for environmental clearance of the proposed
TRANSCRIPT
Conceptual Plan, Form-1 & Form -1A
for Environmental Clearance of the Proposed
Hotel at Plot No.2, Wazirpur District Centre ,
Delhi
Submitted By
Prepared By
Ascenso Management & Consulting Services Pvt. Ltd.
A QCI Accredited Environmental Consulting Organization
Asrani Inns and Resorts Private Limited
Asrani Inns and Resorts Private Limited
TABLE OF CONTENTS
Description.............................................................................................Page No.
FORM–I .............................................................................................................................. 1-15
FORM- IA........................................................................................................................... 1-71
1. Land Environment ...............................................................................................................1
2. Water Environment ............................................................................................................11
3. Vegetation ..........................................................................................................................22
4. Fauna ..................................................................................................................................28
5. Air Environment ................................................................................................................29
6. Aesthetics ...........................................................................................................................31
7. Socio-economic Aspects ....................................................................................................32
8. Building Materials .............................................................................................................33
9. Energy Conservation ..........................................................................................................37
10. Environmental Management Plan ......................................................................................53
CONCEPTUAL PLAN ...................................................................................................... 1-20
1. Introduction ..........................................................................................................................1
2. Site Surrounding & Connectivity.........................................................................................2
3. Project Location and Description .........................................................................................6
4. Details of Building Block……………………………..………………………………….7
5. Population Detail .................................................................................................................7
6. Road and Parking Detail .....................................................................................................8
7. Landscape Development .....................................................................................................9
8. Water Requirement, Supply and Distribution ...................................................................10
7.1 Water requirement during Construction phase.....................................................…...10
7.2 Water requirement during operation phase ....................................................................... 10
7.3 Wastewater Generation................................................................................................11
9. Storm Water Drainage .......................................................................................................16
10. Rainwater Harvesting .........................................................................................................16
11. Power Requirement ............................................................................................................18
12. Solid Waste Generation and Management .........................................................................18
13. Fire Fighting System ..........................................................................................................19
14. Detail of Construction Material .........................................................................................20
LIST OF TABLES
Form-IA
Table-1: Infrastructural Details……………………………………………………………………4
Table-1(a): Parking Details…………………………………………………………………….…5
Table-1(b) Basement Area under Parking ……………………………………………………….5
Table-2: Waste Composition-During Construction Phase………………………….…...……….10
Table-3: Detail of Water Requirement ….....................................................................................13
Table-4: Summary of water requirement (Hotel + Retail)…………………………………….14
Table-5: Recycled Water Uses .......................................................................................................16
Table-6: Details of Wastewater Generation ..................................................................................17
Table-7: Runoff Calculation of the Area .......................................................................................18
Table-8: Numbers of Pits Calculation ………………………………………………………...18
Table-9: Suggested Species to be used for Greenbelt Development ............................................24
Table-10: Archeological sites within 15 Km of the project site....................................................32
Table-11: Social Infrastructure around the project site.........................…..……………….……33
Table-12: Activities during Construction and Operation along with Mitigation ……….….….45
Table-13: Environmental Management Plan – Construction and Operation Phase.....................55
Table-14: Environmental Monitoring Schedule …………...…………….……...........……..….65
Table-15: Proposed Monitoring Program for Construction Phase of the Project..........................68
Table-16: Proposed Monitoring Program for Operational Phase of the Project……… ……………68
Table-17: Environmental Documentation for Operational Phase of the Project…………..……69
Table-18: Environmental Management Cost ……………………………………….…..………71
Conceptual Plan
Table-1: Site Surroundings and Connectivity Details ....................................................................2
Table-2: Coordinates of the Project Boundary ...............................................................................6
Table-3: Area details of the proposed project site ...........................................................................6
Table-4: Details of Building Blocks ...............................................................................................7
Table-5 Floor wise details of building...................................................................................…......7
Table-6 Calculation of Population (Hotel + Retail) .........................................................................8
Table-7: Parking Details .................................................................................................................9
Table-8: Basement Area under Parking ..........................................................................................9
Table-9: Calculation of Green Area ..............................................................................................10
Table-10: Details of water requirement… .....................................................................................11
Table-11: Recycled Water Uses....................................................................................................16
Table-12: Runoff Calculation of the Area.......................................…..........................................17
Table-13: Numbers of Pits Calculation..........................................................................................17
Table-14: Proposed Solid Waste Generation Rate……………………………..………………..18
LIST OF FIGURE
Form-IA
Figure-1: Google Map showing surrounding areas of the project site within 500 m…..................3
Figure-2 Topographical map (Survey of India) of 10km radius ……….........................................4
Figure-3: Topographical map (Survey of India) of 15km radius showing Eco-sensitive area........5
Figure-4: Map showing the Seismic Zone classification of NCT....................................................7
Figure-5: Water Balance Diagram for Non-Monsoon Season...................…...............................14
Figure-6: Water Balance Diagram for Monsoon Season....................................... ......................15
Figure-7: Typical Design of Rain Water Harvesting Pit..............................................................19
Conceptual Plan
Figure-1: Google Map of 500m radius showing surroundings of the area...................………….2
Figure-2: Topographical Map of 10km radius showing surrounding area................…………....2
Figure-3: Topographical Map of 15km radius showing surrounding area..........…….…….…....5
Figure-4: Water Balance Diagram for Non-Monsoon Season …………………….....................14
Figure-5: Water Balance Diagram for Monsoon Season............................................…………...15
Figure-6: Solid Waste Management Plan………………………………………………………19
LIST OF ANNEXURE
Annexure -I Land Document
Annexure -II Environmental Clearance Letter
Annexure -III Consent To Establish
Annexure -IV Receiving of Last six monthly compliance, December
2018
Annexure-V Site Plan
Annexure -VI AAI NOC
Annexure -VII Basement cum Traffic circulation Plan
Annexure -VIII Landscape plan
Annexure- IX Geo technical report
Annexure - X Section Plan
Annexure- XI Elevation Plan
Annexure - XII Dual Plumbing Plan
Annexure- XIII Fire NOC
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 1 of 16
APPENDIX -I
(See Paragraph – 6)
FORM-1
(I) Basic Information
Sl. No. Item Details
1. Name of the project Proposed Hotel at Plot No. 2,Wazirpur District
Center, Delhi
2. S.No. in the Schedule 8 (a)
3. Proposed capacity/area/length/tonnage to
be handled/command area/lease area/
number of wells to be drilled.
Total Plot Area : 7,030 m2
Built up Area (FAR + Non FAR): 38,953.117 m2
4. New/Expansion/Modernization Expansion Project
5.
Existing Capacity/Area etc.
The Project earlier has received
environmental clearance vide EC letter No.
Environmental Clearance No. DPCC/SEIAA-
SEAC/200/13/1272 Dated 01/08/2014 from
SEIAA, Delhi. The earlier EC letter is
attached as Annexure-II.
But now due to internal management decision
projects has some planning to modify the
building plans hence the separate
Environmental Clearance will be sought.
The project is being developed on the total plot
area of 7,030 m2. Earlier the built up area is
27,867.49 sqm but after modification of plan
the built-up area increase to 38,953.117 m2.
6. Category of Project i.e. ‘A’ or ‘B’ B
7. Does it Attract the general condition? If
yes, please specify. No
8. Does it attract the specific condition? If
yes, please specify. No
9. Location
Plot No.2
Wazirpur District Centre
Plot/Survery/Khasra No
Village
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 2 of 16
Tehsil
Delhi
New Delhi
District
State
10. Nearest railway station/airport along with
distance in kms.
Nearest railway station is Delhi Junction
Railway Station at an aerial distance of approx. 9
km towards South- East.
Indira Gandhi International Airport at an aerial
distance of 16 km towards South.
11. Nearest Town, City, District
Headquarters along with distance in kms.
Nearest Town: Bahadurgarh-22.3 km
District Headquarters- New Delhi
12. Village Panchayats, Zilla Parishad,
Muncipal Corporation, Local body
(Complete postal addresses with
telephone nos. to be given)
Delhi Development Authority (DDA)
Vikas Sadan, New Delhi-110023.
Telephone: 011-24690431/24690435
13. Name of the applicant Mr. Jagdishprashad M Joshi
14. Registered Address Plot No.1 & 2,WazirpurDistrict Center, Netaji
Subhash Place,Delhi-110034
15. Address for correspondence:
Mr. Jagdishprashad M Joshi
Director
JMJ House,5th
Floor,Orchard Avenue,
Hiranandani Gardens, Powai,
Mumbai
400076
[email protected] 91-22-67112233 91-22-67112234
Name
Designation(Owner/Partner/CEO)
Address
Pin Code
Telephone No.
Fax No.
16. Details of Alternative Sites Examined, if
any, Location of these sites should be
shown on a topo sheet.
The possession of the plot no.2 was handed
over to Asrani Inns and Resorts Private Limited
by Delhi Development Authority
admeasuring 7,030sq.m.
The copy of the possession letter, (Ref. File No.
F30 (I)/2006/CL/2158 dated: 30/06/2006). No
need to examine the alternative site.
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 3 of 16
17. Interlinked Projects Not Applicable
18. Whether separate application of
interlinked project has been submitted?
Not Applicable
19. If yes, date of submission Not Applicable
20. If no, reason Not Applicable
21. Whether the proposal involves
approval/clearance under: If yes, detail of
the same and their status to be given
(a) The Forests (Conservation) Act,
1980?
(b) The Wild Life (Protection) Act,
1972?
(c) The C.R.Z. Notification, 1990?
Applicability of these rules will be examined and
if required, clearance will be taken.
22. Whether there is any Government
order/policy relevant/relating to the site?
Not Applicable.
23. Forests Land Involved (Hectares) Forest land is not involved.
24. Whether there is any litigation pending
against the project and/or land in which
the project is proposed to be setup?
(a) Name of the Court
(b) Case No.
(c) Orders/ directions of the Court, if
any and its relevance with the proposed
project.
No litigation is pending against the project
and/or land in which the project is proposed.
(II) Activity
1. Construction, operation or decommissioning of the Project involving actions,
which will cause physical changes in the locality (topography, land use, changes in water
bodies, etc.)
S. No. Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
1.1 Permanent or temporary change in
land use, land cover or topography
including increase in intensity of
No The selected site falls under land use as
per the Master plan of Delhi 2021 and will
be developed as per the same.
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 4 of 16
land use (with respect to local land
use plan)
The possession of the plot no.2 was
handed over to Asrani Inns and Resorts
Private Limited by Delhi Development
Authority admeasuring 7,230 sq.m. The
copy of the possession letter, (Ref. File
No. F30 (I)/2006/CL/2158 dated:
30/06/2006) is attached as Annexure-I.
The land cover project site is a fallow land
and depicts plain topography (relative
relief is less than 5m) it is anticipated that
the construction activities of the project
will be as per master plan of Delhi and
will help in increasing the aesthetic
beauty.
1.2 Clearance of existing land,
vegetation and building? No
No clearance of existing land, vegetation
and building will be required.
1.3 Creation of new land uses? No
The selected site falls under land use as
per the Master plan of Delhi 2021 and will
be developed as per the same.
The possession of the plot no.1 was
handed over to Asrani Inns and Resorts
Private Limited by Delhi Development
Authority admeasuring 7,030 sq.m. The
copy of the possession letter, (Ref. File
No. F30 (I)/2006/CL/3790 dated:
13/10/2006) is attached as Annexure-I.
There will be no creation of new land
uses.
1.4 Pre-construction investigations
e.g. bore houses, soil testing?
Yes Geo-Technical investigation had been
done. It is attached as Annexure- VIII.
1.5 Construction Work? Yes Construction work will be done as per
Building Plan and Building Bye Laws of
Delhi.
The basement work was started earlier
after getting the Environmental Clearance.
The Project was granted Environmental
Clearance by Ministry of Environment &
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 5 of 16
Forest, vide Letter No. DPCC/SEIAA-
SEAC/200/13/1272 Dated 01/08/2014
from SEIAA, Delhi. and the copy of
Environmental Clearance Letter is
attached as Annexure-II.
1.6 Demolition works? No Not Required
1.7 Temporary sites used for
construction works or housing of
construction workers?
Yes Site office will be provided for the
Construction Management team during
construction phase. Workers camp will be
provided. Mostly local workers will be
involved.
1.8 Above ground building, structures
or earthwork including linear
structures, cut and fill or
excavations
Yes Excavation was carried out for foundation
of buildings and basements. The total
excavated quantity of earth material will
be approx. 63,750 m3. The excavated soil
will be used in landscaping, backfilling
and other area development activities as
per building plan and Building Bye Laws
of Delhi.
1.9 Underground works including
mining or tunnelling?
No As this is the Building and Construction
project, no mining or tunnelling would be
required.
1.10 Reclamation works? No Not Applicable
1.11 Dredging? No Not Applicable
1.12 Offshore structures? No Not Applicable
1.13 Production and manufacturing
processes?
No As it is a Building and Construction
project, so these activities are not
associated with the project.
1.14 Facilities for storage of goods or
materials?
Yes Material storage yard will be developed or
constructed for storage of construction
materials.
1.15 Facilities for treatment or disposal
of solid waste or liquid effluents?
Yes Details regarding the Disposal of Liquid
Waste:
Sewage treatment plant will be installed.
1. Sewage generation– 278 KLD
2. STP capacity-300 KLD
3. ETP capacity: 60 KLD
4. Technology- Membrane Bio-Reactor
(MBR)
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 6 of 16
Details regarding the Disposal of Solid
Waste:
1.Total Solid waste generation-694 kg/day
2. Segregation, Collection and storage will
be done at the site.
1.16 Facilities for long term housing of
operational workers? No
There will be no facility for long term
housing for operational workers.
1.17 New road, rail or sea traffic during
construction or operation? Yes
Road traffic will marginally increase and
existing roads (Lala Jagat Narain Marg)
and Kabirdas Margwill be used.
1.18 New road, rail, air waterborne or
other transport infrastructure
including new or altered routes
and stations, ports, airports etc?
No Existing road (Lala Jagat Narain Marg)
and Kabirdas Marg will be used.
1.19 Closure or diversion of existing
transport routes or infrastructure
leading to changes in traffic
movements?
No
Since the site is adjacent to Lala Jagat
Narain Marg and Kabirdas Marg, there
will be no need for diversion or closure of
existing traffic routes as the traffic routes
which are existing are enough for proper
control and circulation of the additional
traffic. The project shall not affect the
existing traffic status during the
construction and operational phase.
1.20 New or diverted transmission lines
or pipelines? No
There will not be any new/diverted
transmission lines or pipelines around the
project.
1.21 Impoundment, damming,
culverting, realignment or other
changes to the hydrology of
watercourses or aquifers?
No
No impoundment, damming, culverting,
realignment or other changes to the
hydrology of surface watercourses is
proposed.
1.22 Stream crossings? No No stream is crossing in the project site.
1.23 Abstraction or transfers of water
from ground or surface waters? Yes
Source of water will be municipal water
supply.
1.24 Changes in water bodies or the
land surface affecting drainage or
run-off? No
The sewage will be treated in the onsite STP
and the treated water will be used for flushing,
landscaping and HVAC Cooling tower.
Runoff will increase due to increased paved
surface. However, increased runoff will be
managed by well-designed rainwater
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 7 of 16
harvesting system and storm water
management plan.
1.25 Transport of Personnel or
materials for construction,
operation or decommissioning?
Yes Existing road Lala Jagat Narain Marg and
Kabirdas Marg will be used. During the
construction phase, about 8-10 trucks are
estimated per week. Adequate parking
space within the project site for loading
and unloading of materials will be
provided.
1.26 Long-term dismantling or
decommissioning or restoration
works?
No No Long term dismantling or
decommissioning or restoration works
will be involved.
1.27 Ongoing activity during
decommissioning which could
have an impact on the
environment?
No Not Applicable
1.28 Influx of people to an area in
either temporarily or permanently?
Yes Construction phase:
Immigrant workers (Temporarily).
Operation Phase:
Persons in Hotels (Temporarily).
1.29 Introduction of alien species? No
The landscaping will be carried out with
mainly local species and also a few
ornamental varieties of flora that are well
suited to the local conditions.
Native/Local species will be planted.
1.30 Loss of native species or genetic
diversity? No
There will be no significant impact on the
native species or genetic diversity.
1.31 Any other actions? No No
2. Use of Natural resources for construction or operation of the Project (such as
land, water, materials or energy, especially any resources which are non-renewable or
in short supply):
S. No. Information/ Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible
with source of information data)
2.1. Land especially
undeveloped/agricultural
No The selected site falls under land use as
per the Master plan of Delhi 2021 and will
be developed as per the same.
The possession of the plot no.1 was
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 8 of 16
handed over to Asrani Inns and Resorts
Private Limited by Delhi Development
Authority admeasuring 7,220 sq.m. The
copy of the possession letter, (File no. F30
(I)/2006/CL/2158) dated: 30.06.2006 is
attached as Annexure-I.
There will be no creation of new land
uses. The basement work was started
earlier after getting the Environmental
Clearance. The Project was granted
Environmental Clearance by Ministry of
Environment & Forest, vide Letter No.
DPCC/SEAC/199/SEIAA/72/2013 (dated:
1/08/2014) and the copy of Environmental
Clearance Letter is attached as
Annexure-II.
2.2. Water (expected source &
competing users) Unit: KLD
Yes Total Water requirement of the proposed
project will be 556 KLD i.e. (Total Fresh
water requirement will be 314 KLD)
Source of water would be Delhi Jal Board.
2.3. Minerals (MT) Yes Sand, Soil, Stone, Aggregates.
2.4. Construction material – stone,
aggregates, sand/soil ( expected
source – MT)
Yes List of building materials being used at
site:
Sand
Coarse aggregate
Fine aggregate
Cement
Structural Steel
Reinforcement Steel
2.5. Forests and timber (source – MT) Yes Minimum wood will be used in the
project, mainly would be used for doors.
