    Commissioning Measures Form for Approval

    No.YDTD-TS02

    Project

    name

    Phase I of 2330MW Project of Tengda

    Coal-fired Power Plant in India

    Contract

    No.

    To: Tengda Project Department of Sichuan Machinery & Equipment Import & Export Corporation

    Now it is submitted for the examination and approval with the closed circulating water system commissioning

    technical measure of phase I of 2330MW project of Tengda Coal -fi red power pla nt in Ind ia

    Document No: QJCS-02.

    Appendix: Closed circulating water system commissioning technical measure

    Contractor: Sichuan Tongneng Power Technology Co. Ltd.

    Project principal Date

    Examination and approval opinions of the project supervision department:

    Project supervision department (seal)

    Supervision engineer: Date

    Chief supervision engineer: Date

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    2/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    2 21

    Examination and approval opinions of the owner

    Legal person of the project (seal):

    Owner representative Date

    Contractor: Sichuan Tongneng Power Technology Co. Ltd Mar. 2008

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    3/16

    Phase I of 2330MW Project of Tengda Coal-fired

    Power Plant in India

    Closed circulatingwater system

    commissioningtechnical measure

    Sichuan Power Industry Commissioning Test InstituteSichuan Tongneng Power Technology Co., Ltd

    Mar. 2008

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    4/16

    Examination and Approval Record for

    Documents

    D o c u m e n t

    n a m e

    Closed circulating water system commissioning technical measure

    D o c u m e n t

    N o .YDTD-QJCS-02

    The 1st

    version

    Date of

    publication

    The

    2nd

    version

    Date of

    publication

    Main revised content

    E d i t i o n n o .

    The 3rd

    version

    Date of

    publication

    Main revised content

    M a n a g e r s

    a p p r o v a l o f

    t h e

    c o m m i s s i o n i

    n g p r o j e c t

    D a t e :

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    5/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    1 9

    R e v i e w o f t h e

    p r i n c i p a l o f

    p r o f e s s i o n a l

    g r o u p o f

    c o m m i s s i o n i

    n g p r o j e c t

    D a t e :

    C o m p i l e r o f

    t h e t e c h n i c a l

    d o c u m e n t D a t e

    ontent

    1. Compi l ati on purpose . . . . . . . . . . . . . . . . . . 2. Compi l ati on reference . . . . . . . . . . . . . . . . 3. Commi ssi oni ng qual i ty standard and obj ect 4. Responsi bi l i ty di vi si on . . . . . . . . . . . . . . 5. Systembri ef i ntroducti on . . . . . . . . . . . . 6. Condi t i ons pri or to commi ssi oni ng . . . .

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    6/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    2 9

    7. Commi ssi oni ng work procedure . . . . . . . . . 8. Commi ssi oni ng step . . . . . . . . . . . . . . . . . . . 9.

    Safety measure . . . . . . . . . . . . . . . . . . . . . . .

    10. Appendi x . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

    1. Compilation purpose1.1 To instruct and standardize the commissioning work of system and equipment, and

    guarantee safety and normal operation thereof, this regulation is hereby compiled.1.2 Inspect the closed circulating water system electric and thermal work protection interlock

    and signal unit, and determine the reliability of the action.

    1.3 Inspect the system and equipment operation status, check the system performance, find outand eliminate the possible defects.

    2. Compilation reference2.1 Thermal Power Plant Basic Construction Engineering Startup and Completion Acceptance

    Code(1996version) power construction [1996]159#

    2.2 Power Construction and Acceptance Technical Specification (SteamTurbine )DL5011-1992

    2.3 Power Construction and Acceptance Technical Specification(Pipe )DL5031-19942.4 Standard for Quality Inspection and Evaluation of the Adjustment and Commissioning in

    Thermal Power Project, Construction Quality [1996]111#

    2.5 Regulations for the Startup and Commissioning of the thermal Power Projects,Construction Quality [1996]40#

    2.6 Manufactory drawings, installation and operation instructions, quality assurance book andex-factory certifications

    2.7 Design documents, drawings, specifications, and commissioning documents as well asconference summary, etc.

    2.8 Equipments supply contract, and the international and national standards stated therein

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    7/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    3 9

    3. Commissioning quality standard and object3.1 The industrial water system commissioning result conforms to the quality standard of

    related closed circulating water systems of Standards for the Inspection and Assessment of

    the Adjustment and Commissioning Quality for Thermal Power Projects (1996 version),

    and quality requirements of commissioning contract, as well as satisfy with turbine

    complete set startup requirements.

