1 An Overview of the Commissioning Cycle Presented by Norman Kirwan-Ward Global Completions and Commissioning Manager Sponsored by the IICA and EA 2 Agenda Completions and Commissioning Systems Completion A Framework for Completions and Commissioning Systems Commissioning Database

Upload: cartar

Post on 04-Sep-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 01-Mar-13

    1

    1

    An Overview of the Commissioning CyclePresented by Norman Kirwan-WardGlobal Completions and Commissioning Manager

    Sponsored by the IICA and EA

    2

    Agenda

    Completions and Commissioning

    Systems Completion

    A Framework for Completions and Commissioning

    Systems Commissioning Database

  • 01-Mar-13

    2

    3

    Completions

    The management, development, planning and preparation for the final stages of a project, when new or upgraded plant and equipment is checked, tested, commissioned and started up to first time operational status.

    Completions begin during the early stages of a project where budget and schedule, organisational structure, general documentation and information requirements, supplier deliverables and site requirements are identified. It continues through all the other stages culminating in the completed and first time operational facility being turned over to the Operator for care, custody and control.

    4

    Commissioning

    The checks, tests and demonstration that prove the plant and equipment have been built to the plans and specifications and perform to the design intent. Commissioning can also be described as the field tasks of the completions process.

    Field commissioning commences during the construction phase (Commissioning Stage 1 - Mechanical Completion Constriction Verification etc.) and culminates with the facility started up to first time operational status.

  • 01-Mar-13

    3

    5

    A Framework for Completions

    Failure to PLAN is a plan for Failure

    A framework for Completions (and Commissioning) is in effect a master plan for completions

    Lets walk through a Completions Framework

    This master plan aligns with most of the global top shelf Operators expectation for a structured and considered commissioning process

    6

    Systems Completion Concept

    An important part of successful commissioning is to break down the plant into System and Sub-systems with clearly defined boundary limits directly related to the start-up sequence

    System Completions facilitates the progressive early start up in planned stages.

    This is a proven methodology that introduces inherent efficiencies into the commissioning process.

    The greatest hurdle to Systems Completions is the transition by the constructor from Area Build to System Delivery

  • 01-Mar-13

    4

    7

    Completions Framework

    Identify Evaluate Define

    Detail

    Engineering &

    Procurement

    Stage 1

    Mechanical

    Completion

    Stage 2

    Function

    Testing

    Stage 3

    System

    Commissioning

    Stage 4

    Start Up &

    Ramp Up

    Operation &

    Performance

    Testing

    Interim

    Facility

    Turnover

    IDENTIFY EVALUATE DEFINE EXECUTE OPERATE

    IDENTIFY

    (Pre-feasibility

    studies)

    EVALUATE

    (Conceptual

    Engineering)

    DETAIL

    ENGINEERING

    & DESIGN

    DEFINE

    (Front End Eng

    & Design; Cost

    Estimating &

    Execution Plan)

    CONSTRUCTION / COMPLETIONS ENGINEERING SUPPORT

    Dry Commissioning Wet/Live Commissioning

    Early Procurement

    ActivityProcurement

    Early FAT

    Activity

    CONSTRUCTION DEVELOPMENT &

    PREPARATIONS

    Factory Acceptance Testing

    CONSTRUCTION

    CONTRIBUTION

    Early Construction

    Activity

    FABRICATION , INSTALLATION

    & CONSTRUCTION

    COMPLETIONS

    CONTRIBUTION

    COMPLETIONS DEVELOPMENT &

    PREPARATIONS

    Commissioning STAGE 1

    Commissioning STAGE 2

    Commissioning STAGE 3

    Commissioning STAGE 4

    Attend to Punch Lists

    Operation &

    Performance Testing

    Facilities TurnoverCompletions Manpower

    Opportunity to Manage Risk

    COMPANY PROJECT PHASES Support across all project delivery phases

    COMPLETION FRAMEWORK STAGES

    COMPLETION FRAMEWORK RELATIONSHIPS

    PreFEED - input

    to scope

    development,

    strategies and

    budget and

    schedule

    FEED - Input into HSE strategies and plans

    Input to project scope development & strategies

    Contribution to budget and schedule

    First Pass Systemisation & start up sequence

    Coordinate data requirements from engineering

    Risk and Constructability reviews

    Develop the Completions Strategy and Management Plan(s)

    Identify Completions Interfaces (including 3rd parties)

    Identify REQ needing Commissioning input(including FAT)

    Identify field commissioning opportunities for modular units

    Identify a CMT

    DETAIL DESIGN & PROCURE

    interfacing with engineering and design

    finalise collection of engineering data,

    commence CMT population,

    complete completions documentation,

    finalise site preparations

    Issue the Field Commissioning Documentation.

    Special attention will be given to selected engineering

    requisitions that require FAT.

