3-16 Details of Groundwater Quality Monitoring Locations

Station

Code Location

Distance (km) from

Project boundary

Azimuth

Directions

GW1 Project Site Within Site

GW2 Paradwipgarh 4.41 NNE

GW3 Dochhaki 4.08 NE

GW4 Musharhia 6.9 NE

GW5 Paradwip (Coast Guard) 4.91 E

GW6 Dhinkia 2.11 W

GW7 Sunadiakandha 2.46 W

GW8 Gandakipur 3.35 NNW

EIA Report

270 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-26 Map showing the groundwater monitoring locations

EIA Report

271 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 3-17 Ground Water Monitoring Results

S.

N

o

Parameters Unit

Drinking water

Standard (IS

10500: 2012)

Project

Site

Paradwi

pgarh

Dochha

ki

Musharh

ia

Paradwi

p (Coast

Guard)

Dhinkia Sunadia

kandha

Gandakipu

r

Accep

table

Limit

Permi

ssible

Limit

GW1 GW2 GW3 GW4 GW5 GW6 GW7 GW8

1. Colour Haze

n 5 15

BLQ

(LOQ 1)

BLQ

(LOQ 1)

BLQ

(LOQ 1)

BLQ

(LOQ 1)

BLQ

(LOQ 1)

BLQ

(LOQ 1)

BLQ

(LOQ 1)

BLQ (LOQ

1)

2. Turbidity NTU 1 5 BLQ

(LOQ 1)

BLQ

(LOQ 1) 15

BLQ

(LOQ 1)

BLQ

(LOQ 1)

BLQ

(LOQ 1)

BLQ

(LOQ 1)

BLQ (LOQ

1)

3. pH -- 6.5-8.5 NR 8.21 7.02 7.35 7.51 7.57 7.12 7.39 7.28

4. Conductivity µS/c

m - - 1269 745 1084 987 663 1175 1352 1201

5.Total Dissolve

Solids mg/l 500 2000 785 474 679 609 406 760 868 779

6.

Total

Suspended

Solids

mg/l - - 2 3 34 5 3 6 5 4

7.Alkalinity as

CaCO3

mg/l 200 600 151 148 175 230 117 199 259 186

EIA Report

272 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

N

o

Parameters Unit

Drinking water

Standard (IS

10500: 2012)

Project

Site

Paradwi

pgarh

Dochha

ki

Musharh

ia

Paradwi

p (Coast

Guard)

Dhinkia Sunadia

kandha

Gandakipu

r

Accep

table

Limit

Permi

ssible

Limit

GW1 GW2 GW3 GW4 GW5 GW6 GW7 GW8

8.

Total

Hardness as

CaCO3

mg/l 200 600 251 289 274 240 143 263 301 266

9. Sodium as Na mg/l - - 121 45 89 62 51 102 131 112

10.Potassium as

K mg/l - - 16 3 12 9 4 10 15 14

11. Calcium as Ca mg/l 75 200 52.41 60.12 58.12 48.1 31.86 61.3 62.32 54.2

12.Magnesium as

Mg mg/l 30 100 29.06 33.8 31.3 29.16 15.31 26.71 35.26 31.74

13. Chloride as Cl mg/l 250 1000 251.21 94.03 182.31 128.69 104.14 209.32 229.36 226.42

14. Sulphate SO4 mg/l 200 400 108.31 42.47 73.16 32.03 41.92 86.26 52.75 90.54

15. Nitrate as NO3 mg/l 45 NR 4.8 3.5 3.9 5.1 4.1 3.9 6 4.6

16. Phosphate PO4 mg/l - - 0.71 4.42 0.08 0.09 0.11 0.18 0.21 0.04

17. Fluorides as F 1 1.5 0.52 0.39 0.5 0.56 0.51 0.48 0.47 0.27

18. Cyanide mg/l 0.05 NR BLQ BLQ BLQ BLQ BLQ BLQ BLQ BLQ (LOQ

EIA Report

273 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

N

o

Parameters Unit

Drinking water

Standard (IS

10500: 2012)

Project

Site

Paradwi

pgarh

Dochha

ki

Musharh

ia

Paradwi

p (Coast

Guard)

Dhinkia Sunadia

kandha

Gandakipu

r

Accep

table

Limit

Permi

ssible

Limit

GW1 GW2 GW3 GW4 GW5 GW6 GW7 GW8

(LOQ

0.01)

(LOQ

0.01)

(LOQ

0.01)

(LOQ

0.01)

(LOQ

0.01)

(LOQ

0.01)

(LOQ

0.01)

0.01)

19. Arsenic as As mg/l 0.01 0.05

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ (LOQ

0.005)

20. Boron as B mg/l 0.5 1.0

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ (LOQ

0.1)

21.Cadmium as

Cd mg/l 0.003 NR

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

BLQ

(LOQ

0.001)

BLQ (LOQ

0.001)

22.Chromium as

Cr mg/l 0.05 NR

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ (LOQ

0.01)

23. Copper as Cu mg/l 0.05 1.5 BLQ BLQ BLQ BLQ BLQ BLQ BLQ BLQ (LOQ

EIA Report

274 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

N

o

Parameters Unit

Drinking water

Standard (IS

10500: 2012)

Project

Site

Paradwi

pgarh

Dochha

ki

Musharh

ia

Paradwi

p (Coast

Guard)

Dhinkia Sunadia

kandha

Gandakipu

r

Accep

table

Limit

Permi

ssible

Limit

GW1 GW2 GW3 GW4 GW5 GW6 GW7 GW8

(LOQ

0.01)

(LOQ

0.01)

(LOQ

0.01)

(LOQ

0.01)

(LOQ

0.01)

(LOQ

0.01)

(LOQ

0.01)

0.01)

24. Total Iron mg/l 0.3 NR 0.2 0.19 0.14 0.11 0.07 0.13 0.12 0.18

25. Lead as Pb mg/l 0.01 NR

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ (LOQ

0.005)

26.Manganese as

Mn mg/l 0.1 0.3

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

BLQ

(LOQ

0.05)

BLQ (LOQ

0.05)

27. Mercury mg/l 0.001 NR

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

BLQ

(LOQ

0.0005)

BLQ (LOQ

0.0005)

28. Nickel as Ni mg/l 0.02 NR

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ

(LOQ

0.01)

BLQ (LOQ

0.01)

EIA Report

275 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

N

o

Parameters Unit

Drinking water

Standard (IS

10500: 2012)

Project

Site

Paradwi

pgarh

Dochha

ki

Musharh

ia

Paradwi

p (Coast

Guard)

Dhinkia Sunadia

kandha

Gandakipu

r

Accep

table

Limit

Permi

ssible

Limit

GW1 GW2 GW3 GW4 GW5 GW6 GW7 GW8

29.Selenium as

Se mg/l 0.01 NR

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ

(LOQ

0.005)

BLQ (LOQ

0.005)

30. Zinc as Zn mg/l 5 15

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ

(LOQ

0.1)

BLQ (LOQ

0.1)

(Note: BLQ – Below Limit of Quantification; LOQ – Limit Of Quantification; NR – No Relaxation)

EIA Report

276 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.9.2.2 Results and Discussions

A summary of analytical results are presented below:

The ground water results of the study area indicate that the pH range varies between 7.02

and 8.21. It is observed that the pH range is within the limit of IS 10500:2012.

The Total Dissolved Solids range is varied between 406mg/l –868 mg/l for the ground

water, whereall the samples are well within the permissible limit of IS 10500: 2012.

The acceptable limit of the chloride content is 250mg/l and permissible limit is 1000

mg/l. The chloride content in the collected ground water samplesof the study area ranges

between 94.03 mg/l – 251.21 mg/l. It is observed that all the samples are well within the

permissible limit of IS 10500:2012.

The acceptable limit of the sulphate content is 200mg/l and permissible limit is 400mg/l.

the sulphate content of the collected ground water samples of the study area is varied

between 32.03mg/l – 108.31 mg/l.It is observed that all the samples are meeting the

acceptable limit of the IS 10500: 2012.

The Total hardness ranges is between 143 mg/l – 301mg/l for ground water samples. It is

observed that all the samples are well within the permissible limit of the IS 10500: 2012.

3.10 Soil as a resource and its quality

As the entire district is situated at Mahanadi Deltaic region, mostly the soil is alluvial.

Besides, brown soils (hydromorphic) and recently formed hydromorphic soils are also found

in this district. Technically the suborder associations of the soil may be classified as Aquepts-

Aquents, Fluvents-Aqueots-Aqualfs and Ochrepts-Orthents. Soil analysis was carried as per

IS: 2720 methods. Soil quality monitoring locations & results are given in Table 3-18

&Table 3-19. Map showing the soil monitoring locations is given in Figure 3-27.

(Source:

http://censusindia.gov.in/2011census/dchb/DCHB_A/21/2111_PART_A_DCHB_JAGATSING

HAPUR.pdf)

Table 3-18 Soil & Sediment Quality Monitoring Locations

Location

Code Location

Distance (Km)

w.r.t project site

Direction

w.r.t. project site

S1 Project Site Within Site

S2 Paradwipgarh 4.41 NNE

S3 Dochhaki 4.08 NE

EIA Report

277 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Location

Code Location

Distance (Km)

w.r.t project site

Direction

w.r.t. project site

S4 Musharhia 6.9 NE

S5 Paradwip (Coast Guard) 4.91 E

S6 Dhinkia 2.11 W

S7 Sunadiakandha 2.46 W

S8 Gandakipur 3.35 NNW

EIA Report

278 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 3-27 Map showing the soil monitoring locations

EIA Report

279 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 3-19 Soil & Sediment Quality Monitoring Results

S.N

o

Parameter

s Units

Project

Site

Paradwipg

arh Dochhaki Musharhia

Paradwi

p (Coast

Guard)

Dhinkia Sunadiakandh

a

Gandakipu

r

S1 S2 S3 S4 S5 S6 S7 S8

1 Soil

Texture

Loamy

Fine

Sand

Sandy Clay Clay Clay Loam Fine sand Clay Fine sand

2 Sand % 80.16 51.32 12.4 1.86 38.77 91.42 38.6 88.6

3 Silt % 16.44 11.21 7.44 8.61 36.4 4.96 14.97 8.11

4 Clay % 3.4 37.47 80.16 89.53 24.83 3.62 46.43 3.29

5 pH 7.94 6.22 6.12 5.63 6.4 6.27 5.94 6.45

6

Electrical

conductivit

y

umhos/c

m 236 227 196 213.6 280 210 245 195

7 Bulk

Density gm/cc 1.44 1.21 1.19 1.18 1.38 1.4 1.29 1.48

8

Cation

Exchange

Capacity

meq/100

gm 13.62 9.87108 26.5 22.71 16.09 15.33 24.2 11.54

9 Moisture % 8.31 9.12 14.06 16.2 9.53 6.81 4.77 5.23

EIA Report

280 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.N

o

Parameter

s Units

Project

Site

Paradwipg

arh Dochhaki Musharhia

Paradwi

p (Coast

Guard)

Dhinkia Sunadiakandh

a

Gandakipu

r

S1 S2 S3 S4 S5 S6 S7 S8

content

10 Organic

Carbon % 0.62 0.46 1.42 1.12 0.76 0.6 1.33 0.72

11 Organic

matter % 1.07 0.79 2.45 1.93 1.31 1.03 2.29 1.24

12 Nitrogen

as N mg/kg 253.76 216 195.6 165.42 313.8 295.3 226.35 238.3

13 Phosphoru

s mg/kg 286.31 246.61 272.23 296.71 260.5 173.88 288.72 133.17

14 Potassium mg/kg 130.17 93.26 96.25 112.15 135.6 144.69 69.9 110.62

15 Calcium mg/kg 73.42 91.64 126 88.72 107.31 106.73 95.43 99.27

16 Magnesiu

m mg/kg 139.66 122.6 140.21 97.05 119.06 133.4 110.08 129.6

17 Boron mg/kg BLQ

(DL 0.1)

BLQ

(DL 0.1)

BLQ

(DL 0.1)

BLQ

(DL 0.1)

BLQ

(DL 0.1)

BLQ

(DL 0.1)

BLQ

(DL 0.1)

BLQ

(DL 0.1)

18 Cadmium mg/kg BLQ

(DL 0.1)

BLQ

(DL 0.1)

BLQ

(DL 0.1)

BLQ

(DL 0.1)

BLQ

(DL 0.1)

BLQ

(DL 0.1)

BLQ

(DL 0.1)

BLQ

(DL 0.1)

EIA Report

281 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.N

o

Parameter

s Units

Project

Site

Paradwipg

arh Dochhaki Musharhia

Paradwi

p (Coast

Guard)

Dhinkia Sunadiakandh

a

Gandakipu

r

S1 S2 S3 S4 S5 S6 S7 S8

19 Chromium mg/kg 6.27 5.89 14.55 15.62 16.24 2.98 8.52 6.13

20 Copper mg/kg 31.43 21.47 37.6 25.69 36.75 18.55 36.11 36.92

21 Manganese mg/kg 67.66 42.31 79.34 65.43 197.54 37.12 247.08 31.08

22 Zinc mg/kg 21.46 15.92 16.36 13.73 17.93 15.1 20.64 13.7

(Note:BDL: Below Detectable Limit; DL: Detectable Limit; BLQ: Below Limit of Quantification; LOQ: Limit Of Quantification)

EIA Report

282 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.10.1 Results and Discussions

Summary of analytical results

The pH of the soil samples ranged from 5.63 to 7.94. It shows that the soils are

moderately acidic to moderately alkaline in nature.

Conductivity of the soil samples ranged from195 to280 μmhos/cm.

Nitrogen content ranged from 165.42 mg/kg to 313.8 mg/kg.

Phosphorous ranged from 133.17 mg/kg to 296.71 mg/kg.

Potassium content ranges from 69.9 mg/kg to 144.69 mg/kg.

3.11 Biological Environment

An ecological study of the ecosystem is essential to understand the impact of industrialization

and urbanization on existing flora and fauna of the study area. Studies on various aspects of

ecosystem play an important role in identifying sensitive issues for under taking appropriate

action to mitigate the impact, if any. The biological study was under taken as a part of the

EIA study report to understand the present status of ecosystem prevailing in the study area, to

compare it with past condition with the help of available data, to predict changes in the

biological environment as a result of present activities and to suggest measures for

maintaining its health. Secondary information was collected to list the flora & fauna in 10 km

radius.

During secondary survey, following aspects were considered for ecological studies:

Assessment of present status of flora and fauna;

Identification of rare and endangered species of plants and animals (if any);

Identification of ecologically sensitive areas within the study area;

Assessment of migratory route of wildlife (if any); and

Assessment of Aquatic Ecology with specific reference to aquatic birds.

Project site is situated near Dhenkia. In this region comprises of deciduous type forests, along

the Mahanadhi river, numerous wetland and human population area. There is Mangrove

forest situated towards North east of the project site but from 8.5 km from the plant area. The

project area is considered as core area, whereas, 10 km radial distance for the project site is

being considered as buffer area

EIA Report

283 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.11.1 Flora

The information of important terrestrial Angiosperm habit such as herb, shrub, climber, grass,

sedge and tree were collected from the secondary sources. Mahanadi delta once had extensive

mangrove forests located at a distance 6.93km(NE) from the project site. An inventory of the

list reported in the study area is given in Table 3-20.

Table 3-20 List of flora reported/observed in the study area

S.No Scientific Name Family Life form

Local Name IUCN Status

1 Abroma augusta Sterculiaceae Shrub Ulat-kombol, Hati-piola

LC

2 Abutilon hirtum Malvaceae Herb Jopa bondha LC

3 Abutilon indicum Malvaceae Herb ─ LC

4 Acacia diadenia Mimosaceae Tree Sia-nahar LC

5 Acanthephippium silhetense

Orchidaceae Herb ─ VU

6 Aegle marmelos Rutaceae Tree Beal LC

7 Aeschynomene aspera Fabaceae Shrub Kuhila, Kankula. LC

8 Albizia lebbeck Mimosaceae Tree Kothiya-koroi, Sirish. LC

9 Albizia odoratissima Mimosaceae Tree Sirolu, Koroi. LC

10 Albizia procera Mimosaceae Tree Tantari-asing, Koroi. LC

11 Alysicarpus bupleurifolius

Fabaceae Herb ─ LC

12 Alysicarpus monilifer Fabaceae Herb ─ LC

13 Alysicarpus vaginalis Fabaceae Herb Chauli, Sauri LC

14 Ampelocissus latifolia Vitaceae Shrub ─ LC

15 Anacardium occidentale Annacardiaceae Tree Kaju-badam LC

16 Antiaris toxicaria Moraceae Tree Dhuna-goch LC

17 Apluda mutica Poaceae Grasses ─ LC

18 Argemone mexicana Papaveraceae Herb ─ LC

19 Argemone mexicana Fabaceae Herb siyalakanta LC

20 Aristida setacea Poaceae Grasses ─ LC

21 Arthraxon prionodes Poaceae Grasses ─ LC

22 Artocarpus heterophyllus

Moraceae Tree kothal LC

23 Artocarpus hirsutus Moraceae Tree Sam LC

24 Artocarpus incisus Moraceae Tree ─ LC

25 Azadirachta indica Meliaceae Tree ─ LC

26 Bambusa bambos Poaceae Grasses ─ LC

27 Barringtonia acutangula Lecythidaceae Tree Hendol, Hinyol LC

28 Bauhinia purpurea Caesalpiniaceae Tree Og-yok,. Kurial LC

29 Bauhinia racemosa Caesalpiniaceae Tree kanchan LC

30 Bauhinia retusa Caesalpiniaceae Tree ─ LC

EIA Report

284 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Scientific Name Family Life form

Local Name IUCN Status

31 Beilschmiedia roxburghiana

Lauraceae Tree ─ LC

32 Biophytum sensitivum Oxalidaceae Herb ─ LC

33 Brassica campestris Brassicacea Herb ─ LC

34 Buchanania lanzan Anacardiaceae Tree Piyal LC

35 Bulbostylis barbata Cyperaceae Sedge ─ LC

36 Bulbostylis densa Cyperaceae Sedge ─ LC

37 Bulbostylis puberula Cyperaceae Sedge ─ LC

38 Butea monosperma Fabaceae Tree bipornok LC

39 Butea parviflora Fabaceae Shrub ─ LC

40 Capparis zeylanica Capparaceae Shrub ─ LC

41 Careya arborea Lecythidaceae Tree Kumbi LC

42 Cardiospermum halicacabum

Sapindaceae Herb ─ LC

43 Casearia vareca Flacourtiaceae Herb ─ LC

44 Cassia fistula Caesalpiniaceae Tree Sonaru, Sonalu. LC

45 Cayratia trifolia Vitaceae Climber ─ LC

46 Cicer arietinum Fabaceae Herb ─ LC

47 Cinamomum bejolghota Lauraceae Tree Tejpat, Mahpat, Tejpat. LC

48 Cissampelos pareira Menispermaceae Climber ─ LC

49 Cissus quadrangularis Vitaceae Climber ─ LC

50 Citrus limon Rutaceae Tree Nemu tenga. LC

51 Clematis buchananiana Ranunculaceae Climber ─ LC

52 Coelogyne trinervis Orchidaceae Herb ─ VU

53 Courtoisia cyperoides Cyperaceae Sedge ─ LC

54 Creteva magna Capparaceae Herb Barun LC

55 Crinum amoenum Amaryllidaceae Herb ─ LC

56 Crotalaria alata Fabaceae Herb ─ LC

57 Crotalaria linifolia Fabaceae Herb ─ LC

58 Crotalaria mysorensis Fabaceae Herb ─ LC

59 Crotalaria prostrata Fabaceae Herb Dhundhuni LC

60 Crotalaria verrucosa Fabaceae Herb ─ LC

61 Crypteronia paniculata Lythraceae Climber ─ LC

62 Cymbopogon flexuosus Poaceae Grasses Nemu-gondhibon. LC

63 Cynodon dactylon Poaceae Grasses ─ LC

64 Cyperus compressus Cyperaceae Sedge ─ LC

65 Dalbergia latifolia Fabaceae Tree ─ LC

66 Dalbergia sissoo Fabaceae Tree Sisu-goch. LC

67 Desmodium pulchellum Fabaceae Shrub ─ LC

68 Desmodium triquetrum Fabaceae Herb ─ LC

69 Digitaria longiflora Poaceae Grasses ─ LC

70 Dillenia indica Dilleniaceae Tree Outenga, Ou-tenga. LC

EIA Report

285 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Scientific Name Family Life form

Local Name IUCN Status

71 Drymaria diandra Caryophyllaceae Herb ─ LC

72 Euryale ferox Nymphaeaceae Herb ─ LC

73 Ficus amplissima Moraceae Tree ─ LC

74 Ficus benghalensis Moraceae Tree Barh LC

75 Ficus hispida Moraceae Tree Dimoru LC

76 Ficus racemosa Moraceae Tree Mou-dimoru,. Jagya-dimoru.

LC

77 Ficus religiosa Moraceae Tree ─ LC

78 Fimbristylis miliacea Cyperaceae Sedge ─ LC

79 Garcinia lancaefolia Clusiaceae Tree Mahi thekera LC

80 Garcinia xanthochymus Clusiaceae Tree ─ LC

81 Globba sessiliflora Zingiberaceae Herb ─ LC

82 Glycosmis pentaphylla Rutaceae Tree Gin Berry LC

83 Gmelina arborea Verbenaceae Tree ─ LC

84 Gmelina asiatica Verbenaceae Shrub Gomari LC

85 Helicteres isora Sterculiaceae Shrub ─ LC

86 Kyllinga triceps Cyperaceae Sedge ─ LC

87 Lagerstroemia minuticarpa

Lythraceae Tree Saoni. VU

88 Lagerstroemia speciosa Lythraceae Tree ─ LC

89 Ludwigia perennis Onagraceae Herb ─ LC

90 Ludwigia prostrata Onagraceae Herb ─ LC

91 Malvastrum coromandelianum

Malvaceae Herb ─ LC

92 Mangifera indica Anacardiaceae Tree Aam, Am, Aam. LC

93 Pongamia pinnata Fabaceae Tree koroch LC

94 Portulaca oleraceae Portulacaceae Herb ─ LC

95 Portulaca quadrifida Portulacaceae Herb ─ LC

96 Pouzolzia hirta Urticaceae Herb ─ LC

97 Pseudarthria viscida Fabaceae Shrub ─ LC

98 Psidium guajava Myrtaceae Tree ─ LC

99 Pterocarpus marsupium Fabaceae Tree IndianKino, Bijasal LC

100 Pycreus stramineus Cyperaceae Sedge ─ LC

101 Schima wallichii Theaceae Tree ─ LC

102 Semecarpus anacardium Anacardiaceae Tree Bhallataka, geeru beeja LC

103 Shorea assamica Dipteroarpaceae Tree Mekoi, Mekahi. LC

104 Sida acuta Malvaceae Herb ─ LC

105 Solanum melongena Solanaceae Herb ─ LC

106 Solanum tuberosum Solanaceae Herb ─ LC

107 Soymida febrifuga Meliaceae Tree Raktarohan LC

108 Spondias pinnata Anacardiaceae Tree Amara, Amra-tenga LC

109 Stephania japonica Menispermaceae Climber ─ LC

EIA Report

286 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Scientific Name Family Life form

Local Name IUCN Status

110 Sterculia urens Sterculiaceae Tree Kulu LC

111 Sterculia sp. Sterculiaceae Tree ─ LC

112 Sterculia villosa Sterculiaceae Tree Odal, Udal. LC

113 Swietenia mahagoni Meliaceae Tree ─ LC

114 Syzygium cumini Myrtaceae Tree Jamu, kala jamu LC

115 Syzygium salicifolium Myrtaceae Tree ─ LC

116 Tectona grandis Verbenaceae Tree Segun. LC

117 Tephrosia purpurea Fabaceae Herb ─ LC

118 Terminalia chebula Combretaceae Tree ─ LC

119 Terminallia arjuna Combretaceae Tree Arjun. LC

120 Tinospora cordifolia Menispermaceae Climber ─ LC

121 Toona ciliata Meliaceae Tree Lal-poma LC

122 Trapa natans Trapaceae Herb ─ LC

123 Viscum articulatum Viscaceae Shrub ─ LC

124 Vitex negundo Verbenaceae Tree Posotiya LC

Table 3-21 List of Mangroves in the study area

S.No Scientific Name Family Life form Local Name

IUCN Status

1 Acanthus ilicifolius Acanthaceae Shrub Harkancha LC

2 Acanthus volubilis Acanthaceae Shrub Harkancha EN

3 Acrostichum aureum Adiantaceae Fern Kharakhari LC

4 Bruguiera sexangula Rhizophoraceae Tree Bandari EN

5 Ceriops decandra Rhizophoraceae Tree Garana LC

6 Dolichandrone spathacea Bignoniaceae Tree Gosinga LC

7 Excoecaria agallocha Euphorbiaceae Tree Guan LC

8 Heritiera kanikensis Stercullaceae Tree Kanika Sundari EN

9 Heritiera littoralis Stercullaceae Tree Dhala Sundari EN

10 Kandelia candel Rhizophoraceae Tree Sindhuka LC

11 Rhizophora macronata Rhizophoraceae Tree Raai LC

12 Sonneratia caseolaris Sonneratiaceae Tree Orua LC

13 Xyloearpus granatum Meliaceae Tree Shishumar LC

14 Xylocarpus mekongensis Meliaceae Tree Pitamari LC (LC- Least Concern, NT- near Threatened, EN- Endangered, NA-Not yet assessed, DD -Data

Deficient, VU-Vulnerable)

Source:

Fascicles of flora of India. Botanical survey of India. https://bsi.gov.in/page/en/fascicles-of-flora-of-india

EIA Report

287 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.11.2 Fauna

The information of important terrestrial animals group such as birds, reptiles and mammals

were collected from the secondary sources. An inventory of the animals has been prepared

separately for mammals, reptiles and birds. List of fauna reported in the study area is given in

Table 3-22.

Table 3-22 List of Fauna observed in the study area

Mammals in around project site

A total of 16 species of Mammals were recorded from the secondary source

(EN-Endangered; VU-Vulnerable; NT-Near Threatened; LC- Least Concern in IUCN red list)

Amphibian and reptile Diversity in around project site

A total of 36 species were referred. There are Turtle nesting sites along the Mahanadhi river

mouth region. The Kujang Coast and Hetamundia Seashore Village is predominant turtle

nesting area.

S. No Scientific name Family IUCN IWPA

schedule Amphibian

S.

