digital railway joint development group outcome based ... · the interim joint development group...

63
Reference:157319NWRREPCPO000002 Issue/ver: 1.0 Date: 10/08/2018 Digital Railway Joint Development Group Outcome Based Project Delivery Strategy Case Study: Moorgate Northern City Line Renewal with ETCS Technology Prepared By: Keith Attwood, Professional Head of Signalling, Alstom Prepared By: Simon D’Cruz, Chief Engineer, Atkins .................................. Date: ......................... Prepared By: Ben Lane, Regional Commercial Manager, Siemens .................................. Date: ......................... Prepared By: Andrew Woods, Senior Systems Engineer, Siemens .................................. Date: ......................... Approved By: Christos Panou, Senior Project Engineer, on behalf of Daniel Holder, Programme Engineer Manager, Network Rail .................................. Date: ......................... Approved By: Graham Lawrence, Project Manager, Network Rail .................................. Date: .........................

Upload: others

Post on 19-Mar-2020

13 views

Category:

Documents


0 download

TRANSCRIPT

Reference:157319NWRREPCPO000002

Issue/ver: 1.0

Date: 10/08/2018

Digital Railway – Joint Development Group

Outcome Based Project Delivery Strategy

Case Study: Moorgate – Northern City Line Renewal with ETCS Technology

Prepared By: Keith Attwood, Professional Head of Signalling, Alstom

Prepared By: Simon D’Cruz, Chief Engineer, Atkins .................................. Date: ......................... Prepared By: Ben Lane, Regional Commercial Manager, Siemens .................................. Date: ......................... Prepared By: Andrew Woods, Senior Systems Engineer, Siemens .................................. Date: ......................... Approved By: Christos Panou, Senior Project Engineer, on behalf of Daniel Holder, Programme Engineer Manager, Network Rail .................................. Date: ......................... Approved By: Graham Lawrence, Project Manager, Network Rail .................................. Date: .........................

2

Document Control

Electronic file reference: 157319NWRREPCPO000002

Disclaimer

Group Digital Railway has used its best endeavours to ensure that the content, layout and text of this document are accurate, complete and suitable for its stated purpose. It makes no warranties, expressed or implied, that compliance with the contents of this document will be sufficient to ensure safe systems of work or operation. Group Digital Railway will not be liable to pay compensation in respect of the content or subsequent use of this document for any purpose other than its stated purpose or for any purpose other than that for which it was prepared, except where it can be shown to have acted in bad faith or there has been wilful default.

© Copyright 2017 Group Digital Railway.

This document is the property of Group Digital Railway. It shall not be reproduced in whole or in part, nor disclosed to a third party, without the written permission of Group Digital Railway.

Document owner: Joint Development Group (JDG) – [email protected]

Distributed to: Public

Issue/Version: 1.0

Feedback to be provided to: Daniel Holder [email protected], Graham Lawrence: [email protected], and Joint Development Group (JDG) - [email protected]

Version Comments Updated By Reviewed By Date

0.5 Final Draft SDC 1st June 2018

0.6 JDG Preface included PW SDC 7th June 2018

0.7 Updated Exec Summary. Renamed System Integrator to RSIP. Updated RSIP/TI roles

SDC 8th June 2018

0.8 Updated report with B Lane’s comments.

BY 13th June 2018

0.9 Updated report with DR comments. BY BY, QZ, GL, DH 19th June 2018

0.10 Updated with Recommendations highlighted

SDC 6th July 2018

1.0 Final version for publication JDG Team 14th August 2018

3

Contents

EXECUTIVE SUMMARY ................................................................................. 6

1 INTRODUCTION ....................................................................................... 8

1.1 JOINT DEVELOPMENT GROUP (JDG) ..............................................................................................8

1.2 PROJECT BACKGROUND AND PROBLEM STATEMENT ..............................................................8

1.3 THE IJDG PROJECT TEAM ................................................................................................................9

1.4 KEY MILESTONES ........................................................................................................................... 10

1.5 EXPECTED OUTPUTS ..................................................................................................................... 10

1.6 FINDINGS .......................................................................................................................................... 11

2 OUTCOME SPECIFICATIONS ................................................................ 12

2.1 INTRODUCTION ............................................................................................................................... 12

2.2 THIN CLIENT ENGINEERING MODEL ............................................................................................ 13

2.3 DEFINING REQUIREMENTS ............................................................................................................ 14

2.4 THE V-LIFE CYCLE .......................................................................................................................... 15

2.5 SYSTEM OF SYSTEMS .................................................................................................................... 17

2.6 SAFETY MANAGEMENT ................................................................................................................. 18

2.7 VERIFICATION AND VALIDATION ................................................................................................. 19

2.8 GATEWAYS AND AUDITS ............................................................................................................... 19

2.9 CONFIGURATION CONTROL AND CHANGE MANAGEMENT ..................................................... 21

3 REQUIREMENT MANAGEMENT PROCESS AND TOOLS ................... 22

3.1 PROGRESSIVE ASSURANCE ......................................................................................................... 23

3.2 FOR TENDERING ............................................................................................................................. 23

3.3 FOR PLANNING ............................................................................................................................... 24

3.4 FOR PROJECT MONITORING AND CONTROL ............................................................................. 24

3.4.1 ENGINEERING MANAGEMENT STRUCTURE ....................................................................... 26

3.5 ENGINEERING INTERFACE MANAGEMENT ................................................................................. 26

3.6 SUPPLIER MATURITY ..................................................................................................................... 28

3.7 SECTION SUMMARY ....................................................................................................................... 28

3.8 ROLES, RESPONSIBILITIES AND ACCOUNTABILITIES ............................................................. 29

3.9 RAILWAY SYSTEMS INTEGRATION PARTNER (RSIP) ............................................................... 29

3.10 TECHNICAL INTEGRATOR ............................................................................................................. 32

3.11 SECTION SUMMARY ....................................................................................................................... 33

4 TECHNOLOGY SOLUTION .................................................................... 35

4

4.1 INTRODUCTION ............................................................................................................................... 35

4.2 INPUTS REQUIRED FOR ETCS DATA CREATION ....................................................................... 36

4.3 NRT .................................................................................................................................................... 37

5 FORM OF CONTRACT ........................................................................... 39

5.1 PROPOSED FORM OF CONTRACT ............................................................................................... 39

5.2 CONTRACT CLAUSES .................................................................................................................... 39

5.2.1 GENERAL .................................................................................................................................. 39

5.2.2 CONTRACTOR’S MAIN RESPONSIBILITIES .......................................................................... 40

5.2.3 TIME .......................................................................................................................................... 40

5.2.4 QUALITY MANAGEMENT ......................................................................................................... 40

5.2.5 PAYMENT .................................................................................................................................. 41

5.2.6 COMPENSATION EVENTS ...................................................................................................... 41

5.2.7 USE OF EQUIPMENT, PLANT AND MATERIALS ................................................................... 41

5.2.8 LIABILITIES AND INSURANCE ................................................................................................ 41

5.2.9 TERMINATION .......................................................................................................................... 41

5.2.10 OPTION CLAUSES ................................................................................................................... 41

5.3 COST COMPONENTS ...................................................................................................................... 42

5.4 NEC4 VS NR12 TERMS AND PROPOSED ADDITIONAL TERMS ................................................ 42

5.5 SUPPLIERS APPROACH TO CONTRACT RISK ............................................................................ 43

6 MAINTENANCE CONTRACTING ........................................................... 44

6.1 BACKGROUND ................................................................................................................................ 44

6.2 MANAGING CHANGE ...................................................................................................................... 44

6.3 MAINTENANCE SCOPE ................................................................................................................... 44

6.4 SPARES AND REPAIRS .................................................................................................................. 45

6.5 CONSIDERATIONS FOR THE SPARES SCOPE ............................................................................ 45

6.6 TECHNICAL SUPPORT .................................................................................................................... 46

6.7 TECHNICAL INVESTIGATION ......................................................................................................... 46

6.8 TESTING EQUIPMENT, SPECIAL TOOLS AND TRAINING EQUIPMENT .................................... 46

6.9 MANAGING OBSOLESCENCE........................................................................................................ 46

6.10 NETWORK AND CYBER SECURITY MANAGEMENT ................................................................... 47

6.11 KEY PERFORMANCE INDICATORS ............................................................................................... 47

6.12 RELIABILITY TARGETS AND PERFORMANCE ............................................................................ 47

6.13 MAINTENANCE REPORTING .......................................................................................................... 47

6.14 TENDER FORMAT ............................................................................................................................ 48

7 RISKS AND CHALLENGES .................................................................... 50

5

7.1 CULTURAL CHANGES .................................................................................................................... 50

7.2 SYSTEM OF SYSTEMS .................................................................................................................... 50

7.3 SYSTEMS AUTHORITY .................................................................................................................... 50

7.4 TECHNICAL CHANGES REQUIRED ............................................................................................... 51

8 CASE STUDY: MOORGATE – NORTHERN CITY LINE RENEWAL ...... 52

8.1 BACKGROUND ................................................................................................................................ 52

8.2 CONOPS ........................................................................................................................................... 52

8.3 CLIENT DELIVERY TEAM ................................................................................................................ 53

8.4 ENGINEERING STRUCTURE .......................................................................................................... 54

APPENDIX 1 ................................................................................................. 56

6

EXECUTIVE SUMMARY

The Interim Joint Development Group (IJDG) Moorgate Project Team has analysed the problem statement to

determine whether using an Outcome Based Specification approach can facilitate a different project delivery

model. The IJDG Project Team used the proposed Moorgate: Northern City Line Renewal as a case study for

the deployment.

To realise the Digital Railway vision requires the complex integration of technology, processes and people and

focus needs to be given equally to each to ensure success. The need for the delivery team to manage across

the business (i.e. train operators, maintainers, TOCs, etc.) as well as manage the technology supplier requires

a different approach.

The key issues include:

• Digital Rail technology requires integration between the technology and the people and process that is

significantly greater than for traditional railways.

• Introduction of new technology means that there is a shift in knowledge base to the suppliers and their

products.

• Over specifying complex integrated solutions would restrict the supplier’s ability to apply products and

to innovate.

• A systematic rather than a prescriptive approach to project delivery is required.

Outcome Based Specifications enables focus on what is important to the success of the project which can be

lost during the project lifecycle. The requirements set should be as well defined as possible to allow innovation.

However, the constraints within the contract must also be carefully considered. With the supplier taking on more

responsibility, they must be cognisant of being able to demonstrate that the requirements have been met in a

complex regulatory environment.

The IJDG Project Team supports a new thin client organisation that is responsible for the system integration

with the System of Systems and the stakeholders. Responsibility for technical integration will be transferred to

the supplier.

During the transition there will be significant risk resulting from managing new technology deployment within a

new organisation structure. New processes will need to be introduced which would require practical application

rather than strict adherence. Resistance to change can also be expected.

A review of the technical issues arising from the deployment of ETCS is considered in the report including the

need to have accurate site data and the interface with NRT who will be required to provide GSM-R technology

to the project.

The NEC4 contract is considered to be an appropriate vehicle for the new delivery strategy and with the

recommended amendments can be used to manage the risks of the new structure whilst providing incentives

to the suppliers in key areas. This includes arrangements for the long-term management of the system.

The Moorgate Northern City Line ETCS Renewal is a good opportunity to assess the performance of a new

contracting model. The project is over a small geographic location but includes the complexity of an integrated

solution including ETCS trackside and onboard as well as a transition point and tunnel operations.

7

The Panel recommends that for Moorgate, an Outcome Based Specification (OBS) is considered with a suitable

project delivery team model. Several recommendations made in this report should be considered for further

assessment to enable this strategy to be successful.

Key Recommendations

Recommendation Document Reference

OBS is a suitable project delivery model for the Moorgate Northern City Line Project

Section 8

NEC4 Contract with amendments is a suitable vehicle for contracting OBS Section 5

Progressive Assurance with Audits and Gateways to be deployed for Moorgate Section 3.1

Business Change Management Team for initial projects Section 7.1

New Job Titles in the new organisation to enable cultural change Section 7.1

Physical Railway Configuration Data needs to be improved Section 7.4

NRT collaboration with the Technical Integrator (TI) Section 7.4

8

1 Introduction

1.1 Joint Development Group (JDG)

Building on the lessons learned from the previous Early Contractor Involvement (ECI) work streams combined with an industry specific benchmarking exercise, the Digital Railway Programme (DRP) developed the concept of a Joint Development Group (JDG). The JDG seeks to leverage the breadth and depth of technical competencies that exist in the supply chain to inform a diverse industry opinion and respond to novel and ambiguous problem statements that emerge within the Digital Railway Programme. The core concept behind the JDG is to bring together a community of suppliers with a wide range of skills and capabilities, each able to be called upon/invited to support the DRP’s development activities. This new way of working allows the DRP to utilise the diversity of thinking from the supply chain on a variety of problem statements. For the remainder of CP5, the JDG will be in its interim phase (IJDG) during which the concept and operating model will be validated prior to a solution being locked in CP6.

1.1.1. THE COMMISSIONING PROCEDURE

The diagram below shows each step with descriptions.

Figure 1: JDG commissioning process

1.2 Project Background and Problem Statement The London North Eastern Route (LNE) and the Franchise Govia Thameslink Railway (GTR), in conjunction

with Digital Railway (DR) are considering the roll out of a European Train Control System Level 2 Baseline 3.4.0

(ETCS L2). This rollout will be without lineside signals, on the Northern City Line between Drayton Park and

Moorgate stations (route hereafter referred to as ‘Moorgate Branch’). The implementation scope also includes

the necessary sub-systems to operate ETCS L2, such as Radio Block Centres (RBC), Global System for Mobile

Communications – Railway (GSM-R), balises etc.

Customer will approach JDG core management team with a problem statement. The JDG work with the customer to convert the problem statement into a capability request.

The core management team will issue the capability request, evaluation criteria, submission form and NR03 construction services agreement via email

Instructions regarding the submission process will be included in the capability request email. Suppliers will be asked to populate a submission form

JDG core management team use a simplified process whereby only submission forms are evaluated. There will be no interview component

All competing suppliers will be notified of the evaluation outcome and awarded suppliers will be issued an NR03 construction services agreement for execution. A kick off meeting is convened to capture deliverables and assign responsibilities.

9

Through this commissioned piece of work DR wants to continue exploring the ‘thin client’ approach, whereby

the DR organisation itself operates leanly, relying on its partners and suppliers for delivery support. One way of

achieving this is through Outcome Specification based procurement, and more specifically, Outcome

Specifications when developing a future Invitation To Tender for the Moorgate Branch ETCS L2 rollout

described above.

Based on collective experience of suppliers and the information to be delivered, working on this project, DR had

the aim of understand what procedures suppliers envisage may need to change within, to support an Outcome

Specification document. This includes identification of inputs and level of data quality required along with a

methodology for change, to create a robust suite of Outcome Specification documents for the Moorgate Branch.

This suite of documents will support the LNE/GTR/DR plan to roll out ETCS Level 2 across the East Coast Main

Line.

