distribution franchise … an experience. 2 integrated power company torrent power – at a glance...
TRANSCRIPT
Distribution Franchise
… An Experience
2
Integrated Power Company
Torrent Power – At a glance
Part of Rs. 8200 Crore Torrent Group
• Pharma (Turnover ~ Rs. 1916 Crores)
• Power (Turnover – Rs. 5958 Crores)
• Licensee in Ahmedabad, Gandhinagar & Surat• Franchisee in Bhiwandi, Agra & Kanpur*
DistributionDistribution
1647.5 MW Capacity • 500 MW at Ahmedabad• 1147.5 MW near Surat
GenerationGeneration
• JV with PowerGrid for 400 KV network TransmissionTransmission
* - yet to takeover operations
3
4
Why Distribution Reforms???
Present Distribution Scenario
• SEBs are majorly responsible for distribution
• Monopoly – Defined License areas
• Lack of requisite investment in T&D sector
• Lack of R&D in the distribution sector
5
Present Distribution Scenario – Drawbacks!
High AT&C losses
Frequent power failures due to very old and dilapidated network
Massive load shedding
Low customer satisfaction• Customer service standards are poor• Lengthy and tedious mechanisms for resolving consumer grievances
Uninspiring work culture
Old and obsolete technologies still being used
Unacceptable safety standards
6
0
5
10
15
20
25
India Russia China Brazil World
23.2
10.66.7
16.4
8.5
Distribution losses in developing countries in 2008
Source: Think BRIC – Comparative Study of Power Sector by KPMG- Jan 2010
Present Distribution Scenario – High Distribution losses
7
Present Scenario of Power Shortage
8
The power sector requires huge capital outlay to reduce the current deficit
and to sustain future GDP growth
It is not possible for the government to fund the growth of the sector on its
own
Investment are forthcoming in Generation from the private sector but it is not
sustainable if distribution reforms are not undertaken
The government has embarked on an aggressive mission – “Power for All by
2012” and the private sector has a key role in achieving the objectives stated
in the mission
Need of the hour
9
Models for Distribution Reforms
Allocation of Responsibilities
Management Contract
Franchisee Licensee
Asset ownership Public Public Private
Operation & Maintenance Private Private Private
Capital investment Public Private Private
Commercial risk Public Private Private
Duration 3-5 years 10-20 years 25 years
10
Distribution Reform Process Effectiveness and Acceptance Model
Privatization
DistFranchise
SEB DrivenReforms
ContractManagement
Pol
itica
l Acc
epta
nce
Low
Hig
h
Reform ProcessSlow Fast
11
Benefits of Franchise Model
Reduction in technical losses and theft
Improvement in Metering, Billing and Revenue Collection
Capital investments in upgradation of the network
Enhancement in customer service quality
A win-win scenario for all:Consumers, DISCOM and Franchisee
12
Technical Benefits
State of the art distribution system in franchise area
Lower peaking load due to better technical T&D management
Better overall grid stability due to lower system interruptions
Improvement in reliability parameters like SAIFI, SAIDI,
CAIDI, etc.
13
Financial Benefits to the State
Assured returns from distribution franchisee
No investment in the franchise area by licensee
Reduction in losses
Contribution to the Government exchequer
• Increase in collection of Electricity Duty as the metering and billing
becomes more accurate
• Increase in collection of other Central and State taxes pursuant to
growth of economy of franchisee area
14
Better services to Customers
Improved services
• Faster new connections/ load extensions
• Lower attendance time for faults
• Grievance Redressal mechanism
• Convenient bill payment facilities
Better availability and quality of power
Increased customer satisfaction
15
What is a Franchisee?