2.6. Energy including electricity and
fuels (source, competing users)
Unit: fuel (MT), energy (MW)
Yes Power Requirement: 1980 kW
Power Back-up:
4 no. of DG Sets having total capacity of
7500 KVA (3 x 2000 kVA + 1 x 1500
kVA (on stand by))
Total Fuel Requirement: 1200 Lit/hr
Source for power: BSES
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 9 of 16
2.7. Any other natural resources (use
appropriate standard units)
No Not Applicable
3. Use, storage, transport, handling or production of substances or materials, which
could be harmful to human health or the environment or raise concerns about actual or
perceived risks to human health.
S.
No.
Information/Checklist
Confirmation
Yes/
No
Details there of (with approximate
quantities/rates, wherever possible)
with source of information data
3.1 Use of substances or materials, which
are hazardous (as per MSIHC rules)
to human health or the environment
(flora, fauna, and water supplies)
No Diesel for DG sets will be stored in drums
in earmarked locations. It shall also be
handled as per The Manufacture, Storage
and Import of Hazardous Chemical
(Amendment) Rules, 2000.
3.2 Changes in occurrence of disease of
disease or affect disease vectors (e.g.
insect or water borne diseases)
No Suitable drainage and waste management
measures will be adopted in both the
construction and operational phase such
that there will be no stagnation of water or
accumulation of waste .This will
effectively restrict the reproduction and
growth of disease vectors.
3.3 Affect the welfare of people e.g. by
changing living conditions?
Yes Due to the proposed project Socio-
Economic condition of the area will
improve. The project shall not have any
adverse effect on the living condition of
the people.
3.4 Vulnerable groups of people who
could be affected by the project e.g.
hospital patients, children, the elderly
etc.,
No The project shall not affect any vulnerable
groups of people in the vicinity.
3.5 Any other causes No Not Applicable
4. Production of solid wastes during construction or operation or operation or
decommissioning (MT/month)
S. No. Information/Checklist
confirmation
Yes/
No
Details thereof (With approximate
quantities/rates, wherever possible)
with source of information data
4.1 Spoil, overburden or mine wastes No As this project is the Building and
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 10 of 16
Construction project, so no mine, spoil
and overburden waste will be generated
4.3 Hazardous wastes (as per Hazardous
Waste Management Rules)
Yes Used oil from the DG Sets as per the
Category 5.1, of Schedule-1 of the
Hazardous Wastes, (Management, &
Transboundary Movement) Rules, 2016.
4.4 Other industrial process wastes No Not Applicable
4.5 Surplus product No Not Applicable
4.6 Sewage sludge or other sludge from
effluent treatment
Yes S.T.P. Sludge: 196.56 kg /day (on wet
basis).
4.7 Construction or demolition wastes Yes Details of Construction waste is given
below:
1. Soil, Sand and Gravel
2.Brick and Masonry
3. Concrete
4. Metal
5. Bitumen
6.Wood
7. Other (Glass, Plastic material, paper
etc.)
4.8 Redundant machinery or equipment No Not Applicable
4.9 Contaminated soils or other materials No Not Applicable
4.10 Agricultural wastes No Not Applicable
4.11 Other solid wastes No Not Applicable
5. Release of pollutant or any hazardous, toxic or noxious substances to air (kg/hr)
S.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
5.1 Emissions from combustion of fossil
fuels from stationary or mobile
sources
Yes DG Sets emissions during construction
and operational phase.
5.2 Emissions from production processes No Not Applicable
5.3 Emissions from materials handling
including storage or transport
Yes Fugitive Dust emission during unloading
the construction material, transportation
and earthwork (levelling etc.)
5.4 Emissions from construction
activities including construction
Yes Fugitive Dust emission during earthwork
and construction activities.
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 11 of 16
materials, sewage and waste
5.5 Dust of odours from handling of
materials including construction
materials, sewage and waste
Yes Fugitive dust during material handling and
STP sludge during operational phase.
5.6 Emissions from incineration of waste No Not Applicable
5.7 Emissions from burning of waste in
open air (e.g. slash materials,
construction debris)
No Burning of waste will not be done and the
waste generated shall be managed as per
Solid Waste Management Rules, 2016.
Construction debris will be used in
internal road construction.
5.8 Emissions from any other sources No Not Applicable
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
S. No Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
6.1 From operation of equipment e.g.
engines, ventilation plant, crushers
Yes Moderate noise will be generated from
Construction Machineries such as
Concrete mixer with hopper,
JCB/Pockline, Road roller. To avoid
this, ear muffs will be provided to the
construction workers.
6.2 From industrial or similar processes No Not Applicable
6.3 From construction or demolition Yes Moderate noise during construction.
6.4 From blasting or piling No Not Applicable
6.5 From construction or operational
traffic
Yes Moderate noise during construction
/operation traffic.
6.6 From lighting or cooling systems No Not Applicable
6.7 From Any other sources No Not Applicable
7. Risks of contamination of land or water from releases of pollutants into the ground or into
sewers, surface waters, groundwater, coastal waters or the sea:
S. No. Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever
possible) with source of
information data.
7.1 From handling, storage, use or
spillage of hazardous materials
No The used oil from DG sets will be
carefully stored in HDPE drums at
isolated storage, and periodically
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 12 of 16
sold to authorized recyclers. All
precautions will be taken to avoid
spillage from storage as per Solid
Waste Management Rules, 2016
7.2 From discharge of sewage or other
effluents to water or the land
(expected mode and place of
discharge)
Yes Treated sewage from STP will be
reused for flushing, landscaping and
HVAC Cooling towers. After reuse
and recycle, excess treated water
will be discharged into sewer during
the Monsoon season.
7.3 By deposition of pollutants emitted
to air into the land or into water
No Not Applicable
7.4 From any other sources No Not Applicable
7.5 Is there a risk of long term build-up
of pollutants in the environment
form these sources?
No There is no such risk.
8. Risk of accidents during construction or operation of the Project, which could affect
human health or the environment
S.N o. Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever
possible) with source of
information data
8.1 From explosions, spillages, fires etc
from storage, handling, use or
production of hazardous substances
No Fire Fighting: Safety measures for
the potential sources of Fire
hazards, like diesel storage for DG
sets etc. will be taken into
consideration from safety point.
8.2 From any other causes No Not Applicable.
8.3 Could the project be affected by
natural disasters causing
environmental damage (e.g. floods,
earthquakes, landslides, cloudburst
etc)?
No The project falls under seismic
active Zone IV indicating High
damage risk zone. The buildings
will be designed as earthquake
resistant and comply with the
required IS specifications.
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 13 of 16
9. Factors which should be considered (such as consequential development) which could
lead to environmental effects or the potential for cumulative impacts with other existing or
planned activities in the locality
S. No. Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever
possible) with source of
information data
9.1 Lead to development of supporting
facilities, ancillary development or
development stimulated by the
project which could have impact on
the environment e.g.:
Supporting infrastructure
(roads, power supply, waste or
waste water treatment, etc.)
Housing development
Extractive industries
Supply industries
Other
Yes
No
No
No
Yes
Appropriate infrastructure like
roads, power supply, waste
management and waste water
treatment will be developed within
the project site. Development of the
area will be as per the Master Plan
of Delhi 2021.
Not Applicable
Not Applicable
Not Applicable
Hotel building/Retail Building
9.2 Lead to after-use of the site, which
could have an impact on the
environment
No Not Applicable
9.3 Set a precedent for later
development
Yes Infrastructure development of area.
Socio Economic condition will
improve.
9.4 Have cumulative effects due to
proximity to other existing or
planned projects with similar
effects
No Negligible
(III) Environment Sensitivity
S. No.
Area Name/ Identity
Aerial distance
(within 15km)
Proposed project
location boundary
1. Areas protected under
international conventions,
national or local legislation
for their ecological,
Forest:
Central Ridge RF
Garhi Mandhu PF
Archaeological Sites:
8 km, S
7 km, E
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 14 of 16
landscape, cultural or other
related value
Red Fort
Lal Darwaza, Hauz Qazi
10.26 km, SE
9.56 km, SE
2. Areas which are important or
sensitive for ecological
reasons –Wetlands,
watercourses or other water
bodies, coastal zone,
biospheres, mountains,
forests
Forest:
Central Ridge RF
Garhi Mandhu PF
Water Bodies:
River Yamuna
8 km, S
7 km, E
8 km, E
3. Area used by protected,
important or sensitive
species of flora or fauna for
breeding, nesting, foraging,
resting, over wintering,
migration
Forest:
Central Ridge RF
Garhi Mandhu PF
8 km, S
7 km, E
4. Inland, coastal, marine or
underground waters
Inland:
River Yamuna
Ground Water:
Ground Water Depth
8 km, E
6 metres below ground
level. During heavy
rainfall, it rises upto
4.5 metres below
ground level.
5. State, National boundaries UP-Delhi State Boundary
12 km,E
6. Routes or facilities used by
the public for access to
recreation or other tourist,
pilgrim areas
None There is no Routes or
facilities used by the
public for access to
recreation or other
tourist, pilgrim areas.
7. Defence installations No There are no defence
installations near the
project site.
8. Densely populated or built-
up area
Sandesh Vihar Approx.450 m, SW
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 15 of 16
9. Areas occupied by sensitive
man-made land uses
(hospitals, schools, places of
worship, community
facilities)
List of Schools:
Guru Gobind Singh College
M.M. Public School
Ravindra Public School
List of Hospitals:
Max Hospital
Bhagvan Mahavir Hospital
Sunder Lal Jain Hospital
List of Temples:
Hanuman Mandir
Kali Mata Mandir
600 mtrs., North-East
460 mtrs., West
285 mtrs., North
450 mtrs ,East
Approx.2 km, North
3.4 km , East.
600 m, South
850 m, South-West
10. Areas containing important,
high quality or scarce
resources (ground water
resources, surface resources,
forestry, agriculture,
fisheries, tourism, minerals)
River Yamuna
Ground Water Depth
8 km, E
6 metres below ground
level. During heavy
rainfall, it rises upto
4.5 metres below
ground level.
11. Areas already subjected to
pollution or environmental
damage. (those where
existing legal environmental
standards are exceeded)
Najafgarh Drain
Wazirpur Industrial Area
5 km, S
2 km, E
12. Areas susceptible to natural
hazard which could cause the
project to present
environmental problems
(earthquakes, subsidence,
landslides, erosion, flooding
or extreme or adverse
climatic conditions)
Yes Area is susceptible to
Earthquake. Project
area falls in Zone-IV
as High Damage Risk
Zone.
(IV) Proposed Terms of Reference for EIA studies - Not Applicable
Proposed Expansion of Hotel at Plot No.2, Wazirpur District Center, Delhi by M/s. Asrani
Inns and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 16 of 16
Date: 02/03/2019
Place: Delhi
Kundan Bhanawat
Chief Executive Officer
(Authorised Signatory)
Asrani Inns and Resorts Private Limited
1. The projects involving clearance under coastal Regulation Zone Notification, 1991 shall
submit with the application a C.R Z map duly demarcated by one of the authorized agencies,
showing the project activities, w.r.t. C.R.Z (at the stage of TOR) and the recommendations of
the State Coastal Zone Management Authority (at the stage of EC). Simultaneous action shall
also be taken to obtain the requisite clearance under the provisions of the C.R,Z Notification,
1991 for the activities to be located in the CRZ.
2 The projects to be located within 10 km or the National parks, Sanctuaries, Biosphere
Reserves, Migratory corridors of wild Animals, the project proponent shall submit the map
duly authenticated by chief wildlife warden showing these features vis-à-vis the project
location and the recommendations or comments of the Chief Wildlife Warden’ thereon (at the Stage of EC)."
3. All correspondence with the Ministry of Environment & Forests including submission of
application for TOR/Environmental Clearance, subsequent clarifications, as may be required
from time to time, participation in the EAC Meeting on behalf of the project proponent shall
be made by the authorized signatory only. The authorized signatory should also submit a
document in support of his claim of being an authorized signatory for the specific project."
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 1 of 69
APPENDIX II
(See paragraph 6)
FORM-1 A (only for construction projects listed under item 8 of the Schedule)
CHECK LIST OF ENVIRONMENTAL IMPACTS
(Project proponents are required to provide full information and wherever necessary
attach explanatory notes with the Form and submit along with proposed environmental
management plan & monitoring program)
1. LAND ENVIRONMENT
1.1 Will the existing land use get significantly altered from the project that is not consistent
with the surroundings? (Proposed land use must conform to the approved Master Plan /
Development Plan of the area. Change of land use if any and the statutory approval from
the competent authority to be submitted). Attach Maps of (i) site location, (ii) surrounding
features of the proposed site (within 500meters) and (iii) the site (indicating levels &
contours) to appropriate scales. If not available attach only conceptual plans.
M/s Asrani Inns and Resorts Pvt. Ltd. has been allotted the land vide allotment cum conveyance
Deed and possession letter for Plot-2 vide (File no. F30 (2)/2006/CL/3790) dated: 30.06.2006.
The copy of Land Documents is attached as Annexure-I.
The Project earlier has received environmental clearance vide EC letter No. Environmental
Clearance No. DPCC/SEIAA-SEAC/200/131272 Dated 01/08/2014 from SEIAA, Delhi. The
earlier EC letter is attached as Annexure-II.
The project had been granted Consent to Establish (CTE) by Delhi Pollution Control Committee
(DPCC) vide Certificate No. O-023449 dated 19.12.2014. The copy of CTE certificate is
attached as Annexure-III.
Regular compliance report of the EC is being submitted. Receiving of latest compliance report
are attached as Annexure IV.
But now due to internal management decision projects has some planning to modify the building
plans hence the separate Environmental Clearance will be sought.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 2 of 69
The project is being developed on the total plot area of 7,030 m2. Earlier the built up area is
27,867.49 Sqm but after modification of plan the buildup area increase to 38,958.524 m2.
The development to be done is in accordance with Delhi Master Plan 2021. Considering the
above; the existing land use is not expected to get altered due to construction of proposed
project.
The Project is designated under Category “B” and falls under Item 8(a) (Building & Construction Project) of the Environmental Impact Assessment (EIA) Notification of September 14, 2006 and
its amendments. Site Plan along with Area statement and details of building blocks is attached as
Annexure- V.
Google image showing surrounding features of within 500 m is shown as Figure-1.
Topographical map (Survey of India) of 10km radius showing surrounding area is shown as
Figure-2.
Topographical map (Survey of India) of 15km radius showing Eco-sensitive area is shown as
Figure-3.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 3 of 69
Figure-1: Google Map of 500m radius showing surroundings of the area
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 4 of 69
Figure-2: Topographical map (Survey of India) of 10km radius showing surrounding area
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 5 of 69
Figure-3: Topographical map (Survey of India) of 15km radius showing Eco-sensitive area
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 6 of 69
1.2 List out all the major project requirements in terms of the land area, built up area, water
consumption, power requirement, connectivity, community facilities, parking needs etc.
Table-1 shows the list of major project requirements:
Table-1 Infrastructural Details
S. No. Detail
1. Total Plot Area 7,030 m2
2. Built-up Area 38,958.524 m2
3. Total Water Consumption 523 KLD
4. Total Freshwater Requirement 298 KLD
5. Power Requirement 2725 KW
6. Power Backup 3 DG sets of 2000 KVA and 1 DG set
of 1500 KVA (on stand by)
7. Total Parking proposed 517 ECS
Connectivity
1. Nearest Railway Station Nearest railway station is Delhi
Junction Railway Station at an aerial
distance of approx. 9 km towards
South-East.
2. Nearest Airport Indira Gandhi International Airport at
an aerial distance of approx. 16
towards South.
Land Area:-M/s Asrani Inns and Resorts Pvt. Ltd. has Proposed Hotel at Plot-1, Wazirpur
District Centre, Delhi-110052 on the total plot area of 7,030 m2. The total built up area is
38,958.524 m2
AAI NOC is attached as Annexure-VI.
Water Consumption: Water requirement during the operational phase is met through Municipal
Council. The total water requirement for the project is 523 KLD. This includes domestic water
requirement, flushing, landscaping, cooling tower makeup, swimming pool, Laundry, RO plant,
Kitchen demand, filter back wash and for firefighting tank. The total fresh water requirement is
298 KLD which includes Domestic water requirement. The water requirement for Flushing,
HVAC Cooling, road washing and landscaping will be met through treated water from STP.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 7 of 69
Power Requirement: The total electrical load demand is 2725 KW. The source of power supply
is New Delhi Municipal Council.
In case of power failure, 3 DG sets of 2000 KVA capacity are provided for backup power supply
system and 1 DG set of 1500 kVA will be on standby. All 4 Nos. DG Sets are fully synchronized
with AMF, Auto Load Management and Auto Load Sharing thru PLC / PCCM (Power
Command Control module) for optimum utilization of backup system. The DG sets are water
cooled.
Parking Details- The total parking proposed is 517 ECS and parking required is 503 ECS.
The detailed Parking details are provided in the Table-1(a). The comparative parking details are
given in Table-1(b).
Table-1(a): Parking Details
Description Norms (As per Delhi Building Bye Laws) Parking (E.C.S.)
Parking
Required
3 ECS/100 sq.m of FAR (16,839.183 m2) 505.1
Total ECS required 505
Basement Area under Parking 14531.086
Total ECS Proposed (@ 32 sqm/ECS for
Normal Car Park & 16 Sqm/ECS for
Stacked Parking)
517
Table-1(b): Basement Area under Parking
S.
No.
Surface / Basement Basement Area under
Services (sq.mtrs.)
1 Basement-1 2465.299
2 Basement-2 810.212
3 Basement-3 551.238
4 Basement-4 509.868
Total Area under
services
4336.617
Total Area under
Parking
14531.086
Basement cum Traffic Circulation Plans are attached as Annexure- VIII.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 8 of 69
1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to the
proposed site? (Such as open spaces, community facilities, details of the existing land use,
disturbance to the local ecology).
In the proposal, the ground coverage, the floor area ratio, the setbacks, heights of buildings, and
parking provisions are as per the DDA bye laws. All kinds of community facilities like shops,
hospitals, schools, etc. are situated within two km of the site. None of the project activities will
result in any adverse impact on the existing facilities adjacent to the proposed site. DDA has
developed all necessary infrastructures like roads, drainage, piped water supply, and
electrification near the project site. Commercial Centre exists close to the project site. The
proposed project site is designated for the intended purpose and as per the Master Plan.
