diagram# description · billing = total production = a not billed = b three%phase% netmeter p1...

16
Rev. 11/16 Single phase or three phase installation with a 240 volt inverter and batteries using 2s meters with a sub panel and transfer switch Typical three phase installation with a 120 or 240 volt inverter Typical single phase or three phase installation with a 120 volt inverter and batteries Single phase or three phase installation with two 120 volt inverters and batteries using 12s meters with a sub panel Single phase or three phase installation with two 120 volt inverters and batteries using 2s meters with a sub panel Single phase or three phase installation with two 120 volt inverters and batteries using 2s meters with a sub panel Single phase or three phase installation with two 120 volt inverters or a 240 volt inverter and batteries using 2s meters with a sub panel 8 6 7 4 5 2 3 TABLE of CONTENTS Diagram # DESCRIPTION Typical single phase installation with a 120 or 240 volt inverter 1 Diagram # DESCRIPTION 9 "Sunny Island Design" Two Inverters with one production meter with DC backup 10 Hat Island Design Two Net Meters One Production Meter 11 Large Coupled System #1 w/ Batteries 12 13 AC Coupled System #2 w/Batteries Hat Island Design Two Net Meters 3 Production Meters and a Generator Meter w/Batteries 14 AC Coupled System #3 w/ Batteries 15 Configurations

Upload: others

Post on 29-Jan-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

Rev.  11/16

Single  phase  or  three  phase  installation  with  a  240  volt  inverter  and  batteries  using  2s  meters  with  a  sub  panel  

and  transfer  switch

Typical  three  phase  installation  with  a  120  or  240  volt  inverter

Typical  single  phase  or  three  phase  installation    with  a  120  volt  inverter  and  batteries

Single  phase  or  three  phase  installation  with  two  120  volt  inverters  and  batteries  using  12s  meters  with  a  sub  panel

Single  phase  or  three  phase  installation  with  two  120  volt  inverters  and  batteries  using  2s  meters  with  a  sub  panel

Single  phase  or  three  phase  installation  with  two  120  volt  inverters  and  batteries  using  2s  meters  with  a  sub  panel

Single  phase  or  three  phase  installation  with  two  120  volt  inverters  or  a  240  volt  inverter  and  batteries  using  2s  

meters  with  a  sub  panel

8

6

7

4

5

2

3

TABLE  of  CONTENTS

Diagram  # DESCRIPTION

Typical  single  phase  installation  with  a  120  or  240  volt  inverter1

Diagram  # DESCRIPTION

9"Sunny  Island  Design"  Two  Inverters  with  one  production  

meter  with  DC  back-­‐up

10 Hat  Island  Design    Two  Net  Meters  One  Production  Meter

11

Large  Coupled  System  #1  w/  Batteries12

13 AC    Coupled  System  #2  w/Batteries

Hat  Island  Design    Two  Net  Meters  3  Production  Meters  and  a  Generator  Meter  w/Batteries

14 AC  Coupled  System  #3  w/  Batteries

15 Configurations

Page 2: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

Billing = Total Production = A Not Billed = B

Single  Phase

   P1 Net  Meter

Customer load

A = kWhs received on production meter displayed on register 1B = kWhs delivered on production meter displayed on register 2

DIAGRAM  1                                                                                      SINGLE  PHASE  with  1  INVERTER

Line    

Load  

Line    

Load  

Main Panel

Inverter

Solar Panels

PUD

A

1S, 2S prod meter

2S, 4S net meter

B

Page 3: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

Billing = Total Production = A Not Billed = B

Three  phase  

Net  Meter

 P1

Customer load

A = kWhs received on production meter displayed on register 1B = kWhs delivered on production meter displayed on register 2

DIAGRAM  2                                                                                                                          3  PHASE  with  1  INVERTER

Line    

Load  

Line    

Load  

Main Panel

Inverter

Solar Panels

PUD

A

2S, 12S, 16S prod

meter

9S, 16S net meter

B

Page 4: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

Billing = Total Production A - B

   P1 Net  Meter

Customer load

A = kWhs received on production meter displayed on register 1B = kWhs delivered on production meter displayed on register 2

DIAGRAM  3                                                                                                        1  INVERTER  with  BATTERIES

Line    

Load  

Line    

Load  

Main Panel

Battery Bank

Inverter 120v

Solar Panels

PUD

A

1S, 2S,12S prod

meter

B

2S, 4s, 9S, 16S net mtr

Charger

Page 5: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

Billing = Total Production A + C - B - D

     P2  P1 Net  Meter

Customer load

A = kWhs received on production meter 1 (sub panel) displayed on register 1B = kWhs delivered on production meter 1 displayed on register 2C = kWhs recieved on production meter 2 (sub panel) displayed on register 1D = kWhs delivered on production meter 2 displayed on register 2