    3.2 The sub-plant trial operation, attestation and acceptance are qualified, and meet thecomplete set startup requirements.

    4. Responsibility divisionAccording to the statements of the administry newly issued Startup Regulation, and the

    Commissioning Contract, the responsibilities of each party are as following:

    4.1 Installation unit:4.1.1 Responsible for individual equipment commissioning and trial operation work.4.1.2 Responsible for isolation work of the system.4.1.3 Responsible for repair, maintenance and defect elimination of the trial operation

    equipments.

    4.1.4 Prepare the necessary repair tools and materials.4.1.5 Cooperate with the commissioning unit for subsystem commissioning.4.1.6 Responsible for attestation work after trial operation of system sub-section.4.2 Manufacturing unit:4.2.1 Responsible for startup/closedown, operation regulation and accident treatment of system

    trial operation.

    4.2.2 Responsible for hanging the formal brand mark of the related systems and equipments.4.2.3 Prepare the regulations, tools, and record reports, etc.for operation;4.2.4 Responsible for patrol inspection and normal maintenance during trial opereation.4.3 Responsibility of commissioning unit:4.3.1 Responsible for compiling trial operation scheme together with technical clarification.4.3.2 Prepare the apparatuses, instruments and tools for the related tests.4.3.3 Responsible for command and control work of subsystem commissioning.4.3.4 Responsible for test data record and sorting.4.3.5 Fill in trial operation quality evaluation table.

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    8/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    4 9

    4.3.6 Responsible for attestation work after trial operation of the system and subsystem.4.3.7 Compile the commissioning report.4.4 Individual commissioning of pump group will be responsibility of the installation unit,

    with parcitipation of commissioning unit. The sub-system commissioning of pump group

    will be responsibility of commissioning unit, with participation and cooperation of the

    installation unit and other units. The circulating water pump system commissioning will be

    carried out with uniform instruction of trial operation team, it will be implemented by

    circulating water system commissioning professional team, the steam turbine discipline

    will take the lead, with cooperation of electric, thermal control and other disciplines.

    5. System brief introduction5.1 General description

    1# and 2# machine sets of phase I of 2330MW newly built up project of Tengda

    Coal-fired power plant in India are respectively set by three sets of rated capacity 50%

    closed circulating water pumps, and three sets of capacity 50% closed circulating

    cooling water heat exchanges, and one 10m3 expansion water tank, the makeup water of

    the expansion water tank will be provided by the condensate system and desalt water

    system. During normal operation, the closed circulating water pump and the closedcirculating water heat exchange are all respectively two sets operation and one set

    standby.

    Closed circulating water cooling water system will provide the generator stator

    cooler, generator hydrogen cooler, exciter air cooler, electric feed pump motor cooler,

    electric feed pump lubricating oil cooler, work oil cooler, anti-flammable oil cooler,

    condense pump motor cooler, low pressure drainage pump, hydrogen drier, boiler water

    supply pump bearing cooler, condense transfer pump bearing cooler, electric group

    mechanical sealing (and cooling chamber) cooling water, and it can also makeup water

    for the mechanical vacuum pump. In addition, it will also provide boiler side blower,

    draught fan, primary blower lubricating oil station and bearing cooling water, air

    preheater bearing cooler, sealing blower cooler, coal grinding machine motor cooler,

    high pressure oil pump station, and thin oil station cooler cooling water.

    5.2 Equipment specification5.2.1 Closed circulating water pump

    Model500S-59B

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    9/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    5 9

    Mode double suction horizontal centrifugal pump

    flow1300 m3h

    lift58 m

    efficiency79.4

    necessary net positive suction head4 m

    shaft power273 KW

    rotating speed970r/min

    5.2.2 closed circulating pump auxiliary motormodel310KW-6

    rated power310KW

    rated voltage6KV

    rated current39 A

    synchronous speed988 r/min

    6. Conditions prior to commissioning6.1 The circulating water system, circulating water makeup system, opening

    circulating water system can be operated.

    6.2 All pipelines and equipments installation of closed water system is completed, andmeet design requirements, together with complete installation technical record;

    6.3 It has reliable operation power supply and dynamic power supply, and each AC andDC distribution panel has been electrified;

    6.4 Each manual gate and automatic gate of the system has been one by onecommissioned and inspected, the action is proper and flexible, together with

    indication of name and switch direction, and it is in the standby status;

    6.5 Each instrument, switch and signal has been fully installed, and calibrated properly,they are cleaned up with marking of name, and are ready for use.