The main areas of concern which will pose a significant impact are Emissions from D.G. Sets,
Noise from D.G. Sets and Sewerage discharge. Mitigation options that are proposed are
mentioned below,
i. Emission from the numbers of DG sets: Proper stack height will be provided as per
CPCB/MoEF&CC guidelines;
ii. Noise from DG sets: Acoustic enclosure will be provided for D.G. sets.
iii. A Sewage Treatment Plant (STP) of capacity 300 KLD and 60 KLD ETP (situated at Plot no.1)
is proposed and the treated water will be reused for landscaping, flushing and HVAC Cooling
purposes.
Further, there shall not be any change in the land use pattern due to the proposed project.
Currently, there is no construction on the area. The area is marked as per Delhi Master Plan
2021.
1.4 Will there be any significant land disturbance resulting in erosion, subsidence &
instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc
may be given).
As the topography in and around the site is mostly plain with no slope, digging of the site at the
beginning of the construction work would not result any significant effect on soil erosion and silt
run off, even during the heavy rains. The average elevation of land surface in the project area is
about 225 m above MSL. The project requires extensive work on the excavation and removal of
soil and hence will temporarily affect soil structure and stability localized. Apart from a very
localized constructional impacts at the project site, no significant adverse impact on the soil in
the surrounding area is anticipated. Most of the top soil and excavated soil will be reused within
the site itself. This will avoid any use of soil from outside. Also, ready mix construction method
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 9 of 69
will be followed for the construction, which will reduce stress on soil environment of the site.
During the operation phase, landscape will be carefully designed.
A Geotechnical investigation report is attached as Annexure-IX.
Seismicity:
The whole country has been divided into 5 Seismic zones as per maximum intensity of
„Modified Mercalli Scale‟ (MMS). The project site lies in Seismic Zone IV, called as „High
Damage Risk Zone‟.
Seismic zone classification of National Capital Territory is shown in Figure 2.
Source: Indian Meteorological Department
Figure-4: Map showing the Seismic Zone classification of NCT
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 10 of 69
1.5 Will the proposal involve alteration of natural drainage systems? (Give details on a
contour map showing the natural drainage near the proposed project site).
Drainage has two aspects – flood protection and storm water discharge, which are interrelated.
The storm water and flood protection in Delhi are not local but have regional bearing including
areas of Haryana and Rajasthan. The main drainage system of Delhi is such that all water
collected through main drains, link drains and small rivulets is discharged into Yamuna. On the
basis of topographical characteristics and existing drainage network, NCT of Delhi has been
divided into five drainage basins namely Najafgarh, Alipur, Shahdara, Khushak nallah and
Mehrauli. The major portion of NCT – Delhi is being drained by Najafgarh drain leading to
Yamuna River. Most of these drains mainly carry the urban sewage and industrial effluents. The
relief and soil conditions cause localized stagnation during rainy season. During high rains and
high floods in Yamuna River, the drainage system becomes ineffective as the outlets of rainwater
blocked.
1.6 What are the quantities of earthwork involved in the construction activity-cutting,
filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of
fill materials from outside the site etc?)
The only earth work involved is on account of the three level basements proposed for parking of
vehicles. The existing levels of the site result in a gradual slope from the south west part of the
site to the north east boundary of the site. Part of the excavated soil will be used to augment the
slope of the site for proper drainage. During the construction activity, it is expected that no fill
materials will be transported from outside. The total quantity of earthwork involved is estimated
to be about 63,750 m3 including the cut and fill requirements. No reclamation is involved on the
site. The details of quantity usage of soil within the site are mentioned below:
Backfilling ~13,750 m3
Landscaping ~7,500 m3
Surplus earth ~42,500 m3
It is expected the surplus earth will be utilized to fill the low lying area nearby and after
authorization from the civic authority.
1.7 Give details regarding water supply, waste handling etc. during the construction period.
Water required during the construction period will be supplied through private water tankers.
Water will be used in the construction activity for cement mixing, sprinkling, dust
suppression and domestic purposes of the construction workers.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 11 of 69
The only source of wastewater during the construction is domestic sewage of construction
workers and water used in construction activities and it will be disposed by septic tanks.
Waste to be generated during the construction period includes construction waste and solid
waste that will be stored in a separate covered area so as to prevent damage to property and
personnel working at the project site. Further, most of the construction debris will be used for
filling activities and the rest will be disposed of through authorized recyclers. Major types of
construction wastes are expected from the proposed Project: -
Clean Fills:
Clean fill is uncontaminated soil, rock, sand, gravel, concrete, asphaltic concrete, cinder
blocks brick, minimal amounts of wood and metal and inert (non-reactive) solids for fill,
reclamation or other beneficial use. Minimal means the smallest amount possible.
Recovered Materials
Recovered Materials are those removed for reuse (lumber, doors, windows, ceramic tile
and glass) and those removed to be recycled into new products. Potentially recyclable
construction and demolition wastes will include scrap metals, asphalt shingles, sheet
rock, lumber, glass and electrical wire.
Regulated construction and demolition waste
Regulated construction and demolition wastes are those not classified as clean fill and not
being reused or recycled. Regulated non-hazardous construction and demolition wastes
will be disposed off at a permitted landfill or transfer station.
Scrap metal painted with heavy metals will be sent to a salvage yard for recycling. If this
would not possible, the metal would be disposed off at a sanitary or demolition landfill.
Asbestos containing material
Buildings may contain asbestos in materials such as ceiling or floor tile, as insulation or
soundproofing on ceilings, pipes, ductwork or boilers, or on the outside as transit siding
or in shingles. The presence of asbestos-containing materials cannot be confirmed just by
looking.
1.8 Will the low lying areas & wetlands get altered? (Provide details of how low lying and
wetlands are getting modified from the proposed activity).
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 12 of 69
There are no low lying areas and wetlands in near vicinity of the project site. The topography
in and around the site is mostly plain with no slope. Thus no impacts are envisaged on any
low lying areas or wet lands due to the proposed project activities.
1.9 Whether construction debris & waste during construction cause health hazard? (Give
quantities of various types of wastes generated during construction including the
construction labor and the means of disposal).
No significant health hazard is associated with the proposed construction.
During construction period, source of fugitive dust generation will be material handling and
vehicular movement. Impact due to fugitive dust emission is negligible as water sprinklers
will be used to suppress fugitive dust emission as and when generate. However, the impacts
will be confined to laborers/workers particularly with regard to occupational exposure.
Proper Personal Protective Equipment will be provided to the workers working in the
potential areas (e.g. masks, ear plugs etc.).
Careful design, planning and good site management would minimize waste of materials such
as concrete, mortars and cement grouts. Construction wastes will be segregated as much as
possible at site itself to increase the feasibility of recycling concrete and masonry as filling
material and steel pieces as saleable scrap. Litter disposal and collection points will be
established around the work sites. Empty packaging materials, drums, glass, tin, paper,
plastic, pet bottles, wood, thermocol and other packaging materials, etc will be disposed
through recyclers. The construction spoils will be temporarily stored at designated dumpsite
located inside the site premises. Later on these wastes will be used for land filling / leveling
work within the site premises. An estimate of the average composition of waste generated
from the onsite construction activities given in Table-2.
Table-2: Waste Composition - During Construction Phase
Sl. No. Constituents Percentage Composition
1 Soil, Sand and Gravel 34.99
2 Brick and Masonry 29.95
3 Concrete 24.98
4 Metal 4.97
5 Bitumen 2.04
6 Wood 2.04
7 Other 1.02
Total 100
Source: TIFAC Report “Utilization of Waste from Construction Industry,” 2001
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 13 of 69
2. WATER ENVIRONMENT
2.1. Give the total quantity of water requirement for the proposed project with the breakup of
requirements for various uses. How will the water requirement met? State the sources &
quantities and furnish a water balance statement.
The main water requirement of the proposed hotel will be for the following purposes:
a) Domestic requirements (in Guest Rooms, Visitors‟ Public Area, Restaurants, Banquets,
Meeting Rooms, Health Club, Kitchen etc.)
Drinking
Sanitation (Flushing in Toilets, Washbasins, Bathing etc.)
Cooking
b) Process water requirements
Hot Water Generators (Primary Circuit) Make up (The hot water generators are
proposed for catering to domestic hot water heating, kitchen, and swimming pool
heating)
Swimming Pool Make-up
HVAC Cooling
DG Set Cooling
Landscaping
Source of water supply: Delhi Jal Board
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 14 of 69
Table-3: Details of water requirement
Description Total
Population /
Area
Unit Water
Consumption
(LPCD)
Total Water
Requirement
(KLD)
Domestic Cold
Water
Requirement
(KLD)
Domestic hot Water
Requirement
(KLD)
Total hot + Cold water
Requirement
(KLD)
Flushing
Requirement
(KLD)
Wastewater
Generation
(KLD)
Hotel Population
Keys 306 320 97.92 47.43 32.13 79.56 18.36 83.232
Hotel Staff Permanent (40) +
Banquet & Specialty
Restaurant staff permanent (79)
119 135 15.39 6.27 4.165 10.435 5.355 13.4215
Hotel Day Staff (40) +
Banquet & Specialty
Restaurant day staff (79)
119 45 5.355 2.28 0.595 2.875 2.38 4.46675
Visitors 165 15 2.475 0.825 0.825 1.65 0.825 2.10375
For Kitchen 306x3 + 80x2 +
770x2+1778x2) = 4634 @ 12
Lit per meal
4634 12 55.608 37.072 18.536 55.608 ……. 47.2668
R.O. Plant for Drinking water
for guest room and
preparation of food &
beverages
….. ….. 29 29 …….. 29 ….. 14.5
Banquet halls 1778 15 26.67 8.89 8.89 17.78 8.89 22.6695
Specialty Restaurant 334 70 23.38 11.69 6.68 18.37 5.01 19.873
Gym & Spa 609 15 9.135 3.571 3.095 8.666 3.095 10.0278
Water for laundry @ 8 Kg /
guest room / day (Total 1088
Kg / day) & 20 Lit /Kg
1,224 20 29.92 17.952 11.968 29.92 …. 26.928
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 15 of 69
Description Total
Population /
Area
Unit Water
Consumption
(LPCD)
Total Water
Requirement
(KLD)
Domestic Cold
Water
Requirement
Domestic hot Water
Requirement
Total hot + Cold water
Requirement
Flushing
Requirement
(KLD)
Wastewater
Generation
(KLD) Retail (Visitors) 0 First Floor 297 15 4.455 1.485 -- 1.4885 2.97 3.78675 Second Floor 267 15 4.005 1.335 1.335 2.67 3.40425
Day staff (salesmen) in shops (30 shops)
50 45 2.25 1.25
1.25 1 1.9125
Admin / security staff 70 45 3.15 1.75 1.75 1.4 2.6775 Miscellaneous water
requirement for Hotel / Retail /
Office
0
Make up water for cooling tower
of A/C plant (150000 LPD) ….. ….. 170 …. ……….. 0 170 0
Landscaping water requirement
for 30% of plot area = 2434 m2
@ 1 Lit / m2
….. ….. 10.5 …. ……….. 0 ……….. …..
Road Washing ….. ….. 5 ….. ….. ….. ……….. WTP Backwash & regeneration ….. ….. 8 8 8 ….. 6.8
Mopping & Washing ….. ….. 2 2 …. 2 Swimming Pool (For Hotel)
make-up water ….. ….. 18 18
18 ….. …..
Fire Fighting ….. ….. 6.00 …. ……. 0 ….. ….. Total 9972 522.773 195.01 84.453 279.47 237.41 254.51
Total (Rounding off)
(Lit/Day) 9972 523 195 84.00 279 237 255
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 16 of 69
Table-4: Summary of water requirement (Hotel + Retail)
Water requirement summary(Hotel + Retail) KLD
Total Gross Water Requirement 556
Total Flushing Water Requirement 73
Total Domestic & Drinking Water Requirement 266
Total Swimming Pool requirement 18
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 17 of 69
Figure-5: Water Balance Diagram for Non-Monsoon Season Zero Liquid Discharge
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 18 of 69
Figure-6: Water Balance Diagram for Monsoon Season Zero Liquid Discharge
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 19 of 69
2.2. What is the capacity (dependable flow or yield) of the proposed source of water?
The proposed source of water is Delhi Jal Board. The total fresh water requirement for the
proposed project is approx. 298 KLD.
2.3. What is the quality of water required, in case, the supply is not from a municipal source?
(Provide physical, chemical, biological characteristics with class of water quality)
The source of water supply is from Delhi Jal Board. Permission from competent authority will be
sought if ground water is abstracted.
2.4. How much of the water requirement can be met from the recycling of treated wastewater?
(Give the details of quantities, sources and usage)
Total waste water generated is 255 KLD (Sewage + laundry), which will be treated in the STP of
capacity higher than the waste water generated i.e. 300 KLD (300 KLD STP and 60 KLD ETP,
which was situated at Plot No. 1). The 60 KLD Effluent Treatment Plant (ETP) is situated as site
Plot no. 1 which is common for both Asrani Inns & Resorts Pvt. Ltd. Plot 1 & Plot 2. The 21
KLD wastewater released from laundry effluents at Plot No. 2 has been treated in the same. The
treated water available is 245 KLD (@ of 90%) and it will be recycled and re-used for flushing,
road washing, landscaping, HVAC makeup, DG cooling, thus achieving Zero Liquid
Discharge. During monsoon season, as there will be less water requirement for landscaping, the
excess treated water to be discharged to sewer shall be in tune of 11 KLD. The details of
recycled water uses are provided in Table-11 below.
Table-5 Recycled Water Uses
Treated
Water Flushing
Landscaping
and road
washing
DG
Cooling
Road
washing
Mopping
and
Washing
HVAC
Cooling
Discharge
to
Sewer
Non-
Monsoon
Season
245
KLD
6 KLD 11KLD 20 KLD 5 KLD 2 KLD 170
KLD
0 KLD
Monsoon
Season
245
KLD 6 KLD 0 KLD 20 KLD
5 KLD 2 KLD 170
KLD
11 KLD
2.5. Will there be diversion of water from other users? (Please assess the impacts of the project
on other existing uses and quantities of consumption).
No adverse impact or diversion of water resources is expected from the proposed Project.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 20 of 69
2.6. What is the incremental pollution load from wastewater generated from the proposed
activity? (Give details of the quantities and composition of wastewater generated from the
proposed activity).
The proposed waste water generation is given in Table-6
Table-6: Details of Wastewater Generation
Details Water (KLD)
Water requirement for domestic & Drinking purpose 194
Wastewater generated from domestic use (@ 80% of domestic
water requirement) 153
Water requirement for Flushing Purpose 52
Wastewater generated from Flushing (@ 100% of flushing
requirement) 52
Miscellaneous (Laundry, Back wash wastewater, RO Plant
Reject) 50
Total Wastewater generated 255
2.7. Give details of the water requirements met from water harvesting? Furnish details of the
facilities created.
(i) Rainwater Collection Potential for Reuse or Recharging
Rainwater harvesting is the activity of direct collection of rainwater. Collected Rainwater
will be stored for direct use or for recharging the groundwater. Rain Water Harvesting is the
technique through which rain water is captured from the roof and paved surfaces and stored
in sub-surface ground water reservoir by adopting artificial recharge techniques. The run off
calculations for Rain Water Harvesting are shown in Table-7 and for pits in Table-8. Typical
design of Rain water harvesting pit is provided in the Figure-5.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 21 of 69
Table-7: Runoff Calculation of the Area
Table-8: Numbers of Pits Calculation
As per the calculation provided above, the nos. of RWH Pits is required 1, but we are proposing
8 no. of RWH pit as per MOEFCC notification number S.O. 3999( E) dated 09 December 2016.
S.
No. Type of Surface
Catchment
Area (m2)
Runoff
Coefficient
Intensity of
Rainfall
(mm/hr)
Intensity
of Rainfall
(m/hr)
Runoff
(m3 /hr)
1. Total Roof /Terrace
Area 3,106.28 0.85 11 0.011 29.04
Total Runoff (m3/hr) 29.04
S. No. Diameter of the
Pit
Depth of the
Pit
Volume of
the Pit
Runoff in
15 minutes
No. of
pits
required
No. of pits
proposed
1. 1.5 m 3 m 5.30 m3 7.26 1 4 pits
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 22 of 69
Figure-7: Typical Design of Rain Water Harvesting Pit
2.8. What would be the impact of the land use changes occurring due to the proposed project
on the runoff characteristics (quantitative as well as qualitative) of the area in the post
construction phase on a long term basis? Would it aggravate the problems of flooding or
water logging in any way?
There will not be such impact as the proposed project will be developed on a land base.
As the project site is almost plain land and the topography of the site is not anticipated to
change due to the project activities, hence, no impacts are expected on the drainage profile or
runoff characteristics after construction phase.
A network of storm water drain is proposed all along the direction along the main roads and
cross roads of suitable area size. All storm water drains will be covered with RC slabs so as to
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 23 of 69
prevent the entry of soil and dust. Storm water collected through storm water drains and
discharged into existing Storm Water Drains. Storm water drains will be constructed on all
the edges of roads.
2.9. What are the impacts of the proposal on the ground water? (Will there be tapping of
ground water; give the details of ground water table, recharging capacity, and approvals
obtained from competent authority, if any)
Adequate management measures are suggested to protect the water quality during construction
phase. Excavation during monsoon season will be avoided. Care would be taken to avoid soil
erosion. Community toilets shall be constructed on the site during construction phase and the
wastewater will be channelized to the septic tank in order to prevent wastewater from entering the
water bodies. Any area with loose debris within the site shall be planted. To prevent surface and
ground water contamination by oil/grease, leak proof containers would be used for storage and
transportation of oil/grease. The floors of oil/grease handling area would be kept effectively
impervious. Collection and settling of storm water, prohibition of equipment wash downs, and
prevention of soil loss and toxic release from the construction site will be adhered to minimize
water pollution.
2.10. What precautions/measures are taken to prevent the runoff from construction activities
polluting land & aquifers? (Give details of quantities and the measures taken to avoid the
adverse impacts)
Most of the storm water produced on site will be harvested for ground water recharge. Thus proper
management of this resource is a must to ensure that it is free of contamination. A detailed Storm
Water Management Plan will be developed which will consider the sources of storm water. The
plan will incorporate best management practices which will include the following:
Regular inspection and cleaning of storm drains.
