an investigation of training and mentoring of emerging

203
COPYRIGHT AND CITATION CONSIDERATIONS FOR THIS THESIS/ DISSERTATION o Attribution — You must give appropriate credit, provide a link to the license, and indicate if changes were made. You may do so in any reasonable manner, but not in any way that suggests the licensor endorses you or your use. o NonCommercial — You may not use the material for commercial purposes. o ShareAlike — If you remix, transform, or build upon the material, you must distribute your contributions under the same license as the original. How to cite this thesis Surname, Initial(s). (2012) Title of the thesis or dissertation. PhD. (Chemistry)/ M.Sc. (Physics)/ M.A. (Philosophy)/M.Com. (Finance) etc. [Unpublished]: University of Johannesburg. Retrieved from: https://ujcontent.uj.ac.za/vital/access/manager/Index?site_name=Research%20Output (Accessed: Date).

Upload: khangminh22

Post on 23-Jan-2023

1 views

Category:

Documents


0 download

TRANSCRIPT

COPYRIGHT AND CITATION CONSIDERATIONS FOR THIS THESIS/ DISSERTATION

o Attribution — You must give appropriate credit, provide a link to the license, and indicate if

changes were made. You may do so in any reasonable manner, but not in any way that

suggests the licensor endorses you or your use.

o NonCommercial — You may not use the material for commercial purposes.

o ShareAlike — If you remix, transform, or build upon the material, you must distribute your

contributions under the same license as the original.

How to cite this thesis

Surname, Initial(s). (2012) Title of the thesis or dissertation. PhD. (Chemistry)/ M.Sc. (Physics)/

M.A. (Philosophy)/M.Com. (Finance) etc. [Unpublished]: University of Johannesburg. Retrieved

from: https://ujcontent.uj.ac.za/vital/access/manager/Index?site_name=Research%20Output (Accessed:

Date).

PERFORMANCE EVALUATION OF CONTRACTOR DEVELOPMENT PROGRAMMES IN SOUTH AFRICA

by

AMBROSE DENTEH DAPAAH

A dissertation submitted in partial fulfilment of the requirements for the degree of

MAGISTER TECHNOLOGIAE

in

CONSTRUCTION MANAGEMENT

in the

FACULTY OF ENGINEERING AND BUILT ENVIRONMENT – DEPARTMENT OF CONSTRUCTION MANAGEMENT AND QUANTITY

SURVEYING

UNIVERSITY OF JOHANNESBURG

SUPERVISOR: PROF. W.D. THWALA

CO-SUPERVISOR: DR. I. MUSONDA

April 2016

ii

DECLARATION

I, AMBROSE DENTEH DAPAAH, do hereby declare that the “Performance

evaluation of contractor development programmes in South Africa” is my own

heuristic research, that all sources I have used or cited have been acknowledged,

and that it has never been submitted for degree purposes to this or any other

university. It is presented to the University of Johannesburg (Department of

Construction Management and Quantity Surveying) in fulfilment of the requirement

for MAGISTER TECHNOLOGIAE degree in Construction Management.

Signature…………………………………………………………April 2016

A.D. Dapaah

University of Johannesburg

Doornfontein Campus

iii

ACKNOWLEDGEMENTS

I am deeply beholden to YAHWEH-JIREH, The Lord, who provided and His Son,

Jesus Christ, without whom this academic task could not have been realised.

I would also like to specially thank Prof. D.W. Thwala, my supervisor, for his

guidance and Dr. Innocent Musonda, my co-supervisor, for his counsel, patience

and constructive criticism in achieving the objectives of this inquiry and conveying

it to realisation.

I am thankful to my parents, the late Mr. Bossman Denteh and Madam Christiana

Kumah, and also to my sister, Elizabeth Denteh, without forgetting my nephews

and nieces, Henry, Mabel, Charlotte, Jesse, Grace, Anna and Saviana, for their

contribution to upliftying my spirit.

Lastly, my sincere appreciation goes to the entire staff and members of the

Department of Construction Management and Quantity Surveying, University of

Johannesburg, South Africa.

Dapaah, A.D.

April 2016

iv

DEDICATION

This work is dedicated to:

My son, Master Bossman Dapaah,

My wife, Comfort, and

My late sister, Lucy Dapaah.

v

ABSTRACT

Contractor development programmes (CDPs) are aimed at creating an enabling

environment for the continued existence and sustainability of small, medium and

micro enterprise (SMME) contractors. Literature shows that the views of

beneficiaries of these CDPs have not been sufficiently evaluated to access their

effect. The purpose of this study was to establish from the beneficiaries what their

expectations of the CDPs are and whether they believed the CDPs are meeting

those expectations.

A questionnaire survey, consisting of closed-ended as well as open-ended

questions, was administered to, and structured interviews were conducted with the

respondents to establish their views on the CDPs and whether they have benefited

from the CDPs. Based on the findings, recommendations were made on how

CDPs could be improved.

The study showed that the beneficiaries were fairly satisfied with the CDPs and

regarded them as adding some value to their upgrade and sustainability; however,

gaps exist within the CDPs that require the implementing agencies’ attention to

ensure the successful implementation of the CDPs. Evidence from the study

showed that CDPs which had a strong mentorship programme also had a higher

number of contractor upgrades. Information from interviews also revealed that

contractors believed that continuous mentorship programmes would be the

solution to the lack of CDPs performance. Therefore continuous contractor

mentorship (CCM) programmes were found to be vital to a successful CDP and

these were found to be lacking in most South African CDPs. Therefore the study

will aid in improving the quality of the CDPs and achieving their goals of developing

a contractor. The research focused on contractors as a whole who had undergone

the CDPs and did not separate them into their fields of specialities such as general

building, engineering or specialised contractors. The questionnaire survey was

conducted only in the Gauteng Province of South Africa and not the entire country.

Keywords: Contractor development programmes; contractor mentorship; small,

medium and micro enterprise contractors

vi

TABLE OF CONTENTS

DECLARATION .............................................................................................ii

ACKNOWLEDGEMENTS ............................................................................. iii

DEDICATION ...............................................................................................iv

ABSTRACT .................................................................................................. v

TABLE OF CONTENTS ...............................................................................vi

LIST OF TABLES ........................................................................................ xii

LIST OF FIGURES ..................................................................................... xiii

LIST OF ACRONYMS ................................................................................ xiv

DEFINITIONS ............................................................................................. xvi

CHAPTER ONE ............................................................................................ 1

INTRODUCTION .......................................................................................... 1

1.1 BACKGROUND ................................................................................... 1

1.2 RESEARCH OBJECTIVE .................................................................... 6

1.3 OBJECTIVES ....................................................................................... 6

1.4 BENEFIT OF THE STUDY ................................................................... 7

1.5 SCOPE OF THE RESEARCH.............................................................. 7

1.6 DELIMITATION OF THE STUDY ......................................................... 7

1.7 STRUCTURE OF THE REPORT ......................................................... 7

1.8 CONCLUSION ..................................................................................... 9

CHAPTER TWO ......................................................................................... 10

LITERATURE REVIEW: CONTRACTOR’S DEVELOPMENT PROGRAMMES ................................................................................................................... 10

2.1 INTRODUCTION ................................................................................ 10

2.2 HISTORY OF CONTRACTOR DEVELOPMENT PROGRAMMES .... 10

2.3 CONTRACTOR DEVELOPMENT PROGRAMME FRAMEWORKS .. 11

2.3.1 Qualities of a successful contractor development programme 12

vii

2.3.2 Aims and objectives of contractor development programmes . 14

2.3.3 Challenges of contractor development programmes ............... 16

2.4 MENTORSHIP IN CDPs .................................................................... 17

2.4.1 Components of mentoring in training and development .......... 18

2.4.2 Mentorship programmes .......................................................... 21

2.4.3 Benefits of mentoring for the mentor and the protégé ............. 21

2.4.4 Mentorship of a company ........................................................ 22

2.5 CONCLUSION ................................................................................... 28

CHAPTER THREE ..................................................................................... 29

CONTRACTOR DEVELOPMENT PROGRAMMES – SOUTH AFRICAN PERSPECTIVE .................................................................................. 29

3.1 INTRODUCTION ................................................................................ 29

3.2 Legislative backing of CDPs in South Africa ...................................... 29

3.2.1 Emerging contractor development programmes (ECDPs) ....... 30

3.2.2 Contractor incubator programmes ........................................... 30

3.2.3 Eskom Construction Academy ................................................. 34

3.2.4 Vuk’uphile Learnership Programme ........................................ 35

3.2.5 Masakhe Emerging Contractor Development Programme ...... 41

3.2.6 Small Enterprise Development Agency – Construction Incubator (SCI) Programme..................................................... 43

3.2.7 Khuthaza Contractor Development .......................................... 46

3.3 CONCLUSION ................................................................................... 50

CHAPTER FOUR ....................................................................................... 51

REVIEW OF INTERNATIONAL CONTRACTOR DEVELOPMENT PROGRAMMES ................................................................................. 51

4.1 Introduction ........................................................................................ 51

4.2 Development programme – Tanzania CRB initiative .......................... 51

4.2.2 Development programme – Tanzania NCC initiative ............... 53

4.2.3 Development programme – Palestine ..................................... 54

4.2.4 Development programme – Lesotho ....................................... 55

viii

4.3 CONCLUSION ................................................................................... 58

CHAPTER FIVE ......................................................................................... 60

CONTRACTOR DEVELOPMENT MODELS .............................................. 60

5.1 INTRODUCTION ................................................................................ 60

5.1.1 The South African Construction Excellence Model .................. 60

5.1.2 The Integrated Emerging Contractor Development Model ...... 61

5.1.3 Supply-side interventions to accelerate growth of priority enterprises ............................................................................... 65

5.2 FACTORS FOR SUCCESFUL IMPLEMENTATION OF CDPs .......... 68

5.2.1 Classroom work ....................................................................... 69

5.2.2 Fieldwork ................................................................................. 69

5.2.3 Mentorship ............................................................................... 69

5.3 CONCLUSION ................................................................................... 71

CHAPTER SIX ............................................................................................ 72

IMPORTANCE OF CDPs IN THE CONSTRUCTION INDUSTRY .............. 72

6.1 CONSTRUCTION’S CONTRIBUTION TO ECONOMIES .................. 72

6.2 CONSTRUCTION BUSINESS REQUIRES COMPETENCE ............. 74

6.2.1 Technical competences ........................................................... 76

6.2.2 Managerial/business competences ......................................... 76

6.2.3 Generic skills and knowledge competence .............................. 77

6.3 FACTORS CONSTRAINING THE COMPETITIVENESS OF SMME CONSTRUCTION BUSINESSES ...................................................... 77

6.4 CONTINUOUS TRAINING AND DEVELOPMENT ............................ 81

6.4.1 The concept of training and development ................................ 82

6.4.2 Modules of training and development programmes ................. 82

6.4.3 Model of training management ................................................ 83

a) Identifying training needs ................................................................ 85

b) Identifying competence gaps ........................................................... 87

c) Setting training objectives................................................................ 87

ix

d) Securing or designing training programmes .................................... 88

e) Training methods ............................................................................ 89

f) Providing training ............................................................................. 89

g) Evaluating the training ..................................................................... 91

h) Follow up training ............................................................................ 91

6.4.4 Benefits of training and development ...................................... 92

6.5 CONCLUSION ................................................................................... 93

CHAPTER SEVEN ..................................................................................... 95

RESEARCH METHODOLOGY .................................................................. 95

7.1 INTRODUCTION ................................................................................ 95

7.2 RESEARCH DESIGN ........................................................................ 95

7.3 RESEARCH TOOLS .......................................................................... 95

7.3.1 Questionnaire .......................................................................... 95

7.3.2 The structured interview .......................................................... 97

7.4 DATA COLLECTION .......................................................................... 98

7.5 RELIABILITY AND VALIDITY ............................................................ 99

7.6 RATING SCALE ............................................................................... 101

7.7 THE CORRELATION BETWEEN CDPs AND THEIR OUTCOMES 101

7.8 CONCLUSION ................................................................................. 102

CHAPTER EIGHT .................................................................................... 103

PRESENTATION OF RESULTS .............................................................. 103

8.1 INTRODUCTION .............................................................................. 103

8.2 RESPONDENTS’ PROFILES .......................................................... 104

8.3 RESULTS ........................................................................................ 105

8.3.1 Implementation of CDPs ........................................................ 105

8.3.2 Results on improvement of management skills ..................... 106

8.3.3 Results on contractor upgrades ............................................. 107

8.3.4 Results on participation of previously disadvantaged individuals .............................................................................. 109

x

8.3.5 Results on contractor satisfaction with the CDPs .................. 109

8.3.6 Value addition of the development programmes ................... 111

8.4 RESULTS FROM THE INTERVIEW ................................................ 112

8.4.1 Consultants’ responses on CDPs and contractors’ performance .......................................................................... 112

8.4.2 Contractors’ views on long term mentorship .......................... 112

8.5 IMPACT OF THE MENTORSHIP PROGRAMME ON CONTRACTORS’ CIDB GRADING ................................................. 113

8.5.1 Migration in CIDB grading in Vukuzakhe Contractor Development Programme ...................................................... 114

8.5.2 Migration in CIDB upgrade in the Masakhe Contractor Development Programme ...................................................... 115

8.5.3 Migration in CIDB upgrade in EPWP-Vuk'uphile Learnership Programme ............................................................................ 116

8.5.4 Migration in CIDB upgrade in Khuthaza Contractor Development Programme ...................................................... 117

8.5.5 Migration in CIDB upgrade in SCI Programme ...................... 118

8.5.6 Migration in CIDB upgrade in Eskom Construction Academy 119

8.5.7 Migration in CIDB upgrade in other construction development programmes .......................................................................... 120

8.6 CONCLUSION ................................................................................. 121

CHAPTER NINE ....................................................................................... 123

DISCUSSION OF THE RESULTS ............................................................ 123

9.1 INTRODUCTION .............................................................................. 123

9.2 QUESTIONNAIRE SURVEY RESULTS .......................................... 123

9.2.1 Improvement of management skills ....................................... 123

9.2.2 Contractor upgrades .............................................................. 124

9.2.3 Participation of PDIs .............................................................. 125

9.2.4 Contractor satisfaction ........................................................... 126

9.3 STRUCTURED INTERVIEW RESULTS .......................................... 127

9.3.1 Consultants’ perception of CDPs’ impact on contractor performance improvement ..................................................... 127

xi

9.3.2 Contractors’ perceptions on mentorship ................................ 127

9.4 KEY FINDINGS ................................................................................ 128

9.4.1 Continuous contractor mentorship ......................................... 129

9.5 CONCLUSION ................................................................................. 131

CHAPTER TEN ........................................................................................ 132

SUMMARY, CONCLUSIONS AND RECOMMENDATIONS .................... 132

10.1 INTRODUCTION ................................................................... 132

10.2 OBJECTIVES OF THE STUDY ............................................. 132

10.2.1 Objective one......................................................................... 132

10.2.2 Objective two ......................................................................... 133

10.2.3 Objective three ...................................................................... 133

10.2.4 Objective four ........................................................................ 133

10.3 CONTRIBUTION AND VALUE OF THE RESEARCH ........... 134

10.4 CONCLUSION ....................................................................... 134

10.5 RECOMMENDATIONS ......................................................... 135

10.5.1 Methodological ...................................................................... 136

10.5.2 Theoretical ............................................................................. 136

10.5.3 Practical ................................................................................. 136

10.6 LIMITATIONS ........................................................................ 137

10.7 SUGGESTION FOR FURTHER RESEARCH ....................... 137

10.8 CONCLUSION ....................................................................... 137

REFERENCES ......................................................................................... 140

APPENDICES .......................................................................................... 170

xii

LIST OF TABLES

Table 3.1: Requirement in relation to contractor grading designation ........... 33

Table 4.2: CDP gaps in some developing countries ....................................... 58

Table 5.1: Factors for successful CDPs ........................................................ 70

Table 7.1: Cronbach’s Alpha Coefficient ...................................................... 100

Table 8.1: Implementation of CDPs .............................................................. 105

Table 8.2: Improved management skills ....................................................... 106

Table 8.3: Contractor upgrade ...................................................................... 108

Table 8.4: Participation of PDIs ................................................................... 109

Table 8.5: Contractor satisfaction ................................................................. 110

Table 8.6: Migration in CIDB grading in Vukuzakhe CDP ............................ 115

Table 8.7: Migration in CIDB grading in Masakhe CDP ................................ 116

Table 8.8: Migration in CIDB grading in Vuk'uphile CDP .............................. 117

Table 8.9: Migration in CIDB grading in Khuthaza CDP ............................... 118

Table 8.10: Migration in CIDB grading in SEDA CDP .................................... 118

Table 8.11: Migration in CIDB grading in Eskom CDP ................................... 119

Table 8.12: Migration in CIDB grading in others CDP .................................... 120

xiii

LIST OF FIGURES

Figure 5.1: The structure of SACEM ................................................................ 61

Figure 5.2: The structure of IECDM ................................................................. 65

Figure 5.3: Supply-side interventions required to accelerate the growth of prioritised enterprises .................................................................... 68

Figure 5.4: Elements of successful CDPs........................................................ 71

Figure 6.1: Eckstrand's systems model of training ........................................... 83

Figure 6.2: The ADDIE model of training ......................................................... 84

Figure 6.3: The PRISM model for training management ................................. 85

Figure 6.4: The hierarchy of training needs ..................................................... 86

Figure 8.1: CIDB grading before and after CDP ............................................ 108

Figure 8.2: Response on whether CDPs were a waste of time ...................... 111

Figure 8.3: Percentage of migration in CIDB grading .................................... 114

xiv

LIST OF ACRONYMS

CCM Continuous contractor mentorship

CDP Contractor development programmes

CETA Construction Education Training Authority

CIDB Construction Industry Development Board

CIP Contractor incubator plan

CPD Continuous professional development

CSIR Council for Scientific and Industrial Research

ECDP Emerging Contractor Development Programme

EPWP Expanded Public Works Programme

ETQA Education and Training Quality Assurance

FIEC European Construction Industry Federation

GDP Gross domestic product

HDI Historically disadvantaged individuals (see PDI)

IECDM Integrated Emerging Contractor Development Model

ILO International Labour Organisation

NDPW National Department of Public Works

OECD Organization for Economic Co-operation and Development

PDI Previously disadvantaged individuals (see HDI)

RDP Reconstruction and Development Programme

SACEM South African Construction Excellence Model

xv

SAFCEC South Africa Federation of Building and Civil Engineering

Contractors

SEDA Small Enterprise Development Agency

SETA Sector Education and Training Authorities

SME Small and medium-sized enterprises

SMME Small, medium and micro Enterprises

StatsSA Statistics South Africa

xvi

DEFINITIONS

Construction industry – the broad conglomeration of industries and sectors

which add value in the creation and maintenance of fixed assets within the built

environment (CIDB Act, Act No.38 of 2000).

Contractor – a person or body of persons who undertakes to execute and

complete construction works (CIDB Act, Act No.38 of 2000).

Emerging enterprise – an enterprise which is owned, managed and controlled by

previously disadvantaged persons and which is overcoming business

impediments arising from the legacy of apartheid (CIDB Act, No.38 of 2000).

Empowerment – a process whereby SMME entrepreneurs reduce their situation

of dependency in relation to the historical dominance of white-owned business

(Havemann, 1999).

Enabling environment – a set of interrelated conditions (such as legal,

organisational, fiscal, informational, political and cultural) that impact on the

capacity of development actors (Brinkerhoff, 2004).

Management skills – skills required for dealing with or controlling things or people

(Kohlrieser, 2006:99–122).

Mentorship – a human development process that facilitates personal and

professional growth (CMIT, 2010).

Project – a construction works contract or a series of related construction work

contracts (CIDB Act, Act No.38, 2000).

Qualification – formal education level attained in capacity, knowledge or skill at a

higher learning institution that makes someone suitable to be a practitioner of a

particular profession (CETA, 2000).

Training – acquisition of skills and competencies as a result of practical skills

imparted to the individual professional (CETA, 2000).

1

CHAPTER ONE

INTRODUCTION

1.1 BACKGROUND

This chapter introduces the study by providing the background and the problem

context for the research. It states the research questions, the aims and objectives of

the study followed by the research hypotheses. The chapter goes on to explain the

benefits of the study to the built environment, the scope of the study and the

delimitations of the study. Lastly, the chapter outlines the structure of the dissertation.

CDPs have been seen as the solution needed to assist SMMEs to develop their

capabilities to the standard of large enterprises. CDPs in South Africa can be traced

back to 1995 when the National Department of Public Works (NDPW) announced

programmes intended to support contracting companies owners by PDIs to develop

their expert and managerial skills so that they could be equipped to compete with

construction firms established (NDPW, 2004:3).

Subsequent to this initial programme, most regional governments developed CDPs

with similar intents as those of the NDPW. The modelling, outline and the execution of

some of these programmes have been extensively studied, such as the CDP (CIDB,

2011:1-35), the South African Construction Excellence Model (SACEM) (Dlungwana

et al., 2002:1-8) and the Integrated Emerging Contractor Development Model (IECDM)

(Hauptfleisch et al., 2007:1-13).

Even though there are some positive outcomes achieved by some of these CDPs in

the past as postulated by Havemann (2001), Söderbaum (2001) and Mojapelo, Rakale

and Gertzen (2001), McCutcheon and Parkins (2002), , there still appears to be a

limited amount of literature on the success of CDPs and whether they remain useful

to the clients. As Jacquet (2002:7) observed:

“The greatest challenge that exists today in South Africa lies in the fact that no

data is available on how effective interventions are, whether they are achieving

successes, and which sector requires most assistance”.

2

The CIDB concurs with this assertion by recommending that the CPDs must be

evaluated to seek “…the perceptions of the programme beneficiaries on the direct

effects of the programme in addressing their needs” (CIDB, 2011:84).

Studies have shown that few assessments have been carried out on the effects of

CDPs in South Africa, and therefore considerable work remains to be done (CIDB,

2009). This assertion has been affirmed by a study conducted by the OECD in 2002,

where the United Kingdom (UK) and Japan were the only ones that assessed the

results of their training programmes (OECD, 2002:17). Therefore, the current study

endeavours to investigate contractors’ perceptions of CDPs in South Africa and how

beneficial these have been to them. The evaluation was considered to be vital as it

would contribute towards improving the CDPs. The CDPs are critical to the

sustainability of SMMEs.

The significance of SMMEs in general and specifically those in the construction sector

has been thoroughly researched worldwide. It was observed by the World Bank

(2003:3-4) that the contribution of SMME’s is crucial to economic growth, which is

essential for a competitive and efficient market. This plays a criticial role in the

reduction of poverty and a principal role in the developing nations. Russian SMMEs

total 90 per cent of the overall number of companies in the economy, accounting for

45 per cent of the entire employment and 40 per cent of the total sales in the economy.

The Chinese economy outlook on the report was not much different, as SMMEs

totalled 99.9 per cent of the total number of firms, 84 per cent of the total employment

and 71 per cent of total sales of the economy (World Bank, 2003:6-8).

Therefore the participation of SMMEs in the construction industry is similarly important.

Their contribution to the industry is clear and cannot be overlooked, especially when

considering the importance of the construction industry to most national economies.

In Sri Lanka, for example, the construction industry contributed almost eight per cent

of the gross domestic product (GDP) and was seventh among 13 major sectors

contributing to the country’s GDP (Chamber of Construction Industry Sri Lanka, 2012).

In South Africa, the GDP contribution to the construction industry in 2012 was almost

4 per cent (Industry Insight, 2012:17).

3

For most parts of the world, the construction industry is critical. In India, the

construction industry is the second-largest employer after agriculture. The industry

employs about 18 million people directly and 14 million people indirectly (IHG Global

Insight, 2009:7). In 2000 the Palestinian construction industry contributed 26 per cent

to its GDP (Mahamid, 2011:1).

Similarly, Abor and Quartey (2010:1) stated that the contribution of SMMEs in general

to the Ghanaian GDP was 70 per cent and it accounted for 92 per cent of business in

Ghana. The construction industry, which is predominantly made up of SMMEs,

contributes approximately 10 per cent to the GDP (Mhango, 2010:2). In summary, the

input of the construction industry to GDP of all countries is approximately 5 to 10 per

cent and it is a major employer of people with up to 10 per cent of the working

population and the holder of half of the gross fixed capital formations of all countries

(Ofori, 2012:5)

Despite the SMMEs importance within a very strategic industry, research has shown

that these SMMEs are very vulnerable, particularly at their start-up phase and are

expected to ‘die’ before their maturity period, even in developed countries (OECD,

2002:7). The OECD (2002) observed that the smallest firms hardly survive for longer

than five years in developed countries. In developing countries, the survival rate is

even lower. In Malaysia, for example, it is estimated that 10 per cent of start-up

businesses survive beyond the tenth year (Sin, 2010:14). Rwigema and Venter

(2004) reported that around 80 per cent of South African small businesses ‘die’ before

their fifth year.

Consequently, training programmes have been developed to assist with reversing the

trend. These training programmes have to some extent assisted the survival of

SMMEs in developed countries as “…formal training and development cuts, failure

rate by half in the UK – all other things being equal” (OECD, 2002:8). In South Africa,

government initiatives since independence have assisted in sustaining the existence

of SMMEs (Berry et al., 2002). The CIDB (2009: i) also reported that “…there are

several instances where contractors have increased their CIDB grading by three or

four grades during or subsequent to their participation in the CDPs”.

4

Having recognised the potential of SMME construction businesses to contribute to

national economies, it is worth noting that the various initiatives aimed at improving

contractors’ performance in South Africa seemed to have failed to ameliorate

contractors’ ability to run successful businesses owing to a lack of knowledge on key

aspects. Greyling (2012:43) lamented that most SMME contractors do not have

enough understanding of the basic contracts being used in the country. Coupled with

the lack of understanding of basic contracts, most SMME contractors lack the

knowledge of tendering and procurement (Makhura, 2011:65). It is argued that this

lack of knowledge on key aspects causes SMME contractors to forfeit an average of

7 per cent of their profit margin owing to wrong costing and pricing calculations

(Greyling, 2012:7). Furthermore, construction clients are generally dissatisfied with the

quality of work delivered by SMME contractors (Mbachu & Nkado, 2006; Smallwood,

2010:941). The CIDB (2011:4) reported that 10 per cent of the Department of Human

Settlement’s budget for 2009/10 was used to repair houses owing to poor quality of

work from SMME contractors. Eventually, non-performing SMME contractors end up

closing down their businesses.

There is extensive literature on the development and implementation of CDPs and

models in the country (CIDB, 2011:1–35; Dlungwana et al., 2002:1-8; Hauptfleisch et

al., 2007:1–13). Despite these studies, there appears to be little literature on how the

beneficiaries of these programmes perceive them. It is argued that any worthwhile

project must receive an evaluation by the beneficiary. It is therefore warranted that

research should be conducted to ascertain the perception of the beneficiary

contractors on whether the CDPs have assisted in improving contractors’

management skills, whether the CDPs have translated into an upgrade in CIDB

grading, whether the CDPs have ensured an increase in participation of companies

belonging to PDI and, finally, whether the beneficiaries are satisfied with the CDPs.

Therefore the objective of this research was to establish how beneficial contractors

rate the CDPs in which they have participated in South Africa with the aim of improving

these CDPs. The approach used in this study was aimed at finding out the extent to

which the participating contractors rate the CDPs relative to their intended goals.

Therefore the following procedure was adopted:

5

A literature review on CDPs in South Africa and internationally;

A questionnaire survey among beneficiary contractors to seek their views on

how they rated the CDPs;

Structured interviews conducted with beneficiary contractors and consultants

on the importance of CDPs and whether they have assisted in improving

contractors’ performance; and

Conclusions drawn on the findings of the questionnaire survey and structured

interviews.

Problem statement

Studies have shown that few assessments have been carried out on the effects of

CDPs in South Africa, and therefore considerable work remains to be done (CIDB,

2009). Therefore, the current study looks to investigate the extent to which the

contractor development programmes have helped in the improvement of contractors’

management skills, the extent to which the contractor development programmes have

ensured the registration status of contractors at the CIDB, the relationship between

contractors, the achievement of an increased participation of PDIs/organisations in

the construction industry and, finally, the way the beneficiaries rate the contractor

development programme.

RESEARCH QUESTIONS

Based on the above problem statement, the following research questions have been

defined for the study:

Research Question 1

What is the extent to which contractor development programmes have helped in the

improvement of contractors’ management skills?

Research Question 2

What is the extent to which contractor development programmes have ensured the

upgrade in CIDB registration status for contractors?

6

Research Question 3

What is the relationship between contractor development programmes and the

achievement of an increased participation of PDIs/organisations in the construction

industry?

Research Question 4

How do the beneficiaries of contractor development programmes rate these?

1.2 RESEARCH OBJECTIVE

The objective of the research was to investigate the effectiveness of Contractor

development programmes (CDPs) in general with a view to contributing to their

improvement.

1.3 OBJECTIVES

Objective 1

To investigate the extent to which contractor development programmes have helped

in improving contractors’ management skills

Objective 2

To investigate the extent to which contractor development programmes have ensured

contractors’ upgrade/upgrading in CIDB registration status

Objective 3

To examine the relationship between contractor development programmes and the

achievement of an increased participation of PDIs/organisations in the construction

industry.

Objective 4

To establish how beneficiaries of contractor development programmes rate these CDP

programmes.

7

1.4 BENEFIT OF THE STUDY

It has been shown that the construction industry is an important sector in a country’s

economy and that SMME contractors play a significant role in this sector. Therefore

there is a need to train and develop SMME contractors. In order to develop better

training programmes, there is also a need to evaluate the effectiveness of the current

programmes. The starting point is to establish from the beneficiaries of these training

programmes whether the development programmes are achieving their intended

purpose, and if not, what the best implementation method will be for the achievement

of results. This will assist in improving the current states of CDPs.

1.5 SCOPE OF THE RESEARCH

The study is in the form of a summative evaluation which focuses on contractors who

have undergone CDPs and successfully graduated or who are still undergoing the

CDP in Gauteng Province. Consultants’ opinions on the effectiveness of CDPs were

also solicited in order to arrive at a reasonable conclusion.

The premise is that the collected sample represents the view of contractors who have

undergone the various development programmes.

1.6 DELIMITATION OF THE STUDY

The study did not evaluate the structure and the curriculum of CDPs per se and it also

did not investigate how contractors are chosen to participate in these development

programmes. The study evaluated how beneficiary contractors viewed these CDPs

and suggests methods of improving the effectiveness of the CDPs.

1.7 STRUCTURE OF THE REPORT

The report has been structured and organised in chapters and sections as follows:

Chapter 1 - Introduction

This chapter introduces the study, states the importance of SMME construction

industries and explains why contractors must be trained. It also details the problem,

objectives and the benefit of the study.

8

Chapter 2 – Literature Review

This chapter looks at the historical background of CDP in sub-Saharan Africa in

general.

While Chapter 3 presents a review of literature on South Africa Specifically. This

chapter discusses the performance of CDP in South Africa. The conception of these

CDPs, their planning and design, their implementation models, international best

practices and gaps within these CDPs are identified and discussed.

Chapter 4 – Review of International Contractor Development Programmes. This

chapter reviews the CDPs of some third world countries.

Chapter 5 – Contractor Development Models

This chapter looks at selected contractor development models designed to assist with

the development of contractors in South Africa. The chapter compares the models and

examines the similarities and the common factors of the models. These similarities

and common factors were then compared with the literature reviewed on CDPs

internationally. A matrix was produced to assist with identifying the common elements

for better CDP implementation to achieve a better result.

Chapter 6 – Importance of CDPs in the Construction Industry

This chapter discusses the construction industry as a whole. The industry’s

contributions to national economies, the competencies required to run a construction

business and the factors constraining these competencies are presented in this

chapter. In addition, the concept and the benefits of training and development to both

individuals and organisations are also reviewed in this chapter.

Chapter 7 – Research Methodology

This chapter describes the design of the research and the method employed to

investigate the performance of CDPs in South Africa. In addition, it presents the

methods used to analyse and present the data.

9

Chapter 8 – Presentation of Results

Results from the survey are presented in this section. Chapter 8 builds on the research

methods and approaches discussed in Chapter 7 the data received from the survey

are analysed and the results are presented.

Chapter 9 – Discussion of the Results

The interpretation and an extensive discussion of the results are presented in Chapter

8. The findings on the key objectives of the study are therefore presented in this

chapter.

Chapter 10 – Summary, Conclusion and Recommendation

This final chapter concentrates on studying the role of this study regarding the body of

knowledge on CDPs. The aims and objectives of this research are revised. An outline

of each chapter is also presented, indicating how each chapter narrates the aims,

analysing and describing their contribution to the research.

1.8 CONCLUSION

In this chapter, the various components of the study are presented. The research

problem, rationale, research questions and the structure of the project are discussed.

It is against this background that an understanding of the present research was

attained. This chapter also emphasised the understanding of contractor development

programmes. The next chapter discusses the theory and literature on contractor

development programmes in the construction industry.

10

CHAPTER TWO

LITERATURE REVIEW: CONTRACTOR’S DEVELOPMENT PROGRAMMES

2.1 INTRODUCTION

Chapter 2 presents a review of literature on the CDPs that have been implemented

around the world and South Africa. An assessment of the framework of contractor

development programmes regarding their purposes, objectives and their patterns in

implementing nations is also conducted. The chapter further discusses the importance

of the building industry to the socioeconomic growth of nations, the part played by

SMME contractors in economic evolution, problems faced by these SMME contractors

and the reasons why they have to be prepared and be competitive. Literature on the

importance of mentorship and development to businesses is also presented in this

section.