    8

    Commissioning - stages

    Commissioning Stage 1 (MC) - Field checking and testing of individual items of equipment to confirm compliance with drawings, instructions and specifications- single discipline activity, carried out on un-energised static

    tagged items (device by device)- transition from Area Build to System Delivery- Controlled by A Check sheets; managed by CMT

    Commissioning Stage 2 (FT) - live testing- PTW comes into play introduction of energy- verification equipment and loops are functional - Controlled by B Check sheets; managed by CMT

  • 01-Mar-13

    5

    9

    Commissioning - stages

    Commissioning Stage 3 (SC) - multi-discipline- Tests and measurements to prepare systems to ready for start

    up or introduce product- Operations participation mandatory- Controlled by purpose written procedures; managed by CMT

    Ready for Start Up Milestone (RFSU) Confirmation facility is ready for start up- Commissioning complete- Operator ready- PSSRs undertaken and pre-start walk downs completed- Controlled by purpose written procedures; managed by CMT

    10

    Commissioning - stagesCommissioning Stage 4 (SU) - Introduction of product, start up and steady, controlled ramp up to first time operation- Controlled by purpose written procedures; managed by CMT - Undertaken by Operator; guidance from commissioning team

    Operation and Performance Tests defined tests and demonstrations to confirm the facility meets the contract and design parameters. - Controlled by purpose written procedures- Undertaken by Operator using their operating procedures

    Interim Facility Turnover - Formal turn over of the facility to the Operator for care, custody and control pending the formal close out of the project

  • 01-Mar-13

    6

    11

    Completions Framework

    SUMMARY Enables a structured approach Provides the opportunity to minimize risk Can be adapted and applied to different types of WorleyParsons

    projects. Segregates a project into identifiable and measurable

    completions stages Identifies the tasks, control documents, deliverables and risks for

    each stage Provides guidance for managing the completions and

    commissioning activities during each stage Identifies the transition from one stage to another Promotes cooperation and collaboration

    12

    Systems Commissioning Database- SCDB or CMT -

    FUNCTION Systematic technical assurance approach to completing projects Repository of all Completion data Supports the Completions Framework Provides comprehensive turnover packages

    VALUES Improves technical assurance Complete electronic documentation speeds up system turnover Customized turnover packages Equipment preservation management

    MOST POPULAR SYSTEMS WinPCS; PIMS-CMS; QEDI-GoCMS; ORBIT

  • 01-Mar-13

    7

    13

    Completions Framework

    Identify Evaluate Define

    Detail

    Engineering &

    Procurement

    Stage 1

    Mechanical

    Completion

    Stage 2

    Function

    Testing

    Stage 3

    System

    Commissioning

    Stage 4

    Start Up &

    Ramp Up

    Operation &

    Performance

    Testing

    Interim

    Facility

    Turnover

    IDENTIFY EVALUATE DEFINE EXECUTE OPERATE

    IDENTIFY

    (Pre-feasibility

    studies)

    EVALUATE

    (Conceptual

    Engineering)

    DETAIL

    ENGINEERING

    & DESIGN

    DEFINE

    (Front End Eng

    & Design; Cost

    Estimating &

    Execution Plan)

    CONSTRUCTION / COMPLETIONS ENGINEERING SUPPORT

    Dry Commissioning Wet/Live Commissioning

    Early Procurement

    ActivityProcurement

    Early FAT

    Activity

    CONSTRUCTION DEVELOPMENT &

    PREPARATIONS

    Factory Acceptance Testing

    CONSTRUCTION

    CONTRIBUTION

    Early Construction

    Activity

    FABRICATION , INSTALLATION

    & CONSTRUCTION

    COMPLETIONS

    CONTRIBUTION

    COMPLETIONS DEVELOPMENT &

    PREPARATIONS

    Commissioning STAGE 1

    Commissioning STAGE 2

    Commissioning STAGE 3

    Commissioning STAGE 4

    Attend to Punch Lists

    Operation &

    Performance Testing

    Facilities TurnoverCompletions Manpower

    Opportunity to Manage Risk

    COMPANY PROJECT PHASES Support across all project delivery phases

    WORLEYPARSONS COMPELTION FRAMEWORK STAGES

    COMPANY COMPELTION FRAMEWORK RELATIONSHIPS

    PreFEED - input

    to scope

    development,

    strategies and

    budget and

    schedule

    FEED - Input into HSE strategies and plans

    Input to project scope development & strategies

    Contribution to budget and schedule

    First Pass Systemisation & start up sequence

    Coordinate data requirements from engineering

    Risk and Constructability reviews

    Develop the Completions Strategy and Management Plan(s)

    Identify Completions Interfaces (including 3rd parties)

    Identify REQ needing Commissioning input(including FAT)

    Identify field commissioning opportunities for modular units

    Identify a CMT

    DETAIL DESIGN & PROCURE

    interfacing with engineering and design

    finalise collection of engineering data,

    commence CMT population,

    complete completions documentation,

    finalise site preparations

    Issue the Field Commissioning Documentation.

    Special attention will be given to selected engineering

    requisitions that require FAT.

    14

    SCDB Structure

  • 01-Mar-13

    8

    15

    CMT Screen ShotDynamic System

    readiness display

    SubSystem

    Summary

    SubSystem

    Details Tab

    16

    CMT Reports