Installation of clarifiers or Oil/Water separators system of adequate capacity around
parking areas and garages as per requirement.
Cover waste storage areas.
Avoid application of pesticides and herbicides before wet season.
Conducting routine inspections to ensure cleanliness.
Preparation of spill response plans, particularly for fuel and oil storage areas.
Provision of silt traps in storm water drains.
Good housekeeping in the above areas.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 24 of 69
2.11. How is the storm water from within the site managed? (State the provisions made to avoid
flooding of the area, details of the drainage facilities provided along with a site layout
indication contour levels).
No, mostly local laborers will be employed during the construction phase and thus negligible
quantities of wastes will be generated. Mobile toilets will be provided and the wastewater
generated will be collected in septic tanks.
2.12. Will the deployment of construction laborers particularly in the peak period lead to
unsanitary conditions around the project site (Justify with proper explanation).
The 255 KLD sewage generated will be treated in the onsite STP, and the capacity of Sewage
Treatment Plant (STP) will be higher of waste water generated i.e. 300 KLD and the 22 KLD
waste water from laundry will be treat on 60 KLD ETP
2.13. What on-site facilities are provided for the collection, treatment & safe disposal of sewage?
(Give details of the quantities of wastewater generation, treatment capacities with
technology & facilities for recycling and disposal).
Waste water generated from the site is 255 KLD. An STP of capacity 300 KLD (300 KLD STP
and 60 KLD ETP) is proposed by the project.
Proposed Technology
Membrane Bio-Reactor (MBR) Technology is proposed.
This technology combines the aeration and secondary clarifier in one and the same tank by
sucking out the aerated mixed liquor through membranes instead of settling in a separate
downstream tank and to that extent, it does yield a treated sewage with BOD <5mg/L and
suspended solids <5mg/L and hence being clear and virtually transparent treated effluent.
Besides its claimed ability to hold and sustain mixed liquor suspended solids (MLSS) of three to
four times than what is possible in the conventional aeration tanks which in turn offers
minimization of the footprint of the treatment plant. Diffused aeration is of course needed. The
membrane is a matter of proprietorship and the throughput per membrane module offered by
various vendors are different and also each vendor advocates various shapes of the membranes
as flat sheet, cross flow, dead end flow etc, which makes it difficult for common validated
standard design criteria.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 25 of 69
Advantages:
High quality effluent for reuse without separate nutrient removal and fine Filtration
Compact system reduces plant footprint by 25-40% compared to conventional STP.
These membranes are stated to be durable to ensure reliability and long membrane life,
and low membrane replacement frequency.
The modular system is expandable higher stability to organic shocks /upsets due to higher
MLSS concentration.
The process operates under low suction, the ideal filtration method for small to large-
scale membrane facilities, hence low power consumption.
Automated system makes the process operations easier to operate.
Disadvantages:
Each vendor advocates his own criteria for the membranes and their types which make it
difficult to bring about a common and validated design criteria.
It is not possible to cannibalize the system between different manufacturers.
High reliance on energy input in the absence of bio methanation.
Patented process technology and decanters defying local cannibalization.
2.14. Give details of dual plumbing system if treated waste is used for flushing of toilets or any
other use.
Dual plumbing system that utilizes separate piping systems for freshwater and recycled
wastewater will be adopted for the project. Treated water from the on-site STP is estimated at
245 KLD. The recycled water system shall utilize this treated water and serve for non-contact
uses such as flushing, horticulture, HVAC cooling etc.
Dual Plumbing Plan is attached as Annexure-XII
3. VEGETATION
3.1. Is there any threat of the project to the biodiversity? (Give a description of the local
ecosystem with its unique features, if any)
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 26 of 69
There is no such area within 10km radius of the project site. Even the local flora and other
species will not be affected due to the pre and post construction activities. Also, there are no eco-
sensitive areas in the project vicinity.
3.2. Will the construction involve extensive clearing or modification of vegetation? (Provide a
detailed account of the trees & vegetation affected by the project)
No trees are required to be cut.
3.3. What are the measures proposed to be taken to minimize the likely impacts on important
site features (Give details of proposal for tree plantation, landscaping, creation of water
bodies etc along with a layout plan to an appropriate scale?)
The capability of plants to act as a sink for air contaminants has been addressed by a number of
reviews. Various studies indicate that the surface of vegetation provides a major filtration and
reaction surface to the atmosphere for removing pollutants from the atmosphere. Therefore, the
green belt is essential feature of any developmental project because it acts as a pollution
cleansing region, improvement of the aesthetic value of the project and a noise buffer.
The suggested trees and shrubs are given in Table-9.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 27 of 69
Table-9: Suggested Species to be used for Greenbelt Development
S.
No.
Scientific Name English
Name
Common
Name
Family Role in Pollution
Abatement
A. Tree Species (10 to15 mtrs.)
1. Delonix regia (Bojer)
Rafin
Flame
Boyant
Red
Gulmohur
Caesalpinaceae
Fast growing,
deciduous,
flowering in April-
June
and tolerant to air
pollution
2. Jacaranda mimosaefolia - Blue
Gulmohar
Bignoniaceae Fast growing,
deciduous,
flowering in April-
June and tolerant
to air pollution
3. Khurejia sp. Light Red
Flowers
4. Saraca ashoka Ashok
Tree
Ashok Caesalpiniaceae Fast growing,
evergreen and
tolerant to air
pollution
5. Bauhinia purpurea Linn. Butterfly
Tree
Kachnar Caesalpiniaceae Fast growing,
deciduous,
flowering in April-
June
and tolerant to air
pollution
6. Cassia siamea Lamk. Iron Wood
Tree
Kannai Caesalpiniaceae Fast growing,
evergreen,
flowering in
February – April,
September-
October and
tolerant to air
pollution
7. Cassia fistula Linn. Indian
Laburnum
Amaltash Caesalpiniaceae Fast growing,
deciduous,
flowering in
March-May
and tolerant to air
pollution
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 28 of 69
S.
No.
Scientific Name English
Name
Common
Name
Family Role in Pollution
Abatement
8. Lagerstroemia speciosa
Linn
Queen
Crape
Myrte
Larool Lythraceae Fast growing,
evergreen,
flowering in April-
June and tolerant
to air pollution
9. Callistemon citrinus
(Curtis) Stapf
Scarlet
Bottle
Brush
Bottle
brush,
Myrtaceae Slow growing,
evergreen,
flowering
throughout the
year and tolerant to
air pollution
B. Shrubs (1 ft. from Earth)
1. Hamelia patens Jacq. Scarlet
Bush
- Rubiaceae Fast growing,
evergreen,
flowering in
October – January
and tolerant to air
pollution
2. Jatropha Sp. Red
Jatropha
- Euphorbiaceae Fast growing and
deciduous
3. Hibiscus rosa-chinensis
Linn.
Chinese
Hibiscus
Gurhal Malvaceae Fast growing,
evergreen,
flowering
throughout the
year and
propagation can be
done by cutting.
C. Creepers
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 29 of 69
S.
No.
Scientific Name English
Name
Common
Name
Family Role in Pollution
Abatement
1. Quisqualis indica Linn. Rangoon
Creeper
Madhumati
Orange
Combretaceae The plant is used
as an herbal
medicine.
Decoctions of the
root, seed or fruit
can be used as
antihelmintic to
expel parasitic
worms or for
alleviating
diarrhea. Fruit
decoction can also
be used for
gargling. The fruits
are also used to
combat nephritis.
Leaves can be used
to relieve pain
caused by fever.
The roots are used
to treat
rheumatism.
2. Clerodendron
spelendence
Dark Red
Flower
- Lamiaceae Fast growing and
used for
ornamental
purpose.
3. Hiptage madablota
Gaertn.
Malti Malpighiaceae
Fast growing and
used for
ornamental
purpose.
D. Species for Ground Coverage
1. Ipomoea lacunosa Convolvulaceae Fast growing and
used for
ornamental
purpose.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 30 of 69
S.
No.
Scientific Name English
Name
Common
Name
Family Role in Pollution
Abatement
2. Asparagus racemosus Satavari Liliaceae Fast growing and
used for greenery
purpose. The
species have also
high medicinal
value in
international
market.
3. Alternanthera sessilis - - Amaranthaceae Fast growing and
used for greenery
and ornamental
purpose.
4. Buddleja
madagascariensis Lam. Orange
Buddleia
Smokebush
,
Buddleiaceae It is a fragrant
ornamental
shrub with a
sprawling habit
that is cultivated.
This species is an
aggressive plant
that is capable of
spreading beyond
the confines of the
garden.
E. Ornamental Plant (Short Height)
1. Ficus panda - - Ficaceae Fast growing,
evergreen and used
as bonsai for
ornamental
purpose.
2. Ficus banjamina Linn. Chilubar - Ficaceae Fast growing,
evergreen,
flowering in
September to
November.
3. Ficus nuda - - Ficaceae Fast growing,
evergreen and used
as bonsai for
ornamental
purpose.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 31 of 69
S.
No.
Scientific Name English
Name
Common
Name
Family Role in Pollution
Abatement
4. Juniperus communis Common
Juniper
- Pinaceae Fast growing,
evergreen,
flowering in March
to April.
5. Livistonia chinensis, China
Palm
- Palmaceae China Palm Tree
would entice
everyone with its
excellent quality
and visually
appealing
appearance and is
widely used for
enhancing the
visual beauty of
the place. This
China Palm Tree is
renowned for its
ability to circulate
the fresh and pure
air in the
environment and
supply pure
oxygen in bulk
capacities.
Impact will be minimized by existing green cover and soft landscape. Green area of 1,849 m2
is proposed at the project site.
Landscape plan is attached as Annexure-VIII.
4. FAUNA
4.1. Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of
barriers for their movement? Provide the details.
No
4.2. Any direct or indirect impacts on the avifauna of the area? Provide details.
No
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 32 of 69
4.3. Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on
fauna.
Not Applicable
5. AIR ENVIRONMENT
5.1. Will the project increase atmospheric concentration of gases & result in heat islands? (Give
details of background air quality levels with predicted values based on dispersion models
taking into account the increased traffic generation as a result of the proposed
constructions)
The only source of air emissions will be the D.G Sets that will be installed as a power backup
during power failure. Hence, there will not be any significant increase in the concentration of
PM10, PM2.5, SO2, NO2, CO.
Further, in the construction project there is no major source of gaseous pollutants are
associated and prediction of pollutants would be required for the projects associated with
major air pollution sources. Considering these chances of pollution associated with vehicular
congestion is almost negligible.
5.2. What are the impacts on generation of dust, smoke, odorous fumes or other hazardous
gases? Give details in relation to all the meteorological parameters.
Source of dust would be material handling during construction and ground activities. Sources
of smoke would be DG sets and there will not be any hazardous gaseous emission from the
proposed project.
During construction period dust will be controlled by sprinkling of water.
5.3. Will the proposal create shortage of parking space for vehicles? Furnish details of the
present level of transport infrastructure and measures proposed for improvement
including the traffic management at the entry & exit to the project site.
No, the proposed project will not create shortage of parking space for the vehicle. The
proposed project will have sufficient parking facilities and space.
Parking facility will be provided as per the norms and standards of the Delhi Building bye
Laws.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 33 of 69
The parking spaces are provided on the surface and in the basement. The total parking
required for the proposed Hotel project is 517 ECS as per the Building Byelaws of Delhi
while parking provided is 505 ECS.
5.4. Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian
pathways, footpaths etc., with areas under each category.
Internal road width is proposed to be 6m for internal traffic management.
Site Plan showing internal roads is attached as Annexure-V.
5.5. Will there be significant increase in traffic noise & vibrations? Give details of the sources
and the measures proposed for mitigation of the above.
There would not be any significant increase in traffic noise and vibration due to the proposed
project. Source of noise would be vehicular movement. The green belt around the project site
will act as effective noise and dust absorber.
All tolerant plants are not necessarily good for green belts e.g. Xerophytes with sunken
stomata can withstand pollution by avoidance but are poor absorbers of pollutants due to low
gaseous exchange capacity. Therefore selection of plants is very important in green belt
development for effective removal of suspended particulate matter and for absorption of
gases.
5.6. What will be the impact of DG sets & other equipment on noise levels & vibration in &
ambient air quality around the project site? Provide details.
As regards DG sets, these shall be provided with acoustic chambers ensuring maximum
outside noise level of 70-75 dB (A) at 1.0 m distance.
The noise level from the DG sets will be maximum 75 dB (A) (at 1.0 m distance) as per the
prescribed compliance standards of the MoEF. The resultant outside noise level expected
from diesel generator sources in simultaneous operation but housed in a efficient acoustic
enclosure shall not exceed 75 dB (A).
Even if the DG sets are housed separately, the total resultant maximum sound pressure level of
the DG sets operating together would not be more than 75 dB (A) by the addition of sound
intensities, based on equation used for calculating cumulative noise.
Leq,T = 10 log{1/n n∑i=110
Li/10}
Where, Li = levels observed at „n‟ equally spaced sources during interval T.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 34 of 69
It is pertinent to mention here that DG sets will be used as power back up units and it is
anticipated that they shall operate only during hours of power failure. However, as they will be
acoustically enclosed, negligible impacts can be expected on the outside community. The
acoustic enclosure would reduce outside noise levels to less than 70 dB (A). It is further
desirable to increase the acoustic efficiency of enclosure to reduce the noise levels to less than
60-65 dB (A).
Another type of likely impact is due to vibration of the DG sets on the buildings and the working
structures. As far as impacts of vibrations are concerned, there would be adequate structural
treatment provided to the foundation of the DG sets (as part of the building design). The DG sets
foundation will comprise of heavy weight inertia concrete block. The generator will be mounted
on Cushy Foot mounting and the concrete block will be isolated from the adjoining floor. Thus
no vibration impacts are expected from the DG sets.
Also during operation stage DG sets will be provided with sufficient stack height. The maximum
height of the proposed building is 50 m
In case of power failure, 3 DG sets of 2000 KVA capacity are provided for backup power supply
system and 1 DG set of 1500 kVA will be on standby. The stack height H, for these units is as
follows:
6. AESTHETICS
6.1. Will the proposed constructions in any way result in the obstruction of a view, scenic
amenity or landscapes? Are these considerations taken into account by the proponents?
The site lies in an urbanized settlement and is well planned. Thus, no obstruction of view or
scenic beauty or landscape is anticipated. Furthermore, the construction will be planned in such a
way that the organized open spaces and landscaped areas will render the plot aesthetically
appealing.
6.2. Will there be any adverse impacts from new constructions on the existing structures? What
are the considerations taken into account?
No impacts anticipated.
6.3. Whether there are any local considerations of urban form & urban design influencing the
design criteria? They may be explicitly spelt out.
Yes, the building will be designed as per the Delhi Urban Art Commission. The development to
be done is in accordance with Delhi Master Plan 2021. Considering the above; the existing land
use is not expected to get altered due to construction of proposed project.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 35 of 69
6.4. Are there any anthropological or archaeological sites or artifact nearby? State if any other
significant features in the vicinity of the proposed site have been considered.
The archaeological site within 15 km of project site is given in Table-10.
Table-10: Archeological sites within 15 Km of the project site
S. No. Name of the Site Aerial Distance
(Km)
Direction from
the site location
1. Red Fort 10.26 km SE
2. Lal Darwaza, Hauz Qazi 9.56 km SE
7. SOCIO-ECONOMIC ASPECTS
7.1. Will the proposal result in any changes to the demographic structure of local population?
Provide the details.
Establishment of any Hotel project leads to socio-economic changes. Development of a society
that will stand robustly against economic or natural calamities. It fulfills the required trained man
power for the development of country. Influx of population leads to change in economic status
of the community. During construction period local people will be engaged and hence there will
be temporary increase in the number of people, till construction complete. During operation
period, there will be increase of approx. 4,000 persons in the demographic structure of local
population..
7.2. Give details of the existing social infrastructure around the proposed project.
The existing Social infrastructure around the proposed project is as shown in Table-11.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 36 of 69
Table-11: Social Infrastructure around the project site.
List of Schools:
Guru Gobind Singh College
M.M. Public School
Ravindra Public School
List of Hospitals:
Max Hospital
Bhagvan Mahavir Hospital
Sunder Lal Jain Hospital
List of Temples:
Hanuman Mandir
Kali Mata Mandir
600 mtrs., North-East
460 mtrs., West
285 mtrs., North
450 mtrs ,East
Approx.2 km, North
3.4 km, East.
600 m, South
850 m, South-West
7.3. Will the project cause adverse effects on local communities, disturbance to sacred sites or
other cultural values? What are the safeguards proposed?
No, the proposed development will not have adverse effects on local communities. On the
contrary, it is expected that there will be major positive impacts due to development of the
proposed project. Positive impacts would include improvement in employment directly and
economic condition of society indirectly.
8. BUILDING MATERIALS
8.1. May involve the use of building materials with high-embodied energy. Are the construction
materials produced with energy efficient processes? (Give details of energy conservation
measures in the selection of building materials and their energy efficiency).
The main construction materials being utilized in the construction of the proposed project
include Stone Aggregate, Coarse sand/fine sand, Steel, Fly Ash, Sand Stone, Granite/Marble,
Bricks, and Blocks, glass etc.
These construction materials will be procured from the reputed suppliers/manufacturers and
thus it is expected that they are produced with energy efficient processes. Most of the quality
grade building material production facilities and industries now use energy efficient
processes.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 37 of 69
8.2. Transport and handling of materials during construction may result in pollution, noise &
public nuisance. What measures are taken to minimize the impacts?
The transport and handling of materials during construction phase has potential impacts on air
and noise emissions in the vicinity. Thus, to control this, various mitigation measures will be
adopted to minimize the impacts.
AIR EMISSIONS
Dust Suppression: The most cost-effective dust suppressant applied to mitigate airborne dust is
water, because of its efficiency as well as ready availability on the construction site. Water can
be applied using water trucks, handheld sprays and automatic sprinkler systems depending on the
location. Water spraying at the site also effectively suppresses dust generated. Results have
proven that for about 80% of such active area(s), the water spray suppresses airborne dust by
about >90%.
