diagram# description · billing = total production = a not billed = b three%phase% netmeter p1...
TRANSCRIPT
Rev. 11/16
Single phase or three phase installation with a 240 volt inverter and batteries using 2s meters with a sub panel
and transfer switch
Typical three phase installation with a 120 or 240 volt inverter
Typical single phase or three phase installation with a 120 volt inverter and batteries
Single phase or three phase installation with two 120 volt inverters and batteries using 12s meters with a sub panel
Single phase or three phase installation with two 120 volt inverters and batteries using 2s meters with a sub panel
Single phase or three phase installation with two 120 volt inverters and batteries using 2s meters with a sub panel
Single phase or three phase installation with two 120 volt inverters or a 240 volt inverter and batteries using 2s
meters with a sub panel
8
6
7
4
5
2
3
TABLE of CONTENTS
Diagram # DESCRIPTION
Typical single phase installation with a 120 or 240 volt inverter1
Diagram # DESCRIPTION
9"Sunny Island Design" Two Inverters with one production
meter with DC back-‐up
10 Hat Island Design Two Net Meters One Production Meter
11
Large Coupled System #1 w/ Batteries12
13 AC Coupled System #2 w/Batteries
Hat Island Design Two Net Meters 3 Production Meters and a Generator Meter w/Batteries
14 AC Coupled System #3 w/ Batteries
15 Configurations
Billing = Total Production = A Not Billed = B
Single Phase
P1 Net Meter
Customer load
A = kWhs received on production meter displayed on register 1B = kWhs delivered on production meter displayed on register 2
DIAGRAM 1 SINGLE PHASE with 1 INVERTER
Line
Load
Line
Load
Main Panel
Inverter
Solar Panels
PUD
A
1S, 2S prod meter
2S, 4S net meter
B
Billing = Total Production = A Not Billed = B
Three phase
Net Meter
P1
Customer load
A = kWhs received on production meter displayed on register 1B = kWhs delivered on production meter displayed on register 2
DIAGRAM 2 3 PHASE with 1 INVERTER
Line
Load
Line
Load
Main Panel
Inverter
Solar Panels
PUD
A
2S, 12S, 16S prod
meter
9S, 16S net meter
B
Billing = Total Production A - B
P1 Net Meter
Customer load
A = kWhs received on production meter displayed on register 1B = kWhs delivered on production meter displayed on register 2
DIAGRAM 3 1 INVERTER with BATTERIES
Line
Load
Line
Load
Main Panel
Battery Bank
Inverter 120v
Solar Panels
PUD
A
1S, 2S,12S prod
meter
B
2S, 4s, 9S, 16S net mtr
Charger
Billing = Total Production A + C - B - D
P2 P1 Net Meter
Customer load
A = kWhs received on production meter 1 (sub panel) displayed on register 1B = kWhs delivered on production meter 1 displayed on register 2C = kWhs recieved on production meter 2 (sub panel) displayed on register 1D = kWhs delivered on production meter 2 displayed on register 2
DIAGRAM 4 2 INVERTERS with BATTERIES and SUB PANEL, requires 5 TERMINAL SOCKETS
12S prod sub panel
Line
Load
Line
Load
Battery Back-up
Subpanel
Main Panel
Battery Bank
Inverter
Solar Panels
PUD
C
D Line
Load
12S prod sub panel
B
A
2S, 9S, 16S net meter
Charger
Inverter IN
OUT
IN OUT
Billing = Total Production A + C - B - D
Prod 2 Prod 1 Net Meter
Customer load
A = kWhs received on production meter 1 displayed on register 1B = kWhs delivered on production meter 1 displayed on register 2C = kWhs recieved on production meter 2 (sub panel) displayed on register 1D = kWhs delivered on production meter 2 (sub panel) displayed on register 2
DIAGRAM 5 2 INVERTERS with BATTERIES and SUB PANEL
2S,12S prod sub
panel
Line
Load
Line
Load
Line
Load
Battery Back-up
Subpanel
Main Panel
Battery Bank
Inverter
Solar Panels
PUD
C
D
A
B
2S,12S production
2S, 9S, 16S net meter
Charger
Inverter
Billing = Total Production A + C - B - D - E
Prod 2 Prod 1 Net Meter
Customer load
A = kWhs received on production meter 1 displayed on regester 1B = kWhs delivered on production meter 1 displayed on register 2C = kWhs recieved on production meter 2 (sub panel) displayed on register 1D = kWhs delivered on production meter 2 (sub panel) displayed on register 2E = kWhs delivered on generator meter ( mechanical register )
DIAGRAM 6 1 INVERTER with BATTERIES , SUB PANEL and GENERATOR
Prod Gen
2S,12S prod sub
panel
Line
Load
Line
Load
Line
Load
Battery Back-up
Subpanel
Main Panel
Battery Bank
Solar Panels
PUD
C
D
A
B
2S,12S production
2S ,4S 9S, 16S net meter
Charger
Inverter
2S,12S mech gen
mtr
E
Billing = Total Production A + C - B - D - E
PUD
Prod 2 Prod 1
A = kWhs received on production meter 1 displayed on regester 1B = kWhs delivered on production meter 1 displayed on register 2C = kWhs recieved on production meter 2 (sub panel) displayed on register 1D = kWhs delivered on production meter 2 (sub panel) displayed on register 2E = kWhs delivered on generator meter ( mechanical register )
DIAGRAM 7 CT SERVICE WITH 1 INVERTER with BATTERIES , SUB PANEL and GENERATOR
Prod Gen
CTS
2S,12S prod sub
panel
Line
Load
Line
Load
Battery Back-up
Subpanel
Battery Bank
Solar Panels
C
D
A
B
2S,12S production
Charger
Inverter
2S,12S mech gen
mtr
E
Line
Load
4S,9S meter
Main Panel
Main Panel
Billing = Total Production A + C - B - D - E
NC NO
Prod 2 Prod 1 Net Meter
NO Customer load
NO
A = kWhs received on production meter 1 displayed on regester 1B = kWhs delivered on production meter 1 displayed on register 2C = kWhs recieved on production meter 2 (sub panel) displayed on register 1D = kWhs delivered on production meter 2 (sub panel) displayed on register 2E = kWhs delivered on generator meter ( mechanical register )
DIAGRAM 8 INVERTER with BATTERIES , SUB PANEL with bypass relay and GENERATOR
Note: Production meter #2 needs to be energized all of the time for meter reading, therefor the load side of the meter socket needs to be connected to a two pole breaker in the sub panel. This will allow the meter to be energized from either source. There is a disconnect relay in the inverter that keeps the circuit from backfeeding into the inverter.