    6.6 The closed circulating water pump inlet strainer, pump inlet channel and pumpoutlet pressure pipe will be cleaned up;

    6.7 The other pipeline system with relation to the closed circulating water pipeline willbe isolated as per requirements;

    6.8 The motor and pump bearing will be filled by lubricating oil till the stated oil

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    10/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    6 9

    level.

    6.9 The expansion water tank has the qualified desalt water, and it can guarantee thesufficient water supply for flushing, and the drainage system is smooth;

    6.10 The trial operation site environemnt is clean, the site hole and channel cover plateare complete, and the temporary hole is mounted by guardrail or cover plate, the

    platform has normal staircase, channel, bridge walk, handrail and bottom

    protection board;

    6.11 The operation suspended door and important monitoring instruments and meterswill be mounted by platform or staircase;

    6.12 The firefighting system is in the reliable and standby status;6.13 The drainage systems and facilities are normal for use.6.14 The site has formal lighting, accident lighting system, which are complete, reliable

    and ready for use.

    6.15 The communication equipments as telephone, etc. are installed and can be puttedinto use.

    7. Commissioning work procedureThe closed circulating water system commissioning work can be carried out as per

    following flow chart:

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    11/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    7 9

    Commissioning technical scheme clarification

    Commisioning conditions determination;

    Interlock protectionand alarming test

    Closed circulating water pump group trial operation

    Pipeline flushing

    System putting into operation and dynamic regulation

    Main equipment installation and individual commissioning are completed

    Instrument constrol installation and related commissioning are completed;

    Electric installation and related commissioning are completed;

    Pipe valve installation and commissioning

    Safety condition is satisfied

    Interlock protection test

    Alarming test

    8. Commissioning step8.1 Prior to system operation, the electric and thermal work professional staffs will carry ou

    the thermal work and electric interlock protection test (the detailed content please refer to the

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    12/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    8 9

    annexed table).

    8.2 Motor individual trial operationThe motor individual trial operation work will be carried out by the installation

    unit,and this content item is only for reference;

    8.1.1 Separate the matching wheel between motor and pump;7.1.1 The motor insulation is qualified;8.1.2 The motor spot-drive rotation direction is proper;8.1.3 The motor is operated 2 hours continuously after normal operation;8.1.4 The trial operation will record the bearing vibration, bearing temperature, motor

    temperature, motor startup/operation current, and cooling water pressure;

    8.3 Trial operation of closed circulating water pump;8.3.1 Preparation prior to trial operation:

    a) Wheel connection between the motor and pump is completed;b) The water of expansion water tank is filled to the work level.

    8.3.2 Closed circulating water pump startup;a) Open the closed cooling water system air valve, and open the closed heat

    exchange water side air valve.

    b) The closed circulating water pump is started up at the field.c) Inspect the pump outlet gate and pump operation statuses;d) After the pump capacity is normal, inspect the closed water system pipe, each

    air valve of the system will be closed when meeting with water, and inspect the

    leakage status;

    e) In the trial operation, record the bearing vibration, bearing temperature, motortemperature, motor startup/operation current, pump outlet pressure;

    f) Pump group trial operation is 8 hours.8.3.3 Stop operation of closed circulating water pump;

    a) The field or remote DCS will stop the operation of closed circulating waterpump;

    b) The pump will not be of reverse rotation.8.4 According to the trial operation site status, it may carry out closed circulating water pump

    dynamic linkage test.

    8.5 Closed circulating water system flushing8.5.1 The pipe will be separated before each system entering the equipment, and the

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    13/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    9 9

    inlet and outlet gate of the equipment will be short connected;

    8.5.2 Start up the closed circulating water pump, maintain the outlet pressure of pump,and continuously flush the system. To maintain the outlet pressure of the pump,

    each sub-system will be flushed in alternation;

    8.5.3 Flush scope:a) Machine side: generator stator cooler, generator hydrogen cooler, exciter air

    coler, electric feed pump motor cooler, electric feed pump lubricating oil cooler

    and work oil cooler, electric group mechanical sealing (and cooling room)

    cooling water inlet, anti-flammable oil cooler, condense pump motor cooler, low

    pressure heater drainage valve, hydrogen drier, boiler water supply pump

    bearing cooler, and condense water transfer pump bearing cooler;

    b) Boiler side: boiler sampling water, coal grinding machine motor cooler, coalgrinding machine high pressure oil pump station, seal blower cooler, primary

    blower lubricating oil cooler, primary blower bearing cooler, draught fan and

    blower lubricating oil cooler and bearing cooler, air preheater top bearing cooler,

    etc;