Reduction of Vehicular Emissions: The transport of materials such as concrete, stone, cement,
asphalt, etc. to the construction site generally generates significant amount of pollutants on road.
Therefore, setting up of local facilities such as temporary portable concrete mixing plants, stone
cutting at site, etc. with adequate pollution control devices eliminates significant emissions
during haulage of materials will be implemented.
Emission Control for Construction Equipment: Construction equipment and heavy transport
vehicles shall meet emission standards like Bharat Stage -III requirements for vehicles. The
operation and maintenance of all vehicles, equipments deployed on site by different contractors
will be regulated and effectively monitored. The Pollution under Control (PUC) certification will
be ensured for proper O&M of vehicles.
Improved Maintenance: Recognizing that significant emission reductions can be achieved
through regular equipment and vehicle maintenance, all site contractors are asked to take
necessary steps for proper maintenance of vehicle and equipments. A monetary incentive/
disincentive provision encourages contractors to comply with regular maintenance requirements.
The fuel used in the equipments, DG sets and vehicles will be of good quality with low
“Sulphur” percentage by following the norms prevailing in project area.
Reduction of On-site Construction Time: The heavy construction activities will be confined to
the daytime to avoid higher impacts during the night time. During daytime, there is higher
atmospheric dilution. Rapid on-site construction would reduce the duration of traffic interference
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 38 of 69
and therefore, reduce emissions from traffic delay. Off-site fabrication of various moulded
structural components, obtaining proper cut size of stone, pre-fabricated concrete slabs, etc. shall
also enhance the quality of work environment at the construction site because other factors such
as traffic congestion and emissions are then not relevant.
NOISE EMISSIONS
The mitigation measures concerning technological control at source (of vehicles) shall meet
the minimum compliance requirements for manufacturing stage. Besides these, other
measures shall be of preventive nature as follows:
Restriction of Time of Construction: The heavy construction and transport activities shall be
restricted to daytime operation when the background noise levels are high so that impacts
like sleep disturbance during the night time are avoided.
Provision of Noise Barrier: No extra barrier will be provided because it is within the
premises of the project site.
Proper Maintenance of Construction Equipment/Vehicles: Proper operation and maintenance
of heavy equipment as well as transport vehicles shall also ensure lower noise emissions.
Occupational & Passive Protection: Ear plugs, ear muffs, etc. will be provided to workers
handling high noise equipment or stone cutting operations shall protect them from high noise
exposure.
8.3. Are recycled materials used in roads and structures? State the extent of savings achieved?
Fly ash used materials would be utilized for paving work etc, if viable. Also, the construction
waste (particularly the construction debris) will be used on the project site for leveling
purposes. An approximate saving of 5% to 7% is proposed to be achieved.
8.4. Give details of the methods of collection, segregation & disposal of the garbage generated
during the operation phases of the project.
The proposed project is expected to generate certain types of wastes which would include
both non-hazardous and some hazardous wastes. The non-hazardous wastes generated at the
project would be municipal solid waste including paper & cardboard wastes, food wastes,
plastic wastes etc. STP sludge and other solid waste would also generate.
It is estimated that total quantity of municipal solid waste generated will be approx. 745
kg/day from the proposed project.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 39 of 69
The solid waste expected to be generated by the population in the proposed Project can be
broadly categorized into bio-degradable and non-biodegradable. These solid wastes will be
collected separately by putting tow type of separate bins at the source of generation.
The proposed Project is also expected to generate following categories of hazardous wastes:
Used Oil - from DG sets
Oil Contaminated Wastes - maintenance operations, etc.
MITIGATION MEASURES:
Bins for storage of bio-degradable wastes shall be painted green, and those for storage of
other wastes shall be painted blue.
Overall it would be ensured that all waste fractions are appropriately recycled/ disposed of
through authorized recyclers/re-refiners/contractors. Records will be kept regarding amount
and characteristics of all types of wastes.
Paper & cardboard wastes, plastic wastes, metal wastes and other recyclable wastes will be
sold to authorized contractors.
The STP sludge will be used as a bio-manure for green area.
As regards hazardous wastes, the building management staff of the proposed project will
review the proposed operations and make a thorough "applicability analysis" of the
Hazardous Waste Rules, to identify specific wastes, to be generated in the proposed project,
that shall be categorized as hazardous wastes. The management staff would then manage
hazardous waste as per the prevailing rules. The management staff of the proposed project
would ensure compliance with all the conditions on a continual basis.
Hazardous wastes shall be stored in secured places with adequate secondary containment and
labelling as per the requirements of Hazardous Waste Rules.
Appropriate records of hazardous wastes generation and disposal (in Form-3, Form-4, Form-
9, Form-13 etc.) shall be maintained as per the requirements of MoEF‟CCs Rule.
The used oil and oil-contaminated wastes shall be disposed of through authorized
recyclers/re-refiners. Any other hazardous wastes, generated on-site, shall be sold only to
authorized contractors.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 40 of 69
9. ENERGY CONSERVATION
9.1. Give details of the power requirements, source of supply, backup source etc. What is the
energy consumption assumed per square foot of built-up area? How have you tried to
minimize energy consumption?
Energy Conservation Measures:
Provision of solar water heater for supply of hot –water for various uses.
Fly ash bricks shall be used.
Use of CFL lights in circulation area and in toilets.
P.V. Cell system shall be installed for all street and compound lighting.
The external surfaces of all the buildings will have granite stone cladding upto first floor
level and aluminum composite panels cladding above to have maintenance free external
façade of the building.
All roofs shall be insulated with foam concrete to reduce the heat gain through the roof.
Use of adequate window areas for getting natural light and ventilation.
Use of electrical fittings, fans, A/C pumps and plants with ultra-star rating to save
electricity.
To minimize the energy consumption & power load, building can be designed and
constructed according to Energy Conservation Building Code 2007 which sets minimum
energy standards for buildings.
The proposed project will adopt various energy conservation measures. The range of these
energy efficiency measures can be broadly categorized under:
Architectural Design Features;
Energy saving preventive practices; and
Behavioral change and raising awareness.
Energy conservation program will include measures taken for both energy demand as well as
supply management
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 41 of 69
The energy conservation efforts may consist of the following mitigation measures:
a. Architectural Design Features
Most of the external surface of the building will be design in way to have an air gap between
the wall surface and the external skin. This should reduce the transmission of heat into the
building as the heat would get dissipated into the air gap to an extent. Landscaping will be
carefully considered within the overall architectural concept.
b. Energy Saving Practices:
Purchase of energy efficient appliances.
Constant monitoring of energy consumption and defining targets for energy conservation.
Adjusting the settings and illumination levels to ensure minimum energy used for desired
comfort levels.
Use of Light Emitting Diodes (LED) and low voltage lighting.
c. Behavioral Change for Reducing the Consumption
Train all staff and operators for energy efficiency measures.
Promoting staffs‟ awareness on energy conservation. Training of staffs on methods of energy conservation and to be vigilant of such opportunities.
Turn on all lights when not in use, especially in conference rooms and turn down remaining
lighting levels where ever possible.
Passive Solar Design Considerations
Following are the consideration adopted for passive solar design of the buildings in the proposed
project:
SUPPLY
Utililise Energy-efficient
equipment.
Exploring the possibilities of
utilizing renewable energy.
Reduce Consumption.
Use energy-efficient building designs
and ventilation systems.
Create staff awareness and conduct
training programme.
Maximizing the use of Natural lighting.
DEMAND
Energy Conservation,
Monitoring & Management
system
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 42 of 69
Maximum openings would be towards the north to get natural light that will not unduly heat
up the interiors.
Least opening would be provided towards southern and western walls so as to cut out the hot
incident rays of the sun.
Windows provided would be shaded adequately by designing double layer glass glazing so
that no direct rays of sun can come into the building.
Most of the external surface of the building will be designed in a way to have an air gap between
the wall surface and the external skin. This should reduce the transmission of heat into the
building as the heat would get dissipated into the air gap to an extent.
As an endnote, the design has been a conscious effort to make a modern building with local
materials and will not use excessive amount of glass and steel. The glasses that would be used on
the surfaces that have direct incident rays have double glazing.
9.2 What type of, and capacity of, power back-up to you plan to provide?
In case of power failure, 3 DG sets of 2000 KVA capacity are provided for backup power
supply system and 1 DG set of 1500 kVA will be on standby.
9.3. What are the characteristics of the glass you plan to use? Provide specifications of its
characteristics related to both short wave and long wave radiation?
It is proposed to use predominantly two types of glazing in the building:
Laminated Glass 8 mm Clear + 1.52 PVB + 6 mm Clear Tempered
Hermetically Sealed Double Glazing 8 mm Clear Tempered + 12 mm Air gap + 6 mm Clear
Tempered
Both the glass types will be shaded with a dense screen, which effectively shade 100% of the
glass throughout the day and the year. The effective Solar Heat Gain Coefficient (SHGC) is
therefore significantly lower than the glazing SHGC alone and meets the ECBC glazing U-factor
and SHGC requirements for 24 Hour Buildings in Composite Climate.
Glass Specifications:
Laminated Glass 8 mm Clear + 1.52 PVB + 6 mm Clear Tempered
U-Value = 5.6 W/m2 K
Solar Heat Gain Coefficient (SHGC) of Glass = 0.77
The windows will be shaded with a dense screen, which does not let any direct sun hit the glass.
Thus, the effective SHGC = 0.77 x 0.50 x 0.50 = 0.19
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 43 of 69
(100% Shaded Overhang Projection Factor 1.0 Multiplication Factor = 0.5 as per Section 4.3.3
of ECBC)
Light Transmittance = 0.87
Hermetically Sealed Double Glazing 8 mm Clear Tempered + 12 mm Air gap + 6 mm Clear
Tempered
U-Value = 2.8 W/m2 K
Solar Heat Gain Coefficient (SHGC) of Glass = 0.69
The windows will be shaded with a dense screen, which does not let any direct sun hit the glass.
Thus, the effective SHGC = 0.69 x 0.50 x 0.50 = 0.17
(100% Shaded Overhang Projection Factor 1.0 Multiplication Factor = 0.5 as per Section 4.3.3
of ECBC)
Light Transmittance = 0.78
9.4. What passive solar architectural features are being used in the building? Illustrate the
applications made in the proposed project.
The proposed project is to be developed on a site in an urban area. The land base for the project
is already categorized for hotel development. The area in the immediate neighborhood is
residential /commercial. The design of the building will be different in terms of its ventilation
and sunlight capacity provisions. The design concept of the building has a combination of open
walkways and terraces that will feed into air-conditioned and sealed areas. Only ~35% of total
plot area is covered with buildings. Thus, most of the ground will be left open to sky. In addition
to these, the project is also proposing to provide landscaped terrace garden for acting as a cooling
mechanism for the entire building. Use of double glazed LOW-e glass will further allow for
natural ventilation and a lot of natural light into the building. Considering the low ground
coverage in the complex, open spaces will help in getting in a lot of natural light into the
buildings and allow good circulation of fresh air in the complex. Based on the sun path diagram
for the project area, it can be seen that the sun travels from East to West bending sharply towards
the south during the hottest hours of the day. This would translate into the fact that the hottest
rays of the sun would be incident from the south.
Based on the above, the following considerations will be made:
All windows and openings should be towards the north and northeast to get natural light that
will not unduly heat up the interiors
The southern and western walls should be with least openings so as to cut out the hot incident
rays of the sun
If openings are provided on the southern and western faces of the building, they should be
shaded so that no direct rays of sun can come into the building
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 44 of 69
The proposed project will provide enough day light factors in the building to permit maximum
day light to interior to minimize overall energy consumption. These features will also minimize
the impact of climate both in summer and in winter and as a result, the use of electricity will
likely to be reduced. In addition to the above, it has been noted that, traditionally, buildings in
the hot and dry climate of this part of India have made the use of water fountains and other water
bodies to lend a cooling effect. All the roofs will be insulated so as to reduce the heat gain into
the building due to direct sunlight. Further, landscaped garden will be created on terrace. Most of
the external surface of the building will be dry clad in local sandstone such that there is an air
gap of about 60 mm between the wall surface and the external skin. This should reduce the
transmission of heat into the building as the heat would get dissipated into the air gap to an
extent.
9.5. Does the layout of streets & buildings maximize the potential for solar energy devices?
Have you considered the use of street lighting, emergency lighting and solar hot water
systems for use in the building complex? Substantiate with details.
Solar street lighting and solar water heater will be provided.
9.6. Is shading effectively used to reduce cooling/heating loads? What principles have been used
to maximize the shading of Walls on the East and the West and the Roof? How much
energy saving has been effected?
Shading can reduce solar gain through windows. For shading effect in the proposed project
double layer glass glazing has been proposed to reduce solar gain.
9.7. Do the structures use energy-efficient space conditioning, lighting and mechanical systems?
Provide technical details. Provide details of the transformers and motor efficiencies,
lighting intensity and air-conditioning load assumptions? Are you using CFC and HCFC
free chillers? Provide specifications.
The HVAC systems have been designed based on the following standard & guidelines:
National Building Code of India, 2016
ASHRAE Hand Book
- Refrigeration 2006
- Fundamentals 2005
- Systems & Equipment 2004
- Applications 2003
Duct construction standards as per relevant BIS codes & SMACNA standards
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 45 of 69
Air Filters as per ASHRAE 52.2-1999
Kitchen Exhaust Ducts as per NFPA and ASHRAE
Indoor Air Quality as per ASHRAE 62.1 - 2004
Motors, cabling, wiring and accessories as per BIS codes.
CENTRAL AIR CONDITIONING SYSTEM
A central air conditioning system shall be designed to provide year round thermal environmental
control for Guest Rooms, Health Club, Lobby, Banquet Halls, Pre-Function, Function Rooms,
Meeting rooms, Coffee Shop, Restaurants, Administrative Offices and Back-of-the-House areas.
Air conditioning shall be provided by a central variable flow chilled water recirculation system
for maximum energy conservation.
The central air conditioning system shall consist of water chilling units, multiple primary chilled
water pumps, secondary chilled water pumps with variable frequency inverters, condensing
water pumps, FRP induced draft cooling towers, air handling units and fan coil units, chilled and
Condensing water piping, air distribution system, insulation, electrical panels, wiring, control
wiring and Earthing.
Cooling towers for air conditioning system shall be selected for minimum drift losses and
minimum noise, and shall be installed on terrace away from the Public Areas, Guest Rooms.
These shall be FRP construction induced draft type. Cooling tower motors shall be provided with
Variable Frequency Inverter (VFI) to conserve energy during periods of low ambient wet bulb
temperature as cooling towers shall operate round the clock (365 days a year).
Operating the motor through VFI shall save energy by operating the cooling tower fan at 30-
100% speed, thus conserving motor BHP. The speed shall vary in response to ambient wet bulb
temperature and cooling tower leaving water temperature.
All mechanical equipment such as chilling units, pumps, AHU‟s and larger ventilation fans shall be provided with energy efficient motors in order to attain energy savings, since all these
equipment shall operate for extended periods of time.
AIR CONDITIONING SYSTEM
Chilled Water Generation & Distribution
Central air conditioning shall be provided by a Central Variable flow chilled water system for
maximum energy conservation. Chilled water distribution shall be designed to achieve maximum
energy conservation. Various public spaces shall be grouped together according to their location
&similarity in usage and working hours. Following zones are considered:
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 46 of 69
Zone `A‟ : Banquet Hall + Pre-function
Zone „B‟ : Lobby + Coffee Shop + BOH + Restaurant + Retail + Kitchen +Administration Office
Zone `C‟ : Guest Rooms + Guest Corridors
Each zone shall have its own set of chilled water pumps (including a standby) with variable
speed drive and chilled water circuit to achieve variable water flow. Water flow in load circuit
shall be varied but the same through chiller shall remain constant. To achieve this, two separate
circuits i.e. primary and secondary, coupled with automatic bypass line shall be used. Each
chiller shall have its own dedicated primary chilled water and condensing water pump.
Secondary chilled water pumps with variable frequency inverter shall be used for each load
circuit. By monitoring the pressure differential between chilled water supply and return header,
the speed of secondary chilled water pump shall be automatically varied, thus conserving pump
brake horse power. The main advantage of this system is that the circulation of chilled water
through the entire Hotel is avoided, and chilled water is supplied according to demand in each
zone, thus achieving energy conservation and flexibility in operation.
9.8. What are the likely effects of the building activity in altering the micro-climates? Provide a
self-assessment on the likely impacts of the proposed construction on creation of heat island
& inversion effects?
No effect. The building will use energy efficient and environmental friendly designs that will
control formulation of heat island effect. There will be also sufficient green cover at the site to
reduce formation of heat island.
9.9. What are the thermal characteristics of the building envelope? (a) roof; (b) external walls;
and (c) fenestration? Give details of the material used and the U-values or the R values of
the individual components.
In accordance with Energy Conservation Building (ECBC) Code 2008 norms, Delhi comes
under Composite Climate Zone. Hence, based on ECBC norms, U values are considered as
follows:
Roofs:
Climate Zone
Maximum U-
Factor of the
overall assembly
(W/m2-O
C)
Minimum R-Value of
Insulation alone
(m2-O
C/W)
Composite U-0.261 R-3.5
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 47 of 69
Opaque Walls:
Climate Zone
Maximum U-
Factor of the
overall assembly
(W/m2-O
C)
Minimum R-Value of
Insulation alone
(m2-O
C/W)
Composite U-0.440 R-2.10
Vertical Fenestration:
Climate Zone
WWR=40% 40%
<WWR<=60%
Maximum U-
factor
Maximum
SHGC
Maximum
SHGC
Composite 1.7 0.25 0.2
9.10 What precautions & safety measures are proposed against fire hazards? Furnish
details of emergency plans.
Adequate fire protection facilities will be installed including fire detectors, fire alarm and
fire-fighting system. All fire protection facilities would be designed as per the National
Building Code, 2016.
Fire Service Access:
The fire service personnel will be able to get hose lines to all portions of the building.
