Contents Informaon Sheets Decision Tree for Distributed Generaon Connecon Guides Connecon Process—Capacity Cut Off Points Provision of Informaon: DNO Websites Legislave and Regulatory Documents Hierarchy Distributed Generaon Connecon Guide An Introducon Is this the right Guide for my project? Changes to Regulaons A: A Guide to the GB Power Sector B: The Role of Distributed Generaon C: An Overview of Geng connected D: The Connecon Applicaon: Connecon Noficaon E: Costs and Charges F: Selling electricity: Feed-in Tariffs Glossary References Revisions Distributed Generaon Connecon Guide: Contents

Upload: others

Post on 26-May-2020

33 views

Category:

Documents


0 download

TRANSCRIPT

Contents

Information Sheets Decision Tree for Distributed Generation Connection Guides Connection Process—Capacity Cut Off Points Provision of Information: DNO Websites Legislative and Regulatory Documents Hierarchy

Distributed Generation Connection Guide An Introduction Is this the right Guide for my project? Changes to Regulations

A: A Guide to the GB Power Sector

B: The Role of Distributed Generation

C: An Overview of Getting connected

D: The Connection Application: Connection Notification

E: Costs and Charges

F: Selling electricity: Feed-in Tariffs

Glossary

References

Revisions

Distributed Generation Connection Guide: Contents

i

Distributed Generation Connection Guide: Information Sheets

The following pages contain a number of information sheets. These bring information that is contained throughout the Guide into a single page. The information sheets include: • Decision Tree for the Distributed Generation Connection Guide—to help you to identify

whether this is the right Guide for you. • Capacity cut off points—a diagram illustrating the impacts that the generation capacity of

your generating equipment has on the requirements and opportunities for your project. • Provision of Information: DNO websites—a summary of the information you can expect to

find on DNO websites. • Legislative and Regulatory Document Hierarchy—an illustration of document hierarchy,

and list of key documents. You will find the Guide introduction and contents after these information sheets.

ii

Decision Tree for the Distributed Generation Connection Guide

Number of premises In how many premises are you planning to install Micro-generators:

• within 500m of each other; or

• with the same postcode (ignoring the final two letters)?

Yes

1 More than 1

Size of your generating unit within any single premises Does your Power Generating Module (PGM) (or the aggregation of modules if there are more than one) have a capacity of 16A per phase or less, and is it connected at low voltage? In other words:

• Three phase—generation capacity of 11.04kW or smaller and connected at 400V

• Single Phase—generation capacity of 3.68kW or smaller and connected at 230V

There are a number of Distributed Generation Connection Guides, each with a corresponding ‘Summary’ guide. The purpose of the summary guides is to act as a quick check, providing only the most useful information in a condensed format. This flowchart guides you to the most relevant Connection Guide for the Distributed Generation you are planning to install. The Guides can be found on the Distribution Generation section of the ENA website.

No

No

Guide for EREC G99 Type A Power Generating Modules

Guide for EREC G99 Types B to D Power Generating Modules

Guide for EREC G98 projects on

Multiple Premises

Guide for EREC G98 projects for Single Premises

Size Does your Power Generating Module have a registered capacity of less than 1 MW ?

Simplest process Most complex process

Examples of Distributed Generation that is 16 A per phase or less PV system: If you are installing solar panels on the roof of your home (or another similar building), it is likely that your project will be less than 16 A per phase, particularly if your array is about 30 m2 or less; or about 18 panels or fewer.

Wind: Many small wind turbines are also less than 16 A per phase. For example:

• QR5 turbine: Rated 6.5 kW with a rotating section of 5 m height • Bergey wind turbine: Rated 10.0 kW with a diameter of 7 m

Combined Heat and Power (CHP): A micro-CHP plant rated 6 kW (3-phase) (the size of a big dishwasher 0.8 x 1 x 1 m) could have a thermal output of 18 kW.

Projects can no longer connect under EREC G83 and EREC G59.

Yes

Does your Power Generating Module have a connection point below 110 kV ?

Yes No

iii

Connection Process

Size Definitions

Generation Licencing

Metering Incentives Schemes Single

Phase Three Phase

North Scotland

South Scotland

England and

Wales

Section C Sections C and D Section D Section E Section F

3.6kW

11.04kW

10MW

30MW

100MW

30kW

50kW

5MW

50MW

100MW

Covered by G98 if connected at

low voltage (230V or 400V)

and type tested.

G99 Type A

Power Generating Facility Power Generating Facility owner may chose to have an agreement

with NGESO, in order to make use of the transmission system or

to participate in the balancing market.

Large Power Station Must hold an

agreement with NGESO—BEGA or

BELLA.

Large Power station Must hold a Bilateral Embedded Generation Agreement (BEGA)

with NGESO.

Medium Power Station

Do not need a generation

licence.

Must hold a generation

licence, unless exempt.

Must hold a generation

licence.

FITs (Feed-In Tariffs) if

technology is eligible.

CFD (Contracts

for Difference) Projects in

the order of several MW

Usually will have Non-Half

Hourly metering.

Must have Half

Hourly metering.

Smaller Power

Stations

Larger Power

Stations

Smaller Power

Stations

Larger Power

Stations

Connection Process: Capacity Cut Off Points

The tasks that you have to undertake to get connected vary with the capacity of the generating plant. In general, the bigger the generator, the more complex the connection requirements.

The table below illustrates some of the impacts that the capacity of your generating units have on the connection process and requirements on you.

G99 Type D

G99 Type C

1MW

G99 Type B

50MW

iv

Provision of Information: DNO Websites

There is a great deal of published information available from your DNO that can be helpful for your project planning. Some of the most useful sources are summarised here, and links to the DNO websites are in the table below.

Long Term Development Statement (LTDS) Covers the development plans for the network, and other information useful for prospective developers. An introductory chapter is generally available on the DNO’s website and DNOs will give access to the full document on request. These documents are updated every six months, and published annually.

Connection Charging Documents Statements and methodologies will be given for both connection charges and Use of System (UoS) charges. This information may be included in a single document, or in several, and are updated regularly. These are available on DNO websites.

Distributed Generation “Work Plan” The Incentive for Customer Engagement (ICE) exists to encourage DNOs to engage with and respond to the needs of major connections customers (which includes generation customers), and includes a requirement on DNOs to set out plans on what improvements they plan to make in the next regulatory year, consisting of two parts. Part 1 covers plans for improvements for the forthcoming year; and Part 2 reviews the progress in the previous year. Check your DNOs Distributed Generation web pages.

Standards of Performance Ofgem has set minimum performance standards for connections, both during and after their construction. If your DNO fails to meet these standards, you may be entitled to receive payment. Ofgem has guidance documents about these Standards on their website: www.ofgem.gov.uk/licences-codes-and-standards/standards/quality-service-guaranteed-standards

Region DNO Website

North Scotland, Southern England SSE Power Distribution www.ssepd.co.uk

South Scotland, Cheshire, Merseyside and North Wales SP Energy Networks www.spenergynetworks.com

North East England and Yorkshire Northern Powergrid www.northernpowergrid.com

North West Electricity North West www.enwl.co.uk

East Midlands, West Midlands, Southern Wales, South West England

Western Power Distribution www.westernpower.co.uk

Eastern England, South East England, London UK Power Networks www.ukpowernetworks.co.uk

Other Supporting Information Provided by DNOs In recent years, there have been improvements to the information that DNOs provide, including: • web portals and decision support tools/application hotline; • capacity “heat maps”, indicating areas that can more readily facilitate connections; • holding events such as “open surgeries” for Distributed Generation customers; and • more details provided on outages (planned and historic).

v

KEY: Indicates where a document feeds into or influences another. Document Category:

Legislative and Regulatory Documents Hierarchy

The following diagram shows the legislative and regulatory documents in the power sector. These are grouped by category, and where possible the relationship between documents is illustrated. The documents have been colour coded by document category. The most relevant examples of each documents are included in the boxes below.

Acts Licences

Code

Regulations

Standards Agreements / Statements

Tariff regulation

Policy

Renewable Energy Programmes

LICENCES

CODES

TECHNICAL STANDARDS

REGULATIONS

AGREEMENTS AND STATEMENTS

TARIFF REGULATION

GOVERNMENT POLICY

RENEWABLE GENERATION INCENTIVES

PERFORMANCE STANDARDS

ACTS OF PARLIAMENT

ACTS OF PARLIAMENT:

• Electricity Act 1989

• Utilities Act 2000

• Energy Act 2004 (BETTA go-live direction)

• Energy Act 2008 (FITs etc.)

• Energy Act 2013 (CfD etc.)

REGULATIONS:

• Electricity Safety, Quality and Continuity Regulations 2002

• The Electricity (Standards of Performance) Regulations 2015

LICENCES:

• Generation

• Transmission

• Distribution

• Supply

GOVERNMENT POLICY:

• The Clean Growth Strategy 2017

• Upgrading our Energy Systems: Smart Systems and Flexibility Plan 2017 (also 2018 update)

TECHNICAL STANDARDS

• Engineering Recommendations

• Security and Quality of Supply Standard (SQSS)

CODES

• Balancing and Settlement Code

• Connection and Use of System Code

• Distribution Code

• Grid Code

• System operator – Transmission owner Code (STC)

AGREEMENTS AND STATEMENTS

• Connection Agreements

• Charging Statements

• The Distribution Connection and Use of System Agreement

• Master Registration Agreement

TARIFF REGULATION:

• Ofgem Price Controls

PERFORMANCE STANDARDS:

• Guaranteed standards and DG standards

RENEWABLE GENERATION:

• FITs and CfD

EU LEGISLATION

EU NETWORK

CODES

EU Legislation

EU NETWORK CODES

• Requirements for Generators

• Demand Connection Code

• System Operation Guidelines (SOGL)

PERFORMANCE STANDARDS

• Guaranteed standards and DG Standards

EU LEGISLATION:

• EC No 714/2009

Page 1

Who is this Guide for?

This Guide is intended to help you, as a developer or the prospective owner of Distributed Generation, to connect your generating unit to a distribution network in Great Britain. It may also be useful for installers or manufacturers of distributed generation equipment.