No Scientific Name Family Name Common Name

IUCN

status

1 Mus musculus Muridae Common Mouse LC2 Funambulus pennanti Sciuridae Palm -Squirrel LC 3 Mus rattus Muridae Indian rat LC 4 Lepus nigricollis Leporidae Indian Hare LC 5 Rattus norvegicus Muridae Brown Rat LC6 Felis catus Felidae Cat LC7 Felis chaus Felidae Jungle Cat LC8 Canis aureus Canidae Asiatic Jackal LC

9 Herpestes edwardsii Herpestidae Indian Grey Mongoose LC

10 Herpestes javanicus Herpestidae Small Asian Mongoose LC

11 Macaca mulatto Cercopithecidae Rhesus Macaque LC 12 Hystrix brachyura Hystricidae Porcupine LC 13 Rhizomys pruinosus Spalacidae Hoary Bamboo Rat LC

14 Cynopterus sphinx PteropodidaeShort nosed Indian fruit Bat LC

15 Scotophilus kuhlii VespertilionidaeLesser Asiatic yellow Bat LC

16 Suncus murinus Soricidae Asian House Shrew LC

EIA Report

288 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No Scientific name Family IUCN IWPA

schedule 1 Duttaphrynus melanostictus Bufonidae LC NS

2 Megophrys parva Megophryidae LC NS

3 Microhyla ornata Microhylidae LC NS

4 Microhyla berdmorei Microhylidae LC NS

5 Hoplobatrachus tigerinus Dicroglossidae LC IV

6 Euphlyctis cyanophlyctis Dicroglossidae LC IV

7 Fejervarya teraiensis Dicroglossidae LC IV

8 Fejervarya pierrei Dicroglossidae LC IV

9 Fejervarya syhadrensis Dicroglossidae LC IV

10 Fejervarya nepalensis Dicroglossidae LC IV

11 Limnonectes khasianus Dicroglossidae DD IV

12 Amolops assamensis Ranidae DD IV

13 Amolops gerbillus Ranidae LC IV

14 Humerana humeralis Ranidae LC IV

15 Silvirana leptoglossa Ranidae LC IV

16 Clinotarsus alticola Ranidae LC IV

17 Hylarana tytleri Ranidae LC IV

18 Polypedates teraiensis Rhacophoridae LC NS

19 Philautus garo Rhacophoridae VU NS

20 Rhacophorus bipunctatus Rhacophoridae LC NS

21 Ichthyophis garoensis Ichthyophiidae DD NS

22 Ichthyophis moustakius Ichthyophiidae DD NS

Reptile

23 Nilssonia hurum Tryonichidae VU I

24 Lissemys punctata Tryonichidae LC I

25 Xenochrophis piscator Tryonichidae NE II

26 Amphiesma stolata Tryonichidae NE IV

27 Enhydris enhydris Tryonichidae LC IV

28 Ptyas mucosa Tryonichidae NE II

29 Ptyas korros Tryonichidae NE IV

30 Rhabdophis subminiatus Tryonichidae LC IV

31 Chrysopelea ornata Tryonichidae NE IV

32 Psammodynastes pulverulentus Tryonichidae NE IV

33 Naja kaouthia Elapidae LC II

34 Bungarus fasciatus Elapidae LC IV

35 Trimeresurus albolabris Viperidae LC IV

(S-I-Schedule-Iof Indian Wild Life Protection Act-1972; EN-Endangered; VU-Vulnerable;

NT-Near Threatened; LC- Least Concern in IUCN red list)

Birds Diversity in around project site

A total of 62 species of birds, belonging to 17 families, were recorded from the secondary

source.

EIA Report

289 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Common Name Scientific name Conservation

status I ANATIDAE

1. Gadwall Mareca strepera LC 2. Lesser Whistling Duck Dendrocygna javanica LC 3. Eurasian Wigeon M. penelope LC 4. Baer’s Pochard Aythya baeri En5. Common Teal Anas crecca LC6. Mallard A. platyrhynchos LC7. Northern Pintail A. acuta LC 8. Northern Shoveller Spatula clypeata LC 9. Red-crested Pochard Netta rufina LC

10. Ferruginous Duck A. nyroca NT 11. Garganey S. querquedula LC12. Common Pochard A. ferina LC13. Tufted Duck A. fuligula LC

II CHARADRIIDAE

14. Northern Lapwing Vanellus vanellus LC 15. Grey-headed Lapwing V. cinereus LC 16. Red-wattled Lapwing V. indicus LC17. Pacific Golden Plover Pluvialis fulva LC18. River Lapwing V. duvaucelii LC19. Little Ringed Plover Charadrius dubius LC20. Greater Sand Plover C. leschenaultii LC III ARDEIDAE

21. Great Egret Ardea alba LC 22. Intermediate Egret A. intermedia LC23. Little Egret Egretta garzetta LC24. Cattle Egret Bubulcus ibis LC25. Grey Heron Ardea cinerea LC 26. Indian Pond Heron Ardeola grayii LC IV PHALACROCORACIDAE

27. Little Cormorant Microcarbo niger LCV CICONIIDAE

28. Asian Openbill Anastomus oscitans LC29. Lesser Adjutant Leptoptilos javanicus VuVI JACANIDAE 30. Pheasant-tailed Jacana Hydrophasianus

chirurgus LC

31. Bronze-winged Jacana Metopidius indicus LC VII RECURVIROSTRIDAE

32. Pied Avocet Recurvirostra avosetta LCVIII PODICIPEDIDAE

EIA Report

290 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Common Name Scientific name Conservation

status 33. Little Grebe Tachybaptus ruficollis LC34. Great Crested Grebe Podiceps cristatus LC IX RALLIDAE

35. Common Coot Fulica atra LC 36. Purple Swamphen Porphyrio porphyrio LC

X ALCEDINIDAE

37. White-throated Kingfisher Halcyon smyrnensis LC38. Common Kingfisher Alcedo atthis LC 39. Pied Kingfisher Ceryle rudis LC 40. Ruddy Kingfisher H. coromanda LC XI MOTACILLIDAE

41. Western Yellow Wagtail Motacilla flava LC42. White Wagtail M. alba LC43. Citrine Wagtail M. citreola LC 44. Grey Wagtail M. cinerea LC XII LARIDAE

45. Black-headed Gull Chroicocephalus ridibundus

LC

46. Whiskered Tern Chlidonias hybrida LC XIII HIRUNDINIDAE

47. Barn Swallow Hirundo rustica LCXIV FALCONIDAE

50. Common Kestrel Falco tinnunculus LC XV ACCPITRIDAE

51. Pied Harrier Circus melanoleucos LC 52. Eastern Marsh Harrier C. spilonotus LC53. Osprey Pandion haliaetus LC

XVI SCOLOPACIDAE

54. Jack Snipe Lymnocryptes minimus LC 55. Common Snipe Gallinago gallinago LC 56. Marsh Sandpiper Tringa stagnatilis LC 57. Green Sandpiper T. ochropus LC58. Wood Sandpiper T. glareola LC59. Common Sandpiper Actitis hypoleucos LC60. Common Green Shank T. nebularia LC 61. Little Stint Calidris minuta LC

XVII ROSTRATULIDAE

62. Greater Painted-snipe Rostratula benghalensis LC

EIA Report

291 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

(EN-Endangered; VU-Vulnerable; NT-Near Threatened; LC- Least Concern in IUCN red list)

Butterfly Diversity in around project site

A total number of 56 species of butterflies belonging to 5 families were reported. Among

various families of butterflies found, Nymphalidae family was represented by 17 species

followed by 16 species of Pieridae, 11 species of Lycaenidae, 5 species of Papilionoidae, 6

species of Hesperidae.

S.No Scientific Name IUCN WPA

Family Papilionidae 1 Graphium doson NE -2 Graphium agamemno NE - 3 Pachliopta aristolochiae LC - 4 Papilio demoleus NE - 5 Papilio polytes NE -

Family Nymphalidae 6 Danaus genutia NE -7 Tirumala limniace NE -8 Parantica aglea NE Schedule II - Part II

9 Euploea core LC Schedule IV

10 Melanitis leda NE - 11 Phalanta phalantha NE - 12 Acraea terpsicore NE -13 Phalanta phalantha NE -14 Ariadne merione NE -15 Ariadne ariadne NE - 16 Junonia iphita NE - 17 Junonia orithya NE - 18 Junonia atlites NE -19 Junonia lemonias NE -20 Junonia almana LC -21 Hypolimnas misippus NE Schedule I - Part IV

22 Hypolimnas bolina NE -

Family Pieridae 23 Catopsilia pomona NE - 24 Catopsilia pyranthe NE -25 Eurema hecabe NE -26 Eurema brigitta NE -27 Eurema laeta NE - 28 Delias eucharis NE - 29 Pareronia hippia NE - 30 Ixias marianne NE - 31 Ixias pyrene NE -32 Colotis aurora NE -33 Colotis danae NE -34 Colotis fausta NE -

EIA Report

292 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

35 Colotis amata NE -36 Colotis vestalis NE - 37 Belenois aurota NE - 38 Cepora nerissa NE Schedule II - Part II

Family Lycaenidae 39 Caleta caleta NE -

40 Castalius rosimon NE Schedule I - Part IV

41 Tarucus nara NE -

42 Euchrysops cnejus NE Schedule II - Part II

43 Catochrysops strabo NE - 45 Zizeeria karsandra LC - 46 Zizina otis NE - 47 Chilades lajus NE -48 Freyeria putli NE -49 Leptotes plinius NE -50 Spindasis vulcanus NE -

Family Hesperiidae 51 Borbo cinnara NE - 52 Pelopidas mathias NE -53 Hasora chromus NE -54 Suastus gremius NE -55 Telicota ancilla NE - 56 Spialia galba NE -

Fish Diversity in around project site

S.No Common Name Species IUCN

1 Indian butter Cat fish Ompok bimacutatus NT

2 Rohu labeo rohita LC

3 Mrigal Cirrhinus mrigata LC

4 (Magur) Ctarias magur LC

5 Sunset Gourami Trichogaster talius LC

6 Dangila danio Danio dangita LC

7 Tiger Loach Botia dario LC

8 Devil fish Chaca chaca LC

(EN-Endangered; VU-Vulnerable; NT-Near Threatened; LC- Least Concern in IUCN red

list)

Source :

Fauna of Mahanadi Estuary Orissa. Zoological Survey of India Calcutta. 1998. http://faunaofindia.nic.in/PDFVolumes/ess/003/index.pdf

Fauna of Orissa. Part 3. State Fauna Series 1. Zoological Survey of India. 1991 https://zsi.gov.in/App/regcenters.aspx?reg=544&link=538

Bivash Pandav, B C Choudhury and C S Kar. 1994. Sea Turtle Nesting Habitats on the Coast of Orissa1 https://www.semanticscholar.org/paper/Sea-Turtle-Nesting-Habitats-on-the-Coast-of-Orissa1 PandavChoudhury/8c4be98dcc768e2d89e79cf676476fac178fc451?p2df

EIA Report

293 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.11.3 Management in and around Project area

Environmental problems in the state of Odisha have been influenced partly by the increasing

population, survival needs of the poor and the economic greed of the commercial interests.

They are also aggravated by prevalent economic disparities and unemployment, which are

deeply embedded in unsustainable patterns of production and consumption; ill-informed

policies and programs; and inappropriate developing strategies. As far as the forest resources

of the Near Brahmaputra valley is concerned, gap in scientific knowledge, increasing

demands, lack of value addition are the main causes for which the vast potential is yet to be

tapped properly and in some cases over exploited. Gap in scientific knowledge on various

forest resources and products is a major problem for management of resources in the state.

Although considerable amounts of revenue have been collected from forest products where

local people are also directly or indirectly involved in gathering and in some cases marketing

as well, but they have hardly any knowledge on the silvicultural management of various

minor forest products. Except for some well-known commercial species, the information on

distribution of various forest products, their density, regeneration status, yield estimate and

harvesting levels are lacking. There is need to formulate sound management plan that

addresses the knowledge about the life cycle pattern of the species, productivity and yield

estimation techniques.

Monitoring and maintaining of the complex ecosystem is important aspect of bioresource

management. Technical aspects include choice between different methods and techniques and

development of appropriate harvesting and processing technologies. There is also social

aspect of resource management that deal with people, cultures, belief systems, attitudes and

behaviour, ethics, aspirations and social values. As far as the state of Odisha is concerned, all

these aspects should be taken into consideration prior to the formulation of management

strategies. Finally, exercise of administrative power in another important aspect to hold

control over users of resources and decision-making.

For reclamation of degraded forest lands and riparian sites, plantation and ecorestoration

programme may be initiated with prioritize species in relation to ecoregion/ agro-climatic

zones. In riparian sites plantation of bamboo and various species of grass can be initiated to

check erosion. Eco-sensitive zones in the valley should be demarcated and regulations may

be imposed on developmental projects like mega dams, industrial activities, 34 quarrying and

mining in such areas are other important measures of conservation may be initiated.

EIA Report

294 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Updation of the database on floristic diversity in terms of species, ecosystems & genetic traits

with reference to status, pressures and also in regard to changing climate are other issues of

resource management.

Source:

1. List of Schedule Species

http://wiienvis.nic.in/Database/ScheduleSpeciesDatabase_7969.aspx

3.11.4 Summary

a.Flora There is a vulnerable herbs in the study area i.e., named Acanthephippium silhetense

and Coelogyne trinervis

There is a vulnerable tree in the study area i.e., named Lagerstroemia minuticarpa

There is a endangered Shrub Mangrove in the study area i.e., named Acanthus

volubilis Wall

There are three endangered Tree Mangrove in the study area i.e., named Bruguiera

sexangula, Heritiera kanikensis Majumdar and Heritiera littoral is Dryand

b.Fauna

There is a vulnerable Amphibian in the study area i.e., named Philautus garo

(Boulenger 1919)

There is a endangered bird in the study area i.e., named Baer’s Pochard

There is a vulnerable bird in the study area i.e., named Lesser Adjutant

There is a near threatened fish in the study area i.e., named Indian butter Cat fish

There are two Schedule-I Species in study area i.e., reptiles named Nilssoniahurum

(Gray 1831) and Lissemyspunctata (Bonnaterre 1789) habitats.

There are two numbers of Schedule-I-Part-IV in study area i.e., Hypolimnas misippus

and Castalius rosimon

Summary on Flora in the Study area

Not yet assessed

Data Deficien

t

Least Concern

Endangered

Near Threatene

d

Vulnerable

Critically Endangered

Trees — — 65 3 — 1 —

Grasses — — 7 — — — —

Herbs — — 33 — — 2 —

Shrubs — — 11 1 — — —

Climber — — 7 — — — —

EIA Report

295 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sedges — — 8 — — — —

Fern __ __ 1 __ __ __ __

Summary on Fauna in the Study area

Not yet assessed

Data Deficien

t

Least Concer

n

Endangered

Near Threaten

ed

Vulnerable

Near Threatened

Mammals — — 16 — — — —

Reptiles — — 6 — — 1 6

Amphibians — 4 17 — — 1 —

Butterfly 52 — 4 — — — —

Birds — — 59 1 1 1 —

Fish — — 7 — 1 — —

3.12 Socio Economic Profile

In terms of population per Sq.Km Jagatsinghapur is 2nd densely populated district in the state.

The population of the district is 11,36,971 which comprise of 5,77,865 male and 5,59,106

female populations.

Source: (Census 2011)

3.12.1 Socio Economic Profile of PIA District

In Jagatsinghapur district 29.2% of the people does not have house, 89.9% of people uses

firewood for cooking, 47.3% of people uses kerosene for lighting and 45.9% of people are

landless

Source:

People’s Audit of Health, Education and Livelihood- Survey Report of Odisha, 2012-

http://phdmaodisha.nic.in/Reports/HDRS/PaheliReport-Odisha-2009-10-2012.pdf

3.12.1.1 Socio Economic Aspects

A socio-economic study was undertaken in assessing aspects which are dealing with

social and cultural conditions, and economic status in the study area. The study provides

information such as demographic structure, population dynamics, infrastructure resources,

and the status of human health and economic attributes like employment, per-capita income,

agriculture, trade, and industrial development in the study area. The study of these

characteristic helps in identification, prediction and evaluation of impacts on socio-economic

and parameters of human interest due to proposed project developments. The parameters are:

EIA Report

296 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Demographic structure

Infrastructure Facility

Economic Status

Health status

Cultural attributes

Awareness and opinion of people about the project and Industries in the area.

Table 3-23 shows some important Social Indicators of Jagatsinghapur District.

Table 3-23 Social Indicators of Jagatsinghapur District

S.No Social Indicators Jagatsinghapur District

1 Decadal variation % 7.5

2 Urban population % 10.20

3 Sex ratio 968

4 0-6 age group % 9.11

5 Population density (Persons per square Km) 682

6 Scheduled caste population % 21.8

7 Scheduled tribe population % 0.7

8 Literacy rate % 86.59

9 Work Participation rate % 35.5

10 Main Workers % 25.52

11 Marginal Workers % 9.98

12 Cultivators % 27.58

13 Agricultural labourers % 27.33

14 Workers in household industries % 4.05

15 Other workers % 41.04

Source:

http://censusindia.gov.in/2011census/dchb/2111_PART_B_DCHB_JAGATSINGHAPUR.p

df

3.12.1.2 Population and Household Size

The total population of the district as per 2011 Census is 11,36,971. Of the total population,

5,77,865 are males and 5,59,106 are females. The population of the district is further

EIA Report

297 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

distributed as 10,20,991 living in rural areas and 1,15,980 living in urban areas. The total

number of households in the Jagatsinghapur district is 2,60,846.

Source:

http://censusindia.gov.in/2011census/dchb/2111_PART_B_DCHB_JAGATSINGHAPUR.p

df

3.12.1.3 Sex Ratio

The sex ratio is defined as number of females to 1000males. According to 2011 Census, the

sex ratio of the district is 968. The sex ratio of the rural and urban areas of Jagatsinghapur

district is 976 and 900 respectively. The 0-6 age group sex ratio is 9.11 for the district.

Source:

http://censusindia.gov.in/2011census/dchb/2111_PART_B_DCHB_JAGATSINGHAPUR.p

df

3.12.1.4 Scheduled Castes and Scheduled Tribes

Total Scheduled Castes (SCs) population reported in the district is 2,48,152 persons,

constituting about 21.83 percent of total population of the district. Total Scheduled tribe

population reported in the district is 7,862 persons constituting about 0.69 percent of total

population.

Source:

http://censusindia.gov.in/2011census/dchb/2111_PART_B_DCHB_JAGATSINGHAPUR.p

df

3.12.1.5 Education & Literacy

The study of the education and literacy profile in the region is relevant in order to have an

understanding whether the proposed project can utilize skilled human resources available

within the area. According to 2011 census data, the literacy rate in the Jagatsinghapur district

is 86.59 %. The literacy rate has been the major determinant of the rise or fall of the other

indicators. The accessibility of Primary and Upper Primary education has increased the

literacy rate as well as reducing the dropout rate. Table 3-24 Shows the details of education

infrastructures in Jagatsinghapur District.

EIA Report

298 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 3-24Education Infrastructures in the Jagatsinghapur District

Type of school Total schools Rural Schools

Government Private Government Private

Primary 906 34 886 32

Primary + Upper Primary 361 89 346 81

P + UP+ Secondary + Higher Secondary 1 2 0 1

UP only 67 66 67 66

UP + Secondary + Higher Secondary 0 0 0 0

P + UP + Secondary 8 14 8 9

UP + Secondary 161 128 153 126

(Source: District Information Systems on Education (DISE report card 2016-17))

3.12.1.6 Health Facilities

Primary Health Centers (PHCs) and Health Sub-centers (HSCs) are providing the preventive,

curative and rehabilitative health care services to the rural people. The district has good

number of public health systems accessible and affordable apart from the private health

facilities. The Health Facilities given in Table 3-25.

Table 3-25 Medical Facilities available in JagatsinghapurDistrict

Name of

the

District

Type

of

Facili

ty

Facilities As on 11th June 2019

Total Facility Active Facilities

Total

[(A+B

) or

(C+D)

]

Publi

c [A]

Priva

te [B]

Urb

an

[C]

Rur

al

[D]

Total

[(A+B

) or

(C+D)

]

Pub

lic

[A]

Priva

te [B]

Urb

an

[C]

Rur

al

[D]

Jagatsin

ghapur

SC 189 189 0 0 189 189 189 0 0 189

PHC 37 37 0 0 37 35 35 0 0 35

CHC 12 11 1 1 11 12 11 1 1 11

SDH 0 0 0 0 0

DH 2 2 0 0 2 1 1 0 0 1

Total 240 239 1 1 239 237 236 1 1 236

EIA Report

299 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

(Note: SC – Sub Center; PHC – Primary Health Center; CHC – Community Health Center;

SDH – Sub District Hospital; DH – District Hospital)

(Source: National Health Mission, as on June 11, 2019)

3.12.1.7 Employment and Livelihood

The relevance of economic activity and livelihood pattern is important in the context of the

study

since depending on the existing situation one can predict the impact of the project activity on

the economy of the region. In Jagatsinghapur district, as per the Census 2011, there were a

total of 4,03,649 workers, comprising 1,11,320 cultivators, 1,10,323 agricultural labourers,

16,357 house hold Industry workers and 1,65,649 other workers. A vast majority of the

people living in rural areas mainly depend on agriculture and animal husbandry for their

livelihood.

Source:

http://censusindia.gov.in/2011census/dchb/2111_PART_B_DCHB_JAGATSINGHAPUR.p

df

3.12.2 Socio Economic Profile of study area

Social Economic Profile of the study area

The project area comes under the Jagatsinghapur District of Odisha. Table 3-26 provides the

details on population profile within study area. Table 3-27 show the socio-economic

indicator within the study area.

EIA Report

300 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 3-26 Population profile within study area

Sl.

No Name

No of

Households

Total

Population

Person

Total

Population

Male

Total

Population

Female

Population

in the age

group 0-6

Person

Sex

ratio

Scheduled

Castes

Population

Person

Scheduled

Tribes

Population

Person

Jagatsinghapur

1 Abhayachandapur 8 28 13 15 5 1154 0 12

2 Aganasi 0 0 0 0 0 0 0 0

3 Alligarh 122 506 269 237 39 881 0 0

4 Anantapur 103 405 200 205 29 1025 110 0

5 Badabandha 196 889 460 429 90 933 98 6

6 Badagabapur 279 1193 623 570 113 915 152 0

7 Bagadia 544 2736 1422 1314 293 924 887 0

8 Bagoi 405 1970 1006 964 184 958 182 0

9 Baharatari 32 140 72 68 10 944 40 1

10 Baidigadi 52 227 115 112 23 974 5 29

11 Balarampur 1143 5464 2838 2626 521 925 1247 0

12 Baleipur 150 680 358 322 38 899 51 0

13 Balia 361 1681 828 853 180 1030 233 0

14 Balidia 386 1972 989 983 228 994 66 4

EIA Report

301 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.

No Name

No of

Households

Total

Population

Person

Total

Population

Male

Total

Population

Female

Population

in the age

group 0-6

Person

Sex

ratio

Scheduled

Castes

Population

Person

Scheduled

Tribes

Population

Person

15 Balitutha 297 1231 598 633 138 1059 320 0

16 Bamadeipur 710 3161 1592 1569 346 986 919 3

17 Banapatakandha 135 631 332 299 45 901 57 0

18 Barabelari 28 133 61 72 24 1180 0 0

19 Baradakandha 0 0 0 0 0 0 0 0

20 Baulanga 300 1429 738 691 134 936 196 1

21 Bayanalkandha 43 186 98 88 18 898 104 0

22 Bhitarasrichandanpur 59 295 150 145 28 967 48 0

23 Bhutumundai 850 3933 2035 1898 422 933 811 4

24 Boitarakuda 0 0 0 0 0 0 0 0

25 Chadeigahanjharakati 0 0 0 0 0 0 0 0

26 Chakradharpur 180 851 432 419 94 970 198 4

27 Chakulia 104 474 245 229 49 935 1 0

28 Chatua 366 1577 809 768 165 949 239 1

29 Chaukimatha 0 0 0 0 0 0 0 0

30 Chauliapalanda 6 30 13 17 6 1308 0 0

EIA Report

302 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.

No Name

No of

Households

Total

Population

Person

Total

Population

Male

Total

Population

Female

Population

in the age

group 0-6

Person

Sex

ratio

Scheduled

Castes

Population

Person

Scheduled

Tribes

Population

Person

31 Chhatarakandha 124 524 268 256 64 955 0 0

32 Dagan 189 813 388 425 68 1095 337 0

33 Dhinkia 832 4141 2114 2027 365 959 1649 2

34 Gandakipur 1310 5925 3025 2900 591 959 4305 1

35 Garhkujang 455 2082 1031 1051 242 1019 1247 0

36 Ghodamara 121 593 309 284 58 919 359 0

37 Gobinda Pur 512 2153 1060 1093 164 1031 434 0

38 Guamunda 200 795 413 382 70 925 50 0

39 Jaganathapur 90 385 209 176 34 842 4 0

40 Jamukana 167 680 330 350 69 1061 358 0

41 Jhimani 595 2963 1502 1461 314 973 502 3

42 Kaduapalli-kandha 0 0 0 0 0 0 0 0

43 Kansaripatia 5 9 4 5 0 1250 5 0

44 Karatutha 258 1142 562 580 103 1032 185 0

45 Katakulla 182 890 464 426 84 918 42 0

46 Katha-ada 107 417 243 174 35 716 41 0

EIA Report

303 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.

No Name

No of

Households

Total

Population

Person

Total

Population

Male

Total

Population

Female

Population

in the age

group 0-6

Person

Sex

ratio

Scheduled

Castes

Population

Person

Scheduled

Tribes

Population

Person

47 Keruadia-kandha 0 0 0 0 0 0 0 0

48 Kothi 425 2074 1063 1011 187 951 361 0

49 Kujang 38443 176065 90027 86038 17500 956 41187 462

50 Mahakaldia 0 0 0 0 0 0 0 0

51 Mangarajpur 724 3314 1674 1640 309 980 1647 0

52 Mirigidiakandha 0 0 0 0 0 0 0 0

53 Musadia 810 2852 1625 1227 387 755 186 27

54 Naladia Palanda 0 0 0 0 0 0 0 0

55 Narendrapur 319 1442 750 692 151 923 478 0

56 Niharuni 72 314 160 154 44 963 52 0

57 Nimidhihi 261 1371 704 667 163 947 151 5

58 Noliasahi 191 780 406 374 101 921 0 0

59 Nuagan 1248 5185 2674 2511 424 939 547 0

60 Nuagarh 525 2565 1282 1283 309 1001 236 0

61 Panigadiakandha 4 12 6 6 1 1000 3 0

62 Paradipgarh (CT) 1006 4790 2425 2365 505 975 1807 48

EIA Report

304 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.

No Name

No of

Households

Total

Population

Person

Total

Population

Male

Total

Population

Female

Population

in the age

group 0-6

Person

Sex

ratio

Scheduled

Castes

Population

Person

Scheduled

Tribes

Population

Person

63 Paradip(M) 17485 68585 37300 31285 7403 846 7167 2924

64 Parapada 71 360 189 171 35 905 86 0

65 Parianga 152 625 313 312 72 997 113 0

66 Patapur 147 752 401 351 63 875 58 14

67 Pitambarpur 143 680 343 337 77 983 32 0

68 Polanga 96 396 216 180 72 833 24 21

69 Potak 81 356 193 163 30 845 43 0

70 Purusotampur 127 560 276 284 38 1029 253 0

71 Raghunathpur 515 2527 1266 1261 202 996 554 0

72 Rajapur 157 669 298 371 65 1245 321 0

73 Rangiagarh 430 2068 1072 996 237 929 429 12

74 Ranipada 98 439 227 212 39 934 8 0

75 Raulapada 44 185 98 87 23 888 75 0

76 Sahada 264 1115 522 593 115 1136 253 0

77 Saharadia 303 1447 739 708 156 958 366 0

78 Sandhapur 154 784 385 399 92 1036 19 0

EIA Report

305 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.

No Name

No of

Households

Total

Population

Person

Total

Population

Male

Total

Population

Female

Population

in the age

group 0-6

Person

Sex

ratio

Scheduled

Castes

Population

Person

Scheduled

Tribes

Population

Person

79 Santara 338 1683 872 811 166 930 437 0

80 Siju 303 1531 776 755 172 973 219 0

81 Srirampur 155 747 386 361 68 935 93 0

82 Sunadiakandha 96 509 245 264 96 1078 0 0

83 Tentulia 296 1284 661 623 84 943 165 0

84 Tentuliakhamar 320 1403 733 670 138 914 313 0

85 Trilochanpur 554 2803 1436 1367 250 952 935 0

86 Uchhabanandpur 157 908 467 441 102 944 72 0

87 Udayabata 449 1953 1008 945 291 938 111 11

Kendrapara

88 Akhadasali 35 174 89 85 26 955 6 0

89 Chhanda 214 998 517 481 109 930 41 0

90 Gararomita 454 1953 977 976 219 999 507 0

91 Kankadia 61 290 143 147 30 1028 15 0

92 Khurusia 278 1068 550 518 87 942 33 0

93 Khurusiapat 120 456 230 226 50 983 124 0

EIA Report

306 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.