Prod Gen
2S,12S prod sub
panel
Line
Load
Line
Load
Line
Load
Battery Back-up
Subpanel
Main Panel
Battery Bank
Solar Panels
PUD
C
D
A
B
2S,12S production
2S, 9S, 16S net meter
Charger
Inverter
2S,12S mech gen
mtr
E
ACustomer load
B
Solar Panels
Main Panel
Net Meter
Production Meter
DIAGRAM 9 "AC Coupled System" Two Inverters with Batteries and One Production Meter
SWBattery Back-‐Up Panel
AC Inverter DC Converter
"Sunny Island "
A = kWhs received on production meter register 1B = kWhs delivered on production meter register 2
Billing = Total Production = A
Not Billed = B
Battery Bank
Solar Inverter Runs Continuous
Load
PUD
2S Meter
2S, 4S,12S,16S,9S
Line
Load
Line
A B
A = kWhs received on production meter displayed on register 1
B = kWhs delivered on production meter displayed on register 2
Diagram 10 " Hat Island " Single Inverter with two Net meters and one Production meter
Customer Panel
Uses Turtle Meters
FROM PUD 120/240 single phase
Billing = Total Production = A Not Billed = B
Inverter/ Micro Inverters
Solar Panels
A = kWhs Delivered on Net meter 1 displayed on regester 1B = kWhs Received on Net meter 2 displayed on register 1C = kWhs Delivered on Production meter 3 displayed on register 1D = kWhs Received on Production meter 4 displayed on register 1E = kWhs Received on Production meter 5 displayed on register 1F = kWhs Delivered on Generator meter 6 ( mechanical register )
Generator
Net kWhs = A-‐BTotal Production kWhs "Received" = D+E-‐C-‐F
Received
Production
Received
Uses Turtle Meters
Generator
DIAGRAM 11 " Hat Island" 1 INVERTER with BATTERIES , SUB PANEL and GENERATOR
PUD
Net
Delivered
Net Production
Received
Production
Delivered
120/240 Single Phase
Delivered
Billing : Total kWhs Delivered = ATotal kWhs Received = B
Battery Back-up
Subpanel
Main Panel
Battery Bank
Solar Panels
Charger/Controller
Inverter
123456
A B C D E F
Diagram 12 Large AC Coupled System w/ Batteries
A C
BD
PUD
Alt Production Meter Loc
200 Amp Panel
200 Amp Panel
SW
J-‐Box
AC Gutter
ATS
Gen
Inv
Net Meter
DC Gutter
Inv
Production Meter Combiner
Panel
Battery BankInvInv
Transfer SwitchCritical Loads
kWh Del
Net Meter A = KWH DeliveredNet Meter B = KWH Received
Production Meter C = KWH Received Production Meter D = KWH Delivered = Non Billed
Inv Inv Inv
AC Gutter
Solar Panels
kWh Rec
AC Coupled System #2 w/ batteries
kWh Rec
A C kWh Rec
B D
Standby Power Distribution Panel
AC Inverter AC Inverter
Grid Power Distribution Panel
Essential Panel
Main Panel
kWh Rec
Production Meter #1
Production Meter #2
kWh Del kWh Del
Transfer Switch DC Inverter/Batteries
Net Meter
PUD
Diagram 13
kWh Del
Production Meter Total kWh Rec = A+CProduction Meter Total kWh Del = B+D = Non Billed
Solar PanelsSolar Panels
Diagram 14 AC Coupled System #3 w/ batteries
A C E
B D
Disc Switch
Generator Meter
Generator
PUD
kWh Rec
kWh ReckWh Del
kWh Del
Prod #2 Meter
Net Meter Billing 01 = kWh Del 02 = kWh RecProduction Meter Billing = Total kWh Rec = A+C minus Total kWh Del B+D+E
Battery Bank
Buss GutterCT EnclosureEssential
Panel
Net MeterProd #1 Meter
InverterInverter
Outback Inverter with Transfer
Switch
Dist. Combiner Panel
kWh DelkWh Rec
kWh Del
Solar Panels
Internal and Displayed Registers
Config Register Net Meter Production Meter
40-Net 01 kWh Del 50- Net kWh Rec
02 kWh Rec kWh Del
50-Net 01 kWh Del 50- Net kWh Rec
02 kWh Rec kWh Del
9-Net 01 kWh Del 50- Net kWh Rec
02 KW kWh Del
03 kWh Rec
10-Net 01 kWh Del 50- Net kWh Rec
02 KW kWh Del
03 kVarh Del
04 kWh Rec
50 01 kWh Del
50 01 kWh Rec
NET METER REGISTER CONFIGURATIONS
Hat Island Turtle Meter
Hat Island Turtle Meter