2.2 HISTORY OF CONTRACTOR DEVELOPMENT PROGRAMMES

The current concept of contractor development, according to McCutcheon and Parkins

(2002:1), can be traced to 1969 when the ILO initiated the World Employment

Programme (WEP) in Geneva, with the primary aim being to test and define an

engagement-oriented growth strategy. According to Croswell and McCutcheon

(2001:2), this employment-oriented development transformed into small CDPs in sub-

Saharan Africa in the 1970s owing to the lack of local, indigenous contractors to

enforce the policy, and the overriding presence of large foreign contractors. There is

evidence of some success of small CDPs in some sub-Saharan countries such as

Ghana, Kenya, Lesotho and Malawi (Larcher, 1998; Ofori, 2002; Eyiah, 2004).

The background to the current CDPs in South Africa could/can, however, be traced

back to 1995 when the National Department of Public Works (NDPW) announced

programmes designed at supporting contracting businesses owned by the Previously

Disadvantaged Individuals (PDI.) These programmes were designed to develop

SMME’s technical and managerial skills so that they could be able to contend/compete

with reputable construction companies (NDPW, 2004:3).

11

Historically, most countries have developed their local contractors to withstand

challenges and adversities caused by foreign construction companies, and for South

Africa, the imbalances caused by historical events (Adams, 1997; Larcher, 1998;

Croswell & McCutcheon, 2001; Verwey & Havemann, 2001; McCutcheon, 2008; Ofori,

2012).

It should also be noted that the challenges facing SMME contractors in South Africa

are not only old/historical but are also related to current challenges such as

globalisation, demographic changes, the demand for green and sustainable buildings,

technical advancement and threats from emerging economies (Department for

Business, Innovation and Skills, (DBIS), 2013:7). Therefore it is prudent that all

contractor development stakeholders keep track of the changes and requirements of

the industry to enable them to keep abreast of all aspects of the sector.

CDPs are capable of influencing contractors’ human resource development, materials

development, engineering development, company growth, documentation

development, routines and working environment, institution building, and the evolution

of working surroundings (Ofori, 2012:8). Consequently, these development

programmes are essential and critical to growth.

2.3 CONTRACTOR DEVELOPMENT PROGRAMME FRAMEWORKS

As different nations design and carry out their own programmes based on what they

want to accomplish, and with fluctuating results emanating from these programmes

owing to several/diverse reasons stated by the CIDB (2011), there is a need for the

adoption of a set of minimum requirements for every CDP. According to the CIDB

(2011:8), the ILO made a proposal to improve the performance of CDPs in developing

countries. Such as pointed out by CIDB (2011) include the following:

Improving access to employment opportunities: Where tender procedures

and tender documentation are made simpler, projects are packaged into

smaller sizes for the contractors’ easy handling and encouraging sub-

contracting for smaller contractor sustainability.

12

Improving the business environment: Where requirements for providing

performance bonds and retention requirements, guaranteed loan schemes,

selected contractors’ access to mobilisation allowances, figures and financial

education for contractors and the right of contractors to use to materials and

equipment are relaxed for contractors’ development.

Offering training and advisory services: The development and

implementation of training systems that are fitting and suitable for contractors

and encouraging contractors on the significance of such training arrangements

(CIDB, 2011:8).

Aside from the ILO basis, the CIDB (2011:8) also suggests that the following best

practices must be included in the development programmes:

Promotion of recent technological applications and through combined research

on development and technology transferal methods of construction;

Promotion of uniform and value-added techniques of construction to improve

output and effectiveness; and

Facilitation of interactions and sub-contracting opportunities,

formation/maintenance of cordial associations with professionals within the

industry and the government, and facilitation of standardised design

specifications, details and documentation (CIDB, 2011:8).

2.3.1 Qualities of a successful contractor development programme

In this respect there are some qualities that good development programmes need to

exhibit to assure their efficacy. Such qualities, when properly incorporated into SMME

training programmes, are likely to ease most of the challenges confronted by the

contractors. As proposed by Van der Kuip and Verheul (2003), Martin (2004),

Dlungwana and Rwelamila (2004), Vanderstraeten and Matthyssens (2005), Ofori

(2006) and Storey (2008), such best practices may include what the CIDB (2011) has

recorded under the following two headings:

2.3.1.1 Programme organisation

An effective programme should have:

13

a political backing and that of senior management of the implementing

organisations;

appropriate objectives and dedication by the implementing organisations to

take on such objectives;

a defined and sufficient budget for its conception and execution;

sufficient management resources to drive its implementation;

a flexible model that houses the dynamic needs of contractors at changed

levels of advance, and encourages the implementation of industry Grade A

practices;

constant monitoring and reporting systems to track its achievements; and

a way to integrate all the development activities, and stakeholders from

government and the private sector (CIDB, 2011:11).

2.3.1.1 Contractor interventions

The other aspect has to do with contractor interventions. An effective development

programme should:

develop strategies for procurement and instruments to make available

continuous and lucrative work openings for contractors on the programme;

provide suitable and reassuring structures to assist contractors on contractual

issues such as provision of sureties and guarantees;

provide suitable contract management and quality assurance mentorship to the

contractors;

enable participating contractor’s easy admittance to funding, credit and working

capital;

develop a suitable technical capability, construction management and quality

control know-how to contractors through teaching and mentoring to enhance

their progress;

be able to facilitate right to use economical materials, plant and machinery;

afford graduates entrée to information and information technology (IT);

connect contractors to stakeholders’ expertise development programmes;

ensure transparent selection and registering of contractors;

14

access and identify individual contractors’ training and mentoring needs;

assess the performance and grade accordingly to monitor their development;

and

have clear milestones with the guidelines and method of entry and departure

points (CIDB, 2011:11).

In support of the above, Croswell and McCutcheon (2001:365-379) also observed that

successful CDP should have certain approaches which should include, inter alia:

continuity of contracting opportunities;

training and ongoing mentoring;

high level support; and

institutional support.

The authors further argue that a successful programme should be structured as a

series of consecutive contracts, during which the fundamentally-trained small

contractors are progressively mentored until they are able to act independently, that

is, having the entrepreneurial approach towards marketing for work and tendering

successfully to ensure their sustainability (Croswell & McCutcheon, 2001: 365–379).

2.3.2 Aims and objectives of contractor development programmes

Nations do not have the same aims for the design and execution of their development

courses. For example, Khan (2004:1) stated that the CDP of Brunei Darussalam was

aimed at entrepreneurship education and training to foster enterprise development.

On the other hand, according to Ofori (2012:10), Malaysia’s development programme

was aimed at evolving Malaysia’s construction sector into a world-class, advanced,

expert international resolution provider, whereas Singapore’s Construction 21 initiative

was aimed at increasing the output of the industry by upgrading its practices and

processes (Ofori, 2012:8).

The objectives of the development programme in Tanzania were different from that of

Singapore. The Contractors’ Registration Board (CRB) development programme in

Tanzania went after the closing of gap skills which existed between contracting firms

15

internationally and locally. In addition, the development programme was also designed

to improve the ability of local contractors so that they could perform at optimum levels

(Uriyo & Jere, 2003:1).

Therefore the CIDB (2011:4) recommends that CDPs should be developed and

implemented on the basis that contractors have different needs and are at different

stages in their life. Consequently, the CIDB recommend that the national framework

for CDPs requires programmes be developed along the following principles:

2.3.2.1 Construction workforce development

This aims at the training of CIDB contractors through artisan and supervisor

development. The programme targets the growth of companies within the CIDB

grading of 1 to 5 through leadership and other skills development of contractors. This

basically aims at the development of the construction workforce.

2.3.2.2 Contractor development

According to CIDB (2011:4), this should be targeted at the growth of the construction

organisation and comprises the following:

Emerging contractor development: The group targeted here are contractors

with CIDB grading 2 to 3 where contractors’ skills in the business side of

contracting are developed through mentorship and learnership programmes.

Examples of skills taught here include tendering, pricing, financial

management, marketing and contract administration.

Enterprise development: The aim of this programme is to assist contractors

to market themselves properly to prospective clients, to accumulate capital and

to be able to break into higher grades and different markets. The targeted

groups are Grade 3 to 6 contractors. The aim is to train contractors’ survival

strategies in a competitive bidding environment.

Performance improvement: Grade 4 to 7 contractors are the target for this

training. At this level, contractors are presumed to have completed the previous

training levels and are looking to introduce best practice management systems

16

such as quality management, health and safety, and environmental

management in order to improve their sustainability.

CDPs are planned and implemented in countries or localities with the intention of

eradicating or improving some particular circumstances. The CDPs in South Africa,

for example, were also developed to give effect to the affirmative action agenda.

Therefore the CDPs target firms owned and operated by women, the disabled, youth

and individuals who were previously unable to participate in the economy (CIDB,

2011:6).

2.3.3 Challenges of contractor development programmes

Just as with many other development programmes, the various contractor intervention

programmes have their own challenges. The challenges have been widely

documented (Dlungwana & Rwelamila, 2004; Ofori, 2006; Buys & Ludwaba, 2013).

The CIDB (2011) has summarised these challenges and listed them as including, inter

alia, the following:

Access is usually open to all interested participants, thus leading to difficulty in

selecting the appropriate entrants into a programme;

Lack of insistence on prior experience in the industry, and on prior technical,

managerial and construction related skills;

Inadequate training and difficulties in synchronising training to make it available

at times suitable for contractors and their workloads; in addition, the amount of

training required both for contractors and development agency staff is generally

underestimated;

Contractors with little understanding of the nature and complexity of

construction, and how to deal with rising risks;

Unequal access to finance, trade credits and guarantees;

Lack of construction-specific skills such as pricing, project management and

the programming of site activities, contract conditions, and risk management;

Reluctance to employ qualified personnel, normally due to fiscal restraints;

Compromising quality over speed and budgetary considerations;

17

Low profit margins in the industry, reducing the viability of small contractors

irrespective of intervention;

Lack of understanding or commitment on the part of the contractors to the

objectives of contractor development, and to improving their performance as

contractors;

Difficulty in creating a culture of entrepreneurship among contractors,

especially among survivalist firms;

Fluctuating industry workloads;

Institutional challenges, including limited training institutions and the dearth of

appropriate training materials, legal challenges to the selection and provision

of services to a select group, poor management, a lack of financing for the

programmes, and difficulty identifying deserving contractors; and

Lack of monitoring and valuation of the programmes and the use of

inappropriate metrics to measure success (such as the number of companies

trained and the quantity of credit disbursed) (CIDB, 2011:10-11).

The CDPs face many challenges and in many instances mentorship is sidelined.

2.4 MENTORSHIP IN CDPs

Mentorship is a vital element in professional development and it seems to be lacking

in a number of CDPs. Mentoring is a relationship between two people, namely a

mentor and the protégé. It is very complex and varies from one situation to another

(McKimm et al., 2007:1). Mentoring is also defined as a one-to-one relationship in

which an expert or a senior person voluntarily gives time to teach, support, and

encourage another (Inzer & Crawford; 2005:32). Mentorship has been identified as an

important factor in professional development in both the public and private sector (The

United States Office of Personnel Management [USOPM], 2008:2).

Mentoring is a protected relationship in which learning and experimentation occur

through analysis, examination, re-examination and reflection on practice, situations,

problems, mistakes and successes (of both the mentors and the mentees) to identify

learning opportunities and gaps (McKimm et al., 2007:5).

18

Literature abounds with information regarding when mentoring and mentorship

actually started. McKimm et al. (2007:2) argue that informal mentorship can be traced

back to Greek mythology when Odysseus entrusted his son, Telemachus, to the

goddess, Athena, while he went on a ten-year journey. The goddess disguised herself

in human form as a mentor, an old friend of Odysseus whose function was to act as a

wise counsellor and helper to the youth. On the other hand, Douglas (1997) posits that

formal mentoring relationships were developed in the 1930s by the Jewel Tea

Company but did not grow significantly until the 1980s, when their rapid expansion

was fuelled by the attention given in the literature to the effectiveness of informal

mentoring relationships and to the growing body of work that supported the importance

of developmental relationships in career development (Douglas, 1997:75).

2.4.1 Components of mentoring in training and development

Mentoring has been identified as being a vital component of a successful training and

development programme. There are copious empirical studies regarding the

definitions and the importance of mentoring and mentorship. McKimm et al. (2007:1)

explain that a mentor is someone who helps another person through an important

transition such as coping with a new situation such as a new job or a major change in

personal circumstances such as in career development or personal growth. Inzer and

Crawford (2005:32) also point out that a mentor is someone who helps a protégé learn

something that he or she would have learnt less well, more slowly, or not at all if left

alone.

Mentoring has many benefits to individuals and organisations. Organisations choose

mentoring for their various benefits such as for career development and an increase

in an organisation’s productivity. The United States Office of Personnel Management

(2008:3) listed some of the reasons why organisations implement mentorship which

include, inter alia:

On boarding process – mentors help new recruits, trainees or graduates to

settle into the organisation;

Skills enhancement – mentoring enables experienced, highly competent staff

to pass their expertise on to others who need to acquire specified skills;

19

Professional identity – mentors play a role in defining professional behaviour

for new employees;

Career development – mentorship helps employees plan, develop and

manage their career;

Leadership and management development – mentoring encourages the

development of leadership competencies that are gained through examples,

guided practice or experience by education and training;

Education support – mentoring helps bridge the gap between theory and

practice. Formal education and training is complemented by the knowledge and

hands-on experience of a competent practitioner;

Organisational development and culture change – mentoring can help

communicate the values, vision and mission of the organisation; a one-to-one

relationship can help employees understand the organisational culture and

make any necessary changes;

Customer service – mentoring assists in modelling desired behaviours,

encouraging the development of competencies in support of customer service,

and above all, cultivating the right attitudes; and

Knowledge management/knowledge transfer – mentoring provides for the

interchange/exchange of information/knowledge among members of different

organisations.

The components of mentoring are the mentor, the protégé, the relationship, and the

atmosphere in which they operate (Inzer & Crawford; 2005:32). The atmosphere,

according to Inzer and Crawford (2005:32), could be the organisation, friendship or

family.

Since a mentor is defined as being an advice-giver, counsellor, confidant, promoter,

and listener, he or she must be self-assured, sensitive to diversity, and be a good

communicator (Inzer & Crawford, 2005:32). The mentor’s role includes, among others,

identifying the protégés’ career goals, providing guidance and career advice,

encouraging their career and personal development to the fullest, sharing own insights

into the organisation, providing ideas on happenings and information that would

benefit the protégé’s growth, commending pursuits that will develop specific areas in

20

the protegés’ professional advancement, and assisting employees by being a

reference and advocate (Inzer & Crawford, 2005:32; USOPM, 2008:3-5;

Douglas,1997).

There are mainly four types of mentors, according to the USOPM (2008:4):

Career guide – promotes development through career guidance, counselling

and visibility;

Information source – provides information about formal and informal

expectations;

Friend – interacts with the protégé socially and provides information about

people; and

Intellectual guide – promotes an equal relationship, collaborates on research

projects and provides constructive feedback and criticism.

Organisations’ and corporates’ planning mentoring programmes should therefore

consider the type of mentors to use with care.

The second part is the protégé, the mentee. The primary role of the protégé is to learn

new knowledge and skills from the mentor (Construction Manager in Training Program

(CMIT), 2010:7).The protégé must have knowledge of his or her needs. The protégé

must be in constant communication with the mentor. The mentee must develop priority

issues for action, must seek comment and come ready to each meeting to discuss

topics, and must not require the mentor to be knowledgeable in all areas (Inzer &

Crawford, 2005:34; CMIT; 2010:7).

The third aspect in mentoring is the relationship. This is the relationship between

mentor and protégé, and it must be a special relationship where two people make a

real connection with each other, in other words they form a bond (McKimm et al.,

2007:5). According to Inzer and Crawford (2005:34), there must be an understanding

between the mentor and protégé as sometimes the relationship may not always work

and the mentor must be happy in accepting the success of the protégé. If the

relationship between the protégé and the mentor is not working, it should be

terminated (Inzer & Crawford, 2005:34).

21

Apart from the relationship, mentorship also depends on the organisation. According

to Inzer and Crawford (2005:35), this is the atmosphere in which mentoring takes

place. The organisation must be an active participant, it should provide the necessary

resources and time required for the personnel to participate and it must develop

mentors and protégés through training and education (Inzer & Crawford, 2005:35).

Finally, the organisation must have the mentoring programme high on the priority list,

with sufficient resources and training, or not go into an official mentoring programme

(Inzer & Crawford, 2005:35).

2.4.2 Mentorship programmes

There are two main types of mentorship, namely informal and formal mentorship.

Informal mentoring is a natural component of relationships that occur throughout

society, in the workplace, in social, in professional and in family activities (Inzer &

Crawford, 2005:35). Informal mentoring occurs in a relationship between two people

where one gains insight, knowledge, wisdom, friendship, and support from the other.

It has minimal to no structure and oversight, may or may not have a clear and specific

goal and is normally for interpersonal enhancement, but can also promote career

development (USOPM, 2008:4).

On the other hand, formal mentoring programmes are more effective and structured

(Inzer & Crawford, 2005:35), have oversight, and have clear and specific

organisational goals (USOPM, 2008:4). According to the Workplace Gender Equality

Agency (WGEA) (2013:16), formal mentoring occurs when the relationship is

facilitated and supported by the organisation so that more participants can benefit.

2.4.3 Benefits of mentoring for the mentor and the protégé

There is much literature with evidence of the benefits of mentoring to an individual and

organisations. Douglas (1997) Inzer and Crawford (2005), McKimm et al. (2007) and

WGEA (2013) have all elaborated on the benefits of mentoring to mentors and

protégés and these benefits are as follows:

For a mentor, the benefits include the following:

Renewed enthusiasm for the role of expert;

22

Obtaining a greater understanding of the barriers experienced at lower levels

of the organisation;

Enhancement of skills in coaching, counselling, listening and modelling;

Developing and practising a more personal style of leadership;

Demonstrating expertise and sharing knowledge; and

Increased generational awareness (USOPM, 2008:4-5).

As for the protégé, the benefits include the following:

Making a smoother transition into the workforce;

Development as a professional;

Gaining the capacity to translate values and strategies into productive actions;

A complement to ongoing formal study and/or training and development

activities;

Gaining some career development opportunities;

Developing new and/or different perspectives;

Getting assistance with ideas;

Demonstrating strengths and exploring potential; and

Increasing career networks and receiving greater agency exposure (USOPM,

2008:4-5).

The above benefits summarise the benefits of mentoring to both the mentor and the

protégé.

2.4.4 Mentorship of a company

Companies and organisations require mentorship to develop their capabilities just as

individuals require mentorship for their career and psychosocial development. The

behaviour of a company or organisation’s manager is likely to make or break the

organisation. Therefore entrepreneurial mentorship is required to assist the

sustainability of SMMEs. Whereas most SMMEs are unaware of business

mentorships, the few that are aware do not use the services of business mentors

(Business, Innovation and Skills (BIS), 2013). Among the contributing issues to the

23

possibility of accomplishment to the businessperson are the period and concentration

devoted to activites, including the identification of mentors (Gartner et al., 1992).

Owing to the complexity and range of tasks required of entrepreneurs it is required

that they need entrepreneurs. Higly relevant to the personal development of

entrepreneurs is the need of an entrepreneur to enable them to become positive role

models, motivating their mentees to copy them (Pompa, 2012:8). Mazzarol et al.

(2006:2) describe business mentoring as the practice of providing a way in which

business difficulties are examined and deliberated so as to agree to an entrepreneur

coming up with plans to solve present and possible future issues. The role of a

business mentor is to help as a contemplative counsellor to the entrepreneur,

functioning with everyone on developmental matters related to their endeavour. For

that reason it is vital to differentiate the role of a business mentor from that of a

consultant. A consultant makes available a contracted service and uses his/her

expertise to find a solution to complex problems (Mazzarol et al., 2006:2).

There are different definitions of business mentorship. Gravells (2006) defines

corporate mentorship as a mentoring backing provided to owners of small businesses,

both at start-up and beyond, whereas Harrington (1999) defines business mentorship

as the connection that includes one entrepreneur performing as a guide, serving to

manage the career and development of a less experienced entrepreneur.

The development and management of business mentoring programmes are complex

issues that require careful planning. To ensure a successful mentoring programme, it

is important for both the mentors and the protégés to agree to the affiliation, have a

strong bond and get on at their interpersonal level (Pompa, 2012:8). It is also

imperative to match the protégé’s wishes with the abilities, know-how and expertise of

the mentor (Mazzarol et al., 2006:3).

Protégés should be given clear instructions on how to get the best from their mentors

and mentors need to be taught on how to best interact with their protégé (Mazzarol et

al., 2006:3); By so doing the expectations and cultural differences of persons

concerning the position of mentors and their roles can be managed. However, the

mentor–protégé relationship raises a number of legal issues. Foremostly, there are

24

simple principles of agency and fiduciary responsibility that need to be managed and

monitored, as well as the management of conflicts of interest. Secondly, there are

matters of commercial discretion. Lastly, there is the concern of professional obligation

and covers between the parties. These issues, according to Mazzarol et al. (2006:3),

are of importance to the mentor–protégé relationship as they often serve as potential

obstacles to the successful implementation of the mentoring programmes. For the

mentor–protégé relationship to yield the required results, the mentor is required to

possess particular skills and characteristics which Cunningham and Eberle (1993)

outline as the following:

Personal security and confidence;

Readiness to trust;

Capability to communicate;

Introspection and openness;

Ability to be innovative;

Patience and tolerance; and

Accessibility.

Pompa (2012:8) states that the mentor’s skill, know-how, knowledge of the protégé’s

exact situation, and his or her accessibility are vital to the accomplishment of the

mentoring relationship.

Despite the benefits, a number of potential mentees resist enrolling for mentorship

programmes. Some of the reasons include trusting that mentors’ advice is not concrete

enough, not tailor-made to the state, too expensive or given by people who are not

sufficiently well acquainted with small businesses (Pompa, 2012:8; BIS, 2013; CIDB,

2009). Therefore the mentor–protégé relationship can only succeed if the protégé

demonstrates some characteristics and skills as outlined by Cunningham and Eberle

(1993) as follows:

Having the craving to learn;

Being people-focused;

Being goal-oriented;

25

Having abstract ability;

Being contemplative;

Showing initiative; and

Being assertive.

To succeed, a protégé in a business mentorship should exhibit most of the

characteristics above.

There are some common problems associated with mentors and protégés. The

mentor’s weaknesses can include nonexistence of time, absence of training, a

professional mismatch of expertise/personality, the extra burden connected with

mentoring and frustration with the mentee, while the protégé’s glitches include

gender/race problems, negative attitude of the mentee, jealousy, and pressure from

work (Pompa, 2012:9).

Mazzarol et al. (2006:4) postulate that most existing mentoring programmes are too

firmly fixated on improving abilities and capabilities alongside acquiring accreditation

as the primary objectives, rather than addressing the necessities of the entrepreneur,

and that they lack flexibility and can be too ‘academic’ or technical in nature.

Entrepreneurs are not identical in their learning requirements and require a more

flexible programme reflecting both a yearning/desire for individual learning and direct

backing from mentoring. It is therefore important that the selection of owner-managers

into business mentoring programmes be based on an individual needs assessment

report.

Mazzarol et al. (2006:4) maintain that the business mentoring process falls into three

phases, namely (i) the diagnostic assessment phase – where an initial business

diagnostic is done to provide a valuation of the business and how it accomplishes

against established management standards; (ii) the individual mentoring phase –

where contributors are coordinated with a personal mentor who works with the owner-

manager over the duration of the programme and (iii) the educational support phase

– where in addition to the facilitated workshops, online learning support is provided

that allows the owner-manager to download information and upload assignments.

26

It was also observed by Mazzarol et al. (2006:3) that the key role for a business

mentoring programme was to assist entrepreneurs to chart a course through the

investment linkage and widen their strategic networks while developing business

competencies.

According to Mazzarol et al. (2006:3), mentoring has been successful in some

countries to improve advance centres and to expedite the growth of new start-up

projects and the development of technology incubators. Thierstein and Wilhelm (2001)

observed that about 90 per cent of Swiss incubator, technology and invention centres

are offering mentoring services using either in-house or out-sourced services. In the

United States many former high-growth businesspersons who have now attained

success are offering their knowledge to ‘rookie’ and promising entrepreneurs through

a series of non-profit and for-profit mentoring services businesses (Mazzarol et al.

2006:4). A successful mentoring process should therefore include both formal and

informal processes in conjunction with education of the entrepreneur (Leonard &

Swap, 2000; Colman, 2002).

Great benefits of business or entrepreneurial mentorship processes and programmes

are recorded in the literature (Mazzarol et al. 2006; Pompa, 2012; BIS 2013). The

benefits can be divided into benefits to the protégé or entrepreneur and benefits to the

business. The benefits of business mentoring for the entrepreneur or protégé include,

among others, better performance and productivity; value-added knowledge and skills;

greater confidence, empowerment and well-being; job satisfaction improvement and

motivation; quicker learning and decision-making skills improvement; enhanced

understanding of the business; creativity and innovation improvement; positive risk-

taking encouragement; and development of leadership abilities. The benefits to the

enterprise or business consist of, among others, partnerships facilitation, change and

innovation, solving problems and better project management (Pompa, 2012:9;

Mazzarol et al., 2006; BIS, 2013).

The literature shows that time seems to be one of the key components that stands

between the success and failure of the mentor–protégé relationship.

Protégés/mentees have often requested more time to be with the mentors (Douglas,

27

1997; Inzer & Crawford, 2005; Mazzarol et al., 2006; McKimm et al., 2007; Pompa,

2012; BIS, 2013). Mazzarol et al. (2006:9) observed in their study that only one

respondent strongly agreed they had more than sufficient time with their mentor on an

individual basis. The bulk of the supporting remarks related to the need for additional

mentoring time and most of the protégés indicated their willingness to pay for

additional time with the mentors.

2.4.4.1 Section summary

The concept of CDP had its origins around 1969 when the ILO initiated WEP. WEP

then transformed into small CDPs in sub-Saharan Africa in the 1970s owing to the lack

of local, indigenous contractors to enforce the policy and the overriding presence of

large foreign contractors (Croswell & McCutcheon, 2001). The small CDPs have been

successful in some sub-Saharan countries such as Ghana, Kenya, Lesotho and

Malawi (Larcher, 1998; Ofori, 2002; Eyiah, 2004). Based on the small CDPs, in 1995

the NDPW of South Africa announced programmes intended at supporting contracting

organisations owned by PDIs to improve their technical and managerial skills and

allow them to compete with well-known construction organisations (NDPW, 2004:3).

There are some challenges facing the successful implementation of contractor

development which include, inter alia, a lack of mentoring after graduation, a lack of

resolve on preceding experience in the industry, and contractors with little or no

understanding of the nature and complexity of construction industry or how to deal

with rising risks.

However, the success of every CDP has to be based on some best practice such as

continuity of contracting opportunities, training and ongoing mentoring with a high level

and institutional support (Croswell & McCutcheon, 2001:365–379). Mentorship has

been found to be very important in the quest for value addition to better CDPs.

However, studies indicate that mentorship should be continuous until the protégé is

able to perform independently, as opposed to once-off mentorship programmes.

28

2.5 CONCLUSION

This chapter presented an overview of of literature on CDPs around the world. An

assessment of the framework of contractor development programmes regarding their

purposes, objectives and their patterns of implementions was also discussed. The

chapter further commented on the importance of the building industry to the

socioeconomic growth of nations, the part played by SMME contractors in economic

evolution, problems faced by these SMME contractors and the reasons why they have

to be prepared and be competitive. Literature on the importance of mentorship and

development to businesses was also presented in this section.

29

CHAPTER THREE

CONTRACTOR DEVELOPMENT PROGRAMMES – SOUTH AFRICAN PERSPECTIVE

3.1 INTRODUCTION

This section of the dissertation reviews CDPs in South Africa, focusing on their

legislative backing, their intents and objectives.

3.2 Legislative backing of CDPs in South Africa

The South African CDPs are designed and implemented with the backing of legislation

and policy which support the principles of preferential procurement, supporting SMME

businesses and reserving work for contractor development. The legislation includes

the National Small Business Act No. 102 of 1996; the Skills Development Act No. 97

of 1998; the Public Finance Management Act No. 1 of 1999 as amended; the

Preferential Procurement Policy Framework Act No. 5 of 2000; and the CIDB Act No.

38 of 2000. Policy documents include the Black Economic Empowerment Policy; the

Construction Sector Broad Based Black Economic Empowerment Charter, 2003; the

Procurement Risk Management Policy 2003; South Africa’s Economic Strategy for

Broad Based Black Economic Empowerment, March 2003 and Breaking New Ground

on Housing Delivery: A Comprehensive Plan for Creation of Sustainable Human

Settlements, 2004 (CIDB, 2011:15–16).

The legislation, according to the CIDB (2011), came into being as the result of a

constitutional requirement as set out in section 217 (1–3) of the Constitution of the

Republic of South Africa, 1996 (Act No. 108 of 1996), which requires that contracts for

goods and services entered into by every state, provincial and local government organ

be conducted in a system which is fair, just, transparent, competitive and cost-

effective. The Constitution does not prohibit the organs of state or institutions referred

to in the above sub-section from implementing a procurement policy providing for (a)

categories of preference in the allocation of contracts; and (b) the protection or

advancement of persons, or categories of persons, disadvantaged by unfair

discrimination. It also sets aside the framework within which the policies mentioned

30

above may be implemented in compliance with the national legislation (CIDB,

2011:15–16).

3.2.1 Emerging contractor development programmes (ECDPs)

The ECDP was initiated by the Department of Public Works (DPW) as one of its

pioneering programmes based on some of the legislation mentioned above with the

intention of promoting emerging contractors in the building industry (DPW, 2004:2).

Increasing the penetration of firms owned and managed by PDIs into the construction

industry was the primary aim of the ECDP. The focal point of the training was therefore

on contractors transacting business of up to R500, 000 on the CIDB grading as shown

in Table 3.1.

The ECDP was designed to target the business side of construction which, according

to the DPW (2004:2), includes tendering for work, pricing, human resource

management, financial management, marketing and contract administration.

According to the report by the DPW (2004), most programmes at their inception phase

of the ECDP had shortfalls such as an inappropriate organisational structure, a lack of

staff capacity and the lack of effective and efficient management systems. There was

a failure to guarantee effective performance, satisfactory control and incorporation into

sub-systems as a consequence of these weaknesses (DPW, 2004:2).

It was also found that the programmes did not perform as expected in rural areas,

such as the inability of the ECDP to record field information that related to contractors’

vital details, training received and progress of contractors (DPW, 3004:2).

As a consequence of the abovementioned issues, and considering the impact of

sustaining contractors versus the high monetary value of contractor development

under ECDP, the conclusion was that the ECDP was not a viable programme. A

contractor incubator programme was therefore proposed (DPW, 2004).

3.2.2 Contractor incubator programmes

Considering that the bulk of public works projects were in the region of R1.5 million to

R5 million on the CIDB grading (Table 3.1) and that many contractors were stuck at

31

the R2 million to R5 million levels, the incubation programme was therefore directed

at encouraging the growth of construction enterprises owned and controlled by

historically disadvantaged individuals (HDIs) and contractors who come within the

R1.5 million to R5 million cost range (DPW, 2004:3).

According to the DPW (2004:3), the incubator programme was geared at “…creating

an enabling environment within which selected existing contracting enterprises could

grow into sustainable contracting enterprises”. An enabling environment was

supposed to include regular access to contracting opportunities, with values ranging

from R1.5 million to R30 million and provide measures for the support of these growing

enterprises (DPW, 2004:3). This objective was to be achieved through:

regular access to openings to assure sustainability;

supply-side actions underpinned by an enterprise development programme

including mentorship, training, finance and data; and

an enabling atmosphere, specifically uniform and standard procurement,

contract documentation, and swift payment (NPWD, 2008).

Aspiring participants of the CIP were expected to abide by the following entry

requirements:

having a CIDB grading designation of between 3 to 7;

having a certain training in construction;

having skilled staff employed in the company; and

being owned by blacks, women, youth and people living with disabilities

(NPWD, 2008:6).

The envisaged outcome of the CIP as stated by the NPWD (2008:7) was to enable

contracting entities belonging to PDIs having knowledge and the ability to embrace

financial expertise, human and material resources to complete a construction project.

It was also envisaged that on completion of the CIP contractors would improve their

managerial and commercial abilities in the industry.

32

According to the NDPW Contractor Incubator Programme overview report (2008:22),

the CIP achieved some successes, such as the selection of the right project team,

selection of suitable contractors and contracts, and communication and acceptance

by various stakeholders. The report states that the programme was monitored and

evaluated, that people employed in the programme understood their responsibilities

and there was an integrated approach, unlike the ECDP.

However, despite the successes, it has been noted that there are some shortfalls

relative to the CIP. These shortfalls include the following:

Mismatch between suitability of contractors and accessibility to contracts;

Contractors dropping out beforehand completing the programme; and

Unsuitable sustainability indicators (NPWD, 2008:21).

Most of the CDPs implemented by the national, provincial and local stakeholders were

designed and carried out along the principles of ECDP.

33

Table 3.1: Requirement in relation to contractor grading designation

Financial capability Track record for the past 2 years Minimum current

financial capability

Code Maximum value of

contracts that a

contractor is considered

capable of performing

(upper limit of bid value

range)

Minimum average

annual turnover

At least one

contract with a

value greater

than

Employable capital

(EC) of at least (next

asset value x bank

rating factor) +

financial

sponsorship

1 (#) R200,000.00 R0.00 R0.00 R0.00

2 (#) R500,000.00 R0.00 R80,000.00 R0.00

3 (*) R1,500,000.00 R780,000.00 R260,000.00 R0.00

4 (*) R3,000,000.00 R2,400,000.00 R800,000.00 R600,000.00

5 (*) R5,000,000.00 R4,800,000.00 R1,600,000.00 R1,200,000.00

6 (*) R10,000,000.00 R9,000,000.00 R3,000,000.00 R2,250,000.00

7 (*) R30,000,000.00 R24,000,000.00 R8,000,000.00 R6,000,000.00

8 R100,000,000.00 R78,000,000.00 R26,000,000.00 R19,500,000.00

9 "No Limit" R240,000,000.00 R80,000,000.00 R60,000,000.00

(#) These contracting enterprises are the targets for training under ECDP.