DIAGRAM  4                              2  INVERTERS  with  BATTERIES  and  SUB  PANEL,  requires  5  TERMINAL  SOCKETS  

12S prod sub panel

Line  

Load  

Line    

Load  

Battery Back-up

Subpanel

Main Panel

Battery Bank

Inverter

Solar Panels

PUD

C

D Line  

 

Load  

12S prod sub panel

B

A

2S, 9S, 16S net meter

Charger

Inverter IN  

 OUT  

IN    OUT  

Page 6: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

Billing = Total Production A + C - B - D

Prod  2 Prod  1 Net  Meter

Customer load

A = kWhs received on production meter 1 displayed on register 1B = kWhs delivered on production meter 1 displayed on register 2C = kWhs recieved on production meter 2 (sub panel) displayed on register 1D = kWhs delivered on production meter 2 (sub panel) displayed on register 2

DIAGRAM  5                                                                                      2  INVERTERS  with  BATTERIES  and  SUB  PANEL

2S,12S prod sub

panel

Line  

Load  

Line    

Load  

Line    

Load  

Battery Back-up

Subpanel

Main Panel

Battery Bank

Inverter

Solar Panels

PUD

C

D

A

B

2S,12S production

2S, 9S, 16S net meter

Charger

Inverter

Page 7: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

Billing = Total Production A + C - B - D - E

Prod  2 Prod  1 Net  Meter

Customer load

A = kWhs received on production meter 1 displayed on regester 1B = kWhs delivered on production meter 1 displayed on register 2C = kWhs recieved on production meter 2 (sub panel) displayed on register 1D = kWhs delivered on production meter 2 (sub panel) displayed on register 2E = kWhs delivered on generator meter ( mechanical register )

DIAGRAM  6                                                                                              1  INVERTER  with  BATTERIES  ,  SUB  PANEL  and  GENERATOR

Prod  Gen

2S,12S prod sub

panel

Line  

Load  

Line    

Load  

Line    

Load  

Battery Back-up

Subpanel

Main Panel

Battery Bank

Solar Panels

PUD

C

D

A

B

2S,12S production

2S ,4S 9S, 16S net meter

Charger

Inverter

2S,12S mech gen

mtr

E

Page 8: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

Billing = Total Production A + C - B - D - E

PUD

Prod  2 Prod  1

A = kWhs received on production meter 1 displayed on regester 1B = kWhs delivered on production meter 1 displayed on register 2C = kWhs recieved on production meter 2 (sub panel) displayed on register 1D = kWhs delivered on production meter 2 (sub panel) displayed on register 2E = kWhs delivered on generator meter ( mechanical register )

DIAGRAM  7                                                                      CT  SERVICE  WITH  1  INVERTER  with  BATTERIES  ,  SUB  PANEL  and  GENERATOR

Prod  Gen

CTS

2S,12S prod sub

panel

Line  

Load  

Line    

Load  

Battery Back-up

Subpanel

Battery Bank

Solar Panels

C

D

A

B

2S,12S production

Charger

Inverter

2S,12S mech gen

mtr

E

Line    

Load  

4S,9S meter

Main Panel

Main Panel

Page 9: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

Billing = Total Production A + C - B - D - E

NC NO

Prod  2 Prod  1 Net  Meter

NO Customer load

   NO

A = kWhs received on production meter 1 displayed on regester 1B = kWhs delivered on production meter 1 displayed on register 2C = kWhs recieved on production meter 2 (sub panel) displayed on register 1D = kWhs delivered on production meter 2 (sub panel) displayed on register 2E = kWhs delivered on generator meter ( mechanical register )

DIAGRAM  8                              INVERTER  with  BATTERIES  ,  SUB  PANEL  with  bypass  relay  and  GENERATOR

Note:  Production  meter  #2  needs  to  be  energized  all  of  the  time  for  meter  reading,  therefor  the  load  side  of  the  meter  socket  needs  to  be  connected  to  a  two  pole  breaker  in  the  sub  panel.  This  will  allow  the  meter  to  be  energized  from  either  source.  There  is  a  disconnect  relay  in  the  inverter  that  keeps  the  circuit  from  backfeeding  into  the  inverter.

Prod  Gen

2S,12S prod sub

panel

Line  

Load  

Line    

Load  

Line    

Load  

Battery Back-up

Subpanel

Main Panel

Battery Bank

Solar Panels

PUD

C

D

A

B

2S,12S production

2S, 9S, 16S net meter

Charger

Inverter

2S,12S mech gen

mtr

E

Page 10: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

ACustomer load

B

Solar  Panels

Main  Panel

           Net  Meter

Production  Meter

DIAGRAM  9                            "AC  Coupled  System"  Two  Inverters  with  Batteries  and  One  Production  Meter

SWBattery  Back-­‐Up  Panel

AC  Inverter  DC  Converter

"Sunny  Island  "

A = kWhs received on production meter register 1B = kWhs delivered on production meter register 2