The types of generation that most frequently connect to the distribution networks include:

• renewable energy projects;

• waste to energy projects;

• energy storage devices (e.g. batteries); and

• on-site generation and Combined Heat and Power (CHP) projects.

What is the aim of the Guide?

The main aim of the Guide is to provide a ‘route map’ of the processes for getting a generation project connected to the distribution network. The Guide provides an overview of the connection process, as well as more details on the application stage.

The connection process involves discussions and agreements between you and your Distribution Network Operator (DNO). This process is more likely to be successful if you and the DNO can communicate effectively and understand each other’s concerns. So, in addition to its main aim of providing a ‘route map’ of the connection process, the Guide has a number of other aims:

• to provide background information about the GB power sector and the role Distributed Generation has to play;

• to describe the main factors affecting connection costs and ongoing charges;

• to highlight your options relating to your connection works, identify different contracts relating to your connection and discuss some day-to-day operational issues; and

• to describe two key financial incentives for Distributed Generation: Feed-in Tariffs (FITs) and Contracts for Difference (CFD).

What is not covered in the Guide?

In addition to arranging a connection to the network, you will also have other issues to address in order to get your project up and running. These include:

• Designing, installing and operating the generation installation

• Buying and selling electricity (beyond FITs and CFDs)

• Planning the project

• Financing the project

• Resolving local planning issues

These issues are outside the scope of this Guide, but you will need to about these in parallel with the connection process.

Note that this document covers the process for connecting generation to the distribution networks in Great Britain. Northern Ireland has different connection arrangements, for example different versions of Engineering Recommendations G98 and G99 are in use. For more information, refer to the Northern Ireland Electricity website: www.nie.co.uk

Distributed Generation Connection Guide: An Introduction

Page 2

The format of the Guide

This Guide has been written and formatted with you, the reader, in mind. In particular we think this Guide will be useful for customers with generation, installers and developers. We have tried to make this Guide as clear and easy to read as we can, bearing in mind that some of the issues discussed are technical and complex. In particular:

• Terms which may be unfamiliar are defined or explained in boxes around the main text.

• Key points and summaries are highlighted.

• Text is emboldened for emphasis.

• Where necessary the Guide distinguishes between the arrangements that apply in Scotland and those which apply in England and Wales. This is indicated with a Scottish flag.

• At the end of most chapters there is a pointer on where to find more information.

Though this Guide is intended for the general public and should not require the reader to be technical or familiar with the energy industry, please be aware that the topics covered here are technical and complex. It is therefore necessary to refer to such concepts as voltage and power. Where possible, terms that may be unfamiliar have been explained.

Governance of the Guide

This Guide is a Distribution Code Review Panel (DCRP) document. The DCRP will update the Guide using similar processes it has for updating other distribution related documents.

There are many areas of regulation and legislation relating to Distributed Generation

which are evolving and a number of issues are under consultation. The Guide has tried to capture the most up to date position at the time of writing. However, for the most up to date information you should refer to key documents and organisation websites. Please see the reference section for more information.

Governance of related Codes and documents

Many of the codes and other documents described in this guide are governed in such a way that any interested and materially affected party can propose a change to the codes and documents. This includes the Connection and Use of System charging arrangements (for both distribution and transmission) and the Distribution and Grid Codes. There are also groups with Distributed Generation community and DNO representation where issues can be raised and discussed which may lead to changes being proposed.

The overarching group to discuss commercial and procedural issues associated with connection is the ENA DER (Distributed Energy Resources) Connections Steering Group. Any issues you have for the Group should be raised through trade associations who are represented. Please note that practices between DNOs may be different; for example where the connection requirements are location specific or the connection risks and the network characteristics are different.

Distributed Generation Connection Guide: An Introduction

Page 3

The process of connecting Distributed Generation to the electricity distribution network varies depending on the size of the generation to be connected, and the specific technology to be used. In general, the larger the generation capacity, the more complex the process.

The Engineering Recommendations that cover the connection of Distributed Generation to the electrical distribution network are: EREC G98 (for smaller generation capacities) and EREC G99 (for all other projects). These are described further in the information boxes on the following pages.

A number of a Guides have been developed:

• EREC G98 compliant units in a single premises;

• EREC G98 compliant units in multiple premises within a close geographic region;

• Guides for G99 installations

A “summary” version of each Guide, containing the minimum, essential

information from each chapter, is also available—refer to the ENA website.

The table on the next page includes a quick check for finding the right Guide for you. Read the information boxes for further explanations of terms that may be unfamiliar to you. Where you are installing multiple generating units, the application process (ie EREC G98 ) is based on the total installed capacity of the generating units in each premises, how many premises equipment will be installed in, and whether each unit is type tested. Alternatively you can connect new generating units under EREC G99—refer to the G99 Guides.

Distributed Generation Connection Guide: Is this the right Guide for my project?

Important note: Generation projects can no longer connect under EREC G83 and G59. Generation will only be allowed to connect under EREC G98 and G99, with an exception for certain generators. For more information on this transition, refer to “Recent Changes to Regulations” page—just before Chapter A.

Page 4

Guide Criteria

A guide for connecting Distributed Generation that falls under EREC G98 in a single premises

Installation of one or more Distributed Generation units at a single premises.

Distributed Generation is compliant with EREC G98 if: • It meets the size definition of Micro-

generator; • It is installed in accordance with

EREC G98. Your installer should be familiar with these requirements; and

• It has been tested and approved according to the relevant Type Testing Annex in EREC G98.

A guide for connecting Distributed Generation that falls under EREC G98 in multiple premises

Installation of Distributed Generating units at more than one premises within a close geographic region.

A guide for connecting Type A Power Generating Modules under EREC G99

This Guide is written for installations where:

• The registered capacity of each Power Generating Module is >16 A/phase, but less than 1 MW; and

• The connection point is below 110 kV (in practice in GB this is at 66 kV or below).

A guide for connecting Type B—D Power Generating Modules under EREC G99

This Guide is written for installations where the registered capacity is at or above 1 MW, or for any generation connected at or above 110 kV (in practice in GB this is at 132 kV or above).

Distributed Generation Connection Guide: Is this the right Guide for my project?

Page 5

Distributed Generation Connection Guide: Is this the right Guide for my project?

Engineering Recommendation G98 EREC G98 is called “Requirements for the connection of Fully Type Tested Micro-generators (up to and including 16 A per phase) in parallel with public Low Voltage Distribution Networks”. It sets out the requirements you must meet before your Micro-generator can be connected to the network. The capacity threshold refers to the aggregate generating capacity installed in a single premises. EREC G98 is available on the Distribution Code website.

The document is aimed at the manufacturers and installers of your Micro-generator.

Engineering Recommendation G99 EREC G99 is called “Requirements for the connection of generation equipment in parallel with

public distribution networks”. The purpose of the document is to provide guidance to you and

to DNOs on all aspects of the connection process. It contains a glossary of items and diagrams

of Power Generating Module types and categorisation, which you may find helpful. EREC G99

is available on the Distribution Code website.

Micro-generator A Micro-generator is defined in EREC G98 as “A source of electrical energy and all associated interface equipment able to be connected to an electric circuit in a Low Voltage electrical installation and designed to operate in parallel with a public Low Voltage Distribution Network with nominal currents up to and including 16A per phase. For the avoidance of doubt this includes electricity storage devices”. 16 A per phase corresponds to 3.68 kW on a single-phase supply and 11.04 kW on a three-phase supply, and refers to the aggregate Micro-generator capacity installed in a single premises.

Close Geographic Region Typically, a Close Geographic Region is one which is fed by the same part of the distribution network, from a single feeder or distribution transformer. Your DNO will be able to advise you as to whether your installation sites are within a close geographic region. A general rule of thumb is that if your installations are within 500 meters of each other, or if the post codes are the same at least up until the last two letters, then they are likely to be within a close geographic region.

Page 6

Distributed Generation Connection Guide: Is this the right Guide for my project?

Inverters An inverter is an electrical device that converts Direct Current (DC) to Alternating Current (AC). This is required when you want to connect a generating unit with a DC output (eg. a Photovoltaic array) to the distribution network, which operates at AC. The term Micro Inverter is used to describe small inverters which are connected to (multiple) small generating units, such as individual PV panels. This is often done so that if one panel is impaired for any reason, then the output of the others is not affected. As with any installation with more than one generating unit, the application process is dictated by the aggregate capacity of all generating units and not the individual units.

Type tested equipment Type tested equipment is defined in EREC G98 and G99 as “A product which has been tested to ensure that the design meets the relevant requirements of this EREC G98/G99, and for which the Manufacturer has declared that all similar products supplied will be constructed to the same standards and will have the same performance”. Examples of products which could be type tested include generating units, inverters and the interface protection. Using type tested equipment simplifies the connection and commissioning process. EREC G98 and G99 annexes contain methodologies for testing equipment against a set of test

conditions to demonstrate compliance. The manufacturer produces a Type Test or

Compliance Verification Report to demonstrate compliance. Where the whole Micro-

generator or Power Generating Module is type tested (rather than just a part), it is Fully Type

Tested. All Micro-generators connecting under EREC G98 must be Fully Type Tested. The Fully

Type Tested concept also applies in EREC G99.

The ENA hosts an online Type Test Verification Report Register. This contains certificate and test documentation for generation products and enables product identification and information sharing. The product manufacturer is responsible for uploading and maintaining data and documentation relating to their products. You can access the register at: http://www.ena-eng.org/gen-ttr/

Equipment Certification The ENA are working with potential Equipment Certificate providers and manufacturers to investigate formal equipment certification. This will be progressed throughout 2019.

Page 7

Distributed Generation Connection Guide: Is this the right Guide for my project?