As per Definitions of The Electricity Act, 2003
“franchisee” means a person authorised by a distribution licensee to
distribute electricity on its behalf in a particular area within his area of
supply;
Facilitation of Franchise Model in the Section 14 of the Act:
Provided also that in a case where a distribution licensee proposes to
undertake distribution of electricity for a specified area within his area of
supply through another person, that person shall not be required to
obtain any separate licence from the concerned State Commission
………………………
Features of Input Based Distribution Franchise
17
Role of a franchisee
Generation Transmission Distribution
Energy Input Metering
Fault Restoration
O&M
Customer Care
Revenue Collection
ConstructionCAPEX
Planning
Meter Reading
State DISCOM
to supply power at
EHV substationsAll Obligation and Rights of a
Distribution Licensee
18
Rights of DF
DF to distribute power in the franchise area for a fixed term
as per the agreement
DF is an exclusive agent of Licensee in the Franchise Area
DF has all rights of a Distribution Licensee
E.g. authorization under Section 126, 135,152 of Electricity Act 2003
19
Responsibilities of DF
Purchase of power
From Licensee at EHV substations feeding the franchise area
Network Related
Network analysis and improvement planning
Make capital investment for renovation/ upgradation of network
Distribution asset maintenance
20
Responsibilities of DF
Consumer Related
Metering
Meter reading
Billing as per Regulatory Commission’s approved Retail Tariff
Collection (both current revenues and arrears)
Issuing new connections
Adherence to all relevant Regulations of ERC including Supply Code
and SOPs
Attending consumer grievances
21
Responsibilities of Licensee
Supply of energy
As per the pre-determined schedule of supply on a non discriminatory
basis subject to power availability
Payment to DF upon expiry / termination
For assets created during the agreement term at depreciated value.
For closing inventory
Arrears for last one month
22
Responsibilities of Licensee
Grant of Right to use of distribution assets in the circle
Network assets in field from the start of outgoing 22 kV feeders of
EHV s/s
Assets in stores as opening inventory
Deputation of willing employees to DF
Deputation rules/ deputation package of DF will be applicable.
23
Commercial Terms
DF
LICENSEE
Payment by LicenseeIncentive on recovery of arrears
SubsidySpecified payments upon termination / expiry
Payment by DFCharges for input energy as quoted by franchisee
Arrears collectedSecurity Deposit for new connections
Electricity Duty etc
Competitive bidding ensures that the State Discom gets the right price for input energy
Bhiwandi Franchise experience
25
Bhiwandi : Introduction
Government of Maharastra took the lead in distribution reforms and
introduced a franchisee model for public-private partnership
DISCOM consequently put through a process for selection and
appointment of a distribution franchisee for the Bhiwandi Circle of its
license area of Maharastra State
Torrent Power was selected as the Distribution Franchisee through an
open competitive bidding process
Distribution Franchise Agreement was signed with DISCOM on 20th
December, 2006
Operations taken over from 26th January, 07
26
Area 721 sq kms
Population 10 lacs
No of Customers 160,000 Nos
Demand 800 MVA
Annual Energy Input 2500 MUs
( at the time of takeover)
Bhiwandi
27
Bhiwandi : At the time of takeover
AT&C losses : 58%
Mandatory load shedding of 6 hours at the time of takeover and subsequently increased to 8 hours
Further distress load shedding due to deficit of 300 MVA in EHV Network
Overstressed distribution Network
• Overloading
• Breakdowns / trippings
Distribution transformer failure rate of 40%
Poor reliability of supply
Only 23% of the customers have accurate metering and there are many unregistered consumers
28
Key Challenges
Internal
• Human Resource Manpower
Integration
• Administrative Setup Offices
• T&D loss reduction Technical loss
Commercial loss
• Reliability of system
• Safety
External
• Power Availability Load Shedding
Transmission Capacity
• Customer Confidence Customer Service
Becoming a part of Bhiwandi
29
Overcoming the Challenge
Problem: HR Challenge
Measures: Offices made functional before Day One
Training provided in batches at Ahmedabad
Providing basic necessities – food, commutation
Defining uniform policies for all employees
Developing a “team attitude”
Direct communication with all employees regarding Goals and Targets