Fire Tender, Rescue Tender, Hydraulic Platform access roads will be wide enough to
support the equipment used by the fire service. They also will be able to support the
weight of Fire Tender/Rescue Tender/ Hydraulic Platform. Access roads will be provided
for emergency uses designated as fire lanes and vehicle parking will be prohibited.
Fire-fighting water suppliers:
Adequate quantity of Water supply will be maintained in underground tanks as per
National Building Code / National Fire Protection Association will be available for fire
service to fight a fire in a building as shown in site plan. All fire safety system will be run
from fire control room as provided in project.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 48 of 69
Disaster Management Plan:
The proposed project encompasses the lives of a large number of people. It also involves
installation of various structures and machineries that meet the comfort and needs of its
population but may also pose serious threat to the occupants in case of an accident. It is thus
considered necessary to carry out a risk assessment and disaster management plan for the project.
Type of Emergency, External and Internal Origin of Hazards
It is attempted to plan and construct the buildings following all safety norms. However, it is not
always possible to totally eliminate such eventualities and random failures of equipment or
human errors. An essential part of major hazard control has therefore, to be concerned with
mitigating the effects of such emergency and restoration of normalcy at the earliest. A detailed
Table showing activities during construction and operation phase along with mitigation measures
are given in Table-12 below:.
Table-12: Activities during Construction and Operation along with Mitigation Measures
Hazards Associated with Activities Control / Mitigation Measures
Manual Handling
Strains and sprains - incorrect lifting - too
heavy loads -twisting - bending -
repetitive movement - body vibration.
Exercise/ warm up-get help when needed-
control loads-rest breaks/ no exhaustion-
no rapid movement/ twisting/
bending/repetitive movement - good
housekeeping.
Falls - Slips - Trips
Falls on same level - falls to surfaces
below - poor housekeeping- slippery
surfaces uneven surfaces -poor access to
work areas climbing on and off plant-
unloading materials into excavations wind
- falling objects.
Housekeeping - tidy workplace -
guardrails, handholds, harnesses, hole
cover, hoarding, no slippery floors/trip
hazards - clear/ safe access to work areas-
egress from work areas - dust/water
controlled - PPE.
Fire
Flammable liquids/Gases like LPG,
Diesel Storage area and combustible
building materials - poor housekeeping -
grinding sparks - open flames, absence of
Fire hydrant network.
Combustible/ flammable materials
properly stored / used -good
housekeeping-fire extinguishers made
available & Fire hydrant Network with
reserve Fire water (As per NFPA Code) -
Emergency Plan in case of Fire or collapse
of structure.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 49 of 69
Hazards Associated with Activities Control / Mitigation Measures
Absence of Personal Protective
Equipment
Lack of adequate footwear- head
protection hearing/ eye protection -
respiratory protection-gloves-goggles.
Head / face- footwear- hearing / eye-skin-
respiratory protection provided - training-
maintenance.
Defective or wrong Hand Tools
Wrong tool - defective tool - struck by
flying debris- caught in or on -missing
guards -carbon monoxide - strains and
sprains - dust.
Right tool for the job - used properly -
good condition/ maintenance guards-
isolation- eye/ face protection - flying
debris controlled.
Electricity
Electrocution – overhead / underground
services - any leads damaged or poorly
insulated- temporary repairs -no testing
and tagging-circuits overloaded-non use
of protective devices.
Leads good condition and earthed - no
temporary repairs - no exposed wires-
good insulation-no overloading - use of
protective devices - testing and tagging -
no overhead/ underground services
Scaffolding
Poor foundation-lack of ladder access
insufficient planking-lack of guardrails
and toe boards-insufficient ties or other
means-all scaffolds incorrectly braced or
stabilised to prevent overturning.
All scaffolds correctly braced and
stabilized - 3:1 height to base ratio - firm
foundation, plumb and level - ladder
access provided and used - proper
platform (3 planks/ 675 mm) - planks
secured- guardrails and toe boards – 900
mm to 1100mm high, within 200 mm of
working face, mid - rail.
Ladders
Carrying loads - not secured against
dislodgement - defective ladders– not
sufficient length- wrong positions -
incorrectly placed (angles, in access
ways, vehicle movements.
Secured against movement or footed -
ladders in good condition - regularly
inspected - extend 1m above platform -
4:1 angle - out of access ways, vehicle
movements - climbing - no carrying loads
- 3 points of contact - no higher than 3rd
step down - use for access only, not
working platforms.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 50 of 69
Hazards Associated with Activities Control / Mitigation Measures
Excavations
Trench collapse - material falling in
undetected underground services-falls-
hazardous atmosphere struck by traffic
and mobile plant.
Soil stability known-no water
accumulation- existing services known -
material 600 mm from edge - clear of
suspended loads-hardhats/ PPE- ladders -
public protection - atmospheric testing-
traffic controls - Emergency Plan.
Gas Cutting and Welding
Fire-welding flash, burns, fumes,
electrocution in wet conditions-
flashback in oxygen set, leaking
cylinders, acetylene cylinders lying
down-poorly maintained leads.
Welding flash and burns controlled with
PPE and shields -fumes controlled with
ventilation and PPE (in good condition
and properly positioned),Gas cylinders be
kept upright & secured position (properly
tied) - combustible materials to be kept at
secured place to avoid fire & Fire
Extinguishers to be kept in fire prone area
with training to people for its use.
Noise
Unknown noise levels - known noise
levels over 85 decibels
Levels below 85 decibels - proper
protection.
Falling Material
Fall during carrying/ Lifting materials-
dislodged tools and materials from
overhead work areas.
Materials to be secured-kept away from
edge- toe boards -Use of hard hats.
Craneage& Lifts
Display of carrying capacity i.e load (No.
of person) incorrectly slung, defective
lifting equipment, unsecured loads,
craning in close proximity to building
people and plant- falls-falling materials.
Periodic testing by competent authority-
correctly slung/ secured loads, lifting
equipment good condition-use of proper
hand signals - falls while unloading
controlled.
Visitors Presence at site
Falls -struck by - dropped materials-road
accidents -insufficient hoarding or
fencing-pedestrian access past site-
mechanical plant movement on and off
site
Sufficient hoarding - fencing and
barricades-safe pedestrian access past site
traffic management for loading and
delivery- construction separated from
occupied areas of projects
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 51 of 69
Emergency Response Plan (ERP)
The overall objective of an Emergency Response Plan (ERP) is to make use of the combined
resources at the site and outside services to achieve the following:
• To localize the emergency and if possible eliminate it;
• To minimize the effects of the accident on people and property;
• Effect the rescue and medical treatment of casualties;
• Safeguard other people;
• Evacuate people to safe areas;
• Informing and collaborating with statutory authorities;
• Initially contain and ultimately bring the incident under control;
• Preserve relevant records and equipment for the subsequent enquiry into the cause and
circumstances of the emergency;
• Investigating and taking steps to prevent reoccurrence.
The ERP is therefore related to identification of sources from which hazards can arise and the
maximum credible loss scenario that can take place in the concerned area. The plan takes into
account the maximum credible loss scenario-actions that can successfully mitigate the effects of
losses/ emergency need to be well planned so that they would require less effort and resources to
control and terminate emergencies, should the same occur.
Standards and codes used in building construction to minimize the risk of natural calamities like
wind load, seismic load (earthquake), thunder storm/ lightning etc, as per NBC 2016 are given
below:
Design Standards
• IS: 456-2000 - Code of Practice for Plain and Reinforced Concrete
• IS: 875 (Part 1 to 5)-1987 - Code of Practice for Design Loads (Other Than Earthquake)
for Buildings and Structures.
o Part-1 Dead Loads- Unit Weights of Building Materials and Stored Materials
o Part-2 Imposed Load
o Part-3 Wind Loads
o Part-4 Snow Loads (Not releventin this case)
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 52 of 69
o Part-5 Special Loads and Combinations
• IS: 1893 (Part1)-2002 - Criteria for Earthquake Resistant Design of Structures
• IS: 4326- Earthquake resistant design and construction of building
• IS: 13920-1993-Code of Practice for Ductile Detailing of Reinforced Concrete Structures
subjected to Seismic Forces
• IS: 3370 (Part I, II & IV)- 1965: Code of practice for concrete structure for the storage of
liquids
• IS: 2950 (Part I) Code of practice for design and construction of raft foundations
• IS: 1904- Code of practice for design and construction of foundations in soils
• IS: 800-2007–General construction in steel-code of practice.
Main hazards identified for the project include hazards pertaining to fires in buildings and fire in
diesel storage areas, earthquake and LPG leakage and an ERP pertaining to these is described in
the following section.
Response in case of Earthquake
Response Procedures for Occupants
If indoors:
• Take cover under a piece of heavy furniture or against an inside wall and hold on.
• Stay inside: The most dangerous thing to do during the shaking of an earthquake is to try
to leave the building because objects can fall on you.
If outdoors:
Move into the open, away from buildings, streetlights, and utility wires. Once in the open, stay
there until the shaking stops.
If in a moving vehicle:
Stop quickly and stay in the vehicle. Move to a clear area away from buildings, trees, overpasses,
or utility wires. Once the shaking has stopped, proceed with caution. Avoid bridges or ramps
that might have been damaged by the quake.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 53 of 69
After the quake
• After the quake be prepared for aftershocks.
• Although smaller than the main shock, aftershocks cause additional damage and may
bring weakened structures down. Aftershocks can occur in the first hours, days, weeks, or
even months after the quake.
Help injured or trapped persons.
• Give first aid where appropriate. Do not move seriously injured persons unless they
are in immediate danger of further injury. Call for help.
• Remember to help those who may require special assistance--infants, the elderly, and
people with disabilities.
• Stay out of damaged buildings.
• Use the telephone only for emergency calls.
Response Procedure for emergency team
• Formulate an emergency response team for earthquake response. Using the public
address system, inform residents of response procedures discussed above.
• Inform the necessary authorities for aid.
• Ensure no person is stuck beneath any debris, in case of a structural failure.
• Ensure that all occupants standing outside near the buildings are taken to open areas.
• Ensure that the first-aid ambulance and fire tender vehicles are summoned if
necessary.
• Inform the nearby hospitals if there are any injuries.
• Check the utilities and storage tanks for any damage.
Response in case of LPG Leakage
• The affected area should be evacuated and cordoned off immediately
• Initiate an Emergency Response Team for LPG leakage.
• Shut down the main valves in the gas bank.
• Ensure that only concerned personnel are present in the affected area and all other
personnel and visitors are moved to the nearest assembly points.
• Rescue trapped personnel, also check if any personnel are unconscious in the area and
immediately move them outside and provide first aid. Ambulance should be summoned
to take injured personnel to the nearest hospital.
• Personnel in the nearby buildings to close all doors and windows to prevent entry of the
leaked gas.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 54 of 69
• Source of leakage to be traced and isolated from all the other areas and if required use
pedestal fans to bring down the gas concentration.
• In case of a fire follow the instructions in case of fire.
Response in case of Fire
• Required response during in the event of a fire should be described in signs located in the
lobby.
• On sighting a fire, it should be immediately informed to the environment manager giving
the exact location and type of fire in detail.
• Initiate the Emergency Response Team for fires.
• If the fire is small, engage in extinguishing the fire using the nearest fire extinguisher.
• Guide the Emergency Response Team staff to the emergency assembly point.
• The Emergency Response Team should immediately inform the nearest dispensary and
security force. If required a fire tender should be summoned.
• The response team should immediately move to the point of fire and take all necessary
steps to stop the fire. If the fire is not controllable and spreads then the manager in charge
should inform the district authorities and call for external help.
• The Emergency Response Team will provide immediate relief to the injured residents at
the scene of incident. Any injured persons should be evacuated on priority to the
dispensary or one of the nearest hospitals based on their condition
General Instructions for Occupants in case of Fire
• Get out of buildings as quickly and as safely as possible.
• Use the stairs to escape. When evacuating, stay low to the ground.
• If possible, cover mouth with a cloth to avoid inhaling smoke and gases.
• Close doors in each room after escaping to delay the spread of the fire.
• If in a room with a closed door.
• If smoke is pouring in around bottom of the door or if it feels hot, keep the doorclosed
• Open a window to escape or for fresh air while awaiting rescue.
• If there is no smoke at bottom or top and the door is not hot, then open the door slowly
• If there is too much smoke or fire in the hall, slam the door shut.
• Stay out of damaged buildings.
• Check that all wiring and utilities are safe.
Fire Fighting system is proposed to prevent and control fire outbreaks for the project. The fire-
fighting system will consist of portable fire extinguishers, hose reel, wet riser, yard hydrant,
automatic sprinkler system, and manual fire alarm system. The project will also be provided with
automatic fire detection and alarm system.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 55 of 69
The NOC from Delhi Fire Service has been obtained for the project and the copy is attached as
Annexure-XIII.
9.10. If you are using glass as wall material provides details and specifications including
emissivity and thermal characteristics.
It is proposed to use predominantly two types of glazing in the building:
Laminated Glass 8 mm Clear + 1.52 PVB + 6 mm Clear Tempered
Hermetically Sealed Double Glazing 8 mm Clear Tempered + 12 mm Air gap + 6 mm Clear
Tempered
Both the glass types will be shaded with a dense screen, which effectively shade 100% of the
glass throughout the day and the year. The effective Solar Heat Gain Coefficient (SHGC) is
therefore significantly lower than the glazing SHGC alone and meets the ECBC glazing U-factor
and SHGC requirements for 24 Hour Buildings in Composite Climate.
Glass Specifications:
Laminated Glass 8 mm Clear + 1.52 PVB + 6 mm Clear Tempered
U-Value = 5.6 W/m2 K
Solar Heat Gain Coefficient (SHGC) of Glass = 0.77
The windows will be shaded with a dense screen, which does not let any direct sun hit the glass.
Thus, the effective SHGC = 0.77 x 0.50 x 0.50 = 0.19
(100% Shaded Overhang Projection Factor 1.0 Multiplication Factor = 0.5 as per Section 4.3.3
of ECBC)
Light Transmittance = 0.87
Hermetically Sealed Double Glazing 8 mm Clear Tempered + 12 mm Air gap + 6 mm Clear
Tempered
U-Value = 2.8 W/m2 K
Solar Heat Gain Coefficient (SHGC) of Glass = 0.69
The windows will be shaded with a dense screen, which does not let any direct sun hit the glass.
Thus, the effective SHGC = 0.69 x 0.50 x 0.50 = 0.17
(100% Shaded Overhang Projection Factor 1.0 Multiplication Factor = 0.5 as per Section 4.3.3
of ECBC)
Light Transmittance = 0.78
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 56 of 69
9.11. What is the rate of air infiltration into the building? Provide details of how you are
mitigating the effects of infiltration.
Since most of the building is air-conditioned; air infiltration has been kept to required minimum
level. Axial flow fan shall be provided for basement ventilation system. The fresh air and
exhaust air also be carried through masonry shall as per following parameter.
Ventilation Details:
As per NBC 12 ACPH for Normal parking exhaust and 30 ACPH in case of Fire.
All public area smoke exhaust @ 12 ACPH.
Pressurization:
All lifts lobbies shall be pressurized during fire conditions through axial fans through masonry
shafts and pressurized air released at each floor through suitable grilles.
9.12. To what extent the non-conventional energy technologies are utilized in the overall energy
consumption? Provide details of the renewable energy technologies used.
The Energy efficient lighting will be done with the use of CFL and LED lamps. Additionally
solar energy will be used for hot water provision.
Use of Solar energy for street lightening and Solar water heater will be adopted.
10. ENVIRONMENT MANAGEMENT PLAN
10.1. The Environment Management Plan would consist of all mitigation measures for each item
wise activity to be undertaken during the construction, operation and the entire life cycle to
minimize adverse environmental impacts as a result of the activities of the project. It would
also delineate the environmental monitoring plan for compliance of various environmental
regulations. It will state the steps to be taken in case of emergency such as accidents at the
site including fire.
The mitigation measures suggested for the impacts identified on the various environmental
components due to the project activities are given in this section. A detailed environmental
management plan is presented in Table-13 to mitigate all the identified environmental impacts
that are found to be significant.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 57 of 69
Table-13: Environmental Management Plan – Construction and Operation Phase
S. No Environment
al
components
Potential
Impacts
Potential Source of
Impact
Controls Through
EMP & Design
Impact Evaluation Remedial Measures
1 Ground Water
Quality
Ground Water
Contamination
Construction Phase
Sewage
generated from
temporary labor
tents.
Soak pit or septic
tank will be provided
and treated sewage will
be used for
construction purposes.
No significant impact
as majority of labors
would be locally
deployed
Operation Phase
Sewage
Discharge from the
project
Proponent will
provide the STP to
treat the sewage of
Project.
No negative impact on
ground water quality
envisaged. Not
significant.
In an unlikely event of
soil and ground water
contamination.
Remediation measures
shall be implemented.
2. Ground Water
Quantity
Ground Water
Depletion
Construction Phase
Ground water
will be not be used
during construction.
Not Applicable No significant impact
on ground water
quantity envisaged.
Operation Phase
Groundwater
will not be used
during operation
phase. The required
water will be met
through the
municipal supply
Rain water harvesting
scheme.
Black and Grey
water treatment and
reuse.
Storm water
collection for water
harvesting.
Percolation well to
be introduced in
landscape plan.
No significant impact
on surface/ground
water quantity
envisaged.
In an unlikely event of
non-availability of water
supply, water will be
brought using tankers.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 58 of 69
Awareness
Campaign to reduce
the water consumption
3. Surface Water
Quality
Surface water
contamination
Construction Phase
Surface runoff
from site during
construction
activity.
Silt traps and other
measures such as
additional onsite
diversion ditches will
be constructed to
control surface run-off
during site
development
No off site impact
envisaged as no surface
water receiving body is
present in the core
zone.
Operation Phase
Discharge of
domestic
wastewater to STP.
Domestic water will
be treated in STP and
ETP
No off site impact
envisaged
Excess of water will be
discharged as per CPCB
standards.
4. Air Quality Dust Emissions Construction Phase
All heavy
construction
activities
Suitable control
measures will be
adopted for subsiding
the PM level in the air
as per air pollution
control plan.