1.3 The IJDG Project Team The IJDG Project Team working on the Moorgate problem statement included Subject Matter Experts from

around the industry, working collaboratively alongside the Digital Railway Programme customer to develop a

solution. The Moorgate organogram and key are below.

Figure 2: Organisation

Digital Rail Team

Supplier Community Team

Core Management Team Graham Lawrence

Project Manager

Ben Lane

Regional Commercial Manager, Siemens

Andrew Woods

Senior Systems Engineer, Siemens

Simon D’Cruz

Chief Engineer, Atkins

Keith Atwood

Professional Head of Signalling, Alstom

Dan Holder

Problem Statement Owner, Programme Engineer Manager

Pareisse Wilson

Project Manager, IJDG

Bernard Yeo

Project Engineer

Christos Panou

Senior Project Engineer

10

1.4 Key milestones

Figure 3: Key Milestones

1.5 Expected outputs The original brief included 9 expected outputs.

No Expected Output Output 1 What would an Outcome Specification look like and how should

this be presented in the tendering process for a DR Scheme of

this size?

The Outcome Specification is described in two key documents – the Concept of Operations and the Application High Level Specification (CRD). In Section 2, there is a description of how the Outcome Specifications will be managed through the V-Lifecycle. Specific consideration of the Moorgate project is given in Section 8.

2 How would current DR Practices and processes need to change?

.

The Engineering Practice and process would need to change to reflect the new contracting arrangements. Section 3 considers the implication of these changes

3 Given the shift to Outcome Specifications based procurement, how are the roles of DR and a Supplier impacted? Do new roles need to be defined? If so, what does this look like?

Sections 2 and 3 consider the implications on the roles of those involved in the development of these technologies. Newly defined roles of Railway Systems Integration Partner (RSIP) and Technical Integrator help to define the new responsibilities of the Client and Supplier and try to set out their respective involvements in the deployment process. Section 7 considers the risks and challenges of this new arrangement.

4 What is the role of DR and the Supplier in the delivery of outcomes and what would the assurance regime be?

Section 2 proposes a new regime of gateways and audits to replace the current assurance model.

5 Define the roles of System Integrator and Technical Integrator, how do they inform a deployment strategy given the shift to

Outcome Specifications based procurement?

Section 3 describes the roles of the RSIP and the Technical Integrator.

23 April, Kick Off Meeting

4 May, identified areas of expertise

for Problem Statement

22 May, finalisedoutcomes

8 June, final report submitted

11

No Expected Output Output 6 What are the asset and data requirements for a scheme this

size? What need to be included as part of the above?

The implication for the asset and the data requirements are considered in Section 4. Specific issues for the Moorgate Project are considered in the Case Study

7 How could performance be measured and compensated?

Section 2 considers potential methods of measuring the Supplier which could be developed into a payment structure

8 A view to whether the existing asset data need the quality

requirements of an Outcome Specification based procurement?

In Section 4 there is a description of the quality of data requirements for ETCS systems and how this can be applied to an Outcome Based Specification

9 What lessons learnt from previous tenders can be shared with DR?

The team has drawn from its experience and knowledge of other technology deployments to build this strategy for a thin client organisation using Outcome Based Specifications

1.6 Findings The JDG report concentrated on four key areas:

• How to develop and use Outcome Based Specifications through the project lifecycle

• The impact on the current engineering practices and the roles and responsibilities of the engineers

• The impact on the engineering specifically around the handling of data and the technical interface with

others

• The commercial and contractual implications of using Outcome Based Specifications

The Moorgate Northern City Line project has been considered as a case study and the specific findings have

been addressed separately.

12

2 Outcome Specifications

2.1 Introduction

In the Digital Railway, the stakeholders are predominantly the same as they are for conventional projects. There

will still be physical infrastructure; track, traction power, signalling, control centres, stations, passenger

information systems, performance monitoring/recording systems, all using a backbone communication network.

These systems will still need the supporting organisational structures for the day to day running of the railway

infrastructure operations department, Railway undertakings (TOC, FOC), Rolling Stock Operating Company

(ROSCO), infrastructure maintainer, rolling stock maintainer, route controllers, rostering clerks, timetabling

clerks. The conventional railway system allows each of these organisational structures to focus inwards towards

their own elements of physical infrastructure and procedures. The railway system operating as multiple discrete

sub systems, many of which have minimal interactions with the other sub systems around them, managed

through compliance with historically proven standards. Where sub systems are ‘connected’ information is

generally transferred as an information dump at predefined intervals to allow the other sub systems to extract

what they require and discard the rest. These interactions with others are out of necessity and generally for the

personal gain of the individual organisation. So, for example a train operator will liaise closely with a route

controller to recover their train pattern following perturbation because it minimises their customer (passenger)

discontent and places their rolling stock and train crews into the required locations to minimise onward delays

caused by rostering issues such as rest periods, competency, route knowledge, train maintenance schedules

etc. Whilst the route controller’s interests are to minimise financial penalties associated with attributable delays.

In the Digital Railway the core disciplines to control the railway will remain the same; the change will be upon

how these disciplines interact. The core sub systems being used to perform the day to day utilising available

and new technology will require a higher level of integration into the railway system.

This integration at the digital level will aid the railway in meeting the demands of the current and future population

demographic who have become reliant upon technology to provide anything and everything they ask. In the

railway system of systems this translates into the vital and non-vital systems required to operate the railway of

the future. But even here the boundaries will change, what is vital? The train control sub systems that ensure

the safe movement of trains (interlocking) or the traffic management sub system that plans train movements to

minimise conflicts at junctions and maintains a smooth throughput to meet the timetable?

In simplistic terms the needs of the railway users can be met by identifying the required functions and assigning

to the appropriate subsystem. The digital information transfer between these subsystems becoming critical for

day to day operations also creates a necessity for clear definitions as to what is required. As these system

interfaces become more complex and reliant upon on each other, the raw standard compliance approach

becomes untenable. The System of Systems must therefore be represented as explicit requirements,

characterised and assigned to sub systems and / or interfaces. The traditional engineering structure applied to

project delivery following standards compliance approach fails to meet the future needs and the engineering

structure and roles need to be manipulated in the system of systems.

Requirements Management are the activities that ensure requirements are identified, documented, maintained,

communicated and traced throughout the life cycle of a system, product, or service.

13

The result of requirements engineering is a hierarchy of requirements that:

• enables an agreed understanding between stakeholders (e.g., acquirers, users, customers, operators,

suppliers)

• is validated against real-world needs,

• can be implemented provides a basis of verifying designs and accepting solutions

For a contracting strategy, that is based on Outcome Based Specifications where the responsibility for the

detailed design relies on the supplier to assure their works there is a need for a requirements management

driven strategy.

Furthermore, the client team can also focus on assuring the outcomes of the project are satisfied and

demonstrating those outcomes to the client and the stakeholders. This change in focus removes them from

obligation of checking the suppliers’ works as they are assured that works is being satisfied through the reporting

generated by the requirements management systems.

A robust requirements management system that is integrated into the project delivery, technical assurance and

reporting systems should provide the degree of satisfaction required to assure clients, stakeholders and

designers alike that the right products are being delivered.

2.2 Thin Client Engineering Model

The traditional supplier project delivery assurance model as depicted in

Figure 4 predominantly focuses effort towards the supplier. Engineering assurance is achieved at project level

through the client organisation conducting detailed analysis of design deliverables required by the supplier to

construct and verify the build status of the end solution. The acceptance reviews are based on confirming

compliance with standards and procedures, clients’ needs being considered satisfied if the installed end product

is compliant.

Figure 4: Current NR Signalling Engineering Model

In the Digital Rail environment, the system interactions will only provide the required benefits if they are clearly

defined. To be clearly defined they must first be identified and captured. With clearly defined and measurable

system performance criteria and interactions, engineering assurance of suppliers can be tailored to utilise

different and more appropriate assessment techniques. The aim being to assure the delivery of the end solution

is progressing to plan and meets all achievable stakeholder requirements.

14

The Digital Railway engineering model therefore needs to place greater emphasis on identifying and engaging

with stakeholders to understand their needs and interactions, enabling them to be translated into clearly defined

requirements that can be developed into technical solutions. This in turn will allow for the transition from the

standards compliance engineering assurance process, to an outcome-based assurance technique. This

engineering management model requires greater effort in the direction of the stakeholder and relatively less

effort in the direction of the supplier, creating the ‘thin client’ model depicted within Figure 5.

Figure 5: Future Engineering ‘Thin Client’ Model

The ‘thin client’ model follows the consideration that the client’s effort would be better placed in managing the

higher-level interfaces and stakeholders to ensure that expectations are managed, and outcomes achieved

through ensuring whole system integration or System of Systems integration. The client therefore takes on the

role of ‘Railway System Integrator Partner (RSIP)’.

2.3 Defining Requirements The Digital Railway programme will affect the entire industry and there are several different stakeholders that

will be impacted by the new technology; each one

will have their expectations and perceived

overcomes. It is almost evitable that, whilst they

might all share the same overall ambitions for the

Programme, their specific needs may well be

contradictory or overambitious.

The Application Business Requirements (ABR)

will be developed to consolidate all the

stakeholder’s needs into a single common set.

Potential stakeholders in the ABR could include

DfT, RDG/FOCs, Supply Chain, TfL, RSSB, etc.

as depicted in Figure 6. The ABR describes the

outcomes that will be met by any given

programme or project.

The ABR can be generated using several different sources including; Client /Sponsor Brief, regulatory

requirements, stakeholder engagement workshops, standards, etc.

It is inevitable that the form of the input will come in different formats; maybe narrative, or, standards,

diagrammatic or a specific set of outcomes. These will be interpreted into the Concept of Operations (ConOps)

and the Application High-Level Outcomes (CRD). These documents transform the stakeholder requirements

into the application specific operational, functional and non-functional requirements. Once this process is

underway it will be necessary to conduct a series of workshops with the various users to ensure that the system

is being developed with their needs in hand.

ABRDfT

Trade unions

RDG/ RFG

Supply Chain

TfLRSSB

Maintainer

Operator

ORR

Figure 6: Stakeholders input into the ABR

RSIPStakeholder Supplier

EffortEffort

15

The requirements will also include for any assumptions or constraints that are ascertained as a part of the

stakeholder engagement processes.

2.4 The V-Life cycle The V-Life cycle (

Figure 7) is a model that is used to describe the process steps required to deliver Digital Rail project or

programme. The V-Life cycle provides us guidance on how we can execute projects in a sequential manner

whilst providing the framework for verification and validation to assure that the supplier produces the expected

outcomes. For the proposed contracting strategy, the V-Life cycle also provides the depth to which the client

organisation needs to step to undertake his verification and validation activities. This allows the client to focus

on the outcomes and demonstrates satisfaction of those outcomes to the client and stakeholders.

The Digital Railway Programme V-Lifecycle describes the process and reflects their delivery strategy.

Supplier s System Requirements Specification

(SRS)

Generic Source Information

DR Customer

Requirements Suite

Application

Concept of

Operations

(ConOps)

Application

Customer

Requirements

(CRS)

Application-

Specific

Engineering

Rules &

Standards

Route

Commissioned

and Track

Handed Back

Integrated

Route System

Installed

Components

Detailed Design and Production

Factory

Acceptance Tests

Integrated

System of

Systems

Application

Business

Requirements

Generic

Concept of

Operations

DR System of

Systems &

System

Requirements

Engineering Rules &

Standards

Final

Acceptance

Lin

ked

Compliance

Integration Tests

(RIDC Laboratory)

Integration Tests

(RIDC Test Track)

Integration Tests

(Route)

System

Maintained

and in

Operation

System

Decommissioned

Filtered Subset

Existing Level B & C

Requirements

(Initial Applications only)

Validation

Final Validation

Application

High Level

Outcomes

(CRD)

Application

System

Requirements

(RRD)

Application

Sub-system

Requirements

(DRRD)

Filtered Subset

Filtered Subset

Application

Operational

Test

Scenarios

Figure 7: ‘V’ Life cycle for Digital Rail projects

Due to the nature of the technology, the introduction of a DR solution cannot be considered in isolation. Generic

Concept of Operations and System and Subsystem Requirements Specification set out the overall requirements

and these will be considered as inputs to the requirements capture process too.

The supplier will be expected to work with the client to develop System Requirements Specification (SRS)

derived from the Application Customer Requirements Definition (CRS) and the Application System

Requirements (RRD) that addresses the Application Concept of Operations and ABR whilst adopting the

technical requirements as specified in the generic documents.

16

This allows for tailored solutions to be realised that are based on the specific project demands, the supplier’s

technology and the contracting strategy. The requirements for these solutions are captured and the variances

to the Generic are understood and managed under configuration control processes. This allows the Network

Rail team to;

• implement the best solution for the given application,

• understand where projects have varied from the generic, and,

• adopt best practice from projects and improve the generic.

To ensure that the overall DR solution can be integrated as a “System of Systems”, it will be essential to ensure

that the mandatory or common integration requirements are well defined and controlled to ensure that different

projects can be interoperable.

Assurance has traditionally been undertaken by continual design checking, reviews and approvals. However,

this is more difficult to do where the technology and the tools that develop the technology are automated and

software based. Furthermore, Digital Rail technology is a fast-developing forum where solutions are complex

and integrated in data. The solutions are driven by the supplier’s technology and that is where the expertise

resides.

It is, therefore, natural for the quality assurance to revert to the supply chain as they retain the expertise and

knowledge of their products. The client still needs to assure themselves of the solution, but need to look at

different approaches.

Figure 8: Relationship between the RSIP and the Technical Integrator

The adoption of a ‘thin’ system integration team requires the assurance paradigm to change. Both the Railway

System Integration Partner (RSIP) and the Technical Integrator must have confidence in the requirements

management process and in each other to perform the tasks that exist within their domain. The RSIP can choose

17

to check certain key deliverables to ensure the quality of the outputs are assured. The level and depth of

checking should be set out at the beginning of the arrangement, but be assessed on a periodic basis (i.e. at the

gateways) to determine if the right level of surveillance is suitable. However, the Technical Integrator will retain

the primary responsibility for the design process. The use of audits to assess the overall quality of the outputs

can be conducted to retain the ability to assess the work being undertaken at the bottom of the ‘V’, but these

audits should be focussed on enabling the project to proceed rather than a mechanism to ‘check-up’ on the

detail.

During the detailed design and development stages, the supplier will be expected to demonstrate that they are

conducting verification and validation exercises to the client. The client team will not be actively involved in these

processes.

The RSIP can use several techniques during the project to assure themselves, including verification tests that

can be conducted at each stage – i.e. do all the parent requirements have child requirements? Are there

orphaned requirements? Has the parent been reasonably defined?

The requirements management tool provides the ability to connect parent requirements to children

requirements. It is reasonable to assume that the relationship between a parent and their children is a one to

many one.

2.5 System of Systems The development of application specific solutions will need to be carefully managed to ensure interoperability

with other DR projects. The generic specifications provide both the architecture and the requirements needed

to ensure the various projects can be effectively integrated into the System of Systems (SoS).