Uniform and quick appraisal & reward mechanism
Issue: Creating administrative setup
Recruiting & Training of Manpower
Integration of all employees – TPL, MSEDCL, Laterals and Freshers
30
Bhiwandi Team Logo
31
Sharing Goals and Targets
32
Communicating Commitment
33
Overcoming the Challenge
Problem: Lack of Adequate Power
Measures: Joint team with Transco & DISCOM formed
EHV network reconfigured
All support provided for creating additional capacity
Reduction in losses led to reduction in load shedding
as per MERC approved MSEDCL load shedding criteria
Issue: Mandatory Load Shedding of 6 hrs increased to 8 hrs
Further distress load shedding of 2 to 4 hrs
Inadequate EHV transmission capacity
34
EHV Network Augmentation
Joint Team of TRANSCO / DISCOM / DF to identify the bottlenecks in Transmission Network
3-Years EHV Augmentation Plan prepared and got approved
• Reconfiguration of EHV Lines
• Additional power transformers
• New EHV Substation
• Switchyard extension for 22KV feeders
250 MVA Transformation capacity added so far
Pre-takeover
Proposed
35
Overcoming the Challenge
Problem: Frequent Power Failures
Measures: Failed DT replaced within 24 hours
24 x 7 control room to ensure faster restoration
All DTs revamped
Issue: 2 to 3 DTs failing everyday
Frequent conductor breakdown
Lack of adequate maintenance leading to deterioration
of network
Long restoration time in case of faults
Overloaded System
36
Overcoming the Challenge
Problem: Technical Losses
Measures: Reconfigured the existing feeders
Added 29 new feeders to the existing 46 feeders
Added 125 MVA distribution transformer capacity
Proper termination and crimping provided
Installed capacitor banks to improve power factor
Issue: Overloaded feeders leading to higher I2R losses
Improper crimping at joints
Poor power factor of the system
37
Distribution System
22 KV feeders
Distribution Transformers and FSPs
38
Shunt Capacitors
39
Overcoming the Challenge
Problem: High Commercial losses
Measures: Provide systematic metering for accurately measuring consumption of the customers
Securitization of the network and extensive vigilance
Filing of FIR in case of repetitive power theft
Streamline processes to improve collection efficiency
“Ujjwal Bhiwandi Abhiyan” for legalising connections
Issue: Only 23% customers metered
Rampant theft of energy
No substantial action against non payment of bills
40
Metering
41
Ujjwal Bhiwandi Abhiyan
98000 connections since launch of UBA in Sept 07
42
Overcoming the Challenge
Problem: Safety
Measures: Lines replaced by underground cables at critical locations where clearance are issue
Earthing provided for all poles, transformers
Removal of double feed
Fencing provided for transformers
Lines replaced, where necessary
Public Safety Awareness programs
Issue: Lack of adequate clearance with lines
Transformers located at roadsides without any fencing
Double feed through hooking
LT/HT lines in poor condition (conductor snapping)
43
LT Network Revamping
44
Safety
45
Overcoming the Challenge
Problem: Customer Service
Measures: Call Center started from Day One
Customer friendly bill introduced
2 Customer Service Centers Opened
Customer Redressal Mechanism established
Mobile Van as a value added service
Issue: No concept of customer service
No consumer redressal system
Customers had lost confidence in utility
46
24 x 7 Call Center
47
Customer Care Centers
48
Outage Management
49
Overcoming the Challenge
Problem: Creating Customer Confidence
Measures: A series of programs with influential citizens informing them about Torrent Power
Direct interaction with Customers through letters
Performance standards widely publicized in direct mailers, cable TV, hoardings
Cultural adaptability – active participation in all festivals
Completing the communication loop through customer feedback - Setup a Customer Advisory Committee
Issue: Public was instigated against a private company taking over
No knowledge about Torrent’s capability
50
Direct Interaction with Customers
51
Community development activities
Dahi Handi
Ganesh Chaturthi
Iftar Party
Becoming a part of the social fabric
52
Customer Advisory Committee
The results
54
Major Accomplishments :Distribution Transformer Failure Rate
DT Failure Rate reduced by 37%
40% 2.8%
As on Nov 2010
At the time of takeover
55
Major Accomplishments : Load Shedding
Reduction in losses has improved power reliability in the area
10 to 12hours
Less than 3
Hrs
At present
At the time of takeover
56
Major Accomplishments : Accurate Metering
99% of sales is based on actual reading.