Not significant because
dust generation will be
temporary and will
settle fast due to dust
suppression techniques
(wet scrubbers) used.
During construction
phase the contractors are
advised to facilitate
masks for the labors.
Water sprinklers will be
used for suppression of
dust during construction
phase.
Emissions of
SPM, SO2, NO2
and CO
Construction Phase
Operation of
construction
equipment and
vehicles during site
development.
Running D.G.
sets (back up)
Rapid on-site
construction and
improved maintenance
of equipment
Not significant. Regular monitoring of
emissions and control
measures will be taken
to reduce the emission
levels.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 59 of 69
Operation Phase
Power
generation by DG
Sets during power
failure
Emission from
vehicular traffic in
use
Construction Phase
Operation of
construction
equipment and
vehicle movements
during site
development.
Running DG
sets (for power back
up)
Use of Low Sulphur
Diesel in DG sets
Use of clean fuel if
available
Providing Footpath
and pedestrian ways
within the site.
Green belt will be
developed with
specific species to help
to reduce PM level
Use of equipment
fitted with silencers
Proper maintenance
of equipment
Provision of noise
shields near the heavy
construction operations
and acoustic enclosures
for DG sets
Construction activity
will be limited to day
time hours only
Not significant
DG sets would be used
as power back-up
required.
No significant increase
in noise level is
expected from the
project‟s activities. There are no sensitive
receptors located within
the vicinity of site.
Use of Personal
Protective Equipment
(PPE) like earmuffs and
earplugs during
construction activities.
5. Noise
Environment
Operation Phase
Noise from
vehicular
movement
Noise from DG
sets operation
Green Belt
Development
Development of
silence zones to check
the traffic movement
DG set rooms
will be equipped with
No significant impact
due to suitable width
of Greenbelt.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 60 of 69
acoustic enclosures.
6. Land
Environment
Soil
contamination
Construction
Phase
Disposal of
construction
debris
Construction
debris will be
collected and suitably
used on site as per the
solid waste
management plan for
construction phase
No significant impact.
Impact will be local,
as waste generated
will be reused for
filling of low lying
areas etc.
Operation Phase
Dumping of
municipal solid
waste on land.
Used oil
generated from
D.G. sets
It is proposed that
the solid waste
generated will be
managed by an
authorized agency as
per SWM Rules,
2016.
Collection,
segregation,
transportation and
disposal will be done
as per amended
Hazardous waste
management and
Transboundary
Movement Rule,
2016 by the CPCB
authorized recycler.
used oil
Since solid waste is
handled by the
authorized agency,
waste dumping is not
going to be allowed.
Not significant.
Negligible impact.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 61 of 69
generated will be sold
to authorized
recyclers
7. Biological
Environment
(Flora and
Fauna)
Displacement of
Flora and Fauna
on site
Construction
Phase
Site Development
during
construction
Important species of
trees, if any, will be
identified and marked
and will be merged
with landscape plan
The site has scanty
vegetation
Operation Phase
Increase in
green covered area
Suitable green belts
will be developed as
per landscaping plan
in and around the site
using local flora
Beneficial impact.
8. Socio-
Economic
Environment
Population
displacement and
loss of income
Construction
Phase
Construction
activities leading
to relocation
Project
development as per
the Delhi Master
Plan.
No negative impact.
Operation Phase
Site operation
Project will
provide employment
opportunities to the
local people in terms
of labor during
construction and
service personnel
(staff, securities,
gardeners etc) during
operations
Beneficial impact
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 62 of 69
Providing
quality-Integrated
facility in, Delhi
9. Traffic
Pattern
Increase of
vehicular traffic
Construction
Phase
Heavy
Vehicular
movement during
construction
Heavy Vehicular
movement will be
restricted to daytime
only and adequate
parking facility will
be provided
No negative impact
Operation Phase
Traffic due to
people.
Vehicular
movement will be
regulated inside the
project with adequate
roads and parking lots
in the site.
No major significant
impact
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 63 of 69
Environmental Monitoring Plan
It is proposed to monitor essential parameters for ambient air quality, ambient noise quality,
ground water quality, and waste water quality both during the construction and operation phases
of the project. However the monitoring schedule is given in Table-14.
Table-14: Environmental Monitoring Schedule
S. No Particulars Monitoring
Frequency
Duration of
Sampling
Important Monitoring
Parameters
1 Ambient Air Quality Monitoring
Project site Once in 6 Months 24 hr continuously
except CO (8
hourly)
PM10, PM2.5,SO2, NOx &
CO
3 Ambient Noise Level
Near DG set Once in 6 Months 8 hr continuous
with 1 hr interval
Noise level in dB(A)
4 Ground/Drinking Water Quality Monitoring
Ground Water –
at project site
Once in 6 Months Grab Sampling Parameters specified under
IS:10500, 2012
5 Soil Quality
At the green belt
area
Twice in a year Samples were
collected from
three different
depths viz., 30cm,
60cm, and 100cm
below the surface
Parameter for soil quality:
pH, texture, electrical
conductivity, organic
matter, nitrogen, phosphate,
sodium, calcium, potassium
and Magnesium.
Environmental Monitoring:
Various environmental protection and mitigation measures have been suggested in the previous
Chapter/section for ensuring compliance with the stipulated environmental regulations and
applicable standards. Also, there are specified environmental monitoring and record keeping
requirements for operating facilities that the proposed Project will have to comply with. Though
record keeping would be largely an in-house activity, environmental monitoring within and
outside of the proposed Project would be carried out through recognized environmental
laboratories as per the requirements of MoEF&CC and DPCC and other regulatory authorities.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 64 of 69
The purpose of environmental monitoring is to evaluate the effectiveness of implementation of
EMP by periodically monitoring the important environmental parameters within the impact area,
so that any potential adverse impacts are detected and timely action can be taken. In order to
ensure compliance with the applicable regulatory requirements, the Project plans to conduct the
following environmental monitoring activities.
Wastewater Quality Monitoring and Record Keeping
The wastewater discharges from the proposed Project will mainly comprise of domestic sewage
and other wastewater discharges from drinking water points, toilets, washbasins, food court and
kitchen, backwashing of filters (used in water treatment) etc.
Therefore, as per the requirements of the Water (Prevention and Control of Pollution) Act 1974,
the Project will apply to DPCC for the Consent to Establish. Before starting the operation, the
Project will apply to DPCC for the Consent to Operate for Wastewater Discharges and thereafter
periodically renew its Consent to Operate. Subsequently, whenever there is a change in the
operations, the Project will get the requisite amendments in its Consent.
The Project would maintain an inventory of all sources of wastewater and maintain records of
waste water quality and quantity for the wastewater streams, as required. The Project will ensure
that wastewater analysis is conducted for all regulated parameters as per DPCC‟s specification or as per conditions of Consent to Operate and to ensure compliance with any other specifically
applicable standards. The frequency of wastewater quality monitoring would be decided in
consultation with the DPCC officials. Care will be taken to ensure that wastewater analysis is
conducted at such a frequency that potential variations due to various operational factors are
recorded.
Noise Level Monitoring and Record keeping
The Project would maintain an inventory of all point and non-point sources of noise emissions
and identify regulated sources, if any, if specified in the DPCC's Consent to Operate for Air
Emissions. Main source of noise would be DG sets. But as DG sets with acoustic enclosure has
been proposed, there would be minimal chance of noise pollution. However, the Project
management would conduct noise level monitoring at the specified locations within, on the fence
line/boundary, and outside the Project‟s premises to ensure compliance with the specific standards and conditions of the Consent to Operate. The locations of the noise monitoring
stations and frequency of noise level monitoring would be decided in consultation with the
DPCC officials. The noise level monitoring would be conducted at such a frequency that
potential variations due to various operational factors are recorded.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 65 of 69
Solid Waste Management Plan
In order to ensure compliance with the applicable requirements for waste management, the
Project would prepare an inventory of wastes generated on-site. This would be compiled from
waste inventories of different areas/processes of the proposed Project. Solid waste from the
proposed Project will be mainly:
(i) Biodegradable wastes organic wastes like foods wastes from the offices and canteens
which is would be collected on daily basis by municipal trucks of the locality.
(ii) Non-biodegradable Inorganic wastes like papers, cartons, thermocol, plastics, polythene
bags, glass etc shall be sold to recyclers.
These inventories/records will include waste quantities and characteristics, as well as the
utilization/disposal methods.
Awareness and Training
Training and human resource development is an important link for achieving sustainable
operation of the facility and environmental management. For successful functioning of the
project, relevant EMPs will be communicated to the residents of the project. Everyone will be
made aware of importance of their various environmental responsibilities including waste
segregation and storage, water and energy conservation, etc. This awareness will be provided
through documents and periodic meetings. They will be informed of their responsibilities for
successful operation of various environmental management schemes inside the Project premises.
Relevant personnel at site will be trained for the following:
Applicable EH&S regulations and compliance requirements for the same.
Collection, Segregation, Storage and Disposal of solid and hazardous wastes.
Operation and maintenance of Sewage Treatment Plant and recycling system
Techniques for waste minimization, water conservation and energy conservation, etc.
Functioning of the Project‟s Environmental Management System (EMS) including environmental monitoring, reporting and documentation needs.
Requirements and responsibilities in case of an emergency as per emergency response plan.
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 66 of 69
Environmental Monitoring Program during Construction period
Based on the above, the following environmental monitoring program during construction
activities is proposed for the Project. The monitoring program would be discussed and approved
by DPCC are given in Table-15.
Table-15: Proposed Monitoring Program for Construction Phase of the Project
S. No. Type Locations Parameters Period and
Frequency
1.
Ambient Air
Quality
Monitoring
As per requirement SO2, NO2, PM10, PM2.5
and CO
As per DPCC‟s requirements
2.
Ambient Noise
Monitoring
As per requirement Noise level Leq both
during daytime and
nighttime
As per DPCC‟s requirements
3.
Water Quality
Testing
(Potability
testing)
(i) Any operational
borewell
(ii) One of the
Drinking Water
Point
Drinking water
parameters as per IS
10500:1991.
As per DPCC‟s requirements
4.
Treated
Wastewater
Quality
Inlet and outlet of the
STP
Parameters for assessing
compliance with
standards for recycling
and horticulture use
As per DPCC‟s requirements
Post-Project Environmental Monitoring Program
Based on the above, the following post-project environmental monitoring program is proposed
for the Project. The monitoring program would be discussed and approved by DPCC are given in
Table-16.
Table-16: Proposed Monitoring Program for Operational Phase of the Project
S. No. Type Locations Parameters Period and
Frequency
1.
Ambient Air
Quality
Monitoring
As per requirement SO2, NO2, PM 10,
PM2.5 and CO
As per DPCC‟s requirements
2. Ambient Noise As per requirement Noise level Leq both As per DPCC‟s
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 67 of 69
S. No. Type Locations Parameters Period and
Frequency
Monitoring during daytime and night
time
requirements
3.
Water Quality
Testing
(Potability
testing)
(iii) Any operational
borewell
(iv) One of the
Drinking Water
Point
Drinking water
parameters as per IS
10500:2012.
As per DPCC‟s requirements
4.
Treated
Wastewater
Quality
Inlet and outlet of the
STP
Parameters for assessing
compliance with
standards for recycling
and horticulture use
As per DPCC‟s requirements
Environmental Documentation
Documentation and reporting of environmental performance is an important management tool for
ensuring sustainable operation of the Project. Documents/Records shall be maintained for
regulatory, monitoring and operational issues. Typical documentation requirements for the
“Project” are summarized in Table-17.
Table-17: Environmental Documentation for Operational Phase of the Project
PARAMETER PARTICULARS
Air Emissions
(incl. Noise)
Consent to Operate for Air Emissions from DPCC
Operational details of DG sets, and air pollution control equipment
including number of hours of operation, fuel usage, etc.
Ambient Air Quality and Stack Emissions Monitoring records
“Type Approval Certificates” and “Conformance Labels” for the DG sets
Ambient Noise Monitoring Records
Water Supply Water Quality Monitoring records
Water Cess Returns
Wastewater
Discharges
Consent to Operate for Wastewater Discharges from DPCC
Details of quantity of wastewater discharged from various sources
and discharged from the outlet of the STP for recycling/into the
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 68 of 69
PARAMETER PARTICULARS
sewer (if any)
Operational details of STP including number of hours of operation,
chemical usage, in-process wastewater quality, etc.
Wastewater Quality and Quantity Monitoring records
Waste Management Permission for disposal of solid wastes from concern
municipality/authority
Wastes Management Inventory including details of quantity of
wastes generated on-site and mode of their disposal
Inventory of wastes stored on-site
Records of hazardous wastes stored on-site (in Form-3) (if
generated)
Annual Returns for hazardous wastes (in Form-4 and Form-13) to
DPCC
Documentation related to off-site transportation and disposal of
hazardous wastes (including Form-9 and Form-10)
Environmental
Statement
Submission of Environmental Statement to DPCC before 30th
September every year
Petroleum Storage License from PESO for storage of HSD and other petroleum
substances (based on their quantities)
Inventory of petroleum substances stored on-site both at storage
and usage locations
Regular integrity testing/inspection reports for the storage tanks
Proposed Hotel at Plot No.1, Wazirpur District Center, Delhi by M/s. Asrani Inns and Resorts
Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 69 of 69
Table-18: Environmental Management Cost
COMPONENT CAPITAL COST
(RS. IN LACS)
RECURRING COST
(RS. IN LACS)
Sewage Treatment Plant 108 20
Rain Water Harvesting System 12 2.4
Solid Waste Management 14.9 2.99
Environmental Monitoring - 4
Green Area 1 2
Others (Energy saving devices,
miscellaneous) 40 8
Total 186 40
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 1 of 20
CONCEPTUAL PLAN
1. INTRODUCTION
M/s Asrani Inns and Resorts Pvt. Ltd. has Proposed Hotel at Plot-2, Wazirpur District Centre,
New Delhi-110052.
M/s Asrani Inns and Resorts Pvt. Ltd. has been allotted the land vide allotment cum
conveyance Deed and possession letter for Plot-2 vide (File no. F30 (2)/2006/CL/2157)
dated: 30.06.2006. The copy of Land Documents is attached as Annexure-I.
The Project earlier has received environmental clearance vide EC letter No. Environmental
Clearance No. DPCC/SEIAA-SEAC/200/13/1272 Dated 01/08/2014 from SEIAA, Delhi. The
earlier EC letter is attached as Annexure-II.
The project had been granted Consent to Establish (CTE) by Delhi Pollution Control Committee
(DPCC) vide Certificate No. 0-023449 dated 19.12.2014. The copy of CTE certificate is attached
as Annexure-III.
Regular compliance report of the EC is being submitted. Receiving of latest compliance report
December’2018 are attached as Annexure IV.
But now due to internal management decision projects has some planning to modify the building
plans hence the separate Environmental Clearance is required.
The project is being developed on the total plot area of 7,030.40 m2. Earlier the built up area is
27,867.49 m2 but after modification of plan the built up area increase to 38,953.117 m
2.
The development to be done is in accordance with Delhi Master Plan 2021. Considering the
above; the existing land use is not expected to get altered due to construction of proposed
project.
The Project is designated under Category “B” and falls under Item 8(a) (Building & Construction
Project) of the Environmental Impact Assessment (EIA) Notification of September 14, 2006 and
its amendments.
2. SITE SURROUNDING &CONNECTIVITY
Site surroundings and Connectivity details of the proposed project are given in Table-1.
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 2 of 20
Table-1: Site Surroundings and Connectivity Details (in 10 km radius of project site)
S. No. Connectivity & Site Surroundings
Description Distance and Direction
1. Nearest Railway
Station New Delhi Railway Station Approx. 9 km towards South-East
2. Nearest Metro Station Netaji Subhash Place Metro
Station 390 m towards North-East
3. Nearest Airport Indira Gandhi International
Airport Approx. 16 km towards South
4. Nearest
Highway/Roads U.P.-Delhi State Boundary Approx. 12 km towards East
5. River Yamuna River Approx. 8 km towards East
6. Nearest School &
College
Guru Govind Singh College
M.M. Public School
Ravindra Public School
600mtrs towards North-East
460mtrs towards West
285mtrs towards North
7. Nearest Hospital
Max Hospital
Bhagvan Mahavir Hospital
Sundar Lal Jain Hospital
450mtrs towards East
Approx. 2 km towards North
3.4 km towards East
8. Places of worship Hanuman Mandir
Kali Mata Mandir
600 m towards South
850 m towards South-West
9. Fire Station
Pitampura Fire Station
Wazirpur Fire Station
Rohini Fire Station
250 mtrs towards South
1.93 km towards North-East
1.88 km towards North-West
10. Environmental
Sensitive Area
Najafgarh Drain
Central Ridge Reserve Forest
Wazirpur Industrial Area
Garhi Mandhu PF
Approx. 5 km towards South
Approx. 8 km towards South
Approx. 2 km towards East
Approx. 7 km East
Source: Google Map and Survey of India Toposheet
A Google Map of 500m buffer map showing the surrounding area of the proposed project is
shown in Figure-1.
The topographical map showing the surrounding area within 10 km radius is shown in the
Figure-2 and topographical map showing the eco-sensitive area within 15 km radius is shown in
the Figure-3.
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 3 of 20
Figure-1: Google Map of 500m radius showing surroundings of the area
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 4 of 20
Source: Survey of India
Figure-2: Topographical map (Survey of India) of 10km radius showing surrounding area
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 5 of 20
Source: Survey of India
Figure-3: Topographical map (Survey of India) of 15km radius showing Eco-sensitive area
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 6 of 20
3. PROJECT LOCATION AND DESCRIPTION
M/s Asrani Inns and Resorts Pvt. Ltd. has Proposed Hotel at Plot-1, Wazirpur District Centre,
Delhi- 110052 on the total plot area of 7,030 m2. The total built up area is 38953.11 m
2. Site Plan
along with Area statement is attached as Annexure-V.
The coordinates of the project boundary along with the center of the project site is given below
in the Table-2.
Table-2: Coordinates of the Project Boundary
Latitude Longitude Site Height of
Building (AGL)
Corner-I 28°41'41.90"N 77°8'48.13"E 217 130M.