No Name

No of

Households

Total

Population

Person

Total

Population

Male

Total

Population

Female

Population

in the age

group 0-6

Person

Sex

ratio

Scheduled

Castes

Population

Person

Scheduled

Tribes

Population

Person

94 Koratapanga 240 1076 550 526 84 956 211 0

95 Lunia 21 95 45 50 6 1111 0 0

96 Nalitajori Pal 33 168 78 90 34 1154 0 0

97 Nandanpur 0 0 0 0 0 0 0 0

98 Paunsiapal 0 0 0 0 0 0 0 0

99 Rajendra Nagar 32 158 79 79 24 1000 41 0

100 Subala 209 1067 565 502 105 888 20 8

101 Taradeipur 4 19 13 6 2 462 0 0

102 Tekarapanga 169 736 387 349 75 902 49 0

Total 80839 358725 185659 173066 36501 932 75330 3603

(Source: Census 2011)

EIA Report

307 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 3-27 Summary of Socioeconomic indicators within the study area

S.No Particulars Study Area Unit

1 Number of villages and Town in the Study Area 102 Nos.

2 Total Households 80839 Nos.

3 Total Population 358725 Persons

4 Children Population (0-6 Years Old) 36501 Persons

5 SC Population 75330 Persons

6 ST Population 3603 Persons

7 Total Working Population 118859 Persons

8 Main Workers 95224 Persons

9 Marginal Workers 23635 Persons

10 Cultivators 27679 Persons

11 Agricultural Labourers 18768 Persons

12 Household Industries 5087 Persons

13 Other Workers 67325 Persons

14 Literates population 279756 Persons

(Source: Census 2011)

3.12.2.1 Employment and livelihood

Economic vibrancy in area is shown by the type and nature of the occupation available in the

area. Of the total working population, the majority is the main workers i.e. they have steady

job more than six months per annum. It is due to the industrialization in the area. The job

opportunity is due to the development of Industrial and Service sectors. Table 3-28 shows

the classification of workers within the study area.

Table 3-28 Classification of workers within study area

Type of workers Main Marginal

1 Cultivators 23443 4236

2 Agri. Labourers 11076 7692

3 Household Industries 3422 1665

EIA Report

308 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4 Others 57283 10042

Total 95224 23635

(Source: Census 2011)

3.12.2.2 Educational infrastructure within study area

The district has good primary and secondary education infrastructure in urban and rural

areas. The people around the study area have well connected to educational infrastructures.

Table 3-29 shows the literates population.

EIA Report

309 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 3-29 Details of Literacy population in the study area

Sl.

No Name

Total

Population

Person

Literates

Population

Person

Literates

Population

Male

Literates

Population

Female

Illiterate

Persons

Illiterate

Male

Illiterate

Female

Jagatsinghapur

1 Abhayachandapur 28 13 7 6 15 6 9

2 Aganasi 0 0 0 0 0 0 0

3 Alligarh 506 437 249 188 69 20 49

4 Anantapur 405 319 170 149 86 30 56

5 Badabandha 889 752 407 345 137 53 84

6 Badagabapur 1193 967 530 437 226 93 133

7 Bagadia 2736 1985 1135 850 751 287 464

8 Bagoi 1970 1582 868 714 388 138 250

9 Baharatari 140 123 64 59 17 8 9

10 Baidigadi 227 167 88 79 60 27 33

11 Balarampur 5464 4438 2434 2004 1026 404 622

12 Baleipur 680 561 318 243 119 40 79

13 Balia 1681 1251 674 577 430 154 276

14 Balidia 1972 1506 809 697 466 180 286

15 Balitutha 1231 970 501 469 261 97 164

EIA Report

310 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.

No Name

Total

Population

Person

Literates

Population

Person

Literates

Population

Male

Literates

Population

Female

Illiterate

Persons

Illiterate

Male

Illiterate

Female

16 Bamadeipur 3161 2362 1282 1080 799 310 489

17 Banapatakandha 631 538 296 242 93 36 57

18 Barabelari 133 87 52 35 46 9 37

19 Baradakandha 0 0 0 0 0 0 0

20 Baulanga 1429 1148 618 530 281 120 161

21 Bayanalkandha 186 130 75 55 56 23 33

22 Bhitarasrichandanpur 295 231 126 105 64 24 40

23 Bhutumundai 3933 3001 1676 1325 932 359 573

24 Boitarakuda 0 0 0 0 0 0 0

25 Chadeigahanjharakati 0 0 0 0 0 0 0

26 Chakradharpur 851 720 383 337 131 49 82

27 Chakulia 474 410 219 191 64 26 38

28 Chatua 1577 1220 665 555 357 144 213

29 Chaukimatha 0 0 0 0 0 0 0

30 Chauliapalanda 30 22 10 12 8 3 5

31 Chhatarakandha 524 407 226 181 117 42 75

32 Dagan 813 597 299 298 216 89 127

EIA Report

311 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.

No Name

Total

Population

Person

Literates

Population

Person

Literates

Population

Male

Literates

Population

Female

Illiterate

Persons

Illiterate

Male

Illiterate

Female

33 Dhinkia 4141 3181 1750 1431 960 364 596

34 Gandakipur 5925 4349 2410 1939 1576 615 961

35 Garhkujang 2082 1564 817 747 518 214 304

36 Ghodamara 593 443 238 205 150 71 79

37 Gobinda Pur 2153 1805 922 883 348 138 210

38 Guamunda 795 624 341 283 171 72 99

39 Jaganathapur 385 313 179 134 72 30 42

40 Jamukana 680 499 259 240 181 71 110

41 Jhimani 2963 2166 1187 979 797 315 482

42 Kaduapalli-kandha 0 0 0 0 0 0 0

43 Kansaripatia 9 7 3 4 2 1 1

44 Karatutha 1142 919 472 447 223 90 133

45 Katakulla 890 702 390 312 188 74 114

46 Katha-ada 417 332 194 138 85 49 36

47 Keruadia-kandha 0 0 0 0 0 0 0

48 Kothi 2074 1644 909 735 430 154 276

49 Kujang 176065 138868 75374 63494 37197 14653 22544

EIA Report

312 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.

No Name

Total

Population

Person

Literates

Population

Person

Literates

Population

Male

Literates

Population

Female

Illiterate

Persons

Illiterate

Male

Illiterate

Female

50 Mahakaldia 0 0 0 0 0 0 0

51 Mangarajpur 3314 2668 1432 1236 646 242 404

52 Mirigidiakandha 0 0 0 0 0 0 0

53 Musadia 2852 2205 1334 871 647 291 356

54 Naladia Palanda 0 0 0 0 0 0 0

55 Narendrapur 1442 1173 640 533 269 110 159

56 Niharuni 314 221 118 103 93 42 51

57 Nimidhihi 1371 1053 575 478 318 129 189

58 Noliasahi 780 441 273 168 339 133 206

59 Nuagan 5185 4143 2262 1881 1042 412 630

60 Nuagarh 2565 2003 1056 947 562 226 336

61 Panigadiakandha 12 10 6 4 2 0 2

62 Paradipgarh (CT) 4790 3709 1998 1711 1081 427 654

63 Paradip(M) 68585 52575 30069 22506 16010 7231 8779

64 Parapada 360 288 162 126 72 27 45

65 Parianga 625 488 271 217 137 42 95

66 Patapur 752 560 326 234 192 75 117

EIA Report

313 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.

No Name

Total

Population

Person

Literates

Population

Person

Literates

Population

Male

Literates

Population

Female

Illiterate

Persons

Illiterate

Male

Illiterate

Female

67 Pitambarpur 680 547 297 250 133 46 87

68 Polanga 396 248 153 95 148 63 85

69 Potak 356 286 161 125 70 32 38

70 Purusotampur 560 430 230 200 130 46 84

71 Raghunathpur 2527 2158 1134 1024 369 132 237

72 Rajapur 669 465 240 225 204 58 146

73 Rangiagarh 2068 1615 879 736 453 193 260

74 Ranipada 439 367 199 168 72 28 44

75 Raulapada 185 144 79 65 41 19 22

76 Sahada 1115 836 426 410 279 96 183

77 Saharadia 1447 1025 577 448 422 162 260

78 Sandhapur 784 636 325 311 148 60 88

79 Santara 1683 1351 731 620 332 141 191

80 Siju 1531 1195 658 537 336 118 218

81 Srirampur 747 622 328 294 125 58 67

82 Sunadiakandha 509 328 185 143 181 60 121

83 Tentulia 1284 1095 594 501 189 67 122

EIA Report

314 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.

No Name

Total

Population

Person

Literates

Population

Person

Literates

Population

Male

Literates

Population

Female

Illiterate

Persons

Illiterate

Male

Illiterate

Female

84 Tentuliakhamar 1403 1008 565 443 395 168 227

85 Trilochanpur 2803 2135 1156 979 668 280 388

86 Uchhabanandpur 908 640 359 281 268 108 160

87 Udayabata 1953 1308 719 589 645 289 356

Kendrapara

88 Akhadasali 174 135 75 60 39 14 25

89 Chhanda 998 788 426 362 210 91 119

90 Gararomita 1953 1468 798 670 485 179 306

91 Kankadia 290 249 123 126 41 20 21

92 Khurusia 1068 867 476 391 201 74 127

93 Khurusiapat 456 331 187 144 125 43 82

94 Koratapanga 1076 839 466 373 237 84 153

95 Lunia 95 80 38 42 15 7 8

96 Nalitajori Pal 168 124 64 60 44 14 30

97 Nandanpur 0 0 0 0 0 0 0

98 Paunsiapal 0 0 0 0 0 0 0

99 Rajendra Nagar 158 108 63 45 50 16 34

EIA Report

315 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Sl.

No Name

Total

Population

Person

Literates

Population

Person

Literates

Population

Male

Literates

Population

Female

Illiterate

Persons

Illiterate

Male

Illiterate

Female

100 Subala 1067 830 465 365 237 100 137

101 Taradeipur 19 15 12 3 4 1 3

102 Tekarapanga 736 586 329 257 150 58 92

TOTAL 358725 279756 153665 126091 78969 31994 46975

(Source: Census 2011)

EIA Report

316 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.12.2.3 Dwelling within study area

Due to industrialization in nearby area and various Government Schemes, the standard of

dwelling place has improved.

3.12.2.4 Health facilities within the study area

The majority of people visit nearby Hospitals/health services provided by the Government.

The area has got good public health facilities at easily reachable distances. Even for any

minor ailments they contact medical facilities immediately as it is very accessible to them.

The local transport facilities and the communication facilities are the main reasons to get

immediate medical attention. The emergency medical service facility “108” is very familiar

and being used by the people in this area. The incidents of institutional delivery are high due

to awareness, education, economic development, proximity to health delivery system. The

Infant mortality rate and the maternal mortality rate have significantly reduced.

Table 3-30 Health facilities available in the study area

Sl.No Type Study area

1 Community health centre 3

2 Primary health centre 0

3 Primary health sub-centre 25

4 Maternity and Child Welfare Centre 2

5 TB hospital/Clinic 2

6 Hospital Allopathic 7

7 Hospital Alternative Medicine 2

8 Dispensary 4

9 Veterinary hospital 4

10 Mobile health clinic 1

11 Family Welfare Centre 4

12 Non Government Medical facilities

Out Patient 5

(Source: Census 2011)

EIA Report

317 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3.12.3 Observations

The public has mixed responses of industrialization in the study area. The people near to the

site are very apprehensive about the developments of refinery. The people of villages away

from the site are welcoming the industrialization as it provides job opportunities and good

infrastructure developments.

The total population of the district as per 2011 Census is 11,36,971. Of the total population,

5,77,865 are males and 5,59,106 are females. The population of the district is further

distributed as 10,20,991 living in rural areas and 1,15,980 living in urban areas. The total

number of households in the Jagatsinghapur district is 2,60,846.According to 2011 census

data, the literacy rate in the Jagatsinghapur district is 86.59 %.According to 2011 Census, the

sex ratio of the district is 968.The 0-6 age group sex ratio is 9.11 for the district.

In Jagatsinghapur district, 29.2% of the people do not have houses, 89.9% of people uses

firewood for cooking, 47.3% of people uses kerosene for lighting and 45.9% of people are

landless.

This project will provide better socio-economic benefits by providing direct and indirect

employment.

EIA Report

318 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CHAPTER 4

ANTICIPATED ENVIRONMENTAL

IMPACTS AND MITIGATION

MEASURES

EIA Report

319 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION

MEASURES4.1 Introduction

One of the important components in the process of environmental impact assessment is

identification of significant impacts as it leads to other elements such as quantification and

evaluation of impacts. Any change in environment whether adverse or beneficial, wholly or

partially, resulting from impacting activity is called Environmental Impact. Each individual

activity with respect to each environmental parameter will have its own impact potential.

Proposed project activities will be carried out in such a way so that potential adverse/negative

impacts are avoided, wherever possible. While for remaining impacts which are inevitable,

practicable mitigation measures will be recommended to minimize the adverse impacts.

The prediction of impacts helps to develop and implement mitigation measures/environment

management plan in such a way that the developmental activity will minimize the

deterioration of environmental quality.

4.2 Proposed Project Activities

The proposed project will have impacts on environment during the tenure of two phases; i.e.

construction phase and operation phase.

4.3 Construction Phase

Construction phase of the proposed project is temporary and will mainly involve the

following generic construction activities

Excavation

Formwork & concreting

Material handling and Transportation

Use of Tools and Potable power tools

Scaffolding

Crane Usage

Mechanical Equipment’s

Working in confined space

EIA Report

320 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.3.1 Impacts during Construction Phase

As the main impacts of the construction phase are envisaged in terms of air pollution only,

this natural mitigation would be significantly helpful in elimination of predicted impacts of

the phase. The overall impact of the pollution on the environment during construction phase

is localised in nature, reversible and is for a short period . However, the following principal

major impacts to the environment are considered for further planning of mitigation measures:

The use of automobiles and machinery during construction can deteriorate the air

quality and generate temporary emission.

The use of automobiles and machinery generates noise pollution from construction

activities.

The irregular working hours, & traffic, night-working, flood-lighting and

transportation damage the socioeconomic balance of surrounding region.

Effects may occur due to the accumulation of the contaminant in water resources &

soil due to uptake of construction material.

Short term heavy construction might cause increase in noise level

Effects on work place condition & human health due to the accidents during the

construction works.

Effects on the socio-economic activity due to direct impacts or indirect impacts on

socio-economic activities.

4.3.2 Mitigation Measures for Construction Phase

The entire construction activities will be confined with the designated area inside the

existing premises.

The small amount of unused construction material shall be stored in proper area to

utilise further in construction activities and surplus excavated material shall be

disposed of in suitable pre-identified areas.

Construction material shall be stored at adequate distance from the water storage in

order to prevent any chances of accidental leakage or spillage which could pollute the

water storage

Wherever required impervious lining shall be provided to the storage premises to

avoid accidental mixing or mixing due to fugitive losses.

To reduce the dust generation on site wherever & whenever required water shall be

EIA Report

321 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

sprinkled on ground or stock pile of excavated soil.

Equipments / machineries shall be used efficiently and shall be kept shut in order to

reduce air emission, noise pollution and consumption of energy resource

Emission from the equipments/machineries shall be monitored on regular basis and

possible implementation shall be provided on site

Transport vehicles shall be monitored & maintained regularly to control the emission

quality and fuel consumption

Provision of necessary PPEs like face mask & eye-glasses to employees /labours

engaged in construction activities.

The machineries/equipment used on site shall be maintained so they do work with

optimum efficiency generating less noise pollution

Operation of machineries/equipment causing high noise level shall be stopped during

the night time and all such operations shall be planned for day time only.

Transportation activities shall not be conducted during the night (other than in case of

emergency) to avoid high noise level in nearby villages/locality.

4.3.3 Land environment

a) Impacts

The proposed process units under the PX PTA project will be implemented within M/s IOCL,

PDR premises. The proposed project will be done in land area, which is identified as

appropriate location based on environmental and engineering requirements. The activities

carried out during the construction phase will involve a change in the land use from vacant

industrial land to a built up industrial land, which will pose the following impacts on the land

environment.

1. Compaction of soil and a change in the soil structure due to the use of heavy

construction vehicles and machineries.

2. Removal of soil from the site.

3. Mixing of the topsoil and subsoil.

4. Dispersion of dust.

Transportation of construction material (quarry material, cement &steel, paint, bricks etc)

during construction phase of the project results in use of public infrastructure like roads,

railways, drainage, water and power supply which in turn results in extra burden.

EIA Report

322 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

During the construction phase of the project there will be short term employment generation

in the form of skilled and semiskilled labours. This could be for a period of maximum 2 to 3

years but the daily wage unskilled labours employed locally. Also majority of the works will

be sub-contracted. There could be several impacts due to the location of construction camp in

the area where in local area will receive people from most part of the country.

b) Mitigation Measures

1. Employing techniques such as restricting access during wet conditions, using

protective boarding and low ground pressure machineries to minimize compaction of

soil.

2. The removed soil will be properly stored for subsequent reinstatement.

3. Reuse of excess excavated material for road development, green belt development and

landscaping.

4. A well designed closed depository for storage of construction materials to prevent

land/soil pollution.

5. Effective stabilization of altered landforms to minimize soil erosion and the potential

for water pollution (e.g. Vegetation).

6. Reuse of construction wastes such as sand, brick, gravel, cement for developing

internal road and project structures.

7. Trucks with construction material susceptible for fugitive suspension will be covered

with tarpaulin covers during transport of construction materials

8. Transportation management will be adopted for movement of vehicles transporting

construction materials and traffic will be regulated.

9. Vehicles deployed will confirm to emission norms (air/noise) of CPCB and have

validPollution Under Control(PUC) certificates

10. Very old vehicles (more than 20 years) will not be allowed at site

11. Trucks will comply with standards for exhaust emissions and noise levels.

12. To avoid/minimise impact/strain on the existing infrastructure, the worker camps will

be self-sufficient and would not rely on any local resource. This would help to avoid

any conflict with the local population. To mitigate impacts from health hazards,

sanitation facilities will be provided

EIA Report

323 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.3.4 Air environment

In order to predict the impact of constructional and operational activities on the ambient air

quality, the data on emission, micrometeorology and from Indian meteorological department

(IMD)were collected. All these data will be used to predict ground level concentration of

(GLCs) of SO2, NOX and PM10 for different temporal variations.

In the construction phase, activities like site clearance, site leveling, movements of workers

and material, construction of road, transportation activities will generate dust, gaseous

pollutants and particulate matter and affect the air quality. Other impacts include -

1. Site Preparation-fencing, boundary and clearing of site will cause disturbance to the

surroundings.

2. Excavation, backfilling and leveling.

3. Hauling and dumping of earth materials and construction spoils.

4. Foundation works can cause dust generation which will decrease the air quality and it

can impact the labors working.

5. Fabrication, erection of steel structures such as tanks, pipelines and sheds.

6. Construction of internal roads drains and water supply.

7. Cleaning and landscaping.

8. Emission from Construction DG & Construction Equipment’s.

a) Mitigation Measures

1. Barricading the construction area and minimizing exposed areas to reduce dust

generation.

2. Areas generating dust during dry weather will be sprayed with water.

3. Creation of vegetation screens to act as a barrier to dust.

4. Appropriate enclosed areas for storage of construction materials.

5. Facilitating the workers with the required personal protective equipment’s.

6. Efficient usage and maintenance of equipment’s/machineries to lower air emissions,

noise pollution and consumption of energy resource.

7. Exhaust vent of DG set will be provided with adequate stack height to ensure quick

dispersal of gaseous emissions.

8. Periodic monitoring and maintenance of transport vehicles to check on the quality of

emission to be within permissible limits and consumption of fuel.

EIA Report

324 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

9. Regular inspection of construction site to ensure timely removal and disposal of

construction debris to the dumping sites or for recycle/reuse.

4.3.5 Water environment

a) Impacts

1. Contamination of watercourses by leakage from fuel and materials storage areas.

2. Oil and suspended solids in run-off from vehicles and access roads.

3. Use of heavy machineries and vehicles causes compaction of topsoil due to which a

change in the surface water drainage pattern may occur.

4. Generation of sewage / process effluent and blow down.

b) Mitigation measures

1. The water demand during the construction phase will be met from the existing

Refinery water source(Mahanadi River)

2. Storehouse will be located at a distance away from the water storage area to prevent

accidental release or spillage.

3. Proper management of rain water run-off during monsoon and creating bunds to

utilize the rain water for construction purpose.

4. An appropriate water management system will be implemented.

4.3.6 Noise environment

a) Impacts

During construction phase, the noise will mostly be produced because of building activities

and machineries used for carrying out construction. Construction activities mainly involve

diesel generators, laying of foundation, erection of superstructure, clearing of obstruction and

trees if any from the proposed area. Activities such as construction of labor camps, onsite

office, pneumatic hammers, compressors, concrete mixers, construction material plants

however, do not cause significant noise pollution. But if the work continuous for longer

duration, it can affect the health of local people and workers involved in the project work.

b) Mitigation Measures

1. Barricading the construction site.

EIA Report

325 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

2. The green belt will help in reducing the noise nuisance.

3. Selection of equipment’s of high quality.

4. Proper planning and organizing of construction activities which will help in avoiding loud

verbal exchanges between the intervening parties.

5. Transportation activities will be carried out only during the day and only in case of

emergency, the transportation activities will be permitted in night time.

6. The vehicles used for construction activities and transportation of materials will be

provided with the horn of low noise level as recommended by RTO/ concerned

authorities.

7. Minimization of operation time of noisy equipment and operation of

machineries/equipment that generate high levels of noise only during day time.

8. Inadequate use of plant and equipment, namely, running on full power when the work

does not necessitate it will be avoided.

9. Personal protective equipment’s, education and public awareness and exposure control

through rotation of work will be provided to the workers engaged in construction

activities in the area generating high levels of noise.

4.3.7 Waste generation

The source of waste are metal pieces, cardboards, wooden scrap, sand gravels etc., generation

of chemical waste by general site practices (e.g. vehicle and plant maintenance/servicing),

municipal waste generated by site workers.

a) Mitigation measures

1. Recycling/reusing/recovering materials where possible and thereby neglecting or

reducing the disposal requirements.

2. Separation of construction material for reuses either to be used on onsite filling or can

be used as public fill.

3. Training the staff in waste minimizing practices.

4. Chemical waste should be stored in a locked area so as to avoid leaching of harmful

chemicals in the soil or nearby water bodies (If any).

EIA Report

326 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.3.8 Ecology

Except for the removal of weeds, the ecological status of the site will be well maintained by

conserving/ developing the greenbelt at the site.

4.3.9 Social environment

A socio-economic study was undertaken with the help of secondary sources in assessing

aspects, which are dealing with social and cultural conditions, and economic status in the

study area. The study provides information such as demographic structure, population

dynamics, infrastructure resources, and the status of human health and economic attributes

like employment, per-capita income, agriculture, trade, and industrial development in the

study area. There will be temporary employment for manpower required during construction

phase available from local communities. Overall, socioeconomic effect of construction phase

will be positive due to direct and indirect employment opportunities for the local population

4.4 Operation Phase

From an Environmental perspective, this phase is of paramount significance due to its

potential to invoke long-term impacts. The adverse effects that are likely to occur during this

operational phase of the project are Air pollution (gaseous Emissions), Effluent generation,

Noise Generation, Solid waste Generation etc.

4.4.1 Impacts during Operational Phase

Because of its potential to create long-term impacts, this phase is very important from the

environmental impact point of view. The basic impacts like gaseous emissions, water

consumption/ pollution and solid waste will have the potential to adversely affect air, water

and land / soil in the vicinity of the project site.

This phase will broadly include the following direct and indirect activities / actions:

Storage and transportation of raw materials and finished products.

Gaseous emissions

Effluent Generation, treatment and disposal

Noise Generation

Solid waste generation

EIA Report

327 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5 Air Environment

Base line data reveals that the ambient air quality has been monitored at 8 locations for 14

parameters as per NAAQS/CPCB guidelines within the study area. The average baseline

levels of PM10 (55.35 – 80.53µg/m³), PM2.5 (27.72 – 38.16µg/m³), SO2 (8.63 – 13.21µg/m³),

NO2(16.15 – 25.30µg/m³).

The nearest CPCB AAQ monitoring station is PPL Guest House in which the annual average

for the year 2018: PM10 (113 µg/m³), PM2.5 (37 µg/m³), SO2(19 µg/m³), NO2(11 µg/m³).

Source:

https://cpcb.nic.in/displaypdf.php?id=bWFudWFsLW1vbml0b3JpbmcvTG9jYXRpb25fZGF

0YV8yMDE4LnBkZg==

All the parameters are well within the National Ambient Air Quality Standards for Industrial,

Commercial and Residential areas at all monitoring locations during the study period from

March 2019 - May 2019. Stack emission of PM, SOx & NOx are due to process units, Flare

and DG. Adequate measures will be taken to control Air Pollution.

4.5.1 Meteorological data

The meteorological data for a month, i.e. from 01/03/2019 to 31/05/2019 was considered for

the study. Data included for AERMET were daily wind speed, wind direction, temperature,

relative humidity, air pressure, precipitation, and solar radiation recorded during the period.

AERMET reformats meteorological data so that it can be used as input for AERMOD model.

The wind rose for the study period is given as Figure 4-1

EIA Report

328 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-1 Wind rose diagram of Meteorological data considered for Modelling (March to May 2019)

4.5.2 AERMET Process

For the 3 phase AERMET processing of the meteorological data, specifications of the land

use in the area are required to determine the terrain roughness for modelling. The land use

was characterized for in and around the site. The surface characteristics for the site and

surroundings were selected and used to calculate the Albedo, Bowen ratio and surface

roughness parameters.

EIA Report

329 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.3 AERMOD Process

AERMOD Software Version 8.0.5 was used for air dispersion modelling and is applicable to

a wide range of buoyant or neutrally buoyant emissions up to a range of 50 km. In addition to

more straight forward cases, AERMOD is also suitable for complex terrain and urban

dispersion scenarios.

AERMOD is a steady-state plume model. In the stable boundary layer (SBL), it assumes the

concentration distribution to be Gaussian in both the vertical and horizontal. In the convective

boundary layer (CBL), the horizontal distribution is also assumed to be Gaussian, but the

vertical distribution is described with a bi-Gaussian probability density function (pdf). This

behavior of the concentration distributions in the CBL was demonstrated by Willis and

Deardorff (1981) and Briggs (1993). Additionally, in the CBL, AERMOD treats “plume

lofting,” whereby a portion of plume mass, released from a buoyant source, rises to and

remains near the top of the boundary layer before becoming mixed into the CBL. AERMOD

also tracks any plume mass that penetrates into the elevated stable layer, and then allows it to

re-enter the boundary layer when and if appropriate. For sources in both the CBL and the

SBL AERMOD treats the enhancement of lateral dispersion resulting from plume meander.

The emissions from proposed stacks are estimated and used for the air dispersion modeling as

shown in Table 4-2.

Maximum incremental values for PM, SO2, NOx and CO have been represented as pictorial

concentration contours and as tabular concentration values in following sections

EIA Report

330 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.4 Emissions

Table 4-1 Existing Stack Emission details

S.No Stack details Fuel Type

used

Stack Details Emission per stack (g/s)

Height (m) Temp

(°C) Dia. (m)

Exit

Velocity

(m/s)

Flue gas

Flow Rate

(Nm3/hr)

PM SO2 NOx CO

1. DHDT Gas Fired 60 167 4.2 1.22 31128 0.03 0.13 1.04 0.05

2. Utility Boiler - 3 Gas + Oil

Fired 73.5 180 3 14.5 285793 0.32 0.66 7.00 0.83

3. Utility Boiler - 4 Gas + Oil

Fired 73.5 180 3 14.5 285793 0.33 1.53 7.21 0.81

4.Gas Turbine – 1-

HRSG-1 Naptha 70.5 170 6 13.5 1062841 0.76 12.64 47.59 2.95

5.HDT Reactor Feed

Heater

Gas + Oil

Fired 60 195 0.997 3.2 15834 0.02 0.10 0.12 0.03

6.Vacuum Charge

Heater of AVU

Gas + Oil

Fired 55 150 3.8 7 112108 0.07 5.57 4.21 0.82

7. FCC Regenerator NA 65 226 3.5 15 320000 2.69 75.56 0.78 7.52

8. Reformer of HGU Naphtha 46.7 150 4 7.12 175222 0.004 2.02 4.60 1.60

9.Fresh Feed

Preheater of FCC

Gas + Oil

Fired 62 189 2.6 10 61013 0.05 4.63 0.49 0.67

10. CCR Gas Fired 103 160 4.39 7 523959 0.06 1.43 3.50 5.20

11.