Emerging Technology

EREC G98 and G99 have a relaxed set of requirements for generation that is classified as an

Emerging Technology. This is because the Requirements for Generators (RfG) allows for

this. The Emerging Technology status only applies to Type A generation, which has a

generating capacity of 0.8 kW to 1 MW and is connected at less than 110 kV (in practice in

Great Britain that is 66 kV or below). The Emerging Technologies are:

• ‘Baxi Ecogen’ generators (the specific products are the Baxi Ecogen 24/1.0, Baxi Ecogen 24/1.0 LPG and Baxi Ecogen System)

• KD Navien stirling engine m-CHP (Hybrigen SE) (the specific products are the ‘NCM-1130HH – 1 KWel’ and the ‘NCM-2030HH – 2 kWel’)

• Pellematic Smart_e

• Dachs Stirling SE Erdgas and Dachs Stilring SE Flussiggas

Page 8

Recent Changes to Regulations Requirements for Generators

The European Third Energy Package was adopted in July 2009, and has been law since March 2011. The Third Energy Package refers to a suite of legislation for both Electricity and Gas. It has three key objectives:

1. Enhancing sustainability and helping the European Union meet its decarbonisation obligations;

2. Ensuring security of supply in light of a changing generation mix; and

3. Creating a single European Market for Electricity.

The Third Energy Package requires the development of European Network Codes. The Network Codes cover three areas: grid connection codes; market codes and system operation codes. One of the Codes is called Requirements for Generators (RfG). This sets out requirements which new generators will need to meet.

The RfG, which became a binding EU regulation in May 2016, is available on the EUR-Lex website.

A joint Distribution Code Review Panel (DCRP) and Grid Code Review Panel (GCRP) workgroup was charged with implementing the Requirements for Generators in GB. This included setting parameters that the RfG leaves to national interpretation. The workgroup proposed changes to the Grid Code, Distribution Code and supporting Engineering Recommendations. The revised documents were consulted upon with stakeholders by the GCRP and the DCRP.

This work resulted in the publication of Engineering Recommendations G98 and G99, as well as revisions to the Distribution Code and Grid Code. These new EREC documents apply to generation that is connecting to the distribution network. The old EREC G83 and EREC G59 should no longer be used after the 27th April 2019.

Page 9

Key Terms for EREC G98 and G99 In the process of drafting EREC G98 and G99, the opportunity was taken to align with European terms used (eg from the Requirements for Generators document) and to consolidate terms previously used in GB documents. This means some new terms have been introduced, which are used widely in the documents. The key terms are summarised on this page, and some are explained further in break out boxes throughout the document or in the main text.

Terms that are particularly relevant for EREC G98 are indicated with a *.

Fully Type Tested* The whole Micro-generator / Power Generating Module is type tested, rather than just part of the Micro-generator / Power Generating Module.

Micro-generator* A source of electrical energy and all associated interface equipment connected at Low Voltage to the distribution network, with nominal currents up to and including 16 A per phase.

Micro-generating Plant* An electrical installation with one or more Micro-generators with nominal currents in sum not exceeding 16 A per phase.

Generating Unit Any apparatus that produces electricity.

Power Generating Module (PGM)

Either a Synchronous Power Generating Module (SPGM) or a Power Park Module (PPM) - see below.

Synchronous Power Generating Module (SPGM)

An indivisible set of Generating Units—ie one or more units which cannot operate independently of each other—which generate electrical energy in

Power Park Module (PPM) Generating Units that are connected to the network either through power electronics (eg solar PV or electricity storage devices connected through an inverter) or asynchronously (eg some wind turbines are induction or asynchronous generation). They have a single Connection Point to the

Power Generating Facility (PGF)

One or more Power Generating Modules connected to at one or more Connection Points.

Registered Capacity The normal full load capacity of a Power Generating Module less the MW consumed when producing the same (ie auxiliary load). For Power Generating Modules connected via an Inverter, the Inverter rating is the

Type A / B / C / D Classifications of Power Generating Modules by size and connection

Page 10

A: A Guide to the GB Power Sector

In this section: • An overview of the commercial structure of the power sector • An introduction to the GB power sector and how it is changing • A discussion about the various types of organisations that you may

come across while developing your Distributed Generation project • A discussion on Network Innovation projects • Guidance on where to find more information

Tip: Read the information boxes for definitions or explanations of terms that may be new or unfamiliar.

Introduction Understanding a little about the GB power sector may be useful when discussing your Distributed Generation project. This section aims to give some background explanation about the GB power sector and how it is changing to meet the challenges of protecting the environment and changing Government policy.

There are many organisations involved in the GB power sector, which are introduced in this section.

Apart from the physical structure of the power sector, there is also a commercial structure, which is discussed in this section.

The Commercial Structure of the Power Sector

The commercial structure of the electricity industry in Great Britain provides a competitive market in electricity retailing. This enables customers to contract with any one of a number of competing electricity suppliers. The sale of energy is also a competitive market. Note, your Feed-In Tariff level is an indication of the minimum you can expect to be paid for the electricity you generate.

Generators sell the electricity that they generate in the wholesale market or directly to suppliers. Suppliers sell the electricity they purchase to customers. The majority of trading occurs in advance of the time of use.

The wholesale market is governed by British Electricity Trading Transmission Arrangements (BETTA), which was introduced in 2005.

If you install Distributed Generation you can use the electricity you produce on site to reduce the amount of electricity that you need to buy thus lowering your electricity bills.

You can also sell electricity to customers, suppliers or, depending on the size of the generation, on the wholesale market. You can read more about power trade options in Section F. Selling Electricity.

Page 11

Transmission System

Power Stations Mostly large coal, gas and nuclear

power stations.

Distribution System

Other Distribution

Systems

Loads

‘Grid Supply

Point’

The distribution system carries the electricity to loads, such as homes and businesses.

The transmission and distribution systems are also called transmission and distribution networks. Both terms are used in this Guide.

The Physical Infrastructure of the Power Sector

These arrows show the normal direction of the flow of

electricity through the system.

In a traditional power system, electricity flows from large

generation sites, through the transmission and distribution

networks, to the loads.

Transports electricity over long distances across the country. Electricity is transported at a high voltage to reduce losses. Voltage Range: 275kV or 400kV. In

Scotland, 132kV is also used.

This symbol

represents a

transformer. These

are used throughout

electricity networks

to change voltage

levels.

Transports electricity from the Transmission System to loads like homes and businesses. The voltage is reduced to the correct supply voltage for the loads. Voltage Range: 132kV and lower in England and

Wales, or lower than 132kV in Scotland. Most

residential customers are supplied at 230V.

Traditional electricity system The diagram below illustrates the infrastructure of the traditional power sector.

Large power stations feed into the transmission system, and the electricity is then transported to the distribution system.

Page 12

Transmission System

Power Stations A mix of energy sources, including

renewable and conventional sources.

Distribution System

Other Distribution

Systems

The Physical Infrastructure of the Power Sector Changing electricity system

In addition to the large power stations connected to the transmission system, an increasing number of small power stations are being developed, often connected to distribution networks. Generation connected to the distribution network is called Distributed Generation. The diagram below illustrates this changing electricity system.

The direction of electricity flow becomes more dynamic

and often less predictable with the increase of

Distributed Generation. This will require more active control of the networks.

Loads Distributed Generation

Distributed Generation (DG or ‘Embedded Generation’) A generation project is classed as Distributed Generation if it operates while electrically connected to the distribution network. Energy generated from Distributed Generation may be used onsite, or some or all of it may be exported to the distribution network.

Distributed Generation can result in electricity flows in both directions; from the distribution network to customers, and from customers with Distributed Generation back into the distribution network. The system is no longer a “waterfall” system, with electricity flowing from the large power stations in one direction towards customers. Instead, electricity flows are more unpredictable.

Page 13

Key Organisations The transmission and distribution systems are owned and operated by regulated monopoly businesses. Transmission and distribution businesses recover the costs of operating and maintaining their systems by levying Use of System charges on electricity traded using their network.

Distribution Network Operator (DNO) A DNO owns, operates and maintains public electricity distribution networks in one or more regions in the GB. They must hold a Distribution Network Operator Licence. Under the terms of their licence, each DNO is allowed to distribute electricity both inside and outside its legacy geographic area.

There are six DNOs in Great Britain. The regions where they operate are shown on the map below.

To facilitate competition in supply, each DNO is required to allow any licensed supplier to use its distribution network to transfer

Map of DNO regions in the UK: For DNO website details, please see the membership area of the ENA website.

electricity from the transmission system (and from Distributed Generation) to customers. DNOs charge suppliers for using the distribution system.

DNOs can form part of a group that undertakes other areas of business as well, e.g. electricity supply. However, these businesses have to be kept separate, and you, as a developer, will have to interface with the network operator business.

Independent Distribution Network Operators (IDNOs) An IDNO designs, builds, owns and operates a distribution network, which is an extension of an existing DNO network. They typically build network for new developments such as business parks and residential areas. IDNOs differ from DNOs in that: • they do not have service areas (they are

not tied to a geographical location); • they are regulated like DNOs, though

have fewer licence conditions to meet.

Page 14

Key Organisations If you are connecting your Distributed Generation to an IDNO’s network, the process is almost identical to that if you are connecting to a DNO. There are a few exceptions to this, which are discussed in Section C of this Guide.

Transmission Owner (TO) A TO owns and maintains the high voltage transmission system, known as the National Electricity Transmission System, referred to in this Guide as the transmission system. Transmission Owners are responsible for making sure that transmission services are available to the System Operator (see explanation later in this section). The Transmission Owners are as follows:

• National Grid Electricity Transmission (NGET) in England and Wales

• SP Energy Networks (SP Transmission plc)

• Scottish and Southern Electricity Networks (Scottish Hydro Electric Transmission plc)

Private Networks Private networks are similar to IDNO networks in that they are extensions of the DNO network which are not owned by the DNO itself. The owners of private networks are distinct from an IDNO because they do not need to be licenced and are unregulated.

For example, private networks can be owned by hospitals, airports, industrial sites, etc. This Guide is not intended to address connections to private networks. If you are connected to a private network, you should discuss your plans with the network owner as soon as possible.

Suppliers Supply is the retail of electricity. Suppliers buy electricity in bulk from generators, and then sell to consumers. They are responsible for providing bills and customer services, and arranging metering and meter reading. Electricity supply is a competitive market so

you can choose and change your electricity supplier.

Aggregators Aggregators specialise in co-ordinating demand and generation (including storage) to provide demand response and other market services. The Network Operators and Suppliers may buy demand response and other grid balancing services from aggregators. Energy Service Company (ESCO) A Government paper defines ESCOs as “a company that provides a customer with energy solutions” rather than simply being an electricity or gas supplier. ESCOs can enter into long-term contracts to provide information, installation, finance, operation and maintenance. There are various models the ESCO can take. ESCOs can work on a performance contract, where they guarantee energy savings and make charges based on the extent to which these savings are achieved. This model is typically used by commercial and industrial customers. ESCOs can also work for communities, servicing a group of customers in the same local area.