Some of the objectives of the DR SoS generic design are to:

• Successfully deploy an integrated and repeatable train command, control and safety system on GB rail

network including

o Traffic Management System;

o Connected-Driver Advisory System;

o ETCS Trackside, incorporating equipment trackside for Level 2 (no signals), modern interlocking

technologies, and trackside equipment necessary for fitted trains running elsewhere on the GB rail

network

o ETCS Onboard

• Provide the framework to ensure that all DR delivery activities are aligned against a common understanding

and baseline architecture (i.e. maintenance, operations, engineering, people and process etc.);

• Provide a foundation for enabling the systems to be configured;

• Automated control of train paths derived from a planned time-table, and

• Increased service reliability and the potential for increased capacity and performance (subject to the

specifics of the deployment)

18

Business Systems

IXLSCWS

Central (STW)

SCWS Portable

(STW)

Trackside Objects

TM

GSM-R Data

FTN(X) EULYNX

SCADA

DRACAS

Digital Railway Programme

TM Protection (Portable)

CA

Trackside objects include level crossing control, train detection, lineside signals where fitted, remote monitoring, TPWS, trackside train monitoring systems etc.

Business systems include operational and business

systems e.g. TRUST, TOPS, Stock & Crew, TD Data etc.

Voice comms includes GSM-R

Voice system and lineside telephony

CCTV

Onboard systems

Voice Comms

CTI

Infrastructure and Onboard

Data Hub#

Trackside Maintainer

Onboard Maintainer

Trackside Operator

Onboard Operator

KMC

TM CCTV inputs include for level crossings, tail lamp

detection, sidings capacityETCS

TracksideETCS

Onboard

COMPASS Central

COMPASS Trackside

COMPASS Onboard

C-DAS Trackside

IM

C-DAS Onboard

C-DAS Trackside

RU

ATOOnboard

LINX

ATOTrackside

Figure 9: System Architecture

Figure 9 is the system architecture for the digital technology solution and demonstrates how the systems will be

integrated to ensure interoperability of systems.

As each project develops their Customer Requirements Definitions that are based on the Generic Requirements

and then tailored to the specific application, careful consideration needs to be given to preserve the generic

requirements such that the interoperability and integration of the project solution into the wider System of

Systems can be achieved.

This is a major challenge and should not be underestimated.

The need to meet challenging project delivery programmes will require the RSIP to make decisions on how to

achieve certain generic requirements that might not be aligned with the System of Systems approach. For

transformational programmes where the end state is not fully defined or understood the risk of deviation in

requirements is potentially high without careful management. This issue is further complicated by parallel

deployments of the Digital Rail solution all “learning” how to apply the requirements to their solution. Lessons

learned and good practice will need to be shared across the industry to ensure that the System of Systems is

realised.

2.6 Safety Management The hazard records that are generated from the safety assurance process are key deliverables for any project.

It is important to be able to demonstrate the Control Measures that need to be applied to satisfy the safety

19

argument for the project was proven. The control measures can be considered as emerging requirements and

should be considered equal to any input requirements.

If the control measures are to be considered as

requirements, and, therefore subject to

attention, in our management process then the

source, the hazard log, could also be considered

as part of the requirements management

process. A robust Requirements Management

Tool can allow for the management of the

hazard log too. Traditionally the hazard log is

maintained in an excel spreadsheet which is

quite restrictive. By considering the Hazard Log

as an element of a database, the hazard data

becomes more usable.

Like the process for requirements capture, the

CRS can consider the control measures from

two sources; the applicable items from the generic

hazard log and the application hazard log. The hazards and the control measures can be decomposed into the

CRS and attributed so that they are marked as Safety Requirements. This effectively builds the Safety

Requirements Specification within the CRS document.

This process embeds the safety assurance work within the requirements management process. The control

measures will be treated the same as all requirements and follow the V-Life cycle process being traced through

the detailed design, implementation and testing regimes. The Application Operational Test Scenario will be

prepared to include tests that demonstrate the safety requirements so that team can witness and be assured

that these are satisfied.

2.7 Verification and Validation Requirements management provides a technique of tracing requirements through the life of the project. This

provides the ability to verify that the children requirements are satisfying their parents. The verification activity

requires expert attention to ensure that the requirements are being satisfied correctly. This is especially

important where the requirements are complex with one to many relationships.

Where the traceability is being undertaken by the suppliers, the client organisation is reliant on their work being

undertaken correctly. The client organisation needs the supplier to assure that the requirements are being

satisfied during the detailed design and development phase.

2.8 Gateways and Audits There will be a need to ensure that the project is progressing according to plan and that the requirements are

being well defined and assured in the design and development phases. The use of audits and gateway controls

are the best approach.

Audits will be used to assure the requirements process is being conducted in an appropriate manner. The audit

should be seen as an opportunity to evaluate the evidence within the requirements database. The objective will

be to demonstrate that the supplier is developing the solution correctly. Where deficiencies may be found the

audit team and the supplier will agree corrective actions that can be enabled as part of the next phase of works.

Applicaton Hazard Control

Measures

Generic Control

Measures

Safety Requirements

Figure 10: Managing control measures as requirements

20

Audits will be conducted during the lower part of the ‘V’ Lifecycle where the supplier is wholly responsible for

the process.

Gateways shall be conducted at key points in the project where the client needs to ensure that the technology

is being deployed correctly, i.e. critically when the systems are being brought in to trial service or into operation.

Gateways will be used by the supplier to demonstrate to the client and stakeholders that the solution meets the

requirements. To ensure that these Gateways operate in a pragmatic and progressive way, the prioritisation of

requirements needs to be made at an early stage in the project. The Gateways will be led by Gateway Managers

whose role will be to focus on the key requirements that affect that gateway.

The client needs to be assured that the supplier has completed the works and that is satisfactory to pass to the

next phase of the project subject to agreement on action/mitigation plans that need to be implemented to

address any open issues that are identified.

Gateways are conducted to ensure the project is sufficiently developed / mature to move to the next delivery

phase. The gate process should commence during the initial phases of the project development through to final

handover and closeout. Early gates should be used to identify the gate stages applicable to a project and identify

the key deliverables and maturity level of the deliverable required at each phase to ensure the project risks and

expectations are managed. The gateway review should be conducted by a person independent of the direct

delivery of project but with sufficient understanding and knowledge of the project to ensure potential issues are

identified. The independent person should also be empowered to agree targets and mitigations against any

deficiencies identified during the gate review process.

Requirements Assurance Lifecycle – the following diagram sets out a possible path through the project

lifecycle and where gateways and audits could be inserted to assure the input requirements are being satisfied.

For the Digital Railway programme this diagram will be multi-layered as the deployment will include multiple

strands that need to be met for a brown-field implementation.

Figure 11: Proposed Assurance Lifecycle

The proposed Requirements Assurance Lifecycle includes 6 steps. It will be important to consider alternative

gateways depending on the application, i.e. additional gateways for system modelling, test track running, etc.

G1 – Tender: The client and sponsor agree the ABR, Application ConOps and the Application High Level

Outcomes. Depending on the nature of the project, this Gateway could include other stakeholders such as the

DfT, RDG, TOC, etc. This is a Gateway for the client to demonstrate to the sponsor and stakeholders that their

requirements as defined in the ABR have been properly defined and understood. By including the Stakeholders

21

in this stage, we are ensuring their engagement with the high-level requirements. This is a Go/No-Go Gateway

that happens before the supplier is engaged.

G2 – Preliminary Design Gateway: with the finalisation of the supplier’s System Requirements Specification,

the client and supplier agree the exact requirements to be implemented by the project. It is also possible to

finalise other project matters, i.e. programmes, costs, etc. The Gateway is undertaken with the supplier and is

for the supplier to demonstrate that the requirements have been properly defined and understood. This Go/No-

Go Gateway allows the supplier to progress into the Design and Development phase.

G3 (s) – Supplier Design Audit (s): this is an audit of the progress being made during the detailed design and

development phase. The number and frequency of audits will depend on several factors, i.e. the duration of the

design and development phase, the sensitivity of the project and the maturity of the supplier.

G4 (s) – Pre-Deployment Audit (s): This audit is an overview of the solution prior to the system being

manufactured or installed on site. The number and frequency of audits will depend on several factors, i.e. the

duration of the design and development phase, the sensitivity of the project and the maturity of the supplier.

G5 – Approval for Train Running: This is a key Gateway where the supplier will demonstrate their system is

ready for dynamic train running. The supplier will need to demonstrate that the verification and validation of

requirements has been met including the client’s relevant testing requirements as defined in the Application

Operational Test Scenarios. This is a Go/No-Go Gateway that empowers the supplier to undertake dynamic

test running.

G6 – Completion: This is a key Gateway where the supplier will demonstrate that all the requirements have

been satisfied including all the requirements in the Application Operational Test Scenarios. This is a Go/No-Go

Gateway that allows for the final handover of the system. It should be noted that this will happen after the

operational handover which will be achieved by the normal handover/handback processes.

2.9 Configuration Control and Change Management Audits and Gateways also provide an opportunity to baseline the requirements. Baselining the requirements at

key points in the project enable multi-disciplined activities to work from a source of the truth with confidence that

they are working from the same condition. It also provides the client a baseline for reference.

Projects mature across time and new emerging requirements are to be expected and managed. New

requirements may come from the design and development process, from the safety assurance process and

other sources including change of stakeholder expectations.

Using requirements management to assess changes provides a systematic approach that can provide a holistic

view of how the change impacts the entire system. The change can be analysed by tracing both up and down

the requirements path and across the affected areas to ensure that the impact of the change is fully understood

before it is implemented. Both the client and the stakeholder can have an agreed understanding of the impact

through this process.

As changes emerge throughout the project life it is important to re-consolidate the changes – this can be done

at the next baseline.

22

3 Requirement Management Process and Tools This proposal is based on integrating a solution that acknowledges the current working practice with tools that

have been used on mega projects to deliver a progressive assurance process that enables project owners to

take a holistic and pragmatic stance in the management of complex railway programmes.

The processes and tools described below have been successfully deployed on multiple overseas projects where

the client has a “thin organisation” which have relied upon using outcome-based specifications and minimal

national standards.

The ability to integrate the Requirements Management Database with the Electronic Document Management

System and the Progressive Assurance Tool is extremely powerful

Requirements Management Database: Traditionally in the UK, the DOORS database has been the “go to”

application for managing requirements. The database is a collation of requirements that can be linked together

to demonstrate that the design, implementation, verification and validation are aligned.

For complex and multi-layered projects, the need to understand how

requirements are being interpreted as the design matures through the

project lifecycle is both challenging and complicated. It is also essential

to understand to ensure the outputs realise the intended outcomes.

However, technical submissions remain a document driven process

meaning the Requirements Management is subservient to the

demands of a programme driven document submittal register.

Documentation that is not coordinated with the Requirements

Management database can contain many orphaned and unrealised

requirements.

Electronic Document Management Systems: Projects, invariably, are driven by documents. These

documents are registered in an Electronic Document Management System such as Enterprise Bridge (eB). This

system provides an electronic record of the deliverables, their versions and their history. However, these

documents tend to be isolated without practical links with other documents. Embedded requirements in these

documents can be lost, mis-acquired or deviate the results incorrectly.

Progressive Assurance Tool: The Progressive Assurance provides the ability to manage the requirements

assurance process. It can be used to capture assurance checking comments on the decomposition of

requirements and on documents. It provides clear traceability paths both upwards and downwards. Reporting

can be managed better, providing stakeholders clarity on their specific requirements, as well as providing project

delivery teams focus on the issues.

The combination of the three systems (system suppliers can provide more than one product within their system)

provides a framework for requirements to managed in a proactive and controlled manner.

By having a model that connects the three systems together we can ensure that the requirements in the

documentation are aligned with the requirements in the database. Changes in the documents or in the database

can be flagged in the progressive assurance tool for attendance and assessment. This approach provides the

ability to manage the configuration in a dynamic and proactive manner.

Using a web-based requirements management system provides suppliers (and their supply chains) the ability

to use the “live” database to undertake their requirements management activities. The client can observe the

Requirements Database

Progressive Assurance Tool

Document Control

Figure 12: RM Tool arrangement

23

progress remotely without the need for intrusive design review and checking regimes. There is still a need for

audits to be conducted but these can be planned at key stages in the project timeline.

3.1 Progressive Assurance As the ABR is outcome based it will be benefit driven in terms that can relate to the

various stakeholders. Using progressive assurance techniques, it is possible to take

the stakeholders on the same journey with full visibility of how their benefits are being

translated into design requirements through to delivered products.

By using the input documents as a baseline, the supplier shall develop the System

Requirement Specifications and then trace the relationship with the performance requirements. The relationship

can be one to one or one to many depending on the nature of the requirements.

By using a progressive assurance technique, the client can then monitor the development of the design and the

evolution of the client requirements in real time online. The client can be satisfied that the design of their

requirements is maturing through the design process without undertaking intrusive and time-consuming review

processes. Gateways can be established (as set out above) throughout the design process that checks the

maturity of the requirements rather than on the completion of design documents

Progressive Assurance has been proven to provide the client the ability to monitor the supplier’s work by

measuring compliance to the requirements rather than on the ability to submit documents. Focus can be given

to requirements that are not evolving allowing the client and supplier to trouble shoot better.

By giving the supplier the freedom to operate in the design domain it can improve the client-supplier relationship.

Governance becomes more than a simple measure of compliance adherence and thus removing some of the

unnecessary and irrelevant constraints that a compliance approach introduces.

3.2 For Tendering Traditionally tendering has been a process of reviewing tender submissions that

are provided in paper or electronic format. Even having a compliance matrix can

be difficult to follow or trace the requirements and therefore be assured that the

supplier has demonstrated that can achieve the requirements.

With a Requirements Management Tool (RMT), the system can be used as the

key tendering submission. The client organisation will prepare the tendering

specification requirements within a subset of the database which is issued to the

tendering parties.

The tenderers are then required to respond using the database demonstrating

how they will comply with the tender requirements.

The tender review panel then use the progressive assurance tool to evaluate the

tenderers responses, confirm compliance, comment and, where necessary,

raise Technical Queries.

Tender Queries can be issued in the database formatted format and responses can be received in the same

manner.

In this way, the tendering process can be well managed, configuration control can be maintained, and progress

can be easily demonstrated.

Tender Specification

Tender Response

Tender Review

Tender Queries

Figure 13: Tendering process managed by the RMT

24

3.3 For Planning Every requirement must be analysed to determine its prioritisation, its lifecycle and its verification and validation

(test) conditions.

The process of requirements analysis also provides a method of planning the requirements life.

Requirement prioritisation is the process of assessing the need; most projects consider whether the

requirement is mandatory (i.e. safety/operation critical), preferred, or optional. Prioritisation allows the delivery

teams to focus on the key requirements to ensure that the project can be successfully handed over to operations.

This is important on complex projects where there are 10s of thousands of requirements to be analysed, traced

and assured.

Every requirement has its

own timeline. That is to

mean that requirements

can be assured at different

times in a project lifecycle.

Predominately,

requirements tend to be

validated during the

testing phase, but some

could be assured in the

design phase,

manufacture or the

installation.