(*) These contracting enterprises are the targets for training under CIP.

Source: Adapted from DPW Contractor Incubation Programme Management Plan,

2004

34

3.2.3 Eskom Construction Academy

Eskom started the training academy in order to address the shortage of qualified

contractors skilled in electrical infrastructure, line construction and the management

of wayleaves and servitudes in both rural and urban areas. The aim was to train

contractors by developing their skills, help create jobs and alleviate poverty in

communities, and, in so doing, empower the contractors to deliver projects to meet

international standards and Eskom’s requirement for the optimisation of their

infrastructural network (CIDB, 2009).

The cardinal aims of the Eskom Contractor Academy were to:

develop the required business and construction management competencies

within proprietors; and

uplift and build ability in the technical skills of personnel (CIDB, 2009:28).

In addition, the Eskom Contractor Academy was to enable a vertical movement of its

employees and a horizontal movement into other contracting environments by training

sufficient and competent, skilled employees and also equipping contractors to deliver

projects to Eskom’s satisfaction (CIDB, 2009:28).

According to CIDB (2009), the entrants to the Eskom Contractor Academy were

selected from a group of contractors already contracted to Eskom or registered on

Eskom’s vendor list as future contractors. These contractors were vetted according to

their performance in past or current projects and their aptitude to pass other entrance

benchmarks set by Eskom.

Eskom, in partnership with Edupark, set up and ran an eight-month training course

registered under the Energy Sector Education and Training Authority (Eskom, 2011).

The training was modelled to have two phases, namely the classroom phase, where

contractors would have to attend one week per month of classroom study and and the

other phase would involve 26 weeks of fieldwork.

The study module for the classroom study comprises business management, financial

management, supply chain management, project management, people management,

35

safety, health, environment and quality (SHEQ) and the new engineering contract

(NEC). The NEC was selected by ESKOM for training because it is the form of

agreement commonly used by the electrical utility company.

The fieldwork training includes a course in medium-voltage line construction, SHEQ,

pole mount transformers, low voltage (LV) line construction, schools and clinics, pre-

paid metering, LV live work, supervision of work and LV operation (CIDB, 2009; Eskom

2011).

The training is delivered by accredited training providers and it is ranked on the

National Qualification Framework (NQF) as level 4 training. Trainees are required to

achieve 50 per cent or more in both the theory and the practical training before they

are allowed to graduate. The University of Limpopo awards certificates to successful

graduates (CIDB, 2009; Eskom 2011). The goal of the training, according to the CIDB

(2009), is to develop contractors’ competences so that they are able to effectively

manage and sustain their businesses, competently participate in the open market, and

to be competent to upgrade their CIDB grading.

Eskom (2011) claims that the programme has achieved a 97 per cent success rate

since its commencement in 2008 because 167 trainees out of the 173 who have

participated in the programme have successfully graduated. It was further stated that

52 out of the 167 graduates who were business owners were black women.

3.2.4 Vuk’uphile Learnership Programme

The NDPW initiated the Vuk’uphile Contractor Learnership Programme as part of the

Expanded Public Works Programme (EPWP) which was aimed at building capacity

among emerging contractors. By so doing, the EPWP achieved three goals, namely

a) executing work using the emerging contractors, b) increasing the amount of labour-

intensive work and c) providing employment and skills development opportunities for

the unemployed in the country.(CIDB; 2011b:63; EPWP, 2008).

Therefore, the intention of the Vuk’uphile Contractor Learnership Programme was to

build sustainable, empowered and independent contractors expert in labour-intensive

ways that would contribute towards unemployment reduction.

36

The Vuk’uphile Contractor Learnership Programme was therefore geared towards

developing the following entrepreneurial, business and technical skills:

Training contractors at NQF level 4 (254 credits) and site supervisors at NQF

level 4 (218 credits);

Capacity to contract in labour-intensive works sector to support EPWP;

Project sourcing and marketing;

The trainees also benefit from the programme by obtaining the following:

Accepted qualifications;

A project track record;

A financial track record;

A recognised relationship with a financial body; and

An improvement in their CIDB Grading (CIDB, 2011b:63).

The CIDB (2011:64) noted that applicants to the Vuk’uphile Contractor Learnership

Programme are required to possess some prerequisite qualifications such as having

completed at least a Grade 10, having some experience in construction and being

capable of executing contracts of up to R2.5 million. Selection to the Vuk’uphile

Contractor Learnership Programme is targeted at contractors with a CIDB grading

designation of 1 to 4. In addition, the programme targets attracting 80 per cent of HDIs,

50 per cent women and 50 per cent youth in the programme (CIDB, 2011b:64; EPWP,

2008).

The minimum duration required to complete the training is 30 months (CIDB 2011b:64-

65). During this period the contracting entities are assisted in the following ways:

Training: Contractors go through NQF-related teaching at levels 2 to 4 on

applying labour-intensive construction methods of work. The participants are

the learner contractor and learner supervisors such as site managers and site

foremen from the contracting entity to enhance their practical experience.

Mentoring: The mentors are liable for counselling and guiding the students in

the improvement and the management of their businesses and construction

37

competency. Their responsibilities include the opening assessments in the

training curriculum and deciding the areas where the learner contractors require

improvement. The ratio of mentors to contractors on the programme is pegged

at 1 to 10. In certain instances mentors are also co-signatories to the learners’

bank accounts so that accountability of funds is ensured.

Projects: On graduating from the training programme, the implementing body,

as part of its responsibilities under EPWP, provides the graduate contractors

with suitably sized projects so that practical experience can be attained onsite

training. The projects should be appropriate for labour-intensive construction

and favoured points are notched for training in labour-intensive construction.

Financial assistance: Banks and other financial institutions provide

admittance to credit and financial assistance to the graduate contractors. The

trainees benefit from the programme in that collateral is not required for any

financial assistance during the training period; however, the contracting entities

would have to include their mentors as signatories to their bank financial

records (EPWP, 2008).

The number of graduates from the Vuk’uphile Contractor Learnership Programme

could not be established during the current study and therefore it is difficult to establish

how many have benefited from the programme nationally. The Vukuzakhe Contractor

Development Programme was initiated by the KwaZulu-Natal Department of Transport

(KZNDoT), with the objective of transforming and empowering construction companies

involved in the construction of road infrastructure. The historically disadvantaged

individuals (HDIs) also benefitted from the Vukuzakhe CDP when it was first piloted in

1994 as part of the Roads for Rural Development Programme. The programme policy

was revised in 2002 to ensure sustainability of firms and also to capacitate firms

belonging to women, youth and people living with disabilities so that they could be able

to compete with other companies in the infrastructure boom market that was expected

in advance of the 2010 FIFA Soccer World Cup (CIDB, 2011b).

Therefore the Vukuzakhe policy, according to the CIDB (2011b:16), was to create an

effective programme which would transform the road construction and the building

construction sectors in general by creating an enabling environment such as the

38

availability of procurement opportunities and guaranteeing that Vukuzakhe contractors

had technical, management and financial support to execute projects successfully.

Aspiring applicants to the Vukuzakhe programme are interviewed by the department

officials to ascertain contractors’ skill levels in order to ensure that the construction

entity is genuine and that the entity meets the objectives of the programme (Civil

Designer, 2012).

Under the programme, contractors with a CIDB classification of 1 are permitted to take

part in all contracts of worth not exceeding R200, 000.00. However, entities requiring

entrance to the Vukuzakhe Development Programme and possessing a CIDB

contractors’ grading designation of 2 and above are required to comply with the

following:

1. The capability of the contractor in a particular CIDB rating designation;

2. CIDB Registration (mandatory);

3. Registration in the Vukuzakhe Database;

4. Valid Tax Clearance Certificate;

5. Provincial Treasury Supplier Database registration;

6. 100 per cent HDI-owned companies;

7. Registration for Value Added Tax with the South African Revenue Service;

and

8. Management actively involved in the operations of the contractor.

Vukuzakhe contractors are only permitted to go enter the programme at Grades 1 to

3 and registrations are not accepted from contractors who are in Grade 4 or above as

they are deemed to be necessarily established in terms of the programme aims and

objectives (CIDB, 2011b:17).

The CIDB (2011b:19–23) explains that most of the work of Vukuzakhe programme is

coordinated at the Enterprise Development directorate at the head office of KZNDoT

and aided by the Departmental Project Managers from the several regional offices.

The KZNDoT encourages participating contractors to form associations and

participate in these associations through which they can communicate and share ideas

39

regularly among themselves and the Department. The KZNDoT also affiliated their bid

procurement documentation with the CIDB’s standard for uniformity in construction

procurement documentation. Furthermore, consultants are appointed with the view of

supporting contractors’ development.

Vukuzakhe training was envisioned to be delivered in both classroom work and

fieldwork by accredited training providers with financial support coming from KZNDoT

departmental support and other institutions such as the Construction Education and

Training Authority (CETA), the Provincial Treasury SMME Fund, the Department of

Labour, the South Africa National Roads Agency Limited, the South Africa Federation

of Building and Civil Engineering Contractors (SAFCEC), municipalities and the EPWP

Unit of the Department (CIDB, 2011:20). The training programme includes mentorship,

contract management, financial, business management and organisational

development (CIDB, 2011b:20).

Projects are awarded to participating contractors for their training and development.

Contractors in the CIDB grade 2 to 6 are allowed to undertake more than one

development programme at a time, based on their performance on current projects

and their risk profile. On the other hand, contractors in the CIDB grade 1 are only

allowed to undertake one development project at a time (CIDB, 2011b:20).

Contractors with CIDB grading 1 to 3 are limited to tendering for projects within their

designated grading while contractors with the CIDB grades 4 to 6 are not limited to

tendering above their designated grade, but once below their grade, they are not

allowed to tender for jobs. However, joint ventures are encouraged so that there is

skills transfer and therefore the development and transformation goals are achieved.

The joint venture split between the contracting entities was set at 60 per cent for the

entity with the higher grade and 40 per cent for the entity with the lower grade (CIDB,

2011b:21).

One of the incentives built into the development programme is the payment frequency.

Cash flow is a critical element, especially with the emerging contractors. Therefore the

KZNDoT adopted a twice-monthly payment system to contractors for their work done

with the first payment being on the 15th and the second being on the last working day

40

of every month, provided that contractors’ invoices bear no discrepancies (CIDB,

2011b:21).

Thorough financial and technical vetting of contractors is done to ascertain their ability

to complete projects to the required quality, within a set budget and on the allotted

time. This strategy was adopted because the Department carries the risk for the

waived sureties for the work. However, the Department does not set aside the

guarantees for additional work and also reserves the right to withdraw contract

management support systems already offered on any other concurrent projects

awarded in the instance where a participating contractor decides to undertake more

than two projects at a time (CIDB, 2011b:22). The CIDB (2011b) asserts that this is to

encourage contractors to concentrate on the work at hand in order to enhance their

training and mentorship which is the main goal of the Vukuzakhe programme.

According to the CIDB (2011b:19), it is essential that all Vukuzakhe contractors are

registered on the CIDB list of contractors in the relevant grading designation and the

suitable class of works. The progress criteria of the programme are based on the CIDB

upgrading requirements. Contractors are allowed to upgrade from one grade of

Vukuzakhe programme to the next grade if that contractor has successfully applied for

and has been granted an upgrade with the CIDB.

According to the CIDB (2011b:19), contractors may depart from the programme under

the following circumstances:

Being unable to secure tender opportunities in two years;

A written request from the contractor concerned to be removed from the

programme; or

The ability of the contractor to meet the competency criteria for a grade

7 and is deemed to be self-sustaining.

The contractor progress, according to the CIDB (2011b:24), is measured in terms of

the contractor being able to:

source work from client bodies in general;

41

complete projects within time, to the specified quality standards and

within the cost parameters;

comply with training and skills development goals;

comply with the health and safety specifications;

comply with the environmental specifications; and

comply with best practice standards, such as payment of subcontractors

and contract documentation between main contractor and

subcontractors.

3.2.5 Masakhe Emerging Contractor Development Programme

The Masakhe ECD was initiated and operated under the jurisdiction of the KwaZulu-

Natal Department of Public Works (KZN DPW) in accordance with the Construction

Sector Transformation Charter and with the aim of capacitating emerging HDI

contractors so that they are able to excel in the open market (CIDB, 2009). The

contracting entities targeted for training under the Masakhe ECDP were those with

CIDB grading designations of 1 to 5.

According to the Masakhe handbook (n. d.), the objective of the programme is to:

a) create an enabling environment through which the emerging

contractors can flourish and have access to:

markets (DPW KZN contracts);

financial support;

training and mentoring; and

skills transfer.

b) Create an emerging contractor development system which would

provide for:

basic business management and technical training;

implementing targeted procurement interventions;

ongoing technical support through a mentorship plan;

linkages with financial institutions or funding agencies for

appropriate financing products; and

42

ongoing monitoring and evaluation of participating contractors.

c) Establish a credible database of emerging contractors, which will

encompass:

a screening mechanism for profiling HDI status and technical

competence;

a profile verification mechanism;

a performance monitoring and evaluation mechanism; and

adequate elevation of participating contractors through the CIDB-

linked grading system (Masakhe Handbook, n. d.).

In order to qualify for the Masakhe ECDP, aspiring trainees should meet the following

requirements:

The owner must be actively involved in his or her business and its

management;

The contractor must be CIDB registered;

The contractor must be registered with the KZN provincial suppliers’

database;

A CIDB Grade 1 contractor must undergo compulsory basic training with

the Department;

HDI equity ownership should be more than 50 per cent.

The contractor must supply any other documentary proof that may be

requested (Masakhe Handbook, n. d.)

The programme is administered by the Project Management Unit (PMU) of the DPW.

According to theCIDB (2009:18), the PMU is made up of a contractor development

directorate situated at the KZN DPW head office. The directorate has been divided

into regional blocks where the actual contractor training is undertaken. These regional

offices are manned by programme managers, project leaders, mentors, consultants

and other stakeholders such as theCIDB and CETA (CIDB, 2009:18).

The KZN DPW sets aside projects valued between R1 million to R5 million for the

implementation of the Masakhe ECDP. Prospective trainees tender for these projects

43

and the contracts are procured by the following historically disadvantaged individuals

(HDIs):

Women: 40%

Youth: 20%

Priority population group: 35%

Physically disabled: 5%

(CIDB, 2009: 18).

Contractors are trained under the following two main curricula:

Training and development, which entails training in business

management, business administration, tendering, project costing,

construction management, and onsite technical support; and

Financial support, which includes an introduction of ECDP contractor

funding products through traditional and government funding agencies,

establishing relationships between contractors and such funding

agencies, and introduction to a performance guarantee waivers principle

in lieu of contract retentions.

Contractors who have successfully completed their projects on time, within budget, to

high quality and who exhibit the acquisition of business and technical skills are

considered competent to progress to the next stage of the programme. Contractors

who have acquired CIDB grading designations 4 and 5 are encouraged to involve

contractors with lower CIDB grades during the construction phase of project

implementation (CIDB, 2009: 18). However, records to demonstrate the success of

the Masakhe programme are not available and this makes it difficult to conclude on its

performance.

3.2.6 Small Enterprise Development Agency – Construction Incubator (SCI) Programme

The Small Enterprise Development Agency (SEDA) construction incubator (SCI)

programme was well-known in 2005 and is a programme whereby government funds

44

contractor development. The main aim was to improve emergent contractors through

a mixture of practical and business administration expertise incorporating the usage

of technology in order to add to the management effectiveness of their businesses. It

is under the banner of a ring-fenced incubator programme called the Small Enterprise

Development Agency (SEDA) Technology Programme (CIDB, 2011b:27).

The CIDB (2011b:27) noted that the SCI was envisaged to be the forerunner in the

contractor development initiatives to produce competitive construction SMMEs

through the setting up of innovative sustenance involvements. In order to realise this,

the programme’s objective was to increase the capacity of construction SMMEs

through an organised mixture of business, technical and technology involvements

leading to sustainable businesses, substantial job creation and also helping to

contribute positively to the South African economy (CIDB, 2009; 2011b).

In addition to wanting to create a high level of professionalism and formality in the

industry, the SCI includes providing:

contractors with the required support to become successful and run

sustainable businesses which are able to compete in the open market;

business technology incubation services to SMME contractors; and

acceptable technical training, coaching and mentoring to assist

contributing contractors to effectively complete their projects –

contractors are evaluated in the skills to complete the jobs that they have

won through their own undertakings (CIDB, 2011b:28).

The SCI programme is designed for contractors registered in grades 3 to 6 of the CIDB

grading category and who have legally registered their businesses with the registrar

of companies, have a business plan and meet the entry requirements. However, some

of the training centres do cater for the start-up contractors with a grading of 1 to 2

(CIDB, 2011b:28).

In addition, contractors are eligible for the training programme if they are registered

and are active on the CIDB register of contractors (CIDB, 2011b:29). Other listed entry

requirements to the SCI programme include having:

45

a copy of income tax registration;

a certificate of tax clearance ;

acopy of establishment registration document;

A copy of identity documents of all stock holders;

A business plan that clearly demonstrates a company’s future plans;

curricula vitae of all the owners and senior management;

most recent signed annual financial statements;

up-to-date management accounts; and

a letter of motivation provided by the applicant on why he or she wishes

to join the SEDA construction incubator and its benefit to the company.

One of the main interventions the SCI provides is mentorship to willing contractors. A

skills audit is conducted by the SCI in order to determine the skills’ gap and then a

plan is developed to develop those skills. Contractors are also encouraged and

assisted to approach financial institutions for financial assistance (CIDB, 2011b:30).

This mentorship programme is undertaken at a cost agreed between the client bodies

and the mentor.

The SCI also offers assistance to selected SMME contractors for a period of three

years, within which period the participating contractors are expected to improve by a

minimum of one financial level above their entry level on the CIDB register of

contractors and function with little or no support in the open market. The programme

was planned around particular practices that can be found in any construction

enterprise. CIDB (2011b:27) outlines some of them as being the following:

Tender stage: assist contractors to charge tenders correctly with profit

margins factoring in all expenditures;

Pre-construction: help the contractor in organising for the occupation of

the site;

Construction management: make sure the right and expert management

and administration of projects; and

46

Site supervision: facilitate the communication with the site foreman,

consultants and all role players in the construction route, while permitting

the contractor’s management team a certain amount of autonomy.

Contractors are supported under the SCI in both administrative and technical issues.

The administrative assistance includes the provision of infrastructure and compliance

with all statutory regulations. Technical assistance includes (i) tender phase support

which entails assistance in pricing and completing of the tender, estimating, advice on

whether to tender or not; and (ii) construction phase support which includes assistance

with scheduling, cash flow projection, contractual claims, valuations, compliance with

occupational health and safety regulations, compliance with environmental

requirements, and all other contractual issues.

The SCI has a 240 evaluation point system which is used to appraise contractors’

performance. This evaluation scheme is linked to the training modules in order to make

certain that contractors have assimilated what they have been taught and are

implementing such knowledge on site (CIDB, 2011b:29).

Records show that there has been some measure of success with the programme.

According to the CIDB (2011b:27), a total of 63 contracting entities were supported by

the programme within two years of its inception in 2007.

3.2.7 Khuthaza Contractor Development

Khuthaza was set up to offer professional development programmes targeted at

women who were setting up or running construction companies (Khuthaza, 2012). The

programmes included training offered partly by CETA-accredited training providers.

Khuthaza’s goal was to offer a number of training programmes which are creative,

interesting, dynamic, challenging and rewarding (Khuthaza, 2012).

Khuthaza’s CDP offers technical skills training in the following components:

a) Excavation (exploration)

47

The excavation programme was directed at individuals who were exploring the

construction industry and considering the idea of setting up a construction business.

Through the Excavation programme Khuthaza assisted people to decide whether

construction was truly the industry for them and to help them consider the demands

of running their own company. This programme, according to Khuthaza (2012:10),

assisted new entrants to do market research before commencing a business. In this

programme activities are available available to anyone throughout the year. These are

usually day-long technical and classroom-based workshops.

b) Cornerstone (entry level)

At this level, Khuthaza created a medium through which programme partakers were

taken through a foundation of knowledge and skills was built. This course, according

to Khuthaza (2012:10), was intended for those individuals who were in the initial

stages of the setting up of their construction businesses. The programme is a

certificate programme lasting for the period of eight months. The certificate programme

combines aspects of the development of professional, personal, business and

technical skills.

c) Connection (intermediate level)

The connection programme is a medium in which programme partakers are able to

develop their current knowledge and skills. The programme also makes admittance to

industry players available for participants as well as openings with the established

sector. Through this programme Khuthaza aims to provide applicants with skills,

experience, networks and knowledge that will assist them to better the efficient

operations of their businesses and participate more efficiently with the industry. The

duration of the connection programme is eight months (Khuthaza, 2012:10).

d) Re a abelana (raa) (more experienced)

Re a abelana is a forum through which programme participants have greater access

to leaders in the industry and opportunities with the established sector. The

programme was aimed at providing participants with skills, exposure, networks and

48

knowledge that would enable them to grow their businesses and plan for the long term.

This is an eight-month certificate programme (Khuthaza, 2012:10).

e) Re a abelana+ (raa+) (those who have completed re a abelana)

In this Khuthaza programme, the aim was to maintain contact with those individuals

who had completed the RAA programme and provide them with continuous

development programmes and mentoring opportunities.

Entrance to these programmes is open to anyone interested and they are open

throughout the year with fees discounted at 10 per cent at each level of the

programme. However, some of the participants have struggled to make the stipulated

payments and therefore monthly payments have been negotiated with the participants

in Connection and Re a abelana levels.

In terms of performance of the Khuthaza programme, it is reported that there were 65

applicants who registered for the 2012 Cornerstone, Connection and RAA

programmes. Out the 65 who registered, 56 of the participants attended the training

frequently over the year and 45 qualified for certificates. Equally, 45 participants

registered for the Cornerstone programme and out of these, 32 candidates qualified

for certificates some individuals were not able to complete their training. Khuthaza

(2012:11) identified some of the reasons why participants did not complete the

programmes or did not receive certificates as including the following:

Challenges finacially;

Being busy on site/sites sometimes located outside Guateng;

Work commitments related to full-time employment (not their own business);

Busy getting alternative income from non-construction businesses;

Family responsibilities (often family illness and deaths);

Distance and transport challenges;

Commitments related to other degree-related study or other development

programmes; and

Other challenging interests and commitments.

49

The Summary of CDP in South Literature on CDPs in South Africa has revealed that

for CDPs to achieve their aims and objectives, they should possess some qualities

as determined by the CIDB (2011b:14). These qualities include, inter alia, the

following:

Goals, vision and objectives out of the CDP and should identify the target

group clearly;

Sufficient budgets should be available for the operation of the programme.

Recruitment and allocation: A qualified and sufficient management team

should be recruited and allocated;

Clearly communicated entry, progression and exit levels and criteria should

be defined;

The training needs assessment of the contractors should be introduced and

the improvement of training and skills programmes for individual contractors

must be considered;

The training should enhance contractors’ chances of acquiring assistance

pertaining to finance, networking initiatives and credit access;

A successful training appraisal and monitoring method must regularly

assess how effective the programme is to contractors and other

stakeholders; and

The training should provide opportunities for the contractors to

communicate their views and difficulties freely without any hindrances.

However, the literature reviewed on CDPs in South Africa has not revealed much on

the ongoing mentoring support for beneficiary contractors after they have undergone

the various CDPs. With mentorship being one of the core best practices for contractor

development, only a few of the CDPs reviewed had a mentorship process, although

this was for eager contractors and client bodies. According to the CIDB (2011a:76),

some clients regard mentorship as an unnecessary expense. It was found that in most

cases there was not sufficient work to sustain the contractors’ training for longer

periods owing to budget slashes from possible clientele, projects, and large trainee

enrolment in the programmes (CIDB, 2011a:76).

50

The issue of mentorship was not adequately described in most of the CDPs reviewed;

however, it was certain that most implementing agencies seemed to understand the

benefits of mentoring even though they had struggled to implement mentorship with

any realistic amount of success (CIDB, 2011a:76). The CIDB (2011a:76) lamented

that although the notion and design of the models may be proper, the resourcing,

oversight by clients and managing of mentors have been difficult. The CIDB further

notes that, in most cases, the ratio of the mentor to pupil contractors was very high.

This high ratio placed undue pressure on the mentors and also compromised the

quality of the mentorship programme.

3.3 CONCLUSION

This chapter presented an overview of of literature on CDPs in South Africa. An

assessment of the framework of contractor development programmes regarding their

purposes, objectives and their patterns of implementions was also discussed.

51

CHAPTER FOUR

REVIEW OF INTERNATIONAL CONTRACTOR DEVELOPMENT PROGRAMMES

4.1 Introduction

Globally, there have been CDPs designed and implemented mainly to encourage best

practices for contractors from various geographic locations. Tanzania, Palestine and

Lesotho were studied to ascertain the aims, objectives, achievements and lessons

learnt from their contractor development programmes. These countries were chosen

owing to their similarities with South Africa, such as being regarded as third world

countries.

4.2 Development programme – Tanzania CRB initiative

As stated by Uriyo and Jere (2003: 2–15), the Tanzanian Construction Registration

Board (CRB) ushered in a Structured Training Programme (STP) in 2001 with the

purpose of helping indigenous contractors, bridging the gap skill and knowledge wise

and increasing the capability of local contractors involved in infrastructure

development, restoration and upkeep. The agenda was begun after 38 per cent of

prospective clients and 42 per cent of surveyed contractors demanded for training

platforms to be introduced (Uriyo & Jere, 2003:2).

4.2.1.1 Objectives of the STP

The training’s objectives were to seek solutions to the contractors’ apparent paucity of

technical and management capabilities, lack of ability to break through into higher

forms, inability to acquire up-to-date tools, and their limited access to credit facilities.

4.2.1.2 Structure of the STP

The training programme comprised a five-day course covering before-contract

practice, contract management, construction planning, maintenance of plant and

equipment, and health and safety and contractors were obliged to finish six courses

per year. The charge for training was greatly subsidised, with the CRB covering about

70 per cent and the partaking contractor paying only about 30 per cent.

52

4.2.1.3 Achievements of the STP

In measuring the productivities of the STP, Uriyo and Jere (2003:4) obseved that,

within seven years of its commencement, 2,071 contractors had been trained

compared to the budgeted 1,620 contractors. The authors argue that those numbers

demonstrated the popularity of the programme.

Additionally, the annual client opinion report showed a drop in criticisms of contractors’

absence of knowledge and skills during the course of the STP and there was also a

decrease in the complaints related to the use of unqualified individuals on construction

projects.

Equally, contractors also professed the training to be a success although, they

observed some gaps in the programme which they felt required to be taken care of

(Uriyo & Jere, 2003:4).

4.2.1.4 Gaps in the STP

In a study conducted by Uriyo and Jere (2003:5-15) contractors noted the following

gaps:

Training to be made mandatory for all contractors;

Contractors to undertake continuing professional development (CPD) –

(continuous mentoring);

Importance to be placed on lecturing artisans and technicians on skills’

gaps;

Training to be applicable and reactive to industry requirements;

Training in rate-build-up to be included;

Mentorship and internship to be promoted to improve capability;

Continuous monitoring of programmes to assure potency;

Different training programmes for different levels of firms; and

An adequate group of reserve persons to sustain knowledge transferral.

(Uriyo & Jere, 2003:5-15).

53

4.2.2 Development programme – Tanzania NCC initiative

The National Construction Council (NCC) of Tanzania embarked on various training

and development programmes when it realised that there were not enough local

contractors to guarantee the road maintenance and rehabilitation projects created by

the government’s Sixth Highway Rehabilitation Programme and the integrated road

projects.

The training programmes were tailor-made and were conducted on a basis of the

clients’ needs (Joseph & Haule, 2003).The training, according to Joseph and Haule

(2003), took place in the following six centres:

Kilimanjaro Centre: Contractors were trained at this centre in labour-based road

rehabilitation and maintenance programmes. The training was done in three phases

and comprised classroom work, fieldwork and trial contracts.

Morogoro Centre: The training programme at this centre included a gravel and

bituminous road and bridges maintenance programme. This programme was financed

by the Swiss Agency for Development Corporation and was carried out in three stages,

namely classroom study, fieldwork and trial contracts.

Mwanza Centre: This centre trained contractors in labour-based road rehabilitation

and maintenance. The implementing methodology was classroom work, fieldwork and

trial contracts.

Nachingwea Centre: Training of small contractors in Lindi and Mtwara Regions in

labour-based technology was conducted at the Nachingwea Centre. The aim of this

programme was to train small contractors to undertake spot improvement and

maintenance of roads (Joseph & Haule, 2003: 5). The Finnish government through its

FINIDA development agency provided both technical and fiscal support for this plan.

Dodoma and Dar es Salaam Centres: The Swiss Agency for Development and

Cooperation financed contractors who were members of the Tanzania Civil

Engineering Contractors Association to undergo training on road maintenance and

rehabilitation. The training comprised classroom work and trial contracts. A total of 139

54

contractors were trained in the Dodoma and Dar es Salaam regions (Joseph & Haule,

2003:5).

4.2.2.1 Achievements of the CDP

Joseph and Haule (2003) cite some success achieved by the programme as being the

completion of over 756 kilometres of road network and the rehabilitation of 420 culverts

across the country.

4.2.2.2 Gaps in the development programme

Gaps in the programmes have been identified and include: (i) inadequate workload for

contractors after the training; (ii) insufficient financial support to contractors after

graduation; (iii) lack of financial assistance to the programmes; (iv) not being able to

source plant and equipment for work after training; and (v) conflict between trained

contractors and employers as some contractors knew more than their employers

(Joseph & Haule, 2003: 8-9).

4.2.3 Development programme – Palestine

In Palestine contractor development programmes were also implemented. The aim of

the programmes were to help smaller construction companies to advance their

managerial abilities in capacities such as pricing, financial management, tenders

submision, contract administration and construction work marketing (Enshassi &

Shaath, 2007:43).

4.2.3.1 Structure of the CDP

The contractor development programme in Palestine was based on the Improve Your

Business (IYB) book. The Improve Your Construction Business (IYCB) agenda

comprised three handbooks and workshop series that tackled subjects such as (i)

pricing and bidding; (ii) site management; and (iii) business management (Enshassi &

Shaath, 2007).

The putting into practice was in two stages, with stage one being the training of the

trainers and phase two, the training of selected construction businesses’ managers

and proprietors, with each training course lasting for around three months.

55

4.2.3.2 Achievements of the CDP

Enshassi and Shaath (2007:52) perceived that most of the contractors had benefited

significantly from the IYCB handbooks and workshops and were pleased with the

models as the learners were able to apply some of the innovative methods learnt.

4.2.3.3 Gaps of the CDP

The contractors observed some of the following as the problems in the programme

which required the attention of the executing agencies:

The period of the training agenda was too lengthy and they proposed that it

should be shortened;

The Arabic translation was not properly done;

Books were more theoretical than practical;

The training did not differentiate between the different levels of contractors;

and

The books did not quite fit the circumstances of the Gaza Strip and the West

Bank.

4.2.4 Development programme – Lesotho

4.2.4.1 Objectives of the CDP

According to Seth (2004), the Department of Rural Roads (DRR) in Lesotho launched

the contractor training programme (CTP).

The objectives included, among others, promoting labour-based work methods,

creating a sustainable road maintenance system for the DRR, and enhancing the

institutional ability of the DRR to manage the CTP effectively. The CTP was supported

both nationally by the Lesotho government and internationally by the International

Development Agency by providing financial support, while the ILO provided expert

help.

The technical assistance provided included (i) selection of new entrepreneurs to the

programme, (ii) preparation of bidding documents, (iii) planning and implementation of

56

trial contracts, (iv) observing of contractor performance (v) training of DRR staff to

implement the CTPs; and (vi) advice on preparation of training materials, technical

handbooks and a trainer’s manual (Seth, 2004:2).

4.2.4.2 Structure of the CDP

The training was in two phases, with phase one being a nine-month road maintenance

and rehabilitation (ROMAR) programme and phase two a 12-month road construction

and upgrade (ROCAU) programme.

Applicants were screened and selected for the programme based on their educational

background and previous experience in labour-based work methods. Secondly, a

written proficiency test was administered to evaluate the applicants’ knowledge of

English language and mathematics. Successful candidates were invited into the

training programme (Seth, 2004: 2).

Contractors underwent the ROMAR training first and upon successful completion, they

were capacitated to undertake a “no-bid” routine maintenance contract which was

assessed at less than US$10,000 (Seth, 2004:2). Depending on their size and the

calibre of their workmanship, trained contractors were allowed to undertake more than

one project of routine maintenance work and were later promoted to undertake

rehabilitation work valued at under US$100,000. Only candidates who had been

successful in the rehabilitation work were allowed to proceed to the ROCAU training.

The ROCAU training included (i) classroom work; (ii) site demonstration; (iii) trial

contract in routine maintenance; and (iv) trial contract with periodic maintenance (Seth,

2004). The classroom work covered technical and business administration topics such

as road materials, technical specifications, bid planning, estimating, contract

administration, site management and bookkeeping.

The work for trial contracts was granted to contractors without any competitive bidding

and the contractors were allowed to add a 10 per cent profit to the negotiated rates

based on engineers’ estimates.