ESCOs may develop into a household model, to provide energy efficiency savings and small scale generation for home owners, rather than just supplying electricity.

Generators Generators own, operate and maintain power stations which generate electricity from various energy sources, eg. coal, gas, hydro and nuclear. Newer generation technologies include wind, solar, tidal and wave. See the end of this section for links to more information on generating technologies.

Page 15

Example MPAN, with first two digits indicated

To identify your DNO or IDNO:

If you already have a meter at your site, find the first two digits of your MPAN (Meter Point Administration Number), which is shown on your electricity bill, and may be shown on your meter. This corresponds to your DNO or IDNO, see table below.

If you do not have a meter at your site, you can contact the DNO whose geographic area you believe you are in and they will be able to confirm. See the map on page 13.

Key Organisations

First 2 MPAN digits

Service Area Distribution Business

10 Eastern England UK Power Networks– Eastern England

11 East Midlands Western Power Distribution (WPD) – East Midlands

12 London UK Power Networks (UKPN) – London Power Networks (LPN)

13 Cheshire, Merseyside and North Wales

SP Energy Networks – Cheshire, Merseyside and North Wales

14 West Midlands Western Power Distribution (WPD) –West Midlands

15 North Eastern England Northern Powergrid (NPG)

16 North Western England Electricity North West (ENW)

17 Northern Scotland SSE Power Distribution – Scottish Hydro Electric Power Distribution

18 Southern Scotland SP Energy Networks

19 South Eastern England UK Power Networks (UKPN) – South Eastern Power Networks (SPN)

20 Southern England SSE Power Distribution – Southern Electric Power Distribution

21 Southern Wales Western Power Distribution (WPD) – South Wales

22 South Western England Western Power Distribution (WPD) – South West

23 Yorkshire Northern Powergrid (NPG)

24 No area—IDNO GTC (Independent Power Networks)

25 No area—IDNO ESP Electricity Limited

26 No area—IDNO Energetics Electricity Limited

27 No area—IDNO GTC (The Electricity Network Company)

29 No area—IDNO Harlaxton Energy Networks Limited

30 No area—IDNO Leep Electricity Network Limited

31 No area—IDNO UK Power Distribution Limited

32 No area—IDNO Energy Assets Networks Limited

33 No area—IDNO G2 Energy IDNO Limited

34 No area—IDNO Murphy Power Distribution Limited

35 No area—IDNO Fulcrum Electricity Assets Limited

36 No area—IDNO Vattenfall Network Limited

Tbc. No area—IDNO Utility Assets Limited

Page 16

Key Organisations System Operator (SO)

Electricity cannot be stored at a large scale and so demand has to be balanced with generation on a second by second basis by the System Operator. The SO makes requests of generators to increase or decrease output from their units, or may ask some large customers to control their demand. NGESO is the System Operator in Great Britain. Following a government consultation on greater separation between the System Operator role performed by National Grid and the rest of the National Grid group, National Grid has established a new, legally separate company to carry out the Electricity System Operator function within the National Grid Group, which is called the National Grid Electricity System Operator (NGESO). This separation took place on 1st April 2019.

Balancing Settlement Code company

Elexon is the company that manages the balancing and settlement of electricity trading. They do this by identifying where generators have not generated the amount of electricity they are contracted to produce, and suppliers’ customers have not consumed the amount of electricity that was expected. Out of balance parties are charged based on the additional cost to balance supply and demand (often by buying or selling electricity at short notice).

The Balancing and Settlement Code (BSC) governs the operation of this balancing mechanism.

Regulator

The Office of Gas and Electricity Markets (Ofgem) is responsible for:

• regulating prices and performance in the monopoly elements of the electricity supply industry;

• resolving disputes between different parties when necessary; and

• granting licences for the following activities in the power sector:

− Generation

− Transmission (and interconnection, a transmission link with another country)

− Distribution

− Supply

Generation licence requirements for Distributed Generation are discussed in Section D. The Connection Application: Generation Licensing.

European organisations

The regulatory arrangements that apply across continental Europe are implemented by National Regulator Authorities (NRA) in each member state of the European Union; Ofgem is the National Regulatory Authority for Great Britain. The regulations are required to comply with policy criteria determined by the European Parliament and implemented through European Directives and Regulations. To assist with this process in relation to electricity networks, a number of bodies have been set up that represent regulators and transmission system operators. National Energy Regulators work with the Agency for the Cooperation of Energy Regulators (ACER) and the Council of European Energy Regulators (CEER) on policy developments in different areas of electricity market liberalisation.

ENTSO-E, the European Network of Transmission System Operators for Electricity, is a membership body for Transmission System Operators (TSO). ENTSO-E promotes cooperation across Europe’s TSOs. One of ENTSO-E’s roles is drafting the European Network Codes, which includes the Requirements for Generators (RfG).

The UK’s membership in these agencies post-Brexit will be subject to negotiations.

Page 17

Network Innovation and Industry Developments Innovation Funding

New challenges and applications in energy networks have motivated many projects that aim to develop innovative tools and products to improve the way networks operate and customers are connected.

Ofgem has a number of mechanisms that the DNOs and other organisations can use to fund electricity network innovation. The two main mechanisms for network companies are called the Network Innovation Allowance (NIA) and Network Innovation Competition (NIC), which apply to both electricity and gas distribution and transmission.

• NIA is an allowance each network company receives to fund smaller scale innovation projects which have the potential to deliver benefits to network customers.

• NIC is an annual competition, where network companies compete for funding for development and demonstration of network innovations such as new technologies or novel operating and commercial arrangements.

Learning from these projects is shared amongst all DNOs and TOs for the benefit of the power sector as a whole. Incorporation of the learning into business as usual practices is laid out in the business plans of the individual network companies.

For more information, and details about individual projects, refer to the Smarter Networks Portal, hosted by the Energy Networks Association:

http://www.smarternetworks.org/

Electricity Network Innovation Strategy

Following a review of the NIA and NIC, Ofgem

proposed a number of changes to the

innovation funding schemes. One of these was

the requirement on network companies to

collaboratively produce an industry wide

innovation strategy. The Electricity Network

Innovation Strategy sets out a jointly agreed

roadmap which demonstrates how innovation

can accommodate future whole-system

requirements and lead to benefits. The

document was first published on 29th March

2018 and will be reviewed every 2 years at a

minimum. Further information is available on

the ENA website.

Transmission and Distribution Interfaces

There has been a significant increase in the amount of connected Distributed Generation in the last few years. This has meant that the DNOs, TOs and the SO have to change the way they work together, to maintain an economic and secure network. In order to address these challenges, the Transmission Distribution Interface (TDI) Steering Group was established by ENA and its members. Network companies recognise the need for distribution and transmission companies to work together more closely in order to consider how they can tackle the whole system impact of Distributed Generation and other technologies such as storage.

In January 2017 the Open Networks Project was launched by the Steering Group. The aim of the Open Networks Project is to transform the way electricity networks operate and provide the first step towards creating a smart grid.

Full details of the work done so far can be found in the Open Networks Project 2018 report. Network companies have consulted on their future structure in a world where they become system operators. The 2018 report contains some case study examples of changes that the network companies are implementing. The work is continuing in 2019.

Page 18

Network Innovation and Industry Development New technologies

Active Network Management (ANM) schemes, which have been trialled in innovation projects, are now being included as part of Business As Usual Connection Offers. ANM uses control systems to manage Distributed Generation in constrained areas. Note that ANM connections may only be available in selected parts of the network.

Export limiting devices are also coming into use. These devices allow a limit to be set above which the generation will not export. This may allow generation to have a constrained connection, to reduce the need for reinforcement. If you want to explore the use of these devices, seek guidance from your DNO. ENA has published Engineering Recommendation (EREC) G100, which provides technical guidance on the connection of Customer Export Limiting Schemes that operate in parallel with the distribution

systems of licensed DNOs. This is available on:

http://www.energynetworks.org/electricity/engineering/distributed-generation/engineering-recommendation-g100.html

Energy storage is becoming increasingly prevalent in distribution networks. For more information on network connected storage (e.g. batteries), refer to Chapter C: Getting Connected—Energy Storage.

Page 19

Where to Find More Information

There are some very good guides to the UK power sector available in the public domain. In particular, if you want to read more on this subject, you may wish to read the following:

• A Guide: Sale of Power Opportunities for Distributed Generators; DTI (Department for Trade and Industry);

• Guidance Note – The Electricity Trading Arrangements: A beginner’s guide; Elexon

www.elexon.co.uk/knowledgebase/about-the-bsc/

A good source of information on the organisations we have introduced are their own websites:

• Energy Networks Association —the industry body for UK energy transmission and distribution licence holders and operators: www.energynetworks.org

• A list of IDNOs can be found on the Ofgem website:

www.ofgem.gov.uk/Networks/ElecDist/Policy/IDNOs/Pages/IDNOs.aspx

• Ofgem—The Regulator: www.ofgem.gov.uk

• National Grid —The Great Britain Electricity System Operator, and Transmission Owner in England and Wales: www.nationalgrid.com/uk/Electricity/

• Elexon—The Balancing and Settlement Code Company: www.elexon.co.uk

For more information on ESCOs, the following document is a useful reference:

• Making ESCOs Work: Guidance and Advice on Setting Up and Delivering an ESCO; London Energy Partnership, which is on the London Energy Partnership website: www.lep.org.uk

The following website gives more information on generation technologies:

• Energy Saving Trust: www.energysavingtrust.org.uk/Generate-your-own-energy

The GB Distribution Code, Annex 1 and Annex 2 documents and the associated GB Distribution Code User Guide can be found in the link below:

• DCode: http://www.dcode.org.uk/

The GB Grid Code and the associated Guide can be found in the link below:

• GCode: http://www2.nationalgrid.com/UK/Industry-information/Electricity-codes/Grid-Code/

Information about licence exceptions and private networks can be found:

• UK legislation: http://www.legislation.gov.uk/uksi/2001/3270/contents/made

Page 20

B: The Role of Distributed Generation

In this section: • An introduction to the role of Distributed Generation • A discussion on the drivers for Distributed Generation • Some of the benefits and impacts of Distributed Generation • References to some documents where you can find out more on these

issues

Introduction As explained in Section A of this Guide, the electricity industry is undergoing changes with increasing amounts of Distributed Generation being connected to the system. There are a number of drivers behind this:

• Environmental issues;

• New Government Policy;

• Security of supply; and

• Technological innovation.