MHC 1st Train

Reactor Feed

Heater of VGO-

HDT

Gas Fired 60 194 1.456 5.1 64717 0.07 0.36 0.37 0.32

12.

Atmospheric

Distillation Heater

of VGO-HDT

Gas Fired 60 147 2.35 6.5 15834 0.01 0.01 0.15 0.03

EIA Report

331 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Stack details Fuel Type

used

Stack Details Emission per stack (g/s)

Height (m) Temp

(°C) Dia. (m)

Exit

Velocity

(m/s)

Flue gas

Flow Rate

(Nm3/hr)

PM SO2 NOx CO

13.Gas Turbine – 2-

HRSG-2 Naptha 70.5 170 6 13.5 1062841 0.84 9.03 42.68 5.47

14.Gas Turbine – 3-

HRSG-3 Naptha 70.5 170 6 13.5 1062841 0.87 4.28 55.38 3.65

15.Coker Heater -

Stack-1

Gas + Oil

Fired 60 190 2.9 6.2 78412 0.04 0.34 0.87 0.10

16. AVU-CDU Gas Fired 64 150 4.79 7 201847 0.10 7.06 3.81 1.34

17.Coker Heater -

Stack-2

Gas + Oil

Fired 60 190 2.9 6.2 78412 0.16 3.52 1.54 0.40

18. SRU Acid gas 71 316 4.5 5 106499 0.02 12.64 1.07 2.38

19.Charge Heater of

NHDT Gas Fired 70 170 2.8 7 48778 0.02 0.09 0.62 0.15

20. Utility Boiler - 1 Gas + Oil

Fired 73.5 180 3 14.5 285793 0.42 11.09 10.51 1.82

21. Utility Boiler - 2 Gas + Oil

Fired 73.5 180 3 14.5 285793 0.29 17.78 5.29 2.20

Total (g/s) 7.18 170.48 198.80 38.35

Note: Fuel Gas (FG) is the major fuel consumption in heaters. Only shortfall is made up with fuel Oil (FO) in dual fired heaters. In Gas Turbine, Naptha is fired and exhaust gas is utilized for steam up.

EIA Report

332 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.4.1 Point Source Emission (Proposed Stack Emission)

Figure 4-2 Project layout with proposed stack coordinates

EIA Report

333 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-3 Google earth demarcation of proposed stack with coordinates

EIA Report

334 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 4-2Proposed Stack Emission details

S.No

Stack details

Stack Coordinates Fuel Rate

(Natural Gas) (kg/hr)

Flue gas

Flow Rate

(Nm3/hr)

Stack Details Emission per stack (g/s)

N E Heig

ht (m)

Max.

Temp

(°C)

Dia. (m)

Exit Veloc

ity (m/s)

PM SO2 NOx CO CO2

1.Tatory

Furnace 20°15'50.65" 86°35'49.49" 433 4679 43.5 180 0.97 1.8 -

0.0257

0.1688 - 451.53

2.ISOMAR Furnace

20°15'47.79" 86°35'49.57" 2747 29708 60.2 180 2.25 2.1 - 0.083

3 0.6052 -

1402.36

3. XFU 1 20°15'45.09" 86°35'49.64" 7594 82116 81.1 180 3.708 2.1 - 0.559

7 2.7983 -

9553.61

4. XFU 2 20°15'42.46" 86°35'49.51" 4840 52339 61.73 180 4.192 1.1 - 0.439

6 2.1955 -

7495.03

5.

Utility Boiler – 5 (Standby)

*

20°15'17.16" 86°35'32.62" 19973 325061 73.5 180 3 12.8 0.452

8 4.513

9 22.575

1.6931

-

6. Flare 20°15'35.86" 86°36'11.85" 15 162 140 331 1.5 0.025 0.000

2 0.002

3 0.0113

0.0008

-

Total (g/s) 0.453 5.624

5 28.354

1 1.693

9

18902.53

Note:

1. The data is obtained from Section 7.1.2.1 of Detailed Feasibility Report prepared by Toyo Engineering India Pvt. Ltd. and integration of

flow rate of fuel.

2. Utility Boiler -5 is standby and will be in intermittent operation only for the PTA plant start up.

EIA Report

335 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-4 Predicted 24-Hrs’ GLC’s of PM within 10 km Radius of the Study Area on

stack emission

Table 4-3 Estimated Top 10 Highest Concentrations of PM Obtained Through

Modeling on stack emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~km)

Direction from Centre

of Project SiteE N

1. 457316 2240086 0.10691 1 W

2. 457316 2241086 0.0997 1.41 NW

3. 457316 2239086 0.062 1.41 SW

4. 456316 2240086 0.06083 2 W

5. 457316 2242086 0.05969 2.24 NNW

6. 456316 2239086 0.05573 2.24 WSW

7. 457316 2243086 0.04934 3.16 NNW

8. 456316 2241086 0.04563 2.24 WNW

9. 455316 2240086 0.04336 3 W

10. 459316 2241086 0.04236 1.41 NE

EIA Report

336 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-5 Predicted 24-Hrs’ GLC’s of SO2within 10 km Radius of the Study Area on

stack emission

Table 4-4 Estimated Top 10 Highest Concentrations of Sulphur Dioxide obtained

through modeling on stack emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~km)

Direction from Centre

of Project SiteE N

1. 457316 2240086 1.16123 1 W

2. 457316 2241086 1.02893 1.41 NW

3. 456316 2240086 0.8264 2 W

4. 457316 2242086 0.74074 2.24 NNW

5. 457316 2239086 0.697 1.41 SW

6. 458316 2241086 0.66865 1 N

7. 456316 2239086 0.65152 2.24 WSW

8. 457316 2243086 0.62335 3.16 NNW

9. 458316 2242086 0.57572 2 N

10. 460316 2242086 0.5419 2.82 NE

EIA Report

337 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-6 Predicted 24-Hrs’ GLC’s of NOx within 10 km Radius of the Study Area on

stack emission

Table 4-5 Estimated Top 10 Highest Concentrations of oxide of Nitrogen obtained

through modeling on stack emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~km)

Direction from Centre

of Project SiteE N

1. 457316 2240086 5.88927 1 W

2. 457316 2241086 5.15371 1.41 NW

3. 456316 2240086 4.18841 2 W

4. 457316 2242086 3.73953 2.24 NNW

5. 457316 2239086 3.50805 1.41 SW

6. 458316 2241086 3.43833 1 N

7. 456316 2239086 3.33455 2.24 WSW

8. 457316 2243086 3.14953 3.16 NNW

9. 458316 2242086 2.95101 2 N

10. 460316 2242086 2.74009 2.82 NE

EIA Report

338 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-7 Predicted 1-Hr GLC’s of CO within 10 km Radius of the Study Area on

stack emission

Table 4-6 Estimated Top 10 Highest Concentrations of Carbon Monoxide obtained

through modeling on stack emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~km)

Direction from Centre

of Project SiteE N

1. 457316 2240086 1.73122 1 W

2. 457316 2239086 1.61135 1.41 SW

3. 458316 2240086 1.54914 Project Site Project Site

4. 458316 2239086 1.49613 1 S

5. 459316 2238086 1.42198 2.24 SSE

6. 456316 2240086 1.37225 2 W

7. 456316 2239086 1.34013 2.24 WSW

8. 457316 2241086 1.26342 1.41 NW

9. 458316 2238086 1.23531 2 S

10. 459316 2237086 1.19594 3.16 SSE

EIA Report

339 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-8 Predicted 24-Hrs’ GLC’s of CO2 within 10 km Radius of the Study Area on

stack emission

Table 4-7 Estimated Top 10 Highest Concentrations of Carbon Dioxide obtained

through modeling on stack emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~km)

Direction from Centre

of Project SiteE N

1. 457316 2241086 8099.821 1.41 NW

2. 457316 2240086 6593.569 1 W

3. 458316 2241086 5727.344 1 N

4. 458316 2242086 5090.748 2 N

5. 458316 2240086 4706.845 Project site Project site

6. 456316 2239086 4552.406 2.24 WSW

7. 457316 2242086 3899.017 2.24 NNW

8. 456316 2240086 3816.203 2 W

9. 459316 2242086 3596.204 2.24 NNE

10. 456316 2241086 3507.212 2.24 WNW

EIA Report

340 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.4.2 Summary on Stack Emission

Maximum pollutant concentrations of PM, SO2 ,NOx and CO2observed due to proposed

expansion for an 24hr-average period have been studied and CO observed due to proposed

expansion for an 1hr-average period have been studied. The total increase in concentrations

above baseline status to estimate the percentage increase and summarized in Error! Reference

source not found.Error! Not a valid bookmark self-reference..

Table 4-8 Total Maximum GLCs from the Point Source (Stack Emissions)

Pollutant

Max. Base line

Conc. (µg/m3)

Max Base line

location

Estimated Incremental

Conc. (µg/m3)

Total Conc. (µg/m3)

NAAQ standard (µg/m3)

% increase

PM 95.7 Paradwip

(Coast Guard)- A5

0.10 95.8 100 0.10 SO2 15.7 1.16 16.86 80 7.39 NOx 30.06 5.88 35.94 80 19.56 CO 50* 1.73 51.73 4000 3.46 CO2 - 8099.82 8099.82 - -

Note:

1. CO2 parameter is not available for NAAQ standards

3.** Max. Base line values were observed at Paradwip (Coast guard) at a distance ~4.91km,

E from the project boundary

2.*Since the maximum base line concentration of CO is below detectable limit, the detectable limit of CO 50 µg/m3 is considered

EIA Report

341 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.4.3 Line source emission (Transportation)

Figure 4-9 Project layout with PTA truck Route

PTA Truck route R1 to R3

Start : (20°16'4.09"N, 86°35'49.05"E)

End: (20°16'30.1"N, 86°36'08.2"E)

EIA Report

342 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-10 Project layout with Toluene truck Route

Toluene Truck route R1 to R3

Start :(20°15'22.5"N, 86°36'27.5"E)

End : (20°16'30.1"N, 86°36'08.2"E)

EIA Report

343 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-11 Google earth demarcation of proposed truck route with coordinates

EIA Report

344 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 4-9 Proposed Transportation Emission details

S.no

Vehicle type

No.of.Vehicle per day (Based on maximum

operation capacity) based on BS-VI type of vehicles

Emission (g/s)

PM NOX CO

1 4W 5 0.000004 0.000104 0.000617

2 HW 1-PTA

164 0.000137 0.006287 0.054667

3 HW 2-

Toluene 7 0.000010 0.000447 0.003889

Total (g/s) 0.000150 0.006838 0.059172

Note:

PTA product truck Coordinate of Starting Point 20°16'4.09"N, 86°35'49.05"E

Coordinate of Ending Point 20°16'30.1"N, 86°36'08.2"E

Toluene product truck Coordinate of Starting Point 20°15'22.5"N, 86°36'27.5"E

Coordinate of Ending Point 20°16'30.1"N, 86°36'08.2"E

EIA Report

345 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-12 Predicted 24-Hrs’ GLC’s of PM within 10 km Radius of the Study Area on

Transportation emission

Table 4-10 Estimated Top 10 Highest Concentrations of Particulate Matter obtained

through modeling on Transportation emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~km)

Direction from Centre

of Project SiteE N

1. 458316 2242086 0.02742 2 N

2. 458316 2241086 0.0076 1 N

3. 457316 2243086 0.00667 3.16 NNW

4. 459316 2241086 0.00647 1.41 NE

5. 458316 2243086 0.00644 3 N

6. 458316 2240086 0.00576 Project site Project site

7. 459316 2243086 0.00537 3.16 NNE

8. 457316 2244086 0.00516 4.12 NNW

9. 459316 2242086 0.00478 2.24 NNE

10. 459316 2238086 0.00471 2.24 SSE

EIA Report

346 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-13 Predicted 24-Hrs’ GLC’s of NOx within 10 km Radius of the Study Area on

Transportation emission

Table 4-11 Estimated Top 10 Highest Concentrations of oxide of Nitrogen obtained

through modeling on Transportation emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project Site

E N

1. 458316 2242086 1.25863 2 N

2. 458316 2241086 0.34914 1 N

3. 457316 2243086 0.30618 3.16 NNW

4. 458316 2243086 0.29596 3 N

5. 459316 2241086 0.29386 1.41 NE

6. 458316 2240086 0.26452 Project site Project site

7. 459316 2243086 0.24575 3.16 NNE

8. 457316 2244086 0.23699 4.12 NNW

9. 459316 2238086 0.21644 2.24 SSE

10. 459316 2242086 0.21146 2.24 NNE

EIA Report

347 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-14 Predicted 1-Hr GLC’s of CO within 10 km Radius of the Study Area on

Transportation emission

Table 4-12 Estimated Top 10 Highest Concentrations of Carbon Monoxide obtained

through modeling on Transportation emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project Site

E N

1. 458316 2242086 78.73534 2 N

2. 459316 2242086 32.5808 2.24 NNE

3. 459316 2244086 31.26969 4.12 NNE

4. 458316 2240086 30.98063 Project site Project site

5. 458316 2241086 30.02529 1 N

6. 458316 2243086 29.31596 3 N

7. 460316 2243086 26.72553 3.60 NNE

8. 458316 2239086 26.11 1 S

9. 460316 2245086 22.94802 5.38 NNE

10. 459316 2241086 21.16236 1.41 NE

EIA Report

348 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.4.4 Summary on Transportation Emission

Maximum pollutant concentrations of PM and NOx observed due to proposed expansion for

an 24hr-average period have been studied and CO observed due to proposed expansion for an

1hr-average period have been studied. The total increase in concentrations above baseline

status to estimate the percentage increase and summarized in Error! Reference source not

found.Table 4-13.

Table 4-13 Total Maximum GLCs from the transportation Emissions

Pollutant Max. Base line Conc.

(µg/m3)

Estimated Incremental Conc.

(µg/m3)

Total Conc. (µg/m3)

NAAQ standard (µg/m3)

% increase

PM 95.7 0.02 95.72 100 0.02

NOx 30.06 1.25 31.31 80 4.16

CO 50 78.73 128.73 4000 157.46

Note: 1. * Max. Base line values were observed at Paradwip (Coast guard) at a distance ~4.91km, E from the project boundary

EIA Report

349 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.4.5 Cummulative Emission

Table 4-14 Proposed Cumulative Emission details (Point source emission and Line source emission)

S.No

Stack details

Stack Coordinates

Fuel Rate

(Natural Gas)

(kg/hr)

Flue gas Flow Rate (Nm3/hr)

Stack Details Emission per stack (g/s)

N E Height

(m) Temp (°C)

Dia. (m)

Exit Velocity

(m/s) PM SO2 NOx CO CO2

1. Tatory Furnace 20°15'50.65"

86°35'49.49"

433 4679 43.5 180 0.97 1.8 - 0.0257 0.1688 - 451.53

2. ISOMAR Furnace

20°15'47.79"

86°35'49.57"

2747 29708 60.2 180 2.25 2.1 - 0.0833 0.6052 - 1402.3

6

3. XFU 1 20°15'45.09"

86°35'49.64"

7594 82116 81.1 180 3.708 2.1 - 0.5597 2.7983 - 9553.6

1

4. XFU 2 20°15'42.46"

86°35'49.51"

4840 52339 61.73 180 4.192 1.1 - 0.4396 2.1955 - 7495.0

3

5. Utility Boiler – 5

(Standby)* 20°15'17.16"

86°35'32.62"

19973 325061 73.5 180 3 12.8 0.4528 4.5139 22.575 1.6931 -

6. Flare 20°15'35.86"

86°36'11.85"

15 162 140 331 1.5 0.025 0.0002 0.0023 0.0113 0.0008 -

S.No

Vehicle type No.of.Vehicle per day (Based on maximum operation capacity) PM SO2 Nox CO CO2

1 4W 5 0.00000

4 - 0.000104

0.000617

-

2 HW 1-PTA 164 0.00013

7 - 0.006287

0.054667

-

3 HW 2-Toluene 7 0.00001

0 - 0.000447

0.003889

-

Total(g/s) 0.4532 5.6245 28.3609 1.7531 18902.

530

EIA Report

350 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-15 Predicted 24-Hrs’ GLC’s of PM within 10 km Radius of the Study Area on

Cummulative emission

Table 4-15 Estimated Top 10 Highest Concentrations of Particulate Matter obtained

through modeling on Cummulative emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from

Centre of

Project SIte

(~Km)

Direction

from Centre

of Project

Site E N

1. 457316 2240086 0.10691 1 W

2. 457316 2241086 0.09996 1.41 NW

3. 457316 2239086 0.06201 1.41 SW

4. 456316 2240086 0.06084 2 W

5. 457316 2242086 0.05972 2.24 NNW

6. 456316 2239086 0.05578 2.24 WSW

7. 457316 2243086 0.04956 3.16 NNW

8. 456316 2241086 0.0459 2.24 WNW

9. 458316 2242086 0.04455 2 N

10. 455316 2240086 0.04345 3 W

EIA Report

351 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-16 Predicted 24-Hrs’ GLC’s of SO2 within 10 km Radius of the Study Area on

Cummulative emission

Table 4-16 Estimated Top 10 Highest Concentrations of Sulphur Dioxide obtained

through modeling on Cummulative emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project Site

E N

1. 457316 2240086 1.16123 1 W

2. 457316 2241086 1.02893 1.41 NW

3. 456316 2240086 0.8264 2 W

4. 457316 2242086 0.74074 2.24 NNW

5. 457316 2239086 0.697 1.41 SW

6. 458316 2241086 0.66865 1 N

7. 456316 2239086 0.65152 2.24 WSW

8. 457316 2243086 0.62335 3.16 NNW

9. 458316 2242086 0.57572 2 N

10. 460316 2242086 0.5419 2.82 NE

EIA Report

352 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-17 Predicted 24-Hrs’ GLC’s of NOx within 10 km Radius of the Study Area on

Cummulative emission

Table 4-17 Estimated Top 10 Highest Concentrations of oxide of Nitrogen obtained

through modeling on Cummulative emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project Site

E N

1. 457316 2240086 5.89096 1 W

2. 457316 2241086 5.16561 1.41 NW

3. 456316 2240086 4.18911 2 W

4. 457316 2242086 3.74015 2.24 NNW

5. 457316 2239086 3.5088 1.41 SW

6. 458316 2241086 3.43833 1 N

7. 456316 2239086 3.33595 2.24 WSW

8. 457316 2243086 3.15945 3.16 NNW

9. 458316 2242086 3.14134 2 N

10. 460316 2242086 2.74057 2.82 NE

EIA Report

353 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-18 Predicted 1-Hr GLC’s of CO within 10 km Radius of the Study Area on

Cummulative emission

Table 4-18 Estimated Top 10 Highest Concentrations of Carbon Monoxide obtained

through modeling on Cummulative emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 458316 2242086 78.6934 2 N

2. 459316 2242086 32.28149 2.24 NNE

3. 459316 2244086 31.28345 4.12 NNE

4. 458316 2240086 30.96416 Project site Project site

5. 458316 2241086 30.00931 1 N

6. 458316 2243086 29.30035 3 N

7. 460316 2243086 26.75492 3.60 NNE

8. 458316 2239086 26.09742 1 S

9. 460316 2245086 22.96254 5.38 NNE

10. 459316 2241086 21.19104 1.41 NE

EIA Report

354 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-19 Predicted 24-Hrs’ GLC’s of CO2 within 10 km Radius of the Study Area on

Cummulative emission

Table 4-19 Estimated Top 10 Highest Concentrations of Carbon Dioxide obtained

through modeling on Cummulative emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 457316 2241086 8099.821 1.41 NW

2. 457316 2240086 6593.569 1 W

3. 458316 2241086 5727.344 1 N

4. 458316 2242086 5090.748 2 N

5. 458316 2240086 4706.845 Project site Project site

6. 456316 2239086 4552.406 2.24 WSW

7. 457316 2242086 3899.017 2.24 NNW

8. 456316 2240086 3816.203 2 W

9. 459316 2242086 3596.204 2.24 NNE

10. 456316 2241086 3507.212 2.24 WNW

EIA Report

355 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.4.6 Summary on Cummulative Emission

Maximum pollutant concentrations of PM, SO2, NOx and CO2 observed due to proposed

expansion for an 24hr-average period have been studied and CO observed due to proposed

expansion for an 1hr-average period have been studied. The total increase in concentrations

above baseline status to estimate the percentage increase and summarized in Table 4-20.

Table 4-20 Total Maximum GLCs from the Cummulative Emissions (point source

emission & line source emission)

Pollutant

Max. Base line

Conc. (µg/m3)

Max Base line location Estimated

Incremental Conc. (µg/m3)

Total Conc. (µg/m3)

NAAQ standard (µg/m3)

% increase

PM 95.7 Paradwip (Coast

Guard)- A5

0.10 95.8 100 0.10SO2 15.7 1.16 16.86 80 7.39NOx 30.06 5.89 35.95 80 19.59CO 50* 78.69 128.69 4000 157.38 CO2 - 8099.82 8099.82 - -

Note:

1. CO2 parameter is not available for NAAQ standards

3.** Max. Base line values were observed at Paradwip (Coast guard) at a distance ~4.91km,

E from the project boundary

The incremental concentrations of PM, SO2, NOx and CO are observed to be 0.10%, 7.39%

19.59% and 157.38% respectively. The total pollutant concentrations of PM, SO2, NOx and

CO are 95.7 µg/m3, 16.86 µg/m3, 35.95 µg/m3 and 128.69 µg/m3 , which is observed to be

within NAAQ standards.

2.*Since the maximum base line concentration of CO is below detectable limit, the detectable limit of CO 50 µg/m3 is considered

EIA Report

356 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.4.7 Other Emission-Storage Tank vent & PX-Process vent emmission

Figure 4-20 Project layout with proposed storage tank vent & PX-process vent coordinates

EIA Report

357 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-21 Google earth demarcation of proposed storage tank vent & PX-process vent coordinates

EIA Report

358 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 4-21 Proposed Storage tank vents and PX-process vent Emission details

S.No

Storage Tank Vent details Stack Coordinates Vent Details Emission per vent (g/s)

N E Height

(m) Temp (°C)

Dia. (m)

Exit Velocity (m/s)

VOC Benze

ne Tolue

ne CO2

1 Toluene day tank- 045-TK-

001A 20°15'49.

6" 86°36'02.

2" 7 40 0.025 0.1

0.078125

- - -

2 Toluene day tank- 045-TK-

001B 20°15'49.

6 86°36'03.

5 7 40 0.025 0.1

0.078125

- - -

3 Plant inventory tank- 044-TK-

001 20°15'49.

0" 86°36'03.

5 7 40

0.0508

0.1 - 0.0167

0.00755

-

4 Paraxylene day tank- 049-TK-

001 A 20°15'51.

2" 86°36'02.

2" 17 40 0.101 0.1

0.220486

- - -

5 Paraxylene day tank- 049-TK-

001 B 20°15'51.

2" 86°36'03.

5" 17 40 0.101 0.1

0.220486

- - -

6 Desorbent storage tanks-049-

TK-002 20°15'50.

3" 86°36'02.

2" 15 45 0.152 0.1

0.451389

- - -

7 Plant inventory storage tanks-

049-TK-003 20°15'50.

3" 86°36'03.

5 15 45 0.152 0.1

0.451389

- - -

8 Aromatic tank-048-TK-001 20°15'52.

1" 86°36'02.

2" 17 40 0.304 0.1

1.006944

- - -

9 Light reformate storage tank-

048-TK-002 20°15'52.

1" 86°36'03.

5" 17 40 0.152 0.01

1.145833

- - -

10 Isomer Regeneration Vent 20°15'44.

50" 86°35'56.

72" 30 120 0.15 17.3 - - -

97.222

Total(g/s) 3.6527

77 0.016

7 0.007

55 97.222

Note:

The data is obtained from Section 7.1.2.1 of Detailed Feasibility Report prepared by Toyo Engineering India Pvt. Ltd.

EIA Report

359 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-22 Predicted 24-Hrs’ GLC’s of VOC within 10 km Radius of the Study Area

on other vent emissions

Table 4-22 Estimated Top 10 Highest Concentrations of VOC obtained through

modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 458316 2241086 91.35354 1 N

2. 458316 2242086 42.70533 2 N

3. 458316 2243086 40.18009 3 N

4. 458316 2240086 33.90201 Project site Project site

5. 458316 2244086 31.72217 4 N

6. 459316 2242086 27.26532 2.24 NNE

7. 457316 2240086 26.44746 1 W

8. 458316 2245086 25.94425 5 N

9. 459316 2243086 24.39668 3.16 NNE

10. 458316 2246086 21.40595 6 N

EIA Report

360 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-23 Predicted 24-Hrs’ GLC’s of Benzene within 10 km Radius of the Study

Area on other vent emissions

Table 4-23 Estimated Top 10 Highest Concentrations of Benzene obtained through

modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 458316 2241086 2.56533 1 N

2. 458316 2242086 0.81094 2 N

3. 459316 2242086 0.4194 2.24 NNE

4. 458316 2243086 0.39163 3 N

5. 459316 2243086 0.37502 3.16 NNE

6. 457316 2242086 0.32137 2.24 NNW

7. 460316 2242086 0.31513 2.82 NE

8. 457316 2243086 0.30667 3.16 NNW

9. 459316 2237086 0.27299 3.16 SSE

10. 457316 2244086 0.24116 4.12 NNW

EIA Report

361 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-24 Predicted 24-Hrs’ GLC’s of Toluene within 10 km Radius of the Study Area

on other vent emissions

Table 4-24 Estimated Top 10 Highest Concentrations of Toluene obtained through

modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 458316 2241086 1.15977 1 N

2. 458316 2242086 0.36662 2 N

3. 459316 2242086 0.18961 2.24 NNE

4. 458316 2243086 0.17705 3 N

5. 459316 2243086 0.16955 3.16 NNE

6. 457316 2242086 0.14529 2.24 NNW

7. 460316 2242086 0.14247 2.82 NE

8. 457316 2243086 0.13864 3.16 NNW

9. 459316 2237086 0.12342 3.16 SSE

10. 457316 2244086 0.10903 4.12 NNW

EIA Report

362 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-25 Predicted 24-Hrs’ GLC’s of CO2 within 10 km Radius of the Study Area on

other vent emissions

Table 4-25 Estimated Top 10 Highest Concentrations of Carbon Dioxide obtained

through modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre

of Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 458316 2240086 277.7933 Project site Project site

2. 458316 2241086 266.6417 1 N

3. 458316 2242086 182.829 2 N

4. 456316 2239086 136.0366 2.24 WSW

5. 458316 2243086 131.4561 3 N

6. 457316 2238086 131.1408 2.24 SSW

7. 459316 2243086 130.7743 3.16 NNE

8. 455316 2238086 125.1713 3.60 WSW

9. 457316 2240086 119.79 1 W

10. 459316 2241086 110.5063 1.41 NE

EIA Report

363 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.4.8 Summary on Other Emission-Storage Tank vent & PX-Process vent emmission

Maximum pollutant concentrations of VOC, Benzene, Toluene and CO2 observed due to

proposed expansion for an 24hr-average period have been studied. The total increase in

concentrations above baseline status is summarized in Table 4-25.

Table 4-26 Total Maximum GLCs from the Storage Tank vent & PX-Process vent

emmission

Pollutant Baseline values Estimated Incremental Conc. (µg/m3)

VOC BLQ 91.35

Benzene BLQ 2.56

Toluene -- 1.15

CO2 -- 277.79

Note:

1. There is no standard for VOC, Toluene & CO2

2. Benzene NAAQ 2009 standards is 5 µg/m3 (annual)

EIA Report

364 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.4.9 Other Emission-PTA Process vent & Silo vent emmission

Figure 4-26 Project layout with proposed PTA Process vent & Silo vent coordinates

EIA Report

365 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-27 Google earth demarcation of proposed PTA Process vent & Silo vent coordinates

EIA Report

366 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 4-27 Proposed PTA Process vent & Silo vent emission details

S.No

Process & Silo Vent

details

Vent Coordinates Flue gas

Flow Rate

(Nm3/hr)

Stack Details

Emission (g/s)

N E Heig

ht (m)

Temp

(°C)

Dia(m)

Exit Velocity (m/s)

Benzene

Toluene

Xylene

Acetic

Acid

Methanol

Methyl

acetate

Bromine

Methyl

bromide

Carbon

monoxide

PTA Dust

Nitrogen

1. G1-Process Inert Vents- 051-C-175

20°16'07.8"

86°36'03.6"

292000 43.5 27 0.97

1.8 0.3 0.487 0.73 0.162 0.406 6.489 0.406 0.73 3.244 0 -

2.