Overall, we can generate

a Requirements Lifecycle

Model that describes the

completion of all the requirements. This model describes when the requirements are completed and does not

reflect the actual effort conducted in the requirements management exercise. It is therefore sensible, to weight

effort for all the requirements (i.e. weighting for requirements could be based on the current DR model design

of 50%, 95% and then at completion of the testing).

We can now monitor the project using two ‘S’ Curves; Requirements Lifecycle Model and Requirement Effort

Model in mapping requirements. The first provides a measure of the progress to actual completion and the

second provides a measure of the value of the work undertaken.

These requirements management techniques provides another tool to the project in planning the works being

undertaken.

3.4 For Project Monitoring and Control Progressive Assurance is designed to enable the engineers in both the client and supplier’s organisation to

focus on the system engineering solution. The system provides the tools for tracing the requirements through

the project life cycle. It also provides the ability to review and comment in a controlled place.

Design Reviews: Projects will continue to deliver requirements in document formats for the foreseeable future.

These documents can be uploaded into the progressive assurance tool and compared to the requirements

management database. Compliance can be assessed and where comments required they are generated within

Manufacture/Install

System Test

Dynamic TestDesign

Progress %

Effort weighted progress S Curve

Requirement Lifecycle

Completion

Project Lifecycle

Figure 14: Requirements driven 'S' Curves

25

the tool. Reviews are therefore linked to requirements and are contained with the Progressive Assurance Tool

providing a permanent and traceable record of the assurance process.

A requirements traceability record can be a particularly powerful tool when demonstrating the safety assurance

process to others such as the ISA or the regulator.

New versions of the documents can be reviewed in the same system and updates that have resulted from

review can be assessed in the system.

Progress: using requirements management to monitor the progress can be a useful project management tool

that can be used alongside the more traditional progress matrices. The ‘S’ Curves are just some of the reports

that a progressive assurance tool can generate. As the system is “live” it can provide daily, weekly or monthly

reports that can be optimised for the audience, i.e. stakeholder specific progress reports that focuses on the

specific stakeholder and their needs.

Benefits Driven Programmes: with technology projects there is an opportunity to manage the delivery

programme based on delivering benefits rather than delivering products. By understanding what functionality

provides what benefits we can judge what value can be had from providing them early. This type of programme

strategy can only be considered in specific projects such as traffic management systems where the functionality

can be achieved in a more staged manner rather than ETCS where the requirements requires all products to

be realised at the same time.

Managing Innovation: Digital Rail takes advantage of new and emerging technology to deliver solutions. The

delivery strategy needs to be open to the continued innovation in new technology to ensure the most appropriate

solutions are realised.

Managing requirements progressively allows the delivery team to “innovate” by defining those requirements that

are mandatory and those that can be innovated. Programmes can then be developed so that the innovation

requirements follow different timelines to the mandatory ones. Separating mandatory and innovative

requirements means the delivery of the core functionality can be focussed on and assured to achieve the

schedule whilst allowing the design teams more time to innovate and create solutions that meet the emerging

requirements.

26

3.4.1 Engineering Management Structure

The Digital Railway introduces a need for greater interaction between track and train. To realise the railway

system benefits required for the future, these systems need to be highly integrated.

The current Network Rail signalling project delivery structure focuses heavily upon re-assessing the finite detail

of the supplier’s deliverables, in particular the application design. The complexity of the system interfaces using

software and application data makes this traditional approval process (design/check/review/approve) ineffective

in assuring the sponsor that the high-level safety, functional and operating requirements are being fulfilled.

The engineering assurance model required for corporate governance must therefore change to ensure that

suppliers are providing a solution that meets the client’s needs. This model will need to apply different

techniques to provide this assurance with focus on moving towards measuring the supplier through

outcomes/outputs rather than through the constraints of standard compliance. The modified assurance model

will create a different engineering management structure focusing on the interactions between the project and

other stakeholders. This model is being referred to as the ‘Thin Client’.

3.5 Engineering Interface Management

The thin client model presents a single supplier interface to the client. In practice this model would be extremely

limiting and contrary to the client procurement policy. The key elements of the Digital Railway (TMS, ETCS

Trackside, ETCS Onboard, Communication network) may be procured from multiple suppliers. This creates a

further consideration as to how the engineering interactions between multiple suppliers can be managed. The

solution must ensure that the technical skills within each supplier organisation work effectively together to

achieve the final integrated Digital solution.

Network Rail’s Engineering Management for Projects process (NR/L2/INI/02009 Issue 6) provides three

engineering interface management structure models (options 1-3). The three models are based around the

responsibility for design integration. Recent IP signalling renewals projects have applied a hub and spoke

contracting model with Network Rail managing the interfaces and acting as the design integrator, this is

represented as option 2 within the standard.

Option 1 [Figure 15] and Option 3 [Figure 16] align with the ‘thin client’ approach where the supplier Contractors

Engineering Manager (CEM) takes responsibility for the integration of the multi discipline designs. The two

options allow for different contracting arrangements, with option 1 covering the single source option whereby

the supplier is contracted to undertake all discipline activities, while option 2 permits Network Rail to contract

individual disciplines directly but appoints one supplier as the design integrator. Using the existing management

models within the thin client structure the traditional CEM role will be a ‘Technical Integrator’ for the activities

within their work scope. The Technical Integrator (supplier) will become responsible for conducting assurance

activities in line with their Quality Management System, allowing the RSIP to satisfy themselves that assurance

is being actively controlled/managed by receipt of supplier declarations and reports.

27

Figure 15 - Design Integration Model (extract NR/L2/INI/02009 Option 1)

Figure 16 - Design Integration Model (extract NR/L2/INI/02009 Option 3)

28

3.6 Supplier Maturity

The supplier maturity will dictate how closely Network Rail will need to monitor and interface with the supplier

in the discharge of their duties for corporate governance, legislation and regulation compliance. The engineering

model applied needs to ensure that Network Rail is executing its duty to adequately manage safety and business

risk.

A justifiable method to support Network Rail’s decision to discharge some of these duties to the supplier under

the thin client model could be based on a predetermined supplier maturity level scoring or ranking. The ranking

system could be based on external body supplier qualification schemes such as Railway Industry Supplier

Qualification Scheme (RISQS) and Capability Maturity Model Integration (CMMI). Network Rail would use this

pre-assessed ranking to supplement a maturity level verification process at tender pre-qualification or during

the formal tendering process. This will allow Network Rail to execute an appropriate level of control, scaling its

engineering delivery team commensurate with the risk, complexity and novelty, as appropriate and forming part

of Network Rails Assurance process for level 2 – Corporate Oversight.

The application of a maturity model-based approach to engineering assurance, taking cognisance of the

maturity and experience of the supplier / suppliers within the GB mainline railway and Digital Railway

frameworks, allows for a scaling of the client team based on the supplier’s experience. The use of a supplier

maturity assessment also provides Network Rail with a mechanism to introduce new suppliers into the GB

railway market to ensure competition is maintained through the procurement chain. The new supplier having a

potentially lower maturity rating requires an increased level of effort for monitoring/review to achieve client

confidence in the supplier’s assurance process.

Figure 17 – Immature Supplier Engineering Assurance Model

The Project Engineering Management plan should be used to record the supplier maturity level and define an

appropriate Network Rail Engineering structure to manage the corporate risk.

3.7 Section Summary

The use of NR/L2/INI/02009 Issue 6 options 1 or 3 appears to provide potential models to implement the thin

client / supplier engineering interface. A supplier maturity assessment should be considered as this will provide

an indicator as to the level at which Network Rail can discharge its duties to the supplier whilst maintaining its

legislative obligations and satisfying corporate governance requirements.

Further consideration, whilst NR/L2/INI/02009 Issue 6 provides options that can be applied, the use of an

existing process may lead individuals to follow previous behaviour and overly focus on assuring the supplier’s

deliverables. For this reason alone, the production of a new or revised standard may be appropriate as this is

likely to create the desired new behaviour. Alternatively, the Project Engineering Management plan could be

subject to high level senior review to ensure the engineering assurance process is clearly defined and satisfies

Network Rails corporate governance requirements.

RSIPStakeholder Supplier

EffortEffort

29

3.8 Roles, Responsibilities and Accountabilities

The Digital Railway thin client engineering management structure will evolve around two key defined roles:

➢ Railway System Integration Partner (RSIP)

➢ Technical Integrator

These roles will take the lead in ensuring the technical solution fulfils the requirements for the system of systems,

meeting the safety and functional requirements. They will also retain responsibility for executing engineering

assurance activities to comply with legislation and corporate governance.

3.9 Railway Systems Integration Partner (RSIP)

The RSIP will be a role within the refined engineering structure with a focus on the greater railway system

(System of Systems). Responsible for ensuring the technical requirements of stakeholders are clearly defined,

captured and satisfied. The specific duties of the RSIP will align with the contracting model and supplier maturity

to ensure that Network Rail’s duties and obligations as required by legislation and governance polices are

adequately executed. However, the RSIP’s focus will be on ensuring that stakeholder interfaces are defined

and managed to ensure whole system

integration.

The stakeholder interactions and interface to

the sponsor shall be detailed within the

project engineering management plan.

The RSIP may need to execute some or all

of the duties of the DPE role as defined

within NR/L2/INI/02009, where these have

not been discharged to the Technical

Integrator. This shall be detailed within the

Project Engineering Management plan.

The RSIP should contain a Lead Engineering competence and be appointed.

The RSIPs key technical duties could include:

➢ Act on behalf of DRs Systems Authority as the system authority for the System of Systems

o Owner of project engineering management plan

o Define the NR engineering structure based on the maturity of the supplier & baseline solution.

o Act as registration entity - updating of each European Union Member State’s National Vehicle

Register (NVR)

o European Railway Agency (ERA) project register (one stop shop)

Figure 18 –RSIP’s Interactions

Stakeholder

System

Integrator

Independent

Assessor

Regulatory

Body

Route

Sponsor

Technical

Integrator

(Supplier)

Others

Railway

Undertaking

30

o Act as Sponsor for Product Acceptance

o Manage the Asset Management Plan

o Develop IM and RU compatibility tests

o Production of Technical file

o Appoint lead Technical Integrator

o Technical Change Control Management

o Manage System Baseline

o Infrastructure data management

o Manage open points and deviations with combined SRS

o Key contact between projects with responsibility for ensuring integration

o Identify performance indicators in conjunction with the project manager

o GB ERTMS National Identities project co-ordinator

o GB ERTMS KMC key co-ordinator

o Lessons Learned are feedback in to the DR team

o Certify the System Solution

➢ Legislative Compliance - Network Rails duties under the regulations are satisfied.

o CDM compliance

o ROGS compliance

o TSI compliance

o NTR compliance

o CSM compliance

o HSE – ensure suitable and sufficient risk assessments are completed

➢ Corporate Governance

o Maintain a level of technical governance, although reduced to fit thin client model based on the

supplier maturity.

o Define Engineering Verification Plan NR/L2/RSE/070 Issue 2 – the verification plan shall specify

the split between supplier self-assurance and Network Rail engineering assurance activities.

o Conducting supplier Assurance activities. Based on NR/L2/ASR/036 Issue 5 Network Rail

Assurance Framework Level 1 and NR/L2/SIG/10027 Issue 4 for Surveillance of Signal

Engineering Activities. Note this should be based on the supplier maturity model and limited to

performing spot tests on the supplier rather detailed deep dives. Activities such as site

surveillance may be satisfied through review of supplier’s own records.

o Identify / define whole system level integration requirements

o Define system level integration points. This should be commenced during specification phase

to ensure all stakeholders are identified, consulted and requirements captured.

o Support Project Manager for technical gate reviews

o Support Project Manager in defining a regime for monitoring key project integration milestones

o Manage technical approval process for elements identified within the Project Engineering

Management plan.

➢ Stakeholder Technical Interface

o Identify / define stakeholder interfaces with sponsor

o Identify / classify technical interfaces between stakeholders

o Act as technical contact for sponsor stakeholder interactions

o Assist client in defining and specifying technical elements of the CRD

31

o Ensure stakeholders are advised of/aware of training requirements

➢ Tender Support

o Current pre-contract award DPE duties as defined in NR/L2/INI/02009 Issue 6 will need to be

retained by the RSIP

o Endorse contract technical work scope

➢ Requirements Capture / Management

o Manage requirements outside of the supplier’s remit.

o Selection and gap analysis of Generic source information (concept of operations, System of

systems requirements, Engineering rules & Standards)

o Prepare relevant technical requirements for inclusion in contract

o Capture stakeholder requirements and ensure clearly defined (Customer Requirements

Specification)

o Assist in production of RRD

o Compile DRRD

o Identify and define expected supplier outcomes and measurement criteria from combined SRS

o Align stakeholder CRS with Digital Railway RS and Route RS

➢ Change Control

o Manage changes to stakeholder requirements

o Facilitate the resolution of issues within the defined requirements, deviations and non-

compliances with the requirements.

➢ Safety Assurance

o Appoint Safety Assessor

o Agree safety assurance process and CSM models to be applied.

o Accept Safety-Related Application Conditions (SRACs) exported by supplier

o NoBo / DeBo interface

o Confirm that adequate assurance has been undertaken to take the system into use.

➢ Pre-supplier appointment

o Act as Technical Integrator

➢ Project RSIP Handover to Route Asset Manager (RAM)

o Transfer system performance requirements to RAM

o Verify outcome criteria satisfied / identify deviations

o Lesson learned outputs

o Authorisation to operate

o Warranty

The need for a Maintenance RSIP to manage the maintenance contract has not been considered in this

remit, but it may be of consideration in the future.

32

3.10 Technical integrator

The technical integrator

role may be performed by

an individual or a group of

closely interacting

individuals with a

nominated lead. The

technical integrator shall

be responsible for the

interactions between the

signalling sub systems and

this may be extended to

incorporate both the

trackside and on-board

sub systems dependent

upon on the contracting

strategy.

This role is likely to

execute the duties of a

design integrator and

CEM.

The technical integrator

organisation structure and

interfaces shall be detailed

within the Project

Engineering Management

Plan. It is expected that

each supplier / technical

integrator will develop their

own sub-system

Engineering Management

Plans which will act as

child documents to the

Project Engineering

Management Plan.

The lead technical

integrator shall be

responsible for ensuring

the functional interfaces

between signalling

subsystems are clearly

defined and functionally

correct. The role may include activities to

support the V&V process.

Figure 19 –System Integrator Interactions

Lead

Technical

Integrator

(Supplier)

CEM

CRE

Disciplin

e 1

CRE

Disciplin

e 2

CRE

Disciplin

e 3

Engineer

ing

Manager

CRE

Disciplin

e 1

CRE

NRT

Stoke

Tech

CORE

Control

System

ARS

TMS

Time

table

processo

r

C-DAS

Access

Node

Gauge

Engineer

Traction

System

Signallin

g

System

Depot

Maintain

er

Safety

Assuran

ce

Indepen

dent

Assessor

Product

Assuran

ce

Trackside

Technical

Integrator

Onboard

Technical

Integrator

Control

System

Technical

Integrator

Assessor

Maintain

er 2nd

Line

33

The Technical Integrator shall be nominated by the lead supplier and appointed by the RSIP.