In this section, these drivers are discussed in more detail. We will also introduce some of the benefits and challenges of Distributed Generation.

We refer to some useful documents and reports for further reading on this topic.

What is Driving Distributed Generation? Environmental concerns Globally there has been increasing concern over greenhouse gas emissions and the impact that they may be having on the environment.

Most of the electricity in the UK has traditionally been generated by power stations fuelled by fossil fuels, for example coal, gas and oil. The burning of these fuels makes a significant contribution to emissions.

There is therefore a drive to change the mix of generation technologies we have, to include more low-carbon options.

Technological innovation Technology is developing all the time, and due to drivers such as environmental concerns and government policy, there are more generating technologies available now than there were when the national grid was being developed. For example, wind, wave, solar and biomass generation.

Although the connection and integration of these newer generating technologies may pose challenges, innovative technical solutions are being sought to overcome these challenges. These are discussed on page 17.

Government policy The Department for Business, Energy and Industrial Strategy (BEIS) oversees energy policy and climate change mitigation policy. The UK energy supply is one of BEIS’s key policy areas. BEIS is developing policy to ensure that in the UK energy supplies are secure, low carbon, and fuelled from a diverse mix of energy supplies. However, BEIS also has to ensure that energy prices are maintained at affordable levels. Relevant pieces of legislation include: • Climate Change Act 2008

• Energy Act 2008 • Energy Bill

Page 21

What is Driving Distributed Generation? The Climate Change Act sets out legally binding targets for emissions reductions. As such, policy has been developed, which introduces initiatives such as: • Climate Change Agreement (Climate

Change Levy) • Zero Carbon Homes

As well as legislation from the UK Government, the EU also introduces relevant legislation and initiatives, such as the EU Emissions Trading System and the European Third Package, which is driving a set of new European Network Codes.

Security of Supply The UK increasingly relies on importing fuel, in the form of gas, coal and oil. This introduces a

great deal of uncertainty as the cost and reliability of supply is outside of UK control. It is therefore an advantage to have a diverse mix of energy sources, which would make the UK less vulnerable to a restriction in fuel availability or rise in price.

It is also known that fossil fuels will eventually run out as they are being used much faster than they are being created. As they become more scarce, the prices will rise as the markets become more competitive. Therefore to ensure the security of the energy supply into the future, alternative sources are being encouraged.

Benefits of Distributed Generation There are a number of benefits that increased Distributed Generation has for the UK and its electricity system. These include:

• Increased energy mix —Distributed Generation is often a renewable source of energy, such as solar, wind or biomass, or uses the energy in a more efficient way as with Combined Heat and Power (CHP) projects. Therefore increased Distributed Generation results in a lower carbon mix of energy sources in the electricity system.

• If Distributed Generation is connected close to the point of use, there is a reduced need for the distribution and transmission infrastructure. In some cases, this can delay the need for reinforcement, although the TO and the DNO also need to ensure that the network provides adequate security of supply for its users.

• Where there is a balance between Distributed Generation and local demand the transmission and

distribution losses are reduced, when compared with the alternative of the centralised power stations and bulk transmission of electricity.

• The introduction of local generation in businesses and communities can lead to greater awareness of energy issues.

There are a variety of commercial benefits to having Distributed Generation, which include:

• Self Consumption, where you use the electricity that you generate to avoid importing from the grid, therefore lowering your electricity bills.

• Selling electricity that you generate, including gaining Feed In Tariff (FIT) payments and Contracts for Difference (CFD). This is discussed further in Section F: Selling Electricity.

• Climate Change Levy Exemption Certificates (LECs) are issued to generators of renewable energy and good quality Combined Heat and Power (CHP). These can be sold to the supplier

Page 22

Impacts of Distributed Generation As well as introducing benefits, the increased penetration of Distributed Generation in UK distribution networks also poses challenges. These will depend on a variety of factors, such as the generation technology, the voltage level the Distributed Generation is connected to, the size of the generating unit(s), the level of export to the distribution system, and on the type of network (e.g. urban or rural).

Some examples of the challenges posed to distribution networks by Distributed Generation include: • Distributed Generation changes the

current flows and shape of the load cycle where they are connected. This could cause: • Thermal ratings to be exceeded. • System voltage to rise beyond the

acceptable limits. • Reverse power flows, i.e. power

flows in the opposite direction to

which the system has been designed.

• Distributed Generation can contribute to fault level, which can raise the fault level above the rating of network equipment.

• There are a number of power quality limits that can be affected by Distributed Generation, including: • Contributions to harmonics,

particularly if a significant number of invertor controllers are present.

• Voltage unbalance which affects power quality, if there are lots of single-phase generating units.

• Voltage fluctuation or flicker, if the output of the Distributed Generation changes rapidly.

Note: The technical terms used above are defined in the glossary.

Benefits of Distributed Generation along with the energy generated. Companies can use LECs to avoid paying the Climate Change Levy tax.

• Embedded benefits of the generating unit being connected to the distribution rather than the transmission network, e.g. charge avoidance of Transmission Network Use of System charges and Balancing Services Use of System charges.

• Generators whose equipment has a capacity greater than 3 MW (and/or the ability to deliver in excess of +/- 15 MVAr of reactive power) can enter into agreements with NGESO to provide Ancillary Services, for which they will be paid.

• Generation that is not receiving low carbon support (e.g. Feed-in Tariffs, Renewables Obligation) and does not

have a long-term contract to provide Short Term Operating Reserves (STOR) to National Grid Electricity Transmission could be eligible to enter the Capacity Market, and receive payments for delivering energy at times of system stress.

• EU Emissions Trading System (ETS) - applies to approximately 10,000 energy intensive users in the UK such as metal industry, paper factories and refineries. These large energy users have been allocated green-house gas allowances for their operations. At the end of each year, they must ensure they have enough allowances to cover their emissions: they can buy additional allowances or sell any surplus allowances generated from reducing their emissions.

Page 23

Where to Find More Information The amount of generation connected to distribution networks has increased significantly since 2010. Today there is over 27,000 MW of Distributed Generation in the UK. The benefits and challenges of Distributed Generation are complex, and the industry’s understanding of them is evolving as experience increases. For more information on current initiatives in distribution networks, the following documents are useful:

• The Electricity Networks Innovation Strategy; Energy Networks Association; 2018

• The Open Networks project; Energy Networks Association

The following documents are useful if you want more information on Government policy:

• The Clean Growth Strategy; BEIS; 2017

• Upgrading our energy system: smart systems and flexibility plan; BEIS; 2017

For the most up to date information on relevant Government policy, refer to the BEIS website:

https://www.gov.uk/government/organisations/department-for-business-energy-and-industrial-strategy

For more information on Embedded Benefits, the following document is useful:

• Embedded Generation and Embedded Benefits; Elexon; March 2019

Page 24

C. An Overview of Getting Connected

In this section: • An introduction to getting connected • The main tasks in the process of connecting one or more units within a

single customer’s installation, and who can help you • Guidance on where to find more information

Introduction

In most cases, the installation of small generating units into a single premises will have very little affect on the network. Therefore the connection process is relatively simple, and can be summarised as “fit and inform”.

The diagram opposite presents the key actions that you have to complete to connect one or more units of small-scale generation in a single premises. These tasks are based on the requirements set out in EREC G98 and are described in more detail in this section.

FIND AN INSTALLER

INFORM THE DNO The installer must submit the “Installation

Commissioning Confirmation” form within 28 days of commissioning.

ONGOING RESPONSIBILITIES

INSTALLATION AND COMISSIONING

Note that this document covers the process for connecting generation to the distribution networks in Great Britain. Northern Ireland has different connection arrangements, for example different versions of Engineering Recommendations G98 and G99 are in use. See www.nie.co.uk

EREC G98 was introduced in May 2018. It is based on the archived EREC G83, which was revised

to take account of a European Network Code called Requirement for Generators. Micro-

generators connecting to the distribution network must connect under EREC G98.

Page 25

Installation and Commissioning

Your installer should be aware of the requirements to ensure that installation and commissioning is in line with EREC G98. This includes ensuring that the installation complies with the wiring regulations (BS 7671) and is correctly earthed. Your installer must also ensure, among other things, that:

• No modifications should be made to the equipment;

• Appropriate safety labelling is provided;

• The generating unit will disconnect from the distribution network if your mains power is interrupted; and

• The generating unit is installed in accordance with the manufacturer’s instructions.

During the commissioning, your installer will check that your equipment is working as it should.

Informing the DNO

Once your installation and commissioning is complete, the DNO needs to be made aware of your generating unit(s). This is so that the DNO can take this into account when operating and designing the network. Your installer must notify the DNO within 28 days of commissioning the generating unit, and provide them with information on the installation. This is a legal requirement.

The information is captured on an “installation commissioning confirmation” form, which is given in the “Installation Document”, which is Form B in Appendix 3 of EREC G98. These are available on the Energy Networks Association website.

Note: DNOs may have their own installation commissioning confirmation forms on their websites.

Getting Connected — Main Tasks

Finding an installer

The first task is to find a competent installer, who is using type tested equipment (see note in “Is this the right Guide for my project?”). Installation must be carried out by installers who are competent and have sufficient skills and training to apply safe methods of work to install a generating unit in compliance with EREC G98. This includes having recognised and approved qualifications relating to the primary energy source and general electrical installations. There are companies who design, install and commission domestic generation. They can fully certify and sign off installations. Certified generation products and installers can be found on the following website:

www.microgenerationcertification.org

The Microgeneration Certification Scheme is operated by the Department for Business, Energy and Industrial Strategy (BEIS). Your installer must be certified in order for you to claim Feed-in Tariffs, with the exception of hydro and anaerobic digestion projects, which have to go through the ROO-FIT process. There is more information about this in Section F: Selling Electricity - Feed-in Tariffs (FITs).