G2/G3/G4-PTA Day silo A/B Off- Spec PTA Silo- 051-M-600A/B/C

20°16'03.1"

86°36'02.3"

13400 45 35 0.4 29.6 0.004 0.005 0.006 0.001 0.003 0.051 0.004 0.009 0.051 0.025 -

20°16'03.1"

86°36'02.7"

13400 45 35 0.4 29.6 0.004 0.005 0.006 0.001 0.003 0.051 0.004 0.009 0.051 0.025 -

20°16'03.1"

86°36'03.2"

13400 45 35 0.4 29.6 0.004 0.005 0.006 0.001 0.003 0.051 0.004 0.009 0.051 0.025 -

3. PSV Vent

Scrubber Stack20°16'8.53"

86°36'4.37"

55 27 80 0.35

0.z2 - - - - - - - - - - 19.16

67

Total (g/s) 0.312 0.502 0.748 0.165 0.415 6.642 0.418 0.757 3.397 0.075 19.16

67

Note:

The data is obtained from Section 7.1.2.2 of Detailed Feasibility Report prepared by Toyo Engineering India Pvt. Ltd.

EIA Report

367 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-28 Predicted 24-Hrs’ GLC’s of Benzene within 10 km Radius of the Study

Area on other vent emissions

Table 4-28 Estimated Top 10 Highest Concentrations of Benzene obtained through

modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~km)

Direction from Centre

of Project SiteE N

1. 458316 2242086 0.43865 2 N

2. 456316 2242086 0.27416 2.82 NW

3. 459316 2239086 0.20384 1.41 SE

4. 456316 2244086 0.2006 4.47 NNW

5. 455316 2242086 0.18984 3.60 WNW

6. 457316 2241086 0.18756 1.41 NW

7. 459316 2242086 0.17653 2.24 NNE

8. 455316 2245086 0.17557 5.83 NNW

9. 458316 2243086 0.17373 3 N

10. 459316 2243086 0.17193 3.16 NNE

EIA Report

368 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-29 Predicted 24-Hrs’ GLC’s of Toluene within 10 km Radius of the Study Area

on other vent emissions

Table 4-29 Estimated Top 10 Highest Concentrations of Toluene obtained through

modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~km)

Direction from Centre

of Project SiteE N

1. 458316 2242086 0.70718 2 N

2. 456316 2242086 0.44173 2.82 NW

3. 459316 2239086 0.32821 1.41 SE

4. 456316 2244086 0.32394 4.47 NNW

5. 455316 2242086 0.30527 3.60 WNW

6. 457316 2241086 0.30092 1.41 NW

7. 459316 2242086 0.28438 2.24 NNE

8. 455316 2245086 0.28333 5.83 NNW

9. 458316 2243086 0.27985 3 N

10. 459316 2243086 0.27668 3.16 NNE

EIA Report

369 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-30 Predicted 24-Hrs’ GLC’s of Xylene within 10 km Radius of the Study Area

on other vent emissions

Table 4-30 Estimated Top 10 Highest Concentrations of Xylene obtained through

modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 458316 2242086 1.05513 2 N

2. 456316 2242086 0.65882 2.82 NW

3. 459316 2239086 0.4893 1.41 SE

4. 456316 2244086 0.48389 4.47 NNW

5. 455316 2242086 0.45469 3.60 WNW

6. 457316 2241086 0.44751 1.41 NW

7. 459316 2242086 0.42408 2.24 NNE

8. 455316 2245086 0.42303 5.83 NNW

9. 458316 2243086 0.41732 3 N

10. 459316 2243086 0.41231 3.16 NNE

EIA Report

370 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-31 Predicted 24-Hrs’ GLC’s of Acetic Acid within 10 km Radius of the Study

Area on other vent emissions

Table 4-31 Estimated Top 10 Highest Concentrations of Acetic Acid obtained through

modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 458316 2242086 0.23307 2 N

2. 456316 2242086 0.14547 2.82 NW

3. 459316 2239086 0.10799 1.41 SE

4. 456316 2244086 0.10701 4.47 NNW

5. 455316 2242086 0.10026 3.60 WNW

6. 457316 2241086 0.09852 1.41 NW

7. 459316 2242086 0.09362 2.24 NNE

8. 455316 2245086 0.09351 5.83 NNW

9. 458316 2243086 0.09213 3 N

10. 459316 2243086 0.09096 3.16 NNE

EIA Report

371 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-32 Predicted 24-Hrs’ GLC’s of Methanol within 10 km Radius of the Study

Area on other vent emissions

Table 4-32 Estimated Top 10 Highest Concentrations of Methanol obtained through

modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 458316 2242086 0.58572 2 N

2. 456316 2242086 0.36566 2.82 NW

3. 459316 2239086 0.27152 1.41 SE

4. 456316 2244086 0.26874 4.47 NNW

5. 455316 2242086 0.25223 3.60 WNW

6. 457316 2241086 0.24809 1.41 NW

7. 459316 2242086 0.23536 2.24 NNE

8. 455316 2245086 0.23489 5.83 NNW

9. 458316 2243086 0.23161 3 N

10. 459316 2243086 0.22877 3.16 NNE

EIA Report

372 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-33 Predicted 24-Hrs’ GLC’s of MethylAcetate within 10 km Radius of the

Study Area on other vent emissions

Table 4-33 Estimated Top 10 Highest Concentrations of MethylAcetate obtained

through modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project Site

E N

1. 458316 2242086 9.37147 2 N

2. 456316 2242086 5.85109 2.82 NW

3. 459316 2239086 4.34518 1.41 SE

4. 456316 2244086 4.29868 4.47 NNW

5. 455316 2242086 4.03725 3.60 WNW

6. 457316 2241086 3.97236 1.41 NW

7. 459316 2242086 3.76622 2.24 NNE

8. 455316 2245086 3.75769 5.83 NNW

9. 458316 2243086 3.70619 3 N

10. 459316 2243086 3.66129 3.16 NNE

EIA Report

373 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-34 Predicted 24-Hrs’ GLC’s of Bromide within 10 km Radius of the Study

Area on other vent emissions

Table 4-34 Estimated Top 10 Highest Concentrations of Bromide obtained through

modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 458316 2242086 0.589 2 N

2. 456316 2242086 0.36789 2.82 NW

3. 459316 2239086 0.27332 1.41 SE

4. 456316 2244086 0.26987 4.47 NNW

5. 455316 2242086 0.25417 3.60 WNW

6. 457316 2241086 0.25047 1.41 NW

7. 459316 2242086 0.23683 2.24 NNE

8. 455316 2245086 0.23602 5.83 NNW

9. 458316 2243086 0.23306 3 N

10. 459316 2243086 0.23039 3.16 NNE

EIA Report

374 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-35 Predicted 24-Hrs’ GLC’s of Methyl Bromide within 10 km Radius of the

Study Area on other vent emissions

Table 4-35 Estimated Top 10 Highest Concentrations of Methyl Bromide obtained

through modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 458316 2242086 1.06497 2 N

2. 456316 2242086 0.6655 2.82 NW

3. 459316 2239086 0.49468 1.41 SE

4. 456316 2244086 0.48729 4.47 NNW

5. 455316 2242086 0.46051 3.60 WNW

6. 457316 2241086 0.45465 1.41 NW

7. 459316 2242086 0.42848 2.24 NNE

8. 455316 2245086 0.4264 5.83 NNW

9. 458316 2243086 0.42168 3 N

10. 459316 2243086 0.41718 3.16 NNE

EIA Report

375 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-36 Predicted 1-Hr GLC’s of CO within 10 km Radius of the Study Area on

other vent emissions

Table 4-36 Estimated Top 10 Highest Concentrations of Carbon Monoxide obtained

through modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 458316 2242086 53.97387 2 N

2. 456316 2242086 46.14078 2.82 NW

3. 456316 2244086 42.75771 4.47 NNW

4. 459316 2242086 39.55771 2.24 NNE

5. 459316 2239086 39.40617 1.41 SE

6. 455316 2245086 38.31169 5.83 NNW

7. 459316 2243086 34.72436 3.16 NNE

8. 454316 2246086 31.13434 7.21 NNW

9. 455316 2242086 29.4794 3.60 WNW

10. 457316 2243086 28.15549 3.16 NNW

EIA Report

376 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-37 Predicted 24-Hrs’ GLC’s of PTA Dust within 10 km Radius of the Study

Area on other vent emissions

Table 4-37 Estimated Top 10 Highest Concentrations of PTA Dust obtained through

modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~Km)

Direction from Centre

of Project SiteE N

1. 458316 2242086 0.10857 2 N

2. 460316 2242086 0.10211 2.82 NE

3. 459316 2242086 0.06468 2.24 NNE

4. 462316 2243086 0.06038 4.99 ENE

5. 457316 2241086 0.05948 1.41 NW

6. 456316 2242086 0.05564 2.82 NW

7. 457316 2240086 0.05521 1 W

8. 458316 2243086 0.05163 3 N

9. 457316 2242086 0.05091 2.24 NNW

10. 455316 2242086 0.04849 3.60 WNW

EIA Report

377 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 4-38 Predicted 24-Hrs’ GLC’s of Nitrogen within 10 km Radius of the Study

Area on other vent emissions

Table 4-38 Estimated Top 10 Highest Concentrations of Nitrogen obtained through

modeling on other vent emission

S. No

UTM coordinates (m) Conc.

(µg/m3)

Distance from Centre of

Project SIte (~km)

Direction from Centre

of Project SiteE N

1. 458316 2241086 150.7935 1 N

2. 458316 2242086 96.06833 2 N

3. 458316 2243086 60.6044 3 N

4. 458316 2240086 51.86108 Project site Project site

5. 459316 2242086 49.56477 2.24 NNE

6. 458316 2244086 46.40236 4 N

7. 456316 2240086 45.36553 2 W

8. 457316 2240086 43.48103 1 W

9. 459316 2244086 42.54081 4.12 NNE

10. 458316 2245086 39.63591 5 N

EIA Report

378 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.4.10 Summary on Other Emission- PTA Process vent & Silo vent emmission

Maximum pollutant concentrations of Benzene, Toluene, Xylene, Acetic Acid, Methanol,

Methyl acetate, Bromine, Methyl bromide, PTA Dust and Nitrogen observed due to proposed

expansion for an 24hr-average period have been studied and CO observed due to proposed

expansion for an 1hr-average period have been studied. The total increase in concentrations is

summarized in Table 4-38.

Table 4-39 Total Maximum GLCs from the Process & Silo Vent Emissions

Pollutant Estimated Incremental

Conc. (µg/m3)

Benzene 0.43

Toluene 0.70

Xylene 1.05

Acetic Acid 0.23

Methanol 0.58

Methyl acetate 9.37

Bromine 0.58

Methyl bromide 1.06

Carbon monoxide 53.97

PTA Dust 0.10

Nitrogen 150.79

Note:

1. There is no standard for Toluene, Xylene, Acetic Acid, Methanol, Methyl acetate, Bromine,

Methyl bromide, Nitrogen.

2. Benzene NAAQ 2009 standards is 5 µg/m3 (annual) & Carbon monoxide NAAQ 2009

standards is 4 mg/m3 (1hour).

EIA Report

379 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.5.5 Impacts due to Traffic and Transportation

The vehicular movement for the proposed project is given in Table 4-40.

Table 4-40 Existing & proposed vehicular movement per Hour (Peak Hour)

S. No

Type of Vehicle

Existing vehicles

Existing PCU

Proposed

vehicles

Proposed

PCU

Total vehicles

after project

implementation

PCU Factors IRC (SP

41)

Total PCU after

project implement

ation

1 2 wheeler 124 93 0 0 127 0.75 93

2 3 wheelers 48 96 0 0 48 2 96

3 4 wheelers/ cars

91 91 5 5 96 1 96

4 truck/Lorry 79 292.3 17 62.9 96 3.7 355.2

5 agricultural tractor

11 44 0 0 11 4 44

6 light emission vehicle

9 12.6 0 0 9 1.4 12.6

Total 362 628.9 22 67.9 384 696.8

Table 4-41 Traffic Volume after Implementation of the Project

*LOS (Level of Service) categories are A-Free Flow, B- Reasonably Free Flow, C-Stable

Flow, D-Approaching unstable flow, E- Unstable flow, F- Forced or breakdown flow

Due to propose project there will be slight increment in the vehicle movement but the level of

service (LOS) anticipated will be Stable Traffic Flow.

4.6 Noise Environment

4.6.1 Impact

The noise generated during the operational phase can be divided into two categories

For the Road Volume of

Traffic Volume

(V)

Road Capacity

(C)

V/C Ratio

LOS Category*

Traffic Classification

Existing 362 628.9 1500 0.42 “B” Stable Traffic

Flow After

implementation384 696.8 1500 0.47 “B”

Stable Traffic Flow

EIA Report

380 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

A) Stationary source due to heavy duty machineries at the project site such as compressors,

DG sets, pumps etc.

B) Mobile source corresponding to mainly vehicular traffic for staff mobilization, materials,

material transportation, liquid fuel transportation to project site, etc.

Vibrations are expected to be generated by various activities associated with the proposed

project during operational phase. The impact of vibrations beyond the site would be

negligible during normal operation phase. However, the impacts on workers engaged in the

plant area would be considerable due to occupational exposure. The proposed fixed major

equipment/units such as compressors, pumps, DG sets etc., also generate vibrations during

operational phase and may cause exposures to the workers/operators engaged at these units.

All equipment’s in the plant produce 40 to 55 dB(A) after control measures and equipment’s

are designed/operated to have a noise level not exceeding 85 to 90 dB(A) as per the

requirement of Occupational Safety and Health Administration Standard (OSHA). In

addition, since most of the noise generating equipment would be in closed structures, the

noise transmitted outside would be still lower and for any other case of higher noise sufficient

safety ear plugs and ear muffs will be provided to the employees.

4.6.2 Mitigation Measure

The major noise generating equipment like Compressors, DG sets, pumps etc. will be

enclosed in an acoustic enclosure designed for an insertion loss of 25 dB (A) and

silencers to other equipment etc.

Major noise generating equipment will be designed with 85 dB (A) ensuring

cumulative noise at 1.0 m remains at 85 dB (A).

The occupational noise exposure to the workers in the form of eight hourly time

weighted average will be maintained well within the prescribed Occupational Safety

and Health Administration (OSHA) standard limits.

Acoustic design with sound proof glass paneling will be provided for critical operator

cabins / control rooms of individual modules as well as central control facilities.

Use of personal protective equipment’s/devices such as ear-muffs, ear plugs etc. will

be strictly enforced for the workers engaged in high noise areas.

EIA Report

381 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Periodic maintenance of the equipment to be used in the developmental works will be

carried out. Worn out parts will be replaced and rotating parts will be lubricated to

minimize noise emissions.

Implementation of greenbelt for noise attenuation will be undertaken: shrub

plantation; landscaping with horticulture; and Tree plantation at vehicle parking areas

and along approach roads.

Ambient noise levels will be monitored at regular intervals during operational phase

of the project.

Low vibration generating machines/equipment will be selected to meet international

standards and foundations will be so designed to minimize vibrations and secured

properly.

Vibration generating sources and their platforms should be maintained properly to

minimize vibrations and related impacts.

Various standards pertaining to vibrations are formulated by statutory bodies like

Bureau of Indian Standards (BIS) and Director General of Mines Safety (DGMS),

which is being practiced would be continued to mitigate the workers’ health effects

due to vibrations.

Vibration dampers will be provided around the source of generation.

Transportation Management Plan will be prepared and the transportation of

construction materials will be planned in line with the same.

4.7 Water Environment

No water will be extracted from ground water sources. The total raw water requirement for

existing facility is 3497 m3/hr and for proposed operation phase total requirement will be

1299.5 m3/hr. On total after expansion 4796.5 m3/hr of raw water of which the fresh water of

3743 m3/hr will be taken from existing water source (Mahanadi River). New ETP is proposed

for installation to process effluent @ 408 m3/hr with 10% design Margin (Maximum capacity

with high TOC).

The source of water will be from Existing Refinery water source i.e., Mahanadi River. Hence

there will be no separate permission is required for the proposed projects

EIA Report

382 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.7.1 Mitigation Measures

Various mitigation measures are proposed to be adopted to minimize the impact if any on the

water environment due to the wastewater/runoff generation during the operation phase of the

project.

Institutional arrangement for monitoring of water pollution.

Corrective and preventive measures if any contamination happens.

Monitoring should ensure early determination of any threats to water resources in

terms of contamination.

If contaminated, proper expertise will be brought to schematize the various recharge

mechanism to reduce or nullify the impact effects.

4.7.2 Waste Water Quality, Quantity and Treatment Method

a) Existing

Approx. 1082.1 m3/hr of effluent is generated in the existing facility of which 190.88 m3/hr

rejects from RO is disposed to Deep Sea, 50 m3/hr rejects from RO is sent to Coke Dust

Suspension and 50 m3/hr rejects from RO is sent to Coke Cutting. The Sludge created during

the treatment of about 32.46 m3/hr along with a water loss of about 10.76 m3/hr. Remaining

748m3/hr from RO is reused back in the system for DM Water Makeup.

b) Proposed

In the proposed expansion Approx. 408 m3/hr of effluent is generated in the proposed facility

of which 78% of effluent is processed in RO plant and its rejects of 86.18 m3/hr is disposed

into deep sea. The Sludge created during the treatment of about 12.24 m3/hr along with a

water loss of about 4.08 m3/hr. The remaining RO processed water of 305.5 m3/hr is reused

back in the system for DM Water Makeup and cooling tower. New ETP is proposed for

installation to process effluent @ 408 m3/hr with 10% design Margin (Maximum capacity

with high TOC)

The existing and proposed effluent disposal into deep sea is 190.88 m3/hr and 86.18 m3/hr

respectively. On total, 277.06m3/hr will be discharge into deep sea and it is observed to be

within the discharge approval limit of 350 m3/hr as per the OPCB consent for Air and water

obtained vide:5543/IND-I-CON-6414 dated 31.03.2021 valid till 31.03.2022 copy enclosed

as Annexure 3. The industrial effluent is discharged into deep sea through the pipeline where

its outlet of pipe is at a distance of 3km from the Low Tide Line (LTL).

EIA Report

383 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

4.8 Land Environment

During operational phase the impact shall be due to disposal of solid and hazardous waste

generated during operation of the plant. Spent Catalyst after every 4-5 years will be duly

recovered by PCB approved agencies

4.8.1 Potential Impact Due to Location

The proposed expansion is within the IOCL existing facility, there will be no additional land

acquisition and resettlement or Rehabilitation required. Therefore, there will not be any direct

impacts.

4.8.2 Impacts Due to Changes in Land Use Pattern

One of the factor that is usually considered as a major impact from any project is the land use

change. But since the proposed expansion will be established within the existing IOCL site,

no land use change is foreseen, as the current land use is that of industrial.

4.8.3 Mittigation Measures

The following mitigation measures may be explored:

Periodic maintenance and check of wastewater conveyance pipelines

Attempt to restore by replacing a part or putting together the torn or broken parts

of the conveyance pipeline in case of any leakage is detected.

Necessary preventive measures for spillage from pipelines, such as surface RCC

channels along the pipelines shall be adopted.

Treated wastewater quality shall be ensured as per standards before using internal

use.

4.9 Marine Environment

The impact in the context of biota and fishery resources in the area is not considered to be

significant as the construction in the creek is for minimal period. The impact of closed

conveyor passing through the creek would have least impact on the aquatic ecological status

as there will be no spillage in this area.

The project proponent shall adopt preventive practices like leak monitoring of existing

effluent discharge pipelines in the sea, surveillance to prevent any liquid hydrocarbon falling

on the water body of the creek from the hydrocarbon pipelines passing over the bridge of

Santa Creek. The project proponent shall have mitigation plan with Oil spill contaminant

EIA Report

384 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

boom under the new pipe bridge to take care of any inadvertent oil spills and suitable

skimmers for recovering of any accidental oil spill over the creek water.

The existing and proposed effluent disposal into deep sea is 190.88 m3/hr and 86.18 m3/hr

respectively. On total, 277.06m3/hr will be discharge into deep sea that it is observed to be

within the marine discharge approval limit of 350 m3/hr as per the OPCB consent for Air and

water obtained vide: 3946/IND-I-CON-6414 dated 27.03.2020 valid till 31.03.2021 copy

enclosed as Annexure 3. The industrial effluent is discharged into deep sea through the

pipeline where its outlet of pipe is at a distance of 3km from the Low Tide Line(LTL).

4.10 Solid Waste Management

4.10.1 Impact Due to Solid Waste Generation

During operation phase, various types of solid waste are likely to be generated which can be

broadly categorized as Hazardous Waste and Non-hazardous Waste. Further, the generated

solid waste generation may include Biodegradable, Recyclable and Inert compounds. The

details of solid waste generation and its management proposed are discussed in Chapter 2,

Section 2.18.

4.10.2 Mitigation Measures

The hazardous waste generated can be processed by bioremediation techniques or with proper

disposal to the authorities. The biodegradable waste generated can be composted and used as

manure. The other waste can be disposed in municipal bins.

EIA Report

385 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CHAPTER 5

ANALYSIS OF ALTERNATIVES

EIA Report

386 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

5 ANALYSIS OF ALTERNATIVES 5.1 Introduction

Indian Oil Corporation Limited (IOCL), Paradip Refinery Proposes “Integrated Para-Xylene

& Purified Terephthalic Acid (PX-PTA) Project at IOCL Paradip Refinery & Petrochemical

Complex, Paradip

The range of alternatives selected for the purpose of analysis includes:

Site alternative

Water supply alternative

Technology alternative

5.2 Site Alternative

Paradip Refinery, has spread over a total area of 3,345 acres, including about 314 acres for

Residential and about 240 acres of land for other office and buildings. The area of 355 acres

is utilized for the connecting road in the total area. Since the proposed project is expansion

within the existing facility there is no new site/ alternative sites considered.

5.3 Water Supply Alternative

The total fresh water requirement of 2749 m3/hr for the existing refinery is met from water

from Mahanadi River. Since the proposed project uses the existing water source there is no

alternative water supply considered

5.4 Technology Alternative

Paradip Refinery has a unique INDMAX Unit technology, which is indigenously been

developed by Indian Oil's R&D Centre. The INDMAX (FCC) Unit has designed to produce

44% LPG, the highest yield from such plants. The commissioning of INDMAX Unit at

Paradip marks a major milestone in the history of Indian refining. With this, IndianOil has

now recognized globally as a technology licensor. The other first-time technological features

of the Refinery include Flue Gas Desulphurisation facilities, Vapour Recovery system from

jetty loading and an alkylation process to get octane-rich low-benzene MS blend component,

etc. So no alternative technologies available.

EIA Report

387 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CHAPTER 6

ENVIRONMENTAL MONITORING

PROGRAM

EIA Report

388 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

6 ENVIRONMENTAL MONITORING PROGRAM 6.1 Introduction

Environmental monitoring is an essential tool for sustainable development & ensuring

effective implementation of environmental management plan & mitigation measures adopted.

Environmental monitoring will undertake primarily to determine the environmental effects of

human activities and secondarily to increase understanding of cause – effect relationships

between human activity and environmental change. Environment monitoring is a repetitive &

systematic measurement of the characteristics of environmental components to test specific

hypotheses of the effect of human activities on the environment. Environmental monitoring

program enables the proponent to identify the deviation of environmental quality due to the

proposed project activities.

6.2 Environmental Effects Monitoring in EIA

Environmental effects monitoring programs provide the necessary information to:

Verify the accuracy of EIA predictions;

Determine the effectiveness of measures to mitigate adverse effects of projects

on the environment.

Environmental monitoring program is a vital process of any management plan of the

development project. This helps in signalling the potential problems resulting from the

proposed project and will allow for prompt implementation of effective corrective measures.

The environmental monitoring will be required for the construction and operational phases.

The main objectives of environmental monitoring area:

i. To assess the changes in environmental conditions,

ii. To monitor the effective implementation of mitigation measures,

iii. Warn significant deteriorations in environmental quality for further prevention

action.

iv. In order to meet the above objectives, the following parameters need to be

monitored:

v. Afforestation,

vi. Water Quality and Public Health,

vii. Air and Noise quality,

viii. Soil Conservation, and

ix. Sanitation and Waste Disposal

EIA Report

389 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

6.2.1 Post Project Environment Monitoring Program

The summarized form of post monitoring details is presented in the following Table 6-1.

Table 6-1 Post Project Environmental Monitoring Plan

S.

No Particulars

Frequency of

monitoring Parameters for Monitoring

1. Air pollution monitoring

Ambient air quality within

the premises

Continuous PM, SOx, NOX, NO2, CO, O3,

VOC

Ambient air quality within

the premises

Twice in a week All 12 parameters as given in

NAAQS

Ambient air quality at 1

location in Prevalent Down

Wind Direction

Twice in a week All 12 parameters as given in

NAAQS

Ambient air quality at 1

location in Up Wind

Direction

Twice in a week All 12 parameters as given in

NAAQS

2. Noise monitoring

At two locations within the

premises

Once in a month Noise Levels in dB(A)

3. Ground water quality monitoring

One location at site Quaterly Physicochemical properties and

Heavy Metals The groundwater

results are compared with the

acceptable and permissible water

quality standards as per IS:

10500 (2012)

4. Soil Quality monitoring

One location near Hazardous

waste storage area at site and

one location outside site

Annually Physicochemical properties,

Nutrients, Heavy metals as per IS

2720 (All Parts)

EIA Report

390 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

No Particulars

Frequency of

monitoring Parameters for Monitoring

5. Effluent Quality Monitoring

Inlet and outlet of ETP Once a month pH, Temp, TDS, TSS, Chloride,

Sulphide, Sulphate, fluoride,

ammoniacal Nitrogen, Sodium,

Copper, Zinc, Phenolic

compounds, Oil and Grease,

Boron, BOD, COD, Total

Residual Chlorine, Arsenic,

Cadmium, Total Chromium,

Hexavalent Chromium, Lead,

Selenium, Mercury, Pesticides,

Alpha emitters, Free Ammonia,

Dissolved Phosphates, Total

Kjeldhal nitrogen, Cyanide,

Nickel, Residual Sodium

Carbonate. All the Parameters

are to be verified as per CPCB

Standard Guidelines.

Inlet and out let of STP Once a month Sewage is Biologically treated as

a part of the ETP and standards

are met through the pH, Temp,

TDS, TSS, BOD, COD, Oil and

grease. All the Parameters are to

be verified as per CPCB

Standard Guidelines.

6. Work place Monitoring Quarterly Noise, VOC, Lux levels

6.2.2 Monitoring Methodologies

Monitoring of environmental samples shall be done as per the guidelines provide by

MoEF&CC/CPCB/SPCB-Odisha. The methods conducted or applied shall be approved or

sanctioned by the any recognized body or authority i.e. MoEF&CC/CPCB/SPCB-Odisha.

EIA Report

391 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

As per the gathered information by IOCL Paradip Refinery on its previous EC and EIA, one

AAQMS envisaged in for the current site for the project was relocated near the main entrance

to the battery limit as the proposed unit was deferred that time. Further keeping in view of the

increased vehicular movement through North Site of the plan for petrochemical product

movement, two additional AAQMS with continuous AAQ monitoring system and manual

monitoring to be installed in north site of the plant as per CPCB guideline.

6.3 Reporting & Documentation

All the necessary reports and documents shall be prepared complying with the statutory rules

& regulations. Proper and due care shall be taken to adhere to the laid down rules and

regulation by the government. Regular and periodic record shall be kept in order to ensure

easier, comparable and brisk review and projection of past, present and future performances.