Technical Integrator key responsibilities:

➢ Principal Contractor

➢ Subsystem Interface Act as subsystem design authority

➢ Subsystem integration

o Act as CEM including managing the self-assurance of all technical documents. The CEM, under

the NEC4 contract, would need to satisfy the Service Manager that the correct approvals have

been obtained to enter the system into service.

o Identify functional interfaces between physical sub systems i.e. CCS trackside, On board,

Control system / TMS and communication network.

o Ensure functional interface requirements are clearly defined and allocated to the relevant sub-

system

o Ensure sub system interfaces are subject to configuration management as required by the

engineering management plan.

o Lead Interdisciplinary checks and reviews (IDC/IDR) ensuring functional interface designs are

aligned, integrated and meet the defined requirements.

o Ensure tests are defined for testable functional interface requirements

➢ Ensure open points within sub systems / interfaces are managed

➢ Competence

o Appoint competent people to key roles identified within the Technical Integrators organisation

structure.

o Ensure key personnel within the technical integrator framework are formally appointed.

➢ Manage technical change.

➢ Put forward product acceptance

➢ Compile SRS

➢ Audit / surveillance checks

➢ Technical KPI reporting in line with supplier QMS

➢ Technical Query Management between Technical Integrators

➢ Technical Query escalation to RSIP

➢ Generating Engineering Compliance Certificate

➢ Manage and resolve construction issues

➢ Manage handover process to maintainer

➢ Define sub system training programmes

Further consideration will need to be given to defining these roles so that the contractual boundaries and

responsibilities are well understood. Contractual consideration needs to be given to the delegation of duties by

each party and how the technical authority can execute his works whilst engaging with suppliers that they may

have no contractual relationship with (i.e. train manufacturers). This has not been considered in this remit.

3.11 Section Summary

The RSIP and Technical Integrator will be the leading responsible engineers within the thin client model. The

RSIP role being held by the client organisation, whilst the Technical Integrator role is contained within the

supplier organisation. The detail of the responsibilities split will be based upon the level of devolution for

engineering assurance from the client to the supplier, which should reflect the maturity of the supplier within the

GB mainline railway environment. The project engineering management plan should be used as the vehicle to

34

define and record the engineering management structure applied to the project, thus ensuring that the detail of

the roles and boundaries are clearly recorded.

35

4 Technology solution

4.1 Introduction The use of ETCS Level 2 effectively mandates a specific solution architecture for the signalling system. An

ETCS level 2 system will consist of an Interlocking Safety Processor which is in close communication with the

Radio Block Centre. The Radio Block Centre generates Movement Authorities which are based upon the

geography of the railway and the availability of routes from the Interlocking. The Interlocking communicates to

the trackside assets (points machines and train detection) via the communication network (FTN) and the RBC

communicates to the ETCS onboard units via the fixed communications network (FTN) and the radio network

(GSM-R). This is shown in Figure 20.

.

ETCS OnboardETCS Onboard

InterlockingRadio Block

Centre

Control Centre

Trackside Assets

ETCS Onboard

Units

FTN/GSMR

Trackside Assets

Trackside

Assets

Figure 20 Signalling System Architecture

Figure 20 highlights the importance of the integrated communication system (FTN<>GSM-R) for the

communication between the Interlocking and Trackside Assets and between the RBC and ETCS Onboard Units.

Without reliable and timely access to the Network, the delivery of the ETCS system can be put in jeopardy.

As stated earlier the RBC generates the movement authority based upon route availability and geography of

the railway. The purpose of the movement authority is to provide information to the onboard unit to allow it to

calculate a safe movement and braking profile to ensure the safety of the train. Previously under traditional

signalling the location of the point at which the driver would begin braking was based upon the performance of

the worst braking train which could run on the line. With ETCS this braking position is calculated dynamically

36

for each train. This provides the opportunity for trains to be operated closer together (subject to optimising the

existing fixed block lengths for Level 2 systems) providing greater capacity over traditional signalling.

Extra capacity can be provided by increasing speed through sections as a result of reduced braking curves.

Block section length may also be reduced by using the characteristics of the worst braking train. Variations in

rolling stock will still be a constraint as the trackside design is only a facilitator to increasing capacity. A holistic

approach which considers the trains and the trackside is required to maximise the capacity gains that ETCS

can provide and to prevent safety events. Poor input data can cause the design tolerances to be so great that

any benefit is lost to compensating for those tolerances.

4.2 Inputs Required for ETCS Data Creation To deliver ETCS data of suitable quality and veracity the Infrastructure Manager needs to provide an accurate

3D geographical model of the physical railway (or allow for suppliers to generate their own).

This input includes media that enables the designer to determine the location of assets. It will include the location

of all physical assets in a form that is both human readable and electronically readable. Ideally, it will be available

in a visual form that enables the designer to check for logical inconsistencies. Ideally, it will identify the location

of assets in a datum plus offset format.

The geographical model will identify the location of:

• signals;

• track detection sections IBJ / Axle Counter Heads;

• point tips;

• gradients/spot heights;

• static(line) speed restrictions;

• buffer stops;

• platforms;

• balises;

• marker boards

The geographical model may also identify the location of:

• Low adhesion areas (LAAs);

• ESAs/ Signal Group Replacement Controls (SGRCs);

• Interlocking boundaries;

• RBC boundaries;

• Tunnel emergency exits This input forms the primary geographical input into the process. Hence, its correctness and control is vital. It

must contain geographical information covering all physical assets on the railway to a high resolution, potentially

in the order of 0.1m and to an accuracy of +/-0.5m for dense high capacity sections of the Railway. This level

of accuracy is required to ensure high performance ETCS operation. Lower accuracy data can be used but the

additional tolerance may reduce the performance of the ETCS system. Modelling of the performance required

and therefore the survey accuracy required may be undertaken prior to the survey beginning.

Surveying of gradient is important as an incorrect gradient measure could cause an overrun of an MA by a

protected train. Attention should be paid to accurate measurement of the gradient.

A secondary data source for verification of logic, completeness and correctness is also required. This needs to

be a diverse survey and must be entirely independent of the geographical 3D model. The required accuracy of

37

the secondary survey information is less than onerous than the primary geographical survey information. It shall

be accurate to +/-5m. However, its completeness and correctness is critical. This could be other documentation

such as Signalling Plans, Verification Surveys for other engineering domains such as Permanent Way or Civil

Engineering or drone surveys.

Following completion of the surveys it is vital that the railway configuration is managed. This is especially

important where other works are undertaken alongside ETCS implementation. Any changes need to be

identified and supplied to the ETCS supplier in order to keep the data model accurate.

As implementation of the scheme continues a feedback loop between design and implementation also needs

to be closed to ensure the ETCS data reflects the actual implementation of the system and to the above

accuracy. An example of this is siting of ETCS balises as per the design. This may be prevented due to other

equipment in the siting location. Any change in this location (even by a few metres) must be fed back to the

ETCS data design team to keep the data correct. This could be done using an ETCS test train running over the

area to ensure they are within the design window.

4.3 NRT As part of the Digital Railway thin client approach

it is proposed that changes are made to the

mechanism of contracting Network Rail –

Telecoms (NRT). Currently NRT is contracted to

Network Rail IP Signalling. This can create issues

in communication as all design work needs to be

passed via the IP Signalling team. These issues

can reduce the ability of the contractors and NRT

to collaborate efficiently and deliver the best

solution.

As part of the Digital railway proposals there is the

concept of the Technical Integrator. This role would be

undertaken by a major contractor. It is proposed

that Network Rail Telecoms would have a direct

relationship with the Technical Integrator. This

would allow direct communication between the

Technical Integrator and NRT. It is expected that

this would enable greater collaboration between the

two organisations, as well as communication to

ensure issues are resolved quickly and efficiently.

An issue may be around encouraging collaborative

behaviour in the relationship. The provision of a

service level agreement to formalise this

relationship may be a useful device.

A service level agreement could include the

following areas:

• Timescales for design work and reviews

this may include an agreed baseline programme

NRT

Technical System

Integrator

Railway System

Integrator

Figure 22: Proposed Project relationship

IP Signalling

Signalling Contractor

NR-T

Figure 21: Current NRT Project Relationships

38

• Attendance at Interdisciplinary Design Checks/Reviews

• Agreed inputs and deliverables.

• Availability of the provided FTNx services

• Integrity of the provided FTNx services

Previous collaborations between suppliers have shown that for it to be truly effective then collaboration needs

to be more than skin deep. A deep commitment between organisations is required to break down borders and

ensure team members engage with each other. It must be a true relationship with common goals and a desire

to meet those goals. Co-location of key staff to allow the building of relationships and to create a dynamic

problem-solving environment can help with this. Whilst a service level agreement can attempt to force

behaviours; true collaboration requires active engagement from all and can lead to a more successful outcome.

There may be scope for NRT to “sub-contract” design work for the FTNx solution to suppliers chosen by the

Technical Integrator. NRT would still be responsible for setting the constraints around the design such as

equipment used to ensure maintainability. The Technical Integrator may be able to use suppliers already in their

supply chain and to maximise that relationship to improve delivery quality.

As a national system the FTNx may also be subject to multiple simultaneous changes which can impact one

another. As the Infrastructure Manager NRT needs to be able to manage these changes in parallel and ensure

that conflicts do not occur. They would need to place requirements on the Technical Integrator as part of the

whole system integration piece.

39

5 Form of Contract

5.1 Proposed Form of contract

Digital Railway (DR) has proposed using the Design, Build and

Operate NEC4 contract for the Moorgate line and other DR works

on the ECML South. This contract shall be performed as a Design,

Build and Maintain contract with the current NR maintenance staff

maintaining as employees of NR. The current maintenance staff

may however be working under the instruction of the Contractor.

The following sections provide a supplier commentary on

questions and concerns that would have to be addressed during

or ideally before a tender was issued.

To ensure that an effective tender process is completed, it may

be of significant benefit to workshop some of the questions raised

below with the suppliers to reduce the number of TQ’s during the

tender phase, which could disrupt the tender process, before the

OJEU notice for the works is issued.

5.2 Contract clauses This section shall comment on the core clauses by category set out within the contract. This section should be

read cross referencing the NEC 4 contract.

5.2.1 General

Clause Commentary

11.2 (2) Affected property – given the nature of working on the railway the “property” is handed over and back on a regular basis. Similarly, other parties shall be working on the network; the impact of this scenario may have to be considered.

11.2 (5) Defect – depending upon any contract incentive or penalties a defect will have to be clearly defined within the service, there will need to be consideration to a defect within the build phase verses the maintain phase of the works.

11.2. (6) Defined Cost – discussed within the Schedule of Cost Components.

11.2 (9) Equipment – When will the transfer of ownership take place? What obligations will be on the Contractor at the end of the maintenance period? The required state of the equipment at the end of the maintenance phase.

11.2 (17) Price Adjustment Factor - What price adjustment factor would be most relevant to this type of works?

11.2 (20) The Price for Services Provided to Date – What measurement within the price list shall be used to assess the payments? The client or contractor could propose this, for the build phase. It is more likely to be defined for the maintain phase e.g. periodic payments.

11.2 (22) Scope:

Describes the Service: This is obviously a key document and traditionally be the contract requirements technical.

Figure 23: NEC4 Contract

40

Clause Commentary

Constraints on how the Contractor Provides the Service – Given the move to an outcome specification approach this section is key to setting the parameters within which the contractors can work.

13.2 Communication system: Which system would be used EB?

5.2.2 Contractor’s main responsibilities

Clause Commentary

20.2 The Contractor minimises the interference caused to the affected property – Traditionally it is the Client’s responsibility to provide access to the railway, however would typically provide an access schedule within the CRT. This clause may need to be amended to reflect how access would be treated within the project.

21.2 The Service Manager accepts the design – Who within the Project acts as the Service Manager, what stakeholders would be involved within the process, or would this be an independent activity for example and ISA? Approvals such as ORR approvals would have to be defined within the scope.

21.5 Record of the contractor’s design – What records would be required to be retained and for what period? Drawings are typically handed over however IP is retained by the Contractor.

23.1 What “Key People” would be required to be provided by the Contractor? Typically, frameworks contracts often also have further management requirements such as management boards.

24.1 The Contractor co-operates with others – Others would need to be defined within the contract, this should state the responsibilities of who manages which stakeholders. The list of others could be significant if the Contractor takes on the Principal Contractor role.

5.2.3 Time

Clause Commentary

30.3 At the end of the Service Period the contractor returns the …property in the condition stated within the scope. Currently the property is handed over to the client after the build stage, i.e. the property is new. Works may need to be undertaken to define in what condition this property is in at the end of a 10+ year maintenance period.

33.1 Access – Access is provided by the Client in accordance with the Accepted Plan. This clause may need to be modified depending on how the access is to be estimated for and provided.

5.2.4 Quality Management

Clause Commentary

40.1 The Contractor operates a quality management system which complies with the scope – Under existing contracts this is not defined as the Client takes an active involvement of the checking of designs, there are only usually references to materials and workmanship.

41 Tests and Inspections – currently there is an obligation on NR to provide the track time and potentially a train from the TOC’s to facilitate any testing this may need to be accounted for with in the clause.

41

5.2.5 Payment

Clause Commentary

52. Defined Cost shall be reviewed within cost components.

53 Performance measures – The performance measurement criteria need to be set out within the contract data, the mechanism of the any adjustments needs to be reflected within this clause. This is a key factor when assessing the risk which is to be designed out or priced.

54 Price Adjustment – needs to be decided as previously stated in the definitions, 11.2 (17).

55 Price List – The format of the price list needs to be defined for both the build and maintain phase. In addition to a rate card what form would the pricing exercise take for a given tender.

5.2.6 Compensation Events No specific comments within the process set out for compensation events; there is a section to add additional

compensation events within Contract Data Part 1.

5.2.7 Use of equipment, Plant and Materials

Clause Commentary

73.1 Title to Materials – The contractor has no title to materials within the Affected Property … Whilst the title of materials passes to the Client the clause does not deal with any provision of IPR, licences or third-party guarantees. These are likely to need to be addressed somewhere within the contract.

5.2.8 Liabilities and Insurance The levels / limits of insurance and liabilities are to be completed as an option in X18. The level of risk around

schedule 4/8 railway costs is typically defined and capped within the contract. Similarly, the risk around liability

during the maintain phase needs to be defined as it could have a significant impact on the solutions or pricing

of the works. Consequential losses are usually also defined in more specific detail for the protection of both

parties.

NR usually provides an insurance manual for each project, there is an expectation this would continue for future

projects.

5.2.9 Termination Digital Railway has already stated that their governance dictates that they have a termination at will clause

within the contract. The clause will need to be amended to reflect this.

5.2.10 Option clauses Dispute resolution – would need to be agreed between the parties, but given the on-going, established

relationships with the supply chain, a governance board type approach may be more applicable as a form of

mediation initially.

Ultimate Holding Company Guarantee – Many suppliers have different parent company relationships. Given

the scale of the majority of the suppliers in the market the implementation of this clause may provide DR with

additional cost for a negligible level of additional security.