All Micro-generators connecting under EREC G98 must be Fully Type Tested. This is where the whole Micro-generator is type tested, rather than just part of the Micro-generator.

Page 26

Getting Connected — IDNO’s Networks

Getting Connected — Energy Storage

Getting Connected — Main Tasks

Ongoing responsibilities

Although the focus of this Guide is to inform

you about the process of connecting your

generation to the distribution network, you

should be aware that once it is connected you

have some responsibilities. These include:

• The responsibility to keep it maintained

by someone who is competent to do so;

• Notify your DNO of any operational

incidents or failures that affect your

compliance with EREC G98; and

• Inform your DNO if you remove or

replace you generating unit.

The process for connecting your Distributed Generation to an IDNO’s network follows EREC G98 or G99, and is therefore similar to connecting to a DNO’s network. IDNOs are licensed entities and are bound by some of the same licence conditions as DNOs, including certain performance standards such as timescales for responding to requests for quotes. The majority of what is included in this guide applies to both DNO and IDNO connections.

However, there are a few key differences for a

Distributed Generation connection to an IDNO network. The most significant of these is that the IDNO has a relationship with their DNO. This relationship will not involve you directly, but may restrict what the IDNO can readily allow to connect to their network. This is not likely to affect a generation project that is compliant with G98.

To determine whether you are connected to a

DNO or IDNO network, refer to the guidance

on page 15.

Storage devices for electrical energy are becoming more prevalent, and can be used as part of Distributed Generation schemes to allow generated electricity to be stored within the premises rather than exported to the distribution network. DNOs treat storage as demand when its importing from the distribution network and generation when its exporting to the distribution network, and need to be aware of storage because of the potential impact on their networks. Therefore storage needs to meet the relevant connection requirements (EREC G98 or G99).

If you are planning to use storage in

conjunction with PV (or other technologies) to offset consumption, the total connected generation is likely to be above 16A / phase and G99 applies. However, DNOs have implemented a fast track application process, for domestic scale storage. This involves submitting the G99 Form A1-2 : Application for connection of Fully Type Tested Integrated Micro Generation and Storage installations and reduces the time for the DNO to provide confirmation that the connection is acceptable from 45 days to 10 days or less. If the storage is intended to be operated in island mode (during a power outage) the fast track process is not applicable and the standard G99 process applies.

Page 27

Supply Issues

Your DNO is obligated to maintain the power quality on their network within a set of defined limits. These include maintaining voltage at the required levels. This is so that customer equipment is not damaged. If you have a voltage complaint you should contact your DNO. Your DNO should respond to your complaint within 5 working days, or visit within 7 working days. If work is required to correct the issue, the DNO should complete this within 6 months.

In rare cases, such as where there are many generating units in a small area, the DNO may feel it is necessary to for you to disconnect your generating unit in order to maintain the power quality on the network. This will be a temporary measure until the problem is resolved. As long as your equipment and its installation complies with G98, then the DNO will be responsible for resolving the problem at their own expense. The timescales for this will depend on the nature and complexity of work to be done.

Health and Safety considerations Safety is very important in the design of generation connections. Some of the safety requirements for Distributed Generation connections are set out in EREC G98. This document references the Regulation that informs these requirements, the Electricity Safety, Quality and Continuity Regulations (ESQCR) 2002, and also lists the relevant British Standards. You can find out more about Health and Safety aspects of Distributed Generation connections on the following websites:

• The Electrical Safety Council (ESC): www.esc.org.uk • The Energy Networks Association—Safety, health and environment:

www.energynetworks.org/electricity/she/overview.html

EREC G98 exceptions

If you are installing a generating unit under EREC G98 then the requirements apply in full in most circumstances. However, if your generating unit is one of the following, some of the technical requirements in EREC G98 do not apply:

• Classified as an Emerging Technology (see Emerging Technology box on page 7)

• An electricity storage device

• Has a registered capacity of < 800 W

The full details of the requirements that do not apply are in EREC G98. If you are installing generating units that are connected via an inverter, the 800 W threshold applies to the aggregate installed capacity of generation. So, for example, if you are installing 3 x 500 W solar PV inverters, the aggregate installed capacity exceeds 800 W and EREC G98 applies in full.

However, because storage is one of the exceptions, it does not count towards the aggregate

capacity when considering the 800 W threshold. For example, if you are installing a 500 W solar

PV inverter and a 500 W storage inverter, they are both excepted from certain requirements in

EREC G98.

Getting Connected

Page 28

Where to Find More Information

If you want to find out more, these documents are particularly relevant:

• Engineering Recommendation G98: Requirements for the connection of Fully Type Tested Micro-generators (up to and including 16 A per phase) in parallel with public Low Voltage Distribution Networks on or after 27 April 2019. This can be downloaded free of charge via the DCode as well as ENA website.

• Electricity Safety, Quality and Continuity Regulations (ESQCR) 2002, Section 22: Statutory Instrument Number 2665, available free of charge.

• Ofgem’s information about how to get an electricity connection for a new building or site.

Some DNOs have produced their own guidance notes for small scale Distributed Generation connections - check your DNO’s website.

Dealing with disputes If you are not satisfied with a particular aspect of service during the process of connecting your generation, your first port of call should be the party with whom the issue lies, eg. the DNO, supplier, etc. DNOs have their complaints process set out on their websites. If you still cannot resolve the issue you can contact the Energy Ombudsman: www.ombudsman-services.org/energy.html If you are still unable to resolve the matter, as a last resort it can be referred to Ofgem.

Getting Connected — Vehicle to Grid

Vehicle to Grid (V2G) is in its infancy and trials are being undertaken to further understand and demonstrate its benefits. The electric vehicle will be considered as both a demand and a generator by DNOs. The generator application will depend on the power export capacity of the V2G and what generation or storage devices are already connected at the designated charging point. Where the total of all generation, fixed storage and the power export capacity of the V2G is

< 50 kW 3-phase or 17 kW single-phase, the G99 simplified application Form A1-1 can be used. Where the total of all generation, fixed storage and the power export capacity of the V2G is > 50 kW 3-phase, the connection application should be made using the Standard Application Form. It is likely that V2G will be > 16 A/phase and therefore G98 is not applicable and G99 should be used.

Page 29

D. The Connection Application: Connection Notification

In this section: • What the installer of your generating unit needs to do to notify the DNO

that your generation has been installed and commissioned in accordance with EREC G98

• Details of the information that you will need to provide to the DNO.

Introduction

Under the provisions of the Electricity Safety, Quality and Continuity regulations (ESQCR) you only need to inform the DNO that you have installed your generating unit. You do not need to contact the DNO in advance if the total capacity of all your generating units combined is 16 Amps or less per phase at low

voltage.

This section of the Guide summarises the information which you will need to provide to your DNO and gives information about the forms that are used for providing the necessary technical details.

The Installation Document

You do not need to talk to your DNO before your generation equipment is up and running. Your installer must inform the DNO and provide a number of pieces of information within 28 days of the date of commissioning. This information is defined in a Installation Document, which is provided in Appendix 3 of EREC G98. There forms are available on the Energy Networks Association website.

Your installer should prepare all of the details requested in the installation document and submit all this with the form to confirm that your equipment has been commissioned.

The information required includes:

• details about the site where you are connecting your generating unit, including metering information;

• contact details for the owner of the

generating unit;

• technical information about the generating unit itself, including the generating capacity, type test reference and primary energy source;

• details of the installer of the generating unit, including the party’s accreditation and qualifications;

• supporting information, eg. circuit diagrams; and

• a signed declaration as to the compliance of the generating unit with the requirements of EREC G98.

Page 30

Other Requirements

The declaration that your installer signs on the Installation Document requires them to confirm that they’ve installed your generating unit in accordance with EREC G98. It’s important that you use an installer who is familiar with the requirements of these standards. If you appoint a competent installer (see Section C: An Overview of

Getting Connected), they should know about these standards and make sure that your installation meets with all the relevant standards. You should check that your installer is aware of all these requirements.

Page 31

E. Cost and Charges

Use of System Charges

Use of System charges are levied by the DNO to the supplier, so as a generator you will not be charged these directly. However, this section is included for your information, as Use of System charges may appear as an item on your bill.

What are Use of System charges?

Use of System charges cover the development, operation, maintenance and repair of the distribution network. DNOs make Use of System charges to suppliers. Suppliers may reflect these charges to their customers as either:

• a ‘pass-through’ item so that the customer can clearly see the Use of System element; or

• ‘wrapped-up’ in a total electricity supply tariff where the customer may not be able to clearly see the Use of System element.

DNOs are obliged to publish documents about their Use of System charges. These cover their Use of System charging methodology and a statement of what the charges are for both generation and demand customers. You can find these on DNOs’ websites.

All generators connected at Low Voltage are subject to Generation Distribution Use of System charges under the Common Distribution Charging Methodology (CDCM). These charges may be negative (ie credits). You can find out more about the Common Distribution Charging Methodology (CDCM) by looking at Distribution Charging on the Ofgem website, Distribution Charges Overview on the Energy Networks Association website and some DNOs’ websites.

Categories of Use of System charges

UoS charges are categorised by:

• the voltage level your equipment is connected to and;

• the type of meter you have.

The boxes below define the voltage level that will apply to EREC G98 compliant equipment (Low Voltage) and the metering arrangements that are likely to apply to this equipment (Non-Half Hourly meters). With the Common Distribution Charging Methodology charges for LV generation customers with NHH meters are in the form of a single unit rate (p/kWh).

LV (Low Voltage) 400/230 V in practice, less than 1 kV in general.

Non-Half Hourly Meters (NHH) NHH meters record total energy passing through the meter, but do not record the times the energy is transferred. Typically the recorded data would be collected a few times a year, eg. every quarter. Most domestic and small commercial properties have NHH meters. You can contact your current electricity supplier to discuss the provision of NHH meters, or other meter suppliers.

Page 32

F: Selling Electricity- Feed-in Tariffs (FITs)

In this section: • An introduction to the Feed-in Tariff Incentive • Eligibility and Accreditation • Deployment caps and how they work • Guidance on where to find more information

Tip: Read the information boxes for definitions or explanations of terms that may be new or unfamiliar.