Also, the management shall ensure to prepare separate records for water, wastewater, solid

waste, air, emission, regularly and periodically in order to provide better and smooth

vigilance.

The management shall look into the fact that as soon as the preparation of reports gets over it

shall be forwarded to the concerned authority with due care for the purpose of reviewing.

Adhering to the rules and regulations the management shall ensure that the outcome of the

reports and the conclusions been drawn shall be prepared as per the laid down regulations and

procedures. No breach of any convention shall be availed.

These reports/documents shall be regularly and periodically reviewed and any changes/

discrepancies found in mitigation measures/ operation/ management/ technology shall be

brought into notice instantaneously and all possible corrective actions shall be taken to match

the discrepancies been witnessed.

6.4 Budget for Environmental Monitoring Plan

Particulars and frequency of environmental Monitoring is given in Table 6-2.

Table 6-2 Budgetary allocation for Environmental Monitoring

S. No Particulars Frequency of monitoring Cost in

Lakhs

1. Air pollution monitoring

Stack monitoring Manual. Twice in a Month 150

EIA Report

392 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No Particulars Frequency of monitoring Cost in

Lakhs

Ambient Monitoring

within the premises, 1

location in Prevalent

Down Wind and Up

Wind Direction

Continuous

100

2. Noise monitoring

At two locations within

the premises

Once in a month 3

3. Ground water quality monitoring 4 One location at site Quaterly

4. Soil Quality monitoring

4

One location near

Hazardous waste

storage area at site and

one location outside

site

Annually

5. Effluent Quality Monitoring

Inlet and outlet of ETP Once a month 10

6. VOC monitoring Quarterly 10

Total 281

EIA Report

393 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CHAPTER 7

ADDITIONAL STUDIES

EIA Report

394 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

7 ADDITIONAL STUDIES 7.1 Public Consultation

The project is falling under ‘A’ category as per EIA Notification 2006 and Public Hearing is

mandatory as per ToR obtained. Hence draft EIA report has been prepared as per the No: J-

11011/395/2012-IA.II(I) dated 30th September 2018 and submitted for Public Hearing.

Public Hearing paper advertisement was published in The New Indian Express and The

Pramaya newspapers on 30.01.2021.

Public hearing was conducted by OSPCB on 02-03-2021 at 10.30am at Municipality Kalyan

Mandap, Madhuban, Paradeep and Sri Kanhu Charan Dhir, Additional District Magistrate,

Paradip presided over the meeting along with Er. Dillip Kumar Dash, Regional Officer, State

Pollution Control Board, Odisha, Paradip. Newspaper Publication details and Public Hearing

minutes are enclosed as Appendix 3. The newspaper advertisement details are shown in

Figure 7-1 & Figure 7-2. Notice issued for public hearing is enclosed as Figure 7-3. Public

Hearing photographs are shown in Figure 7-4. The total fund allotted for the commitment

made on the requirement of public during public hearing is INR 6.64Cr.

EIA Report

395 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 7-1 Public Hearing Advertisements(Odisha)

EIA Report

396 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 7-2 Public Hearing Advertisements(English)

EIA Report

397 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 7-3 Public Hearing Announcement in nearby villages

Figure 7-4 Public Hearing photographs

EIA Report

398 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

7.1.1 Reply to the issues raised by the public during Public Hearing on 02.03.2021

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

1 Kishore Kumar

Parida from

Sarpanch,

Dhinkia G.P

He had welcomed the project and

also showed his concerns about

IOCL's failure in fulfilling prior

commitments in local employment.

Recruitment for permanent post in IOCL is done through open

competition and candidates are selected as per Corporation

recruitment policy.

For contractual engagement in various agencies working for

Paradip Refinery, are done by the agency itself based on their

requirement subject to meeting the requisite qualification and

skill.

As per RR Plan 2002, approved by RPDAC under the

chairmanship of RDC(C), Cuttack (Gov. of Odisha), for

Paradip Refinery project, there is no provision for any

preferential engagement at Paradip Refinery or in various

agencies engaged by Paradip Refinery except preference in

engagement of identified displaced persons who have not

taken cash grant in the above RR plan.

-

He requested to provide facilities

in local area to protect the villagers

during high tide and cyclonic

Storm periods when salty water

enters into their villages and

agricultural land.

Gov. of Odisha is arranging relief for natural calamities like

cyclonic storm & high tide. IOCL will extend support in such

events as per requirements in association with District

Administration and concerned Gram Panchayat (GP).

Rs. 25 Lakh over 5

year for calamities

support

EIA Report

399 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

2. Ranjan Kumar

Bardhan from

Govindapur,

Dhinkia GP

He had welcomed the project with

condition for spending CSR

budgets in Dhinkia GP and nearby

areas.

Various developmental activities e.g. providing drinking

water facilities, infrastructure developments, women

empowerment, organizing medical camps, community

development, promoting education, skill development

trainings, swachhta & conservation of environment etc. in

nearby GPs under CSR are being finalized by CSR team of

Paradip Refinery in consultation with Dist. Administration.

IOCL Paradip refinery has spent about Rs. 7.3 Crore during

FY 2019-20 under CSR in nearby GPs.

-

He further requested to recruit land

losers at least in contractual jobs,

to reconstruct the by-pass road and

to clean the drains for eradicating

mosquito nuisance in the area.

For contractual engagement in various agencies working for

Paradip Refinery, are done by the agency itself based on their

requirement subject to meeting the requisite qualification and

skill.

In consultation with Dist. Administration, IOCL will explore

the possibility of reconstruction of bypass road under its CSR

program. Regarding eradication of mosquito breeding, IOCL

is already in the job and will continue the same.

5.0 Lakh over 5

years for drain

cleanliness,

Mosquito

containment

measures and

continuing.

3 BishnuCharan

Swain from

Kujang,

Jagatsinghpur

He expressed many things

irrelevant to the project and

highlighted general environmental

condition of Paradip area.

- -

4 Subash Pradhan

from

Trilochanpur,

Dhinkia

He asked to provide Basic facilities

to the nearby areas.

He emphasized on boundary side

drain cleaning in Dhinkia to

Various basic amenities / facilities like providing drinking

water, organizing medical health camps, mobile medical vans

with free consultation & medicines, promoting education,

swachhta & conservation of environment etc. in nearby GPs

5.0 Lakh over 5

years for drain

cleanliness,

Mosquito

EIA Report

400 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

eliminate mosquito nuisance. under CSR are being carried out on regular basis.

Regarding boundary side drain cleaning & eradication of

mosquito breeding, IOCL is already in the job and will

continue the same.

containment

measures &

continuing.

He also said agriculture land has

been affected due to salty water

intrusion for which sluice gate to

be provided.

Being the GP dominated by agro

dependent population he

emphasized on utilization of more

CSR fund on education, road

transport & health care facility by

the unit. He stated that focus

should be on the affected

agriculture land and local

employment.

In consultation with District Administration, installation of

sluice gate to prevent intrusion of salty water into agriculture

land will be explored under CSR project.

Various developmental activities e.g. infrastructure

developments, women empowerment, organizing medical

camps, mobile medical units with free consultation &

medicines, community development, promoting education,

skill development trainings, swachhta & conservation of

environment etc. in nearby GPs under CSR are being

identified & finalized by CSR team of Paradip Refinery in

consultation with District Administration.

Rs. 25 Lakh over 5

years for taking up

these facilities.

5 Bikramjit

Samantaray

from Dhinkia

He highlighted about the existing

pollution problems due to IOCL

refinery and expressed his

concerns about their adverse

impacts. He supported the project

with a condition to minimize

existing pollution problems and

IOCL should look into the social

issues of local area.

Paradip Refinery complex deployed latest technology

process units, equipments and commissioned refinery in

year 2015-16andoperations gradually stabilised at rated

capacity in 2019-20.All requisite pollution control facilities

have been installed & mitigation measures taken for

prevention of environmental pollution with compliance to the

applicable statutory rules, regulations and specified limits.

High efficiency heater & boilers with low NOx burners,

treated low Sulphur fuel Gas (H2S <150 mg/Nm3) and fuel

oil (<0.5%), BSVI Diesel fuel are being used.

Rs. 30.0 Lakh over 5

years for social

issues like drinking

water, drainage,

women

empowerment,

scholarship etc.

EIA Report

401 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

Monitoring reports enclosed Annexure-26.

Display board has been installed for public view&

appreciation for the emission and discharge parameters.

Awareness training programs are being conducted for Local

Sarpanchs to disseminate information, knowledge about the

pollution control measures installed in Paradip Refinery.

Pollution control measures as per standard meeting statutory

requirement shall be implemented in the proposed project

also.

6 Arakshita Das,

Kothi

He supported the project because

no additional land is required.

However, he highlighted the

failure of IOCL in fulfilling

previous commitments.

Recruitment for permanent post in IOCL is done through open

competition and candidates are selected as per Corporation

recruitment policy.

For contractual engagement in various agencies working for

Paradip Refinery, are done by the agency itself based on their

requirement subject to meeting the requisite qualification and

skill.

As per RR Plan 2002, approved by RPDAC under the

chairmanship of RDC(C), Cuttack (Gov. of Odisha), for

Paradip Refinery project, there is no provision for any

preferential engagement at Paradip Refinery or in various

agencies engaged by Paradip Refinery except preference in

engagement of identified displaced persons who have not

taken cash grant in the above RR plan.

Various developmental activities e.g. providing drinking

-

EIA Report

402 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

water facilities, infrastructure developments, women

empowerment, organizing medical camps, community

development, promoting education, skill development

trainings, swachhta & conservation of environment etc. in

nearby GPs under CSR are being identified & finalized by

CSR team of Paradip Refinery in consultation with Dist.

Administration.

IOCL Paradip refinery has spent about Rs. 7.3 Crore during

FY 2019-20 under CSR in nearby GPs.

He expressed that the project

should come and IOCL should take

up CSR activities including

provision of medical facility and

drinking water supply in the area.

Medical health camps are being organized in nearby villages,

GPs. Last check-up was done in 2019-20, however the same

will resume on normalization of Covid-19 pandemic situation

in the localities. Mobile medical services are being provided

in Paradip & Jagatsinghpur district.

Drinking water supply is being done through tankers. Three

Drinking water supply projects for nearby villages have been

approved and are under execution at about Rs. 3.4 Cr

expenditure.

Rs. 10.0 Lakh per

month over 2 years

for mobile medical

servicesandhealth

camps.

He also demanded about

requirement of local people to the

extent of 70 % at least in

contractual jobs.

For contractual engagement in various agencies working for

Paradip Refinery, are done by the agency itself based on their

requirement subject to meeting the requisite qualification and

skill.

-

EIA Report

403 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

He further emphasized that IOCL

should resume its scheme of

awarding scholarship to local

meritorious student.

Scholarship to meritorious students is already in place and

will be continued. There was a disruption during 2020 due to

Covid-19 pandemic situation in Odisha. Scholarship Scheme

has been utilised Rs 7 Lakh in 2019-20.

Rs. 8.0 Lakh for

2021-22 for

scholarship award to

meritorious students

from nearby Gram

Panchayats.

7 Pabitra Kumar

Sahoo from

Kothi

He supported the project.

However, he requested district

administration to take up all local

concerns with IOCL for fulfilling

their demand and minimizing

pollution problems.

Modern and best technological Pollution control measure

have been installed in Paradip Refinery. Pollution monitoring

is being done on continuous basis and remains well within

limits.

Monitoring reports enclosed as Annexure- 26.Display board

is installed for public view for emission and discharge

parameters.

Awareness programs are being conducted for nearby villages

Sarpanchs and the same will be further conducted to enhance

their knowledge.

Pollution control measures as per standard meeting statutory

requirement shall be implemented in the proposed project

also.

IOCL has spent about Rs. 30 Crore for environment control

operations and about Rs. 7 Crore under CSR program to

nearby areas, villages, gram panchayats (GPs).

Rs. 30 Lakh over 5

year for fulfilling

local concern, issues

related jobs.

He further emphasize on general IOCL Paradip Refinery has been cleaning the NH-5 road from Rs. 6.0 Lakh annual

EIA Report

404 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

environmental issues to road

transportation, road conditions of

Paradip area and appealed for

introducing a road cleaning

scheduled from Bhutamundai to

Paradip.

‘Zero Point’ to Dochakki engaging mechanized road cleaner

on regular basis. As per resolution of the Environment

Committee Meeting in 2019 chaired by District Magistrate&

Collector, major industries of Paradip have been allocated the

road zones for cleaning and the same is being done.

Respective authorities NHAI, SPWD and Paradip

municipality are maintaining roads in Paradip area.

for the road segment

cleaning.

8 NrusinghCharan

Das from

Dhinkia

He emphasized about

persistingissues related to air and

noise pollution during operation of

refinery.

IOCL has installed latest high efficiency Heaters Boilers with

Low NOx burners, uses very low Sulphur Fuel Gas (<150

mg/NM3), Fuel Oil (<0.50%) and BS-VI Diesel fuel. All

requisite pollution control facilities has been provided &

mitigation measure being taken for prevention of

environmental air pollution with compliance to the applicable

statutory rules, regulations, specified limits. Continuous

monitoring of emission and pollution, ambient air quality

through analysers and accredited agencies is being done. The

emissions are observed within limits. Monitoring report

enclosed as Annexure-26.

Display board is installed for public view for emission and

discharge parameters.

Low Noise level equipments are installed with acoustic

enclosures for noise reduction. Noise level monitoring is

being done periodically and corrective action taken. Noise

level report enclosed as Annexure-27.

IOCL Paradip refinery spend about Rs. 30 Crore for

environment control operations.

-

EIA Report

405 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

He further intimated about

breeding of mosquitoes in nearby

drain which are not cleaned by

IOCL.

Regarding boundary side drain cleaning & eradication of

mosquito breeding, IOCL is already in the job and will

continue the same.

Rs. 5.0 Lakh over 5

years for drain

cleanliness,

Mosquito

containment

measures and

continuing.

He finally expressed that he does

not opposed the project but IOCL

should take up the existing issues

for providing a better life to the

nearby dwellers.

IOCL Paradip Refinery has undertaken the following

activities under the scope of CSR for the betterment of life of

the nearby villagers:

Providing drinking water facilities

Organizing medical camps and mobile medical units

Infrastructural developments such as construction of

concrete roads, toilet complex,

Promoting education by renovation of school building,

library, boundary wall, boys & girls toilets, distribution of

dual desk benches, UV water coolers & desktop

computers.

Skill development in association with NSDC & CIPET.

Women empowerment – improving income generation

capabilities of women through self-help group by

distributing sewing machines, waste paper recycling

machines. Few more machines have been planned for

distribution in FY 2021-22 which will create employment

opportunities and improve the livelihood of the women of

neighbouring GPs.

IOCL has spent

about Rs. 11 Crores

in last 3 years under

CSR and

environment

program.

EIA Report

406 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

9 Shyma Sundar

Sahoo from

Bagadia

He had signed in the attendance

sheet but remained absent

during deliberation.

- -

10 Pramod Kumar

Jena from

Nuagarh GP

He mentioned that industrialization

should be aimed at development.

He intimated about failure of IOCL

in CSR activities, drinking water

supply, medical treatment,

providing green belt and providing

minimum facilities to its

contractual employees.

Paradip Refinery has undertaken the following activities

under the scope of CSR for the betterment of life of the

nearby villagers:

Providing drinking water facilities

Organizing medical camps and mobile medical units

Infrastructural developments such as construction of

concrete roads, toilet complex,

Promoting education by renovation of school building,

library, boundary wall, boys & girls toilets, distribution of

dual desk benches, UV water coolers & desktop

computers.

Skill development in association with NSDC & CIPET.

Women empowerment – improving income generation

capabilities of women through self-help group by

distributing sewing machines, waste paper recycling

machines. Few more machines have been planned for

distribution in FY 2021-22 which will create employment

opportunities and improve the livelihood of the women of

neighbouring GPs.

FourRest shelters for

contractual workers

inside Refinery

complex have been

approved and three

have been already

completed and are in

use. Balance one no.

completionexpected

bySep’2021.

He demanded IOCL to provide (i)

a parking shed for its contractual

employees (ii) medical camps in

IOCL has provided (i) parking area at its refinery gate,

Material gate, admin area and TTL gate.(ii) Medical camp

conducted in 2019-20 and same will be resumed in 2021

Additional three

drinking water

supply projects are

EIA Report

407 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

villages (iii) plantation by

engaging NGOs and drinking

water to nearby villages.

which could not be held in 2020 due to pandemic COVID-19

situation. (iii) Tree plantation is under execution through

contract. Paradip refinery has planted approximately 8 Lacs

trees since inception. (iv) Drinking water is being supplied

through tankers.

approved at cost of

Rs. 3.4 Crore for

execution over 2

years period.

He further requested that IOCL

should take up for establishment of

a super specialty hospital. He

supported the project with

conditions to fulfil the above.

At this moment IOCL has no plan for establishing any super

speciality hospital at Paradip. However, IOCL is providing

medical health services in nearby area villages GPs and

conducting medical camps at regular intervals.

Rs. 10.0 Lakh over 5

years for medical

camps and health

services.

11 Rabindra Majhi,

Jamihara Ekata

Mancha,

President from

Gandakipur

He supported the project with a

request to fulfil earlier

commitments made by IOCL.

Recruitment for permanent post in IOCL is done through open

competition and candidates are selected as per Corporation

recruitment policy.

For contractual engagement in various agencies working for

Paradip Refinery, are done by the agency itself based on their

requirement subject to meeting the requisite qualification and

skill.

As per RR Plan 2002, approved by RPDAC under the

chairmanship of RDC(C), Cuttack (Gov. of Odisha), for

Paradip Refinery project, there is no provision for any

preferential engagement at Paradip Refinery or in various

agencies engaged by Paradip Refinery except preference in

engagement of identified displaced persons who have not

taken cash grant in the above RR plan.

Various developmental activities e.g. providing drinking

-

EIA Report

408 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

water facilities, infrastructure developments, women

empowerment, organizing medical camps, community

development, promoting education, skill development

trainings, swachhta & conservation of environment etc. in

nearby GPs under CSR are being identified & finalized by

CSR team of Paradip Refinery in consultation with Dist.

Administration.

IOCL Paradip refinery has spent about Rs. 7.3 Crore during

FY 2019-20 under CSR programs in nearby GPs.

12 Bipin Kumar

Tripathy from

Mangarajpur

He supported the project with a

request that IOCL should consult

with more and more local people

of the area through CSR activities.

He further requested to complete

drinking water supply to his GP for

which Rs. 3 crores has already

been sanctioned.

Facilities under CSR program are being fulfilled as per the

discussions with local villages Gram Panchayats,RPDAC

recommendation and approval of District Administration.

IOCL CSR program facilities areexecuted accordingly.

Three drinking water

supply projects are

approved at cost of

Rs. 3.4 Crore for

execution over 2

years period.

13 Jogendra Tarai,

Mangarajpur

He supported the project with a

request to fulfil earlier

commitments made by IOCL.

Recruitment for permanent post in IOCL is done through open

competition and candidates are selected as per Corporation

recruitment policy.

For contractual engagement in various agencies working for

Paradip Refinery, are done by the agency itself based on their

requirement subject to meeting the requisite qualification and

skill.

As per RR Plan 2002, approved by RPDAC under the

-

EIA Report

409 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

chairmanship of RDC(C), Cuttack (Gov. of Odisha), for

Paradip Refinery project, there is no provision for any

preferential engagement at Paradip Refinery or in various

agencies engaged by Paradip Refinery except preference in

engagement of identified displaced persons who have not

taken cash grant in the above RR plan.

Various developmental activities e.g. providing drinking

water facilities, infrastructure developments, women

empowerment, organizing medical camps, community

development, promoting education, skill development

trainings, swachhta & conservation of environment etc. in

nearby GPs under CSR are being identified & finalized by

CSR team of Paradip Refinery in consultation with Dist.

Administration.

IOCL Paradip refinery has spent about Rs. 7.3 Crore during

FY 2019-20 under CSR in nearby GPs.

14 Dr. Ayeskant

Ray

He opposed the project and the

public hearing and blamed the

entire process of EIA. He

threatened to go on strike if the

project comes mentioning that

IOCL has failed to provide 33%

plantation as per EC conditions.

As per Paradip refinery project’s EC condition for green belt

(GB) development wason 580 acres land and green belt on the

same has been developed in full. Additional tree plantation

has been done on land in and around residential township,

along access roads, village schools, panchayats, coastal

villages etc. IOCL Paradip refinery till now has done

plantation of suitable species trees about 8.5 Lakh including

GB covering about 800 acres area. Further plantation of

100000 treesis under execution.

GB demarcated in google image Refinery layout enclosed as

Rs. 1.5 Crore over 2

years for tree

plantation.

EIA Report

410 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

Annexure-8.

15 Surendra

Mahanta,

He expressed that the project

should come and development of

the area should be done. However,

IOCL should consult more and

more local people examining their

demands and to fulfil them.

Facilities under CSR program are being fulfilled as per the

discussions with local villages Gram Panchayats,RPDAC

recommendation and approval of District Administration.

IOCL CSR program facilities are being executed accordingly.

-

16 Siba Charan

Biswal,

Paribesha

Surakhya Trust,

Paradeep

He supported the project and

emphasized to increase budget

provisions for improvement of

environmental status of Paradip

area.

IOCL Refinery has adequate budgetary provision towards

environmental work expenditure in year 2020-21 is Rs 30

Crore. IOCL investment about Rs. 3800 Crore is under

execution for BS-VI fuel Quality upgradation units.

New SRU for

environment

protection is under

executionat the cost

of 371 Crore.

He requested to maintain the road

connecting Zero point to

Atharabanki for minimizing traffic

congestion and air pollution.

As per resolution of the Environment Committee Meeting in

2019 chaired by District Magistrate & Collector, Major

industries of Paradip have been allocated the road zones for

cleaning and the road cleaning is being done accordingly.

Roads in Paradip area are being maintained by respective

authorities NHAI, SPWD and Paradip municipality.

Traffic management is carried out by the district

administration, traffic police.

IOCL Paradip Refinery has been cleaning the NH-5 road from

‘Zero Point’ to Dochakki engaging mechanized road cleaner

on regular basis.

Rs. 5.0 Lakh per

year for the road

segment cleaning.

He further appealed to start

construction of the proposed 8 lane

road from Paradip

Proposed 8 Lane highway is part of Paradip Port Area

Development Zone and concern authorities will do needful.

Project Proponent IOCL has no role for the highway

construction.

-

EIA Report

411 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

17 Sarat Kumar

Rout from

Paradeep

He questioned about the

authenticity of data mentioned in

the executive summary and asked

IOCL to clarify if entire the CSR

budget has been spent for

betterment homeless people of

Jagatsinghpur.

The query on authenticity of data is not relevant.

Paradip Refinery has undertaken the following activities

under the scope of CSR for the betterment of life of the

nearby villagers:

Providing drinking water facilities

Organizing medical camps and mobile medical units

Infrastructural developments such as construction of

concrete roads, toilet complex,

Promoting education by renovation of school building,

library, boundary wall, boys & girls toilets, distribution of

dual desk benches, UV water coolers & desktop

computers.

Skill development in association with NSDC & CIPET.

Women empowerment – improving income generation

capabilities of women through self-help group by

distributing sewing machines, waste paper recycling

machines. Few more machines have been planned for

distribution in FY 2021-22 which will create employment

opportunities and improve the livelihood of the women of

neighbouring GPs

-

He showed his concern about the

flame visible from the flaring stack

and its negative impacts on nearby

area including Bhitarakanika

Wildlife Sanctuary.

Flare is important integral part of safetydesignof a Refineryfor

safe operation. The flare ensures combustion,requisite

dispersion, improves environmental conditions and reduces

pollution. As per extant flare load, the radiation intensity is

miniscule about 0.001 KW/m2 which has almost nil impact in

comparison to solar radiation about 1.0 KW/m2.

Flare Detail:

-

EIA Report

412 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

Height: 131 m, Dia: 80 inch,

Location: Latitude 200 14’ 33.05” N& Longitude860 36’26.68” E

Exit flow Velocity: 0.15 m/s

18 Ohirendra

Biswal, Bagadia He expressed that he supports

industrialization in general but has

no hopes on commitments made by

IOCL.

For contractual engagement in various agencies working for

Paradip Refinery, are done by the agency itself based on their

requirement subject to meeting the requisite qualification and

skill.

As per RR Plan 2002, approved by RPDAC under the

chairmanship of RDC(C), Cuttack (Gov. of Odisha), for

Paradip Refinery project, there is no provision for any

preferential engagement at Paradip Refinery or in various

agencies engaged by Paradip Refinery except preference in

engagement of identified displaced persons who have not

taken cash grant in the above RR plan.

Various developmental activities e.g. providing drinking

water facilities, infrastructure developments, women

empowerment, organizing medical camps, community

development, promoting education, skill development

trainings, swachhta & conservation of environment etc. in

nearby GPs under CSR are being identified & finalized by

CSR team of Paradip Refinery in consultation with Dist.

Administration.

IOCL Paradip Refinery has spent about Rs. 7.3 Crore under

CSR in nearby GPs.

-

EIA Report

413 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

He further objected about not

conducting public hearing inside

nearby villages.

District Administration and Odisha SPCB has conducted

Public Hearing consultation at the suitable location

forcompliance to COVID-19 pandemic situation protocol and

guidelines for protection and safety of public in general.

-

He appealed before IOCL to take

care of the health of water, forest,

people, animals and agricultural

land failing which people will be

forced to go on strike.

IOCL works with sustainable development & operations with

continual environment improvement philosophy for better

life to own employees, stakeholders, associates and nearby

population.

IOCL has installed latest high efficiency Heaters Boilers with

Low NOx burners, uses very low Sulphur Fuel Gas (<150

mg/NM3), Fuel Oil (<0.50%) and BS-VI Diesel fuel. Modern

ETP of adequate capacity 1400M3/hr with matching RO

recovery plant has been installed to treat effluent water and

reduce discharge to minimum through re-use in refinery units

itself.

All requisite pollution control facilities has been provided &

mitigation measure being taken for prevention of

environmental air, water pollution with compliance to the

applicable statutory rules, regulations, specified limits.

Continuous monitoring of emission and treated effluent

discharge, ambient air quality through analyzers and

accredited agencies is being done. The quality parameters of

emissions, noise & effluent discharge are being maintained

within limits, monitoring report enclosed (Annexure-26).

Low Noise level equipments are installed with acoustic

enclosures for noise reduction. Noise level monitoring is

being done periodically and corrective action taken. Noise

Rs. 35 Lakh over 5

year for fulfilment of

community concern

development

EIA Report

414 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Issue Raised by Issue Reply by IOCL Paradip Commitment on

fund allocation

level report enclosed (Annexure-27).

IOCL is aware of corporate citizen’s role & responsibilities

take care of its surroundings. IOCL provide drinking water

supply, medical & health amenities, sanitation, education &

scholarship, skill development, self-employment assistance,

environment pollution control operations and monitoring etc.

to nearby population.

IOCL has spent about Rs. 30 Crore for environment control

operations and about Rs. 7.3 Crore under CSR program to

nearby areas, villages,gram panchayats (GPs).

EIA Report

415 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

7.2 Risk Assessment

The recommendations and mitigation measures of Risk Assessment will be implemented. The

impact contours will be kept within the refinery limit. Continuous onsite and offsite

emergency plan will be done in accordance with local district authorities. Periodic mock

drills will be conducted and any gaps if found will be addressed. Risk Assessment report is

attached as Annexure 10. Material Safety Data Sheet is enclosed in Annexure 12.and the

Disaster Management Plan is enclosed in Annexure 11. The certified EC compliance to

environmental conditions is provided in Annexure 2.

The following audits is being carried out periodically for environmental safety ,

Internal System Audit on Yearly Basis.

Internal & External Audit for OHSAS on Yearly Basis

Cross refinery safety & Environment Audit Yearly Basis.

External Safety Audit by OISD team once in Three Years.

Pre-commissioning Safety Audit for each New Facility.

