do real options really have any value

Upload: mohi-asad

Post on 07-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Do Real Options Really Have Any Value

    1/22

    Do Real Options really have any value?

    DO REAL OPTIONS REALLY HAVE ANY

    VALUE?

    A DEMO OF OPTION TO DELAY FOR A POWER

    GENERATION PROJECT

    Mohiuddin Asad

    MBA(UK), ACCA, CMA, CIA, CFE, FFA, CCSA,

    Mohiuddin Asad 1

    1

  • 8/3/2019 Do Real Options Really Have Any Value

    2/22

    Do Real Options really have any value?

    Introduction

    In this article, author has designed a real-life example to demonstrate

    evaluation of real options. He has selected a Power Generators

    Company which is reviewing an Option to delay for a special solar

    power generators project. Author has collected current data from

    market and has made realistic assumptions about future cash flows,

    volatility and time horizon. Based on this information, he has first

    calculated the value of project using discounted cash flow techniques

    and then calculated the value of the project by real option valuation

    techniques, using Black-Scholes model. He has used excel

    spreadsheets for above computations and has varied critical inputs to

    demonstrate their impact on net present value (NPV) and real option

    value which is supported by graphical illustrations also.

    In the final section, Author has discussed the difference between NPV

    and real option value, explaining why or why not one should always be

    greater than the other and which variables affect the difference

    between these two valuations. Finally, he has assessed the reliability of

    the conclusions obtained using NPV versus real options approach.

    Mohiuddin Asad 2

    2

  • 8/3/2019 Do Real Options Really Have Any Value

    3/22

    Do Real Options really have any value?

    Overview of the Project

    ABC Company is a medium sized limited liability company which was

    incorporated in 1990 in a Middle eastern country. It produces and sells

    specialized Power generators, ranging from 10kva to 600kva. ABC is

    now considering a project to produce and sell solar energy power

    generators which shall mainly be used in remote parts of the country.

    Accordingly, a Three year project named Project solar is under

    review. The project will cost $80 million and is expected to generate

    cash flows of $34.12 million per year for three years. ABCs weighted

    average cost of capital (WACC) is 8% which is same as its required rate

    of return but considering risk of the project, it has added a risk

    premium of 2% so the adjusted required rate of return is 10%. Current

    risk-free rate for three years is 1.06% which is derived from latest US

    treasury bills rate. Marketing department of ABC has carried out a

    detailed market research, based on which they have forecasted that

    that there is a 28% chance of high demand in which case, future cash

    flows shall be $50 million per year. There is a 43% chance of average

    demand, with future cash flows of $36 million per year and a 29%

    chance of low demand with future cash flows of $16 million per year

    only. The management of ABC is very concerned about future

    prospects of the project. Though the project looks feasible and is

    expected to generate positive NPV, yet if the demand does not pick up

    Mohiuddin Asad 3

    3

  • 8/3/2019 Do Real Options Really Have Any Value

    4/22

    Do Real Options really have any value?

    as expected, ABC will have to sustain heavy losses. This uncertainty is

    further enhanced by the rumours that government is considering a

    plan to supply electricity to the remote areas of the country.

    ABC has advantage in this project because of its existing resources and

    set up; otherwise barrier to entry is quite high. Due to the special

    characteristics, Project solar has an investment timing option and can

    be delayed for one year. ABC is interested to evaluate whether such

    option would be valuable. In line with special features of the project

    and for the sake of simplicity, it is assumed that the cost will still be

    $80 million at the end of the year, and the cash flows for the

    mentioned scenarios will still last three years; hence, there is no cost

    to delay. Since the barrier to entry is very high, there is no possibility

    for competitors to snatch business during deferral period. The deferral

    can help ABC to understand and analyse the level of demand in a

    better way so that it will implement the project only if it adds value to

    the company. Value of any real option increases if the underlying

    project is very risky and if there is a long time before option must be

    exercised. Since Project solar is risky and has one year before ABC

    must decide, so the option to delay seems valuable.