Billing = Total Production = A

Not Billed = B

Battery  Bank

Solar  Inverter  Runs  Continuous

Load

PUD

       2S                                Meter  

2S,  4S,12S,16S,9S  

Line  

Load  

Line  

Page 11: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

     A      B

A = kWhs received on production meter displayed on register 1

B = kWhs delivered on production meter displayed on register 2

Diagram  10            "  Hat  Island  "            Single  Inverter  with  two  Net  meters  and  one  Production  meter

   Customer  Panel

                                                                                                                   Uses  Turtle  Meters

FROM  PUD  120/240  single  phase

Billing = Total Production = A Not Billed = B

Inverter/ Micro Inverters

Solar Panels

Page 12: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

A = kWhs Delivered on Net meter 1 displayed on regester 1B = kWhs Received on Net meter 2 displayed on register 1C = kWhs Delivered on Production meter 3 displayed on register 1D = kWhs Received on Production meter 4 displayed on register 1E = kWhs Received on Production meter 5 displayed on register 1F = kWhs Delivered on Generator meter 6 ( mechanical register )

Generator

Net  kWhs  =  A-­‐BTotal  Production  kWhs  "Received"  =  D+E-­‐C-­‐F

Received

Production

Received

Uses  Turtle  Meters

 Generator

DIAGRAM  11      "  Hat  Island"                                        1  INVERTER  with  BATTERIES  ,  SUB  PANEL  and  GENERATOR

PUD

Net

Delivered

Net  Production

Received

Production

Delivered

120/240  Single  Phase

Delivered

Billing : Total  kWhs  Delivered  =  ATotal  kWhs  Received  =  B

Battery Back-up

Subpanel

Main Panel

Battery Bank

Solar Panels

Charger/Controller

Inverter

123456

A B C D E F

Page 13: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

Diagram  12 Large  AC  Coupled  System  w/  Batteries

A C

BD

PUD

Alt  Production  Meter  Loc

200  Amp  Panel

200  Amp  Panel

SW

J-­‐Box

AC  Gutter

ATS

Gen

Inv

Net  Meter

DC  Gutter

Inv

Production  Meter Combiner  

Panel

Battery  BankInvInv

Transfer  SwitchCritical  Loads

kWh  Del

Net  Meter    A  =  KWH  DeliveredNet  Meter    B  =    KWH  Received

               Production  Meter    C  =  KWH  Received          Production  Meter    D  =    KWH  Delivered  =  Non  Billed

Inv Inv Inv

AC  Gutter

Solar  Panels

kWh  Rec

Page 14: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

AC  Coupled  System  #2  w/  batteries

     kWh  Rec

A C      kWh  Rec

B D

Standby  Power  Distribution  Panel

AC  Inverter AC  Inverter

Grid  Power  Distribution  Panel

Essential  Panel

Main  Panel

                   kWh  Rec

Production  Meter  #1

Production  Meter  #2

kWh  Del      kWh  Del

Transfer  Switch            DC  Inverter/Batteries

Net  Meter

PUD

Diagram  13

kWh  Del

Production  Meter  Total  kWh  Rec  =  A+CProduction  Meter  Total  kWh  Del  =  B+D  =  Non  Billed

Solar  PanelsSolar  Panels

Page 15: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

Diagram  14 AC  Coupled  System  #3  w/  batteries

A C E

B D

Disc  Switch

Generator  Meter

Generator

PUD

     kWh  Rec

     kWh  ReckWh  Del

kWh  Del

Prod  #2  Meter

                         Net  Meter  Billing  01  =  kWh  Del          02  =  kWh  RecProduction  Meter  Billing  =  Total  kWh  Rec  =  A+C  minus  Total  kWh  Del  B+D+E

Battery  Bank

Buss  GutterCT  EnclosureEssential  

Panel

Net  MeterProd  #1  Meter

InverterInverter

Outback  Inverter  with  Transfer  

Switch

Dist.  Combiner  Panel

kWh  DelkWh  Rec

kWh  Del

Solar  Panels

Page 16: Diagram# DESCRIPTION · Billing = Total Production = A Not Billed = B Three%phase% NetMeter P1 Customer load A = kWhs received on production meter displayed on register 1 B = kWhs

Internal and Displayed Registers

Config Register Net Meter Production Meter

40-Net 01 kWh Del 50- Net kWh Rec

02 kWh Rec kWh Del

50-Net 01 kWh Del 50- Net kWh Rec

02 kWh Rec kWh Del

9-Net 01 kWh Del 50- Net kWh Rec

02 KW kWh Del

03 kWh Rec

10-Net 01 kWh Del 50- Net kWh Rec

02 KW kWh Del

03 kVarh Del

04 kWh Rec

50 01 kWh Del

50 01 kWh Rec

NET METER REGISTER CONFIGURATIONS

Hat Island Turtle Meter

Hat Island Turtle Meter