57

4.2.4.3 Achievements of the CDP

Seth (2004:3) observed that some of the key outcomes of the programme, and hence

successes, included: (i) the training of 43 new contractors in ROMAR and 12 in

ROCAU; (ii) the creation of temporary employment opportunity in rural areas to

alleviate poverty; (iii) the improvement of the DRR’s institutional efficiency by reducing

staff by 260; (iv) a reduction in foreign exchange due to reliance on local construction

equipment; (v) the improvement of construction standards of local contractors; (vi) the

improvement of the technical and managerial capabilities of local contractors; and (vii)

a total of 2,100 kilometres of routine maintenance, 56 kilometres of periodic

maintenance, 45 kilometres of rehabilitation and 20 kilometres of upgrading work

worth an estimated cost of US$7.5 million executed under the programme.

4.2.4.4 Gaps in the CDP

Some of the constraints in implementing the programme were said to include: (i) the

contractors’ inability to handle site management; (ii) the unwillingness of private banks

to give credit facilities to contractors without collateral; (iii) the inability of contractors

to secure sureties or guarantees from financial institutions; (iv) new contractors finding

bidding documents to be too complex; and (v) multipart bureaucratic payment

procedures delaying contractors’ payments for months.

Synthesis of findings from CDPs

A synthesis of the CDPs reviewed in this section has been undertaken as can be seen

in Table 4.1. It appears from the four development programmes that they all have

similar gaps. The gaps in the CDPs include the need for continuous development and

training being designed based on the contractors’ area of business as it becomes

difficult for contractors to travel away from their homes in order to attend training. The

CDPs must be aimed at addressing specific contractor needs in order to avoid ‘one

size fits all’ programmes. Beneficiaries wanted the CDPs to be designed with the aim

of bridging the skills’ shortage gap between contractors by targeting the training at the

contractors’ level of competencies. The trainees also believed that the CDPs should

be more practically oriented, have shorter durations, subsidise the cost of training to

58

affordable levels or preferably should be free and should have easy-to-understand

bidding documents. The lack of prompt payment and assistance from clients and

financial institutions during and after the training were also identified as some

impediments and hence would impact on the CDP sustainability.

Table 4.1: CDP gaps in some developing countries

Item Contractors’ perceived Gaps. CDP had no

Tanzania -CRB

Palestine Lesotho Tanzania -NCC

i.

Continuous professional development (CPD) – Mentoring of contractors after graduation

X X X X

ii. Plan to bridge skill shortage gap between start-ups and established firms

X X X X

iii. Training adopted to specific area

X X X X

iv. Different training requirements adopted to different levels of contractors

X X X X

v. Allowance for those unable to afford the training cost

X

X X

vi. Relevant and responsive training to industrial needs

X X X X

vii. Consideration of the duration of training programme. Perceived to be too long

X X X X

viii. Emphasis on practical training

X X X X

ix. Assistance in acquiring financial and technical advice

X X X X

x. Simplified bidding documents

X X X X

xi. Prompt payment system to trained contractors

X

X X

4.3 CONCLUSION

The chapter on some selected contractor development programmes has discussed

their performance in South Africa and other developing countries. The conception of

these CDPs, their planning and design, their implementation models, some best

practices and some gaps were identified and discussed.

59

The results indicate that a holistic approach to the implementation of CDPs is required

in order for the programme to succeed. However, what is also apparent is that

mentoring and continuous training in the CDPs are increasingly being recognised as

being at the focal point of the CDP performance and sustainability. In addition, the

institutional structures, training and skills’ development models, and monitoring and

evaluation were all identified as complementing the successful implementation of

CDPs.

60

CHAPTER FIVE

CONTRACTOR DEVELOPMENT MODELS

5.1 INTRODUCTION

This chapter reviews some models which have been developed to assist with

contractor development. The literature shows how many national, provincial and local

government bodies, implementing stakeholders and some financial institutions have

worked assiduously to formulate and implement models and other interventional

measures to assist the development of contracting firms. This chapter presents some

of the models.

5.1.1 The South African Construction Excellence Model

The South African Construction Excellence Model (SACEM) as shown in Figure 5.1

was produced by the Council for Scientific and Industrial Research (CSIR) as a tool

for contractor development in South Africa. The SACEM is a business performance

assessment tool designed to evaluate the overall performance of contracting entities

and also to assist in developing contractor capabilities in an effort to eliminate some

of the challenges facing SMME contractors (Dlungwana & Rwelamila, 2005:2).

Dlungwana and Rwelamila (2005:2–3) explain that the SACEM uses a questionnaire-

based method to assess the contractor’s level of improvement and the degree to which

the contractor is adhering to best practices. This model was built on the principle of

strong leadership, long-term approach, continuous improvement, client focus, people

management and results orientation. Therefore, the model provides an assessment of

contractors’ strengths and weaknesses in order that appropriate improvement be

implemented by the management.

Dlungwana and Rwelamila (2005:3) further assert that the SACEM is not only a

performance assessment tool but also aims at supporting the national strategic

development for the construction industry by expediting the rapid implementation of

best practices to guarantee contractors’ improvement of their output, competitiveness,

and planned management of social and environmental matters. The contractors’ quest

61

for profit, growth and sustainability should match their performance in the management

of socio-environmental matters (Dlungwana & Rwelamila, 2005:3).

This model suggests that a CDP should be subjected to monitoring and evaluation to

assess whether the programmes are being implemented as planned. Of importance

in this model is the measurement of the actual development of the trainee contractor.

Figure 5.1: The structure of SACEM

Source: Dlungwana and Rwelamila (2005:5)

5.1.2 The Integrated Emerging Contractor Development Model

The integrated emerging contractor development model was developed to be a vehicle

to facilitate skills and knowledge transfer to the construction firms. The objective of the

IECDM was to assist with developing small construction firms to become competitive

and sustainable businesses (Dlungwana et al., 2004). Hauptfleisch (2006:9) explains

that even though implemented in some provinces with satisfying outcomes, the IECDM

shown in Figure 5.2 is a complex model which requires capable management for its

successful implementation. Lazarus (2005:3) notes that the IECDM is a best-practice

tool designed to help implementing agents to aid the implementation of CDPs with the

62

added elements of project management and total quality management. According to

Dlungwana et al. (2004.), the model is a framework for managing contractor

development by facilitating the selection of suitable construction firms, implementation

of a programme of skills training, mentorship and total quality management. It

incorporates training and mentorship and depends on various stakeholders

contributing towards contractor development. The framework is therefore an all-

inclusive model which requires the involvement of all stakeholders for its successful

implementation.

According to Hauptfleisch (2006:4–9), the successful implementation of the IECDM

depends on the following:

Project manager: The IECDM is functional as a project within a project management

programme. Mediocre outcomes have been observed where the method was mainly

to assign funds to development inventiveness short of solid project management.

Hauptfleisch (2006) observed that if “a programme is not project managed, the ending

is unsurprisingly poor.”

Client - every project should have a clearly identified client who is committed to:

provide or facilitate a construction contract for contractors, valued not less

than R5 million for a period of 24 months. The model of contractor

development is based on the ‘learn and earn’ surroundings with mentoring

backing on site. The on-and-off obtainability of jobs for contractors on the

programme disturbs the progression and distracts the contractors’ attention

on development; and

dedicate management contributions in the agenda, make adequate budget

available for the programme, require attainable assurances from contractors

and enter into contracts with all necessary role players (Hauptfleisch,

2006:6).

Emerging contractors: The contractors should meet the following criteria:

63

Can be assessed for the recognition of prior learning (RPL) in order to select

a sustainable training package;

Meet minimum CETA requirements to enter a “learnership” programme,

leading to a national construction contractor qualification;

Intensive 24 month training programme commitment; and

Be previously predisposed to a mentor/protégé relationship.

Accredited construction mentors: Being trained in a specific discipline does not assure

automatic ability to act as a mentor. Mentors are selected for the programme according

to the following specific criteria. They must:

pass an examination and a psychometric evaluation

take part in a structured training course to establish understanding and

compliance requirements of mentoring objectives;

pass an interview for selection into the programme;

be devoted and unswerving to perform as a business guide and sounding

board of the emergent contractor, in some cases taking on executive duty;

supervise the established (formal) training of the upcoming contractor and

the transference of such expertise to the business of the contractor; and

have as a main objective the development of a self-sufficient and

sustainable contractor who can operate independently for 24 months.

Construction Education and Training Authority: CETA, as the constitutional body

providing funding for skills advancement, is involved in the training programme and

should therefore provide the following:

Finance for a three-party contract to enable training by a training worker, the

three parties for the agreement being the emerging contractor, the client

(acting as the employer) and a training provider registered with CETA;

Assistance with the recognition of prior learning (RPL) process; and

Fulfilling its customary role as training consultant, evaluating results of the

training.

64

a) Training providers: CETA-accredited training providers should be carefully

selected in order to ensure their capability to make available the necessary

training, working inside a organised managed agenda differing from the

common practice where training providers are only answerable to CETA. Banks

and other financial institutions: Banks and other financial institutions see

emerging contractors as high risk and therefore ‘not bankable’ and where they

are willing to help, they ask for collateral which contractors cannot provide.

Owing to this higher risk of the emerging contractors, financial institutions,

including some government-controlled ones, are reluctant to do business freely

with these contractors. The following security should therefore be built into any

facility:

An out-and-out bank account for each construction agreement that is

signed;

All disbursements outstanding to the contractor for job completed should be

paid to this account and withdrawals should only be made under the

combined signatures of the contractor and the mentor;

Facilities should first be provided by banks alongside a pre-set cash flow

forecast permitted by a mentor.

Construction Industry Development Board: The CIDB should be involved as a critical

stakeholder in order to add value. Equally, by the contractors getting registered, they

ascribe to the CIDB ‘best-practice: registration is a symbol of the ability to undertake

projects of a particular magnitude and it also helps contractors to aspire to grow to

higher levels of grading on the record, and be permitted to be able to contest for larger

and more rewarding projects in the yet to come. This consequently conveys a strong

motivation for contractors to progress themselves and their businesses.

Quality managers: Self-governing quality managers with the function of visiting the

contractors and their mentors regularly and reporting to all concerned for the duration

of the programme. Monthly progress reports from the quality managers and the

tripartite parties such as contractors, mentors and training providers can be the

foremost ideal documents used to offer the client with complete responses concerning

the development programme.

65

a) Professional services: The role of professional services in the IECDM is dual.

First, the project consultants are made mindful of the arrangement of the

programme and their backing is lobbied for the progress of the contractors. The

conflict between consultants wanting to complete projects on time and within

cost limits versus a ‘learning’ contractor not having the skills to complete on

time and within budget is minimised. Second, even though not a common

occurrence, a financial plan must be put in place to get specialist expert support

for the programme when required.

The IECDM differs from the SACEM in that it incorporates a linkage for the critical

stakeholders in the construction industry to be part of the development programme.

The IECDM also relies on the aspect of measurement of contractor progress.

Figure 5.2: The structure of IECDM

Source: Hauptfleisch (2006:1–5)

5.1.3 Supply-side interventions to accelerate growth of priority enterprises

It is also argued that contractor growth can be accelerated from interventions related

to the supply side of the value chain. Watermeyer et al. (2001:5–8), in support of this

66

theory, recommend the linking of procurement and supply-side interventions in CDPs

in order to speed up the growth of prioritised enterprises.

The range of interventions in a structured CDP, according to Watermeyer et al.

(2001:5-8), must encompass the following:

a) Interventions facilitated by the client. These are an integral part of the supply

chain activities and are facilitated and paid for by the client to provide a mechanism

for prioritised contractors to accelerate their development. The client may allow for

any or all of the following:

Third party management support: In this planning, a client employs

service providers to make available certain construction and

materials management facilities and to direct, help and train ‘on-the-

job’ young contractors in the carrying out of the contract and

supervise that the jobs progress acceptably according to the

specified requirements, thus reducing the client's risk exposure.

There is no contract between the prioritised contractor and the third

party management support provider. However contracts are entered

into between the third party and the client and between the selected

contractor and the client (Watermeyer et al., 2001:5–8).

Mentorship: In this arrangement the client should make provision

for the services of a qualified mentor in the contract by including a

re-measurable item for mentorship in the bill or schedule of

quantities. This item would comprise a maximum number of hours,

the whole or part of which may be omitted by the client, and a fixed

hourly rate for mentorship services. The contractor would appoint

the mentor and be reimbursed for the services of the mentor in

accordance with the provisions of the contract. Contractors are

required to obtain the services of accredited mentors who are then

required to assist contractors with the preparation of their tenders at

risk and should then be required to certify that, in their opinion, the

tenderer is able to complete the contract for the tendered sum. The

contractor, upon award of the contract, is required to submit a

67

mentorship plan to the client that sets out the mentorship

requirement for the contract. Mentorship is only provided by the

client department if the plan is approved. According to Watermeyer

et al. (2001:5-8), a contract is not entered into between the mentor

and the client in this type of client intervention arrangement.

b) Interventions facilitated by institutions. In these types of arrangements, the

contractors are afforded services of professional institutions to do with legal and

business decisions. Watermeyer et al. (2001:5–8) explain that in this type of

intervention, support is autonomous of the supply chain arrangements, and

generally encompasses the following:

Business and risk management.These are multifaceted business services

which, according to Watermeyer et al. (2001:7), should be provided by legal

and accounting firms aimed at assisting contractors to grow in their

businesses.

Supportive institutional arrangements. Different institutional arrangements

may be obligatory, reliant upon the administration within which line up

enterprises function and may include tender/business guidance centres,

training in commercial, technical, administration and managerial areas,

financial facilitation, ‘soft’ loans, connecting finance facilities and capability

building (Watermeyer et al., 2001:7).

5.1.3.1 Linking procurement and supply-side interventions

Growth of small contracting organisations may also be achieved by linking

procurement strategies to supply side interventions. Watermeyer et al. (2001:7) argue

that there has to be a link between interventions and procurement in order to achieve

rapid growth in CDPs. Figure 5.3 shows how the two interventions could be linked with

government procurement process for contractors’ growth.

68

Figure 5.3: Supply-side interventions required to accelerate the growth of

prioritised enterprises

Source: Watermeyer et al. (2001:7- 8)

5.2 FACTORS FOR SUCCESFUL IMPLEMENTATION OF CDPs

Ensuring that CDP programmes are successful is critical. Therefore knowing what

factors would assure success is essential. According to the CIDB (2011:76–78), the

implementing client’s knowing the rationale for the programme is critical to the success

69

of a CDP. Furthermore, a successful CDP must have political and administrative

backing and the size of the programme should be determined by the implementing

agents. The programmes should also have clear entry and exit points and commitment

of funds from management and political bodies where applicable.

The CIDB argues that the selection of contractors to the CDPs, transparent, cost-

effective and fair procurement strategies and the simplicity of contract documentation

will contribute to success of the programmes.

The common elements observed for the successful implementation of CDPs from the

literature reviewed on South Africa, some developing countries and the models of

contractor development are summarised and presented in Table 5.1. The elements

common to most of the studies include classroom work, fieldwork and mentorship.

5.2.1 Classroom work

With the exception of the SACEM and supply-side interventions which did not

specifically mention classroom work, the rest of the studies (Uriyo & Jere, 2003;

Joseph & Haule, 2003; Seth, 2004; Hauptfleisch, 2006; Enshassi & Shaath, 2007;

CIDB, 2009 & 2011; Khuthaza, 2012) as per Table 5.1 identified classroom work as

being the first part of the implementation of CDPs.

5.2.2 Fieldwork

With construction being practically oriented, it is crucial that fieldwork be part of a

contractor development programme. The use of fieldwork for the implementation of

CDPs feature prominently in all the literature reviewed (Uriyo & Jere, 2003; Joseph &

Haule, 2003; Seth, 2004; Hauptfleisch, 2006; Enshassi & Shaath, 2007; CIDB, 2009

& 2011; Khuthaza, 2012). All these sources see fieldwork as an integral part of

contractor development as depicted in Table 5.1.

5.2.3 Mentorship

As can be seen in Table 5.1, all the studies reviewed (Uriyo & Jere, 2003; Joseph &

Haule, 2003; Seth, 2004; Hauptfleisch, 2006; Enshassi & Shaath, 2007; CIDB, 2009

70

& 2011; Khuthaza, 2012) identify mentorship as an important element for contractor

development.

Table 5.1: Factors for successful CDPs

Factors for successful CDPs

Cla

ssro

om

wo

rk

Org

an

isatio

n

Fie

ldw

ork

Me

nto

rsh

ip

Vukuzakhe CDP (CIDB, 2011) X X X

Masakhe CDP (CIDB,2009 & 2011) X X X

Vuk'uphile Learnship Programme (CIDB,2009 & 2011) X X X

Khuthaza CDP (Khuthaza,2012) X X X

SEDA Construction Incubator (SCI) Programme (CIDB,2009 & 2011) X X X

Eskom Construction Academy (CIDB,2009) X X X

Development Programme – Tanzania 1 (Uriyo & Jere, 2003) X X X

Development Programme – Tanzania 2 (Joseph & Haule, 2003) X X X

Development Programme – Palestine (Enshassi & Shaath,2007) X X X

Development Programme – Lesotho (Seth, 2004) X X X

SACEM – Dlungwana and Rwelamila (2005) X X

IECDM – Hauptfleisch (2006) X X X

Supply-side interventions required to accelerate growth of priorities

enterprise (Watermeyer et al., 2001)

X X

Source: Researcher’s design

71

Figure 5.4 summaries the elements required for a successful implementation of CDPs.

Figure 5.4: Elements of successful CDPs

Source: Author’s own design

5.3 CONCLUSION

This chapter discussed the role of various institutions in assisting the development of

contractors in the South Africa. Equally, all the models for successful implementation

of CDPs in South Africa point to the fact that for CDPs to be successful, there has to

be a combination of strong leadership, government approval and participation, and the

involvement of financial institutions. Since the capacity of contractors varies, any CDP

needs to be flexible in terms of content adjustment, methods of implementation and

their accessibility. Therefore it appears that the critical elements for successful CDP

implementation should include classroom work, fieldwork and the mentoring of

contractors after graduation from the CDPs.

72

CHAPTER SIX

IMPORTANCE OF CDPs IN THE CONSTRUCTION INDUSTRY

6.1 CONSTRUCTION’S CONTRIBUTION TO ECONOMIES

The CDPs are very important because of the industry within which they are located:

the construction industry. The construction industry plays a myriad of important roles

in the socioeconomic development of most countries as it is able to employ both skilled

and unskilled labour in the economy and also provide infrastructure for the other

industries, as noted in the scenarios below.

The Organisation for Economic Co-operation and Development (OECD) (2008:6)

postulates that one of the most important driving forces for construction activity in

OECD countries is the increased spending on infrastructure and non-residential

development. It was further noted by the OECD (2008:6) that the construction industry

sector contributes about 6 per cent of the GDP in some of the largest OECD countries

and about 9 per cent of employment in these countries.

In a UK study by the Department for Business, Innovation and Skills (DBIS) it was

noted that the construction industry contributed about 7 per cent of the UK economy,

comprising over 280,000 businesses and covering some 2.93 million jobs (DBIS,

2013:7). The Australian construction industry, according to Gallery (2008:6),

contributed about 6 per cent to the economy and comprised about 8 per cent of the

labour force.

The Sri Lankan construction sector contributed nearly 8 per cent of the gross domestic

product (GDP) and was seventh among 13 major sectors contributing to the country’s

GDP (Chamber of Construction Industry Sri Lanka,2012), while the Palestine

construction industry contributed about 26 per cent to the country’s economy in 2000

(Mahamid, 2001:1).The importance of the construction industry in the Indonesian

economy reflects almost the same as the above scenario (Wibowo, 2009) and also in

Ghana as shown by Osei (2013).

73

PWC (2013) stated that the construction industry in South Africa attained a net profit

margin of up to 6 per cent in 2010 while Industry Insight reported that South Africa’s

construction industry contributed nearly 4 per cent to the GDP in 2012 (Industry

Insight, 2012:17). The industry could also be used as an economic stimulus to revive

the country's economy as it was used by the South African government after the

world’s economic meltdown.

Ngandu et al. (2010) discuss how the government used construction to stimulate the

South African economy after the recession. They observe that “…when construction

is stimulated through a government infrastructure investment program, demand for

intermediate inputs used by construction expands” (2010:10).

To elaborate on their observation, Ngandu et al. (2010:10) argued that;

“…assuming that the R787 billion allowed for in the 2010 National Budget Review for

infrastructure project over three years is entirely used in construction activities, the

total effect during the first year generates an increase of over R1.3 trillion in income of

all production activities and R250 billion in household incomes”.

Ofori (2012:4–5) summarised the importance of the construction industry to countries’

economies as being the spine of every country’s socioeconomic development, as the

outputs of construction industry’s activities such as buildings and other infrastructure

are where production and manufacturing of goods and services take place.

Businesses require buildings to work from, and roads and highways to transport and

distribute their goods. In most countries the provision of basic shelter and basic

education are constitutional obligations and these are achieved by the involvement of

the construction industry. The industry promotes tourism in most countries, as tourists

look for better accommodation and other infrastructure. The literature shows that for

most economies the construction industry contributes between 5 per cent and 10 per

cent of the GDP. About 10 per cent of the working population of countries are

employed in the construction industry.

Ofori (2012) postulates that governments can regulate the way they spend country’s

fiscal resources by using construction to introduce desired changes in their

economies. This can be done by investing a large part of their income in the

74

construction of basic infrastructure such as hospitals, schools, roads, bridges, airports,

harbours and power stations.

With the construction industry’s links to other industries in the economy, it means that

when the construction industry struggles, the ripple effect is felt in other industries and

the economy in general (Ofori, 2012:4-5).

Employing about 10 per cent of a country's population means that when there is a

boom in construction activities, there will be money in the economy to be spent in the

other sectors such as manufacturing, legal and other professional services as well.

Finally, the construction industry’s use of employee labour-intensive methods allows

it to generate employment for the citizens of most nations. Since most of construction

activities in developing countries happen in rural areas, most of the youth in these

areas are employed and able to support their families and the economy in general.

The majority of the construction activities on the site are undertaken by mostly local

SMME contractors who have acquired the projects through direct bidding processes,

sub-contracting or through joint ventures with other firms.

Wharton and Payne (2003:1) opine that about 90 per cent of construction firms in the

EU are small to medium-size and 93 per cent of these firms are macro enterprises.

They further elaborated that these SMME firms employ 50 per cent of the whole

construction workforces.

The OECD (2008:7) affirms this point by citing the European Construction Industry

Federation (FIEC) which observed that out of a total 2.9 million EU construction

companies in 2007, 95 per cent were SMEs with fewer than 20 employees. It was said

that 60 per cent of all construction work in the EU was undertaken by companies with

not more than 50 employees.

6.2 CONSTRUCTION BUSINESS REQUIRES COMPETENCE

The construction industry is a specialised sector of an economy and it poses its own

unique challenges such as overcoming fierce competition, dangerous work

environments, material supply interruptions, price escalations, labour disputes, many

75

projects being undertaken at the same time, litigation, rigorous and ever-changing

regulations, and often ambiguous drawings, specifications and contract

documentation. Consequently, such demands require a unique set of skills and

competencies to run a construction business effectively.

Entrepreneurs venturing into the construction business should be aware that just as in

any other business, there are some competences to be acquired to enable the

successful running of a construction business. Contracts signed between clients and

contractors oblige contractors to undertake the work with due diligence and complete

it within a reasonable time and budget, and deliver an acceptable quality to serve the

clients’ purpose. The contractor is expected to play its part in delivering the contract

as per the client’s scope and this can only be achieved through the competences built

over a period or taught under the CDPs.

According to Arslan and Kivrak (2008), some of the important factors of a company’s

success include sound business management and the ability to organise and plan for

a project or projects. In addition to planning and organising, the availability of cash is

also another essential part of a company’s success. The authors further contend that

the behaviour of the owner-manager is also a critical success factor. Quality of work

and workmanship which includes client satisfaction, use of good quality materials,

teamwork and harmony was the other factor. Other success factors include company

image, good advertisement and competitive pricing which were considered as the

most important strategies for a construction business. It was identified that doing

business in markets where the company has adequate experience was another factor:

experience is therefore a critical issue in the market entry assessment and basis of

competitive advantage. This factor was considered as an essential element for

success (Arslan & Kivrak, 2008:43–46).

Paz (2006) also posits that contractors need to possess some qualities such as

effective leadership, where the contractor can take risks and has a ‘can-do’ type of

personality to propel the firm through difficult times, and also be firm but fair, deliver

on promises and hold others accountable for their commitments. Paz (2006) argues

that competent contractors are able to view human resource talents as their most

76

important asset and are able to train them periodically. In addition, the author contend

that competent contractors have sound project management systems which allow for

the regular update of their information, and they must also possess and retain good

financial management and liquid cash flow for the successful implementation of

projects. They must possess superior estimating skills and must be selective in the

work they bid for and they must have a well-defined market niche and then focus their

efforts within those niches (Paz, 2006:1-3).

Mbachu (2012:864) summarise these competences required by a contractor and

group them under three main subjects, namely technical, managerial/business and

generic skills and knowledge.

6.2.1 Technical competences

The contractor technical competencies may include the ability to:

price and submit tenders or quotes as requested by clients;

estimate quantities of materials required for a job;

interpret construction drawings, specifications and contract documentations

for setting out projects on site; and

prepare requests for quotations from subcontractors and be able to select

their preferred subcontractor.

6.2.2 Managerial/business competences

Other preferred competencies that contractors should possess relate to managerial

and or business aspects such as:

project management;

risk management;

contract and conformity management;

financial management, accounting and cash flow management; and

planning and variation management.

77

6.2.3 Generic skills and knowledge competence

In addition to the core technical and management competencies, other more generic

competencies are just as critical. The set, according to Mbachu (2012:864), should

include, inter alia, the following:

Computer literacy;

negotiation skills;

Dispute resolution skills;

Organisational skills;

Operational research;

Numeracy skills; and

The ability to solve problems.

Larger construction firms have all the above skills as they are able to employ

professionals for almost all the aspects. However, most SMME companies are unable

to employ professionals and as such they are owner-managed. Therefore the owner-

managers are responsible for the implementation of the various skills. The need,

therefore, arises for the owner-managers to be trained in all the competency elements

to enable them to function effectively to the benefit of the firm.

6.3 FACTORS CONSTRAINING THE COMPETITIVENESS OF SMME CONSTRUCTION BUSINESSES

The other important reason for implementing CDPs is the competitive nature of the

construction industry. The highly competitive nature of the construction industry

requires that contractors attain certain competencies which they may currently lack.

According to Wasi et al. (2001), Enshassi and Shaath (2007), Thwala and Mvubu,

(2008), Thwala and Phaladi (2009) and Laryea (2010), some of these challenges

include contractors’ inability to price and complete a winning tender and this affects

them negatively because there is a high number of contractors at the starting or lower

end of the CIDB grading, and that means a large number of contractors have to

compete for the limited projects in the market. With a situation such as this, astute

contractors have an advantage in such a competitive environment. Makhura (2011:65)

found that one of the greatest challenges facing SMME contractors is their lack of

78

knowledge on tendering and procurement. This aspect is a disadvantage in such an

environment and definitely requires development. According to Ntuli and Allopi (2013),

competitive pricing enhances the contractor’s chances of getting continuous work.

In fact, SMME contractors in the country appear to lack these qualities as “…an

average of 7 per cent profit margin for the construction sector is forfeited with wrong

costing and pricing calculations” (Greyling, 2012:7).

The other hindrance that constrains SMME contractors is their inability to market

themselves. Word-of-mouth can elevate or diminish one's chances of getting more

work. The construction market is one of those unique markets where continuity can be

assured due to the quality of work delivered in the previous work. However, it seems

that most clients are dissatisfied with the quality of work they receive from SMME

contractors (Mbachu & Nkado, 2006). The CIDB (2011c:4) also points out the fact that

most SMMEs seem to deliver projects of low quality as their evidence suggest that the

quality of work decreases with increased project size in South Africa.

Smallwood (2010:941) observed that quality of work ranks the highest in the clients’

satisfaction index in South Africa. The lack of quality in contractors’ work has resulted

in the Department of Human Settlements using 10 per cent of its 2009/10 year’s

budget to repair poorly built Reconstruction and Development Programme (RDP)

houses (CIDB, 2011:4).

Further to the above is the contractors’ lack of or poor management skills. Poor

management affects a company’s reputation and a bad company reputation can have

adverse effects on the survival of the company. Management skills entail

administrative, financial and technical skills.

Greyling (2012:43) laments that most contractors do not have enough understanding

of the basic contracts being used in the country. Makhura (2011:65) supports this

observation and notes that most of the contractors were not familiar with contracts

being used in the South African industry. Similarly, Ntuli and Allopi (2013) find a lack

of management skills as being one of the obstacles retarding the progress of the

contractor.

79

Financial skills are found to be among the high-ranking challenges which SMME

contractors are facing (Ntuli & Allopi, 2013; Makhura, 2011). Identified practices

among SMMEs included ineffective financial skills, which may result in bad cash flow

projections, cross-financing other businesses and misuse of company funds, which

can be detrimental to the health of the SMME firm.

Equally, a lack of technical skills may lead to construction mistakes and the work

needing to be redone. Reworking takes additional time and could have serious

implications regarding the completion time of the project. A bad or careless

interpretation of drawings and specifications on site can result in a catastrophe; the

contractor will have to rectify the problem at his or her own cost and in his or her time

(Greyling, 2012:43).

The problem is also compounded by the fact that there are many small contractors

registered in the lower categories. Records at the CIDB suggest that the current CIDB

register of contractors takes the form of a pyramid with more contractors being

registered in the base categories and the few at the peak, enjoying most of the contract

work. According to the CIDB (2013), over fourteen thousand contractors were

registered on the CIDB Register of Contractors in Grades 2 to 9. In 2012, 90 per cent

of the registered contractors were in the designation of Grades 2 to 4 and 10 per cent

were in Grades 5 to 9.

Moreover, over 80 per cent of the general building and civil engineering classes of

works contracts in the public sector were awarded to contractors in the CIDB Grades

of 7 to 9 and only about 6 per cent to 8 per cent were awarded to Grades 2 to 4

(CIDB, 2013:1-2).

Records also show that not many contractors have been able to move upwards in

terms of grading. One of the reasons for this stagnation is that the grading system of

the CIDB targets the enterprise and not the individual and therefore the enterprise is

downgraded when the contractor fails to sustain workflow (Greyling, 2012:41).

The apparent lack of information communication and technology (ICT) skills also

hinders most SMME contractors’ progress. With ITC skills businesses have become

80

more productive in their business and are able to exploit other ventures and look for

and communicate with other potential clients. Unfortunately, it appears that contractors

in South Africa lack the expertise to utilise the advantages that ICT offers. Dlungwana

et al. (2002:1) contend that “…South Africa is a technology colony” and therefore

contractors, especially SMME firms, should capitalise on ICT.

Finally, other basic skills such as negotiation and dispute resolution, organisational

knowledge, numeracy and the ability to solve problems are critical to the survival of a

business (Mbachu, 2012:864). Greyling (2012:41) concludes that despite all the

copious interventions and strategies that have been put in place by government and

other stakeholders, SMME contractors reflect poor human resources management,

poor business planning, poor investments and they fail to perform within the set

quality, time frames and budgets. These inadequacies put their competency in

question. In agreement with this assertion, Ntuli and Allopi (2013:95) contend that

most of the people running SMME companies lack operational and strategic skills.

SMME contractors should be able to communicate with stakeholders, should be

abreast of their procurement of materials and services, must possess risk

management skills and manage human resources (Makhura, 2011:58).

The CIDB (2011:5-8) identified a number of challenges impacting on SMMEs and

summarised them as follows:

Absence of business and financial skills;

inadequate admittance to finance, trade credit and performance bonds;

Delayed compensation by clients affecting contractor cash-flows, causing

deferrals in the conclusion of projects and eroding away their profit margins

and also tying up operational capital, and consequently encouraging

corruption;

High turnover amongst skilful personnel due to doubts in job openings;

The fragmentation of the construction method having a confrontational

result on the total performance of the industry;

The short-term way of the job which makes it difficult to advance and carry

outt long-term approaches and growth procedures;

81

Officious or overly complicated contract award and contract administration

procedures;

Strong competition, particularly in lower levels of construction enterprise,

and struggles in challenging with larger construction firms;

Not enough wealth to provide a harmless and decent functioning

environment such as protection, equipment and attire;

Lack of expert advisors and consultants, and whenever available, the

unwillingness to use them due to alleged high costs of professional charges;

Dearth of assets equipment such as vehicles, heavy machinery or

scaffolding; and

Doubts/Uncertainty of supplies and prices of resources, associated with

commonly absent or poor relationships with suppliers.

These factors may lead to low productivity, poor quality workmanship, and low delivery

of construction projects in the South African construction industry (CIDB, 2011:6–8).

6.4 CONTINUOUS TRAINING AND DEVELOPMENT

Continuous professional development is key for most professions. It is arguably even

more critical to SMME contractors because of the competitive nature and difficult

environment in which they operate. With competition for limited work opportunities

becoming stronger, and globalisation threatening local businesses, most companies

are striving to improve their skills and knowledge in order to survive. The importance

of training and development has been advocated for by many (Paradise, 2007; Aguinis

& Kraiger 2009; Ongori & Nzonzo 2011; Jehanzeb & Bashir 2013). Those entities

which have embarked on this road of training have also seen benefits. Numerous

companies and organisations have seen the benefits of training and development and

have subsequently invested huge sums of money into training and development for

the betterment and improvement of the skills of their employees (Jehanzeb & Bashir,

2013:244). Paradise (2007) states that companies in the United States alone spend

more than $126 billion per year on employee training and development.