    Mohiuddin Asad 4

    4

  • 8/3/2019 Do Real Options Really Have Any Value

    5/22

    Do Real Options really have any value?

    Valuation

    Based on the above information, we can first calculate the Net present

    value of the project using the classical discounted cash flow method,

    without considering any option. Below table shows NPV of the project

    using Present value annuity table for 3 years at 10% i.e.

    $34.12mx2.487= $84.85m - $80m = $4.85m.

    Now we can use decision tree analysis to calculate NPV of the project

    with the investment timing option. First, we will calculate NPV

    assuming that ABC implements the project now. Scenario A in following

    Table shows NPV, Variance, Standard deviation and coefficient of

    variation calculated assuming that the project is started now :

    Mohiuddin Asad 5

    5

  • 8/3/2019 Do Real Options Really Have Any Value

    6/22

    Do Real Options really have any value?

    Scenario B shows NPV, Variance, Standard deviation and coefficient of

    variation calculated assuming that the project is implemented after

    one year, only if optimal:

    It should be noted that in Scenario B, cost of the project is discounted

    at the risk-free rate, since the cost is known. However, operating cash

    flows are discounted at adjusted required rate of return (RRR). The

    option to defer the project resembles a financial call option. Inputs

    needed to apply option pricing theory to valuing the option to delay

    Mohiuddin Asad 6

    6

  • 8/3/2019 Do Real Options Really Have Any Value

    7/22

    Do Real Options really have any value?

    are the same as those needed for any option. We will need value of the

    underlying asset, the variance in the value of underlying asset, the

    time to expiration on the option, the strike price, the risk less rate and

    the equivalent of the dividend yield i.e. cost of delay which is not

    applicable in ABCs case as assumed earlier.

    According to our base case, ABC has until Year 1 to decide whether or

    not to implement the project, so the time to expiry of the option is one

    year. If ABC exercises the option, it must pay a strike price equal to

    the cost of implementing the project. If it executes the project, it gains

    the value of the project. Like when a call option is exercised, a stock is

    received that is worth equal to whatever its price is. Similarly If ABC

    implements the Project; it will gain a project whose value is equal to

    the present value of its cash flows. Thus, the present value of a

    project's future cash flows can be used in place of current value of a

    stock. The rate of return on the project is equal to its cost of capital.

    To find the value of a call option, we also need variance of its rate of

    return; hence, to apply call option formula, we will need standard

    deviation of the projects expected rate of return, square of which is

    equal to Variance.

    Firstly, we need to find the value of the project's future cash flows, as

    of the time the option must be exercised. We will also need the

    standard deviation of the project's value as of the date it must be

    exercised. This calculation is shown in Table below:

    Mohiuddin Asad 7

    7

  • 8/3/2019 Do Real Options Really Have Any Value

    8/22

    Do Real Options really have any value?

    The above figure of $84.85m is the future cash flows which should be

    converted into present value of the project's future cash flows as

    calculated below:

    As discussed earlier, to find the value of real option, we need variance

    of the projects expected rate of return. This can be done using direct

    approach to estimate the variance of the project's rate of return as

    shown in table below and:

    Mohiuddin Asad 8

    8

  • 8/3/2019 Do Real Options Really Have Any Value

    9/22

    Do Real Options really have any value?

    the indirect approach which starts by estimating the coefficient of

    variation (CV) of the project's value at the time the option expires. We

    have already calculated that (CV=0.38) above. Putting figures into

    below formula, we get Variance of the projects rate of return that is

    13.5%.

    We now have all information ready to use the black Schole model to

    calculate value of ABC option to delay as follows:

    Mohiuddin Asad 9

    9

    t

    ]1CVln[2

    2 +=

  • 8/3/2019 Do Real Options Really Have Any Value

    10/22

    Do Real Options really have any value?

    Therefore, for Project solar ABC has an option to delay worth

    $10.41m. Considering NPV of $4.85m, total value of the project without

    any option is $4.85m whereas total value of the project including

    option to delay is $4.85 + $10.41= $15.26m.

    Mohiuddin Asad 10

    10

  • 8/3/2019 Do Real Options Really Have Any Value

    11/22

    Do Real Options really have any value?