Adequate ventilation will be maintained in the control room with a minimum of five to six air

changes per hour. Air intake to be properly located in line with OISD-STD 163. The latest

Cross-refinery safety & Environment Audit report is enclosed as Annexure 19 and the Latest

Daily Environmental Safety Report is enclosed as Annexure 21.

Following are the safety measures have been adopted in the plant.

1. Emergency isolation valves are provided with manual mode that will close them

immediately through push button located at a safe place and auto mode that will close them

immediately through gas/fire detector system.

2. The Vessels/ tanks are designed as per standards and corrosion protection is accounted in

the design.

3. Material of Construction of vessels is assumed to be suitable for the process conditions.

4. The facilities are well designed as per acceptable Indian / International codes & standards.

5. Inherent safety like appropriate equipment spacing as per OISD-118, Hazardous area

classification is considered.

6. Passive fire protection such as fire proofing shall be provided.

7. Appropriate detection measures such as fire and gas detectors are to be provided and

verified throughout the plant area.

EIA Report

416 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

8. Use of separate Fire and Gas PLC (programmable logic controllers) for operation of gas

detector and hardwiring of emergency switches for all new plants and facilities.

9. Inter distance Analysis for the facilities has been performed as per OISD standard and the

facilities are located safely. Overall Risk is in ALARP region and plant is equipped with

well-defined safety measures and no additional safety mitigation measures are recommended

7.3 Applicability of Environmental Clearance

List of latest and Existing Environmental Clearance obtained by MoEF & CC:

S. No MoEF File No Date of issue Status of Project

1 J-11011/70/2007-IA. II(I) 06-07-2007 Commissioned

2 11-86/2011-IA.III 21-02-2012 Commissioned

3 11-117/2009-IA-III 13-07-2012 Commissioned

4 11-33/2013-IA.III 19-09-2013 Commissioned

5 J-11011/395/2012-IA. II 18-09-2014 --

6 J-11011/395/2012-IA. II(I) 06-01-2015 Commissioned

7 11-30/2015-IA.III 11-02-2016 Commissioned

8 J-11011/344/2016-IA. II(I) 11-10-2018 Under Construction

9 J-11011/395/2012-IA II(I) - Applied now.

The existing refinery obtained several Environmental Clearances since 2007.Summary of

EC’s obtained enclosed as with latest EC obtained from MoEF vide: J-11011/344/2016-IA. II

(I) dated 11thOct 2018, enclosed as Annexure-2

7.4 Consent for Existing Operation

The existing plant is under operation with OPCB consent for Air and water obtained vide:

Ref No.- 5543/IND-I-CON-6414 dated 31.03.2021 valid till 31.03.2022 copy enclosed as

Annexure 3. PESO license obtained vide P/HQ/OR/15/1163 (P223845) dated 29.12.2020

Valid Up to: 31.12.2023 enclosed as Annexure-4.

EIA Report

417 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

7.5 TOR issued by MoEF

EIA Report

418 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

7.6 Copy of Standard TOR

EIA Report

419 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

EIA Report

420 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

EIA Report

421 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

EIA Report

422 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

EIA Report

423 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

EIA Report

424 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CHAPTER 8

PROJECT BENEFITS

EIA Report

425 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

8 PROJECT BENEFITS

8.1 Project Benefits

Importance of the project:

1. The project is of national importance and will reduce import dependence to the tune

of 1.2 million MT per year PTA product through domestic production and reduction

in foreign exchange outgo.

2. The project of Indian Oil is one of significant projects under the Govt. of India’s

“Make in India” Initiative for the Manufacturing Sector.

3. The proposed project is to meet the market potential having a deficit of about 2.2

MMTPA PTA in India by 2024.

4. An important project under the Petroleum Chemicals and Petrochemicals Investment

Region (PCPIR) in Odisha and spur industrial investment and development of the

region.

5. Expand Petrochemical Production footprint of Indian Oil, Paradip Refinery in Odisha.

6. The PTA plant project along with under construction MEG Plant at Paradip, will

accelerate the development of Textile Industry in the Eastern Region of India.

Leading to additional employment opportunities.

Benefits of the project:

1. The project will propel industrial development, downstream industry revolution in

Odisha and eastern regions of India, which will support consequential development of

entrepreneurship, MSMEs in nearby locality and state of Odisha.

2. The project will help India in attaining Self Sufficiency in PTA product demand as

feedstock for industries in value addition chain of products like Polyester fiber, Yarn,

Textiles, PET polymer production.

3. Employment opportunities about 5000 people directly /indirectly during construction

period and about 200 persons during Operating period.

4. The project will spur further investments in the downstream industries, Textile

Industries and provide better socio-economic benefits, direct and indirect employment

opportunities.

EIA Report

426 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

5. PTA is a non-hazardous, solid white powder, which is the preferred raw material and

the basic building block to produce Polyester Staple Fibre (PSF), Polyester Filament

Yarn (PFY), bottle and industrial grade polyester resin, polyester chips and so on.

6. PSF and PFY are substitutes for natural cotton and widely used for production of

textiles and garments. Eastern India does not have any economic size of PSF, PFY or

PET resin plants.

7. The first PTA plant at IOCL Paradip can provide steady supply of feedstock PTA to

PSF, PYF and PET resin plants. The polyester resins/chips can further be processed to

produce audio/ video tapes, x-ray films, photographic films, tapes, aseptic bottles for

packing mineral water, carborated drinks, vegetable oil, cosmetics, toiletries, tea,

coffee etc.

8. The above PP and PTA plant products shall be building blocks for envisaged Plastic

& Textile Park respectively in Odisha.

EIA Report

427 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CHAPTER 9

ENVIRONMENTAL COST AND

BENEFIT ANALYSIS

EIA Report

428 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

9 ENVIRONMENTAL COST AND BENEFIT ANALYSIS

This Chapter is not in Scoping Stage

EIA Report

429 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CHAPTER 10

ENVIRONMENTAL MANAGEMENT

PLAN

EIA Report

430 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

10 ENVIRONMENTAL MANAGEMENT PLAN

10.1 Introduction

This Environmental Management Plan (EMP) for Indian Oil Corporation Limited identifies

the principles, procedures and methods that will be used to control and minimize the

environmental impacts of the proposed minor construction and operational activities

associated with the revamp project. It is intended to ensure that commitments made by IOCL

to minimize project related environmental and social impacts are upheld throughout all

project phases.

As part of our ongoing commitment to excellence in environmental and social performance

we will ensure the following:

Fulfill all environmental conditions associated with project approvals.

Develop, promote and foster a shared sense of responsibility for environmental and

performance of the project.

Promote environmental awareness and understanding among employees and

contractors through training, identification of roles and responsibilities towards

environmental management and linking project performance to overall

environmental performance.

Monitor environmental performance throughout the project and implement an

adaptive management approach to continuous improvement and to meet the future

regulations.

10.2 Objectives of EMP

To suggest the formation of a core group (Environment Management Cell)

responsible for implementation of environmental control & protective measures as

well as monitoring of such implementation.

To ensure project components are compliant with all laws and approval conditions

Continue baseline monitoring

Facilitate a continual review of post construction and operation activities.

To suggest preventive and mitigation measures to minimize adverse impact and to

maximize beneficial impacts like

Preparation of afforestation or Greenbelt Development scheme.

EIA Report

431 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Preparation of rain water harvesting scheme and energy conservation actions

To prepare a capital cost estimate and annual recurring cost for Environmental

Management Plan.

To prepare a detailed action plan for implementation of mitigation measures.

Measure the effectiveness and success of proposed mitigation measures

10.3 EMP Structure and Organization

This EMP is designed as an overriding document in a hierarchy of control plans, and sets out

the overarching framework of environmental management principles that will be applied to

the project during preconstruction, construction and operation phase of the project.

The EMP contains guiding environmental principles and procedures for communication,

reporting, training, monitoring and plan review to which all staff, contractors and

subcontractors are required to comply with throughout the preconstruction, construction and

operation phases of the proposed projects.

Figure 10-1 Typical HSE Department Organogram

EIA Report

432 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

The EMP should also be considered as an overall framework document that establishes the

terms of reference for all project environmental and social sub-plans including the following:

Environmental Supervision Plan (construction);

Environmental Monitoring Plan (construction and operation); and

Social and Health Management Plan (construction and operation).

10.4 EMP Roles and Responsibilities

This section describes the organizational structure and responsibilities for implementation of

the EMP as shown below in Table 10-1

Table 10-1 Responsibility for EMP Implementation

S.No Organisation Responsibility

1 HoD, HSE Overall responsibility for environmental performance Decision-maker on applicable policies. Overall supervisory role during the construction phase Overall responsibility for EMP implementation during

the operating phase Responsible for changes to the EMP as part of an

adaptive approach to environmental and social management

EIA Report

433 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Organisation Responsibility

2 Sectional Head – Env., HSE

Develop an environmental unit, headed by the Project Environmental Officer to implement EMP responsibilities.

Oversight, implementation, monitoring and compliance of the EMP and any approval conditions, including construction supervision and performance of all staff, contractors and all subcontractors

Review of EMP performance and implementation of correction action, or stop work procedures, in the event of breaches ofEMP conditions, that may lead to serious impacts on local communities, or affect the reputation of the project.

Ensuring effective communication and dissemination of the content and requirements of the EMP to contractors and subcontractors

Assisting the contractor with implementation of EMP sub-plans

Ensuring compliance to all project social commitments, including implementation of corporate social responsibility.

Report environmental performance of the project directly to MoEF&CC

Report on environmental performance also to other government regulators as required.

3 SM / M, HSE Implementation of the Environmental Monitoring Plan during construction and operation.

Supervision of contractor performance of implementation of the Construction.

Reporting any incidents or non-compliance with the EMP to the PCB.

Ensuring adequate training and education of all staff involved in environmental supervision.

Making recommendations to the MoEF&CC regarding EMP performance as part of an overall commitment to continuous improvement.

EIA Report

434 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Organisation Responsibility

4 HoD, Project Department

Preparation and implementation of the Construction Management Plan

Prepare and maintain records and all required reporting data as stipulated by the EMP, for submission to the Supervising Engineer.

Ensure that all construction personnel and subcontractors are informed of the intent of the EMP and are made aware of the required measures for environmental and social compliance and performance

During construction, maintain traffic safety along access roads, with special emphasis on high trafficked areas

5 Independent Environmental MonitoringConsultant

Report to MoEF&CC on project compliance with environmental and social commitments in the EMP, EIA and other applicable standards.

10.5 Environmental Management Plan for Construction Phase

Environmental monitoring will be done during construction. The focus of monitoring during

the construction phase will be to implement systematic observations to periodically measure

the success of proposed mitigation measures and continue baseline data collection. The

majority of construction monitoring shall be done visually and verified by the Construction

Supervisor. Specific aspects to be addressed during construction include:

Air quality

Noise

Water quality and water resources

Solid waste

Land environment

10.5.1 Air Quality

There will be major construction activities for the project, civil work like foundation for new

vessels and supporting infrastructure for the new machineries will be carried out. During

construction activities, dust emission and emissions from the movement of vehicles and

construction activity is expected. However, following measures will be taken to reduce /

contain such emissions.

EIA Report

435 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Water will be sprinkled on inner roads to prevent re-suspension of dust into ambient

air due to movement of heavy vehicles etc.

Roads shall be kept free from mud, debris and other obstacles.

Separate civil construction material storage yard will be created within the site and it

will be enclosed.

Cement bags will be separately stored under cover in bales. Sand will be stacked

under tarpaulin cover.

Transport vehicles and construction equipment’s/ machineries will be properly

maintained to reduce air emissions.

All construction workers will be provided appropriate PPEs like dust mask, ear plug,

helmet, safety belt etc. and it will be mandatory for them to wear while entering the

site itself.

Increase signage and speed limit postings

10.5.2Noise Environment

Following measures are proposed during construction period to mitigate adverse impacts of

noise:

Construction activities will be done on round the clock basis.

All machineries to be used for construction purpose will be of highest standard of

reputed make and compliance of noise pollution control norms by this equipment’s

will be emphasized.

All construction workers working in high noise areas will be provided appropriate PPEs like

ear muffs and made to wear them during working hours.

10.5.3 Water Quality and Water Resources

Proper and sufficient sanitary facility will be created at the site in the form of Toilets

& existing ETP will be used for treatment of sewage generated.

The water resource will be provided from the existing facility.

10.5.4Solid Waste

Main solid waste generation during construction phase will be construction debris like

rubble, brick bats, debris, steel scrap, wooden scrap, sand, gravel etc. However, these

materials are inert in nature and will not result into leaching of any substance or its

constituent.

EIA Report

436 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

These materials will be carefully sorted and will be used within premises for filling of

low lying areas.

Wooden scrap, steel scrap will be given to authorized scrap dealers.

On completion of civil work, all debris etc. will be completely removed from site to

avoid any incompatibility with future use.

All the wastes will be stored at a designated site within the premises to prevent

scattered discharge on land.

10.5.5Land Environment

Top soil layers shall be stored for reclamation and re-vegetation and reforestation at

approved locations.

Existing storm water drainage facility will be used for disposal of storm water.

10.5.6Ecology

The Project site is present in existing area, there will not be clearance of land envisaged for

proposed projects and adequate measures will be taken to maintain the existing greenbelt area

of 580 Acres in refinery area while in total it occupies about 850acres of green belt. The

green belt occupies about 30.46% only.

10.5.7Socio Economic

There will be temporary employment for manpower required during construction phase

available from local communities. Overall socioeconomic effect of construction phase will be

positive due to direct and indirect employment opportunity and preference will be given to

the local communities as per IOCL Rules.

10.6 Environmental Management Plan for Operation Phase

Monitoring during the operation phase shall reflect those environmental and socio-economic

issues that may persist upon completion of construction activities. Monitoring shall focus on

evaluating the effectiveness of project mitigation measures and continue baseline monitoring

and sampling. The mitigation measures to prevent adverse impact during the operation phase

of the project shall focus on the following:

Air quality

Noise environment

EIA Report

437 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Solid and hazardous waste

Land environment

10.6.1Air Pollution Management

The air emission is controlled in PX-PTA complex by installing Online continuous emission

monitoring systems, use of clean burning fuel gas and natural gas, increased stacks heights,

installation of low NOx burners and floating roof in storage tanks for reduction of fugitive

emissions & hydrocarbon losses and to attain zero leakage status. For the proposed project,

IOCL Paradip allocates capital cost of INR 24.1 crores budget towards expenditure on stack

and APC equipments, along with the recurring cost of INR 2.57 crores for the same. Ambient

Air Quality is monitored both manually and continuous monitoring at AAQM stations in line

with the CPCB/MoEF&CC guideline

The gaseous emissions from the PX-PTA complex will be controlled to meet all the relevant

standards stipulated by the regulatory authorities. The Standards for Emissions from

Furnaces, heaters and Boilers is given in Table 10-3.

The flare losses will be minimized and monitored regularly.

PX-PTA Complex will install continuous emission monitoring systems for SOx NOx

CO and PM in major stacks with proper calibration facilities.

Paradip Refinery has adopted various measures for control of gaseous emissions. These

include:

Use of clean burning fuel gas and natural gas in PX-PTA unit.

Installation of low NOx burners in all the furnaces and boilers

Tall stacks for better dispersion of flue gases.

Online monitoring of SOx, NOx, CO and PM emissions from furnaces/boilers.

Monitoring of ambient air quality as per revised MoEF

Installation of internal floating roof with double seals in all Class-A tanks for

reduction of fugitive emissions.

Provision of mechanical seals in all the hydrocarbon pumps for reduction of fugitive

emissions.

Reduction of hydrocarbon losses and to attain zero leakage status.

Table 10-2 Proposed Pollution control scheme

S. Stack details Pollution control scheme

EIA Report

438 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

No

1. Tatory Furnace Installation of low NOx burners in all the

furnaces and boilers Adequate stack height APH will be provided

2. ISOMAR Furnace

3. XFU 1

4. XFU 2

5. Utility Boiler – 5 (Standby)*

6. Flare Tall flare stack for better dispersion of flue gases.

Storage vents:

7. Toluene day tank- 045-TK-001A Installation of floating roof with double seals for reduction of fugitive emissions

Provision of mechanical seals in all the hydrocarbon pumps for reduction of fugitive emissions.

All the proposed tanks are of Internal floating roof type minimizing the fugitive emissions in comparison to External floating roof tanks

All the tanks will be under Nitrogen blanketing

8. Toluene day tank- 045-TK-001B

9. Plant inventory tank- 044-TK-001

10. Paraxylene day tank- 049-TK-001 A

11. Paraxylene day tank- 049-TK-001 B

12. Desorbent storage tanks-049-TK-002

13.Plant inventory storage tanks- 049-TK-

003

14. Aromatic tank-048-TK-001

15.Light reformate storage tank-048-TK-

002

16. Isomer Regeneration Vent

Table 10-3 Standards for Emissions from Furnaces, heaters and Boilers

Sr.

No. Parameter

Limiting concentration in

mg/Nm3, unless

Existing

refineries

New refineries,

furnaces, boilers

1 Sulphur Dioxide (SO2) Gas firing 50 50

Liquid firing 1700 850

2 Oxides of Nitrogen (NOx) Gas firing 350 250

Liquid firing 450 350

3 Particulate Matter (PM) Gas firing 10 5

Liquid firing 100 50

4 Carbon Monoxide (CO) Gas firing 150 100

Liquid firing 200 150

5 Nickel + Vanadium (Ni+V) Liquid firing 5 5

6 Hydrogen Sulphide (H2S)

in fuel gas

Liquid/gas

firing 150 150

7 Sulphur content in liquid

fuel, weight %

Liquid/gas

firing 1.0 0.5

a) Fugitive Emission Control Measures

EIA Report

439 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Monitoring of fugitive emissions from IOCL, PDR complex with the help of VOC (Volatile

Organic Carbon), LDAR (Leak Detection and Repair) program is being done monthly with

the help of an external agency. Thus observed leaks are identified and rectified. And the

same will be continued after the proposed expansion.

10.6.1.1 Gaseous Waste Emissions

The atmospheric pollution generated from the ISBL Process Plant mainly comes from the

Process Inerts Vent (G1), PTA Day Silo A exhaust (G2), PTA Day Silo B exhaust (G3),

Offspec PTA silo exhaust (G4), and ISBL PSV Vent Scrubber Stack (G5). There are two

main exhaust treatments used in the PTA plant: catalytic oxidation and bag filtration. G1:

Process Inerts Vent The off-gas to the process vent stack comes from the oxidation reactor,

which contains various volatile organics such as benzene, methylbenzene, methanol, methyl

acetate, methyl bromide, and other volatile organic substances. After the dimethylbenzene

and acetic acid are recovered, most of the organic substances and methyl bromide contained

by the waste gas will be oxidized and decomposed via the high pressure catalytic oxidation

(CATOX) reactor. Low pressure vents requiring treatment, which include vent streams from

the Low Pressure Absorber, the PTA Vent Knock Out Drum, and the PTA Dryer Scrubber

vent, are treated in the Low Pressure catalytic oxidation system. The off-gas from the

CATOX reactor and the Low Pressure catalytic oxidation system is scrubbed for bromine

removal in the Process Vent Scrubber and combined in the Process Inerts Vent with the vent

of the Reverse Osmosis Purge Drum, and the vent of the liquid catalyst tank.

G2/G3/G4: Exhaust Gas from PTA Day Silo A, PTA Day Silo B, and PTA Off-Spec Silo

Off-gas after catalytic oxidation and bromine scrubbing is used for the conveying of PTA

product into the PTA day silos, and the off-spec silo. Because treated off gas is used for

conveying, it does not contain any volatile organic substances. The vent of the silos is treated

by a pulse bag-type dust removal system prior to discharging to the atmosphere, as it contains

a small quantity of PTA powder.

G5: ISBL PSV Vent Scrubber Stack

Many oxidation section relief valves are sent to the Ox unit PSV scrubber to reduce acetic

acid concentration of the streams that are sent to the scrubber during a release event. The vent

from the Ox Unit PSV Scrubber contains nitrogen sweep gas at a normal flow rate of 55

Nm3/h. The normal vent is pure Nitrogen, which contains no organic compounds. The

Gaseous Waste Emissions from PX and PTA Plant is given in Table 10-4 and Table 10-4

respectively.

EIA Report

440 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 10-4 Gaseous Waste Emissions from PX Plant

Unit Storage Tanks Amount Unit Frequency Pollutants Typical

Destination

Benzene-

Toluene

Fractionat

ing Unit

Toluene Day

Tanks (045- TK-

001A/B)

4.5 (Ton/

yr) Continuous

Volatile

Organic

Component

To

Atmosphere

Sulfolane

Plant Inventory

Tank 7.37

(Ton/

yr) Continuous

Benzene &

Toluene

To

Atmosphere

Vent from Ejector

Condensate Drum48-116

(Kg/

hr)

Reduced or no flow in

case of less/no air

leakage into the system

Benzene To Tatoray

Charge

Heater Toluene

Parex

Paraxylene Day

Tanks 12.7

(Ton/

yr) Continuous

Volatile

Organic

Component

To

Atmosphere

Desorbent

Storage Tank 13

(Ton/

yr) Continuous

Volatile

Organic

Component

To

Atmosphere

Plant Inventory

Storage Tank 13

(Ton/

yr) Continuous

Volatile

Organic

Component

To

Atmosphere

XFU

Aromatics Tank 29 (Ton/

yr) Continuous

Volatile

Organic

Component

To

Atmosphere

Light Reformate

Storage Tank 33

(Ton/

yr) Continuous

Volatile

Organic

Component

To

Atmosphere

Isomar

Regeneration

Vent Gas from

Separator

1400 (Kg/

hr)

Intermittent

(Once in

every four

to five year

for a period

of 4 to 5

days)

CO2 To

Atmosphere

EIA Report

441 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 10-5 Gaseous Waste Emissions from PTA Plant

No. Discharge

sources Pollutants

Major pollutants composition

Remark

Normal Concentration (mg/Nm3)

Normal Discharge rate (kg/h)

Maximum Concentra

tion (mg/Nm3)

Maximum Discharge rate (kg/h)

(Note 1)

G1 Process Inerts Vent

Discharge Rate (Nm3/h)

291400 292000

Note 2

Benzene 3 1 3.7 1.1

Toluene 4 1.2 6 1.8

Xylene 5 1.3 9 2.6

Acetic Acid 0.01 0.1 2 0.6

Methanol 1 0.4 5 1.5

Methyl acetate 20 5.8 80 23

Bromine 3 0.9 5 1.5

Methyl bromide

7 2.1 9 2.6

Carbon monoxide 37 10.8 40 11.6

G2/

G3

PTA Day

Silo A/B Discharge

Rate (Nm3/h)6700 (Note 3) 13400 (Note 3)

Bag

Off-Spec

PTA Silo

Benzene 3.5 0.02 3.5 0.04

Filtration

Toluene 4.1 0.03 4.1 0.04

Xylene 5 0.03 5 0.05

Acetic Acid 0.5 0.004 0.5 0.01

Methanol 1.4 0.01 2.1 0.02

Methyl acetate 20 0.14 41 0.44

Bromine 3 0.02 3 0.03

Methyl bromide

7.2 0.05 7.2 0.08

Carbon monoxide 41 0.28 41 0.28

PTA dust 20 0.13 20 0.13 Note:

1. The duration for the high case is typically one hour at a frequency of two to four times

per year.

2. The normal case is assumed that the off-spec PTA recycle system is not in service.

The Max case is max emissions from the PTA day silos during transfer between PTA

day silos and the off-spec PTAsilo.

EIA Report

442 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

3. HP Catalytic oxidation treatment and bromine scrubbing of the oxidation off gas. LP

catalytic treatment of the discharge gas from the Low Pressure Absorber, Purification

Vent Scrubber and Purification Dryer Scrubbervent

10.6.2Waste Water Management

a) Existing

Approx. 1082.1 m3/hr of effluent is generated in the existing facility of which 190.88 m3/hr

rejects from RO is disposed to Deep Sea, 50 m3/hr rejects from RO is sent to Coke Dust

Suspension and 50 m3/hr rejects from RO is sent to Coke Cutting. The Sludge created during

the treatment of about 32.46 m3/hr along with a water loss of about 10.76 m3/hr. Remaining

748m3/hr from RO is reused back in the system for DM Water Makeup.

b) Proposed

In the proposed expansion Approx. 408 m3/hr of effluent is generated in the proposed facility

of which 78% of effluent is processed in RO plant and its rejects of 86.18 m3/hr is disposed

into deep sea. The Sludge created during the treatment of about 12.24 m3/hr along with a

water loss of about 4.08 m3/hr. The remaining RO processed water of 305.5 m3/hr is reused

back in the system for DM Water Makeup and cooling tower. New ETP is proposed for

installation to process effluent @ 408 m3/hr with 10% design Margin (Maximum capacity

with high TOC).

The Waste Effluents from PX Plant is given in Table 10-6.

Table 10-6 Waste Effluents from PX Plant

Liquid Stream

PX Process Unit No

Amount m3/hr

Service FrequencyContaminants

Typical Destination Content ppm

Waste Water from Reformate Splitter Receiver During clay treater dry out

Xylene Fractionation Unit No 048

Avg :0.268

Intermittent

Once in every six

months for period of 2 or 3 days)

Benzene 2000

Pre- Treatment

Toluene 700

Xylenes Trace

Waste Water from Benzene- Toluene Column no1 Receiver Boot

Benzene- Toluene Fractionator Unit -045

Avg: 0.03

Continuous

Continuous Benzene 2200 Pre-

Treatment

Waste Water from Benzene- Toluene Column no1 Receiver Boot during clay Treater Dry

Benzene- Toluene Fractionator Unit -045

Avg: 0.05

Intermittent

During dryers once in 6 months

Benzene 2200

Pre- Treatmen

t

Toluene -

Xylenes -

EIA Report

443 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Liquid Stream

PX Process Unit No

Amount m3/hr

Service FrequencyContaminants

Typical Destination Content ppm

out Waste Water FromBenzene- Toluene Column no2 ReceiverBoot

Benzene- Toluene Fractionator Unit -045

Avg:0.02

Continuous

Continuous

Benzene 2200 Pre-

Treatment

Toluene -

Xylenes -

Waste Water from Ejector Condensate Drum

Sulfone Process Unit (Extractive Distillation) Unit-044

Avg: 0.36 (Design)

Continuous

0.05 m3/hr in case of

no air leakage into the system.

Benzene 2200 Pre-

Treatment

Toluene 750

Xylenes -

Solvent Regenerator Bottom (pH varies according to dilution)

Sulfone Process Unit (Extractive Distillation) Unit-044

2 m3 Intermittent

Frequency –2 times/ year

(Note-2)

Sulfolane 20-70 % (wt)

Diluted with Water and collected Drums and sent to pre- treatment

Aromatics 0-10 (Wt%)

Hydrocarbon- Polymer

5-15 (wt%)

Inorganic Solids

(Note-1)

2-10 (wt%)

Water Balance

Raffinate Column no-1 Receiver and Raffinate column no1 vent Drum Waste Water

Parex Process Unit

-049

Avg 0.0696

(6~ 8pH)

Intermittent

As per process requirement

Benzene - Pre- Treatment

Toluene - Xylenes -

Finishing column Receiver Waste Water

Parex Process Unit

-049

Avg :0.0450

(6~ 8pH)

Intermittent

As per process requirement

Benzene - Pre- Treatment

Toluene - Xylenes -

Desorbent Rerun Column Bottoms

Parex Process

Unit -049

Avg: 0.908

Intermittent

Once in every six months

Hydrocarbon 100% Desorbent Rerun Column Bottom is removed on a batch basis every one to two weeks and disposed of by sending to slopstank

Benzene Nil

Clay Treater Dry Out Water from Decheptanizer Receiver ( 6 ~ 8 pH)

ISOMAR Process Unit- 050

Avg : 0.455

Intermittent

One every six months for a period of three to four days

Benzene 1700 Pre- treatment

Toluene 700

Xylenes 400

Laboratory Effluent

-- Avg: 0.2 m3

Intermittent

Based on testing

Benzene 2200 Pre-

treatment

Effluent during

-- Avg: 1 m3/hr

Intermittent

During shutdown

Benzene/ Aromatics

2200 Pre-

treatme

EIA Report

444 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Liquid Stream

PX Process Unit No

Amount m3/hr

Service FrequencyContaminants

Typical Destination Content ppm

Shutdown nt Effluent from Paved Area during dry weather condition

-- Avg ; 50 m3

Intermittent

Based on weather

condition

Benzene/ Aromatics

2200 Pre-

treatment

Regeneration Spent Catalyst

ISOMAR Process Unit-

050

Avg: 6.0m3/h

Intermittent

For twenty hours during

Catalyst Regeneratio

n

Sodium Bicarbonate

71000

ETP Sodium Chloride

83000

Water Balanc

e

Table 10-7 Waste Effluents from PTA Plant

S.No.