82

6.4.1 The concept of training and development

Several definitions of training and development exist. It should be noted, however, that

these terms have been defined in various ways throughout the literature. Masadeh

(2012:63) defines training as a planned process to modify the attitude, knowledge,

skills or behaviour through a learning experience in order to achieve effective

performance in any activity or range of activities. Its purpose in the work situation is to

develop the abilities of the individual and to satisfy current and future manpower needs

of the organisation (Masadeh, 2012: 63). Aguinis and Kraiger (2009:452) define

training as “…the systematic approach to affecting individuals’ knowledge, skills, and

attitudes in order to improve individual, team, and organisational effectiveness”.

According to Gansberghe (2003), development is a long-term process designed to

enhance potential and effectiveness. It is also defined as the growth or the realisation

of a person’s ability through learning, often from planned study and experience. It is a

systematic effort affecting individuals’ knowledge or skills for purposes of personal

growth or future jobs and/or roles (Aguinis & Kraiger, 2009:452).

6.4.2 Modules of training and development programmes

Different companies and organisations have developed various training and

development programmes to assist in the growth of their companies or the intended

recipients, but for whatever objectives they are designed, for training and development

programmes to be perfect they must consist of a mixture of knowledge, development

and goal setting (Jehanzeb & Bashir, 2013:244).

Cotterill (2004:3) elaborated that before training is implemented, there should be an

identified shortfall of skills, after which training needs must be established, and then

training objectives must be defined. Training methods must also be chosen and the

proficiency target level of the trainees must be set.

83

Cotterill (2004:3) further used Eckstrand’s systems model of training (Figure 6.1) to

explain that before an organisation can undertake training, it should first go through a

series of processes such as definition of training objectives, definition of training

content, definition of training methods and materials and thereafter development of a

training programme

Figure 6.1: Eckstrand's systems model of training

Source: Cotterill (2002:4)

6.4.3 Model of training management

For training to yield successful results for an organisation or an individual it requires a

model to assist management with the training programme. There are numerous

training models which have made an impact in the field of training and development.

These models include instructional systems design, total quality management (TQM),

performance-based instructional design, human performance technology and the

ADDIE model (See Fig. 6.2) (Bichelmeyer, 2005).

84

Figure 6.2: The ADDIE model of training

Adapted from Bichelmeyer (2005)

Cotterill (2004:6) developed a model that includes incorporating concepts such as

those of Eckstrand, Hackett and Mayo, referred to as the PRISM (Figure 6.3) to help

in the training of SMMEs and large firms.

85

Figure 6.3: The PRISM model for training management

Source: (Cotterill, 2002:7)

The PRISM model entails the following:

a) Identifying training needs

The need for training never diminishes within an organisation, just as our needs are

insatiable. Individuals receive training when they are employed in an organisation.

Then they are trained to undertake the specific task for which they have been

86

employed and thereafter they will need further training to enhance their career

advancement. A hierarchy of training needs exists and would follow a pyramid, as

showed in Figure 6.4:

Figure 6.4: The hierarchy of training needs

Source: Cotterill (2002:8)

Training must be maintained in an organisation to keep employees' competencies

renewed as knowledge and skills become obsolete and also as new technology and

expertise are being introduced. The onus, however, lies with the organisation to

analyse and established which training is needed, when it is needed and whether it

adds value (Cotterill, 2004:9).

87

b) Identifying competence gaps

The second step of the model, according to Cotterill (2004), involves identifying

competence gaps. Identification of competence gaps should take place before

training, because this helps to give the trainees the exact training they are looking for.

Different people or organisations have different competence levels and these must be

identified for proper implementation of a training programme to avoid training someone

in what he or she already knows.

Knowing the competence gaps enables the organisation and/or trainers to concentrate

on those areas. According to Cotterill (2004:10), gaps could be the following:

Organisational gap – where an organisation has procured new systems

which requires everybody within the organisation to learn to operate the

system;

Job-related gap – an employee would require training to be able to operate

new equipment or to take up a different position in an organisation; and

Individual gap – where an individual will require frequent training to remain

abreast of new technology and systems.

c) Setting training objectives

Cotterill (2004:11) explains that for any training programme to succeed, there must be

clear and concise objectives of such training, minimum competence levels for trainees

must be defined, and levels must be set that can be assessed to see whether the

organisation is achieving its aims.

Training also requires commitment from both the trainee and the employer or trainer.

The trainee should be willing to be trained to upgrade or improve his or her knowledge

and skills and the employer must also be willing to allow the employee the time to

attend the training. In addition, the employer should be willing to pay the cost of and

provide a conducive environment such as workshops and classrooms for the training

(Cotterill, 2004).

88

Good administration of the training is also a requirement to enable the organisation to

keep track of what is happening in the training. The administration process should

include who the training provider should be, the length of the training, the aims and

objectives of the training, the method of evaluating the training and the success rate

of the trainees.

d) Securing or designing training programmes

The next step in the model is the securing or designing of the training programmes.

Training can be designed and implemented by utilising in-house expertise or it can be

out-sourced to specialist external training providers. It should be decided as to which

of these two would be used, and the decision should be made by taking cognisance

of the need to provide the organisation with value for money spent.

Determination of the appropriate method of implementation of the training programme

is highly recommended. It should be realised that not all people learn with the same

level of understanding; therefore in developing a training programme one has to

consider the following five principles relating to how adults learn:

Readiness – are the users ready to learn or is preparation work required?

Association – build upon existing skills, keep training in context.

Involvement – active participation is more effective than listening to

someone talk.

Repetition – aids memory, stresses importance of key points.

Reinforcement – positive, enthusiastic feedback from the trainer. Rewards

effort and always provides constructive feedback (Cotterill, 2004).

The training needs differ between departments and therefore when selecting or

designing a training programme, one should consider who the recipients are and what

they require. The training programmes should be varied to suit the intended recipients

where necessary and, where possible, a combination of different syllabi should be

considered in order to deliver the best results.

Cotterill (2004) again mentions that the selection of appropriate training material plays

a significant role in the training process. Selecting the right training materials for the

89

right training assists in reinforcing what the trainers have learnt. Many of these can be

produced internally and, where possible, may be hired from the appropriate service

providers.

Common training materials include the following:

Audio visual aids:

Audio tapes

Video tapes

Projected slides or PowerPoint

Diagrams

Printed material:

Manuals

Workbooks

Handouts

Prepared flip-charts

Tools, machines and equipment:

Simulators

Workplace tools

Machinery parts (Cotterill, 2004)

e) Training methods

There are a plethora of methods of providing training: these can be classified as on-

the-job training and off-the-job training methods (Wood, 2004; Alipour et al., 2009).

These training methods include classroom training, distance learning, on-the-job

training, embedded training, simulator training, and computer-based training.

f) Providing training

The next step of the PRISM training model is the provision of training. According to

Cotterill (2004:18), setting up of clear and concise objectives for a training section is

90

paramount to the successful implementation of the programme. Planning and

preparation are also very vital for training implementation, especially if it is an off-the-

job training programme. The planning process as explained by Cotterill (2004) must

also include the choice of a suitable venue, checking whether all training equipment is

working well and the selection of the right training materials.

The trainees see the trainer as a mentor; as such, the competence of the trainer should

not be doubted. The trainer must possess a high level of communication skills and

must be self-motivated. Equally, the trainer should be prepared and be abreast of the

topics to teach, be able to predict likely questions from the trainees and prepare

answers to the questions. The trainer must create and maintain a high-level of mutual

understanding between him- or herself and the trainees for facilitating proper

implementation of the programme.

Another factor that can impede proper provision of training is communication.

According to Cotterill (2004), training should not be conducted in a language that the

trainees do not understand. The trainer must assess the trainees’ ability to

comprehend the language being used. Cotterill (2004) advises that sometimes it would

be prudent to use some industry jargon to teach or explain some points to the trainees.

Training materials should be legible and clear for all trainees to understand them.

Yet another factor in the provision of training is the separation of work from training,

and, as Cotterill (2004:20) puts it, “It is important that ‘on-the-job’ training is not given

‘during the job’”, because this is likely to compromise the effectiveness of the training

as the trainees will be compelled to complete their day’s work and at the same time

grasp the training proceedings. It is therefore essential that training time be carefully

separated from work time to ensure proper implementation of programmes.

The trainer must also encourage trainees’ participation in the training implementation

as they enjoy lessons when they are made to take part in the lesson. This makes them

feel responsible and enhances their recall of what they have been taught.

91

g) Evaluating the training

Evaluation of training programmes is one of the key stages of training. It enables the

stakeholders implementing the training to assess whether the training methods and

material used are benefiting the trainees. The trainers also get to know whether

trainees understand the training methods and, if not, then they have to re-evaluate

their training methodology for proper implementation. Evaluating the training

programme also assists in checking whether the training policy is being achieved and

whether the training gives value for money to the organisation (Cotterill, 2004:21).

Cotterill (2004:21) posits that evaluation can be done in the following ways:

Assessing the course by aiming at the learning that took place, checking

trainees’ attitude and behaviour on their jobs and/or the impact of training

results;

Assessing trainees’ learning levels and changing to suit them: this can be

done through setting of case studies, examinations, practically oriented

tasks, and interviews for trainees to measure their learning levels; and

Assessing trainees’ behaviour, either at work or during examinations, and

changing their behaviour levels.

h) Follow up training

If after evaluating the training programmes it is observed that the majority of the

trainees have difficulty with the assessment programmes, then there is a need for

follow-up training to be conducted. Follow-up training can be conducted by providing

trainees with their evaluation results and providing clarification on where

their answers were incorrect;

a re-training where a majority of the trainees answered incorrectly; and

refresher training to keep trainees up to date (Cotterill, 2004:22).

92

6.4.4 Benefits of training and development

Training programmes have many benefits including those to the trainees. Benefits of

training as pointed out by Aguinis and Kraiger (2009:454-455) and Jehanzeb and

Bashir (2013:246–247) include the following:

Acquiring new skills which enhance job performance: Trainees’ innovative

and implicit skills are improved which in effect adds value to their work

outputs and therefore improves their career competencies;

Improving employees’ technical skills which in turn enhances their career

competencies;

Improving trainees’ declarative knowledge;

Trainees gaining self-confidence if they understand their job description

very well, which makes them want to stay in the organisation longer; and

Enhancement of the trainees’ behaviour of how to perform. Skills are taught

that boost self-confidence and self-reliance (Aguinis & Kraiger, 2009:454).

In addition, strategic knowledge helps trainees organise their work in order to complete

a task (Jong & Ferguson-Hessler, 1996:107). Aguinis and Kraiger (2009:454) describe

this as knowing when to apply specific knowledge or skills for a specific task. Self-

reliance boosts productivity, ensures profits for the organisation and means higher

salaries and bonuses for the employees.

Acquiring knowledge through training ensures employees’ consistency in their line of

work. Consistent performance results in trainees’ loving their job or work. It enhances

employees’ performance and satisfaction in their job.

In summary, as Jehanzeb and Bashir (2013: 246-247) point out, the benefits of training

of individuals result in an enhancement of career competencies, promote employee

satisfaction and ensure employee performance. The other benefits of training relate to

organisational performance. Even though there seems to be a paucity of literature on

the profits of training and development relative to organisational performance,

Jehanzeb and Bashir (2013:247–248) argue that some of the benefits include the

following:

93

An improvement of the organisation's performance, because employees

develop their general knowledge and management skills; and

An improvement to the organisation’s productivity, sales, revenue and

generally their overall profit margins.

The other benefits to organisations which spend money on training is the retention of

employees. As rightly argued by Jehanzeb and Bashir (2013:248), when employees

are offered opportunities to improve their skills and knowledge through training, such

employees are likely to remain in the organisation. They contend that there is a solid

connection between employee training and development on the one hand, and

employee retention on the other. The retained employees subsequently become

experienced employees who, according to literature, are one of the greatest assets to

a company or organisation. Employee retention has been successful in companies

where training and development programmes have been designed and implemented

to the employees’ satisfaction (Jehanzeb & Bashir, 2013:248).

6.5 CONCLUSION

In this chapter the importance of CDPs was discussed in light of the standing of the

construction industry in the socioeconomic development of a country. It was observed

that CDP was important and should be undertaken because it is targeted at SMME

contractors which dominate the construction industry, critical to the social economic

development of a nation.

It was also noted that CDPs were critical because the SMME contractors needed key

skillsto match the demands of the construction industry. The construction industry

demands such key competencies therefore it is imperative for SMMEs to be developed

to match these. Literature reveals that entrepreneurs venturing into the industry must

possess technical, managerial and some generic competencies for them to survive

the fierce competition that exists in the industry. It is, however, noted that contractors,

especially the SMME contractors, are faced with some perennial challenges that

impede their development and sustainability, hence the need to train and develop the

contractors.

94

Furthermore, the chapter discussed training and development, the idea of training and

development, and some models of training and development, and also explored some

training methods. Finally, the benefit of training and development to individuals and

organisations in general was reviewed in this chapter. Acquiring new skills, improving

technical skills, gaining self-confidence, improving organisations’ performance and

productivity were found to be among the benefits of training and development

programmes.

95

CHAPTER SEVEN

RESEARCH METHODOLOGY

7.1 INTRODUCTION

This chapter outlines the design of how the research was conducted and the methods

which were employed to investigate the performance of CDPs in South Africa. In

addition, it presents the methods used to analyse and present the data.

7.2 RESEARCH DESIGN

The main objective of the research was to investigate the effectiveness of CDPs in

South Africa, and to establish the extent to which they have achieved their intended

goals. A review of literature was conducted on the performance of CDPs through

published articles in journals, books, peer reviewed documents and the Wide World

Web. South African and international literature were reviewed and the objectives of

the CDPs as well as their expected outcomes and the perceptions of beneficiaries on

the performance of the CDPs in the construction industry were described. This

information was intended to aid an understanding of how important CDPs are within

the context of the construction industry.

Based on the literature reviewed, structured interviews and a questionnaire survey

were conducted and the data collected from the questionnaire were analysed using

the SPSS software. The data obtained from the questionnaire sought to ascertain how

beneficiaries perceive the CDPs and their impact on the beneficiaries’ growth and

sustainability, while the interviews were conducted to triangulate and validate the

findings from the questionnaire.

7.3 RESEARCH TOOLS

7.3.1 Questionnaire

The questionnaire survey was adopted owing to its advantages as elaborated by Van

Vuuren and Maree (2008:281), which include, among others, that:

96

it is the most inexpensive method to apply and can be distributed to a

broader spectrum of respondents at a price of only a postage stamp or an

electronic mail;

it promotes confidentiality owing to the fact that respondents are usually

anonymous and are willing to be open; the questionnaire survey was

suitable for the type of data being collected and also for answers to actual

questions; and

the respondents have the luxury of reading over the questions a number of

times in order to understand them before answering.

The questionnaire was designed in accordance with the objectives of the study, which

were to investigate the effectiveness of CDPs in South Africa and to establish the

extent to which they have achieved their intended goals. A questionnaire comprising

closed-ended questions was administered to SMME contractors and their views were

solicited on the effectiveness of CDPs in South Africa. In addition, the questionnaire

included open-ended questions which were designed to encourage the respondents

to express themselves freely in those instances. The objectives of the CDPs were

transposed into simple and unambiguous questions to minimise potential errors from

respondents. Questions from relatively similar topics were adopted from the literature

reviewed and were used as the basis for the draft questionnaire. The draft

questionnaire was discussed with the research supervisor who constructively criticised

and gave valuable advice and comments. The draft questionnaire was then revised

and discussed with the university’s statistical department (Statkon) to seek their

opinion on the content and suitability. The final questionnaire was developed after

Statkon’s input.

The questionnaire comprised four main headings:

Organisation’s details: This section comprising questions 1 to 12 was

designed to capture the data of the organisation the respondent

represented. Data such as the respondents’ gender, disability, racial

classification, age, their organisation’s CIDB grading before and after the

97

CDP, and status with respect to whether they were minor, medium or macro

enterprises were captured in this section.

CDP implementation: In this section contractors’ views were solicited on

how the CDPs were implemented and whether the respondents believed

the execution process was to their expectations.

The third section was designed to capture information on contractors’

perception on CDPs, and whether they believe the CDPs were achieving

their intended objectives.

Part four of the questionnaire was an open-ended question which solicited

any other comments regarding the CDPs.

Respondents were asked the extent to which they agreed to each statement put to

them. Responses were either “Strongly agreed”, “Agreed”, “Disagreed” or “Strongly

disagreed” with the statements which were put to them. In addition, an option of

selecting “Not sure” was also included to the response type accorded to the research

participants. Weightings of 5,4,3,2 and 1 in descending order were allocated to each

response on an ordinal scale. Naoum (2007:93) describes an ordinal scale as merely

numerical labels and these do not indicate that the intervals between the scales are

equal, nor do they indicate that absolute quantities are used to rank the respondents’

responses.

7.3.2 The structured interview

In order to boost the rationality, strength and interpretative potential of the study

(Thurmond, 2001), interviews were also conducted. The questions for the structured

interviews were designed and presented in the same order and with the same wording

to all interviewees in accordance with the objective of the research. Again, the draft

questions for both consultants and graduate CDP contractors were discussed with the

research supervisor who reviewed them and gave valuable advice and commented on

them before they were administered. The objective for interviewing the consultants

was to establish their views on the performance improvement of contractors who had

undergone CDPs, if any, and also solicit their perspective on how mentorship could

be used for the betterment of CDPs, while the objective of interviewing the contractors

98

was to establish their views on mentorship and whether there were mentorship

programmes in the CDPs they had undergone.

The advantages of structured interviews as explained by Naoum (2007:57) include the

following:

High chance of answers being more accurate;

Relatively high response rate; and

Exploring answers by finding out why the particular answers were given.

The first part of the interview questions was designed for the consultants and was

comprised of four main questions. The intention of these questions was to solicit views

on the performance of CDP graduate contractors. The questions sought specifically to

establish whether contractors’ performance had improved after undergoing CDPs and

what their views were on mentorship as a way of ameliorating contractors’

performance deficiencies.

The second set of interview questions was designed for CDP graduate contractors

and comprised seven main questions. The purpose of these questions was to elicit the

contractors’ opinion on mentorship programmes during and after CDPs and to

determine whether they believed that mentorship should be continuous until they were

able to sustain themselves.

7.4 DATA COLLECTION

A purposive sampling strategy was adopted for this research because the study had

adopted a multistage purposeful approach for which the sampling method was suitable

(Onwuegbuzie & Collins, 2007). Therefore the survey was aimed at contracting firms

listed with the CIDB in categories 1 to 7 and can be described as low, medium and

macro enterprises. These SMMEs were the targets of the CDPs. The sample was

obtained from the CETA online database in Johannesburg.

In addition, the office of the Department of National Public Works in Pretoria was

contacted for contact details of contracting firms who had undergone their CPD

training with the EPWP.

99

Other respondents were obtained through links with Eskom’s training academy,

Khuthaza, Gauteng Department of Transport’s Maintenance sections and the CIDB’s

contractors’ registration register. The researcher’s networks within the construction

industry were also utilised to reach out to more potential respondents.

Contractors with CIDB grading designations of between 1 and 7 were the main targets

for inclusion in the sample because the CDPs were designed for this category of

contractors. Questionnaires were delivered to respondents’ offices in person and in

most cases the researcher waited for the questionnaires to be completed and handed

back. This approach was taken in order to increase the response rate to the

questionnaires. However, a few of the questionnaires were emailed to respondents

and were returned via electronic mail.

A total of 128 questionnaires were distributed to respondents and 103 questionnaires

were received from the respondents, translating to a response rate of 80 per cent.

According to Baruch and Holtom (2008), Nulty (2008) and Fincham (2008), a response

rate of 80 per cent is acceptable for a survey.

Furthermore, a total of 10 consultants and 12 graduate CDP contractors were

interviewed. The consultants comprised seven quantity surveyors, one architect, one

architectural technologist and one civil engineer. The contractors were made up of

three CIDB Grade 3 contractors, five CIDB Grade 4 contractors and four CIDB Grade

5 contractors.

7.5 RELIABILITY AND VALIDITY

It was important to assess the reliability and the validity of the instrument used to

collect data because statistical measurement fundamentally depends on them.

Therefore the Cronbach’s alpha coefficient was used to measure the internal

consistency of the survey instrument. Cronbach’s alpha coefficient, according Miller

(1986:2), is used during the scale development with items that have several response

options such as the agreement scale ranging from ‘Strongly Disagree’ to ‘Strongly

Agree’ as was the design of the questionnaire for the current study.

100

According to Brown (2002:17), the Cronbach’s alpha index ranges from 0 to 1. Brown

(2002:17) further explains that if the Cronbach’s alpha for a set of scores turns out to

be 0.90, that can be interpreted as meaning that the test is 90 per cent reliable, and

by implication that it is 10 per cent unreliable (100% – 90% = 10%). However,

Cronbach’s alpha coefficient of 0.7 is usually in the high acceptable range. Table 7.1

shows a Cronbach’s alpha coefficient of 0.956, which, according to Brown (2002), is

96 per cent reliable.

Table 7.1: Cronbach’s Alpha Coefficient

NUMBER OF QUESTIONS CRONBACH ALPHA COEFFICIENT

40 0.956

Reliability is the extent to which a questionnaire, test, observation or any measurement

procedure produces the same results on repeated trials (Miller, 1986:1). It is the

degree to which a measurement technique can be depended upon to secure

consistent results upon repeated application (Weiner, 2007). This aspect is critical in

part to the notion of generalisability of results.

In terms of validity, Miller (1986:3) posits that it is the extent to which the survey

instrument measures what it purports to measure. Weiner (2007:20) adds that validity

reflects those errors in measurement that are systematic or constant. There are

different aspects of validity, but for the purpose of this study validity was limited to

content validity and in order to ensure it, repeat questions and the interviews were

implemented (Golafshani, 2003).

Content validity pertains to the degree to which the instrument fully assesses or

measures the construct of interest and where items included in the measure

adequately represent the universe of questions that could have been asked (Weiner,

2007:22).

As stated, the internal consistency index in the form of Cronbach’s alpha coefficient

was used as the measure of reliability. A positive aspect of an internal consistency

101

index of reliability is that it is assessed after only one test administration and

consequently avoids the problems associated with testing over multiple time periods

(Miller, 1986:2).

7.6 RATING SCALE

Weights were assigned to each answer choice as ‘Strongly agree’ = 5, ‘Agree’ = 4,

‘Disagree’ = 3, ‘Strongly disagree’ = 2 and ‘Not sure’ = 1. This rating scale was adopted

because it has been used in many studies and was also deemed suitable for the type

of study and data collected in the current research. It is supported by Svensson

(2001:43) who contends that rating scales are usually applied to measure qualitative

variables such as beliefs, positions, perceptions and many other behavioural

variables.

In order to determine and interpret the rating scale, the indices were calculated as

follows:

X1W1 + X2W2 + X3W3 ……………………XnWn

∑(𝑋1𝑊1+ 𝑋𝑛𝑊𝑛)

where: W = weight of answer choice;

X = response count for answer choice.

Source: (http://www.surveymonkey.com)

7.7 THE CORRELATION BETWEEN CDPs AND THEIR OUTCOMES

One of the main aims of the study was to determine whether a relationship existed

between contractor improvements with the CDP training of concerned contractors.

Therefore correlations between CDPs and the expected outcomes were measured.

For instance, the correlations between the CDPs and the improvement of

management skills, the CDPs and contractor upgrade, the CDPs and promotion of the

participation of companies belonging to PDIs, and the CDPs and contractor

satisfaction were calculated using the t-test: paired two sample for means using a

significance level of 0.05 per cent.

102

The CDPs and their outcomes were correlated using the weighted average ratings.

The p-values were calculated to discover whether there was any significant correlation

between the CDPs and their intended objectives.

Gelman (2013) explains p-value as being a measure of the discrepancy of the fitness

of the null hypothesis and is calculated to measure whether the trial results are likely

to have occurred simply through chance. With p-values less than 0.05, the results from

the study are statistically significant. In brief, if the p-value is less than 0.05, then the

null hypothesis must be rejected: conversely, if the p-value is greater than 0.05, then

the null hypothesis is accepted (De Winter, 2013; Thisted, 2010; Goodman, 2008).

Otherwise, the p-value can range from 0 (chance) to 1 (total certainty).

7.8 CONCLUSION

In this section of the dissertation, the design and description of methods of data

collection were discussed. Structured interviews and self-administered questionnaires

designed and based on literature reviewed as tools for the research used in collecting

data were discussed. These tools were selected because they were found to be

appropriate for the study. Data was analysed using the SPSS software. Cronbach’s

alpha coefficient and the rating scale were used to measure the reliability and validity

of the data collected respectively. The correlation between the inputs of CDPs and the

intended outputs was calculated using the t-test paired two sample for means using a

significance level of 0.05 per cent. Based on the data collected and analysed using

the methods described in the current section, chapter eight discusses the results

thereof.

103

CHAPTER EIGHT

PRESENTATION OF RESULTS

8.1 INTRODUCTION

This chapter presents the results of the survey. It builds upon the research methods

and approaches discussed in Chapter 7. The data received from the survey were

analysed and the results are presented in this chapter.

The aim of this chapter is to present results from the analysis of the responses

received from the respondents. The first part of this chapter presents the results of the

profile of the respondents to the questionnaire. In order to understand the background

of the respondents, this part of the chapter categorises the respondents according to

their gender, disability status, ethnicity, age, and number of employees and their CIDB

grading before and after training. .

The second section of this chapter presents results on how contractors perceive CDPs

by using descriptive statistics. First, it presents the results of respondents’ perceptions

of the mentors and trainers of these CDPs and how they implemented the

programmes. Second, it presents results on the impact of the CDPs on management

skills’ improvement of the respondents. The third part presents results of the

respondents’ rating of CDPs regarding their impact on contractors’ upgrade. Fourth,

the findings on the respondents’ ratings on CDPs’ contribution towards promoting the

participation of PDIs in construction are presented. Finally, the respondents’ overall

ratings of the CDPs are presented.

The third section of this chapter presents results from the structured interviews. The

first sectionpresent results on the consultants’ perceptions of CDPs and contractors’

performance improvement. Secondly, contractors’ views on mentorship in CDPs are

discussed and an attempt is made to deduce the influence of mentorship on

contractors’ CIDB grading.

The data were analysed using SPSS and the outcomes are presented in tables, charts

and figures to address the research objectives which were the folllowing:

104

To investigate the extent to which CDPs have helped in improving

contractors’ management skills;

To investigate the extent to which CDPs have ensured contractors’ upgrade

in CIDB registration status;

To examine the relationship between CDPs and the achievement of an

increased participation of PDIs/organisations in the construction industry;

and

To establish how beneficiaries of the CDPs rate these CDP programmes.

8.2 RESPONDENTS’ PROFILES

To understand the background of the respondents, their gender, disability status,

ethnicity, age and number of employees were sought and are presented below.

The gender distribution of the respondents was reflective of the anecdotal evidence

regarding the nature of the construction industry where it is believed that there are

more males than females. The results show that male respondents accounted for 71

per cent and the female respondents accounted for 29 per cent. In terms of people

living with disabilities and their participation in the industry, 28 per cent of those who

participated in the research indicated that they lived with disabilities or had some kind

of physical disability, whereas 72 per cent indicated that they had none. Equally, 78

per cent of the respondents regarded themselves as PDIs. Most of the respondents

(73%) were in the age group of 18 to 45 years, with 27 per cent being between the

ages of 46 and above. The survey revealed that 59 per cent of the companies

represented in the study belonged to the small-industry category while 22 per cent

were in the micro-industry category and 18 per cent fell under the medium-size

category.

The participants were therefore found to be largely reflective of the current status of

the industry. It is male dominated and most of the respondents belong to SMME

organisations. Equally, the respondents were of the categorised PDI group, black and

young, and falling in the 18 to 45 age group.

105

8.3 RESULTS

8.3.1 Implementation of CDPs

The respondents were requested to rate how the CDPs were implemented and

whether they thought the CDPs were achieving their intended goals. The results from

the survey indicated an average weighted mean of 4.30 overall on the implementation

of CDPs (Table 8.1). This value was below the 4.5 rating which leans more to the

‘Strongly agree’ rating. However, the majority of the respondents agreed that the CDPs

were implemented according to their expectations. Over 90 per cent of the

respondents either ‘Agreed’ or ‘Strongly agreed’ to CDPs being implemented properly

and to their satisfaction. The respondents rated highly, at 4.56, the statement that “the

trainers delivered and explained the training clearly”. The least rated statement, at

4.14, was that there was a single point of contact and the CDP barely met the training

objectives. This was rated at 4.17, making it the second-lowest rating. The majority of

the respondents, namely 81 per cent, simply ‘Agreed’ with the statement that the

training met the intended objectives (Table 8.1).

Table 8.1: Implementation of CDPs

ID Implementation of CDP Weighted average rating

Ranking

1 The trainers delivered and explained the training clearly 4.56 1

2 The time allowed for the classroom work was appropriate

4.43 2

3 Continuous mentorship will be very helpful to successful CDP implementation

4.35 3

4 The site work was adequate 4.32 4

5 The materials given at the training were effective and helpful

4.31 5

6 The training was scheduled and communicated clearly 4.27 6

7 The training was executed according to the predetermine schedule

4.26 7

8 The mentoring processes were helpful 4.21 8

106

9 The training met the set objectives 4.17 9

10 There was a single point of contact for communication between trainers and trainees

4.14 10

8.3.2 Results on improvement of management skills

The first objective was to investigate the extent to which CDPs have helped in

improving contractors’ management skills. To achieve this, a number of questions

derived from the literature were used as indicators in the questionnaire. A weighted

average rating of 4.38 was achieved for the CDPs’ improvement of contractors’

managerial skills which slightly leaned towards ‘Agree’. As seen in Table 8.2, the

results showed that most respondents either ‘Agreed’ or ‘Strongly agreed’ with the

assertion that the training improved their management skills, with over 90 per cent of

the respondents indicating this. However, the total average rating was determined to

be 4.38, indicating a leaning towards ‘agreeing’ as opposed to ‘Strongly agree’. Most

of the respondents indicated that the training had given them more confidence in

management skills; 76 per cent of the respondents ‘Strongly agreed’ with this

statement and it was rated at 4.75. However, respondents did not think that the training

had necessarily enabled them to complete projects on time and within budget as only

62 per cent ‘agreed’ with the assertion (Table 8.2).

Table 8.2: Improved management skills

ID Improved Management Skills Weighted average rating

Ranking

1 The training has given me more confidence on my managerial skills

4.75 1

2 The training has enhanced my knowledge on financial planning

4.49 2

3 The training has broadened my knowledge on project planning

4.38 3

4 The training has assisted me to complete projects within project budget

4.33 4

5 The training has improved my knowledge on estimating and tendering

4.33 4

6 The training has enhanced my knowledge on effective quality control

4.31 5

107

7 The training has enhanced my confidence in contract laws and claims

4.29 6

8 The training has improved my ability to market my services to clients

4.28 7

9 The training has enabled me to complete projects within the contract period

4.27 8

Average weighted mean 4.38

8.3.3 Results on contractor upgrades

The second objective was to investigate the extent to which CDPs have ensured

contractors’ upgrade in CIDB registration status. A number of questions were asked

to assist with achieving this objective. Results showed an overall weighted mean rating

of 4.42, which indicated that respondents agreed that they had seen an improvement

in their registration grading (Table 8.3). Over 90 per cent of the respondents indicated

that they had seen an improvement in their CIDB status after training. Similarly, as

depicted in Figure 8.1, 8 per cent of the companies represented by the respondents

were registered in Grade 1 before the CDP, but this changed to 1 per cent after the

CDP, indicating a drop in numbers, and hence suggesting an upgrade with many of

the contractors leaving their lower grades. This was also the case for those who had

indicated that they had been registered in Grade 2. About 50 per cent of the

respondents indicated that they had been registered in Grade 2 before CDP, but this

statistic changed to 10 per cent after training completion; 31 per cent had Grade 3

before CDP, but this figure changed to 46 per cent after CDP. Grade 4 companies

were at 7 per cent before CDP, but improved to 24 per cent on completion from CDP;

again, there were 2 per cent of Grade 5 companies before CDP but this figure

increased to 13 per cent after CDP, Grade 6 had 1 per cent before CDP, but improved

to 3 per cent after training completion, Grade 7 companies made up 1 per cent before

CDP, and this too changed to 2 per cent and finally, 1 per cent of the companies were

able to attain Grade 8 after graduation from CDPs.

108

Table 8.3: Contractor upgrade

ID Contractor Upgrade Weighted average

rating

Ranking

1 The training has helped me improved my CIDB grading

4.60 1

2 The training has enabled me the opportunity to bid for bigger projects

4.48 2

3 The training has enabled my company to increase the number of employees

4.43 3

4 The training has assisted in the growth of my company’s income

4.30 4

5 The training has helped my company in getting consistent work flow

4.29 5

Average weigthed ean 4.42

The movement in the percentage registrations, namely from high to low percentages

in the lower categories and low to high percentage in the higher categories, seemed

to indicate an improvement in registrations after undergoing the CDP as indicated in

figure 8.1:

Figure 8.1: CIDB grading before and after CDP

Grade 1 Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 Grade 7 Grade 8

Before CDP 8% 50% 31% 7% 2% 1% 1%

After CDP 1% 10% 46% 24% 13% 3% 2% 1%

0%

10%

20%

30%

40%

50%

60%

109

8.3.4 Results on participation of previously disadvantaged individuals

The third objective of the study was to examine the relationship between CDPs and

the achievement of an increased participation of PDI’s/organisations in the

construction industry. A total of five questions were asked to characterise the level of

participation prior to and post CDP training. The results showed an overall weighted

mean of 4.37 which leans more to ‘Agreed’ rather than ‘Strongly agreed that the CDP

enhanced their participation in the construction industry (Table 8.4). The results also

showed that the training programme assisted the beneficiaries in being registered with

the CIDB. Access to register with the CIDB was rated the highest at 4.54 and the least

rated aspect at 4.22 was the enhancement of tendering for projects that they could not

have bid for previously (Table 8.4).