42

Undertakings to others – Given the complex structure of the UK rail industry it is likely over a long-term period,

in a digital environment, that information or services may be supplied to other parties, such as TOC’s. There

may not be any benefit to precluding it from an OJEU notification however initially there may not be a

requirement.

Transfer of rights – Similar to IPR this section would likely need to be expanded given that hardware and

software will form part of the scope.

Information Modelling – The use of BIM is unlikely to add value to the project however information systems

are likely to add value. What information these systems hold and how it is used form part of the potential of a

digital solution.

Performance bond – the risk of the supplier’s performance would have to be assessed by the client, would the

cost of a bond offer value over a long-term agreement?

Advanced Payment – Not common in NR contracts unless an initial outlay is required.

Limitation of Liability – to be defined in accordance with the values in the Contract Data.

Extension of the service period – The conditions, timing and value of the extension would have to be defined.

Housing Grants Act and the Contract Act are likely to apply for UK contracts.

Z - Clauses would need to be defined relevant to the project.

5.3 Cost Components Many of the supply chain work in a mature target cost environment and have an agreed position on the elements

that constitute the Actual Cost and the elements that make up the fee. Often a schedule of labour rates is used

instead of individuals actual cost to ensure that administering the contract is timelier and cost effective. All costs

are made available for NR to audit centrally. Given that suppliers and NR have worked to these standards and

they are agreed across much of the supply chain in may be worth looking to use the cost components within

the ICE framework agreements instead of the NEC definition.

Aligning the schedule of cost components to the contract which is to be used for any new CP6 framework

agreements will also bring savings to the suppliers and DR.

The makeup of the project is likely to include significant amounts of internal labour and therefore it may be

beneficial to have set labour rates or a rate card instead of auditing the make-up of 10’individual’s costs.

5.4 NEC4 vs NR12 terms and proposed additional terms When using a standard form of contract there will inevitably be changes required to ensure that the contract is

workable given its specific requirements, environment and constraints. A review has been undertaken

comparing the base NEC4 Design Build and Operate terms to those of a NR12 S&T contract. Appendix 1

proposes wording for terms that the suppliers believe would need to be amended or added in order to make the

contract workable. The appendix covers:

• Insurance

• Liabilities

• Client Options

43

• Care of the works and handback

• Railway Costs

• Intellectual property rights

• CDM regulations

• Prohibitive Materials

• Construction Industry Scheme

• Confidentiality

• Track access

The appendix also references the clause number within an NR12 contract to demonstrate the current wording

agreed with Network Rail. The NR12 contract has evolved over a number of years and been refined as a result

of the delivery of a significant number of schemes. It would make sense to use this learning and to continue

with the agreed wording where applicable for the Moorgate contract.

5.5 Suppliers approach to contract risk When creating a payment model within the NEC4 framework there is opportunity to create an incentive model

to ensure that the outcome based specification remains the contractual focus. One proposed model is that the

Supplier puts all or part of their fee at risk until an outcome milestone is met. The costs are paid throughout the

duration of the project, subject to the pain/gain mechanism, to provide cash flow to the supply chain and

confidence that the fair payment charter is being upheld. Having the Fee withheld until outcome based criteria

are met ensures that the focus remains on delivering the specific outcome. For differing projects the goals may

be different, for some it may be timely delivery for example to meet other stakeholders delivery dates, for

instance new rolling stock. Another might be reliability performance given the high impact nature of certain parts

of the network should they fail. The Suppliers are accepting to put the fee at risk on an outcome however also

expect to be rewarded if they can provide additional benefits which are agreed with the customer.

When creating an incentive model an outcome based specification should set out the main goals of the customer

and the contracting mechanism must align these with those of the contractor. A framework model allows an

environment where closer working and understanding can be achieved. For example if a section or Railway,

like the Moorgate line, has life expired maintenance issues then the supplier could be rewarded for delivering a

solution faster, saving the customer money on delay costs and improving the end user experience. If the goals

of the customer are not aligned with those of the contract, then a misalignment can cause friction between the

parties who will focus their efforts on different priorities.

44

6 Maintenance Contracting

6.1 Background The majority of the mainline signalling installations within Great Britain are currently maintained by Network Rail

staff. Suppliers are typically asked to provide 3rd line technical support for the technologies that they have

installed and legacy equipment that is still in use on the railway. Suppliers also provide repairs and spares

service and often manage obsolescence of the systems within their working lifetime, and often beyond their

original design life.

As the maintenance activities are undertaken by NR, the supply chain have little involvement in the undertaking

or the decision making process when it comes to developing maintenance strategies.

Typical warranty periods for signalling equipment installed on current schemes are 2 years, however the design

life is significantly longer.

The risks attributed with the maintenance of the equipment is almost entirely with NR including the risk of

Schedule 4 & Schedule 8 payments for when the railway is closed for maintenance or is not available because

of equipment faults. Within the supply chain there is not currently an understanding of the costs involved, or the

process of how costs are attributed, between stakeholders because of preventative or reactive maintenance.

The supply chain has, however, acknowledged that to remain competitive and best serve its clients it needs to

provide products that not only reduce the capital costs but help to reduce the operational cost including

maintenance. As technology continues to develop more products have diagnostics that can notify the maintainer

of their performance, or of any failures. As more data is gathered to understand the performance of products

artificial intelligence can be introduced to predict failures before they occur. This forms part of the benefits of a

Digital Railway.

Outside of Great Britain, it is common for suppliers to take on the operation and maintenance of the railway

infrastructure. This is however usually based on deploying staff directly from within their organisation. The

transition of responsibilities for the maintenance of GB infrastructure will need to be carefully managed.

6.2 Managing Change Changing supplier – client roles, responsibilities and processes is extremely complicated operation and one that

this section will not try to address. It would be worth acknowledging however that a framework arrangement that

allows for flexibility would assist in facilitating the transition. Suppliers could be incentivised to provide

continuous improvement in supporting maintenance activities. Targets may not be able to be set at the tender

stage however mechanisms could be agreed to periodically reassess and reset these targets. Within other

industries where long term maintenance agreements are in place contract extensions are often based upon,

innovation, engagement and KPI’s that are not necessarily defined at the tender phase.

The suppliers may not be able to move to a position where they take liability for the operation of the railway but

suppliers are willing to put “skin in the game” and start to move in that direction.

6.3 Maintenance Scope This section looks to provide DR with some potential maintenance options that the supply chain could provide.

The diagram below provides some of the headings that make up the total lifecycle management of a product.

45

Figure 24: Life Cycle model

6.4 Spares and Repairs Data on spares, repairs usage and requirements can be harvested and used to profile future requirements and

influence ordering as well as stockholding.

Efficiencies may be achieved in central holding/remote warehousing of strategic spares for National

requirements.

Product modifications/upgrades may be developed or realised when new applications are required for other

projects. These can be incorporated into maintenance/enhancement programmes for existing installations.

6.5 Considerations for the spares scope The supplier should define as part of their technical solution the required spares for the scheme in order to

maintain the railway to the required availability specification. The cost of spares should be factored into the

overall scope and whole life cost of the project.

Once the responsibilities of the maintenance teams are defined then the location of the spares holdings could

be defined within the tender. The spares store could be maintained by the maintainer or the supplier.

As part of the tender the supplier should include RAMS targets, FMECA reports and other substantiation that

demonstrates the level of maintenance required including the spares holding required. This can be factored into

determining the cost and the arrangements to repair or replace any spares within a time frame.

46

6.6 Technical Support 1st Line site support: Enhanced site support could be provided 24 hours a day, 7 days a week after the initial

entry into service. It is common for the maintainer to often request this cover post a major commissioning in

case any initial faults occur. The supplier will often provide commissioning spares to avoid failures affecting the

railway during this infant mortality phase.

2nd Line support: During the period of enhanced site support a competent ETCS supplier could be required to

attend site within 24 hours of receiving the request. This option could be implemented for an initial period until

the maintainer is fully confident in managing the new equipment. The duration of this period could be flexible

and may be a function of the quality of the training that has been provided.

3rd Line Support: Telephone support could be provided by the supplier to answer all technical queries. The

telephone support could be available during office hours on working days or 24/7 depending on the railway

regime. When the telephone support is not available the supplier could provide an answering service such that

a message can be left and the supplier shall return the call when the telephone support is next available.

The telephone support will typically provide:

• Over the phone assistance with problems with repaired items;

• Over the phone assistance with the diagnostics on faults;

• Over the phone assistance with component history; and

• Discussion regarding second No Fault Founds (NFF) and next steps.

The traditional 3rd line technical support can be enhanced by remote monitoring of anything from individual

components to mock ups of complete systems. Any faulting issues arising can be quickly understood and

performance diagnostics can be run remotely with solutions being devised in a controlled environment.

By more long-term data gathering and sharing, the life of components can be modelled. This has the potential

to assist in the understanding of reactive maintenance and the planning of preventative maintenance. The

further into the life cycle and the more projects that exist with a supplier, the greater the data and the more

accurate the model. Contracts could be extended based upon the value that the supplier continues to offer, this

feedback loop would also benefit future products where any weaknesses or sub optimisation of the system

could quickly be addresses.

6.7 Technical Investigation In addition to the supplier providing reports on defect analysis and trends, they shall also, on request, undertake

specific investigations into failures, incidents and any other unexpected behaviour of the ETCS system.

Technical investigations are often required where different systems interface with each other to understand the

reasons for failures.

6.8 Testing Equipment, Special Tools and Training Equipment The supplier shall maintain all testing equipment, special tools, maintenance training rigs, and additional

software updates associated with the ETCS system in service for the duration of the project.

6.9 Managing obsolescence The supplier would have to monitor the availability of parts such that the installed equipment remained

maintainable. Where such parts could not be obtained, the supplier would have to provide alternative solutions

to ensure the system remains operable.

47

If a maintenance agreement were to last 30 years at some point there may need to be an update to the

equipment. Certain components or software may no longer be supported and therefore updating equipment

may continue to keep the system operable and extend the life of the system.

When selecting a supplier, the client would need to consider the supplier’s historic record of managing

obsolescence as an important indicator of how well they intend to maintain their current products.

6.10 Network and Cyber Security Management As the railway advances into an ever more digital environment the supplier would need to ensure that the

systems controlling the railway maintain secure.

Where information transfers from the project network on to the national network the protocols and security would

need to be agreed with NRT to ensure the systems remain safe and operational. Careful consideration will need

to be given where remote access to systems is required by the supplier to provide 3rd line support which would

invariably mean remote access to safety related and safety critical systems from a point external to the NR

telecommunications infrastructure.

The supplier should provide a maintenance strategy and process to ensure that networks remain protected

during the maintenance phase.

6.11 Key Performance Indicators Common performance indicators for the maintenance period could include:

• Maintenance of the reliability targets

• Achievement of the lead times for provision of new spares

• Achievement of the lead times for repaired spares

• Response to queries to the telephone service within the required times

• Inputting data concerning the occurrence and rectification of defects into DRACAS

KPI’s could be used as an incentive for the supplier to perform throughout the life of the contract. Monthly

maintenance payments could be awarded based upon the performance against the KPI performance, with a

reduced payment should the supplier not meet the required targets.

6.12 Reliability Targets and performance The ETCS system would initially have a reliability target to be achieved. During the maintenance phase and

during subsequent deployments along a route, the supplier could be rewarded for improving upon the reliability

target. This would incentivise the supplier to continuously develop the reliability of their products. Products could

be systematically upgraded in future years to increase reliability, creating a win-win situation for both the

maintainer and the supplier.

Should the reliability target not be met then the supplier would be penalised. This could be a function of the

periodic maintenance payment based upon the number of failures within the period. Should the supplier not

meet the minimum maintenance requirement then no maintenance payment would be received.

6.13 Maintenance reporting A periodic maintenance report could include the following:

• any failure to maintain a reliability target;

• any incentive payments of deductions

48

• any failure to meet a lead time for new spares with the reasons for the delay and steps being taken

to prevent delay from occurring again;

• any deductions to be made in respect of failure to deliver new spares by the relevant lead time

• any failure to meet a lead time for repaired spares with the reasons for the delay and steps being

taken to prevent delay from occurring again;

• any deductions to be made as a result of failure to deliver repaired spares by the lead time;

• any failure to return calls within the response time or, where such calls were returned in the

Response Time it was not by an appropriately qualified engineer;

• any failure to input defects into a DRACAS as required.

• any draft remedial performance improvement plans;

• any other service failures together with the information required;

• whether a persistent service failure has occurred or is likely to occur; and

• any other information which is related to the performance of the Service, maintenance of the

reliability target and the achievement (or otherwise) of the KPIs or as may be requested by the

Employer.

6.14 Tender Format The format of the tender documentation will need to reflect the use of an Outcome Based Specification. The

proposed arrangement as shown in Figure 25 provides a structured approach.

Figure 25: Proposed Tender Document Structure

The Core Document contains the overview documentation associated with the project including an overview,

the geographical boundaries and the ABR.

49

The Infrastructure Data contains the documents and data that describe the infrastructure that the project will

be implemented upon including the existing asset data, constraints and possession planning information.

The Functional, Process and Non-Functional Requirements are consolidated into the Application High Level

Outcomes (CRD) that describes all the requirements as either functional, non-functional or as process

requirements.

The Preliminary Schedule provides the programme and phases of work including the key milestones and

interfaces with associated and adjacent projects. For a Design, Build and Maintain project, this will include the

period of the maintenance period including renewals and obsolescence matters.

The O&M section provides information regarding the current operating documentation including training issues

and the asset management regime for the route.

The Commercial section sets out the commercial and contractual arrangements for the project.

50

7 Risks and challenges

7.1 Cultural Changes Adopting a “thin” client organisation may introduce culture shock to the project delivery and technical assurance

teams. Whilst it is understood that the current arrangements are no longer fit for purpose, the transition to a new

“thin organisation” will introduce several challenges.

It should be expected that the transition will be jarring with each organisation trying to understand their new

roles. There is a risk that as each organisation flexes into their new roles as RSIP and Technical Integrator that

critical tasks are duplicated or omitted. This would cause confusion and conflict between the teams and

resistance to the new process.

This risk could be mitigated by deploying a “business change management team” that

would be independent and oversee that the process to ensure that the works are

being conducted in accordance with the strategy. They would provide guidance to the

teams and ensure “fair play” was maintained during the transition period.

Whilst this report, retains the current job titles (i.e. DPE) this

is to provide understanding. To provide a clear differential from the existing

organisation to the new one, it is recommended that job titles are revised and aligned

with the new responsibilities. This would provide a clear delineation from the current

and allow new attitudes and behaviours to be established.

7.2 System of Systems The V-Life cycle provides the opportunity to the supplier to provide a bespoke and tailored solution that makes

best use of the generic specifications, the application requirements and their products.

However, their solution will reside in a wider system (the System of Systems (SoS)) that it will need to reside

within to ensure that it can provide interoperability.

Now, the generic specifications provide the requirements for achieving the M9 state and these requirements

need to be preserved in each application to ensure the systems will be interoperable.

There is a risk that the generic specifications could constrain the application requirements and the supplier. It is

understood that the generic specifications have been designed to be flexible and supplier agnostic but this has

not been tested.