    Variation in inputs and their impact

    We will now vary some critical inputs in our base case and see how

    these impact our NPV of $4.85m and real options value (ROV) of

    $10.41m. Firstly, let us assume that the initial investment required was

    $79m instead of $80m with other things remained same. This will

    increase NPV from $4.85m to $5.85m. The increase in NPV is obvious

    because now less cost is required to get the same benefits. This

    change will also result in an increase in ROV from $10.41m to $10.81m

    because the strike price has been reduced now. For the same reasons,

    if we increase the initial investment from $80m to $81m, keeping

    everything else constant, the NPV and ROV will reduce to $3.85m and

    $10.02m respectively. Now let us suppose that required rate of return

    or cost of capital is increased from 10% to 11% in our base case. This

    will reduce NPV from $4.85m to $3.38m and ROV from $10.41m to

    $9.34m. This is because that a higher discount rate will reduce the

    present value of the cash inflows and consequently the NPV will be

    reduced. Similarly for ROV, a decrease in underlying assets value will

    lead to a reduction in the option value. For the same reason if required

    rate of return or cost of capital is decreased from 10% to 9%, NPV will

    increase from $4.85m to $6.37m and ROV will increase from $10.41m

    to $11.59m. Now let us increase uncertainty or volatility and see its

    impact on NPV and ROV. When the uncertainty is higher, the project is

    Mohiuddin Asad 11

    11

  • 8/3/2019 Do Real Options Really Have Any Value

    12/22

    Do Real Options really have any value?

    more risky and consequently NPV is lesser. However, this has opposite

    impact on ROV, the higher the uncertainty or variance, the greater is

    the value of option. In our base case, when we raise standard deviation

    of returns from 32.17 to 35.54, NPV goes down from 4.85m to 4.3m.

    However, this results in an increase in variance; hence ROV goes up

    from $10.41m to $11.22m.

    Mohiuddin Asad 12

    12

  • 8/3/2019 Do Real Options Really Have Any Value

    13/22

    Do Real Options really have any value?

    Difference between NPV and Real option value

    Net present value (NPV) is the main tool in discounted cash flow (DCF)

    analysis and is a standard method for using the time value of money to

    appraise long-term projects in Capital budgeting decisions. It measures

    the excess or shortage of cash flows, in present value terms, once

    financing or required charges are met. In other words, NPV of an

    investment or project is equal to the difference between the present

    value of all future cash inflows and present value of all, initial as well

    as future cash outflows, using the required rate of return. According to

    Mohiuddin Asad 13

    13

    http://en.wikipedia.org/wiki/Discounted_cash_flowhttp://en.wikipedia.org/wiki/Discounted_cash_flow
  • 8/3/2019 Do Real Options Really Have Any Value

    14/22

    Do Real Options really have any value?

    this method, a project with positive NPV is acceptable while a project

    with negative NPV should be rejected. Although NPV measurement is

    widely used for making investment decisions, a limitation of NPV is that

    it does not account for flexibility or uncertainty after the project

    decision.

    The NPV approach assumes that management will be "passive" as

    regards their Capital Investment once committed. It uses information

    that is known at the time of the appraisal and choice is all-or-nothing.

    As compared to this, real options value (ROV) approach is not about

    simply calculating a single NPV before the project begins and then

    making a decision to reject or accept the project and sitting back

    passively until the projects term runs out. Instead, real options provide

    a framework for strategic decision making as the project goes along.

    The choice is an initial choice, followed by more choices as information

    becomes available. Real option can be described as the right but not

    the obligation to acquire the gross Present value of future cash flows

    by making an irreversible investment on or before the date the

    opportunity expires.

    We can explain real option concept by a basic example. Suppose we

    want to buy a house and have chosen one for $1m but our loan

    application is pending for approval with the bank and expected to be

    decided within one week. If we leave the deal open, other buyers will

    purchase that house. To cope with this situation, we may agree with

    Mohiuddin Asad 14

    14

  • 8/3/2019 Do Real Options Really Have Any Value

    15/22

    Do Real Options really have any value?

    the seller to hold the house for one week by paying an amount of say

    $2000. By this payment, we are in fact buying an option to wait

    whereby if our loan is approved, we can proceed with the deal and if

    rejected; we can let the option expire at a cost of $2000 only.

