diagram 08

Upload: fran01334

Post on 03-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Diagram 08

    1/2

    Caspiche Pre-Feasibility Study Update - July 2011

    1. Mining and Infrastructure

    In Pit Crushing and Conveying (IPCC) Study to be advanced to Pre-Feasibility levels

    Similar to other large throughput operations Exeter has been researching the option of using high

    capacity crushers and conveyors to move waste from the proposed pit to a dedicated waste dump. This

    has the advantage of reducing the size of the mine truck fleet and associated operating costs and can

    assist in power generation from downhill laden conveyors. In June Exeter completed a scoping level

    study considering two 21,000tph conveyors and associated crushing and spreading systems for use in

    the large Super Pit mining operations. This scoping study showed that this style of system couldaccommodate over 95% of the mine waste rock and indicated an average operating cost reduction in

    the order of $0.30/t of waste processed compared to trucking. The overall capital expenditure (including

    replacement capital) remained comparable to the trucking case. Following the positive scoping study

    results, Exeter has approved the inclusion of IPCC units in the project PFS for waste handling, and in

    conjunction with Sandvik has begun the associated engineering studies to develop this concept to a

    PFS level of confidence and accuracy.

    Additional synergies with potential to contribute further savings are also being investigated including the

    possibility of using the proposed IPCC system to crush and move oxide ore early in the project life

    and/or support movement of sulphide ore located near the bottom of the proposed pit later in the project

    life as the stripping ratio and waste tonnage decreases.

    2. Processing

    Encouraging results from Heap Leaching testwork on the MacNeill zone

    A first pass metallurgical test program at McClelland Laboratories on the gold rich, copper poor MacNeill

    zone located to the west of the Caspiche porphyry mineralization has returned encouraging results

    showing amenability to leaching with relatively fast leach kinetics. Leaching this material may improve

    the profitability for this section of the resource and in some cases permit inclusion of material not

    considered as appropriate for conventional flotation because of the very low copper grade. Initial

    indications are that it may be both possible and preferable to heap leach as much as 100Mt of this

    material. As such the leach pad size has been increased in the PFS to accommodate this material.

    Follow-up column leach testwork has already begun at McClelland on whole drill core, specifically

    directed to provide support to the initial test results.

    The encouraging MacNeill results prompted a search for similar mineralized, but copper-poor, material

    that could perform in a similar way. Several zones were identified and preliminary testwork will soon

    begin on selected samples to investigate whether this material is better treated by leaching.

    HPGR Testwork commenced

    The Company has commenced work to investigate the possible use of High Pressure Grinding Rolls(HPGR), a crushing and grinding alternative that has the potential to reduce power consump tion and

  • 8/11/2019 Diagram 08

    2/2

    perhaps improve mineral liberation and metal recovery. Tonnage samples from two dedicated

    metallurgical drill holes have been provided to SGS Lakefield (Ontario) to conduct a conventional

    characterization of ore hardness, grindability and abrasive character and to compare this with results

    from a pilot scale HPGR installation. The program will not only deliver a comparison of power

    consumption but also flotation performance on material ground by the two alternative approaches.

    Concentrate Treatment

    Pilot plant testwork has confirmed that arsenic may be successfully removed from the

    concentrate by both roasting and pressure oxidation (which produces the final metal products).

    Studies are now focused on bringing the capital and operating costs for these options to pre-

    feasibility levels. The study is looking at development of this infrastructure at lower altitudes

    closer to a permanent workforce, supplies and markets.