7.3 Systems Authority The ability to tailor requirements to specific applications will require assurance that the tailoring does not affect

the System of Systems approach required to assure the interoperability of the systems provided by individual

projects.

This report supports Digital Rail’s intent to have a Systems Authority that will preside over the Specifications to

ensure that the interoperability of systems is persevered.

The ability to provide guidance in the production of requirements throughout the project lifecycle by using

templates and guidance notes would also help to mitigate deviations and manage the assurance of the generic

requirements.

51

This report recommends further consideration of templates for the project management plans (both delivery and

engineering), assurance and V&V plans, and testing reporting.

7.4 Technical Changes Required Following completion of the surveys it is vital that the railway configuration is

managed. The functionality of an ETCS system is defined in the configuration data.

This data has to match that of the actual railway. Divergence between the data and

the actual railway can result in expensive re-work cycles.

Further collaboration between the Technical Integrator

and Network Rail Telecoms is required as the FTNx and

GSM-R systems are now core to the delivery of the signalling system. This will require

a culture change in NRT as they will no longer be integrating with the IP signalling

team but with a System Integrator as IP signalling operate as a Railway Systems

Integrator in the Thin Client Model.

52

8 Case Study: Moorgate – Northern City Line Renewal

8.1 Background For the Moorgate – Northern City Line Renewal the strategy is to

roll out ETCS Level 2 without signals on the Moorgate Branch

between Drayton Park and Moorgate Stations. This is

approximately 3miles in length with a large section in a tunnel.

The renewal requires the deployment of the ETCS Level 2 system

(e.g. RBC with GSM-R) with the renewal of points, interlockings,

train detection and signalling power.

The TOC is providing stock with ETCS equipment fitted on board

so the focus of this project is the technical integration and the

trackside deployment.

There is no requirement to provide a Traffic Management System

or C-DAS which means this is not aligned with the System of

Systems architecture.

8.2 ConOps The Generic Concept of Operations document consider the operation for an integrated system including ETCS

(trackside and on-board), TM and C-DAS. The Moorgate – Northern City Line Renewal is only considering the

provision of one element of that in the ETCS Level 2 System.

In principle, the Concept of Operations

for the Northern City Line between

Drayton Park and Moorgate using

ERTMS Technology (Issue V2) should be

filtered from the Generic. The application

document should document the

difference, especially around where the

operational principles to be applied

where the other systems (C-DAS and

TM) are not being provided. It would be expected that alternative arrangements would be described in the

application Concept of Operations document that provided functionality that the generic system expects from

the missing systems.

This report recommends that further assessment is undertaken of the Generic

Concept of Operations document to ensure that the Application is configured

correctly.

Generic ConOps

Filtered Requirements

Application ConOps

Figure 27: Filtered ConOps

Figure 26: Route Map of the Northern Line Renewal

53

8.3 Client Delivery Team The client’s delivery organisation includes the following roles:

Figure 28: Proposed Thin Client Organisation Chart

Project Manager – will be responsible for the overall delivery of the project this will include stakeholder

management with the sponsor, the RAMs and the System Authorities.

Project Controller – will be responsible for the monitoring, control and reporting of the project. Detailed project

planning tasks will be transferred to the Technical Integrator whom will be responsible for the planning exercise.

Commercial Manager – will administer the project including managing the contractual and commercial issues.

Systems Integrator DPE – the lead engineering role responsible for ensuring the stakeholders are engaged

and ready for the delivery of the new technology. The SI DPE will need to manage the relationship with the

Route’s RAM Organisation and the Sponsor amongst other stakeholders and interested parties.

The DPE will also work with the DR System Authority to ensure the System of Systems requirements are

assured. The SI DPE will provide support to the Technical Integrator in the development of the system solution

and liaise with stakeholders on his behalf on matters of interest.

The DPE will also be responsible for the verification and validation of requirements by conducting assessments

of the requirements that have been traced to the CRD. This will include requesting specialist expertise to review

technical issues that could be outside of his expertise.

The DPE will organise and lead the gateway and audits that need to be conducted during the project lifecycle.

Requirements Manager/Configuration Manager - the owner of the requirements management process

including the tools. The Requirements Manager will provide support and guidance to the Technical Integrator in

the development of their requirements database including ensuring that the traceability to the CRD is correctly

undertaken.

The Requirements Manager could also be responsible for ensuring that configuration control is retained

including leading the Configuration Change Board.

Project Manager

Project Controller

Commerical Manager

DPE

Requirements Manager

System Assurance Manager

Operations Rep Site Manager

54

ETCS Operations Representative – is the operation facing team member and will be responsible for ensuring

the ETCS system is ready for operations including working with the TOCs. He/she will provide guidance to the

team and the Technical Integrator regarding Concept of Operation matters.

Site Manager – will be involved during the implementation phase and be responsible for assuring that the CDM

obligations are being met by the Technical Integrator. The Site Manager will undertake inspection and test

witnessing activities as required.

Safety Assurance Manager – will manage the Safety Assurance process in accordance with CSM principles.

The SAM will manage the relationship with the Regulator, ISA and other safety bodies that would be required

by the project.

The SAM will provide direction to the Technical Integrator in the development of their safety argument and

ensure that the various Safety Cases are correctly integrated.

8.4 Engineering Structure Figure 29 provides a proposed engineering structure for the Moorgate Project.

The arrangement places the Client engineering team in the centre of the project acting as the RSIP between

the technical activities being conducted by the supplier and the Sponsors, the Users (RAMs/TOC/etc.) and the

Authorities (Digital Rail, ISA, Regulator, etc.).

The RSIP role will require a dynamic team that are prepared to work in a co-operative and pragmatic way to

ensure that the new model is given the chance to evolve and develop into a working solution.

The Technical Integrator role will manage the delivery of critical activities integrating together the various

disciplines into a cohesive solution. Under this structure, key tasks such as Design Assurance, Quality

Assurance and Safety Management will now have to be conducted by the Technical Integrator with little

oversight from the RSIP. Whilst the Supply Chain has considerable experience of undertaking this role on many

overseas mainline and metro projects, this project will be novel in many respects not least because it affects

the established standards and procedures for project delivery on the GB network. Like the RSIP’s team, the

Technical Integrator will need to deploy practical and pragmatic engineers to work in an emerging and evolving

project delivery environment.

55

Requirements

Manager

Configuration

Manager

Sys Int /DPE

GTR

ETCS Operation

s Rep

Safety Assurance Manager

Siemens Class 717

Alstom Class 313

CEM

CRE IXL/

Trackside

CREETCS

CRETrack

Safety Assurance

Assessor

Product Assurance

Technical Integrator

Maintainer 2nd Line

CRECivils

CRETraction

CREPway

Test

CRE Control Centre

Safety Assurance Manager

V&V Lead

NoBo (TSI)

ISA

DeBo (NTR)

AsBo

Train Dispatch

CRE Telecoms

CREPower

RAMTrack

RAMCivils

RAMTraction

RAMPway

RAM Telecoms

RAMPower

Local Mtce

Site Manager

ORR (safety

authority)

ERA(tech

pillar 4th Railway

package)

Test Manager

Trainers

Signal Sighting

Chair

Sponsor

NRT

Passenger flow control

Evacuation plans

Rostering

Possession

Planning

Figure 29: Proposed Organisational Relationships for Moorgate Project

56

Appendix 1 Proposal for Signalling & Telecoms specific amendments to NEC 4 Design, Build and Operate Contract (June 2017)

Clause Proposal Comment Comparison NR12 (S&T) Clause

Proposed Optional Clauses

X15 X15.1 The Contractor is not liable for a Defect which arose from its design unless it failed to carry out that design using the skill and care normally used by professionals designing works similar to the works.

X15.2 The Contractor corrects a Defect for which it is not liable under the contract as a compensation event. X15.3 The Contractor may use the material provided by it under the contract for other work unless

• ownership of the material has been given to the Client

• it is stated otherwise in the Scope X15.4 The Contractor retains copies of drawings, specifications, reports and other documents which record the

Contractor’s design for the period of retention. The copies are retained in the form stated in the Scope.

▪ This is the standard NEC 4 Option X15 clause, with the exception of X15.5. X15.5 has been omitted on the understanding that required insurance will be set-out in a single location, in the insurance table within Core Clause 83.3.

▪ Set-out the general duty for reasonable skill and care for design. ▪ Only X15.1 and X15.2 would be required to maintain the existing principles, but

X15.3 and X15.4 are proposed as potentially helpful clarifications.

Clause 8(2)

X18 X18.1 Each of the limits to the Contractor’s liability in this clause apply if a limit is stated in the Contract Data. X18.2 The liability of each party to the other for any loss of profit, loss of use (including without limitation loss of use

of infrastructure or railway vehicles), loss of production, financial loss, loss of contracts, loss of data or information or for any indirect or consequential loss is limited to the amount stated in the Contract Data.

X18.3 For any one event the liability of the Contractor to the Client for loss or damage to the Client’s property is limited to the amount stated in the Contract Data.

X18.4 The Contractor’s liability to the Client for Defects due to its design is limited to the amount in the Contract Data. X18.5 The Contactor’s total liability to the Client for all matters arising under or in connection with the contract, other

than the excluded matters, is limited to the amount state in the Contract Data. The excluded matters are amounts payable by the Contractor for:

• any liability in respect of death or personal injury resulting from a negligent act or omission or breach of statutory duty by the Contractor or any person for whom the Contractor is responsible;

• any losses directly caused by the fraud of the Contractor. X18.6 The Contractor is not liable to the Client for any matter unless it is notified to the Contractor before the end of

liability date. X18.7 The limitations and exclusions of liability in the contract apply to any breach of contract or statutory duty, tort

(including but not limited to negligence), delict, by way of indemnity or otherwise to the extent allowed under the law of the contract.

▪ Proposes an amended Clause X18 to capture the currently agreed S&T position regarding limitations and exclusions of liability.

▪ X18.2 captures current exclusion of liability provisions within the S&T conditions.

It is assumed that the liability value in the Contract Data would be “£0”. Given the nature of the ETCS works an expansion of the language is proposed. For transparency the operative additional words are underlined in blue for NR’s consideration. As with the existing S&T provisions it is proposed that this clause also applies for the benefit of NR.

▪ X18.5 under the equivalent clause of the NR12(S&T) conditions [clause 88],

insured design liability would also be covered by a separate cap of £10 million. For transparency, this statement has not been proposed here, as it is understood that the design liability cap would be covered by X18.4.

Clause 88 and Clause 8(2)(c)

New X24 Client’s Options

X.24.1 Client’s options are those elements of service stated in the Contract Data which, if requested by the Client on or before the relevant date stated in the Contract Data, shall be undertaken by the Contractor in accordance with this clause.

X.24.2 The Client gives an instruction for perform any or all of the Client’s Options on or before the relevant date stated in the Contract Data. The Client’s instruction to perform a Client’s option is a compensation event.

X24.3 Compensation events instructed under this clause shall be assessed as follows:

• The addition to the Prices is the itemised sum against each Client’s option unless any changes to the services in the relevant Client’s option have been made.

• Any changes to the services in the relevant Client’s option shall be assessed as compensation events and the relevant Price(s) established shall be adjusted either up, or down accordingly.

X24.4 No extension of time shall be allowable as a result of any Client’s option instructed under this clause. For the avoidance of doubt, any subsequent alteration to the services to be delivered pursuant to and following the instruction a Client’s option shall be assessed as a compensation event.

▪ Creates the ability for the contract to include priced options within the scope; which NR has the right to exercise up to the, programme driven, date for exercise of that option.

Clauses 1(1) and 89.

57

New X25 Additional Responsibility for Care of the Works

X25.1 The Client issues a draft hand-over certificate (“the Hand-Over Certificate”) when any part of the Works or other work package contractor’s works (“the Hand-Over Works”) are completed to a standard which is sufficient for it to be capable of being handed over to an Other or the Contractor or the Employer.

X25.2 The Hand-over Certificate shall detail the relevant Hand-Over Works and shall be valid and effective once it is signed by the Contractor, the Service Manager and the relevant Other.

X25.3 Where the Contractor is handing over Works it shall be relieved of its liability for loss of or damage to the Works, Plant or Materials handed over from the date of the Hand-Over Certificate and responsibility for the care of the Hand-Over Works shall pass to the following Other or the Client. The Contractor’s liability for the remaining Works shall not be affected by this clause.

X25.4 The passing of responsibility for the care of the Hand-over Works shall not constitute Works Completion.

▪ The mechanism was introduced by NR to grant clarity for hand-over of parts of the works to either another NR contractor (e.g. from signalling to electrification) or to NR itself. Similarly, it enables hand-over of specific parts of the works from NR or its other contractors to the Signalling contractor.

▪ This provision creates a documented process for recording responsibility for the risk of theft, vandalism or damage for different parts of the works when different contractor disciplines are working on the same project, or if works are required to be installed significantly in advance of commissioning.

▪ The terminology used for these provisions within NR12(S&T) does not translate

naturally in the NEC 4 DBO contract. Therefore, attention is brought to the attempt to align language particularly in respect of X25.2 (language aligned to Cl.81.1 BP 2 of the DBO conditions).

Clause 87

New X26 Liability for Railway Costs

X26.1 Notwithstanding any other provision of the contract, the Client and the Contractor agree that the liability of the Contractor to compensate the Client in respect of any sums payable by the Client pursuant to Schedules 4 and 8 of the Track Access Agreement or the equivalent provisions of any Freight Access Agreement (together “Railway Costs”) are as set out in this clause and the Contactor shall have no further liability for any sums paid by the Client for Railway Costs.

X.26.2 The Contractor pays liquidated damages to the Client where a track possession or speed restriction has gone beyond the times stated in the contract as a result of a matter which is the Contractor’s liability.

X.26.3 The liquidated damages shall apply to the period extending beyond the expiry time of the track possession or speed restriction, detailed in the contract as a result of the Contractor having failed to complete work in accordance with the contract or some matter which is a Contractor liability and will be applied at the rates detailed in the Contract Data.

X.26.4 The Contractor’s liability for liquidated damages in respect of railway costs is limited to the amount stated in the Contract Data.

X.26.5 Without prejudice to the Contractor’s insurance obligations under the contract and save as expressly set out in this clause the Contractor shall have no further liability for any track possession or speed restriction extending beyond the expiry time of the track possession/speed restriction detailed in the contract

▪ Sets-out the Contractor’s liability for Schedule 4 and 8 costs.

▪ Liquidated damages would apply for overrun of granted track possessions and speed restrictions.

▪ Typically, these performance LDs have been limited to 15% of contract price.

▪ Under the current S&T conditions LDs also apply where the systems falls short of the guaranteed MTBF target (subject to the same 15% limit). For transparency, this provision has not been imported across as it is assumed that for a service contract NR will wish to set out specific performance criteria.

Clause 34

New X27 Works Performed under previous contracts

X.27.1 The Contractor has carried out preliminary Works for the contract under the purchase orders listed in the Contract Data and therefore:

• all and any obligations on the part of the Client to make payment under such purchase orders shall determine; and

• any payments made under such purchase orders shall be treated as payments on account of the contract; and

• everything done by the Contractor or on behalf of the Contractor under such purchase orders shall be deemed to have been done pursuant to the contract and any outstanding payments, variations or claims under such purchase orders shall be valued and managed in accordance with the terms and conditions of the contract.

