3 Detailed maintenance advice on workshop machines
3.1 Disc and belt sanding machinesDaily check
Clean any dust not removed by the extraction system.
Check condition of sanding belt/disc and replace if torn/worn.
Check fit of sanding table to disc/belt (it should be as close as possible,
normally no greater than 2 mm).
Check that quadrant guard is in the correct position.
Weekly check
Clean filters in dust-extraction system, if fitted.
Empty dust-collection tray/bag if fitted.
Visually check condition of electrical switches, conduit, cable, etc.
Lubricate if necessary.Termly check
Check condition of motor, drive system and drive belts, if fitted.
Replace if worn.
Lubricate if necessary.
Check operation of dust-extraction system.
Check bearings for ear
-
7/30/2019 DL254
2/10
Check bearings for wear
Lubricate if necessary. Machines with gears running in an oil bath
should have the oil level checked.
Check bearings for wear.
Check that machine vices and hand vices function correctly and are
not worn or clogged with waste materials.
3.3 Bench-mounted jig saw
Daily check
Clean any dust not removed by the extraction system.
Check condition of blade and replace if blunt. Check that blade guard is correctly set.
Where fitted, check that machine foot functions correctly.
Weekly check
Clean filters in dust-extraction system, if fitted.
Empty dust-collection tray/bag, if fitted.
Visually check condition of electrical switches, conduit, cable, etc. If fitted, check fit of table insert and replace if required.
Lubricate if necessary.
Termly check
Check condition of motor, drive system and drive belts, if fitted.
Replace if worn.
Lubricate if necessary
-
7/30/2019 DL254
3/10
Lubricate if necessary.
Termly check
Check condition of motor, drive system and drive belts, if fitted.Replace if worn.
Lubricate if necessary.
Check operation of dust-extraction system.
Check bearings and blade guards for wear and replace if necessary.
3.5 Circular saw
Daily check
Clean any dust not removed by the extraction system.
Check condition of blade and replace if blunt.
Check that top or crown guard is correctly set and connected correctlyto the extraction system, if the latter is fitted.
Check that machine braking system functions correctly.
Weekly check
Clean filters in dust-extraction system, if fitted.
Empty dust-collection tray/bag, if fitted.
Visually check condition of electrical switches conduit cable etc
-
7/30/2019 DL254
4/10
Visually check condition of electrical switches, conduit, cable, etc.
Lubricate if necessary.
Termly check Check condition of motor, drive system and drive belts. Replace if
worn.
Check condition of feed roller drive, clean, overhaul and lubricate as
required.
Lubricate if necessary.
Check operation of dust-extraction system. Check bearings and blade guards for wear and replace if necessary.
3.7 Radial arm saw
Daily check
Clean any dust not removed by the extraction system.
Check that blade guard and side-protection guards are correctly setand function as required.
Check that machine braking system functions correctly.
Weekly check
Clean filters in dust-extraction system, if fitted.
Empty dust-collection tray/bag, if fitted.
Visually check condition of electrical switches conduit cable etc
-
7/30/2019 DL254
5/10
Termly check
Check condition of motor, drive system and drive belts. Replace if
worn.
Lubricate as necessary.
Check operation of dust-extraction system.
Check bearings wear and replace if necessary.
3.9 Metal-turning lathe
Daily check
Clean chuck guard and any chip screens if fitted.
Check functioning of electrical interlock on chuck guard.
Check that cover plate on outer end of hollow mandrel is in place.
Check functioning of electrical interlock on change heel guard
-
7/30/2019 DL254
6/10
Weekly check
Visually check condition of electrical switches, conduit, cable, etc. This
should include any separate motors used for power feeds.
Lubricate if necessary.
Termly check
Check condition of motor, drive system and drive belts. Replace if
worn.
Lubricate as necessary, including slideways.
Check bearings for wear and replace if necessary.
If fitted, check coolant pump and system.
Yearly check
If a coolant pump is fitted, drain the coolant, flush out the system with
clean water and replace the coolant every 12 months.
3.11 Power hacksaw
D il h k
-
7/30/2019 DL254
7/10
Before use
Check condition of chisel and auger bit; replace or sharpen if blunt or
damaged.
Check that the vice functions correctly.
Check that all guards are in place, including the guard around the
auger chuck.
Visually check condition of electrical switches, conduit, cable, etc.
Lubricate if necessary.
Termly check
Check condition of motor, drive system and drive belts, if fitted.
Replace if worn.
Lubricate as necessary, especially sliders of motor frame.
Check bearings for wear and replace if necessary.
3.13 Double-ended, high-speed grinding machine
Weekly check
Clean eye screens and check that they are in the correct position.
Check position of tool rest and adjust if required; (the tool rest should
be as close as possible to the grinding wheel, normally within 3 mm).
Check condition of grinding wheels.
Visually check condition of electrical switches, conduit, cable, etc.
-
7/30/2019 DL254
8/10
A gas shut-off valve should be installed in every room where there is a gassupply. This should be located in an accessible position and should belabelled. It should be standard practice to turn off the gas supply at the end
of the school day, or earlier if the room is not used in the last period of theday. This leaves the room in a safe condition and serves as a check that thevalve is working.
A shut-off valve should be fitted in the supply pipe to each item ofequipment. This should be turned off when the equipment is not in use, andat the end of the school day.
In order to meet the requirements of the COSHH Regulations, the LEVsystem for heat-treatment equipment should be checked every 14 months.
4.2 Brazing hearth and/or chip forge
Weekly check
Check condition of air and gas flexible hoses.
If fitted, check functioning of spark igniter.
Check function of gas shut-off valve.
Visually check extraction system.
-
7/30/2019 DL254
9/10
Visually check fume-extraction system.
-
7/30/2019 DL254
10/10
School D&T Department
EQUIPMENT REGISTER AND MAINTENANCE LOG
Type of equipment . Serial No. . Location
Make . If electrical, details of phase/ power, etc.
DATE OFSERVICE ANDINSPECTION
REPAIR/SERVICING WORK REQUIRED/CARRIED OUT AND REMARKS SIGNATURE OF PERSONCARRYING OUT SERVICE/
INSPECTION
DATE WORKWAS DONE
SIGNATURE OF PERSONCARRYING OUT WORK
REQUIRED
10