Sources of wastewater

Normal Flow rate

of wastewate

r (m3/h)

Maximum Flow rate

of wastewate

r (m3/h)

Peak [Duration]

m3/hr

Discharge frequency

Pollutants composition

(mg/L)

1

Process wastewater from RO Purge Drum

79 79 170 Continuous

TOC: 7500 -9500

COD:20000-

25000 pH:4-6

2

Process wastewater from PTA Vent Knock-out Drum

0 0 160 Intermittent (for 2 hrs))

TOC:20000 -30000

COD:65000-

75000 pH:4-6

3

Intermittent process wastewater from ISBL Sumps

63 -

133 [TAR for 72 hrs] (Note 2) 1636 (Note 1) 114 [Process Upset for 72

hrs]

Intermittent

TOC:2500 –

5000 COD: 7000-

15000 SS: 500 -

2000 Co:20 – 40

Mn:10 – 20

pH:4 - 10

Note:

1.The flow rate of 1636 m3/hr is an assumed maximum case for fire water. The maximum

flowrate shall be no less than max hourly rainfall across the ISBL curbed area (1500 m/hr;

125 mm/hr), TAR peak flowrate, and Process Upset peak flowrate even if the firewater case

is less than this max.This water will be routed CRWS pond. Effleunt from CRWS pond will

be treated in ETP. 20% magin shall be considered over peak flowrate as part of desing

2. Frequency not more than one event per 30-day period.

EIA Report

445 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Table 10-8 Liquid Waste Effluents from Offsite and Utilities

S.No. Source Value-m3/hr

Frequency Destination Composition

1 Cooling tower

blow down 221.67 – 236.96

Continuous Tertiary treatment

through SSF backwash pit

2 Side stream

filter 18 Intermittent -do- Water

3 Oily Drain - Intermittent ETP through oily

water network

Water containing oil from pump area, Oil contain shall be 0-1000 ppm and oil and grease -12500

ppm4 Storm water - NNF Storm Sewer Water

10.6.3Solid Waste Management

Mainly four types of solid wastes are generated in the Refinery and its townships; namely

oily sludge, biological sludge (from the biological treatment of the wastewater), other

industrial solid wastes (intermittent) and the domestic solid wastes. The oily-sludge and spent

catalyst of PX are the hazardous wastes generated in refinery operations.

Oily sludge is generated mainly during cleaning of storage tanks and from ETP. Mechanical

extraction method uses solvent & steam heating and then oily sludge is processed in a plant

equipped with centrifuge in order to recover maximum possible oil and water. The sludge is

broken down into water, oil and base sediments. Water is drained into ETP for further

treatment while the recovered oil is pumped into slop oil tanks for reprocessing in the

refinery. The base sediment (residual oily sludge) in solid state has an oil content of around

3-8%wt and is disposed through bioremediation facility inside the refinery.

One-time Catalyst is generated whenever the activity of catalyst is reduced to such a level

that further plant operation is not possible. These catalysts are stored in drums and are

disposed off suitably.

Kitchen wastes are generated in every household of the township. Also canteen wastes are

generated in refinery. Both these waste are collected and processed in Organic Waste

Convertor.

Waste batteries/Spent catalyst generated and returned back to manufactures/vendors under

buyback scheme.

Metal waste and drum waste generated are disposed suitably.

EIA Report

446 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

For the proposed project, IOCL Paradip allocates the recurring cost of INR 0.1crores budget

towards expenditure on solid waste management. Spent Catalyst after every 4-5 years will be

duly recovered by PCB approved agencies

10.6.4Noise Environment

To contain to the sound pollution in the vicinity of the plant site, all noise making equipment

are specified with maximum noise generation upto 85 db (A). Only in some areas like

Process Air Compressor House, where the sound level is expected to be higher (>90 dbA),

suitable acoustic treatment will be provided along with mandatory use of ear plugs.

Comprehensive measures for noise control will be followed at the design stage in terms of

Noise level specification of various rotating equipment as per Occupational Safety

and Health Administration (OSHA) standards.

Equipment layout considering segregation of high noise generating sources.

Erecting suitable enclosures, if required, to minimize the impact of high noise

generating sources.

Sizing the flare lines with low Mach number to have lower noise levels.

Green belt of appropriate width all around the refinery towards noise attenuation

10.6.5Material Handling Storage and Transportation

Hazardous chemicals are stored in closed tanks and drums with appropriate

blanketing systems.

All transfers from drums / tanks are being done through pumps in closed pipelines.

The loading of finished products to trucks and drums is done through automated

filling systems with overflow protections.

All key raw materials are charged to the reactors through closed pipeline systems

including pneumatic systems for solid handling.

Raw materials/ intermediates/ products are stored in closed tanks/drums provided with

breather arrangements to avoid fugitive emissions.

The Mode of Transport for Product materials is given in Figure 10-2 and the Raw Material

Storage and Dispatch Facilities is given in Table 10-9.

EIA Report

447 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 10-2Mode of Transport for Product materials

Table 10-9 Raw Material Storage and Dispatch Facilities

S.No Feed /Product/ Intermediate

Source Destination Remarks /mode of Receipt/

dispatch

FEED

1 Reformate PDR CCRU /

Storage Tank PX Unit Interconnection pipe (Tie- in)

2 Acetic Acid OSBL PTA unit Tanker Unloading

PRODUCT

3 Paraxylene PX Unit PTA Unit Interconnection pipe (Tie- in)

4 Toluene PX Unit Merchant Sale Merchant sale by Tanker

Loading

5 PTA bulk Silo PTA Unit Merchant Sale Merchant sale by Truck and

wagon LoadingINTERMEDIATE

EIA Report

448 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Feed /Product/ Intermediate

Source Destination Remarks /mode of Receipt/

dispatch

6 TA Mother Liquor Storage tank PTA Unit Interconnection pipe (Tie- in)

7 Raffinate PX Unit MS Blend

Unit

Interconnection pipe (Tie- in)

8 Heavy Reformate PX Unit MS Blend

Unit Interconnection pipe (Tie- in)

Pipeline crossing Santra Creek for the Proposed PX PTA project

1 Fire Water South part of

refinery

North part of

refinery Pipe line crossing santara creek

2 Cooling tower

make up

South part of

refinery

North part of

refineryPipe line crossing santara creek

3 DM Water South part of

refinery

North part of

refineryPipe line crossing santara creek

4 Instrument Air South part of

refinery

North part of

refineryPipe line crossing santara creek

5 Plant Air South part of

refinery

North part of

refineryPipe line crossing santara creek

6 Steam Condensate

out

South part of

refinery

North part of

refineryPipe line crossing santara creek

7 Boiler BlowDown South part of

refinery

North part of

refineryPipe line crossing santara creek

8 BFW(MP) South part of

refinery

North part of

refineryPipe line crossing santara creek

9 MP Steam Export South part of

refinery

North part of

refineryPipe line crossing santara creek

10 HHP Steam South part of

refinery

North part of

refineryPipe line crossing santara creek

11 Fuel Gas South part of

refinery

North part of

refineryPipe line crossing santara creek

12 Fuel oil South part of

refinery

North part of

refineryPipe line crossing santara creek

13 Closed Blowdown

and Hydracarbon

South part of

refinery

North part of

refinery

Pipe line crossing santara creek

Pipe line crossing santara creek

14 Hydrogen South part of

refinery

North part of

refineryPipe line crossing santara creek

15 Raffinate South part of

refinery

North part of

refineryPipe line crossing santara creek

EIA Report

449 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.No Feed /Product/ Intermediate

Source Destination Remarks /mode of Receipt/

dispatch

16 Reformate South part of

refinery

North part of

refineryPipe line crossing santara creek

10.6.6Green Belt Development

A comprehensive green belt development plan was prepared for the refinery in consultation

with eminent ecologist and consequently, a large number of trees were planted inside the

refinery premises to enhance the aesthetic look of the refinery as well as to serve the purpose

of a pollution sink. Utmost priority is given to the Tree plantation activity, which is

undertaken on a regular basis both inside the refinery premises and in township.

EIA Report

450 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 10-3 Green Belt Photographs

19.06.2021 19.06.2021 19.06.2021

19.06.202119.06.2021

19.06.2021

EIA Report

451 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

To maintain eco-friendly environment in and around its premises, Paradip Refinery developed an

ecological park in an area of approximately 2,30,000 m2

Figure 10-4 Ecological park in Paradip Refinery

10.6.7Rain Water Harvesting Plan

Paradip Refinery, being a coastal location, water table is very high. Ground water recharging

with rain water harvesting (RWH) system is not suitable for this region. Therefore, Rain

water harvesting systems have not been constructed at Paradip Refinery & Township.

However, two nos. of storm water reservoirs had been constructed in the Refinery premises to

recieve storm water to use in refinery. Two nos. storm water ponds developed in ECO park

and harvested storm water is used in horticulture in place of fresh water. Two (02 nos) storm

water reservoirs (Capacities: 2,96,000 KL and 3,13,000 KL) have been developed to store

rain water in monsoon in the refinery premises. The Storm water pond for collecting surface

runoff inside Refinery is given in Figure 10-6. The Rain water harvesting integrated with

ecological park is given in Figure 10-5

.

19.06.2021

19.06.2021

EIA Report

452 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 10-5 Rain water harvesting integrated with ecological park

25.04.2020

EIA Report

453 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 10-6 Storm water pond for collecting surface runoff inside Refinery

19.06.2021

19.06.202119.06.2021

EIA Report

454 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

10.7 Occupational Health and Safety

The workers are provided with proper health and safety measures. Personal protection

equipment’s are given to the employers and made sure they wear it during the work. Regular

health camps are conducted for all the workers alike. The Health & Safety department makes

sure all the workers are not exposed to any kind of toxicity and is within the prescribed limit.

Copy of EHS policy enclosed as Figure 10-8; Organogram for OHC is given in Figure 10-7.

The main objectives are

1. Maintenance and promotion of workers’ health and working capacity.

2. Improvement of working environment by following well-being program for its

employees.

3. Monitor the workplace to maintain industrial hygiene practices.

4. Development of work culture in a direction which will support health and safety at work

and thereby promoting positive social climate for smooth operation that will enhance

productivity.

5. Area monitoring.

6. Employees to undergo annual health check-up.

7. All personnel will be provided with personal protective equipment’s individually as

required.

a) Construction Phase

During the construction phase the following measures will be employed;

1. Personal Protective equipment’s will be provided to the workers.

2. Occupational Health Centre will be facilitated to address the emergencies that may arise.

3. Personnel will be trained about firefighting systems and first aid practices.

4. Regular monitoring of occupational health of employees.

b) Operational phase

General functions of the safety committee will be;

1. Conduct routine workplace inspections.

2. Provide Personal Protective Equipment.

3. Develop and implement safe work procedures and rules.

4. Provide on-going safety training & Enforce safety rules and appropriate discipline.

EIA Report

455 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

5. Promote safety awareness and reduce the potential for injury/loss.

6. Identify workplace hazards.

7. Enforce of safety rules, measure safety performance & reduce frequency/severity of

injuries.

c) First aid Boxes

A first aid kit is a collection of supplies and equipment for use in giving first aid. First Aid

boxes will be kept available in Security Room, Admin Block and at OHC. First Aid items

will be issued to injure only by authorized persons.

Following are the contents of First Aid Box,

a.Dettol – Antiseptic solution

b. Ciplox – Eye Drops

c.Soframycin – Skin ointment

d. Silverex – Burn ointment

e.Betadine – Microbicidal solution

f. Iodex – Pain reliever

g. Sterilized Cotton Wool

h. Surgical Paper Tape

i. Small Sterilized Dressings

j. Medium Sterilized Dressings

k. Roller Bandage – 5 cm wide

l. Roller Bandage – 10cm wide

m. Band Aid

n. Crocin / Paracetamol Tablet

Along with the above safety systems, company also ensured the below safety features to

ensure Zero Accident.

1. No ignitable zones are declared and marked so.

2. Work permit system with strict compliance.

3. Dedicated chemical storage area with good ventilation and exhaust system and all

chemical are stored as per compatibility.

4. Dyke walls provided for the day storage chemical tanks.

EIA Report

456 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

5. All reactors provided with safety valves followed by rupture discs and relief valve outlets

are extended.

6. Calibration is ensured for the gauges of pressure, temperature and vacuum.

7. All reactors will be hydro tested and certified by the competent person once in a year.

8. Body earthing provided to all equipment’s involved in the process, electrical earthing,

static earthing and instrument earthing provided wherever required.

Ventilation air units (VAUs) and Exhaust air units (EAUs) and are provided to ensure good

ventilation in the work environment. The tentative Emergency Organization Chart will be

prepared and followed.

Figure 10-7 Organogram for OHC

10.7.1 Safety Measures

The highest standards of safety are being implemented by examining the potential hazards,

accessibility, constructability, operability and maintainability to ensure a safe and

environmentally sound plant and facilities.

Eye-wash and safety showers are provided in all appropriate locations.

All hazardous and hydrocarbon drains are routed to closed systems.

Definition of environmental requirements, Noise studies and associated

recommendations, Dispersion calculations and associated recommendations.

EIA Report

457 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Escape Routes, Accessibility, Operability and Constructability reviews and

implementation of recommendations.

All safety requirements of Indian Boiler Regulations (IBR) will be complied in the

design.

Fire water sprinkler systems will be implemented for applicable equipment, as per

OISD code requirements.

Safety insulation is provided for all pipes/surfaces operating at temperature higher

than 60°C.

Pressure safety valves are provided for over-pressure protection of equipment and

piping in all applicable locations.

Double isolation valves are provided for high pressure streams and hydrogen services.

HAZOP study has been performed for PX-PTA units during FEED phase. HAZOP

recommendations from the HAZOP study shall be incorporated into the design of

these systems.

Detailed HAZOP and SIL study for all units are envisaged during detailed

engineering phase of the project. All HAZOP recommendations will be complied and

recommendations from the studies will be implemented.

Compliance to all National and Local rules and regulations by statutory bodies will be

ensured.

10.7.2 Precaution & Safety Measures Against Fire Hazards

IOCL has taken lot of safety measures against Fire hazards in course of the design &

operation of two plants. They are as follows:

N2 Blanketing in flammable storage tanks.

Breather Valves.

Earthing Continuity.

Lightening Arrester as per IS specification & monitoring of Earth Pit.

Flame proof electrical fittings.

Periodic Tank Inspection.

Storage & handling of Bulk Chemicals & Plant Operations through DCS System.

Periodic Checking of Critical Instruments.

In addition to the above measures the new technology has the following measures embedded

in its design- following are the safety measures in the proposed PX-PTA unit:

EIA Report

458 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Process Design and Engineering is such that it can cater to any emergency

happening in the Plant.

Provision of nitrogen blanketing of the reactor on occasion of a reactor trip.

Critical trips are implemented in the system

Better Process Control System.

Safety Critical Alarms are implemented for the new unit.

Automated Safety Instrumented System.

Over/Under Pressure Relief Protection.

Overfill Containment.

Emergency Response.

10.8 Environmental Management Cell

A separate environment management cell, HSE department consisting of qualified engineers

is in place which monitors all aspects of environmental impacts being caused due to process

units at IOCL, Paradip Refinery.

10.9 Corporate Environmental Policy

The safety policy of PDR is given in Figure 10-8

EIA Report

459 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Figure 10-8 EHS Policy

EIA Report

460 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

10.10 Budgetary Provision for Environmental Management Plan

IOCL PDR allocates budget every year towards expenditure of environment related jobs.

Below is the budget allocated for the year 2019-2020:

S.

No.Description

Capital

Cost in

Crores

Recuring

Cost, in

Crores

1. Air Pollution

i.Stack 22.4 2.4

ii.APC equipments 1.7 0.17

2. Water Pollution

i.ETP 336 3.9

3. Noise Pollution

i. Acoustic enclosure 1.7 0.17

4. Solid Waste management - 0.1

5. Storm Water management/ Rain water harvesting - -

6. Green belt development 3 0.3

Total 364.8 7.04

10.11 Corporate Social Responsibility

CSR activities shall be carried out as per corporation’s CSR policy. Existing activities and

spending for the Period 2019 -2020 enclosed as Annexure 18.

10.12 Corporate Environmental Responsibility (CER)

The company is aware of the obligations towards the Environment and to fulfill the social

obligations. As per OM F. No: 22-65/2017-IA.III dated 1st May 2018 M/s IOCL will

Allocate 0.125% of the project cost (11783 Crores) towards CER i.e. 0.125% of 11783

Crores = 14.73 Crores. As per CEPI compliance for SPA 1.5 times of slab to be allotted(1.5

* 14.72)=22.093 Crores. The detailed CER cost breakup is given below

EIA Report

461 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S.

NoFocus Areas

Amount (INR)

Total

2021-22 2022-23 2023-24 2024-25 2025-26

1. Plantation

Rs.

50,00,000

Rs.

75,00,000

Rs.

75,00,000

Rs.

50,00,000

Rs.

50,00,000

Rs.

3,00,00,000

2.

Environment Improvement -

Mechanised cleaning

facility for roads of nearby

localities

Rs.

30,00,000

Rs.

30,00,000

Rs.

35,00,000

Rs.

35,00,000

Rs.

40,00,000

Rs.

1,70,00,000

3. Swachh Bharat - Public

Toilets, Sanitisation activities

Rs.

45,00,000

Rs.

70,00,000

Rs.

70,00,000

Rs.

50,00,000

Rs.

50,00,000

Rs.

2,85,00,000

4.

Usage of renewable energy-

Solar lanterns, Solar lighting

power, Paper recycling

equipments

Rs.

25,00,000

Rs.

30,00,000

Rs.

40,00,000

Rs.

30,00,000

Rs.

25,00,000

Rs.

1,50,00,000

5.

Clean drinking water supply

projects - Piped supply

projects, Bore wells, Through

tankers

Rs.

60,00,000

Rs.

75,00,000

Rs.

65,00,000

Rs.

70,00,000

Rs.

60,00,000

Rs.

3,30,00,000

6.

Other activities under CER

based on the approval of

Rehabilitation & Periphery

Development Advisory

Committee (RPDAC) under

the Chairmanship of District

Collector

Rs.

1,46,14,500

Rs.

2,43,57,500

Rs.

2,43,57,500

Rs.

2,43,57,500

Rs.

97,43,000

Rs.

9,74,30,000

Total Rs.

3,56,14,500

Rs.

5,23,57,500

Rs.

5,28,57,500

Rs.

4,78,57,500

Rs.

3,22,43,000

Rs.

22,09,30,000

EIA Report

462 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CHAPTER 11

SUMMARY & CONCLUSION

EIA Report

463 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

11 SUMMARY & CONCLUSION

An Environmental Impact Assessment Study has been carried out and assessed for the

proposed project based on the ToR and baseline quality data collected for the study area.

Identification and anticipation of the potential environmental impacts due to the proposed

project with a delineation of appropriate impact mitigation measures in an Environmental

Management plan during both construction and operation phases is provided in the EIA

report prepared

Based on the above evaluation the significance, value addition, impact on various

components of environment during construction and operation phases is summarized below;

Paradip Industrial area attracts CEPI score of 60.61(SPA) and IOCL will comply the

CEPI guidelines by MoEF&CC.

The Project Proponent will follow all the statutory norms and guidelines as per

CPCB/MoEF&CC to safeguard environment.

No land acquisition is carried out since the existing land area is used for proposed

expansion.

The incremental concentrations of PM, SO2, NOx and CO are observed to be 0.10%,

7.39% 19.59% and 157.38% respectively. The total pollutant concentrations of PM,

SO2, NOx and CO are 95.7 µg/m3, 16.86 µg/m3, 35.95 µg/m3 and 128.69 µg/m3 ,

which is observed to be within NAAQ standards

On total 3743 m3/hr of fresh water requirement for the project which is sourced from

Mahanadi River. The approval for extraction of fresh water is 3950m3/hr which is

issued by Government of Odisha & valid upto: Oct 2021.

The wastewater generated in the Refinery complex will be treated in ETP, part of

treated effluent will be reused in the process and the balance will be disposed to

marine with compliance to CPCB/MoEF&CC norms for marine disposal.

On total, 277.06m3/hr will be discharge into deep sea and it is observed to be within

the discharge approval limit of 350 m3/hr as per the OPCB consent for Air and water

obtained vide:5543/IND-I-CON-6414 dated 31.03.2021 valid till 31.03.2022.

The Hazardous waste generated like Spent Catalyst is being stored in intermediate

storage facility (covered warehouse with impervious floor and shed) and disposal in

SLF & Co-processing in cement industry within 90 days.

EIA Report

464 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Project site is located at seismic zone-III and Paradip coast is prone to Cyclone and

Tsunami and IOCL will ensure all these scenarios are considered in designing.

There are two Schedule-I sensitive Species in study area i.e., reptiles named

Nilssoniahurum(Gray 1831) and Lissemyspunctata (Bonnaterre 1789) habitats and

IOCL will develop biodiversity management plan in accordance with local forest

department recommendations and ensure there is no impacts on this species.

Action plan for conservation of Marine life including Olive Ridley Turtle has been

prepared in 2013 by Mangrove Forest Division (Wildlife), Rajnagar, Odisha and

approved by Principal Cheif Conservator Forest(WL) & CheiWildlife Warden,

Odisha. The fund allocation by IOCl of INR 20.04Cr.for the conservation of Marine

life over a period of implantation of 10yrs

The protected area Mahanadi Delta has extensive mangrove forests located at a

distance ~6.93km (NE) from the project site and IOCL will develop biodiversity

management plan in accordance with local forest department recommendations and

ensure there is no impacts on mangroves.

The Kujang Coast and Hetamundia Seashore Village is predominant turtle nesting

area and IOCL will develop biodiversity management plan in accordance with local

forest department recommendations and ensure there is no impacts on this species.

Mangroves are present in Santara creek which bifurcates the refinery into North &

South parts and IOCL will develop biodiversity management plan in accordance with

local forest department recommendations and ensure there is no impacts on

mangroves.

Defence installation of Coast Guard Dist. HQ is present at a distance of ~4.11km from

the project site in ENE direction and if required NOC will be obtained from them.

The above project is proposed to meet the market potential having a deficit of about

2.2 MMTPA PTA in India by 2024.

The project will propel industrial development, downstream industry revolution in

Odisha and eastern regions of India, which will support consequential development of

entrepreneurship, MSMEs in nearby locality and state of Odisha.

The project will induce direct & indirect employment generation for local

communities as well as state & region as a whole and preference will be given to the

local communities within IOCL Rules/Policy.

EIA Report

465 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

CHAPTER 12

DISCLOSURE OF CONSULTANTS

EIA Report

466 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

12 DISCLOSURE OF CONSULTANTS

In order to assess the potential environmental impacts due to the proposed Integrated Para-

Xylene & Purified Terephthalic Acid (PX-PTA) Project, M/s IOCL, PDR has engaged

Hubert Enviro Care Systems (P) Limited, Chennai to undertake EIA study. The nature of

consultancy service rendered covers terrestrial environmental assessment.

12.1 Brief Profile of Hubert Enviro Care Systems (P) Limited (HECS)

Enviro Care Systems was started in the year of 1997 by Dr. J.R.Moses with the vision to

serve the world in all environmental related problems by completing the latest technological

advancements available.

In the year 2004, Enviro Care Systems became Hubert Enviro Care Systems (P) Ltd after

having collaboration with Hubert Stavoren B.V. for higher Technology.

The company provides total pollution control solutions to several industries like Thermal

Power Plant, Pharma, R&D Facilities, Electroplating and Manufacturing, IT Parks,

Residential Complexes, Dairies, Food Processing, Textile mills, Breweries, etc.

The company is specialized in executing projects right from concept development, supply,

erection, commissioning and operation on turnkey basis. HECS has successfully executed

more than 200 environmental engineering projects for various industrial sectors both in India

and overseas.

HECS has state-of-art facilities to provide quality environmental consultancy and engineering

solutions.

Strengths of HECS

Number of Employees as on May 2021

Total No of Employees 1096

Consultancy 43

Laboratory 125

Projects 34

Operation & Maintenance 894

EIA Report

467 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

Declaration of Experts contributing to the EIA

I hereby certify that I was involved in the preparation of EIA/EMP for the “Integrated Para-

Xylene & Purified Terephthalic Acid (PX-PTA) Project” at Abhaychandrapur village,

Jagatsinghpur District, Odisha State by M/s. Indian Oil Corporation Limited as EIA

Coordinator with the support of the following Functional Area Experts.

EIA Co-ordinator

Name: Dr. J R Moses

Signature:

Date:24-06-2021

Contact Information:

Hubert Enviro Care Systems (P) Ltd.,

# A-21, Phase III, Behind Lions Club School,

Thiru-vi-ka Industrial Area, Guindy,

Chennai –600032.

Tamil Nadu, India.

Email: [email protected]

Website: www.hecs.in

Functional Area Experts (FAEs):

S. No.

Functional Areas

Name of the Expert Signature Duration of Involvement

13. AP FAEDr. J R Moses

Sep 2018 till date

Mr. Vamsee Krishna Navooru Sep 2018 till

date

14. AQ FAE Dr. J R Moses Sep 2018 till

date

15. WP FAE

Dr. J R Moses Sep 2018 till

date

Mr. Vamsee Krishna Navooru Sep 2018 till

date

FAA Mr. Chengalvarayan Sep 2018 till

date

16. SHW FAE Mr. A. Manoharan Sep 2018 till March 2021

EIA Report

468 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

S. No.

Functional Areas

Name of the Expert Signature Duration of Involvement

Mr. Vamsee Krishna Navooru Sep 2018 till

date

17. SE FAE Mr. V. Dhivakar Sep 2018 till

date

18. EB FAEDr.. Sundararajan

Sep 2018 till date

Dr. Rajkumar Samuel Sep 2018 till

date

19. HG FAE Mr. MallikarjunaRao Sep 2018 till

date

20. Geo FAE Mr. MallikarjunaRao Sep 2018 till

date

21. NV FAEMr. Vivek P. Navare

Sep 2018 till date

Mr. Vamsee Krishna Navooru Sep 2018 till

date

22. LU FAE Mr. VenkateswarluRachala Sep 2018 till

date

23. RH FAE Dr. J R Moses Sep 2018 till

date

24. SC FAEMr. A. Manoharan

Sep 2018 till March 2020

Dr.B.C.Nagaraja Feb 2020 till March 2021

AP - Air pollution monitoring, prevention and control

AQ - Meteorology, air quality modeling and prediction

EB - Ecology and biodiversity

HG - Hydrology, ground water and water conservation

LU - Land use

NV - Noise & Vibration

RH - Risk assessment and hazards management

SC - Soil conservation

SE - Socio-economics

SHW - Solid and hazardous waste management

WP - Water pollution monitoring, prevention and control

12.2 QCI-NABET - EIA Accreditation

Consultancy Hubert Enviro Care Systems Pvt. Ltd., Chennai

NABET Certificate No &

Date of validity NABET/EIA/1922/RA 0172 Valid up to 13/10/2022

MoEF Reg. Lab F.No. Q-15018/21/2017-CPW

EIA Report

469 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

12.3 Copy of QCI NABET Accreditation

Further details may be seen on the following URL: www.hecs.in

EIA Report

470 HECS/EIA/IOCL Paradip/Final/24.06.2021/1051

HUBERT ENVIRO CARE SYSTEMS (P) LIMITED

A-21, III-Phase, Behind Lions Club School,Thiru vi ka Industrial Estate, Guindy, Chennai – 600 032

Ph: +91-44-43635555; Fax: +91-44-43635500