Table 8.4: Participation of PDIs

ID Participation of PDIs Weighted average rating

Ranking

1 The training has given me access to register with CIDB

4.54 1

2 The training has afforded me the opportunity to get more contracts

4.49 2

3 The training has encouraged clients to pay me promptly to boost my cash flow

4.35

3

4 The training has given financial institutions the confidence to assist me

4.24 4

5 The training has enhanced my chances of tendering for jobs that I couldn’t have tendered for

4.22 5

Average weighted mean 4.37

8.3.5 Results on contractor satisfaction with the CDPs

The final objective of this study was to establish how beneficiaries of the CDPs rate

these CDP programmes. A total of 11 questions as depicted in Table 8.5 were asked

in order to assist with achieving this objective. The results showed a weighted average

rating of 4.31. Generally most of the respondents were somewhat satisfied with the

CDPs, albeit not so strongly, as the overall weighted mean rating was lower than 4.5,

namely at 4.31. Of interest were the ratings on whether the training specifically met

110

the beneficiaries’ expectations. About 51 per cent of the respondents ‘Agreed’ that the

training had met their expectations and rated it at 4.49. As for the method of training,

more respondents were of the view that online training could not have been the best

method of delivery. The rating was 3.71 which leans towards ‘Disagreeing’ rather than

‘Agreeing’. Further, the responses to the three critical questions were not very

convincing and perhaps remain moot. The responses to: “The training programme is

worth the cost of attending; I will be attending the training in future and I will definitely

recommend the training to someone else”, were rated at 4.33, 4.32 and 4.42

respectively. Most of the respondents did not ‘Strongly agree with those statements.

About 65 out of the 103 respondents, representing 63 per cent, ‘Agreed’ that the

training was worth the cost; 62 out of the 103 respondents (60%) also ‘Agreed’ that

they would be attending similar training in future and 56 respondents (54%) ‘Agreed’

that they would definitely recommend the training to someone else. Considering the

benefits that such training would bring, the response regarding recommending to

others was expected to be ‘Strongly agree’.

Table 8.5: Contractor satisfaction

ID Contractor Satisfaction Weighted average rating

Ranking

1 The training would have been better delivered through the Internet

3.71 1

2 The training has enhanced my relationship with my clients

4.50 2

3 The training programme generally met my expectations 4.49 3

4 The training has helped improved my relationship with my employees

4.46 4

5 I will definitely recommend the training to someone else 4.42 5

6 The training has enhanced my understanding of the construction environment

4.40 6

7 The training has helped me reduced complaints about the quality of my work

4.38 7

111

8 The training programme is worth the cost of attending 4.33 8

9 The training was conducted according to our individual experience

4.33 8

10 I will be attending training in future 4.32 9

11 The training has assisted me to avoid penalties due to late completion of work

4.13 10

Average weighted mean 4.31

8.3.6 Value addition of the development programmes

In addition to finding out whether respondents would recommend the training to others,

the other questions put to them concern the value addition of the CDPs. The

respondents were asked to indicate whether the CDPs had added value. The

respondents were requested to give a simple ‘Yes’ or ‘No’ answer. Figure 8.2 shows

that 97 per cent of the respondents did not think that the CDPs were a waste of time.

Generally, most of the respondents felt that the CDPs had added value.

Figure 8.2: Response on whether CDPs were a waste of time

The response to a follow-up open-ended question showed that 59 per cent of the

respondents felt that there has to be provision of financial assistance in order to

improve the efficacy of the programmes. A further 49 per cent of the respondents

indicated that the CDPs required improvement to ensure significant benefit. Other

comments made by the respondents were that some of them were unable to obtain

financial assistance from financial establishments and in their view that situation

rendered the CDPs to be unhelpful.

No, 97%

Abstain, 3%

112

Still on the question of the CDPs’ being helpful, respondents noted that the onsite

training programmes must be conducted by the same people who had initially

conducted the classroom training to ensure consistency. Respondents noted that the

conflicting approaches in the methodology of training when the two were conducted

by different institutions impacted negatively on the effectiveness of the training

programmes. In summary, respondents indicated that the CDP programmes were not

a waste of time and actually did add value to them. However, the respondents felt that

provision of finance and the methodology of training delivery needed to be improved

if the CDP’s were to be of help.

8.4 RESULTS FROM THE INTERVIEW

This section of the chapter presents the results of the interviews conducted on

consultants and contractors. The intention was to solicit consultants’ views on

contractors’ performance improvement after CDPs and also contractors’ views on

mentoring programmes in CDPs. Furthermore, this section looked at the individual

CDPs reviewed in Chapter 2 to assess whether there were any relationships between

their implementation processes and learners’ migration in their CIDB grading. The

results were as follows:

8.4.1 Consultants’ responses on CDPs and contractors’ performance

The results from the survey indicated that majority of the consultants interviewed

(90%) said that they had worked with SMME contractors who had undergone CDPs.

However, most (about 70%) of these consultants believed that contractors’

performance had not improved. As to the possible interventions that could be used to

improve the goals of the programmes, all the consultants (100%) interviewed believed

that a long-term mentorship process could be used to improve contractors’

performance. Furthermore, the majority (80%) of the interviewees believed that

mentorship must be compulsory if at all meaningful contractor development was to be

realised.

8.4.2 Contractors’ views on long term mentorship

The first question to the contractor interviewees was to find out whether they had

undergone or enrolled for a mentorship programme. Findings were that most (83%) of

113

the contractors said that they had not undergone any mentorship programmes.

Interestingly, most of the contractors (83 %) knew or had heard about mentorship

during their time at the CDPs.

With regards to the administration of the mentorship programme for those who had

previously enrolled for the programme, 42 per cent of the interviewees said that they

had had to pay for enrolling in the mentorship programmes. The interview also

revealed that there was a requirement to pay for the mentorship, but some of the

programmes were subsidised. A few of the interviewees (25%) said that the

mentorship programmes that they had enrolled for were subsidised, whereas 33 per

cent said that theirs had been free.

According to many contractors (83%) who had undergone some sort of mentorship

programme, they said that the improvement in their CIDB grading could be attributed

to the mentorship, while 17 per cent said that they had not seen any improvement in

their CIDB grading. It was also observed that most of the contractors (58%) would not

mind adding their mentors as signatories to their bank accounts if that would allow

financial institutions to provide them with financial assistance, while 42 per cent

indicated that they would not sacrifice their privacy for financial assistance. It was,

however, noteworthy that most of the interviewees (75%) believed that mentorship

programmes provided value for money. Statements such as “the mentorship

programme was worth paying for” referred to the fact that interviewees considered the

programme valuable. On the other hand, about a quarter of the contractors did not

believe that the programmes gave them value for their money.

8.5 IMPACT OF THE MENTORSHIP PROGRAMME ON CONTRACTORS’ CIDB GRADING

This section of the chapter compares the movement in contractors’ CIDB grading of

the individual CDPs implemented in South Africa. An attempt was made to verify

whether there was any linkage between the CDPs that had mentorship programmes

and the movement in the CIDB grading.

Figure 8.3 shows the overall movement in contractors’ CIDB grading in the CDPs

reviewed. One hundred per cent of the respondents from Eskom’s construction

114

academy indicated that they had had a higher CIDB grading. Eighty-six per cent of the

respondents from the SCI programme also responded that they had seen an upgrade

in the CIDB grading whereas 72 per cent from the EPWP-Vuk'uphile Learnership

Programme had some upgrade in their CIDB grading. Sixty-three per cent of

respondents from Masakhe CDP and 60 per cent from Khuthaza Contractor

Development had all seen some upgrades in their CIDB grading, with 57 per cent of

the respondents for both Vukuzakhe CDP and others stating that they had seen some

upgrades as depicted in Figure 8.3.

Figure 8.3: Percentage of migration in CIDB grading

8.5.1 Migration in CIDB grading in Vukuzakhe Contractor Development Programme

Critically analysing the contractor’s migration from a lower CIDB grading to higher

grading revealed that a fair percentage of the contractors who had undergone the

Vukuzakhe CPD had upgraded their CIDB grading with a total of 57 per cent of

upgrades. Table 8.6: Migration in CIDB grading in Vukuzakhe CDP shows that 36

per cent of the respondents who had undergone this CDP had migrated from CIDB

grading 1 to 2. Fourteen per cent of the respondents had migrated from CIDB grading

2 to 3 while 7 per cent upgraded from Grade 3 to Grade 4. However, 43 per cent did

not upgrade or did not state whether they had upgraded.

0%

20%

40%

60%

80%

100%

120%

Vukuzakhe Masakhe Vuk'uphile Khuthaza SEDA Eskom Others

Percentage of Migration in CIDB Grading

115

Table 8.6: Migration in CIDB grading in Vukuzakhe CDP

Frequency % of Upgrade

No. of entrants 14

Upgrade from Grade 1 to 2 5 36%

Upgrade from Grade 2 to 3 2 14%

Upgrade from Grade 3 to 4 1 7%

Upgrade from Grade 4 to 5 0 0%

Upgrade from Grade 5 to 6 0 0%

Upgrade from Grade 6 to 7 0 0%

Did not upgrade or state anything 6 43%

Total no. of upgrades 8 57%

8.5.2 Migration in CIDB upgrade in the Masakhe Contractor Development Programme

There were some upgrades in the CIDB grading of companies represented by the

respondents of the survey. The percentage for the total upgrade was 63 per cent.

Table 8.7: Migration in CIDB grading in Masakhe CDP indicates that 13 per cent of

the contractors indicated that they had migrated from CIDB grading 1 to 2. Thirty-eight

per cent had migrated from CIDB grading of 2 to 3, while 13 per cent had upgraded

their CIDB grading from 3 to 4. A total of 38 per cent of respondents did not upgrade

or did not state anything, as depicted in Table 8.7: Migration in CIDB grading in

Masakhe CDP7.

116

Table 8.7: Migration in CIDB grading in Masakhe CDP

Frequency % of Upgrade

No. of entrants 8

Upgrade from Grade 1 to 2 1 13%

Upgrade from Grade 2 to 3 3 38%

Upgrade from Grade 3 to 4 1 13%

Upgrade from Grade 4 to 5 0 0%

Upgrade from Grade 5 to 6 0 0%

Upgrade from Grade 6 to 7 0 0%

Did not upgrade or state anything 3 38%

Total no. of upgrades 5 63%

8.5.3 Migration in CIDB upgrade in EPWP-Vuk'uphile Learnership Programme

Respondents who underwent the Vuk’uphile Learnship Programme showed some

improvement in the CIDB grading with a 72 per cent upgrade. Twenty per cent of the

learners indicated that they had migrated from CIDB grading 2 to 3; while 32 per cent

of the learners had migrated from grading 3 to 4. As indicated by Table 8.88, 12 per

cent had upgraded their CIDB Grade from 4 to 5 while 8 per cent upgraded from 5 to

6. However, 28 per cent of respondents did not upgrade or did not state anything in

the survey.

117

Table 8.8: Migration in CIDB grading in Vuk'uphile CDP

Frequency % of Upgrade

No. of entrants 25

Upgrade from Grade 1 to 2 0 0%

Upgrade from Grade 2 to 3 5 20%

Upgrade from Grade 3 to 4 8 32%

Upgrade from Grade 4 to 5 3 12%

Upgrade from Grade 5 to 6 2 8%

Upgrade from Grade 6 to 7 0 0%

Did not upgrade or state anything 7 28%

Total no. of upgrades 18 72%

8.5.4 Migration in CIDB upgrade in Khuthaza Contractor Development Programme

Table 8.9:9 indicates that 40 per cent of the contractors who underwent the Khuthaza

CDP had upgraded the CIDB grading from 1 to 2 and 20 per cent had migrated from

CIDB grading 3 to 4. A total of 60 per cent upgrade was observed while 40 per cent

did not upgrade or did not state anything.

118

Table 8.9: Migration in CIDB grading in Khuthaza CDP

Frequency % of Upgrade

No. of entrants 5

Upgrade from Grade 1 to 2 2 40%

Upgrade from Grade 2 to 3 0 0%

Upgrade from Grade 3 to 4 1 20%

Upgrade from Grade 4 to 5 0 0%

Upgrade from Grade 5 to 6 0 0%

Upgrade from Grade 6 to 7 0 0%

Did not upgrade or state anything 2 40%

Total no. of upgrades 3 60%

8.5.5 Migration in CIDB upgrade in SCI Programme

As shown in Table 8.10, 18 per cent of the contractors who underwent the SEDA (SCI)

had increased their CIDB grading from Grades 2 to 3, 50 per cent upgraded from

Grades 3 to 4, with 14 per cent indicating that they had migrated from 4 to 5 and

another 5 per cent showed movement from Grade 5 to 6. However, 14 per cent did

not upgrade or did not state anything.

Table 8.10: Migration in CIDB grading in SEDA CDP

Frequency % of Upgrade

No. of entrants 22

Upgrade from Grade 1 to 2 0 0%

119

Upgrade from Grade 2 to 3 4 18%

Upgrade from Grade 3 to 4 11 50%

Upgrade from Grade 4 to 5 3 14%

Upgrade from Grade 5 to 6 1 5%

Upgrade from Grade 6 to 7 0 0%

Did not upgrade or state anything 3 14%

Total No. of upgrades 19 86%

8.5.6 Migration in CIDB upgrade in Eskom Construction Academy

The results of the upgrades in the Eskom Construction Academy’s graduates were

that 38 per cent had shown movement by upgrading from Grade 4 to 5. At least 25 per

cent of the learners had migrated from Grade 5 to 6 while another 38 per cent indicated

that they had migrated from CIDB Grade 6 to 7, as depicted in Table 8.111

Table 8.11: Migration in CIDB grading in Eskom CDP

Frequency % of Upgrade

No. of entrants 8

Upgrade from Grade 1 to 2 0 0%

Upgrade from Grade 2 to 3 0 0%

Upgrade from Grade 3 to 4 0 0%

Upgrade from Grade 4 to 5 3 38%

Upgrade from Grade 5 to 6 2 25%

Upgrade from Grade 6 to 7 3 38%

120

Did not upgrade or state anything 0 0%

Total no. of upgrades 8 100%

8.5.7 Migration in CIDB upgrade in other construction development programmes

Table 8.122 shows that the contractors who had undergone other CDPs also showed

some improvements in the CIDB grading. Twenty-nine per cent indicated that they had

moved from Grade 1 to 2, 5 per cent had upgraded from CIDB Grade 2 to 3, 19 per

cent migrated from CIDB Grade 3 to 4 and 5 per cent upgraded from CIDB grading 6

to 7. However, 43 per cent of the respondents did not upgrade or did not state anything

in the survey.

Table 8.12: Migration in CIDB grading in others CDP

Frequency % of Upgrade

No. of entrants 21

Upgrade from Grade 1 to 2 6 29%

Upgrade from Grade 2 to 3 1 5%

Upgrade from Grade 3 to 4 4 19%

Upgrade from Grade 4 to 5 0 0%

Upgrade from Grade 5 to 6 0 0%

Upgrade from Grade 6 to 7 1 5%

Did not upgrade or state anything 9 43%

Total no. of upgrades 12 57%

121

8.6 CONCLUSION

The aim of CDPs was to create an enabling environment for SMME companies

belonging to PDIs, women, the youth and people living with disabilities. The

demographic data analysed suggested that most of the entrants to the CDPs fell into

those categories. Most of the firms surveyed fell within the SMME category and they

also have CIDB gradings ranging from 1 to 7 which is also a requirement for entrance

to the programmes.

In addition, most of the respondents surveyed were youth and also previously

disadvantaged, with Africans being in the majority. There still remains the historical

male-female dichotomy in the construction industry as those reflected in the data

analysis revealed the number of males exceeding that of females. The other issue that

still exists and is exposed in the analysis is that the representation of people living with

disabilities involved in construction is still low.

In the analysis of respondents’ perceptions on the implementation of the CDPs,

whether the CDPs are helping improve their management skills, whether the CDPs

enhance contractor upgrade, whether the CDPs encourage PDI participation and

whether the respondents were fairly satisfied with the programme, the responses

could be termed as fairly positive with some gaps which all stakeholders must consider

for the future improvement of the CDPs.

However, the interviews conducted revealed some interesting scenarios. The majority

of consultants believed that contractors’ performance had not changed, even after

undergoing these CDPs, and they agreed that mentorship after graduation would

assist in mitigating contractors’ performance deficiencies.

Most of the contractors interviewed claimed that mentorship was useful to their

sustainability, but not all of them had had the chance to undergo mentorship, either

because they were not introduced to it or they believed the process was expensive.

The survey also revealed that there was some kind of relationship between CDPs that

had mentoring programmes and the migration of contractors from lower CIDB grading

to higher grading of learners or graduates. There were correlations between the CDPs

122

that had mentoring and continuous mentoring processes and the migration from a

smaller CIDB grading to a higher grading.

These findings presented in the current chapter are discussed further in the next

chapter to derive meaning and also to compare with other known knowledge on the

matter.

123

CHAPTER NINE

DISCUSSION OF THE RESULTS

9.1 INTRODUCTION

The purpose of the study was to investigate the effectiveness of CDPs in general with

a view to contributing to their improvement. The research’s primary objectives were

(a) to investigate the extent to which CDPs have helped in improving the contractors’

management skills; (b) to investigate the extent to which CDPs have ensured

contractors’ upgrade in CIDB registration status; (c) to examine the relationship

between CDPs and the achievement of an increased participation of

PDIs/organisations in the construction industry; and (d) to establish how beneficiaries

of the CDPs rate these CDPs.

9.2 QUESTIONNAIRE SURVEY RESULTS

The findings as regards each objective are presented below.

9.2.1 Improvement of management skills

The first objective was to investigate the extent to which the contractor development

programmes have helped in improving contractors’ management skills.

The findings from the survey revealed that most of the respondents felt that the CDPs

had slightly ameliorated SMME contractors’ management skills. However, the findings

on the ratings on some individual questions pertaining to their management skills

indicated a not so satisfactory level. The contractors’ responses regarding their

knowledge on estimating and tendering, project planning, contract law and claims and

on marketing were all rated a little below average and could not be regarded as

satisfactory.

These findings including those from the consultants interviewed who indicated that

there was no significant improvement in the contractors’ management skills or

performance. These findings were similar to those found by Ntuli and Allopi (2013),

124

Greylings (2012), Smallwood (2010) and Mbachu and Nkado (2006) who noted that

SMME contractors still lacked some basic construction and management skills.

The study revealed that even though the CDPs had enabled the improvement of some

of the contractors’ management skills, there still remained much work to be done to

improve the contractors’ management skills. These findings were supported by

literature reviewed on CDPs internationally.

9.2.2 Contractor upgrades

The second objective was to investigate the extent to which the contractor

development programmes have ensured contractors’ upgrade in CIDB registration

status.

The findings in the study were that the CDPs might have translated into some

contractor upgrade in their CIDB registration status. However, these findings were in

sharp contrast to the profile of the CIDB contractors’ register which revealed that there

was a large number of contractors at the bottom of the CIDB grading pyramid, and

that there is very little upward movement of contractors from the lower categories

(CIDB; 2009, 2011 & 2013).

The responses to individual statements such as “the CDPs have assisted in the growth

of contractors’ companies” and “the CDP have assisted in companies getting

consistent work flow” were noted to be below average. This finding was consistent

with literature on South Africa which indicates that many contractors were downgraded

in terms of their CIDB grading owing to failure to ensure consistent work flow

(Greylings, 2012).

The favourable response to the question of the CDP giving contractors the opportunity

to tender for bigger projects was noted. The explanation for this positive rating might

be due to the allowance by the CIDB for the PDI contractors with a ‘potentially

emerging’ status to tender for projects one stage higher than their stipulated stage

(CIDB, 2013).

125

Literature on the South African construction industry with specific reference to

contractor registration shows that many SMME contractors dominate the bottom half

of the CIDB grading pyramid (CIDB, 2013). It would appear therefore that the CDPs

have not necessarily assisted in contractor upgrades.

9.2.3 Participation of PDIs

The third objective of the study was also to examine the relationship between the

CDPs and the achievement of an increased participation of companies belonging to

PDIs.

The findings from the survey revealed that most of the respondents actually felt that

the CDPs have ensured an increased participation of these beneficiary companies

belonging to PDIs.

However, with access to funding being the main obstacle to the participation of PDIs

in the construction industry, the findings could therefore not support the assertion that

the CDPs had given financial institutions the confidence to assist them. The question

attained a below average rating which was also consistent with the studies of

Havemann (2001), Söderbaum (2001), Rogerson (2010) and the CIDB (2011) who

observed that PDI construction companies were still faced with some obstacles to

their development which included, among others, the following:

The requirement to provide collateral in order to access loans and other

financial assistance; and

Late and fluctuating payment cycles. Most SMME contractors depend on fluid

cash to transact business. Any delay in paying these contractors results in their

failing to pay their employees and suppliers, which therefore renders them

uncreditworthy and consequently affects their progress and quality of work on

site.

These obstacles were also noted by interviewees in the open-ended questions of this

study.

126

The CDPs might be seen as having some influence on PDIs companies but literature

indicated that PDIs were still regarded by financial institutions as high risk. The fact

that CDP providers on mentorship programmes require mentors to co-sign financial

transactions with the PDI companies also pointed to the fact that PDIs were regarded

as high risk. PDI contractors on the above-mentioned CDP were only granted financial

assistance by financial institutions on evidence of co-signatory arrangements with a

mentor.

9.2.4 Contractor satisfaction

The fourth objective was to establish how beneficiaries of the CDP rate the

programme.

The general impression of the study was that most of the contractors were fairly

satisfied with the CDPs. However, most of the individual questions were rated below

average, suggesting that there were some gaps within the CDPs that required the

collective attention of all stakeholders to rectify.

First, it was observed that the CDPs did not assist the collaboration between

contractors and clients.

Second, the beneficiaries requested that the CDPs should emphasise quality control

and quality assurance knowledge in order to improve contractors’ output on site.

Third, the beneficiaries felt that a needs assessment should be conducted on

individual contractors to ascertain their individual experiences and needs before the

training was conducted. The beneficiaries believed that the one-size-fits-all approach

did not benefit the contractors because they all had different needs and had varying

experience.

Fourth, the beneficiaries felt that the training should have included more modules on

contractors’ human resource management processes in order to improve their

relationship with their employees.

Finally, one of the most interesting observations was the number of beneficiary

contractors who disagreed with the statement that the training would be worthwhile if

127

conducted via the Internet. It was expected that the contractors would have opted for

CDPs to be conducted via the Internet owing to the easy access to different tools that

could be used for this purpose and might assist contractors to be trained in the comfort

of their offices. This finding might be because as technically oriented people, the

contractors preferred their trainers to train them physically on site to being remotely

trained.

These findings were consistent with those by Havemann (1999), Seth (2004),

Enshassi and Shaath (2007) and Rogerson (2010) who found that the beneficiary

contractors regarded the CDPs to be effective and useful but had gaps which required

attention.

9.3 STRUCTURED INTERVIEW RESULTS

9.3.1 Consultants’ perception of CDPs’ impact on contractor performance improvement

The findings from the structured interviews were that consultants had not seen any

major improvement in contractors’ capabilities. The consultants’ opinion was that

continuous mentorship was the way forward in assisting contractors’ performance

improvement. The consultants unanimously agreed that mentorship programmes

were able to ensure contractors’ upgrade and sustainability. It was therefore a

common opinion of the consultants that for the CDPs to achieve their outcomes,

continuous contractor development should be made compulsory in all CDPs. These

findings were supported by Croswell and McCutcheon (2001) who observed that a

successful CDP should have an ongoing mentoring programme.

9.3.2 Contractors’ perceptions on mentorship

The findings from the structured interviews were that mentoring was optional in most

of the CDPs that they had undergone. It was also found that most of the mentoring

programmes were paid for by the contractors themselves and because they were

once-off and non-compulsory, most of the contractors deemed them to be an

unnecessary expenditure. This finding was consistent with CIDB’s finding (2011) that

only one out of the many CDPs reviewed had a working mentorship programme but

even that required the beneficiary to pay for it.

128

The findings were that the contractors, in agreement with the consultants, were in

favour of the idea of having mentoring in all CDPs and that it should be continuous

and compulsory. It was, however, requested that such continuous mentorship

programmes must be subsidised or be made free of charge. These findings were in

congruence with those of Uri and Jere (2003), Joseph and Haule (2003), Enshassi

and Shaath (2007) and Seth (2004) who also postulated that successful CDPs were

those that were subsidised by national or local governments or, in some cases, by

foreign donors and other organisations.

The relevance of mentorship programme was noted by most interviewees and they

indicated that they would not mind having their mentors as co-signatories on their bank

accounts if that was the requirement in order for financial institutions to offer them

assistance. In as much as this could be said to be the contractors’ confidence in the

mentors, it could also be argued that those conditions were accepted by the

contractors because that was their only chance of getting assistance from the financial

institutions which view these contractors as high risk.

9.4 KEY FINDINGS

This study found that the general best practices for a successful CDP implementation

included, among others, the implementing clients’ knowing the rationale for the

programme. In addition, a successful CDP was found to be one with a political and

administrative backing and the size of the programme was determined by the

implementing agents. Furthermore, the programmes should also have clear entry and

exit points and a commitment of funds from management and political bodies where

applicable. In addition, the selection of contractors into the CDPs and the procurement

strategies of the programmes should be transparent, open, cost-effective and fair.

Finally, the documentation for the CDP implementation should be simplified to conform

to the CIDB Standards for Uniformity.

The key findings of this current study were that the elements for a successful CDP

implementation were classroom work, fieldwork and continuing mentorship

programmes.

129

Literature revealed that classwork should be the first training point for successful CDPs

(Uriyo & Jere, 2003; Joseph & Haule, 2003; Seth, 2004; Hauptfleisch, 2006; Enshassi

& Shaath, 2007; CIDB, 2009; 2011; Khuthaza, 2012). Equally, fieldwork was found to

be part of a successful CDP. The use of fieldwork for the implementation of CDPs

features prominently in most of the literature which was reviewed (Uriyo & Jere, 2003;

Joseph & Haule, 2003; Seth, 2004; Dlungwana & Rwelamila, 2005; Hauptfleisch,

2006; Enshassi & Shaath, 2007; CIDB, 2009 & 2011; Khuthaza, 2012;) as these

authors regarded fieldwork as an integral element of any successful contractor

development programmes.

9.4.1 Continuous contractor mentorship

A significant finding of the current study was that, for a CDP to be successful and to

ensure contractors development sustainability, it should have a continuous contractor

mentorship (CCM) programme.

The benefits of CCM to the owner-manager of a SMME, according to the literature,

includes, among others, improved performance and productivity; improved knowledge

and skills; greater confidence, empowerment and well-being; improved job satisfaction

and motivation; faster learning and enhanced decision-making skills; improved

understanding of the business; improved creativity and innovation; encouragement of

positive risk-taking; and development of leadership abilities. On the other hand, the

benefits to the enterprise or business include, among others, strategic change,

facilitation of partnerships, innovation and change, problem solving and better project

management (Mazzarol et al. 2006; Pompa, 2012:9; BIS 2013).

The finding in the current study was that a successful CDP had a structured series of

consecutive contracts, during which the SMME contractors were continuously

mentored until they were able to act independently, that is having the entrepreneurial

approach towards marketing and tendering successfully to ensure their sustainability

(Croswell & McCutcheon, 2001).

The benefits of CCM were evident from literature in that, in most studies, the surveyed

respondents had requested CCM to be included in their CDPs (Uri & Jere, 2003;

Joseph & Haule, 2003; Seth, 2004; Enshassi & Shaath, 2007).

130

The findings from the questionnaire for the implementation of the CDPs were that the

majority of contractors strongly agreed or agreed to the proposition that CCM would

improve the success of CDPs. These findings were in agreement with the findings

from the structured interview conducted among consultants and contractors. Eighty

per cent of the consultants interviewed believed that CCM could ensure a successful

CDP while 75 per cent of contractors believed that CCM would assist in improving the

CDPs.

According to the South African literature, most of the CDPs had mentorship

programmes embedded in their curriculum. However, only a few of the CDPs had

implemented those mentoring programmes.

The current study found that there was a correlation between the CDPs that

implemented their mentorship programmes and the migration of contractors from a

lower CIDB grading to a higher grading. It was found that contractors who had

undergone the SCI programme migrated from a lower CIDB grading to a higher

grading. This movement was also attributed to the SCI programme which provided

support to selected participants, albeit at a cost, for a period of three years, by which

time the contractor would have advanced by at least one financial level above the entry

point in the CIDB grading and should have been capable of operating in the open

market with little or no support (CIDB, 2011:27).

Evidence that greater improvements were achieved in programmes with elements of

CCM was found in the Eskom CDP programme. It was found that the Eskom

Construction Academy’s contractors achieved a significant migration in their CIDB

grading. This result was attributed to the fact that the Academy had continuity of

contracting opportunities, training and ongoing mentoring, and also included a high

level of institutional support, as mentioned by Croswell and McCutcheon (2001). The

Eskom Construction Academy provided full mentoring and coaching support services

throughout the programme (CIDB, 2008:26) and most of the graduates were assured

of a constant workflow from Eskom. These conditions found in Eskom were

acknowledged as the reasons for the success of the CIDB upgrade.

131

9.5 CONCLUSION

The findings from the study showed that the CDPs had not assisted beneficiaries in

improving their management skills. Similarly, the CDPs were found not to have

assisted companies’ upgrades to higher CIDB gradings and that they had not ensured

the participation of PDIs in the construction market. However, beneficiaries were found

to be fairly satisfied with the CDPs and regarded them as value-adding activities.

Nevertheless, there were certain disparities or gaps within the CDPs that required the

implementing agencies’ serious attention to ensure the successful implementation of

the CDPs. Consultants also believed that the contractors’ performance had not

improved after undergoing the CDPs, and both the consultants and contractors

concurred that continuous mentorship programmes would be the solution for this lack

of performance.

A relationship was established between the CDPs that offered mentorship and the

migration of their beneficiaries from lower CIDB grading to higher grading. The

knowledge that the CCM programme seemed to correlate with the successful CDP

outcome was established.

The next chapter summarises the findings of the research, draws conclusions and

provides recommendations for the research problems.

132

CHAPTER TEN

SUMMARY, CONCLUSIONS AND RECOMMENDATIONS

10.1 INTRODUCTION

This concluding chapter concentrates on reviewing the contribution of this research to

the body of knowledge on CDPs. The aims and objectives of this study are reviewed.

An overview of each chapter is also presented, showing how each chapter relates to

the overall aims, analysing and detailing their contribution to the research. The

limitations and implications of the study are also presented in this chapter.

10.2 OBJECTIVES OF THE STUDY

The overall objective of the current study was to investigate the effectiveness of CDPs

in general with a view to contributing to their improvement. In order to achieve the

objectives of the study a mixed methodology was adopted. An extensive literature

review, structured interviews and self-administered questionnaires were used in

collecting the data which were analysed using SPSS. The structured interviews were

conducted to triangulate the findings of the questionnaire and literature reviewed.

Conclusions regarding the study are presented relative to the objective of the study.

10.2.1 Objective one

The first objective of the study was to establish the extent to which CDPs have helped

in improving contractors’ management skills. The findings were that, even though

contractors observed some improvements in their management skills, it could not be

termed sufficient owing to certain gaps within the current CDPs, and this observation

was also made by consultants. The literature reveals that most clients were

dissatisfied with the quality of work undertaken by the SMME contractors. Findings

from the literature were that most contractors were unable to submit winning tenders.

The literature again revealed that for CDPs to improve contractors’ management skills,

the beneficiaries must be trained in the classroom, on the field and through an ongoing

mentoring programme.

133

10.2.2 Objective two

The second objective of the study was to establish the extent to which the CDPs

ensured contractors’ upgrading. The findings were that, although contractors observed

some upgrades during the CDP period, they might have been downgraded after the

CDP. It can therefore be concluded that the CDPs have not ensured contractors’

upgrading because most contractors did not sustain their migration from lower CIDB

grading to higher grades. The literature revealed that many contractors still remained

at the bottom of the CIDB grading pyramid.

10.2.3 Objective three

The third objective was to examine the relationship between CDPs and the

achievement of an increased participation of PDIs/organisations in the construction

industry. The findings were that the CDP had not assisted in alleviating the persistent

obstacles faced by PDIs/organisations in the construction industry. The literature

postulated that PDI organisations were struggling to obtain financial assistance from

financial institutions because they are classified as a major risk.

10.2.4 Objective four

The final objective was to establish how beneficiaries of the CDPs rated these CDPs.

The findings showed an average contractor satisfaction with the CDPs and a belief

that they added value to their businesses. The findings only showed an average

satisfaction because the beneficiary contractors believed there were some gaps in the

CDPs that required attention for their successful implementation. The literature

revealed that even though the CDPs might have assisted in some contractors’

performance improvement, most SMME contractors still faced challenges that these

CDPs were designed to eliminate. The findings of the survey conducted among

construction consultants revealed that contractors’ performance had not improved and

it was suggested that continuous mentorship programmes be made a vital part of

every CDP.

134

10.3 CONTRIBUTION AND VALUE OF THE RESEARCH

The contribution and value of the current study are described below.

The study could contribute to the existing knowledge on CDPs as it pursued

the opinion of the beneficiary contractors about the valuation addition of the

CDPs.