Introduction Feed-in Tariffs (FITs) are a financial incentive to support distributed and small-scale renewable energy generation, up to 5 MW. FITs are available for the following generation technologies: • Anaerobic digestion

• Hydro • Solar PV

• Wind

A number of domestic Combined Heat and Power (CHP) units are also supported through FITs under a Micro CHP pilot scheme. The Micro CHP pilot will support up to 30,000 installations with an electrical capacity no greater than 2 kW. This section will detail the structure of the tariffs and will explain how to get accredited with FITs.

Important Point: the FIT scheme for generators closed on the 31st March 2019. From the 1st April 2019 onwards, network applications for generators will not be eligible to obtain a FIT from their energy supplier. Applications that were submitted before the 31st March 2019 will have a deadline (depending upon technology and ownership) to install the distributed generation. The period of installation is as follows: • Wind projects must be installed within 12 months

• Hydro projects must be installed within 24 months • Anaerobic digestion (AD) must be installed within 12 months

• Solar projects must be installed within 6 months

If the generation projects are FIT accredited by a community then a 6-month extension will be granted to the above timescales. Please refer to https://www.ofgem.gov.uk/system/files/docs/2018/12/cs_guidance_version_4.pdf for more information and the definition of a community.

Page 33

Tariff Structure

There are three sources of financial benefit from a Generation project receiving FITs: • Generation tariff (FITs): A fixed price for

each unit of electricity generated. • Export tariff: A guaranteed price for

each unit of electricity exported to the grid.

• Import reduction: reducing your import from the grid by using your own electricity.

Tariffs are adjusted annually for inflation. The generation tariffs are published by Ofgem, and you can access them on their webpage: www.ofgem.gov.uk/environmental-programmes/feed-tariff-fit-scheme/tariff-tables The tariff level that you will receive will be the most recent tariff level on the eligibility date of the installation. You will continue to receive this same tariff throughout the eligible lifetime of the project, which for most technologies is 20 years. FITs for PV generation The FITs for PV are structured in a slightly different way. PV installations are subject to the following criteria: • Energy efficiency requirements—the

building to which the solar PV is attached should achieve an Energy Performance Certificate (EPC) rating of level D or above for installations up to and including 250 kW; and

• Multi-installation tariffs—applies to any solar PV installation where the recipient of the FIT already receives FIT payments from 25 or more other PV installations.

The impact of these criteria on the tariff level received is summarised in Ofgem’s tariff tables. Refer to the BEIS or Ofgem websites for the most up to date information. Export Tariff The export tariff is a guaranteed price for the export of your generated electricity, and is the same for all installations which are eligible for FITs. At the time of writing, the export tariff is set at 5.24p/kWh, but this is subject to regular reviews. Refer to the BEIS or Ofgem websites for the most up to date information. Metering Requirements You will need to measure three electrical flows to get the most out of the FIT scheme; import (this is your usual electricity meter), generation and export. For your generation financial stream, each of your generating units must be measured separately. For your export payments, you may choose to measure your export to the grid via a meter (often called an export meter). However, the Government is allowing an interim measure of estimating export, subject to conditions. For example, the Energy Savings Trust website states that domestic FIT installations are likely to have an estimated export level of 50% of electricity generated. Your electricity supplier is a good first port of call to discuss metering arrangements.

Page 34

Eligibility and Accreditation Renewable Energy generators under 5 MW are eligible for Feed-in Tariffs. Renewable Energy generators supplying off-grid or private networks are also covered by the FITs scheme. They receive generation tariffs and the benefit of avoiding the costs of generating electricity by other means e.g. Diesel.

Accreditation steps: There are two routes to accreditation. For wind or solar PV generation up to and including 50 kW, and for micro CHP, the accreditation process is as follows (“MCS-FIT”): 1. Install your generating unit—you must

use a Microgeneration Certification Scheme (MCS) installer (see below);

2. Your installer will register you on a central accreditation system;

3. You will receive a certificate confirming you are eligible for FITs;

4. Register for a FIT with your supplier, and provide them with your FIT compliance certificate so that they can verify your eligibility;

5. Indicate to your supplier if you are opting for the guaranteed export tariff or if you prefer to sell your electricity using a Power Purchase Agreement (a legal contract between you and your electricity supplier);

6. Your supplier will then be responsible for the level of payment you will receive for the electricity generated and exported, for which you may be required to provide meter readings.

See Ofgem’s website on MCS-FIT accreditation: www.ofgem.gov.uk/environmental-programmes/feed-tariff-fit-scheme/applying-feed-tariff/mcs-fit

For anaerobic digestion and hydro generators and for solar PV and wind generation over 50 kW, the following “ROO-FIT” process applies (see information box on page 36): 1. Install your generating unit; 2. Apply for accreditation through Ofgem’s

Renewable and CHP register (see ROO-FIT box on page 36);

3. Successful applicants will be awarded an accreditation number;

4. Register for a FIT with your supplier, and provide them with your accreditation number so that they can verify your eligibility.

Steps 5 and 6 are as above.

While Ofgem is responsible for establishing and maintaining the central FITs register, suppliers manage the registration process—they will be your point of contact.

Microgeneration Certification Scheme (MCS) The MCS is currently the only formalised industry standard in the UK based on European and international standards for microgeneration projects. MCS is a BS EN ISO/IEC 17065:2012 Certification scheme covering Renewable Energy products (wind and PV up to 50 kW (electrical), solar thermal, biomass and heat pumps up to 45 kW (thermal), Micro CHP and hydropower) and Renewable Energy installation companies. MCS checks for the products’ performance and quality and for the installation methods and quality. MCS will increase your confidence in the Renewable Energy technology you are buying and in the company installing it. The MCS is linked with FITs accreditation for Renewable Energy generation ≤ 50 kW electrical capacity. For more information please refer to the MCS website: www.microgenerationcertification.org

Page 35

Deployment Caps Deployment caps were introduced to the FIT scheme in February 2016. A deployment cap is defined as a limit on the capacity that can receive a particular FIT tariff, in a particular tariff period. Once a deployment cap has been reached, no further installations are eligible to receive the tariff rate applicable for that band, in that tariff period. All the remaining tariff periods will degress by a further 10% (in addition to the default degression). Ofgem will publish a report once the deployment cap has been reached. Indicative queues for each ROO-FIT and Standalone deployment cap can be found on the Ofgem website.

The deployment caps queue is based on the date and time you submit your FIT application to Ofgem. A place in the queue does not guarantee eligibility for a particular tariff or eligibility for support under FITs, as it will depend on the volume of applications ahead of you. Two examples are given below:

1. A tariff period opens on 1 April 2016 at

00:00:00 and closes on 30 June 2016 at

23:59:59. A standalone PV installation

submits an application to Ofgem on 1

June 2016 at 12:20:35. The deployment

cap for this technology and tariff band

has not been reached and there is

sufficient capacity available to

accommodate this installation. The tariff

rate for this installation is the tariff rate

that applies to the tariff period that the

application was submitted in.

2. A tariff period opens on 1 April 2016 at

00:00:00 and closes on 30 June 2016 at

23:59:59. A standalone PV installation

applies and exceeds the relevant cap for

that tariff period on 1 June 2016 at

12:20:35. The tariff rate for that tariff

period is applicable to installations with

an application date and time from 1

April 2016 at 00:00:00 to 1 June 2016 at

12:20:34. Applications received on or

after 1 June at 12:20:35 are queued for

entry into the next available tariff

period. The tariff rate applicable for

applications submitted after the cap is

exceeded will be the tariff rate

associated with the next tariff period,

with capacity available to accommodate

the capacity of the installation. The next

tariff period opens on 1 July 2016 at

00:00:00 and there is sufficient capacity

to accommodate the capacity of the

installation. The installation receives the

tariff rate available in that tariff period.

Page 36

Demand: 4500kWh per

year

Import: 4500kWh per year

Demand: 4500kWh per

year

Import: 3000kWh per

year

Self—Consumption:

1500kWh

Export: 1000kWh per

year

Generation: 2500kWh per year

Before Installation

After Installation of Distributed Generation

Cost of Import per year: 4500kWh x 10p/kWh = £450

Income per year: Generation: 2500kWh x 8.19p/kWh = £204.75 Export: 1000kWh x 5.24p/kWh = £52.40 This is a total income of £257.15

Cost of Import per year: 3000kWh x 10p/kWh = £300 This is a saving of £150 due to avoided import.

FIT Example The example tariff levels are: Import tariff: 10p/kWh, Generation tariff: 8.19p/kWh

Total net benefit: £257.15 + £150 = £407.15 per year

ROO-FIT accreditation arrangements: Anaerobic Digestion and hydro installations of any size are accredited by the Renewables Obligation (RO) Order Feed-in Tariff (“ROO-FIT”) process, rather than the MCS accreditation process (“MCS-FIT”). Wind and solar installations greater than 50 kW are also accredited in this way. The ROO-FIT accreditation process is run by Ofgem (rather than the generation installer / supplier), via Ofgem’s Renewable and CHP register. There is more information about it on Ofgem’s website: www.ofgem.gov.uk/environmental-programmes/feed-tariff-fit-scheme/applying-feed-tariff/roo-fit

Eligibility and Accreditation

Micro CHP Pilot: The Micro CHP pilot will support up to 30,000 installations with a review to start when the 12,000th installation has occurred. To qualify the CHP unit must have an electrical capacity no greater than 2 kW.

Community Energy Schemes: The Feed-in Tariffs (Amendment) Order 2015 has introduced an exemption to the definition of the term “site” in the FIT legislation, which is effective from April 2015. The amendment allows two projects to share one grid connection and receive separate tariffs based on their individual generating capacity, provided that at least one project is owned by a community organisation. Both parties sharing the grid connection will be required to seek support under the FITs scheme. In order to enable Ofgem to treat the individually owned sections as separate eligible installations each will be required to register as separate FIT generators and to meter their generation separately.