    Since NPV only offers decision makers the choice of investing or not

    investing, a defining distinction between real options and NPV is based

    on the choices that each method offers. NPV rule does not take into

    account how the ability to delay irreversible investment expenditure

    can profoundly affect the decision to invest (Dixit and Pindyck, 1994).

    Thus the basic assumptions of real options and net present value,

    specifically regarding investment deferral and reversibility, are

    important for comparison. Dixit and Pindyck (1994) state that being

    able to delay an irreversible investmentundermines the simple net

    present value rule, and hence the theoretical foundation of standard

    neoclassical investment models. NPV does not recognize the

    managerial alternative of waiting, delaying the start of, or phasing the

    investment of a project whereas real options theory recognizes that an

    investment decision can be delayed, expanded, contracted or

    abandoned.

    Thus to sum up, one of the most important differences between NPV

    and ROV approaches is the Flexibility. NPV implicitly assumes that

    management will be "passive" as regards to their Investment once

    Mohiuddin Asad 15

    15

  • 8/3/2019 Do Real Options Really Have Any Value

    16/22

    Do Real Options really have any value?

    committed, whereas ROV assumes that they will be "active" and can

    modify (i.e. defer, abandon, expand, or contract) the investment as

    necessary. Another important difference arises from the element of

    Uncertainty. In NPV method, higher uncertainty means higher

    discount rate and thus lower NPV. To contrast, in real options theory,

    higher uncertainty leads to higher option values.

    Mohiuddin Asad 16

    16

  • 8/3/2019 Do Real Options Really Have Any Value

    17/22

    Do Real Options really have any value?

    Should one always be greater than the other, why or why

    not?

    In the absence of uncertainty over time, both the real option value and

    the net present value are equal to the present value of the project

    assets less the expenditure required to obtain those assets. However,

    when there is uncertainty, the real options value of a project is always

    higher than the NPV. According to Bodie and Merton (2000), the net

    result of uncertainty is, by not accounting for managerial flexibility,

    the NPV of the project will be underestimated relative to the real

    options approach (Bodie and Merton 2000). Glantz (2000) states that

    net present value essentially disregards any opportunities in

    investment analysis to change the game plan. Because flexibility is the

    epitome of real options theory, NPV consequently underestimates

    projects that are clearly elastic (Glantz, 2000). Hence to sum up,

    flexibility has value because it can help in increasing profit or reducing

    losses of an investment in uncertain situations. Since NPV does not

    account for this flexibility in its valuation whereas real option does, the

    value of a projects ROV is always higher than the projects NPV in

    uncertain situations.

    Mohiuddin Asad 17

    17

  • 8/3/2019 Do Real Options Really Have Any Value

    18/22

    Do Real Options really have any value?

    Which variables affect the difference between the two?

    To explain which variables affect the difference between Real options

    value (ROV) and net present value (NPV), we shall first see what basic

    variables are used in each valuation method. We shall try to map these

    variables and then identify the ones that cause the difference.

    In NPV, main variables are cash inflows, cash outflows and time value

    of money.

    A corporate investment opportunity resembles a call option because

    the company has the right but not the obligation to invest. Thats why

    financial option pricing models are widely used to value real options.

    The main variables in an option pricing model are: Risk free rate (Rf),

    Cost to implement the project or Strike price (X), Current value of the

    project (P), Time until the option expires (t) and Variance of the

    project's rate of return (V). As we know that NPV is the difference

    between how much the assets are worth i.e. their present value and

    how much they cost, cash outflows or initial investment in NPV is

    similar to the strike price or cost to implement the project in ROV

    whereas present value of cash inflows in NPV resembles the current

    value of the project in ROV. Time value of money is given by risk free

    rate in both methods. Hence, the variables which cause the main

    Mohiuddin Asad 18

    18

  • 8/3/2019 Do Real Options Really Have Any Value

    19/22

    Do Real Options really have any value?

    difference are time until the option expires and Variance of the

    project's rate of return. Uncertainty & flexibility to deal with it are the

    main factors that cause the difference as these are what give birth to

    options. In a 100% sure world, options will not have any value.