▪ Allows NR to nominate early works contracts to be subsumed into this contract. Where used the price of the early works contract should also be subsumed into the Defined Cost of the current contract.

▪ If used, the Contract Data needs to include a list of the early works orders subsumed into the contract.

Proposed Additional Conditions of Contract

58

Z1 IPR Z1.1 Intellectual Property supplied by the Contractor for the purpose of the contract shall remain vested in the Contractor.

Z1.2 The Contractor grants the Client an irrevocable, royalty free non-exclusive licence to use all [designs and drawings produced/ Intellectual Property supplied] by the Contractor for any purpose in connection with carrying out of the Works.

Z1.3 The Contractor:

• waives in favour of the Client any and all moral rights in the Contractor’s designs and drawings

• agrees that upon completion of the Works the Client may grant sub-licences to other persons to use and to reproduce the Contractor’s designs and drawings for any purposes of operating, maintaining, dismantling, re-assembling, repairing or adjusting the Works

• procures from copyright holders a licence with a full title guarantee to the Client in the same terms as set out in this clause.

Z1.4 The Client shall have no right to decompile any computer software which forms part of the Intellectual Property licensed to the Client nor shall the Client attempt to derive any algorithms, techniques or other features of the software or modify or attempt to create any derivative works from the software and any sub-licence granted by the Client shall similarly apply these prohibitions to the sub-licensee of that computer software.

Z1.5 Notwithstanding the above provisions no licence is granted to the Client under this Contract to reproduce or have reproduced the Plant and Materials in part or whole; and no licence is granted to the Client to make or have made components or spare parts for the Works which are protected by intellectual property rights vested in the Contractor or any of its Subcontractors for any other purposes other than the maintenance, running or repair of the Works.

▪ Add in a licence to use designs and drawings which is currently missing from the baseline NEC conditions.

▪ In respect of Z.2.2, the current suite of S&T conditions refer only to licences in

‘designs and drawings’. Given the greater involvement of software within ETCS applications, NR may consider it beneficial to expand the scope of the licence to include all Intellectual Property supplied by the Contractor.

▪ As neither the current S&T conditions or the NEC 4 conditions define intellectual

property, if the wider licence is chosen by NR, we would also propose inclusion of the following new definition of ‘Intellectual Property’. This is the standard definition within Network Rail’s NR3 v3.11 conditions:

“Intellectual Property is all intellectual and industrial property and all rights therein in any part of the world including any patent, patent application, trade mark, trade mark application, registered design, registered design application, trade name, trade secret, business name, discovery, invention, process, formula, know-how, specification, improvement, technique, copyright, unregistered design right, technical information or drawing including rights in computer software, database rights, topography rights”

▪ Item’s Z2.4 and Z2.5 are important from a signalling perspective as NR has

included these provisions within its S&T terms for many years. Therefore, these provisions are a common feature in third party licence agreements.

Clause 6(2), (3) and (4)

Z2 CDM Regulations

Z2.1 The Contractor complies with the Client’s health and safety requirements as set-out in the Contract Requirements HSQE.

Z2.2 The Contractor procures that the Contractor’s employees, Subcontractors and other persons engaged by the Contractor receive safety and skills training in accordance with the requirements of the Contract Requirements HSQE and the Employer may instruct the immediate replacement, at the Contractor’s cost, of any person on the site who is not so trained.

Z2.3 The “Principal Contractor” is the entity specified in the Pre-Construction Information Packs included in the Contract Requirements - HSQE.

Z2.4 If the Contractor is the “Principal Contractor” it warrants that it is competent to accept this appointment and will properly perform all the duties required of a Principal Contractor under the Construction (Design and Management) Regulations including, without limitation, liaising with the CDM Co-ordinator named in the Contract Data.

Z2.5 If the Contractor is not the “Principal Contractor” the Contractor will fully support the Principal Contractor to properly perform all the duties required of the Principal Contractor under the Construction (Design and Management Regulations.

▪ Aims to incorporate NR’s standard CDM provisions into the NEC contract.

▪ If adopted, would require a new Contract Data Part One entry specifying the name of the CDM Co-ordinator.

Clause 71

59

Z3 Prohibitive Materials

Z3.1 A material is prohibited if, in the context of its use in the Works (whether alone or in combination with other materials):

• it poses a hazard to the health and safety of any person who may come into contact with the Works (whether during their construction or after their completion)

• either by itself or as a result of its use in a particular situation or in combination with other materials it would or is likely to have the effect of reducing the normal life expectancy of any other material or structure in which the material is incorporated or to which it is affixed

• it poses a threat to the structural stability or performance of the physical integrity of the Works or any part or component of the Works.

Z3.2 The Contractor does not specify, authorise for use or permit to be used any materials which at the time the Works are being carried out are generally accepted or reasonably suspected of:

• being prohibited in themselves

• becoming prohibited when used in a particular situation or in combination with other materials

• becoming prohibited with the passage of time

• becoming prohibited without a level of maintenance which is higher than that which would normally be expected of a structure of the type under construction

• being damaged by or causing damage to the Affected Property and the Contractor, when requested, issues to the Client a certificate that no such materials have been specified for use or permitted for use.

Z3.3 The Contractor warrants that it shall specify materials for use in the Works in accordance with the guidelines contained in publication “Good Practice in Selection of Construction Materials” (1997: Over Arup & Partners and/ or that materials used in accordance with the construction of the Works shall be in accordance with such guidelines.”

▪ Incorporates NR’s standard requirements for use and control of hazard materials; and in respect of Z4.3 for control of hazardous materials generally.

Clause 8(3)

Z4 Construction Industry Scheme

Z4.1 For the purpose of this clause “Scheme” shall mean the Construction Industry Scheme, as provided for Chapter 3 of the Finance Act 2004 and the Income Tax (Construction Industry Scheme) Regulations 2005.

Z4.2 The Contractor provides to the Client the information specified in regulation 6(2)(b)(iii) of the Income Tax (Construction Industry Scheme) Regulations 2005.

Z4.3 The Contractor ensures that at all times it is registered for gross payment under the Scheme. Z4.4 If the Contractor fails to completion with this clause the Client shall not be obliged to make any further payments

to the Contractor until such time as the failure is remedied.

▪ Provides NR with a mechanism to ensure Contractor’s compliance with the Construction Industry Scheme.

▪ Proposal will require validating by tax specialists.

Clause 60(12)

Z5 Confidentiality Z5.1 The Contractor and the Client treat all information obtained from the other in the course or conduct of the contract as confidential and do not divulge it save as necessary to effect the execution of the contract or maintenance, operation or repair of the Works and then only on the basis that the receipt of such information shall be bound by similar confidentiality obligations to those in this clause.

Z5.2 The obligation in this clause shall not apply to information which:

• is or shall become in the public domain otherwise than in consequence of a breach by the Contractor or the Client of its obligations under this clause

• was in the receiving party’s possession prior to award of the contract and which the disclosing party did not notify as confidential or which would not reasonably be regarded as confidential by its nature

• was received from third parties having to the best of the recipient’s knowledge the right to disclose such information

• is require to be disclosed pursuant to a court order or statutory requirement provided that the recipient shall to the extent permitted by the relevant legal or statutory requirement (a) provide the disclosing party with prompt written notice of any such requirement before such disclosure

is made; and (b) take all reasonable action to avoid and limit such disclosure as may be requested by the disclosing

party Z5.3 The Contractor does not make any announcement in relation to the contract or its subject matter without the prior

written approval of the Client except as required by law or by any legal or regulatory authority.

▪ Standard confidentiality clause.

▪ Z6.3 adds requirements not to make press releases relating to the contract without NR’s approval.

Clause 74

60

Z6 Track Access Z6.1 The Contractor submits written notice to the Client confirming any speed restrictions, track possession or isolation requirements in accordance with the Client’s current planning procedures (or as otherwise laid down in the contract) in advance of the proposed commencement of work on or near railway lines.

Z6.2 The Client reserves the right to cancel or alter the dates and times of the agreed speed restrictions, track possessions or isolations at short notice if this proves necessary because of any emergency affecting the safe or uninterrupted running of rail traffic, but in such event the Client makes alternative arrangements as soon as the Client’s programme permits. Such cancellation or change in circumstance shall be a compensation event.

Z6.3 Where any part of the Works has to be carried out during an agreed period of a speed restriction, track possession or isolation, the Contractor shall make adequate arrangements to ensure that such part can commence in accordance with the Accepted Plan, and can be completed as early as possible, and in any case within that period. The arrangements shall include the provision of sufficient and suitable Contractor’s Equipment (including where practicable, standby equipment) and sufficient labour.

Z6.4 Prior to commencement of any speed restriction, track possession or isolation, the Service Manager is of the opinion that the Contractor has failed to comply with the requirements of clause [Z6.3], he may at his discretion cancel the speed restriction, track possession or isolation, or reduce the extent of the work that the Contractor may carry out during such speed restriction, track possession or isolation and the Client notifies the Contractor accordingly.

Z6.5 If, during a speed restriction, track possession or isolation, the Service Manager is of the opinion that the Contractor will be unable to complete the planned work (or any revision proposed by the Contractor) to his satisfaction so as to permit the termination of the speed restriction, track possession or isolation at the time agreed, then the Service Manager may instruct the Contractor to reduce the extent or vary the dates and times of the work to be carried out during such speed restriction, track possession or isolation. Such reduction or variation shall not entitle the Contractor to a compensation event if and to the extent that the Contractor’s inability to complete the planned work was due to a breach by the Contractor of the requirements of the contract.

▪ Establishes NR’s right to amend possessions to the extent this is necessary to ensure uninterrupted operation of the railway.

▪ Actual liability for overruns is set out in clause 34 of NR12(S&T) [see proposed X26 above].

Clause 75; also to be read in conjunction with amended clause 34.

Proposed Bespoke Amendments to Core Clauses

21.2 The Contractor’s design

Add the end of the first sentence add “The Service Manager accepts or rejects the design within the time period set out in the Accepted Plan. If the design is not accepted the Service Manager sets out the reasons for non-acceptance and the changes that in the Service Manager’s opinion are to be made to allow acceptance.”

▪ Confirms that the time scales for acceptance or rejection of designs will be set-out in the Accepted Plan; and that, in order to allow the programme to be maintained, the reasons for any nor acceptance will be stated.

Clause 7

24.2 Working with the Client and Others

Delete the second sentence beginning “Any cost incurred…”. ▪ Typically, LDs would apply for delay, as it will not normally be possible for the Contractor to manage Others. Incentivisation provisions and integration meetings would typically be implemented to ensure collaborative working practices and mitigation of costs.

Clause 47

27 Assignment Add a new 27.2 to read: “27.2 The Client shall be entitled to assign, charge or transfer the contract with the Contractor’s prior written agreement (which shall not be unreasonably withheld or delayed).”

▪ Adds in an additional right for NR to assign or transfer the contract, subject to the agreement of the contract which cannot be unreasonably withheld or delayed.

Clause 3(1)

30.3 Starting and the Service Period

Delete Clause 30.3. ▪ This standard NEC clause appears designed around building/ property management. Management and operation of the Affected Property would be outside of the scope of these works.

60.1(15) Compensation Events

Propose that Cl.60.1(15) is amended to read: (15) A change in the law of the country in which the Affected Property is located or a change in Rail Group Standards,

Network Rail Standards or other equivalent standards which occurs after the Contract Date.

▪ Provides a mechanism for early warning and assessment of changes in applicable railway standards; which can be expected to change many time through the life of the project.

Clause 8(1)

60.1(21) Compensation Events

Add a new Para (21) to read: (21) The Contractor encounters physical conditions which

• are within the Site

• are not weather conditions, and

• an experienced contractor would have judged at the Contract Date to have such a small chance of occurring that it would have been unreasonable to allow for them.

Only the difference between the physical conditions encountered and those for which it would have been reasonable to have allowed for is taken into account in assessing a compensation event.

▪ The comparative clause within NR12(S&T) is clause 12. However, to keep to NEC principles the proposed clause is the standard NEC 4 Clause 60.1(12) wording.

▪ Given the nature and duration of the services it is proposed that this would be a practical level of test process for assessing the impact of unforeseen site conditions.

Clause 12

60.1(22) Compensation Events

Add a new Para (21) to read: (22) A weather measurement is recorded before the Completion Date for the whole of the works which would make it impracticable or unsafe to Provide the Services in accordance with the Accepted Plan.

▪ The comparative NR12(S&T) clause entitles a change in respect ‘exceptional adverse weather conditions’.

▪ We recommend clarifying this to refer to weather conditions which would make it impracticable or unsafe for the works to be provided in accordance with the Accepted Plan.

▪ Given the nature and duration of the services it is proposed that such

circumstances should trigger an assessment of safety and programme mitigation measures.

Clause 44(1)(c)

61

81.3 Insurance Table

Amend the third box to read: “Loss or damages to the Works, Plant and Materials and Equipment (until Works Completion [or transfer of liability under [X.25]]).”

▪ Consequential adjustment if new X.25 (please see above) is introduced. If parts of the work are handed-over under X.25 then responsibility for insurance remains with whomever has responsibility for the works when they are damaged.

Clause 21(3)

90.2/ 91.9 Termination

Propose adding a new right for the Client to terminate at will: “91.9 The Client may terminate by giving two weeks written notice to the Contractor for any other reason (R23)”. With termination Procedures P1 and P4 applying and the Amount Due being A1, A2 and A4.

▪ A termination for convenience provision has been proposed, as NR have identified this as a key requirement in their supplier briefings.

62

Proposed Adjustments to the Contract Data Part One

The following additions to the Contract Data Part One are proposed where the corresponding draft clause mentioned above is adopted. In each instance the information provided is the same a currently specified in the NR12(S&T) conditions.

X24: Client’s Options

The Client’s Options are: Option to be exercised no later than:

1. [Option 1] [Date 1]

2. [Option 2] [Date 2]

3. [Option 3] [Date 3]

X25: Additional Responsibility for Care of the Works

The works for which X25 applies are:

1. [Insert Item Definition]

2. [Insert Item Definition]

3. [Insert Item Definition]

4. [Insert Item Definition]

X26: Liability for Railway Costs

For the first 60 minutes or part thereof £[Insert] per minute

For the next 15 minutes or part thereof £[Insert] per minute

For the next 15 minutes or part thereof £[Insert] per minute

For the next 15 minutes or part thereof £[Insert] per minute

For the next 15 minutes or part thereof £[Insert] per minute

For subsequent delay £[Insert] per minute

The Contractor’s total liability for Railway Costs is limited to [£based of 15% of the Prices]

X27: Works performed under previous purchase orders

The purchase orders to which X27 applies are:

1. [Insert PO Number] dated [Insert date]

2. [Insert PO Number] dated [Insert date]

Z2 CDM Regulations

The CDM Co-ordinator is:

Name: [Network Rail Infrastructure Limited]

Address: [Insert Address]