This study has revealed that continuous contractor mentorship (CCM) could

be used to replace the current once-off mentorship programmes in the

CDPs.

The findings of this study could assist policy makers and stakeholders in

CDP development and implementation.

The study offers an opportunity for further research to improve and possibly

refine the findings of this study.

This study offers many implications for practice and therefore adds value to the body

of knowledge.

10.4 CONCLUSION

The following conclusions could be drawn from the findings of the research study.

The majority of the entrants to the CDPs fell within the PDI or the historically

disadvantaged individuals (HDI) category as enshrined in the Preferential

Procurement Policy Framework Act (PPPFA) (2000). This conclusion could be made

because the research findings showed that most of the trainees of the CDPs fell under

the PDI status with the majority of them being Africans. Again, the majority of the

trainees fell within the SMME category in the South African perspective: they were

youth and were within the requisite CIDB grading of 1 to 7.

Meanwhile, the male–female dichotomy in the construction industry (Moodley, 2012)

was observed in the study. The percentage of women surveyed was 29 per cent, which

fell short of the stipulated 40 per cent as required under the EPWP (2000). However,

there was a higher percentage (28%) of people living with disabilities as compared to

the 2 per cent stipulated in the EPWD (Mukanyima, 2012:138). The research generally

135

showed that the entrants to the CDPs fulfilled the entry requirements as stipulated in

NPWD (2008:6).

The study showed that the CDPs had not assisted beneficiaries in improving their

management skills. Again, the CDPs had not assisted companies’ upgrades into

higher CIDB grading and the CDPs had not ensured the participation of PDIs in the

construction market.

The study also showed that the beneficiaries were fairly satisfied with the CDPs and

regarded them as adding some value to their upgrading and sustainability. However,

there were certain gaps within the CDPs that required the implementing agencies’

serious attention to ensure the successful implementation of the CDPs.

Construction consultants perceived that the contractors’ performance had not

improved even after undergoing the CDPs. Both the consultants and contractors

concurred that continuous mentorship programmes would be the solution to this lack

of performance. There were relationships between the CDPs that offered mentorship

and the migration of their beneficiaries from lower CIDB grading to higher grading.

The finding of this study also showed that the CCM programmes which were found to

be vital to any successful CDP were lacking in most of the South African CDPs

reviewed.

10.5 RECOMMENDATIONS

The research findings have revealed the area(s) that require(s) attention of CDPs to

ensure their successful implementation and to achieve their set objectives of improving

the management skills of contractors, ensuring contractors’ upgrade and encouraging

the participation of PDIs in the construction industry.

CCM was observed as the overall remedy for the improvement of contractors’

performance to ensure their sustainability.

The following recommendations are made to all the relevant stakeholders and

implementation agencies or institutions involved with CDPs as part of the solution for

achieving the aims and objectives of these programmes.

136

10.5.1 Methodological

It is recommended that a similar study be conducted nationwide with a

different population and different sample size to improve the application of

CCM in CDPs.

It is also recommended that different methods other than structured

interviews and questionnaire be encouraged in studies such as this.

10.5.2 Theoretical

The importance of CCM was observed from the literature and the different

definitions of mentorship were provided and explained. This study, however,

observed that the key word for the mentorship programmes was

“continuous”. It is therefore recommended that contractor mentorship

programmes be made continuous to be beneficial to the construction

industry.

10.5.3 Practical

It is recommended that all CDPs should have organised intuitional

structures which are appropriately staffed to deliver the programmes.

It is recommended that all CDPs should have well-defined training and

development models with concise syllabus structures.

It is recommended that CDPs should have well-defined entry and exit levels

to enable the implementing bodies to evaluate learners’ performance.

It is recommended that the government and other CDP-implementing

agencies be observant of the importance of mentorship to contractor

development.

It is recommended that all implementing stakeholders should observe

mentorship as continuous process and not just a once-off process.

It is recommended that mentors implementing these programmes meet the

minimum qualifications as prescribed by the South African Council for the

Project and Construction Management Professions.

137

It is also recommended that CCM be cost free or the cost to contractors

subsidised.

Contractors should be encouraged to form associations to contribute

funding towards the payment of the mentors.

10.6 LIMITATIONS

The research was aimed at surveying contractors across the entire country,

but owing to both time and financial constraints it was limited to the Gauteng

Province only.

There were no respondents to the other provincial CDPs, and it would have

been interesting to know how these provincial CDPs would have fared.

There could have been a larger number of consultants for the interview but

these were reduced owing to time constraints.

10.7 SUGGESTION FOR FURTHER RESEARCH

A nationwide research could be undertaken in the future with time and all other

resources permitting. However, there are copious research opportunities to explore

from the findings of this study, with some of them listed below:

Exploring the effectiveness of CCM in South Africa;

Improving the impact of continuous contractor development and contractor

migration in CIDB grading;

The impact of project and financial management skills on contractors’ CIDB

upgrade;

The role of coaching and mentoring in contractor development; and

Gaps and solutions to a better CDP.

10.8 CONCLUSION

This study focused on the effectiveness of CDPs in South Africa. The aim of the

research was to investigate whether the CDPs had achieved their intended goals and

objectives of improving contractors’ management skills, ensuring contractors’

upgrade, encouraging the participation of PDIs in the construction market, and

138

establishing contractors’ general satisfaction with the programmes. Further, the study

sought to determine how CDPs could be improved so that they could achieve their

goals and also meet the beneficiary requirements.

The study revealed that a continuous mentorship programme embedded in a CDP had

better results in terms of the development programmes meeting their goals and

beneficiary satisfaction. However, most CDPs did not have or did not implement the

mentorship programmes effectively. This study therefore recommends that for CDPs

to meet their intended goals, classwork and field delivery methods need to be

supplemented by CCM as an integral part of every CDP.

These findings were grounded in theory and empirical findings. The study first

established and discussed the importance of the construction industry to the

socioeconomic development of countries and the role that SMME contractors played,

and the challenges that they faced as businesses. It was established that because of

the significant role that SMME contracting organisations played in the industry, and

the significance of the industry itself to national economies, it was necessary to have

effective training and development programmes for these SMME contracting

organisations.

However, the question arises as to what type of training and development programmes

were suitable and effective to meet the goals of development. Various contractor

development programmes were reviewed regarding their aims, methods of delivery

and outcomes. Equally, the implementation of CDPs and their impact on contractors’

development in South Africa and other developing countries were also evaluated.

Other training and development theories, including their benefits, were reviewed.

Findings from the review of the CDPs were that there was number of CDP initiatives

which were sometimes not coordinated, even within a country. Further, although

beneficiaries were happy with the offerings, almost all the CDPs had gaps which the

beneficiaries thought should have been addressed before commencing on the training.

Issues such as understanding the trainee and financing were key findings. The other

key finding was that in almost all the CDPs reviewed, the issue of continuous

mentorship was central and yet it was not effectively implemented. Beneficiaries felt

139

that this aspect of development was critical if all the intended goals were to be

achieved.

This study was embarked on in light of the fact that very few studies have sought the

views of beneficiaries on whether the CDPs have achieved their goals,. The study

adopted a research methodology which investigated small, medium and macro

enterprise contractors’ perceptions of CDPs in South Africa. A mixed method of

structured interviews and a questionnaire survey was utilised to collect triangulated in-

depth data to fully understand how effective the CDPs have been.

The results from the survey presented in Chapter 8 showed a level of satisfaction by

the beneficiaries in the CDPs. However, the CDPs were found not to be as effective

as intended.

140

REFERENCES

Abor, J. & Quartey, P. (2010). Issues in SME development in Ghana and South

Africa. International Research Journal of Finance and Economics, 39:1–11.

Abu B. A. & Tufail, M.A. (2012). Transforming capability of indigenous contractors

through technology transfer: A Malaysia experience. World Applied Sciences

Journal, 16 (10):1450–1461.

ACEVO. (2012). How to be successful and write a winning tender. The ACEVO

Commissioning Support Service. Available from:

http://www.acevo.org.uk/commissioning. (Accessed 12 June 2012).

Agapiou, A., Clausen, L.E., Flanagan, R., Norman, G. & Notman, D. (1998). The role

of logistics in the materials flow control process. Construction Management and

Economics, 16:131–137.

Aguinis, H. & Kraiger, K. (2009). Benefits of training and development for individuals

and teams, organizations, and society. Available from:

http://www.annualreviews.org/doi/abs/10.1146/annurev.psych.60.110707.163505.

(Accessed 12 November 2012).

Ali, A., Mohd-Do, Z., Alias, A., Kamaruzzaman S.N. & Pitt, M. (2010). The

performance of construction partnering projects in Malaysia. International Journal of

Physical Sciences, 5 (4):327–333.

Ali, A.S., Smith, A., Pitt, M. & Choon, C.H. (2010). Contractors’ perception of factors

contributing to project delays: Case studies of commercial projects in Klang Valley,

Malaysia. Available from:

http://www.researchgate.net/publication/271203417_Contractors'_Perception_of_Fa

ctors_Contributing_to_Project_Delay_Case_Studies_of_Commercial_Projects_in_Kl

ang_Valley_Malaysia (Accessed 13 October 2015).

Alipour, M., Salehi, M. & Ali, S (2009). A study of on the job training effectiveness:

Empirical evidence of Iran. International Journal of Business and Management, 4

(11):63–68.

141

Armstrong, S. & Terry, O. (1977). Estimating the non-response bias in mail surveys.

Journal of Marketing Research, 14(3):396–402.

Arslan, G. & Kivrak, S. (2008). Critical factors to company success in the

construction industry. International Journal of Human and Social Sciences, 47:43.

Arslan, G., Kivrak, S. & Tankisi, M. (2009). Collaboration and integration in

engineering, management and technology. Proceedings of the Fifth International

Conference on Construction in the 21st Century. May 20–22, Istanbul, Turkey.

Barr, T. (2003). Measures of central tendency. Available from

http://www.opencontent.org/openpub/ (Accessed 20 February 2014).

Baruch, Y. & Holtom, B.C. (2008). Survey response rate levels and trends in

organizational research. Human Relations, 61 (8): 1139–1160. Available from:

http://hum.sagepub.com (Accessed 20 February 2014).

Bek, D. & Taylor, I. (2001). Evaluation of spatial development initiatives: Case

studies of the Maputo Development Corridor and the West Coast Investment

Initiative, DPRU Working Papers 01/52. Cape Town: University of Cape Town.

Bell, B.S. & Kozlowski, S.W.J. (2002). Adaptive guidance: Enhancing self-regulation,

knowledge and performance in technology-based training. Personal Psychology,

55:267–306.

Berry, A. (2000). The role of the small and medium enterprise sector in Latin

America: Implications for South Africa. Paper presented at the 2000 TIPS Forum,

September, Johannesburg.

Berry, A., Von Blottnitz, M., Cassim, R., Kesper, A., Rajaratnam, B. & van Seventer,

D.K. (2002). The economics of SMMEs in South Africa. Paper presented at the 2002

TIPS Forum, December, Johannesburg.

Bichelmeyer, B. A. (2005). The ADDIE Model – A metaphor for the lack of clarity in

the field of IDT. AECT 2004 IDT Futures Group Presentations. Available from:

http://www.unco.edu/cetl/sir/clt/documents/idtf_bic.pdf (Accessed 13 October 2013).

142

Bowen, M., Morara, M. & Mureithi, S. (2009). Management of business challenges

among small and micro enterprises in Nairobi-Kenya. KCA Journal of Business

Management, 2 (1):16–26.

Brannen, J. (2007). Mixed methods research: A discussion paper. Institute of

Education: University of London.

Brinkerhoff, D.W (200). The enabling environment for implementing the Millennium

Development Goals: Government actions to support NGOs. Conference Paper

presented at George Washington University on The Role of NGOs in Implementing

the Millennium Development Goals, May 12–13, 2004. Washington, DC.

Brook, M. (2004). Estimating and tendering for construction work. 3rd ed. Boston:

Butterworth Heinemann.

Brown, J.D. (2002). The Cronbach alpha reliability estimate. JALT Testing and

Evaluation. SIG Newsletter, 6 (1) February 2002:17–18).

Broxtowe Borough Council. (2012). Tendering guidance. Tips for completing a good

PQQ / tender submission. Available from:

http://www.broxtowe.gov.uk/CHttpHandler.ashx?id=14497 (Accessed 13 October

2015).

Bureau of Economic Research (BER). (2005). Economic growth in South Africa

since 1994. BER: Stellenbosch.

Business Education. (2011). Available from: http://www.bized.ac.uk. (Accessed 29

June 12).

Buys, F. & Ludwaba, D. (2012). The potential of built-environment professionals’

contribution towards emerging contractor development. Available from

http://www.ajol.info/index.php/actas/article/download/87639/77303 (Accessed 16

January 2014).

Cañas, A., Coffey, J., Reichherzer, T., Hill, G., Suri, N., Carff, R., Mitrovich, R. &

Eberle, D. (1998). El-Tech: A performance support system with embedded training

143

for electronics technicians. Available from: http://www.aaai.org (Accessed 20 May

2013).

Chamber of Construction Industry Sri Lanka. (2012). The construction industry of Sri

Lanka. Available from: http://www.ccisrilanka.com (Accessed 5 July 2012).

Chapman, H. (2006). The construction industry guide to internet marketing: A

building talk publication. Available from http://www.buildingtalk.com/. (Accessed 5

June 2012).

Civil Designer. (2012). The Vukuakhe Development Programme. Available from:

http://www.civildesigner.com/showcase/vuk/pillay.asp# (Accessed 13 October 2013).

Colman, R. (2002). California dreaming: New Alberta-California venture capital

channel opens doors for Western high tech. CMA Management 76(6):48–50.

Construction Education Training Authority (CETA). (2006). The CETA sector skills

plan. Available from: http://www.ceta.org.za/sectorskillsplan/chapter_01.htm

(Accessed 6 September 2012).

Construction Industry Development Board (CIDB). (2005a). Contractor tips and

advice: Tender processes for public sector procurement. Construction Industry

Development Board, Pretoria: CIDB:1–2.

Construction Industry Development Board (CIDB). (2005b). Procurement measures

to develop registered contractors. Pretoria: CIDB.

Construction Industry Development Board (CIDB). (2009). CIDB's activities and

achievement during 2009. Proceedings of a postgraduate conference held in May

2009 in Malaysia.

Construction Industry Development Board (CIDB). (2011a). Review of the contractor

development programmes: Towards an NCDP monitoring and evaluation system.

Pretoria: CIDB:93.

144

Construction Industry Development Board (CIDB). (2013a). Construction industry

indicators 2012 report. Pretoria: CIDB.

Construction Industry Development Board (CIDB). (2013a). SME Business

conditions survey, 3rd quarter 2013. Pretoria: CIDB.

Construction Industry Development Board (CIDB). CIDB. (2009). Status quo report:

SA contractor development programmes. Pretoria: CIDB.

Construction Industry Development Board (CIDB). CIDB. (2011b). Baseline study of

provincial contractor development programmes. Pretoria: CIDB.

Construction Industry Development Board (CIDB). CIDB. (2011c). National

contractor development programme framework. Pretoria: CIDB.

Construction Manager in Training Program (CMIT) (2010). Mentoring guide.

Available from: https://cmaanet.org/files/shared/Mentor_Guide.pdf (Accessed 22

October 2013).

Cooperative Research Centre for Construction Innovation (2008). Literature review:

Modelling construction business performance. Available from

http://www.construction-innovation.info/ (Accessed 16 September 2013).

Cotterill, R. (2004). Best practice guidance on training for small and medium-sized

enterprises for prism 4–24. Available from

http://www.epsc.org/data/files/PRISM/Development%20-%20Rev%201.pdf

(Accessed 16 November 2013).

Cozens, W.R. (1998). Why do you collect data? Residential Treatment for Children

and Youth, 15(4):25–44.

Creswell, J. W. (2008). Educational research: Planning, conducting, and evaluating

quantitative and qualitative research. 3rd ed., Upper Saddle River, NJ: Pearson

Education.

145

Creswell, J.W. (2003). Research design: Qualitative, quantitative, and mixed method

approaches. Thousand Oaks, CA: Sage.

Cristina, D. (2009). Marketing on the construction market in an economic crisis.

Annales Universitatis Apulensis Series Oeconomica, 11(2):1055–1059.

Croswell, J. & McCutcheon, R. (2001). Small contractor development and

employment – A brief survey of sub-Saharan experience in relation to civil

construction. Proceedings of First International Conference on Employment Creation

in Development, 2–5 April, Johannesburg, South Africa.

Cunningham, J. B. & Eberle, T. (1993). Characteristics of the mentoring experience:

A qualitative study. Personnel Review, 22 (4):54–66

Danziger, J. & Dunkle, D. (2005). Methods of training in the workplace. Available

from www.crito.uci.edu/papers/2005/danzigerdunkle.pdf (Accessed 16 November

2013).

De Lisle, J. (2011). The benefits and challenges of mixing methods and

methodologies: Lessons learnt from implementing qualitatively led mixed methods

research designs in Trinidad and Tobago. Caribbean Curriculum, (18):87–120.

De Winter, J.C.F. (2013). Using the student’s t-test with extremely small sample

sizes. Practical Assessment, Research and Evaluation, 18 (10)1–12.

Department for Business, Innovation and Skills (BIS). (2013) Demand for mentoring

among SMEs. Available from http://www.BIS.gov.uk. (Accessed 12 December 2014).

Department for Business, Innovation and Skills (BIS). (2013). UK Construction: An

economic analysis of the sector. Available from

https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/21006

0/bis-13-958-uk-construction-an-economic-analysis-of-sector.pdf (Accessed 13

October 2015).

Department of Census and Statistics Sri Lanka. (2012). Web: www.statistics.gov.lk.

Available from: http://

146

/www.statistics.gov.lk/national_zaccounts/Press%20Release/PRESS%20NOTE%20

%202012%20Annual%20English.pdf. (Accessed 21 November 2013).

Department of Census and Statistics Sri Lanka. (2012). Available from:

http://www.statistics.gov.lk/national_zaccounts/Press%20Release/PRESS%20NOTE

%20%202012%20Annual%20English.pdf. (Accessed 21 November 2013).

Department of Public Works (DPW). (2001). Code of Practice: Mentorship in

Engineering and Construction Works Contracts in South Africa. Pretoria: Department

of Public Works.

Department of Public Works (DPW). (2005). Guidelines for the implementation of

labour-intensive infrastructure projects under the expanded public works programme.

Pretoria: Department of Public Works: 1–32.

Department of Public Works (DPW). (2011) Masakhe emerging contractor

development programme, Hand Book. Available from http://www.kznworks.gov.za.

(Accessed 3 June 2012).

Dlungwana, W. S. & Rwelamila, P. D. (2004). Contractor development models that

meet the challenges of globalisation: A case for development management capability

of local contractors. Available from:

http://researchspace.csir.co.za/dspace/bitstream/10204/1936/1/Dlungwana_2004.pdf

(Accessed 13 October 2015).

Dlungwana, W. S., Nxumalo, X. H., Huysteen, S. V., Rwelamila, P. D. & Noyama, C.

(2002). The development and implementation of the South African Construction

Excellence Model (SACEM) Proceedings of the International Conference on

Construction in the 21st Century (CITC2002), “Challenges and opportunities in

Management and Technology” 25–26 April, 2002, Miami, Florida, USA.

Dlungwana, W. S., Roux, E., Setswalo, L. & Lazarus, S. (2008). Implementation of

integrated contractor development model: Towards enhanced competition for small

construction firms. Available from:

147

http://researchspace.csir.co.za/dspace/handle/10204/2571 (Accessed 12 March

2012).

Donkor, S. (2011). Determinants of business failure: The perspective of SME

building contractors in the Ghanaian construction industry. Unpublished thesis.

Kwame Nkrumah University of Science and Technology, Kumasi, Ghana.

Douglas, C.A (1997). Formal mentoring programs in organisations, An annotated

bibliography. Centre for Creative Leadership, Greensboro, North Carolina. Available

from http://www.ccl.org/leadership/pdf/research/formalmentoringprograms.pdf.

(Accessed 18 December 2014).

Egan, J. (1998). Rethinking construction. London: Construction Industry Council.

Eliot, S. (2010). Ten distinctions between quantitative and qualitative studies.

Available from: http://www.qualitative-researcher.com/wp-

content/uploads/2013/02/Ten-Distinctions-Between-Quantitative-and-Qualitative-

Studies.pdf (Accessed 5 April 2014).

Engineering news, (2007). Too few contractors moving up the grades. Available from

http://www.engineeringnews.co.za/article/too-few-contractors-moving-up-the-grades-

2007-11-02 (Accessed 12 November 2012).

Enshassi, A. & Shaath, K. (2007). Training assessment of Palestinian contractors.

Journal of Construction in Developing Countries, 12 (1):39–57.

EPWP. (2008). Expanded public works programme five-year report 2004/05 –

2008/09: Reaching the one million target. Available from: http://www.epwp.gov.za

(Accessed 2 March 2012).

Eskom. (2012). Performance contracting brochure. Available from

http://www.eskom.co.za/sites/idm/Documents/858_Eskom_perfomance_contracting_

brochure.pdf (Accessed 21 November 2013).

148

Eskom. (2013). Construction trade skills development program. Available from

http://www.eskom.co.za/OurCompany/EskomInitiatives/Documents/ConstTradeSKill

sProj13Aug.pdf (Accessed 11 March 2014).

Eyiah, A. (2004). Regulation and small contractor development: A case of Ghana.

Centre on Regulation and Competition working paper series, University of

Manchester: 2–22.

Falkena, H., Abedian, I., Blottnitz, M.V., Coovadia, C., Davel, G., Madungandaba, J.,

Masilela, E. & Rees, S. (2001). SMES’ access to finance in South Africa – A supply-

side regulatory review by The Task Group of the Policy Board for Financial Services

and Regulation. Available from

http://www.treasury.gov.za/publications/other/Access%20to%20Finance%20in%20S

outh%20Africa%20-%20A%20Supply-Side%20Regulatory%20Review.pdf

(Accessed 2 April 2013).

Fincham, J. E. (2008). Response rates and responsiveness for surveys, standards,

and the Journal. American Journal of Pharmaceutical Education, 72(2) Article 43.

Fuentes-del-Burgo, J. & Navarro-Astor, E. (2012). How is job satisfaction in Spanish

building engineers influenced by training? Proceedings of 28th Annual ARCOM

Conference, 3–5 September 2012, Edinburgh, UK, Association of Researchers in

Construction Management: 601–610.

Gale, B. T. & Swire, D. J. (2006). Value-based marketing and pricing. Available from:

http://www.cval.com/ (Accessed 15 July 2012).

Gamage, S. (2003). Small and medium enterprise development in Sri Lanka: A

review. Pp.33–149. Available from

http://www.smmeresearch.co.za/SMME%20Research%20General/Conference%20P

apers/SME%20development%20in%20Sri%20Lanka.pdf (Accessed 6 June 2013).

Ganapathy, S. N. & Wyrick. D. A. (2011). Framework for implementing sustainable

practices in SMEs in the United States. Proceedings of the World Congress on

Engineering, July 6 – 8, 2011, held in London, UK.

149

Garbarino, S. & Holland, J. (2009). Quantitative and qualitative methods in impact

evaluation and measuring results. Available from http://www.gsdrc.org/ (Accessed 16

September 2013).

Gartner, W.B., Bird, B. & Starr, J. (1992). Acting as if: Differentiating entrepreneurial

behaviour from organisational behaviour. Entrepreneurship Theory and Practice,

Vol.16:13–30.

Gcaba, M., Purchase, R. & Distin, T. (2004). Why are black owned contractors

unable to penetrate the blacktop industry in KwaZulu-Natal? Proceedings of the 8th

Conference on Asphalt Pavements for Southern Africa (CAPSA'04), 12–16

September, Northwest, South Africa.

Gelman, A. (2013). P values and statistical practice. Available from:

http://andrewgelman.com/2013/02/08/p-values-and-statistical-practice/ (Accessed 15

October 2014).

Gholba, M. J. (2012). Measures of central tendency. Available from:

http://dspace.vpmthane.org:8080/jspui/bitstream/123456789/2836/1/Measures%20of

%20Central%20Tendency.pdf (Accessed 20 April 2014).

Giese, J. L. & Cote, J. A. (2000). Defining consumer satisfaction. Academy of

Marketing Science Review. Available from:

http://www.amsreview.org/articles/giese01-2000.pdf (Accessed 3 March 2014).

Gijsbrechts, E. (1993). Prices and pricing research in consumer marketing: Some

recent developments. International Journal of Research in Marketing, 10(2):115–51.

Goi, C. L. (2009). A review of marketing mix: 4ps or more? International Journal of

Marketing Studies, 1(1):2–14.

Goodman, S. (2008). A dirty dozen: Twelve p-value misconceptions. Departments of

Oncology, Epidemiology, and Biostatistics, Johns Hopkins Schools of Medicine and

Public Health, Baltimore, MD.

150

Gravells, J. (2006). Mentoring start-up entrepreneurs in the East Midlands –

troubleshooters and trusted friends. International Journal of Mentoring and

Coaching, 6(2):3–22.

Greyling, E. (2012). Capacity building programmes, contractor development and

empowerment: Building capacity for sustainable delivery. Available

from:http://www.sahf.org.za/Images/2012%20Proceedings/PowerPoints/GREYLING

_ERICA.pdf (Accessed: 13 October 2015).

Hager, M.A., Wilson, S., Pollak, T.H. & Rooney, P.M. (2003). Response rates for

mail surveys of nonprofit organizations: A review and empirical test. Nonprofit and

Voluntary Sector Quarterly, 32(2):252–267.

Haider, T. (2009). Financial management of construction contracts (constructability

and its relation with TQM, cost shifting risk and cost/benefit). International Research

Journal of Finance and Economics, Vol.28:43–50.

Hampson, K. D. & Kwok, T. (1997). Strategic alliances in building construction: A

tender evaluation tool for the public sector. Journal of Construction Procurement, 3

(1):28–41.

Harrington, A. (1999). E-mentoring: The advantages and disadvantages of using

email to support distance mentoring. Available from

http://www.coachingnetwork.org.uk/information-

portal/Articles/ViewArticle.asp?artId=63 (Accessed 17 December 2014).

Hauptfleisch, A.C. (2006). An accelerated integrated small construction contractor

development model: A holistic approach for a developing country. Proceedings of the

International Cost Engineering Council Congress 2006 held in Ljubljana, Slovenia.

Available from: http://www.icoste.org/Slovenia2006Papers/icecFinal00014.pdf

(Accessed 13 October 2015).

Hauptfleisch, D., Lazarus, S., Knoetze, T. & Liebenberg, S. (2007). An integrated

emerging contractor development model for the construction industry: Practical

implementation and statistical quantification. CIBD World Building Congress, 2007.

151

Havemann, G. & Van Gass, C. (2001). WORK2001 First International Conference on

Employment Creation in Development, University of the Witwatersrand, 2001,

Johannesburg.

Havemann, G. (1999). Personal communication: Small contractor specialist.

Development Bank of Southern Africa. Johannesburg.

Healy, J., Ryan, W., Stewart, S. & Stewart, R. (2002). Training needs analysis in an

SME in the Irish construction industry. In: Greenwood, D (Ed.), 18th Annual ARCOM

Conference, 2–4 September 2002, University of Northumbria. Association of

Researchers in Construction Management, Vol. 2:687–95.

Hills, M. J., Fox, P.W., Fong, P. S. W., Hon, C. K. H. & Skitmore, M. (2006). Factors

influencing the development of Hong Kong’s construction industry: A qualitative

study. Proceedings of the Joint International Conference on Construction Culture,

Innovation and Management (CCIM), 26–29 November in Dubai. Available from

http://eprints.qut.edu.au (Accessed 1 August 2013).

Holland, C. (2009). On and off the job: Learning experiences, connections and

implications for literacy language and numeracy. Joinery and Glass Industry Training

Organisation. Available from https://akoaotearoa.ac.nz/ako-hub/ako-aotearoa-

central-hub/resources/pages/and-job-learning-experiences-connections-and-implic

(Accessed 12 October 2013).

Hopwood, N. (2007). Research design and methods of data collection and analysis:

Researching students' conceptions in a multiple‐method case study. Journal of

Geography in Higher Education, 28 (2):347–353.

Hox, J.P. & Boeije, H.R (2005). Data collection, primary and secondary.

Encyclopaedia of Social Measurement, Vol.1:593–598.

IHS Global Insight. (2009). India Construction: Importance of infrastructure

construction in India. Available from:

http://www.ihsglobalinsight.com/gcpath/India_Construction_1-7.pdf (Accessed 12

October 2015).

152

Industry Insight. (2011). State of the South African construction industry, 2nd Quarter

2011. Available from:

http://industryinsight.co.za/reports/State_of_the_South_African_Construction_Industr

y_2nd_Quarter_2011_1314016316.pdf (Accessed 12 October 2015).

Industry Insight. (2012). The state of the South African Construction industry. 2nd

Quarter 2012 pp.15–23. Available from:

http://industryinsight.co.za/reports/industry_insight_2nd_quarter_2012.pdf (Accessed

12 October 2013)

Institute of Chartered Accountants in England and Wales. (2012). Best-practice

guideline SME Finance. The Department for Business, Innovation and Skills, 58.

Available from: http://icaew.com/cff (Accessed 12 October 2013).

International Labour Organization (ILO). (1999). Employment-intensive infrastructure

programmes: Capacity building for contracting in the construction sector guidelines.

Geneva: International Labour Office.

International Labour Organization (ILO). (2012). South Africa SME observatory,

opportunities for employment creation through SME development in the construction

sector. Geneva: International Labour Organisation.

Inzer, L. D. & Crawford C. B. (2005). A review of formal and informal mentoring:

Processes, problems, and design. Journal of Leadership Education, 4 (1):31–51.

Jacquet, A. (2002). Sustainable contractor development through focused and

coordinated interventions. Paper presented at the build environment profession

convention, 122. Available at:

https://www.academia.edu/4102530/Sustainable_Contractor_Development_through_

focused_and_coordinated_interventions_May_2002 (Accessed 13 October 2015).

Jehanzeb, K. & Bashir, A.N. (2013). Training and development program and its

benefits to employee and organization: A conceptual study. European Journal of

Business and Management, 5 (2): 243–11.

153

Jong, T. & Ferguson-Hessler M.G.M. (1996). Types of quality knowledge.

Educational Psychologist, 31(20):105–113.

Joseph, H. & John, H. (2003). Challenges and opportunities in the development of

the construction industry personnel: The NCC experience. Available from:

http://www.ncc.or.tz/cod.pdf (Accessed 21 November 2013).

Kaplowitz, M.D., Hadlock, T.D. & Levine, R. (2004). Web and mail response rate.

American Association for Public Opinion Research, 68(1):94–101.

Kelle, U. (2006). Combining qualitative and quantitative methods in research

practice: Purposes and advantages. Qualitative Research in Psychology, 3 (4):293–

311.

Khan, G. (2004). Encouraging entreneurship in Brunei Darussalam. Education and

training for enterprise development. Available from:

http://www.sbaer.uca.edu/research/1998/ICSB/f007.htm (Accessed 27 March 2012).

Khan, R.A.G., Khan, F. A. & Khan, M.A. (2011). Impact of training and development

on organizational performance. Global Journal of Management and Business

Research, 11(7):64–68.

Kobole, S.C. (2009). An evaluation of the citizen contractor development component

of the citizen empowerment policy in Botswana. Unpublished thesis. Johannesburg:

University of the Witwatersrand, Johannesburg.

Kohlrieser, G. (2006). Hostage at the table: How leaders can overcome conflict,

influence others, and raise performance. San Francisco: Jossey-Bass.

Larcher, P. (1998). Privatizing road maintenance in developing countries.

International Journal of Public Sector Management, 11 (2/3):116–129.

Larcher, P. (2001). Case study: A comparison of four contractor development

programmes. Available from: http://www.transport-

links.org/rtkb/english/Module%202%5C2_5b%20Case%20Study%20-

154

%20Contractor%20Development%20Programmes.pdf (Accessed 21 November

2013)

Laryea, S. (2010). Challenges and opportunities facing contractors in Ghana.

Proceedings of a West Africa Built Environment Research (WABER) Conference 27–

28 July 2010 held in Accra, Ghana.

Lazarus, S. (2005). An integrated skills development model for emerging

contractors. Unpublished MBA dissertation: Port Elizabeth Technikon.

Leedy, P.D. & Ormrod, J. E. (2010). Practical research planning and design. 9th ed.

Upper Saddle River, New Jersey: Prentis-Hall Inc.

Leedy, P.D. & Ormrod, J.E. (2001). Practical research: Planning and design. 7th ed.,

Merrill, New Jersey.

Leonard, D., & Swap, W. (2000). Gurus in the Garage. Harvard Business Review,

November- December: pp.71–82.

Madikizela, K. & Haupt, T. (2010). Influences on women’s choices of careers in

construction: A South African study. Australasian Journal of Construction Economics

and Building, 10(1/2):1–15.

Mahamid, I. (2011). Causes of contractors’ failure: Contractors’ view. Proceedings of

the 2nd International Conference on Construction and Project Management, IPEDR,

15, IACSIT Press, Singapore.

Makhura, S. M. (2011). An analysis of entrepreneurial competencies of the

owner/manager of emerging small contractor companies in the Construction

industry. Unpublished thesis. University of Witwatersrand, Johannesburg.

Martin, F. (2004). Business incubators and enterprise development: Neither tried nor

tested? Available from: www.emeraldinsight.com/journals.htm?articleid=1657149

(Accessed 11 October 2013).