Page 37

For more guidance and the most up-to-date information on Feed-in Tariffs, please see the follow-ing organisations’ websites:

• Energy Saving Trust — Initial port of call for information www.energysavingtrust.org.uk/Generate-your-own-energy/Financial-incentives/Feed-In-Tariffs-scheme-FITs

• Carbon Trust — Initial port of call for information for businesses: www.carbontrust.com

• Department for Business, Energy and Industrial Strategy (BEIS) — Policy setting https://www.gov.uk/feed-in-tariffs

• Ofgem—FIT administrator www.ofgem.gov.uk/Sustainability/Environment/fits/Pages/fits.aspx

Note that your electricity supplier is your point of contact for the FIT scheme.

Where to Find More Information

Page 38

Glossary of Terms Aggregator: An organisation which specialise in co-ordinating demand and generation (including storage) to provide demand response and other market services. Network Operators and suppliers may buy demand response and other grid balancing services from aggregators.

Balancing and Settlement Code (BSC): The Code which determines the rules governing the Balancing Mechanism and settlement process for electricity trading in Great Britain. A BSC Panel has been charged with overseeing the management, modification and implementation of the BSC rules, as specified in Section B of the BSC. The Balancing and Settlement Code Company (ELEXON) supports the BSC Panel.

Balancing Mechanism: NGESO has a licence obligation to manage the Transmission System and, and needs to have an arrangement in place for the scenario where more energy is generated than consumed, or vice versa. Unchecked, this would result in system frequency falling or rising to an unacceptable degree. The balancing mechanism provides a means by which NGESO can buy or sell additional energy close to real-time to maintain energy balance, and also to deal with other operational constraints of the Transmission System.

Capacity: The capacity of a generating equipment is the maximum power that can be produced if the equipment is running normally at full power.

Capacity Market: A market that aims to ensure security of electricity supply by providing a payment for reliable sources of capacity.

Climate Change Levy (CCL): Part of a range of taxation measures designed to help the UK meet its legally binding commitment to reduce greenhouse gas emissions. This levy / tax is chargeable on the industrial and commercial supply of taxable commodities for lighting, heating and power by consumers in the following sectors of business: industry, commerce, agriculture, public administration and other services.

Contracts for Difference (CfD): A Contract for Difference is a contract between a generator and the Low Carbon Contracts Company (LCCC, the CFD counterparty), which is government owned. The Feed-in Tariff with Contracts for Difference is a low-carbon generation incentive mechanism.

Distributed Generation (DG): A generating unit which is connected to a distribution network rather than to the transmission system. Distributed Generation is generally smaller than units connected to the transmission system as the maximum operating voltage of distribution networks is 132 kV in England and Wales and 33 kV in Scotland.

Distribution Network (System): The distribution system is the network that comprises the equipment between the transmission system and the customer’s service switch. In England and Wales the distribution systems are the lines with a voltage less than or equal to 132 kV. In Scotland the distribution network is composed of lines with an operating voltage of less than 132 kV.

Distribution Network Operator (DNO): A holder of a Distribution Licence, the DNO owns, operates and maintains a Distribution network and is responsible for confirming requirements for the connection of Distributed Generation to that network.

Embedded Generation: Another term used for Distributed Generation (DG) - see above.

Energy Service Company (ESCO): A Government paper defines ESCOs as “a company that provides a customer with energy solutions” rather than simply being an electricity or gas supplier.

EU Emissions Trading System (ETS): Formerly referred to as the EU Emissions Trading Scheme, the EU Emissions Trading System (EU ETS) is one of the key policies introduced by the European Union to help meet its greenhouse gas emissions reduction target. It is a Europe-wide cap and trade scheme that started in 2005. The EU ETS covers electricity generation and the main energy-intensive industries.

Extension: It is sometimes necessary to extend the DNO’s distribution network in order to provide a connection for a new user (demand or generation customer).

Page 39

Glossary of Terms Generating Unit: Any apparatus which produces electricity.

Generator: A person who generates electricity under licence or exemption under the Electricity Act 1989.

Grid Supply Point (GSP): Any point at which electricity is delivered from the National Electricity Transmission System to the DNO’s Distribution system.

Independent Distribution Network Operator (IDNO): A holder of a distribution licence, an IDNO designs, builds, owns and operates a distribution network, which is an extension to existing DNO network. They typically build network for new developments such as business parks, retail and residential areas and leisure facilities.

Low Voltage (LV): A voltage normally exceeding 50 V AC between conductors and earth or 120 V DC between conductors but not exceeding 1000 V AC or 1500 V DC between conductors or 600 V AC or 900 V DC between conductors and earth.

National Electricity Transmission System Operator (NETSO): Operates the electricity transmission system in England, Wales and Scotland (see System Operator).

National Grid Electricity Transmission (NGET): Owns the electricity transmission network in England and Wales. NGET is a member of the National Grid group of companies.

National Grid Electricity System Operator (NGESO): Operates the transmission system in England, Wales and Scotland (takes the role of the NETSO). NGESO is a member of the National Grid group of companies.

Ofgem: The Office of Gas and Electricity Markets.

Reinforcement: Reinforcement work is usually required to increase the electrical capacity of those parts of the network which are affected by the introduction of new generation or demand. Other work might include upgrading the switchgear at a substation some distance from the proposed generation project, due to the increase in fault level caused by the connection of generating equipment.

Renewable Obligation Certificates (ROCs): A green certificate issued to an accredited generator for eligible renewable energy generated within the UK and supplied to customers within the UK by a licensed electricity supplier. ROCs are issued for each MWh of eligible renewable output generated, the amount of ROCs received depend on the technology of the generating station.

Retail Price Index (RPI): General purpose measure of inflation used in the UK.

Micro-generator: A source of electrical energy and all associated interface equipment able to be

connected to an electric circuit in a Low Voltage electrical installation and designed to operate in parallel

with a public Low Voltage Distribution Network with nominal currents up to and including 16 A per phase.

Supplier (Electricity Supplier): Electricity suppliers purchase electricity (on the market or in contracts) and sell electricity to customers (commercial, industrial and domestic).

System Operator (SO): The operator of the transmission networks, the System Operator balances supply with demand on a minute by minute basis.

Transmission Network (System): A system of lines and equipment owned by the holder of a Transmission Licence and operated by the GB SO, which interconnects Power Stations and substations. In England and Wales the transmission system is the equipment principally rated above 132 kV while in Scotland they are those principally at or above 132 kV.

Type Tested Equipment: Equipment that has been tested to ensure that it meets the requirements of EREC G98 or G99. Using type tested equipment simplifies the connection and commissioning process.

Use of System (UoS): The use of a transmission or distribution system by a generator, supplier, customer or an interconnected party for the purposes of transporting electricity.

Page 40

References Standards and other documents:

Balancing and Settlement Code (BSC) is available free of charge on Elexon’s website

Connection and Use of System Code (CUSC) is available free of charge on National Grid’s website

Distribution Code of Great Britain—available free of charge on the Distribution Code website

Engineering Recommendation G59, relating to the connection of generating equipment to the distribution

systems of licensed Distribution Network Operators. This is not applicable to generation connecting after the 27th April 2019.

Engineering Recommendation G81 is called “Framework for design and planning, materials specification, installation and records low voltage housing development installations and associated new HV/LV distribution substations”. It can be found free of charge on the Energy Network Association’s website

Engineering Recommendation G98: Requirements for the connection of Fully Type Tested Micro-generators (up to and including 16 A per phase) in parallel with public Low Voltage Distribution Networks on or after 27 April 2019— available free of charge on the DCode and ENA websites

Engineering Recommendation G99: Requirements for the connection of generation equipment in parallel with public distribution networks on or after 27 April 2019— available free of charge on the DCode and ENA websites

Electricity Safety, Quality and Continuity Regulations (ESQCR) 2002, Section 22: Statutory Instrument Number 2665, available free of charge

Grid Code of Great Britain — available free of charge on National Grid’s website

IET Wiring Regulations (British Standard 7671) are available to buy on the IET website

Metering Codes of Practice

Requirements for Generators is available free of charge on the EUR-Lex website

Requirements for micro-generating plants to be connected in parallel with public low-voltage distribution networks (BS EN 50438) is available to buy on the BSI website

Statutory Instrument 2001 No. 3270, The Electricity (Class Exemptions from the Requirement for a Licence) Order 2001

Statutory Instrument 2008 No. 2376, The Electricity (Applications for Licences, Modifications of an Area and Extensions and Restrictions of Licences) Regulations 2008

Page 41

References Useful websites:

Agency for the Cooperation of Energy Regulators (ACER)

www.acer.europa.eu

Association of Meter Operators www.meteroperators.org.uk

British Hydropower Association www.british-hydro.org

Renewable UK http://www.renewableuk.com/

Carbon Trust www.carbontrust.com

The Council of European Energy Regulators (CEER)

www.ceer.eu

The Association for Decentralised Energy (combined heat and power)

www.theade.co.uk

Department for Business, Energy & Industrial Strategy

https://www.gov.uk/government/organisations/department-for-business-energy-and-industrial-strategy

Distribution Connection and Use of System Agreement (DCUSA) website

www.dcusa.co.uk

Electricity Networks Strategy Group

https://www.gov.uk/government/groups/electricity-networks-strategy-group

Elexon www.elexon.co.uk

Energy Networks Association www.energynetworks.org

Energy Saving Trust www.energysavingtrust.org.uk/Generate-your-own-energy

Energy UK www.energy-uk.org.uk

ENTSO-E www.entsoe.eu

Lloyds Register www.lr.org/sectors/utilities/schemes/ners.aspx

Microgeneration Certification Scheme

www.microgenerationcertification.org

National Grid www.nationalgrid.com/uk/Electricity/

Ofgem www.ofgem.gov.uk

Renewable Energy Association www.r-e-a.net

Page 42

References

Relevant reports and guides: Electricity Trading Arrangements: A Beginner’s Guide; Elexon

Embedded Generation and Embedded Benefits; Elexon; November 2013

The Electricity Networks Innovation Strategy; Energy Networks Association; 2018

The Open Networks project; Energy Networks Association

The Clean Growth Strategy; BEIS; 2017

Upgrading our energy system: smart systems and flexibility plan; BEIS; 2017

Page 43

Revisions

Version Number

Date Details of Changes

1.0 July 2019 The G83/G98 guides have been replaced with a G98 guide and minor revisions have been made. Changes include: • General Updates • Inclusion of V2G • Update of the FIT’s