disaster risk reduction and climate change adaptation in the dili – ainaro road corridor

30
Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor Supporting the Government of Timor Leste in Disaster Risk Management & Climate Change Adaptation

Upload: kaz

Post on 14-Jan-2016

64 views

Category:

Documents


4 download

DESCRIPTION

Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor. Supporting the Government of Timor Leste in Disaster Risk Management & Climate Change Adaptation. We cannot stop natural disasters but we can arm ourselves with knowledge: - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro

Road Corridor

Supporting the Government of Timor Leste in Disaster

Risk Management & Climate Change Adaptation

Page 2: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor
Page 3: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

We cannot stop natural disasters but we can arm ourselves with knowledge: so many lives and livelihoods across the World wouldn't have to be lost if there was enough disaster preparedness.

Page 4: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor
Page 5: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

"whatever can happen will happen“

Murphy’s Law

Page 6: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor
Page 7: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor
Page 8: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

Timor-Leste Hazard profile

Threats from geological hazard include earthquake and tsunami

rare events but huge potential of significant damage

Main hazards are hydro-meteorological resulting in frequent localized disasters: flash floods, droughts, landslides and destructive winds

frequent and serious impact to community (agriculture and transport sectors)

Page 9: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

According to a road condition survey in 2008, the national road network has almost entirely deteriorated and is no longer maintainable:

- 65% of national roads are in “very poor” condition- 96% of rural roads are in “very poor” condition

Due to the steep terrain, ground conditions and local climate, slope instability is a major problem and slips can result in significant damage to the road network and potential risk to road users.

In many cases roads have not been properly designed, lack sufficient drainage capacity and/or are structurally unsound.

A fragile road network is vulnerable to frequent localized disasters. Flash floods and landslides destroying roads further isolate communities and hamper disaster response efforts.

Page 10: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor
Page 11: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

Loans and Grants

Page 12: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

The World Bank Climate Resilient Road Project

Page 13: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

• The project also includes feasibility studies for the upgrading of additional road segments linked to the Dili-Ainaro road.

Page 14: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

However,…

• The Road’s Right of Way (RoW – the area in which the engineers work) extends only to 25m either side of the central line of the road

• Many of the causes and sources of road-impacting floods and landslides/slips begin outside of this 25m width.

Page 15: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

therefore,…

Page 16: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

TENTATIVE LEVEL AND SOURCE OF FUNDING

Activity Funding Timing

Component 1

Risk Assessment – Climate/Disaster vulnerability

Global Facility for Disaster Risk Reduction – ACP – EU (WB)

Jan 2014

Enabling improved climate and disaster risk management

Least Developed Countries Fund(UNDP)

Mid 2014

Component 2

Capacity Building at National and District level for

Mainstreaming Disaster Risk Management

PHRD – JICA(WB)

Strengthened climate and disaster risk planning,

budgeting and delivery

Least Developed Countries Fund(UNDP)

Mid 2014

Component 3

Community Based DRM Projects around Dili-Ainaro Corridor and Linked roads

PHRD –JICA(WB)

Investments in climate resilient community based

adaptation measures

Least Developed Countries Fund(UNDP)

Mid 2014

Total of tentative level of funding

WB: 3.6 Million (GFDRR and PHRD)UNDP: 5.25 Million (LDCF)

Page 17: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

One joint programme on supporting the government strengthening disaster/climate resilience along the Dili-Ainaro corridor in Timor Leste supported and implemented through two projects:

• UNDP project, LDCF funded – approx. $5.7M• WORLD BANK project, GFDRR ACP-EU (approx.

US$0.9M) and PHRD funds (approx. US$2.7M)

Page 18: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

The joint programme supported by UNDP and the WB aims at:

• Reducing climate change and natural disaster associated risks, and

• Minimizing losses to physical infrastructure arising from natural disasters and climate change

Page 19: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

To do this the programme aims at:

a. Performing a RISK ASSESSMENT - Understand better the natural disaster risks and where they occur and communicate this to decision makers to influence future planning and budgeting

b. Developing capacity to manage disaster risks - influence sub-national and sectoral strategies

c. Strengthening climate and disaster risk planning, budgeting and delivery

d. Investing in climate resilient community based adaptation measures and implementing risk management activities to protect assets and livelihoods from disaster & climate risks.

Page 20: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor
Page 21: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor
Page 22: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor
Page 23: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor
Page 24: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor
Page 25: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

In this way, the joint programme will secure the critical economic infrastructure in the Dili to Ainaro corridor which is increasingly at risk from climate change and disaster related impacts, including localised flooding, landslides and strong winds.

Page 26: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

The joint programme is implemented through two projects with considerable cross over, both spatially and thematically.

This dictates that considerable coordination and synchronization needs to be built into the UNDP and WB supported projects from the design phase through to implementation of activities.

Page 27: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

• In order to ensure the two projects coordinate adequately under the umbrella of a joint programme, a joint steering committee has been proposed. The Ministry of Social Solidarity would be the main ministerial focal point, and would likely appoint the NDMD as the primary National Directorate responsible for chairing the Steering Committee and implementing the Components of the Projects that will be Nationally/Recipient Executed.

Page 28: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

Project management units

• It is likely that two separate project management units will need to be established

• Location

• ToRs

• Integrated Assessment Frameworks

Page 29: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

As well as MSS, line-ministries will be closely involved in all Components

• Close coordination between MSS and line-ministries will also be required

• Inter-ministerial coordination will be an integral part of the success of the project as many of the activities will require other Ministries such as MPW, MSA, MCIE and MAF

• Where possible, Suco development planning process will be utilized

Page 30: Disaster Risk Reduction and Climate Change Adaptation in the Dili – Ainaro Road Corridor

Timing

• January 2014 is likely to be the earliest that Component 1 of the WB’s DRM project will be operational

• UNDP’s project would likely come into operation in mid 2014.