155

Martin, L. & Root, D. (2010). Learning experiences for South African SMEs:

Interactions with established contractors. In: Egbu, C. (Ed.). Proceedings of the 26th

Annual ARCOM Conference, 6–8 September 2010: pp.675–684. Leeds: Association

of Researchers in Construction Management.

Marx, H.J. (2011). Key performance indicators measuring contractor satisfaction. In:

Egbu, C. & Lou, E.C.W. (Eds.). Proceedings of the 27th Annual ARCOM

Conference, 5–7 September 2011: 931–939. Bristol: Association of Researchers in

Construction Management,

Masadeh, M. (2012). Training, education, development and learning: What is the

difference? European Scientific Journal, 8(10):62–68.

Mayombe, C.B. (2009). An evaluation of the implementation of construction

learnership in the expanded public works programme: A case study of the eThekwini

vuk'uphile I, KwaZulu-Natal. Unpublished thesis. University of KwaZulu-Natal,

Pietermaritzburg.

Mazzarol, T., Reboud, S. & Tye, M. (2006). The outsider’s role in the strategic

development of the small firm: A study of mentoring with small business owner-

managers in Australia. Administrative Sciences Association of Canada (ASAC)

Annual Conference 4–7 June 2006, Banff.

Mbachu, J. & Nkado, R. (2006). Conceptual framework for assessment of client

needs and satisfaction in the building development process. Construction

Management and Economics, Vol 24:31–44.

Mbachu, J. (2012). Knowledge and skills required for contractors’ high productivity

and performance in construction project delivery: An exploratory study of the up-

Skilling needs of the New Zealand contractors In: Laryea, S., Agyepong, S.A.,

Leiringer, R. & Hughes, W. (Eds.). Proceedings of the 4th West Africa Built

Environment Research (WABER) Conference, 24–26 July 2012, Abuja, Nigeria,

859–869.

156

McCluskey, A. & Lalkhen, A.G. (2007). Statistics II: Central tendency and spread of

data. Available from: http://ceaccp.oxfordjournals.org/ (Accessed 14 May 2014).

McCutcheon, R. (2008). The generation of productive employment opportunities for

the unskilled: principles, potential & pitfalls of labour-intensive construction.

Proceedings of the 10th Path to Full Employment Conference / 15th National

Unemployment Conference 4–5 December 2008, Centre of Full Employment and

Equity (CofFEE) University of Newcastle, Australia.

McCutcheon, R.T. & Parkins, F.L.M.T. (2002). Capacity building in the transport and

development engineering at WITS University. Innovative Research and Education at

the Research Centre for Employment Creation in Construction. Towards Building

Capacity and Accelerating Delivery. Proceedings of the 21st Annual South African

Transport Conference, 15, 8 July 2002 in South Africa.

McKimm, J. Jollie, C. & Hatter, M. (2007). Mentoring: Theory and practice. Available

from: http://www.faculty.londondeanery.ac.uk/e-

learning/feedback/files/Mentoring_Theory_and_Practice.pdf (Accessed 18

December 2014).

McMullan, J. (2011). Contract administration principles: Guide to engineers.

McMullan Solicitors. Available from: http://www.mcmullansolicitors.com.au

(Accessed 5 June 2012).

Meerwald, A.M.L. (2013). Researcher/researched: Repositioning research

paradigms. Higher Education Research & Development, 32 (1):43–55.

Mhango, Y. (2010). Ghana: Annual economic outlook, the eve of oil production.

Standard Bank Group Limited: pp.1–17.

Miles, (2006). Descriptive statistics. Available from: http://www.sagepub.com/upm-

data/12706_02_Miles_Ch_02.pdf (Accessed 14 April 2014).

Miles, D. (1979). Financial planning for the small building contractor. London:

Intermediate Technology Publication.

157

Miles, D. (1996). The client/contractor relationship in labour-based construction and

maintenance. Labour-based technology — A review of current practice. Water,

Engineering and Development Centre (WEDC), Loughborough: Loughborough

University of Technology.

Miller, J. (1981). Develop an effective marketing plan for your construction company.

Step-by-step instructions with a sample plan showing how they are used. Jack Miller

Seminars for the Construction Industry, 1–4.

Miller, M. (1986). Reliability and validity. Graduate research methods. Available from:

http://www.michaeljmillerphd.com/res500_lecturenotes/reliability_and_validity.pdf

(Accessed 16 October 2014).

Mojapelo, J. & Rakale, T. & Gertzen D. (2001). Meeting the transport challenges in

Southern Africa. Proceedings of a conference 16–20 July held in Johannesburg.

Moodley, M. S. (2012). An investigation of the role of women in the South African

construction industry. Unpublished thesis. University of Johannesburg,

Johannesburg.

Moore, D. S. (2000). The basic practise of statistics. 2nd ed. New York: Freeman.

Moore, J. L, Dickson-Deane, C. & Galyen, K. (2011). E-Learning, online learning,

and distance learning environments: Are they the same? Internet and Higher

Education, Vol.14:129–135.

Mukanyima, A. (2012). An evaluation of the EPWP Vuk’upile Learnship programme

within Ekurhuleni Metropolitan Municipality. Unpublished thesis. University of

Witwatersrand, Johannesburg.

Murray, M. & Owen, M.A. (1991). Beyond the myths and magic of mentoring: How to

facilitate an effective mentoring programme. San Francisco: Wiley.Available from:

http://eu.wiley.com/WileyCDA/WileyTitle/productCd-0787956759.html (Accessed 11

October 2014).

158

Naoum, S.G. (2007). Dissertation research and writing for construction students. 2nd

ed.Oxford: Butterworth- Heinemann.

Natarajan, S.G. & Wyrick, A.D. (2011). Framework for implementing sustainable

practices in SMEs in the United States. Proceedings of the World Congress on

Engineering, Vol. 1 held in London, UK.

National Department of Public Works (NDPW). (2002). Realignment Strategy and

Management Plan for the ECDP. Pretoria: National Department of Public Works.

National Department of Public Works (NDPW). (2004). Contractor Incubator

Programme: Plan. National Department of Public Works. Pretoria: National

Department of Public Works.

National Department of Public Works (NDPW). (2008). Contractor Incubator

Programme. Pretoria: National Department of Public Works.

Ncwadi, M. R. & Dangalazana, T. (2005). An exploratory study into the challenges

facing the emerging contractors involved in the construction of low-cost housing in

Wells Estate and Ikamv’elihle townships in the Nelson Mandela metropole, South

Africa. World Congress on Housing Transforming Housing Environments through

Design, 27–30 September. Pretoria: South Africa.

Ngandu, S., Garcia, A.F. & Arndt, C. (2010). The economic influence of infrastructure

expenditure in South Africa: A multiplier and structural path analysis. Proceedings of

the Employment Promotion Programme and Trade & Industrial Policy Strategies

Conference, 27–29 October, Johannesburg, South Africa.

Nkado, R.N. & Mbachu, J.I.C. (2002). Investigations into causes of client

dissatisfaction in the South African building industry, and possible strategies for

improvement. Proceedings of the 1st International Conference of the CIB W107,

Stellenbosch, 11– 13 November: pp.349–357.

159

Ntuli, B. & Allopi, D. (2013). Capacity challenges facing civil engineering contractors

in Kwazulu - Natal, South Africa. International Journal of Engineering and Innovative

Technology, 2(11):90–97.

Nulty, D. D. (2008). The adequacy of response rates to online and paper surveys:

What can be done? Assessment and Evaluation in Higher Education, 33 (3):301–

314.

Odeyinka, H.A. & Kaka, A. (2005). An evaluation of contractors’ satisfaction with

payment terms influencing construction cash flow. Journal of Financial Management

of Property and Construction, 10 (3):171–180.

Ofori, G. & Toor, S.U.R. (2012). Leadership development for construction SMES.

Proceedings of the Engineering Project Organizations Conference, July 10–12

Rheden, the Netherlands.

Ofori, G. (2002). Challenges of construction industries in developing countries:

Lessons from various countries. Singapore: National University of Singapore.

Ofori, G. (2012). Developing the construction industry in Ghana: The case for a

central agency. Avialable from:

http://www.ghanatrade.gov.gh/file/Developing%20the%20Construction%20Industry%

20in%20Ghana%20BUILDING.pdf (Accessed 2 March 2014)

Olugboyega, A. (1997). Contractor development in Nigeria: Perceptions of

contractors and professionals. Construction Management and Economics, 15 (1):95–

108.

Ongori, H. & Nzonzo, J. C. (2011). Training and development practices in

organisation: An intervention to enhance organisational effectiveness. International

Journal of Engineering and Management Sciences, 2 (4):187–198.

Onwuegbuzie, A. J. & Combs, J. P. (2011). Data analysis in mixed research: A

primer. International Journal of Education, 3 (1):1–25.

160

Onwuegbuzie, A. J. & Collins, K. M. T. (2007). A typology of mixed methods sampling designs in social science research. The Qualitative Report, 12(2), 281-316. Available from http://www.nova.edu/ssss/QR/QR12-2/onwuegbuzie2.pdf (Accessed 18 November 2014)

Onwuegbuzie, A. J. & Leech, N. L. (2005). On becoming a pragmatist researcher:

The importance of combining quantitative and qualitative research methodologies.

International Journal of Social Research Methodology, 8 (5):375–387.

Organisation for Economic Co-operation and Development (OECD). (2002).

Management training in SMEs. OECD: pp. 4–189.

Organisation for Economic Co-operation and Development (OECD). (2008). Trade

and regulations: The case of construction services. OECD: pp. 3-37.

Osei, V. (2013). The construction industry and its linkages to the Ghanaian

economy-polices to improve the sector’s performance. International Journal of

Development and Economic Sustainability, 1 (1):56–72.

Özlem, Ö. (2001). Sources of competitive advantage of Turkish construction

companies in international markets. Construction Management and Economics,

19(2):135–144.

Pandya, M. V. (2012). Comparative analysis of development of SMEs in developed

and developing countries. Proceedings of the International Conference on Business

and Management, 6–7 September, Phuket, Thailand.

Paradise, A. (2007). State of the industry: ASTD’s annual review of trends in

workplace learning and performance. Alexandria, VA: ASTD.

Paz, R. (2006). How to go from good to great in the construction industry,:1–3.

Avialable from: http://www.lorman.com/resources/how-to-go-from-good-to-great-in-

the-construction-industry-15646. (Accessed 13 June 2014).

PriceWaterhouseCoopers (PWC). (2013). Highlighting trends in the South African

construction industry. SA construction. Available from:

http://www.pwc.co.za/construction (Accessed 20 March 2014).

161

Pompa, C. (2012). Literature review on enterprise mentoring. Available from:

http://partnerplatform.org/?dk6sxm5w (Accessed 17 December 2014).

Qongqo, P. N. & Milford, R. V. (2006). Assessing supply and demand for emerging

contractor development programmes. Available at:

http://www.researchgate.net/publication/237445153_ASSESSING_SUPPLY_AND_D

EMAND_FOR_EMERGING_CONTRACTOR_DEVELOPMENT_PROGRAMMES

(Accessed 13 October 2015).

Raftery, J., Pasadilla, B., Y. H. Chiang, Y. H., Hui E. C. M. & Tang B. S. (1998).

Globalization and construction industry development: Implications of recent

developments in the construction sector in Asia. Construction Management and

Economics, 16(6):729–737.

Republic of South Africa. (2003). Broad Based Black Economic Empowerment Act

(No 53 of 2003). Pretoria: Government Printer.

Rogerson, C.M. (2010). Road construction and small enterprise development: The

experience of the N4 Maputo corridor. Development Southern Africa, 17(4):535–566.

Roodt, M.J. (2008). The impact of regional integration initiatives and investment in a

southern African cross border region: The Maputo development corridor. African

Sociological Review, 12(1):90–104.

Roth, S.A. (2007). Understanding pricing objectives and strategies. Pennsylvania

State University. Available from: http://extension.psu.edu/publications/ua441

(Accessed 13 October 2015)

Rwigema, H. & Venter, R. (2004). Advanced entrepreneurship. Cape Town: Oxford

University Press.

Salas, E. & Cannon-Bowers, J. A. (2001). The science of training: A decade of

progress. Annual Review of Psychology, 52:471–99.

162

Sale, J. E. M., Lohfeld, L. H. & Brazil, K. (2002). Revisiting the quantitative-

qualitative debate: Implications for mixed-methods research. Quality & Quantity,

36:43–53.

Sandelowski, M. (2000). Focus on research methods, combining qualitative and

quantitative sampling, data collection, and analysis techniques in mixed-method

studies. Research in Nursing and Health, 23:246–255.

Santamaria, J. O. (2003). Mentoring develops high-potential employees. Asia Africa

Intelligence Wire.Available from:

https://www.google.co.za/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cad=rja&u

act=8&ved=0ahUKEwiWnefM-

dTRAhUHB8AKHRj6C4EQFggbMAA&url=http%3A%2F%2Fwww.journalofleadershi

ped.org%2Fattachments%2Farticle%2F137%2FJOLE_4_1_Inzer_Crawford.pdf&usg

=AFQjCNGrgs037Mxu6wLGvAT6SSpaAk9RFQ&sig2=_bvrbCet63Dz_A3un2zs6w&

bvm=bv.144224172,d.bGs. (Accessed 7 August 2015)

Satchwell, I. (2012). Building mining services clusters in Australia. Peru International

Gold Symposium and Silver Forum. Available at: http://im4dc.org/wp-

content/uploads/2012/01/Peru-InternationalGold-Symposium-and-Silver-Forum-

Building-Mining-Services-Clusters-in-Australia.pdf (Accessed 13 October 2015).

Scheiber, J. & Dickson, M. (2007). Measures of central tendency of grouped data,

standard deviation, histograms and frequency polygons. Johannesburg: University of

the Witwatersrand.

Sebone, M.F. & Barry, M. L. (2009). Towards determining critical success factors for

SME electrical contractors in the construction industry in South Africa. South African

Journal of Industrial Engineering, 20(1):185–195.

Seth, C.S. (2004). Training of small scale contractors for rural road maintenance in

Lesotho. Some lessons from experience. Available from:

http://www.ssatp.org/sites/ssatp/files/publications/SSATP-

TechnicalNotes/ATTN36.pdf (Accessed 23 December 2013).

163

Shields, L. & Twycross, A. (2003). The difference between quantitative and

qualitative research. Paediatric Nursing, 15 (9):1.

Shrivastava, P. (2005). Work embedded E-Learning pp.277-287. Available from:

http://paulshrivastava.com/Research%20Publications%20Directory%5CWork%20Em

bedded%20e-learning.pdf (Accessed 12 October 2013).

Sin, K.C. (2010). The success stories of Malaysian SMEs in promoting and

penetrating global markets through business competitiveness strategies.

Copenhagen Discussion Papers. Paper presented at KISMEC – ASEAN and AOTS

JAPAN TRAINING: Empowering SMEs Business Competitiveness, 20 – 28 August

2008 at Swiss Inn Hotel, Sungei Petani, Kedah, Malaysia.

Skitmore, M. & Smyth, H. (2006). Pricing construction work: A marketing viewpoint.

Construction Management and Economics, 25(6):619–630.

Smallwood, J. J. (2010). The image of contractors: A South African case study. In:

Egbu, C. (Ed.). Proceedings of the 26th Annual ARCOM Conference, 6–8

September 2010, Leeds, UK, Association of Researchers in Construction

Management, pp.939–946.

Söderbaum, F. (2001). Institutional aspects of the Maputo Development Corridor,

Journal of Modern African Studies, 1 (47):1–28.

Statistics South Africa. (2004). Construction industry. Pretoria: Statistics South

Africa.

Statistics South Africa. (2007). Construction industry. Pretoria: Statistics South

Africa.

Statistics South Africa. (2012). Gross domestic product, First quarter. Pretoria:

Statistics South Africa.

Stewart, R. A., Miller, C., Mohamed, S. & Packham, G. (2003). Sustainable

development of construction small and medium enterprises (SMEs): IT impediments

focus: Available at:

164

http://www.researchgate.net/profile/Rodney_Stewart/publication/228466892_Sustain

able_development_of_construction_small_and_medium_enterprises_(SMEs)_IT_im

pediments_focus/links/09e415125548e45ede000000.pdf (Accessed 13 October

2015).

Storey, D. J. (2008). Entrepreneurship and SME policy. World Entrepreneurship

Forum, Warwick Business School, Available from:

http://scholar.google.co.za/scholar?q=Storey,+D.+J.+(2008).+Entrepreneurship+and

+SME+policy.+World+Entrepreneurship+Forum,.+Warwick+Business+School&hl=en

&as_sdt=0&as_vis=1&oi=scholart&sa=X&ved=0ahUKEwi8rPnG-

tTRAhVoD8AKHSKtD1cQgQMIFjAA. (Accessed 2 October 2015).

Suraji, A., Surarso, G. W. & Supriatna, Y. (2010). The construction sector of

Indonesia. National Construction Services Development Board, Available from:

https://www.google.co.za/url?sa=t&rct=j&q=&esrc=s&source=web&cd=2&cad=rja&u

act=8&ved=0ahUKEwjh7N_3-

tTRAhVlCcAKHeaFCD8QFggdMAE&url=http%3A%2F%2Fasiaconst.com%2Fpast_c

onference%2Fconference%2F15th%2F3Indonesia.pdf&usg=AFQjCNG2KWA9Lpcw

v54MICbb7tKGo9S8nQ&sig2=OGeVi2iafkq5kyN8GWs81Q&bvm=bv.144224172,d.b

Gs. (Accessed 15 April 2014).

Svensson, E. (2001). Guidelines to statistical evaluation of data from rating scale

and questionnaires. Journal of Rehabilitation Medicine, 33:47–48.

Tashakkori, A. & Teddlie, C (2003). Handbook of mixed methods in social and

behavioural research. London: Sage.

Tennant C., Boonkrong M., & Roberts P.A.B (2002). The design of a training

programme.

Texas Department of Transport. (2013). Construction Contract Administration

Manual. Avialable from:

https://www.google.co.za/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cad=rja&u

act=8&ved=0ahUKEwiK6MSs-

9TRAhWEIsAKHUxCCEMQFggYMAA&url=http%3A%2F%2Fonlinemanuals.txdot.go

165

v%2Ftxdotmanuals%2Fcah%2Fcah.pdf&usg=AFQjCNHRDH7Xsh2SDPAkl64Ic9udc

_kzmQ&sig2=RpjIg8yFoJK8qGpG7JFm2Q&bvm=bv.144224172,d.bGs. (Accessed

14 January 2015)

The South African Council for the Project and Construction Management Professions

(2012). Board Notice 8 of 2012. No.34989. Available from:

http://www.sacpcmp.org.za (Accessed 2 November 2013).

Thierstein, A. & Wilhelm, B. (2001). Incubator, technology and innovation centres in

Switzerland: Features and policy Implications. Entrepreneurship and Regional

Development, 13(4):315–331

Thisted, R. A. (2010). What is a P-value? Departments of Statistics, Health Studies,

and Anaesthesia & Critical Care, the University of Chicago, Chicago, IL. Available

from: http://www.stat.uchicago.edu/~thisted (Accessed 16 October 2014).

Thorpe, D. & Ryan, N. (2006). Improving technology transfer in the Australian

construction industry. In: Brown, K., Hampson K. & Brandon P. (Eds.). Clients driving

construction innovation – moving ideas into practice. Brisbane: CRC for

Construction: pp. 303–312.

Thorpe, D. & Ryan, N. (2007). Responding to global issues: Sustainability and

innovation in the Australian SME residential building construction sector. In:

ICCPM/ICCEM 2007 Proceedings: Singapore: Building and Construction Authority,

Nanyang Technological University, Korea Institute of Construction Engineering and

Management. (ICCPM/ICCEM 2007: 5th International Conference on Construction

Project Management, 2nd International Conference on Construction Engineering and

Management, 1–2 March 2007, Singapore).

Thurmond, V.A. (2001). The point of triangulation. Journal of Nursing Scholarship, 33(3), 253 -258.

Thwala, W. D. & Mvubu, M. (2008). Current challenges and problems facing small

and medium size contractors in Swaziland. African Journal of Business

Management, 2(5):93–98.

166

Thwala, W. D. & Phaladi, M. J. (2009). An exploratory study of problems facing small

contractors in the North West province of South Africa. African Journal of Business

Management, 3(10):533–539.

United States Office of Personnel Management (USOPM). (2008). Best practices:

Mentoring. Available from: http://www.opm.gov/hrd/lead/BestPractices-mentoring.pdf

(Accessed 18 December 2014).

Uriyo, G. A. & Jere, D. (2003). Contractor training in the millennium, CRB training

achievements, experiences and challenges. Available from:

http://www.ncc.or.tz/ctm.pdf (Accessed 23 December 2012).

Van der Kuip, I. & Verheul, I. (2003). Early development of entrepreneurial qualities:

The role of initial education. Available from: www.entrepreneurship-sme.eu/pdf-

ez/n200311.pdf. (Accessed 3 March 2013).

Van Vuuren, D. & Maree, A. (2008). Survey methods in market and media research:

Applied methods for the social sciences. In: Terre Blanche, M. & Durrheim, K. (Rds.)

Research in practice, Cape Town: UCT Press.

Vanderstraeten, J. & Matthyssen, P. (2005). Measuring the performance of business

incubators, a critical analysis of effectiveness approaches and performance

measurement systems. Available from:

http://www.researchgate.net/publication/229045580_Measuring_the_performance_of

_business_incubators_A_critical_analysis_of_effectiveness_approaches_and_perfor

mance_measurement_systems (Accessed 12 October 2015).

Verwey, I. & Havemann, G. (2001). A project analysis of employment creation

construction SMME involvement in DBSA funded projects –The Involvement of

Women in the Construction Sector WORK2001 Conference Proceedings of the First

International Conference on Employment Creation in Development 2–5 April,

Johannesburg, South Africa.

167

Wasi, D., Bridge, A. & Skitmore, R. M. (2001). Factors affecting the performance of

small indigenous contractors in Papua New Guinea. The Australian Journal of

Construction Economics and Building, 1(1):80.

Watermeyer, R. B. (1995). Evaluating employment and community opportunities

presented by building and construction projects. Employment Intensive Construction

15th Annual Transportation Convention, University of Pretoria.

Watermeyer, R. B. (2004). Facilitating sustainable development through public and

donor regimes: Tools and techniques. Public Procurement Law Review, 1:30– 55.

Watermeyer, R., Jacquet, A. & Noyana, C. (2001). Developing the capacity of

targeted enterprises in contractor development programmes. Proceedings of the

Regional Conference on Developing the Construction Industries of Southern Africa,

23–25 April, Pretoria, South Africa.

Watermeyer, R., Jacquet, A. & Noyana, C. (2001). Developing the capacity of

targeted enterprises in contractor development programmes. Proceedings of

Regional Conference on Developing the Construction Industries of Southern Africa,

23–25 April 2001, Pretoria.

Weddikkara, C. & Devapriya, K. (2001). Demand and supply trends and construction

industry development: A case study in the Sri Lankan construction industry. The

Australian Journal of Construction Economics and Building, 1(1):91–103.

Weiner, J. (2007). Measurement: Reliability and validity measures. Available from:

http://ocw.jhsph.edu/courses/hsre/PDFs/HSRE_lect7_weiner.pdf (Accessed 16

October 2014).

Wells, J. & Hawkins, J. (2008). Increasing local content in the procurement of

infrastructure projects in low income countries. Available from:

http://www.engineersagainstpoverty.org/documentdownload.axd?documentresourcei

d=23 (Accessed 4 July 2013).

168

Wharton, A. & Payne, D. (2003). Promoting innovation in construction SMEs: An EU

case study. Sustainable building and construction. UNEP Industry and Environment,

April-September 2003: pp.76–78.

Whonderr-Arthur, J. (2009). Financial Management in SME. Available from:

ezinearticles.com › Business › Small Business (Accessed 20 December 2012

Wibowo, M.A. (2009). The contribution of the construction industry to the economy of

Indonesia: A systemic approach, 1–9. Available from:

http://eprints.undip.ac.id/387/1/Agung_Wibowo.pdf (Accessed 20 July 2013)

Wilcox, R. R. & Keselman, H. J. (2003). Modern robust data analysis methods:

Measures of central tendency. American Psychological Association, 8(3):254–274.

Wood, S. (2004). Fully on-the-job training, experiences and steps ahead. Available

from: http://www.ncver.edu.au (Accessed 20 November 2013).

Workplace Gender Equality Agency (WGEA). (2013). Training and development,

Establish and maintain effective mentoring programs. Available from:

http://www.wgea.gov.au (Accessed 18 December 2014).

World Bank. (2003). Importance of SMEs and the role of public support in promoting

sme development. Creating a conducive legal and regulatory framework for small

and medium enterprise development in Russia. A Policy Dialogue Workshop, 14–16

September, St. Petersburg, Russia.

Yammarino, F. J., Skinner, S. J. & Childers, T. L. (1991). Understanding mail survey

response behaviour. American Association for Public Opinion Research, 55:613–

639.

Yeasmin, S. & Rahman, K. F (2012). Triangulation research method as the tool of

social science research. BUP Journal, 1(1):154–163

Zachary, W., Cannon-Bowers, J., Bilazarian, P., Krecker, D., Lardieri, P. & Burns, J.

(1999). The advanced embedded training system: An intelligent embedded tutoring

169

system for tactical team training. International Journal of Artificial Intelligence in

Education (1999), 10, 257-277

170

APPENDICES

APPENDIX A – QUESTIONNAIRE

20 January 2014

Dear Sir/Madam

Performance evaluation of Contractor Development Programmes – A Contractor

Perception Survey

I am a student of the University of Johannesburg and currently studying for a Master’s

degree in Construction Management in the Department of Quantity Surveying and

Construction Management.

In fulfilment of my degree requirements I am currently undertaking a research into how

contractors feel about contractor development programmes in South Africa.

You participated in the contractor development programme and as such I kindly

request your taking time to complete the questionnaire about your impression of the

training programme.

The questionnaire is composed of seven (7) pages and it should take no longer than

10 minutes of your time to complete. Your contribution towards this research is highly

valued.

Please do not enter your name, contact details or any identification marks on the

questionnaire in order for you to remain anonymous.

171

Please send the completed questionnaire back to me by email on or before 14t

February 2014.

Should you have any queries or comments regarding this survey, please contact me

on 076 750 9263 or email at [email protected]

Thank you in advance for your valuable time.

Yours sincerely

Ambrose Dapaah

PLEASE ANSWER THE FOLLOWING QUESTIONS BY TICKING (✓) THE

RELEVANT BLOCK OR WRITING DOWN YOUR ANSWER IN THE SPACE

PROVIDED.

EXAMPLE of how to complete this questionnaire:

What is your gender?

If you are male:

Male ✓

Female

We acknowledge the sensitive nature of the information provided below: however, all

information given will be treated in the strictest confidence and no comments will be

172

attributed to any one person or organization. We once again assure you that your

response and all information provided will remain anonymous.

Company’s Details

This section of the questionnaire refers to your company’s background information.

1. What is your gender?

Male

Female

2. Do you have any physical disabilities?

Yes

No

3. Are you a previously disadvantaged individual (PDI)?

Yes

No

4. To which ethnic group do you belong?

173

African

Coloured

White

Asian/Indian

Others

5. What is your age?

6. How many people does your company employ?

Less than 10

10 - 90

100 – 200

201 or more

7. In which province is your company based?

174

Gauteng

Kwa-Zulu Natal

Western Cape

Eastern Cape

North West

Limpopo

Mpumalanga

Free State

North Cape

8. Which of the following contractor development programmes have you attended?

Vukuzakhe Contractor Development Programme

Masakhe Contractor Development Programme (KwaZulu-Natal DPW)

EPWP – Vuk’uphile Learnership Programme

Khuthaza Contractor Development

SCI Programme

175

Eskom Construction Academy

Polokwane Local Municipality Contractor Development Programme

Mpumalanga DPWR&T Programme (Sakh’abakhi Programme)

Free State Depart. of Public Works and Rural Development

Programme

Western Cape Siyanyuka Contractor Enhancement Programme

Northern Cape DR& Public Works Contractor Development

Programme

Free State Depart. of Police, Roads and Transport contractor

Programme

Others

9. In which year did you attend the programme? Please fill in the year

10. In which year did you complete the programme? Please fill in the year

11. What was your CIDB grading before the training? Please fill in your CIDB grade

176

12. What is your CIDB grading after the training? Please fill in your CIDB grade

IMPLEMENTATION OF THE CDP

13. To what extent do you agree with the following description of the programme?

ID IMPLEMENTATION OF THE CDP

Str

on

gly

Ag

ree

Ag

ree

Dis

ag

ree

Str

on

gly

Dis

ag

ree

Not

Su

re

1 The trainers delivered and explained the

training clearly

2 The time allowed for the classroom work was

appropriate

3 The site work was adequate

4 The mentoring process were helpful

5 Continuous mentorship will be very helpful to

successful CDP implementation

6 The materials given at the training were

effective and helpful

7 There was a single point of contact for

communication between trainers and trainees

177

8 The training was scheduled and

communicated to clearly

9 The training was executed according to the

predetermine schedule

10 The training met the set objectives

14. Any other comments on your decision

CDP and CONTRACTOR EMPOWERMENT AND DEVELOPMENT

15. To what extent do you agree with the following description about the training?

ID IMPROVED MANAGEMENT SKILLS

Str

on

gly

Ag

ree

Ag

ree

Dis

ag

ree

Str

on

gly

Dis

ag

ree

Not

Su

re

1 The training has given me more confidence in

my managerial skills

2 The training has improved my knowledge on

estimating and tendering

3 The training has broadened my knowledge on

project planning

4 The training has enhanced my knowledge on

financial planning

5 The training has enhanced my confidence in

contract laws and claims

6 The training has improved my ability to market

my services to clients

178

7 The training has enhanced my knowledge of

effective quality control

8 The training has enabled me to complete

projects within the contract period

9 The training has assisted me to complete

projects within project budget

ID CONTRACTOR UPGRADE

Str

on

gly

Ag

ree

Ag

ree

Dis

ag

ree

Str

on

gly

Dis

ag

ree

Not

Su

re

1 The training has helped me improve my CIDB

grading

2 The training has assisted in the growth of my

company’s income

3 The training has enabled me the opportunity to

bid for bigger projects

4 The training has helped my company in getting

consistent work flow

5 The training has enabled my company to

increase the number employees

ID PARTICIPATION OF PDI’s

Str

ong

ly

Ag

ree

Ag

ree

Dis

agre

e

Str

ong

ly

Dis

agre

e

No

t S

ure

1 The training has given me access to register

with CIDB

179

2

The training has enhanced my chances of

tendering for jobs that I couldn’t have tendered

for

3 The training has afforded me the opportunity

to get more contracts

4 The training has given financial institutions the

confidence to assist me

5 The training has encouraged clients to pay me

promptly to boost my cash flow

ID CONTRACTOR SATISFACTION

Str

ong

ly

Ag

ree

Ag

ree

Dis

agre

e

Str

ong

ly

Dis

agre

e

No

t S

ure

1 The training programme generally met my

expectations

2 The training programme is worth the cost of

attending

3 The training has enhanced my understanding

of the construction environment

4 The training has assisted me to avoid penalties

due to late completion of work

5 The training has enhanced my relationship

with my clients

6 The training has helped me reduce complaints

about the quality of my work

180

7 The training has helped improve my

relationship with my employees

8 The training would have been better delivered

through the Internet

9 The training was conducted according to our

individual experience

10 I will be attending the training in future

11 I will definitely recommend the training to

someone else

16. Any other comments on your decision

17. Are the development programmes a complete waste of time in your view?

Yes

No

18. Any requests and/or suggestions about the contractor development programme

181

FOR ANY OTHER INFORMATION PLEASE CONTACT ME ON 076 750 9263

182

APPENDIX B – STRUCTURED INTERVIEWS – CONSULTANTS

PLEASE ANSWER THE FOLLOWING QUESTIONS BY TICKING (✓) THE

RELEVANT BLOCK OR WRITING DOWN YOUR ANSWER IN THE SPACE

PROVIDED.

EXAMPLE of how to complete this questionnaire:

Has contractor performance improved?

If yes:

Yes ✓

No

Consultants were asked the following questions in a pilot study to test the performance

of SMME Contractors.

1. Have you worked with SMME contractors who have undergone CDP?

183

Yes

No

2. If ‘Yes’, do you think they performed better than those that did not undergo the

CDP?

Yes

No

3. If ‘No’ to Question 2, do you think mentorship will assist in improving contractors’

performance?

Yes

No

4. Should mentorship be made compulsory in your view?

Yes

No

184

APPENDIX C – STRUCTURED INTERVIEWS – CONTRACTORS

PLEASE ANSWER THE FOLLOWING QUESTIONS BY TICKING (✓) THE

RELEVANT BLOCK OR WRITING DOWN YOUR ANSWER IN THE SPACE

PROVIDED.

EXAMPLE of how to complete this questionnaire:

Were you told about mentorship during your CDP?

Yes ✓

No

We acknowledge the sensitive nature of the information provided below: however, all

information given will be treated in the strictest confidence and no comments will be

attributed to any one person or organization. We once again assure you that your

response and all information provided will remain anonymous.

Contractors were asked the following questions in a pilot study to test their views on

mentorship.

1. Were you mentored during the CDP?

185

Yes

No

2. If ‘yes’, did you like it?

Yes

No

3. If ‘No’ to Question 1, were you told about mentorship during CDP?

Yes

No

4. If ‘No’ to Question 2, was the mentorship programme free/subsidized/paid by

you?

Free

186

Subsidised

Paid by me

5 Did the mentorship programme help increase your CIDB grading?

Yes

No

6 Will you accept financial assistance if your mentor has to be a signatory on your

bank account?

Yes

No

7 If you paid for a mentorship programme, do you think it is worth the money

paid?

Yes

No