    In a deferral option situation, the possibility of deferral gives rise to

    two sources of value. The first source of value is the interest that can

    be earned on the required capital expenditure by investing it later

    rather than sooner. The second source of value is that while we wait,

    asset value may change and affect our investment decision

    favourably (Timothy, 1998). NPV misses these extra values because it

    assumes that decision cannot be put off. On the contrary, option

    pricing presumes the ability to defer and provides a way to quantify

    the value of deferring.

    Mohiuddin Asad 19

    19

  • 8/3/2019 Do Real Options Really Have Any Value

    20/22

    Do Real Options really have any value?

    How reliable are our conclusions using NPV versus real

    options approach?

    Both NPV and real option approaches draw their inputs from future

    estimations, hence reliability of both results largely depend on the

    quality and accuracy of the forecasts.

    For instance, NPV calculation is very sensitive to the discount rate,

    future cash flows, Cash flow timings and projects expected life. A

    small change in these estimations can bring a big change in NPV.

    Similarly it is also true that the initial step in most real option analyses

    is the present value of an underlying asset, for which a NPV has to be

    computed. Hence, reliability of the input is the first thing which

    contributes to reliability of the out put from both methods. Further, it

    should be noted that Real option valuation (ROV) method is not a

    replacement of net present valuation method i.e. these are not

    mutually exclusive but rather ROV is an extension of or supplement to

    NPV method, so both have their importance and their results can be

    relied upon based on their objectives. NPV works fine for safe cash

    flows. It also works fine for assets or businesses whose value depends

    primarily on forecasted cash flows and not on real options (Page 187,

    SFM, Module book,2008). However, the extended benefits offered by

    Mohiuddin Asad 20

    20

  • 8/3/2019 Do Real Options Really Have Any Value

    21/22

    Do Real Options really have any value?

    real option valuation are that unlike NPV, real options enable firms to

    cope with high levels of uncertainty about the upside potential or

    downside risk of an investment and allow for high levels of flexibility.

    Real options hold additional importance because they recognize that

    managers can obtain valuable information after the acceptance of a

    project. Though real options are not a cure all for capital budgeting

    projects, yet Informed actions can make a significant difference to

    the overall value of a project. As Baldwin (1987) noted, given the

    increase in variability in both product and financial markets worldwide,

    companies that recognize option values and build a degree of flexibility

    into their investments are likely to be at a significant advantage in the

    future, relative to companies that fail to take account of options in the

    design and evaluation of capital projects. (Baldwin, 1987) In view of

    the current fast changing economic and financial world, Baldwins

    vision more strongly support utilizing real options approach. Thus we

    may conclude that NPV has its own utility and importance, however, in

    today s highly uncertain and challenging business environment, real

    option valuation provides a more informed, flexible and reliable basis

    for capital budgeting decisions.

    Mohiuddin Asad 21

    21

  • 8/3/2019 Do Real Options Really Have Any Value

    22/22

    Do Real Options really have any value?

    References:

    Dixit, A. and R.S. Pindyck, (1994) Investment under Uncertainty,

    Princeton University Press, Princeton, New Jersey.

    Bodie, Z. and R.C. Merton, (2000) Finance, Prentice Hall, Upper Saddle

    River, New Jersey.

    Glantz, Morton (2000), Scientific Financial Management, American

    Management Association, New York.

    Timothy A. Luehrman (1998), Investment Opportunities as Real

    Options: Getting started on the Numbers, Harvard business review,

    July-August 1998.

    Baldwin, C. Y. (1987), the Capital Factor: Competing for Capital in a

    Global Environment,

    Midland Corporate Finance Journal 5 (No. 1), pp. 43-64.

    Mohiuddin Asad 22