    8.5.4 The wate quality is clean and transparent without foreign substances, after theinspection is qualified, the system will be recovered. The water quality will be

    periodically inspected, if it is not consistent with the requirements, the water will

    be replaced;

    8.5.5 When the system water quality reaches certain extent, the thermal workinstrument will be flushed and inputted.

    9. Safety measures9.1 When the closed circulating water pump outlet butterfly is closed, the closed

    circulating water pump will not be operated;

    9.2 Inspect the current and voltage of the closed circulating water pump, and the actualoperation work condition of the pump will be in the stated scope, without

    power-exceeding and motor reverse rotation.

    9.3 Avoid low flow operation of the closed circulating water pump;9.4 Prior to startup of closed circulating water pump, it will not have abnormal

    vibration sound, otherwise the pump will be immediately stopped for inspection

    and treatment;

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    14/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    10 9

    9.5 The normal operation and accident treatment will be rigidly carried out by poewrplant operat ion regulation.

    10.Appendicesa)Condition inspection table

    Closed circulating water system trial operation condition inspection table

    System description: closed circulating water system

    Determination and signature

    No. Condition descriptionInstallation

    party

    Commissioning

    party

    Supervison

    party Owner

    1

    All equipments and pipe installation of the closedcooling water system has been completed,

    accepted and attested.

    2

    The thermal work instrument and electric

    equipment installation and calibration have beencompleted, together with provision of calibrationlist of the instruments, and pressure, temperature

    and vibration switches, etc. The instruments and

    meters are calibrated and installed.

    3

    The valve individual commissioning is

    completed, the switch action is proper, the limit

    switch location and CRT status display is proper.

    4

    The closed circulating water pump inlet

    strainer, pump inlet channel and pump

    outlet pressure pipe will be cleaned up;

    5

    The closed pump motor insulation test isqualified, and the pump and motor bearing have

    been filled by qualified lubricating grease.

    6

    The expansion water tank has the

    qualified desalt water, and it can

    guarantee the sufficient water supply

    for flushing, and the drainage system is

    smooth;

    7

    The trial operation site environemnt is

    clean, the site hole and channel cover

    plate are complete, and the temporary

    hole is mounted by guardrail or cover

    plate, the platform has normal staircase,

    channel, bridge walk, handrail and

    bottom protection board;

    8

    The operation suspended door and

    important monitoring instruments and

    meters will be mounted by platform orstaircase;

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    15/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    11 9

    9

    The closed water system flushing temproary pipe

    has been installed as per requirements. The otherpipeline system with relation to the closed

    circulating water pipe will be isolated.

    10

    The site has formal lighting, accident

    lighting system, which are complete,reliable and ready for use.

    11The firefighting system is in the reliable

    and standby status;

    Sichuan Tongneng Power Technology Co. Ltd

    Date day month 2008

    b) Logic inspection tableClosed circulating water system interlock logic inspection table

    No. Item Set value Interlock protection action

    I. Start up conditions

    Expansion water tank level is higher, low I value

    outlet valve of closed water pump turnoff

    II. Interlock protection conditions

    Expansion water tank level is lower, III value closed water pump tripping

    CRT startup closed water pumpLinkage opening outlet electric

    gate

    CRT stop the closed water pumpLinkage closeing outlet electricgate

    A pump accident tripping, B pump is inputted for

    interlock.B pump interlock startup

    A pump accident tripping, B pump is inputted for

    interlock, the outlet main pipe pressure is low.

    A pump accident tripping, C pump is inputted forinterlock.

    A pump is operated, C pump is inputted intointerlock, the outlet main pipe pressure is low.

    B pump accident tripping, C pump is inputted forinterlock.

    B pump is operated, C pump is inputted intointerlock, the outlet main pipe pressure is low.

    B pump accident tripping, A pump is inputted for

    interlock.

  • 8/13/2019 Dm Water System Ydtd Qj Facs 02

    16/16

    Phase I of 2330MW Project of Tengda Coal-fired Power Plant in India

    Closed circulating water system commissioning technical measure

    12 9

    B pump is operated, A pump is inputted into

    interlock, the outlet main pipe pressure is low.

    C pump accident tripping, B pump is inputted forinterlock.

    C pump is operated, B pump is inputted into

    interlock, the outlet main pipe pressure is low.

    C pump accident tripping, A pump is inputted for

    interlock.

    C pump is operated, A pump is inputted intointerlock, the outlet main pipe pressure is low.