23% 99%
At present
At the time of takeover
57
Major Accomplishments: AT&C Loss
Reduction of 39%
58%
18.8%12 monthMovingAverage
At the time of takeover
As on March 10
58
Agra
Area : 188 Sqkms
Population : 23 Lacs
Customer base : 2.8 Lacs
Peak Demand : 420 MVA
Energy Input : 1800 MU
International Tourist Place
33/11KV Substations : 38 Nos
11KV OH Line : 713 Kms
DTCs : 3269 Nos
HT Consumers : 350 Nos
LT Network : 1500 Kms
33KV OH Line : 230 Kms
59
Agra Network : Major Issues
Power Supply Shortage
• For distressing the system
• Bottlenecks in EHV Network
Technical shortcomings
• Inadequate Network
• Aging T & D Network
• Highly unsafe Network
• Significant Overloading
• Lack of Redundancy
• Inadequate protection system
• Inadequate Reactive Compensation
Sub-optimal Maintenance
• Poor Upkeep & Maintenance
• Complete lack of standardizationCouple of major outages every day adversely affecting the reliability of supply
60
Agra : Major Issues
Commercial Profligacy
• Inadequate metering
Few consumers with accurate metering
• Incongruent billing processes
• Inconsistencies in database
• High theft & pilferage
Many Unregistered consumers
• Low collection efficiency
• Huge backlog of new connections and customer complaints
High distribution losses
Lack of Customer Services
Manpower problems
• Shortage of skilled manpower
Complete lack of IT in overall business
Crying need for complete overhaul of the system
61
Key Challenges
Type text
Type text Type text
Reliability of SupplyRobust, Secured and Safe Network
through absorption of latest technologies
Customer ServicesBringing Value added systems and
technologies for Customers
AT & C LossesBringing efficiency in Network,
metering, billing & other Commercial Processes
… easier said than done … the consumer base, complexity of network & geographical spread being large, it’s a real challenge !!!
Key Requirements for DF arrangement
63
Key Requirements for DF Arrangement
Huge Capital expenditure is required to renovate and modernize the
network
Depreciation rates should be as per CERC norms
Longer tenure (20 to 25 years) increases the investment by Franchise
thereby increasing the pace of reforms
Franchise should have appropriate customer mix and have sufficient load
to have benefit of scale of operations (Input Energy of 2500 MUs per year)
Area will attract the large and experienced players &Tenure will attract the required level of investment from them.
64
Key Requirements for DF Arrangement
The required power should be made available
• Despite the marked improvement brought in Bhiwandi, change not visible as load shedding continues
• Customers want quality power 24 x 7
• Availability of adequate upstream infrastructure (Transmission Capacity) to cater to the demand in the franchise area
• Distributed Generation based Dist Franchisee is a step in the right direction
Franchise should be provided with adequate power so that the benefits of the improvement are realized
65
Key Requirements for DF Arrangement
In Franchise, the overall control lies with Distribution company but to ensure success, independence in operations should be given to Franchisee
• Right to do Capital Expenditure at its own discretion
Only then can a franchisee bring in the required level of improvement in the system which is the main objective of franchising an area
• Rights under section 126,135 of Electricity Act 2003 to stop theft
• Non – interference in day-to-day activities
Franchise should be given the rights as long as it follows the orders of Regulatory Commission and the prevalent laws of land
66
Key Requirements for DF Arrangement
Adequate support from the State Discom
• Manpower (On deputation from Licensee)
List of interested employees to be made available to DF
DF should have the right to select / reject from the list without assigning any
reason
Term of Deputation to be mutually decided
Employee on deputation cannot go back on their own
• Coordination with local authorities / Govt. bodies
Support of Govt , Discom and general public is essential for success of DF
67
Key Requirements for DF Arrangement
For certain statutory / regulatory processes, Franchisee should be considered
independent of licensee
• Levy of Service Line Charges
• Accelerated Power Development and Reforms Programme
• Regulator has to recognise the locus standi of the franchisee so as to ensure that
interests of the customers of the franchise area are protected
Franchisee should have the right to approach the regulator wherever required
Thank you