Corner-II 28°41'41.21"N 77°8'51.00"E 217 130M.
Corner-III 28°41'37.82"N 77°8'49.57"E 217 130M.
Corner-IV 28°41'38.77"N 77°8'46.84"E 217 130M.
The detailed comparative Area Statement is given in Table-3.
Table-3: Area details of the project
S.
No.
Particulars Area in s.q.m.
1 Total Plot Area 7,030.00
2 Total Permissible Ground Coverage @ 50% of plot area 3,515.00
a Permissible Ground Coverage @ 40% of plot area 2,812.00
b Additional ground Coverage for Atrium @ 10% of plot area 703
3 Achieved Ground Coverage @ 40.72 % of Plot Area 3106.287
4 Permissible FAR @ 2.06 of Plot area 14,500.00
5 Total FAR achieved @2.241 of plot area 16,839.183
a Hotel @ 1.83 of Plot Area 13,525.529
b [email protected]% of Plot area 3398.087
c Atrium FAR @0.04 of plot area 305.25
6 Proposed Non FAR (Service area) @ 122.94% of Plot area 3,556.968
7 Total Basement area 22,119.341
a Basement 4 (including service area 1063.805 sqm) 4787.894
b Basement 3 (including service area 1066.086 sqm) 4787.894
c Basement 2 (including service area 892.898 sqm) 4787.894
d Basement 1 (including service area 2325.46 sqm) 4198.691
8 Built up Area (FAR+ Non-FAR+ Service area) 38,958.524
9 Green Area Provided @33.7 % of plot area 1,849
10 Maximum Building Height (in meters) 72.35
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 7 of 20
4. DETAIL OF BUILDING BLOCK
The project comprises of Hotel Building. The building has basement and surface parking
provision and 1,849 m2 will be developed as landscaped.
Details of Building Block are given in Table 4 and Floor wise details of the building are given in
Table 5.
Table 4: Details of Building Blocks
S. No. Type of building No. of Towers Floors
1 Hotel Building 1 4B+G+15
Table 5: Floor wise details of building
S. No Particulars Hotel Building
1 Ground Floor Banquet Hall, Kitchen and Hotel Lobby & Retail Lobby
2 First Floor Commercial. (shops/ offices/ atrium)
3 Second Floor Commercial. (shops/ offices/ atrium)
4 Third Floor Restaurant, Coffee Shop, Kitchen, Hotel Lobby and Lounge.
5 Fourth Floor Service Floor and Lobby.
6 Fifth Floor Gym and SPA, Swimming pool, Pool deck and Lobby.
7 Sixth Floor Suite, Rooms Sky Lobby and lobby.
8 Seventh Floor Suite, Rooms Sky Lobby and Refuge Area.
9 Eighth Floor Suite, Rooms Sky Lobby.
10 Ninth Floor Suite, Rooms Sky Lobby.
11 Tenth Floor Rooms, Sky Lobby and Refuge Area.
12 Eleventh Floor Rooms, Sky Lobby.
13 Thirteenth Floor Suite, Rooms, Sky Lobby and Refuge Area.
14 Fourteenth Floor Rooms, Sky Lobby.
15 Fifteenth Floor Service Floor
AAI NOC is attached as Annexure-VI.
5. POPULATION DETAIL
Total population of the project is approximately 4967 which include the population of guest
rooms, staff population and visitors of various facilities. Breakup of the population is given in
Table-6.
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 8 of 20
Table-6: Calculation of Population (Hotel + Retail)
Description
Total
Population /
Area
Hotel Population
Keys
306
Hotel Staff Permanent (40) + Banquet & Specialty Restaurant staff permanent (79) 119
Hotel Day Staff (40) + Banquet & Specialty Restaurant day staff (79) 119
Visitors 165
Banquet halls 1778
Specialty Restaurant 334
Gym & Spa 609
Retail
Visitor in First Floor 297
Second Floor 267
Day staff (salesmen) in shops (30 shops) 50
Admin / security staff 70
Office
Day staff in offices 742
Admin / security staff 37
Visitors 74
Total 4967
6. ROAD & PARKING DETAILS
Internal Road – Project has 6 mtrs. wide roads in East and North and 9 meter wide
road in South and West direction within the premises.
Entry/exits provided in the Building Premises – 5 exit/entry points have been
provided in the project.
Setbacks: 15mtrs wide in North West direction (Front side of the project) and 9mtrs
wide rest of the directions around the project site.
Parking Details- The total parking proposed is 517 ECS and parking required is 505
ECS.
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 9 of 20
The detailed Parking details are provided in the Table-7. The comparative parking
details are given in Table-8.
Table-7: Parking Details
Description Norms (As per Delhi Building Bye Laws) Parking (E.C.S.)
Parking
Required
3 ECS/100 sq.m of FAR (16,839.183 m2) 505.1
Total ECS required 505
Basement Area under Parking 14531.086
Total ECS Proposed (@ 32 sqm/ECS for
Normal Car Park & 16 Sqm/ECS for
Stacked Parking)
517
Table-8 Basement Area under Parking
S.
No.
Surface / Basement Basement Area under
Services (sq.mtrs.)
1 Basement-1 2465.299
2 Basement-2 810.212
3 Basement-3 551.238
4 Basement-4 509.868
Total Area under
services
4336.617
Total Area under
Parking
14531.086
Basement cum Traffic Circulation Plans are attached as Annexure- VII.
7. LANDSCAPE DEVELOPMENT
Increasing vegetation in the form of greenbelt is one of the preferred methods to mitigate air
pollution. Plants serve as a sink for pollutants, reduce the flow of dust and reduce noise
pollution. Calculation of green area for the project is given in Table-9.
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 10 of 20
Table-9: Species for Green Area
Total Plot area 7030 m2
Total Open area 3923.72 m2
Total Proposed Green Area 1849 m2
Saraca indica (Ashoka)
Casuarina equiselifolia
Cassia fistula (Amaltas)
Jacaranda Mimosaefolia (Jacaranda)
Erythrina indica (Indian Coral tree)
Samanea saman (Monkeypod)
Delonix Regia (Flamboyant tree)
Oreodoxa regia
Lagerstroemia speciosa
Caesalpinia pulcherrina
Landscape plan is enclosed as Annexure VIII.
8. WATER REQUIREMENT, SUPPLY AND DISTRIBUTION
Water Requirement for the proposed project is discussed below.
8.1 Water requirement during Construction phase
The construction activity has been done and hence, there is no requirement for water for
construction phase.
8.2 Water requirement during operation phase
Water requirement during the operational phase is met through Municipal Council. The total
water requirement for the project is 523 KLD. This includes domestic water requirement,
flushing, landscaping, cooling tower makeup, swimming pool, Laundry, RO plant, Kitchen
demand, and for firefighting tank. The total fresh water requirement is 298 KLD which includes
Domestic water requirement, fire-fighting, swimming pool, laundry, Backwash & Regeneration
& R. O. water requirement. The water requirement for Flushing, HVAC Cooling, road washing
and landscaping will be met through treated water from STP.
Details of break-up of water requirement are given in Table-10.
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 11 of 20
Table 10: Details of water requirement
Description
Total
Population /
Area
Unit Water
Consumption
(LPCD)
Total Water
Requirement
(KLD)
Domestic Cold
Water
Requirement
(KLD)
Domestic
hot Water
Requirement
(KLD)
Total hot +
Cold water
Requirement
(KLD)
Flushing
Requirement
(KLD)
Wastewater
Generation
(KLD)
Hotel Population
Keys 306 320 97.92 47.43 32.13 79.56 18.36 83.232
Hotel Staff Permanent (40) +
Banquet & Specialty
Restaurant staff permanent (79)
119 135 15.39 6.27 4.165 10.435 5.355 13.4215
Hotel Day Staff (40) +
Banquet & Specialty
Restaurant day staff (79)
119 45 5.355 2.28 0.595 2.875 2.38 4.46675
Visitors 165 15 2.475 0.825 0.825 1.65 0.825 2.10375
For Kitchen 306x3 + 80x2 +
770x2+1778x2) = 4634 @ 12
Lit per meal
4634 12 55.608 37.072 18.536 55.608 ……. 47.2668
R.O. Plant for Drinking water
for guest room and
preparation of food &
beverages
….. ….. 29 29 …….. 29 ….. 14.5
Banquet halls 1778 15 26.67 8.89 8.89 17.78 8.89 22.6695
Specialty Restaurant 334 70 23.38 11.69 6.68 18.37 5.01 19.873
Gym & Spa 609 15 9.135 3.571 3.095 8.666 3.095 10.0278
Water for laundry @ 8 Kg /
guest room / day (Total 1088
Kg / day) & 20 Lit /Kg
1,224 20 29.92 17.952 11.968 29.92 …. 26.928
Retail (Visitors) 0
First Floor 297 15 4.455 1.485 -- 1.4885 2.97 3.78675
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 12 of 20
Description Total
Population /
Area
Unit Water
Consumption
(LPCD)
Total Water
Requirement
(KLD)
Domestic Cold
Water
Requirement
Domestic
hot Water
Requirement
Total hot +
Cold water
Requirement
Flushing
Requirement
(KLD)
Wastewater
Generation
(KLD) Second Floor 267 15 4.005 1.335 1.335 2.67 3.40425
Day staff (salesmen) in shops
(30 shops) 50 45 2.25 1.25
1.25 1 1.9125
Admin / security staff 70 45 3.15 1.75 1.75 1.4 2.6775
Miscellaneous water
requirement for Hotel / Retail /
Office
0
Make up water for cooling tower
of A/C plant (150000 LPD)
….. ….. 170 …. ……….. 0 170 0
Landscaping water requirement
for 30% of plot area = 2434 m2
@ 1 Lit / m2
….. ….. 10.5 …. ……….. 0 ……….. …..
Road Washing ….. ….. 5 ….. ….. ….. ………..
WTP Backwash & regeneration ….. ….. 8 8 8 ….. 6.8
Mopping & Washing ….. ….. 2 2 …. 2
Swimming Pool (For Hotel)
make-up water
….. ….. 18 18 18
….. …..
Fire Fighting ….. ….. 6.00 …. ……. 0 ….. ….. Total 9972 522.773 195.01 84.453 279.47 237.41 254.51
Total (Rounding off)
(Lit/Day)
9972 523 195 84.00 279 237 255
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 13 of 20
Water balance diagram for Non-Monsoon is given in Figure-4 and for Monsoon is given in
Figure-5.
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 14 of 20
Figure-4: Water Balance Diagram for Non-Monsoon Season
Zero Liquid Discharge
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 15 of 20
Figure-4: Water Balance Diagram for Monsoon Season
Zero Liquid Discharge
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 16 of 20
Reuse of Treated Water:
Total waste water generated is 255 KLD (Sewage + laundry), which will be treated in the STP of
capacity higher than the waste water generated i.e. 300 KLD (300 KLD STP and 60 KLD ETP,
which was situated at Plot No. 1). The 60 KLD Effluent Treatment Plant (ETP) is situated as site
Plot no. 1 which is common for both Asrani Inns & Resorts Pvt. Ltd. Plot 1 & Plot 2. The 21
KLD wastewater released from laundry effluents at Plot No. 2 has been treated in the same. The
treated water available is 245 KLD (@ of 90%) and it will be recycled and re-used for flushing,
road washing, landscaping, HVAC makeup, DG cooling, thus achieving Zero Liquid
Discharge. During monsoon season, as there will be less water requirement for landscaping, the
excess treated water to be discharged to sewer shall be in tune of 11 KLD. The details of
recycled water uses are provided in Table-11 below.
Table-11 Recycled Water Uses
Treated
Water Flushing
Landscaping
and road
washing
DG
Cooling
Road
washing
Mopping
and
Washing
HVAC
Cooling
Discharge
to
Sewer
Non-
Monsoon
Season
245
KLD
6 KLD 11KLD 20 KLD 5 KLD 2 KLD 170 KLD 0 KLD
Monsoon
Season
245
KLD 6 KLD 0 KLD 20 KLD
5 KLD 2 KLD 170 KLD 11 KLD
Wastewater Treatment Scheme
The 255 KLD sewage generated will be treated in the onsite STP, and the capacity of Sewage
Treatment Plant (STP) will be higher of waste water generated i.e. 300 KLD and the 21 KLD
waste water from laundry will be treated on 60 KLD ETP situated at plot 1. The proposed STP is
based on MBBR technology and Ultra filtration.
Geo technical Report is attached as Annexure-IX.
9. STORM WATER DRAINAGE
The storm water disposal system for the premises is self-sufficient to avoid any collection/
stagnation and flooding of water. Maximum harvesting is done within the site. Sufficient rain
water harvesting system with suitable dimension at appropriate locations in order to catch the
maximum run-off in conformity of Delhi state’s regulation regarding adoption of rain water harvesting.
10. RAINWATER HARVESTING
Rainwater harvesting is the activity of direct collection of rainwater. Collected Rainwater is
stored for direct use or for recharging the groundwater. Rain Water Harvesting is the technique
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 17 of 20
through which rain water is captured from the roof and paved surfaces and stored in sub-surface
ground water reservoir by adopting artificial recharge techniques.
Advantages:
To meet the ever increasing demand for water.
To avoid flooding of roads.
To augment the ground water storage and control the decline of water table levels.
To reduce ground water pollution.
To improve the quality of ground water.
To reduce the soil erosion.
To supplement domestic water requirement during summer, drought etc.
Improves the quality of ground water through dilution when recharged to ground water.
In saline areas, rain water provides good quality water and when recharged to ground
water, it reduces salinity and also helps in maintaining balance between the fresh-saline
water inter-faces.
Rainwater Harvesting Calculation for the project is given in Table-12 and Table-13.
Table-12: Runoff Calculation of the Area
Table-13: Numbers of Pits Calculation
As per MoEFCC Notification No. 2910 Dated 9 December 2017 we are proposing 4 pits
(minimum one recharge bore per 5,000 square meters of built up area).
Section Plan is enclosed as Annexure-X.
Elevation Plan is enclosed as Annexure-XI.
Dual Plumbing is enclosed as Annexure-XII.
S. No. Type of Surface Catchment
Area (m2)
Runoff
Coefficient
Intensity of
Rainfall
(mm/hr)
Intensity
of Rainfall
(m/hr)
Runoff
(m3 /hr)
1. Total Roof /Terrace
Area 3,106.28 0.85 11 0.011 29.04
Total Runoff (m3/hr) 29.04
S. No. Diameter of the
Pit
Depth of the
Pit
Volume of
the Pit
Runoff in
15 minutes
No. of
pits
required
No. of pits
proposed
1. 1.5 m 3 m 5.30 m3 7.26 1 4 pits
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 18 of 20
11. POWER REQUIREMENT
The total electrical load demand is 2,725 KW. The source of power supply is New Delhi
Municipal Council.
In case of power failure, 3 DG sets of 2000 KVA capacity are provided for backup power supply
system and 1 DG set of 1500 KVA will be on standby. All 4 Nos. DG Sets are fully
synchronized with AMF, Auto Load Management and Auto Load Sharing thru PLC / PCCM
(Power Command Control module) for optimum utilization of backup system. The DG sets are
water cooled.
The DG sets are provided with acoustic enclosure. Adequate stack heights of D.G. Sets are
provided as per the stipulated guidelines of Central Pollution Control Board (CPCB) to facilitate
natural dispersion of exhaust gases.
12. SOLID WASTE GENERATION AND MANAGEMENT
The project adopts a systematic approach for solid waste collection and disposal. Solid waste
generated from the project is collected properly and managed as per Solid Waste Management
Rules, 2016.
The domestic solid waste generated by the occupants of the Guest Rooms, Service Apartments,
staff and Commercial & Community Population, pertains to the two categories, Bio-degradable
and Non-biodegradable. These solid wastes are collected separately by putting three types of
separate bins at the source of generation. For the biodegradable waste green bins are provided,
for the recyclable waste white bins and for the non-biodegradable waste black bins are provided.
For wet garbage, Organic Waste Converter is installed within the complex. Following are the
solid waste generation rate has been considered as given in Table-14.
Table-14: Proposed Solid Waste Generation Rate
Category of Solid Waste Waste
Generation
Rate
Formula Total
Population
Waste
Generated
Hotel/ office/ retail population 0.1 to 0.2
kg/cap/day
Total
Population*0.15
4967 745.05
Total 745
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 19 of 20
* Source: Manual on Municipal Solid Waste Management, published by Central Public
Health and Environmental Engineering Organization (CPHEEO), Ministry of Urban
Development, Government of India.
The E-waste generated is managed as per the E Waste Management Rules. 2016. The detailed
Solid Waste Generation Management Plan is provided in Figure-6 below:
Figure-6: Solid Waste Management Plan
13. FIRE FIGHTING SYSTEM
The firefighting has been designed as per the recommendations of the National Building Code of
India: Part 4 Fire and Life safety: 2016. The building has been classified under Group-A:
Residential Building, Sub Division A-5: Hotels in the National Building Code 2016.
The Fire Fighting system has been designed considering the following codes, manual and
guidelines;
National Building Code of India (NBC);
Proposed Expansion of Hotel at Plot-, Wazirpur District Centre, Delhi by M/s Asrani Inns
and Resorts Pvt. Ltd.
Consultant-Ascenso Enviro Pvt. Ltd. Page 20 of 20
As per requirement of fire officer/local fire approving authorities; and
As per Indian Standard Code for Fire Protection (IS Codes)
Fire NOC is attached as Annexure-XIII.
14. DETAIL OF CONSTRUCTION MATERIAL
List of building materials used during construction works:
1. Coarse sand
2. Fine sand
3. Stone aggregate
4. Stone for masonry work
5. Cement
6. Fly Ash
7. Reinforcement steel
8. Plywood & steel shuttering
9. Pipe scaffolding (cup lock system)
10. Bricks
11. Marble
12. P.V.C. conduit
13. MCBs/DBs
14. PVC overhead water tanks
15. Pave tiles
16. GI pipe
17. Wastewater lines
18. S.W. sewer line up to main sewer
19. PVC rain water down take
20. Stainless steel sink in kitchen
21. Insulated glass on external facade with ACP
22. Joinery hardware